Ce diaporama a bien été signalé.
Le téléchargement de votre SlideShare est en cours. ×

IPTC 16192 Manuscript

Publicité
Publicité
Publicité
Publicité
Publicité
Publicité
Publicité
Publicité
Publicité
Publicité
Publicité
Publicité
Abstract
Introduction: As wells with existing gas lift (GL) installations mature and reservoir pressures decline conventio...
2 IPTC Number 16192
Graphic 1 – Block 46/02 is located 205km offshore south of Ca Mau, the southernmost land fall of mainl...
IPTC Number 16192 3
Well Completion Philosophy: Production and Nodal Analysis studies concluded that optimum tubing size b...
Publicité
Publicité

Consultez-les par la suite

1 sur 11 Publicité

Plus De Contenu Connexe

Diaporamas pour vous (20)

Similaire à IPTC 16192 Manuscript (20)

Publicité

IPTC 16192 Manuscript

  1. 1. Abstract Introduction: As wells with existing gas lift (GL) installations mature and reservoir pressures decline conventional GL systems often become less efficient. The lack of reservoir pressure makes it difficult to maintain a fluid level at a depth that allows the existing GL system to be effective. The cost of a work over remediation program to redesign and rerun the existing GL system can at times be considered uneconomical. Application: This innovative “Capillary Conveyed” through tubing system can be applied to most wellbores regardless of tubing size or depth. Results, Observations, and Conclusions: The first “Capillary Conveyed GL extension system installation was carried out for a major operator offshore Vietnam in January 2012. The existing GL system was no longer effective. The well was unable to flow and was shut in. After the installation the well took several days to unload and stabilize but then flowed continuously for 60 days at rates that exceeded the operator’s expectations. After the initial 60 days production the well started to fluctuate and has since been put on a cyclical production regime. Cumulative production from the well from the date of the GL Extension System installation until May 2012 was 43,000 bbls oil. Project payout was estimated to be 4 days. Significance of Subject Matter: Wells that were once considered uneconomic due to cost, technical challenges and/or accessibility may now be re-evaluated as candidates for this new technology. This innovative through tubing solution has the potential to reinstate flow to wells where the existing GL system is no longer effective. Furthermore the system can be adapted to allow a new through tubing GL system to be introduced into a well that was completed without a gas lifting system. Technical Contributions: Advanced solutions utilizing “Capillary Technologies” provide cost effective production enhancement and improved reserves recovery while maintaining a relatively small foot print. This paper will review a case history where this “Capillary Conveyed” through tubing solution was successfully installed and reinstated flow in a well that was suffering from an inefficient GL system. Field Overview: Block 46/02 (Graphic 1) is located 205km offshore south of Ca Mau, the southernmost land fall of mainland Vietnam, and just north of the joint development area PM-3 CAA. The producing Kekwa oil and gas field in PM-3 CAA is located 15km to the southeast of Song Doc Area (SDA). Block 46/02 was established on 12 th December 2002. The Truong Son Joint Operating Company (TSJOC) was established to explore for and produce oil and gas from the Block on behalf of the founding partners: PetroVietnam Exploration and Production Company (40%), Petronas Carigali Overseas Sdn. Bdh (30%), and Talisman (Vietnam 46/02) Ltd. (30%). IPTC Paper Number: 16192 Extending Gas Lift Systems Deeper into the Wellbore Using Capillary Through Tubing Services Brad Pate - Baker Hughes Thailand, Rick Stanley - Baker Hughes Singapore, Nguyen Chinh Nghi - TRUONGSON JOC Vietnam Copyright 2013, International Petroleum Technology Conference This paper was prepared for presentation at the International Petroleum Technology Conference held in Beijing, China, 26–28 March 2013. This paper was selected for presentation by an IPTC Programme Committee following review of information contained in an abstract submitted by the author(s). Contents of the paper, as presented, have not been reviewed by the International Petroleum Technology Conference and are subject to correction by the author(s). The material, as presented, does not necessarily reflect any position of the International Petroleum Technology Conference, its officers, or members. Papers presented at IPTC are subject to publication review by Sponsor Society Committees of IPTC. Electronic reproduction, distribution, or storage of any part of this paper for commercial purposes without the written consent of the International Petroleum Technology Conference is prohibited. Permission to reproduce in print is restricted to an abstract of not more than 300 words; illustrations may not be copied. The abstract must contain conspicuous acknowledgment of where and by whom the paper was presented. Write Librarian, IPTC, P.O. Box 833836, Richardson, TX 75083-3836, U.S.A., fax +1-972-952-9435
