Real Estate Development
Commercial Real Estate Development
Youmni Al Jrab, PhD c, MBA
29th November 2012
2
Objectives
• List the components of the real estate development processes
• Conduct market survey and examine the demand and supply of
the real estate market
• Determine the best and optimum commercial use of the lands
• Shortlist and appoint consultants
• Identify and evaluate the critical elements of a real estate
development
• Evaluate financial feasibility of real estate development
• A general overview of each phase of the development process
3
Session Outline
1. Introduction
2. Real estate development phases
3. Land acquisition and site analysis
4. Land statistics & built-up area
5. Conduct real estate market study
6. Conduct market survey & survey analysis
7. Determine the best use of the land &
develop project brief
8. Prepare initial budget
9. Submit development proposal & getting
management approval
10. Shortlist consultants
11. Define consultant scope of work
12. Invite consultants
13. Single source consultant / open a
tender
14. Receive consultants’ proposals
15. Tendering process & consultant award
16. Selection criteria of consultants
17. Selection of building concept design
18. Design process
19. Construction phase
20. Q & A
4
“Real estate or property development includes
activities that range from the renovation and re-
lease of existing buildings to the purchase of
raw land and the sale of improved land or parcels to
others. Developers are the coordinators of the
activities, converting ideas on paper into
real property. Real estate development is different
from construction.” - Wikipedia
Introduction
5
• Developers buy land, finance real estate deals, build or
have builders, build projects, design, control and
orchestrate the process of development from the
beginning to the end.
• Developers purchase a land, determine the sales &
marketing of the property, develop the building program
and design, obtain the necessary approvals and financing,
build the structure, lease, manage, and ultimately sell it.
• Developers work with many different counterparts along
each step of this process, including architects, city
planners, engineers, surveyors, inspectors, consultants,
contractors, lenders, brokers, leasing agents and more.
What Developers Do
6
Real Estate
Development Phases
Research &
Development
Phase
Design
Phase
Construction
Phase
7
Research & Development
Phase
8
• Land location
• Strategic location of the land
• Availability of tourist attraction and major public services
• Land direction, visibility & accessibility
• The land surrounding & overlooking
• Major developments
• Area infrastructure & environmental issues
• Future developments
• Land topography and soil type
• Land regulations, classification & related statistics
Land Description
Land Acquisition and
Site Analysis
9
Site Analysis
Land Location
10
Site Analysis
To Achrafieh
Strategic location of the land
11
Site Analysis
To Achrafieh
4
1
13
2
5
6
2
3
4
5
6
The Lawyer’s house
BLC Bank
The Palace of Justice
The Doctor’s house
TVA Building
The Pharmacists’
Syndicate
7 Adlieh Round About
7
Availability of major public services
12
Site Analysis
Land Surrounding:
Malls and cinemas:
ABC, Sodeco, Galaxy, Abraj
And Habtoor Le Mall
Universities:
USJ, AUST and Sagesse
Schools:
Lyccee Francais,
Girls School
Hospitals:
Hotel Dieux
Others:
Hypodrom, National
Museum,
Palace of Justice, CCF and
Sioufi Park
13
Site Analysis
Site Front View
14
Site Analysis
Panoramic Front View
15
Site Analysis
Site Back View
16
Site Analysis
Site Back View
Panoramic Back View
17
Site Analysis
Site Side View
18
Site Analysis
Site Side View
19
Site Analysis
Site Side View
20
Site Analysis
Site Side View
21
1) Land location and Zone #: Achrafieh Zone 4
2) Plot area: 1,300 sq.m.
3) Total exploitation coefficient: 3.5
4) Extra balconies’ area: 20%
5) Extra area due to land location on a corner: 20%
6) Extra area for shafts & ducts: 20%
7) Allowed gross floor area: GFA 7862 sq.m.
8) Average number of floors: 13 floors
9) Allowed average floor area: 605 sq.m.
10) Average apartment per floor: 2 apartments
11) Apartment floor area: 300 sq.m.
12) Number of car parking pre each apartment
13) Total area required for parking spaces
14) Total number of parking basements
15) No. of Basements+ Ground floor+ Technical floor+ Typical floors+ Roof
floor (# B+GF+Tech.F+#TF+RF)
Land Statistics
& Built-Up Area
22
• Review of the real estate market in the area
• Examine historical figures of demand and supply
• Projection of the upcoming demand
• Upcoming projects and types of supplied units
• Types of the existing projects
• Full description of the surrounding projects (areas, selling
prices, facilities, services, amenities, parking, finishing, no. of
floors…..)
• Performance of the existing projects
• Benchmark
Real Estate Market Study
23
Surrounding Projects
Major Developments
24
J. Towers:
- J. Towers is a 4 luxurious residential buildings
built on a 4,000m2 land.
- Location: Sioufi
- Floors: varies between 14 and 21 floors.
- Area of the apartments: 160, 230, 240, 250 & 300m2.