  2. 2. 2 IPTC Number 16192 Graphic 1 – Block 46/02 is located 205km offshore south of Ca Mau, the southernmost land fall of mainland Vietnam, and just north of the joint development area PM-3 CAA. The Block-46/02 Song Doc field (Graphic 2) was developed using a simple fixed wellhead platform (SDA), with 16 producing strings in single and dual completion wells, with a spread moored Floating Production Storage and Offloading vessel (FPSO). The FPSO facility was designed to separate well fluids, provide for gas lift to the wells, treat produced water and store and export oil. Under the leasing agreement, the FPSO owner supplies systems designed to be as simple as possible to reduce complexity, maintenance requirement and manpower and ensure minimum downtime. Graphic 2 – Song Doc field detail
  3. 3. IPTC Number 16192 3 Well Completion Philosophy: Production and Nodal Analysis studies concluded that optimum tubing size based on known fluid properties and pressures of the SDA field is 3-1/2” tubing for all the wells. This was also consistent with current production data from analogous reservoirs in nearby Malaysian waters. There are some options for well completion which have application at Song Doc development wells:  Dual completion  Single completion  Monobore completion Dual and Single completion types are commonly used in adjacent Malaysian fields with some success while the monobore concept has also been applied successfully for both oil or gas wells in the Gulf of Thailand. The specific well NH-1P, planned to access one sand reservoir, both single and monobore completion techniques were considered. The single, packer type completion is more generally applied to high PI, single sand reservoirs where larger diameter guns are required in order to optimize productivity whereas in general, the monobore type of completion is best suited to smaller reservoirs where completion of the smaller zones can often be uneconomic in a single completion type. In reviewing the various options, it was considered that while the Song Doc development did not fit clearly into one category or another the studies suggested that where two or more reservoirs are targeted, the monobore concept should be applied where only single reservoirs are targeted and so monobore completion was selected for NH-1P but with one gaslift mandrel in the tubing. Well History: NH-1P (Figure 1) is a monobore Oil Producer and started production from November 2010. In its production history the well has been intervened several times to restore production due to sand bridge formed in the wellbore. Besides the sand production and sand bridge issue, there was only one gaslift mandrel installed high above the packer. It was predicted that when reservoir pressure depleted with time there would be a point that fluid level would fall below the gaslift mandrel depth and hence an insert string for gaslift deepening is required for the well to continue to produce. Various insert string options were considered:  Convention 2” 13Cr coiled tubing string with gaslift mandrel installed on coiled tubing and thru-tubing straddle packers  Capillary string / Macaroni / dip tube by using coiled tubing from 5/8” to 1” to deepen the gaslift injection point to top of reservoir with hardware proposals from various providers In August 2011 the NH-1P production ceased. Findings from slickline pressure survey investigation after that revealed that there was no sand fill-up in the wellbore and fluid level in the well was below the gaslift mandrel in the well. All the insert string options above were reviewed again. Lead time of hardware and equipment weight are the main decision criteria. The Extending Gas Lift Systems using Capillary thru-tubing service was chosen because hardware could be delivered in December 2011 and the operation could take place immediately even in December during rough sea season because equipment weight is light enough to be lifted safely to wellhead platform during rough sea season.
  4. 4. 4 IPTC Number 16192 Figure 1 – Wellbore Schematic – Pre Capillary Work NH - 1P m MDDF TVD 3 250 250 SCSSV-TRSV FLOW COUPLING 19 500 496 X NIPPLE 55 1207 961 SPM (Orifice 3/16") FLOW COUPLING 55 1468 1144 SSD ASSEMBLY FLOW COUPLING 55 1484 1150 XN NIPPLE (2.75" BORE) 57 1500 1160 LINER HANGER 57 1650 1240 7" CASING SHOE 3301 3361 3-1/2" TUBING LANDING COLLAR 3-1/2" TUBING SHOE DEPTH COMPLETION STRING 3-1/2", 9.2PPF, 13Cr L-80 KS Bear EQUIPMENT 2.900 2.813 2.813 MAX OD IN MIN ID IN 2.900 2.900 2.992 3.920 5.030 3.920 3.960 3.960 4.540 5.230 COMPLETION SCHEMATIC MONO-BORE OIL PRODUCER 2.690 Dev Deg FLOW COUPLING 2.900 3.920 2.813 2.900 3.920 I-50: 3192-3209 m MDDF (17 m)
  5. 5. IPTC Number 16192 5 Post Installation Production Performance: The well was unable to flow and was shut-in before the Capillary String installation. After the installation completed in mid Jan 2012 (Figure 2) the well took several days to unload and stabilize but then flowed continuously for 60 days at rates that exceeded the operator’s expectations. After the initial 60 days production the well started to fluctuate and has since been put on a cyclical production regime. Cumulative production from the well from the date of the GL Extension System installation until May 2012 was 43,000 bbls oil. Current NH-1P completion diagram as below with 0.75” capillary string installed. Figure 2 – Post Capillary Wellbore Schematic with Gaslift Extension Installed COMPLETION REPORT FIELD : SONG DOC SIZE WEIGHT GRADE DEPTH (M) COMPLETION TYPE : WELL : NH-1PST1 7 47 L-80 1650.000 Dual Oil/gas Producer DATE : 20 Mar 2012 - - - 0 COMPLETION FLUID : TSJOC REPS : JOHN TAGGART TUBING L/S 3 1/2" 9.2 13CR 1499.011 10.2 ppg NACL IAN HALLIBURTON REPS : FRANCIS TANG SALES ORDER NO : 6361200 TRAN CAO DUNG Max deviation: 57.99 deg @ 1383.65m MDDF WilSuperior PICK UP WT: 95 LBS SLACKOFF WT: 88 LBS BLOCK WT: 66K LBS C/LINE PROTECTORS: 21 DEPTH (M) ID OD NO. DEPTH (M) DEV ( O ) ID OD 1 1 SINGLE TUBING HANGER 28 0 FLOW COUPLING 244 5 2.880 3.898 2A STORM CHOCK 2A 2 2 TR-SCSSV 245 5 2.813 5.030 (installed in Apr 2011) FLOW COUPLING 246 5 2.880 3.898 3 3 X-NIPPLE 2.813" BORE 495 16 2.813 3.898 4A INNER STRING 4A 4 4 SIDE POCKET MANDREL 1207 56 2.992 5.360 (ORIFICE VALVE) FLOW COUPLING 1467 57 2.880 3.898 5 5 "XD" SLIDING SIDE DOOR 1467 57 2.813 4.550 FLOW COUPLING 1469 57 2.880 3.898 6 6 XN-NIPPLE 2.75" BORE 1483 57 2.690 3.898 8 WEATHERFORD POLISHED 1496.550 5.290 5.760 8 7 7 WEATHERFORD NO-GO RING 1496 57 5.050 5.800 BORE RECEPTICLE WEATHERFORD SEALS 1498 57 4.320 5.250 WEATHERFORD MULESHOE 1499 57 4.320 5.250 EOT 1499 57 Landing Collar 3302 57 2.930 3.830 Float Collar 3312 57 2.950 3.900 Float Shoe 3360 57 5.700 6.380 JFE Bear LONG STRING DESCRIPTION THREAD CASING VAM TOP LINER -
  6. 6. 6 IPTC Number 16192 Project Objective: Install a through tubing system that will allow for the diversion of the gas lift injection gas from the bottom most gas lift valve in the completion to a pre-determined depth below the packer. Engineering Design: The subject well for the first installation of this new and innovative system was highly deviated with a 57.60 degree section starting at 1006m and extending until TD at 3366m where the deviation built up to 62.84 degrees (Figure 3). To assure project success extensive engineering and program design was completed. Tubing force analysis (TFA) (Figure 4) was carried out to assure that well bore access was achievable. This analysis also supported the final specifications for the tubulars that would be left downhole on a semi- permanent basis in a high CO2 environment of more than 35%. A 2205 Super Duplex Alloy material with a 110ksi tensile rating was selected for the tubing. The high tensile rating would allow for the tubing to be pushed to target depth with the coiled tubing injector head without the risk of buckling. In addition, further simulations were carried out to define the optimum gas lift injection rate and confirm that friction losses in the 0.75in OD extension would not compromise lift efficiency. System Design: The unique design of the system allows it to be a considered as a production enhancement solution applicable to any wellbore where gas can be injected down the annulus and diverted into the production tubing. Typical annulus to production tubing communication devices are, sliding side doors, side pocket mandrels or could simply be perforated tubing. The main component of the system which is the injection sub (Figure 5) was designed and engineered to have the largest possible flow area while maintaining sufficient integrity to securely attach the 0.75in OD extension and maintain the critical flow area for the injection gas. HNBR elastomers were selected for all components due to the high CO2 concentrations. All system components were manufactured from 13Cr material. The connection of the extension to the injection mandrel was pull