- Prices: 2,550$ additional 50$/m2 for each higher floor.
- Underground Cave for an additional 25,000$.
- Bank Facilities with Bank Audi.
- Extra Facilities: Gym and Garden
- Actual status: Excavation. Done in 32months.
Surrounding Projects
25
Ashrafieh 4748:
- Ashrafieh 4748 is a 3 residential towers project.
- Location: Nahr ElMoot, facing Fattal.
- Floors: varies between 26 and 31 floors.
- Area of the apartments: from 185, 230 till 330 m2.
- Prices: 2,100$ additional 40$/m2 for each higher floor.
- 3 Stores: 1,000m2 each with a mezzanine.
- Bank Facilities with Bank Al-Mawared.
- Extra Facilities: Gym, Pool and Garden.
- Actual status: Excavation. Done in Dec 2013.
Surrounding Projects
26
Landmark Tower:
- Landmark tower is a 2 residential tower project
built on a 3285m2 Land.
- Location: Facing the Palace of Justice of Beirut.
- Floors: 32 floors each building.
- Area of the apartments: 350m2.
- Prices: 3000$ for 10% of the project.
4000$ for 70% of the project.
5000$ for 20% of the project.
- Actual status: Design and legal Permit.
Surrounding Projects
27
Ashrafieh 2270:
- Ashrafieh 2270 is a residential Building.
- Location: Behind the Palace of Justice.
- Floors: 10 floors.
- Area of the apartment: 175sm, 2 apartment per floor.
- Prices: 2,200$ additional 15,000$ for each higher floor.
- Bank Facilities with Bloom Bank.
- Actual status: Excavation.
Surrounding Projects
28
Market Survey
Site Analysis
Real Estate
Market Study
Land
Description
Recommended
Land Use &
Project Type
Market
Survey
29
Market Survey
• Select group of people of different (age, gender, marital
status, social status, income)
• Introduce the land, its description and its location
• Ask questions related to the recommended land use:
1) Project types & building functions
2) Unit sizes
3) Expected selling price
4) Finance options
5) Parking
6) Finishing type
7) Facilities, services and amenities required
8) Etc……
30
Survey Analysis
Age Range
21 to 30 yrs
42%
31 to 40 yrs
44%
41 to 50yrs
11%
50yrs & above
3%
21 to 30 yrs
31 to 40 yrs
41 to 50yrs
50yrs & above
single
45%
married
18%
Married/1child
14%
Married/2&above
23%
single
married
Married/1child
Married/2&above
Marital Status
Work Position
Owner
13%
Top mngt
13%
Mid mngt
33%
employee
41% Owner
Top mngt
Mid mngt
employee
where do they live?
Beirut
78%
south
4%
North
4%
Mountains
14%
Beirut
south
North
Mountains
Demographics
31
Survey Analysis
0
20
40
60
Less than 75 m2 75m2 - 100m2 100 m2 - 125m2 More than 125 m2
S1
Office Area
Series1
0
20
40
60
Less than 120 m2 120m2 - 150m2 150 m2 - 200m2 More than 200 m2
S1
Residential Area
Series1
Market Demand
32
Survey Analysis
Residential Price per M2
28%
47%
18%
7%
Less than 2,200$
2,200$-2,500$
2,500$-2,800$
More than 2,800$
Office Price per M2
42%
47%
11% 0%
Less than 2,500$
2,500$-3,000$
3,000$-3,500$
More than 3,500$
Price per sq.m.
33
Survey Analysis
0
5
10
15
20
25
30
35
40
Dependant Less than
2000$
2,000$ - 3,500$Above 3,500$
Monthy Income
Series1
Income
34
Survvey Analysis
63
26
37
74
0
10
20
30
40
50
60
70
80
Residential to buy vs to Rent Offices to buy vs to rent
Options
Percentage
Series1
Series2
Buy Vs. Rent
35
Survey Analysis
0
5
10
15
20
25
1
Single vs. Married Choices
single
married
Floor Choices
36
Survey Analysis
Living in a Multi function Building
0
10
20
30
40
50
60
70
80
Residential &
Offices
Residential &
Commercial
Residential,
Commercial &
Offices
None
Series1
Building Specifications
0
10
20
30
40
50
60
Basic Medium High Luxurious
Series1
Extra Facilities
0
5
10
15
20
25
30
35
40
45
50
Pool Garden Gym All of them
Series1
Extra Parking
0
10
20
30
40
50
60
70
80
5,000$ -
10,000$
10,000$ -
15,000$
15,000$ -
20,000$
More than
20,000$
Series1
Facilities, Amenities & Additional Needs
37
Best Use
of Land
Market
Survey
The Best Use of Land
& Project Brief
Project
Brief
Project Brief:
- Site description
- Design Intent
- Building types mix
- BUA & floor areas
- Floors Description
- Areas
- Unit Sizes
- Room Sizes
- Architectural Style
- Interior Mood
- Amenities
- Facilities
- Services
- Finishing
- Common areas
- Exterior spaces
- Car parking
- Elevators
- Etc…
38
1) Develop building structure
2) Identify cost assumptions (construction, consultancy,
marketing and sales, overhead, management, financial,
utilities, legal, etc….)
3) Assumed selling prices
4) Allocate direct construction costs
5) Allocate indirect cost
6) Sensitivity to cost & break-even point
7) Sales projection
8) Sensitivity to sales & break-even point
9) Cash flow projection
10) Profit & loss
11) Financial indicators (ROI, IRR, GPM, Pay back, etc…)
Initial budget
39
Development Proposal &
Management Approval
Project Brief
Project Initial
Budget
Land
Description &
Best Use
Development
Proposal
GO
AHEAD
STOP
40
Design Phase
41
Prepare consultant selection criteria based on:
1) Consultant profile
2) Types of performed projects
3) Types of projects’ designs
4) Number of years in consultancy
5) Awards achieved
6) Staff qualifications
7) Consultancy fees
8) Available resources
9) Delivery period
10) Projects Designs
Shortlist Consultants
42
• Design & supervision
• Getting local permits
• Geotechnical services
• Civil / structural engineering
• Mechanical / electrical / plumbing
(MEP) engineering
• IT network
• Waste management
• Security / safety / control system
• Environmental study
• Vertical transportation consultancy
• Traffic assessment study &
traffic management
• Façade consultancy
Consultant Scope Definition
• Building maintenance
consultancy
• Fire engineering consultancy
• Interior design
• Landscaping design
• Water feature design
• Specialist lighting design
• Technical review
• Third party structural review
• Value management
• Wind tunnel analysis
• Acoustic consultancy
• Topographical surveys
• Water filtration
• Sewage treatment
43
Send invitations to shortlisted consultants including:
 Project Brief
 Scope of work
 Terms & conditions of proposal
 Plot certificate
 Demarcation plan
 Site development statistics
 Guidelines
 Leveling drawings
 Secrecy undertaking
Invitation of Consultants
44
Reasons of appointing one consultant without going
through tendering process:
1) Repetition of same building design already built
2) Competencies of consultant in special designs
3) Uniqueness of the project
4) Follow management’s instruction
5) Other reasons: financial, time, resources, special
equipment, staff, etc……
Single Source /
Tender Opening
45
Consultancy proposal should include:
1) Understanding of the project
2) Scope of services
3) Proposed design stages & schedule
4) Fee proposal
5) Schedule of payment
6) Payment terms
7) Additional services & reimbursable costs
8) Scope exclusions
9) Provision of site facilities
10) Working hours
11) Termination
Receiving Consultants'
Proposals
46
Tendering Process &
Consultant Award
Tendering Process
ProjectManager/
Development
Manager
TenderCo-
ordinator
ContractorConsultant
Senior
Contracts
Manager
Quantity
Surveyor
Prepare and send the following to consultants/
contractors approved on PRE 001:
1. Inquiry Fax signed by the Chairman of the Tender
committee
2. Form for Secrecy Undertaking
3. Letter of Invitation (only after signing the Secrecy
undertaking)
File a copy of each form in the Projects file
1. Prepare the Tender documents using Emaar Standard
Tender Documentation
Preparation of list of
contractors/consultants
Preparation of Tender documents
Distribute Tender to interested
tenderers and obtain receipt
Issue Tender Documents
Issue Letter of Invitation signed
by Chairman of Tender
Committee
Select Consultant / Contractor /
Supplier from the Registered List of
Contractors with regard to competency,
experience and past performance etc
and Prepare ‘List of Tenderers -
Approval Form’ (PRE 001) and send for
approval to the prescribed signatories
as per Form PRE 001.
Finalise the list (PRE
001) based on signing
of Secrecy undertakingRetain the original approved list.
A
START
Refer PRO
S.O.P C.1
and C.2
Refer PRO
S.O.P C.6
KPI
Tenders to be
floated within
specified time of
receipt of complete
tender documents
from Development.
Process No: UAE/PDT/PDD/PRO 1.9Version No: 4 (25 Feb 2007) Process Owner: Senior Contracts ManagerDept Name: Project (Contracts)
47
Tendering Process &
Consultant Award
Tendering Process
ProjectManager/
Development
Manager
TenderCo-
ordinator
Contractor
Quantity
Surveyor
Senior
Contracts
Manager
Consultant
Issue Submission receipt
to tenderer
1. Compile clarifications to queries.
2. Attach all addendums, circulars, bulletins
etc to the clarification letter
3. Ensure it is signed by the Chairman of the
Tender Committee
B
Receive tender queries
from prospective
tenderers and forward it to
the PM
Tender Submission
Send clarifications with all
addendums, circulars, bulletins etc to
all tenderers and obtain collection
receipt and acknowledgement slip
from tenderer
Submit four (4) copies of
the bid to Emaar
(Contracts department)
Provide clarifications on the
queries posed by the tenderers
to the Tender Coordinator with
copy to Project Manager /
Development Manager
Tender Queries and Addendum, Circulars and Bulletins
A
Keep Tenders in secure
area till Tender opening
Process No: UAE/PDT/PDD/PRO 1.9Version No: 4 (25 Feb 2007) Process Owner: Senior Contracts ManagerDept Name: Project (Contracts)
Refer PRO
S.O.P C.7
and C.8
Refer PRO
S.O.P C.9
Review and get
Consultant to
respond
48
Tendering Process &
Consultant Award
Tendering Process
Tender
Committ
ee
ProjectManager/
Development
Manager
TenderCo-
ordinator
ConsultantContractor
Quantity
Surveyor
Senior
Contracts
Manager
Tender Opening by
Tender Committee
B
Respond to Post Tender
Clarifications to the Chairman of
the Tender Committee
Review the Tender
Reports
Provide supplemental
Tender Reports to Chairman
of the Tender committee
Submit final Tender Report
recommendations to
Chairman of the Tender
Committee
Clarifications
satisfactory?
1. Register and maintain the
safe custody of Tender Bond
2. Make entries in Tender
Opening Register.
3. Monitor the validity of the
Tender bonds and arrange for
extension as required.
1. Prepare ‘Tender Opening - Record
Form’ (PRE 002)
2. Extract Tender Bond