tested to 7000lbs (Figure 6) as part of the manufacturing QA/QC process. Deployment Equipment: A Micro-Coil/Capillary Unit was chosen for the deployment and program execution based on its diverse range of tubing size deployment capabilities and its small light weight foot print (Figure 7). The unit was air freighted to Vietnam from the United Kingdom to meet the operator’s short time frame and window of opportunity. Well Preparation: Prior to mobilization of the Micro-Coil/Capillary Unit conventional slickline methods were used to drift the tubing, locate and confirm the depth of the targeted gas lift side pocket mandrel, clean the tubing in the area where the elastomers will seal against the tubing wall and set the lower tubing stop. Installation Sequence: The system is made of four major components (Figure 8). From the lower most to the upper most these components are:  The lower tubing stop  The lower pack off assembly with the injection sub and the extension tube attached  The upper pack off assembly  The upper tubing stop It should be noted that the depth correlation for the lower tubing stop is critical as it defines the depth of all other components that will be installed above it. The system components are deployed using conventional wire line and coil tubing technologies and methods. Six basic steps are required to install the system. They are listed below: 1. Run and set the lower tubing stop with slickline 2. Run the predetermined extension with the “Micro-Coil/Capillary” injector head 3. Run and set the upper packoff assembly with the extension connected to it on top of the bottom tubing stop with the “Micro-Coil/Capillary” injector head 4. Run slickline to jar down and energize the lower packoff element 5. Run the upper packoff assembly and sting into the polished bore of the lower packoff and jar down with slickline to energize the packoff element 6. Run and set the upper tubing stop with slickline The completed system installation is demonstrated in Figure 9.
  7. 7. IPTC Number 16192 7 Conclusion: This innovative through tubing system can be safely and effectively installed using Capillary Techniques and deployment equipment. Existing inefficient gas lift systems and/or well bores without gas lift systems can now be considered candidates for this cost effective solution as opposed to a costly work over program. References: 1. Baker Hughes Case History: Capillary ExtendLift ™System Restores Lost Production January 2012. 2. Baker Hughes post job report January 2012 3. Baker Hughes Circa Simulation Software 4. WAPRE International drawings and photographs Acknowledgements: The authors would like to give special thanks to TRUONGSON JOC Vietnam and Baker Hughes Thailand for allowing this paper to be published. Special recognition should go to Ashley Wyper and the Baker Hughes team in Vietnam that supported the successful installation of the system.
  8. 8. 8 IPTC Number 16192 Figure 3: Well Bore Profile Figure 4: Tubing Force Analysis - 600 - 300 0 300 600 9 0 0 1 2 0 0 1 5 0 0 1 8 0 0 Easting(m) - 2100 - 1800 - 1500 - 1200 - 900 - 600 - 300 0 300 TVD(m) - 2 1 0 0 - 1 8 0 0 -1500 -1200 -900 -600 -300 0 300 N o r t h i n g (m ) W e ll N H -1 P ST 1 -2 0 0 0 -1 5 0 0 -1 0 0 0 -5 0 0 0 5 0 0 1 0 0 0 0 5 0 0 1 0 0 0 1 5 0 0 2 0 0 0 2 5 0 0 3 0 0 0 E x p e c te d W e ig h t G a u g e a n d O p e r a tin g L im its D u r in g R I H WeightGaugeReading[lbf] B H A D e p th [m ] W e ig h t G a u g e F ric tio n L o c k L im it A c tu a l W e ig h t G a u g e O p e ra tin g L im it Project Title: Packoff ExtendLift Field-Well: SONG DOC -- NH-1P ST1 Company-Client: Truong Son JOC File: C:Documents and SettingsbradpateDesktopVietnamTrung SonTruong Son JOC Packoff ExtendLift.c32 Analysis: Wednesday, March 02, 2011 3:07:59 PM Scenario: ExtendLift .075" x .089" -0 2 5 0 0 5 0 0 0 7 5 0 0 1 0 0 0 0 0 5 0 0 1 0 0 0 1 5 0 0 2 0 0 0 2 5 0 0 3 0 0 0 E x p e c te d W e ig h t G a u g e a n d O p e ra tin g L im its D u r in g P O O H WeightGaugeReading[lbf] B H A D e p th [m ] W e ig h t G a u g e F ric tio n L o c k L im it A c tu a l W e ig h t G a u g e O p e ra tin g L im it Project Title: Packoff ExtendLift Field-Well: SONG DOC -- NH-1P ST1 Company-Client: Truong Son JOC File: C:Documents and SettingsbradpateDesktopVietnamTrung SonTruong Son JOC Packoff ExtendLift.c32 Analysis: Wednesday, March 02, 2011 3:10:24 PM Scenario: ExtendLift .075" x .089"
  9. 9. IPTC Number 16192 9 Figure 5: Injection Sub Figure 6: Injection Sub Pull Test Chart Figure 7: The Micro Coil/Capillary Deployment Unit
  10. 10. 10 IPTC Number 16192 Figure 8: System Components
  11. 11. IPTC Number 16192 11 Figure 9: Completed Installation

×