3. Send copies to Technical
Consultant and Commercial
Consultants for review
Submit 4 copies of Technical and
Commercial Tender Reports to
Chairman of Tender Committee
Conduct detailed
technical and
commercial
evaluations
Open the Tender on behalf of the
Tender Committee and record name,
and price.
Receive the Tender Report on
behalf of Tender Committee and
forward to Project Manager and
Senior Contracts Manager for
review
Review the Tender
Reports
Issue post-Tender
queries to tenderers
Yes
C
No
Tender evaluation, clarifications and negotiations
Submit soft copy of technical and
commercial questionnaires to
Tender Co-ordinator
Is clarification
from tenderer
required?
No
Yes
Process No: UAE/PDT/PDD/PRO 1.9Version No: 4 (25 Feb 2007) Process Owner: Senior Contracts ManagerDept Name: Project (Contracts)
Refer PRO
S.O.P C.10
and C.11
Refer PRO
S.O.P C.12
and C.13
KPI
Recommendation to
Award of Contract
within specified time
of receipt of Tender
bids.
KPI
KPI :
1. Recommendation to Award of
Contract within specified time of receipt
of Tender bids.
2. Ensure procurement of Best Price
for each project.
49
Tendering Process &
Consultant Award
Tendering Process
Tender
Committe
e
ProjectManager/
Development
Manager
Administrative
Assistant
Contractor
Quantity
Surveyor
Senior
Contracts
Manager
Consultant
Inform unsuccessful
tenderers and return
Tender Bond
Receive LOA and distribute as follows:
i. Contractor (Original)
ii. Project Cost Administrator (Copy)
iii. Project Manager (Copy)
iv. Insurance Administrator (Copy)
V. Contracts Department
Prepare the Award of contract - Approval form (PRE
003 / 003A / 003B as applicable) and attach with the
form :
i. Explanatory covering memo to Senior Management
and Board (if applicable)
ii. Summary of Tender Report submitted by consultant
iii. Budget Reconciliation
C
Arrange for Consultant review, Verify
and forward the Performance Bond
to Quantity Surveyor for filing
Performance Bond
Receive Performance bond from
Contractor
Schedule a Kick-off meeting to be
attended by successful contractor,
Consultant and Project Manager
Return countersigned LOA
Prepare LOA for
signature by
authorised
management
personnel Return Tender bond
Prepare the Draft Contract
based on the tender submission,
subsequent clarifications and
agreement reached
Review the contract
document
Review drawings and
specifications
1. Prepare ‘Contracts Document -
Approval Form’ (PRE 004)
2. Get ED (Projects) to sign on both
copies of the Contract
3. Keep one original and return one
original to contractor.
Prepare 2 original sets
of Contract document
and send to contractor
to be signed
END
Award of Contract and Preparation of Contract Documents
Distribute PRE 003 /
003A / 003B as
applicable with
supporting documents
for remaining
signatures as per
Authority Matrix
Register and maintain safe custody
of Performance Bond
Forward the signed
PRE 003 / 003A / 003B
as applicable and
supporting
documentation to
Senior Contracts
Manager.
Refer PRO
S.O.P C.14
and C.16
Refer PRO
S.O.P D.2
Review the PRE 003 / 003A /
003B as applicable with
supporting documentation and
recommend to Tender Committee
Keep the original
documentation and
file.
Process No: UAE/PDT/PDD/PRO 1.9Version No: 4 (25 Feb 2007) Process Owner: Senior Contracts ManagerDept Name: Project (Contracts)
Monitor the validity of the bonds and
arrange for extension, if necessary
Refer PRO
S.O.P D.1
KPI
Issue LOA within
specified time of
receipt of contract
award of aproval.
KPI
Contract to be
signed within
specified time of
LOA.
Review the recommendations
provided and approve or reject.(in
cases of rejection, process to be
repeated until approval is granted.)
50
Selection Criteria of
Consultants
Grade is given for each criteria based on the objective of the developer and the
consultant who gets the highest total grade is selected:
Grade (1-10) Coeff.% T. Grade
1) Consultant profile 5 7 % 0.35
2) Types of performed projects 7 5 % 0.35
3) Types of projects’ designs 8 7 % 0.56
4) Number of years in consultancy 8 8 % 0.64
5) Awards achieved 4 3 % 0.12
6) Staff qualifications 7 10 % 0.70
7) Consultancy fees 9 17 % 1.53
8) Available resources 6 3 % 0.18
9) Delivery period 9 15 % 1.35
10)Design 9 25% 2.25
-------- ---------
100% 8.03
51
Selection of Building
Concept Design
1) Compare design to the design intent mentioned in project brief
2) Compare consultant fee to budget (support of quantity surveyor QS)
3) Specialists’ opinions and management approval
52
1) Concept Design Sign-Off
2) Schematic Design Sign-Off
3) Commence Design Development
4) Design NOCs to Authorities
5) Complete Soils Report & Tests
6) Shoring & Excavation Permits & Commence Shoring &
Excavation
7) Design Budget
8) Design Development Sign Off
9) Commence Working Drawings
10) Commence Piling Package
11) Prepare BOQ
12) Piling Permit & commence piling
13) Working Drawings & Tender Documents Sign-Off
14) Contractors invitation and appoint contractor
15) Contract Award Budget
16) Commence Building Construction
Design Process
53
Construction Phase
Start of Construction
54
55
Thank You!

More Related Content

What's hot

A study on Affordable Housing projects in India (by Manpreet Singh)
A study on Affordable Housing projects in India (by Manpreet Singh)A study on Affordable Housing projects in India (by Manpreet Singh)
A study on Affordable Housing projects in India (by Manpreet Singh)Manpreet Singh Lotey, MBA
 
Elements of national housing policy
Elements of national housing policyElements of national housing policy
Elements of national housing policykvn virinchi
 
Landscape in housing projects
Landscape in housing projectsLandscape in housing projects
Landscape in housing projectsDhanya Pravin
 
sustainable housing case study
sustainable housing case studysustainable housing case study
sustainable housing case studyAr. Prerna Chouhan
 
Affordable Housing
Affordable HousingAffordable Housing
Affordable HousingDr K M SONI
 
Aranya low cost housing-BV Doshi
Aranya low cost housing-BV DoshiAranya low cost housing-BV Doshi
Aranya low cost housing-BV Doshikusha Ahmed
 
presentation on M.H.A.D.A. housing
presentation on M.H.A.D.A. housingpresentation on M.H.A.D.A. housing
presentation on M.H.A.D.A. housingSoumitra Smart
 
Site Analysis for Gated Community for B.Arch Thesis project
Site Analysis for Gated Community for B.Arch Thesis projectSite Analysis for Gated Community for B.Arch Thesis project
Site Analysis for Gated Community for B.Arch Thesis projectGeeva Chandana
 
Urban housing scenario and rental housing in india
Urban housing scenario and rental housing in indiaUrban housing scenario and rental housing in india
Urban housing scenario and rental housing in indiapadamatikona swapnika
 
Assignment mixed land use
Assignment mixed land useAssignment mixed land use
Assignment mixed land usearpriyank
 
Residential Land Development Process
Residential Land Development ProcessResidential Land Development Process
Residential Land Development ProcessDuncan Smith
 
3.1 development control rules
3.1 development control rules3.1 development control rules
3.1 development control rulesSachin PatiL
 
2.6.1 slum case study mumbai
2.6.1 slum case study mumbai2.6.1 slum case study mumbai
2.6.1 slum case study mumbaiSachin PatiL
 
Affordable housing in india
Affordable housing in indiaAffordable housing in india
Affordable housing in indiaPramod Kumar
 

What's hot (20)

A study on Affordable Housing projects in India (by Manpreet Singh)
A study on Affordable Housing projects in India (by Manpreet Singh)A study on Affordable Housing projects in India (by Manpreet Singh)
A study on Affordable Housing projects in India (by Manpreet Singh)
 
Land Development
Land DevelopmentLand Development
Land Development
 
Elements of national housing policy
Elements of national housing policyElements of national housing policy
Elements of national housing policy
 
Landscape in housing projects
Landscape in housing projectsLandscape in housing projects
Landscape in housing projects
 
sustainable housing case study
sustainable housing case studysustainable housing case study
sustainable housing case study
 
Affordable Housing
Affordable HousingAffordable Housing
Affordable Housing
 
OpenDoor coliving
OpenDoor colivingOpenDoor coliving
OpenDoor coliving
 
Aranya low cost housing-BV Doshi
Aranya low cost housing-BV DoshiAranya low cost housing-BV Doshi
Aranya low cost housing-BV Doshi
 
presentation on M.H.A.D.A. housing
presentation on M.H.A.D.A. housingpresentation on M.H.A.D.A. housing
presentation on M.H.A.D.A. housing
 
Naya Raipur - A New City Takes Root - SS Bajaj
Naya Raipur - A New City Takes Root - SS BajajNaya Raipur - A New City Takes Root - SS Bajaj
Naya Raipur - A New City Takes Root - SS Bajaj
 
Site Analysis for Gated Community for B.Arch Thesis project
Site Analysis for Gated Community for B.Arch Thesis projectSite Analysis for Gated Community for B.Arch Thesis project
Site Analysis for Gated Community for B.Arch Thesis project
 
Urban housing scenario and rental housing in india
Urban housing scenario and rental housing in indiaUrban housing scenario and rental housing in india
Urban housing scenario and rental housing in india
 
Assignment mixed land use
Assignment mixed land useAssignment mixed land use
Assignment mixed land use
 
Residential Land Development Process
Residential Land Development ProcessResidential Land Development Process
Residential Land Development Process
 
Affordable Housing
Affordable HousingAffordable Housing
Affordable Housing
 
Housing project
Housing projectHousing project
Housing project
 
3.1 development control rules
3.1 development control rules3.1 development control rules
3.1 development control rules
 
2.6.1 slum case study mumbai
2.6.1 slum case study mumbai2.6.1 slum case study mumbai
2.6.1 slum case study mumbai
 
PUNE BYE LAWS
PUNE BYE LAWSPUNE BYE LAWS
PUNE BYE LAWS
 
Affordable housing in india
Affordable housing in indiaAffordable housing in india
Affordable housing in india
 

Similar to Real Estate Development Guide

Development Economics (Group Assignment) - Financial appraisal
Development Economics (Group Assignment) - Financial appraisalDevelopment Economics (Group Assignment) - Financial appraisal
Development Economics (Group Assignment) - Financial appraisalYee Len Wan
 
2018 Villanova Real Estate Challenge (2nd Place) - University of Southern Cal...
2018 Villanova Real Estate Challenge (2nd Place) - University of Southern Cal...2018 Villanova Real Estate Challenge (2nd Place) - University of Southern Cal...
2018 Villanova Real Estate Challenge (2nd Place) - University of Southern Cal...LuisGonzalez1382
 
The Square at Broadway Place
The Square at Broadway PlaceThe Square at Broadway Place
The Square at Broadway PlaceRLEST8Meg
 
Monona APA Presentatin_10-09-15
Monona APA Presentatin_10-09-15Monona APA Presentatin_10-09-15
Monona APA Presentatin_10-09-15Sonja Reichertz
 
Real Estate Deal Pitch Final
Real Estate Deal Pitch FinalReal Estate Deal Pitch Final
Real Estate Deal Pitch FinalZachary Bardwell
 
2018 Villanova REal Estate Challenge (2nd Place) University of Southern Calif...
2018 Villanova REal Estate Challenge (2nd Place) University of Southern Calif...2018 Villanova REal Estate Challenge (2nd Place) University of Southern Calif...
2018 Villanova REal Estate Challenge (2nd Place) University of Southern Calif...Aleksander Drabovskiy
 
Raimon Profile 2016
Raimon Profile 2016Raimon Profile 2016
Raimon Profile 2016Musa Islam
 
The Etobicoke Report_Spring 2016
The Etobicoke Report_Spring 2016The Etobicoke Report_Spring 2016
The Etobicoke Report_Spring 2016John LaFontaine
 
Wheels of Progress: Downtown Planning 2.0 Beyond the Vision
Wheels of Progress: Downtown Planning 2.0 Beyond the VisionWheels of Progress: Downtown Planning 2.0 Beyond the Vision
Wheels of Progress: Downtown Planning 2.0 Beyond the VisionOHM Advisors
 
Solar city eng
Solar city engSolar city eng
Solar city engRoma Kov
 
Principles of planning and bye laws pns
Principles of planning and bye laws pnsPrinciples of planning and bye laws pns
Principles of planning and bye laws pnsPratap Shinde
 
Raimon profile 2018
Raimon profile 2018 Raimon profile 2018
Raimon profile 2018 Musa Islam
 
Real estate basics - India
Real estate basics - IndiaReal estate basics - India
Real estate basics - IndiaJay Datta
 
D.C. Multifamily Forum - Victor Hoskins
D.C. Multifamily Forum - Victor Hoskins D.C. Multifamily Forum - Victor Hoskins
D.C. Multifamily Forum - Victor Hoskins juliannesifers
 

Similar to Real Estate Development Guide (20)

f7
f7f7
f7
 
Development Economics (Group Assignment) - Financial appraisal
Development Economics (Group Assignment) - Financial appraisalDevelopment Economics (Group Assignment) - Financial appraisal
Development Economics (Group Assignment) - Financial appraisal
 
2018 Villanova Real Estate Challenge (2nd Place) - University of Southern Cal...
2018 Villanova Real Estate Challenge (2nd Place) - University of Southern Cal...2018 Villanova Real Estate Challenge (2nd Place) - University of Southern Cal...
2018 Villanova Real Estate Challenge (2nd Place) - University of Southern Cal...
 
The Square at Broadway Place
The Square at Broadway PlaceThe Square at Broadway Place
The Square at Broadway Place
 
Monona APA Presentatin_10-09-15
Monona APA Presentatin_10-09-15Monona APA Presentatin_10-09-15
Monona APA Presentatin_10-09-15
 
Real Estate Deal Pitch Final
Real Estate Deal Pitch FinalReal Estate Deal Pitch Final
Real Estate Deal Pitch Final
 
2018 Villanova REal Estate Challenge (2nd Place) University of Southern Calif...
2018 Villanova REal Estate Challenge (2nd Place) University of Southern Calif...2018 Villanova REal Estate Challenge (2nd Place) University of Southern Calif...
2018 Villanova REal Estate Challenge (2nd Place) University of Southern Calif...
 
Raimon Profile 2016
Raimon Profile 2016Raimon Profile 2016
Raimon Profile 2016
 
The Etobicoke Report_Spring 2016
The Etobicoke Report_Spring 2016The Etobicoke Report_Spring 2016
The Etobicoke Report_Spring 2016
 
Wheels of Progress: Downtown Planning 2.0 Beyond the Vision
Wheels of Progress: Downtown Planning 2.0 Beyond the VisionWheels of Progress: Downtown Planning 2.0 Beyond the Vision
Wheels of Progress: Downtown Planning 2.0 Beyond the Vision
 
Solar city eng
Solar city engSolar city eng
Solar city eng
 
Principles of planning and bye laws pns
Principles of planning and bye laws pnsPrinciples of planning and bye laws pns
Principles of planning and bye laws pns
 
Raimon profile 2018
Raimon profile 2018 Raimon profile 2018
Raimon profile 2018
 
Orbit tower
Orbit towerOrbit tower
Orbit tower
 
Ahmed Hussien1 2
Ahmed Hussien1 2Ahmed Hussien1 2
Ahmed Hussien1 2
 
Sunny Ridge Residences.pdf
Sunny Ridge Residences.pdfSunny Ridge Residences.pdf
Sunny Ridge Residences.pdf
 
Senior Architect
Senior ArchitectSenior Architect
Senior Architect
 
Real estate investment
Real estate investmentReal estate investment
Real estate investment
 
Real estate basics - India
Real estate basics - IndiaReal estate basics - India
Real estate basics - India
 
D.C. Multifamily Forum - Victor Hoskins
D.C. Multifamily Forum - Victor Hoskins D.C. Multifamily Forum - Victor Hoskins
D.C. Multifamily Forum - Victor Hoskins
 

More from PMILebanonChapter

PMI Lebanon Chapter Newsletter Q4 2019
PMI Lebanon Chapter Newsletter Q4 2019PMI Lebanon Chapter Newsletter Q4 2019
PMI Lebanon Chapter Newsletter Q4 2019PMILebanonChapter
 
I, project manager, The rise of artificial intelligence in the world of proje...
I, project manager, The rise of artificial intelligence in the world of proje...I, project manager, The rise of artificial intelligence in the world of proje...
I, project manager, The rise of artificial intelligence in the world of proje...PMILebanonChapter
 
insurance policies in projects
 insurance policies in projects insurance policies in projects
insurance policies in projectsPMILebanonChapter
 
2019 August - Jad Abou Ibrahim
2019 August - Jad Abou Ibrahim2019 August - Jad Abou Ibrahim
2019 August - Jad Abou IbrahimPMILebanonChapter
 
2019 july pmi coaching and soft skills
2019 july pmi coaching and soft skills2019 july pmi coaching and soft skills
2019 july pmi coaching and soft skillsPMILebanonChapter
 
PMI Lebanon chapter newsletter Q219
PMI Lebanon chapter newsletter Q219PMI Lebanon chapter newsletter Q219
PMI Lebanon chapter newsletter Q219PMILebanonChapter
 
Crypto currencies presentation by Dr. Andre Gholam
Crypto currencies presentation by Dr. Andre GholamCrypto currencies presentation by Dr. Andre Gholam
Crypto currencies presentation by Dr. Andre GholamPMILebanonChapter
 
Leading Millennials in a project context by Mr Charbel Azar
Leading Millennials in a project context by Mr Charbel AzarLeading Millennials in a project context by Mr Charbel Azar
Leading Millennials in a project context by Mr Charbel AzarPMILebanonChapter
 
The Known Unknown - Importance of Project Risk Management by Mr Wissam Yaacoub
The Known Unknown - Importance of Project Risk Management by Mr Wissam YaacoubThe Known Unknown - Importance of Project Risk Management by Mr Wissam Yaacoub
The Known Unknown - Importance of Project Risk Management by Mr Wissam YaacoubPMILebanonChapter
 
PMI Lebanon chapter newsletter Q1 2019
PMI Lebanon chapter newsletter Q1 2019PMI Lebanon chapter newsletter Q1 2019
PMI Lebanon chapter newsletter Q1 2019PMILebanonChapter
 
Values - Applying Emotional Intelligence Concepts in a Project Environment by...
Values - Applying Emotional Intelligence Concepts in a Project Environment by...Values - Applying Emotional Intelligence Concepts in a Project Environment by...
Values - Applying Emotional Intelligence Concepts in a Project Environment by...PMILebanonChapter
 
Behavioral styles 2019 - Applying Emotional Intelligence Concepts in a Proj...
Behavioral styles   2019 - Applying Emotional Intelligence Concepts in a Proj...Behavioral styles   2019 - Applying Emotional Intelligence Concepts in a Proj...
Behavioral styles 2019 - Applying Emotional Intelligence Concepts in a Proj...PMILebanonChapter
 
"so you think you know the code" by Mrs. Gretta Kelzi
"so you think you know the code" by Mrs. Gretta Kelzi"so you think you know the code" by Mrs. Gretta Kelzi
"so you think you know the code" by Mrs. Gretta KelziPMILebanonChapter
 
Another Project Hit the wall by Eng Hisham Zeinoun
Another Project Hit the wall by Eng Hisham ZeinounAnother Project Hit the wall by Eng Hisham Zeinoun
Another Project Hit the wall by Eng Hisham ZeinounPMILebanonChapter
 

More from PMILebanonChapter (20)

PMILC Newsletter Q3 2021
PMILC Newsletter Q3 2021PMILC Newsletter Q3 2021
PMILC Newsletter Q3 2021
 
PMI LC newsletter Q4 2020
PMI LC newsletter Q4 2020PMI LC newsletter Q4 2020
PMI LC newsletter Q4 2020
 
PMI LC Q3 2020
PMI LC Q3 2020PMI LC Q3 2020
PMI LC Q3 2020
 
PMI LC Newsletter Q2 2020
PMI LC Newsletter Q2 2020PMI LC Newsletter Q2 2020
PMI LC Newsletter Q2 2020
 
PMI LC Newsletter Q1 2020
PMI LC Newsletter Q1 2020PMI LC Newsletter Q1 2020
PMI LC Newsletter Q1 2020
 
PMI Lebanon Chapter Newsletter Q4 2019
PMI Lebanon Chapter Newsletter Q4 2019PMI Lebanon Chapter Newsletter Q4 2019
PMI Lebanon Chapter Newsletter Q4 2019
 
I, project manager, The rise of artificial intelligence in the world of proje...
I, project manager, The rise of artificial intelligence in the world of proje...I, project manager, The rise of artificial intelligence in the world of proje...
I, project manager, The rise of artificial intelligence in the world of proje...
 
insurance policies in projects
 insurance policies in projects insurance policies in projects
insurance policies in projects
 
PMI LC Newsletter 2019
PMI LC Newsletter 2019PMI LC Newsletter 2019
PMI LC Newsletter 2019
 
2019 August - Jad Abou Ibrahim
2019 August - Jad Abou Ibrahim2019 August - Jad Abou Ibrahim
2019 August - Jad Abou Ibrahim
 
2019 july pmi coaching and soft skills
2019 july pmi coaching and soft skills2019 july pmi coaching and soft skills
2019 july pmi coaching and soft skills
 
PMI Lebanon chapter newsletter Q219
PMI Lebanon chapter newsletter Q219PMI Lebanon chapter newsletter Q219
PMI Lebanon chapter newsletter Q219
 
Crypto currencies presentation by Dr. Andre Gholam
Crypto currencies presentation by Dr. Andre GholamCrypto currencies presentation by Dr. Andre Gholam
Crypto currencies presentation by Dr. Andre Gholam
 
Leading Millennials in a project context by Mr Charbel Azar
Leading Millennials in a project context by Mr Charbel AzarLeading Millennials in a project context by Mr Charbel Azar
Leading Millennials in a project context by Mr Charbel Azar
 
The Known Unknown - Importance of Project Risk Management by Mr Wissam Yaacoub
The Known Unknown - Importance of Project Risk Management by Mr Wissam YaacoubThe Known Unknown - Importance of Project Risk Management by Mr Wissam Yaacoub
The Known Unknown - Importance of Project Risk Management by Mr Wissam Yaacoub
 
PMI Lebanon chapter newsletter Q1 2019
PMI Lebanon chapter newsletter Q1 2019PMI Lebanon chapter newsletter Q1 2019
PMI Lebanon chapter newsletter Q1 2019
 
Values - Applying Emotional Intelligence Concepts in a Project Environment by...
Values - Applying Emotional Intelligence Concepts in a Project Environment by...Values - Applying Emotional Intelligence Concepts in a Project Environment by...
Values - Applying Emotional Intelligence Concepts in a Project Environment by...
 
Behavioral styles 2019 - Applying Emotional Intelligence Concepts in a Proj...
Behavioral styles   2019 - Applying Emotional Intelligence Concepts in a Proj...Behavioral styles   2019 - Applying Emotional Intelligence Concepts in a Proj...
Behavioral styles 2019 - Applying Emotional Intelligence Concepts in a Proj...
 
"so you think you know the code" by Mrs. Gretta Kelzi
"so you think you know the code" by Mrs. Gretta Kelzi"so you think you know the code" by Mrs. Gretta Kelzi
"so you think you know the code" by Mrs. Gretta Kelzi
 
Another Project Hit the wall by Eng Hisham Zeinoun
Another Project Hit the wall by Eng Hisham ZeinounAnother Project Hit the wall by Eng Hisham Zeinoun
Another Project Hit the wall by Eng Hisham Zeinoun
 

Recently uploaded

Textual Evidence in Reading and Writing of SHS
Textual Evidence in Reading and Writing of SHSTextual Evidence in Reading and Writing of SHS
Textual Evidence in Reading and Writing of SHSMae Pangan
 
4.18.24 Movement Legacies, Reflection, and Review.pptx
4.18.24 Movement Legacies, Reflection, and Review.pptx4.18.24 Movement Legacies, Reflection, and Review.pptx
4.18.24 Movement Legacies, Reflection, and Review.pptxmary850239
 
Oppenheimer Film Discussion for Philosophy and Film
Oppenheimer Film Discussion for Philosophy and FilmOppenheimer Film Discussion for Philosophy and Film
Oppenheimer Film Discussion for Philosophy and FilmStan Meyer
 
ClimART Action | eTwinning Project
ClimART Action    |    eTwinning ProjectClimART Action    |    eTwinning Project
ClimART Action | eTwinning Projectjordimapav
 
Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4JOYLYNSAMANIEGO
 
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONTHEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONHumphrey A Beña
 
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdfVirtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdfErwinPantujan2
 
The Contemporary World: The Globalization of World Politics
The Contemporary World: The Globalization of World PoliticsThe Contemporary World: The Globalization of World Politics
The Contemporary World: The Globalization of World PoliticsRommel Regala
 
Measures of Position DECILES for ungrouped data
Measures of Position DECILES for ungrouped dataMeasures of Position DECILES for ungrouped data
Measures of Position DECILES for ungrouped dataBabyAnnMotar
 
Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Mark Reed
 
Transaction Management in Database Management System
Transaction Management in Database Management SystemTransaction Management in Database Management System
Transaction Management in Database Management SystemChristalin Nelson
 
How to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPHow to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPCeline George
 
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdfGrade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdfJemuel Francisco
 
Expanded definition: technical and operational
Expanded definition: technical and operationalExpanded definition: technical and operational
Expanded definition: technical and operationalssuser3e220a
 
Dust Of Snow By Robert Frost Class-X English CBSE
Dust Of Snow By Robert Frost Class-X English CBSEDust Of Snow By Robert Frost Class-X English CBSE
Dust Of Snow By Robert Frost Class-X English CBSEaurabinda banchhor
 
ICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdfICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdfVanessa Camilleri
 
EMBODO Lesson Plan Grade 9 Law of Sines.docx
EMBODO Lesson Plan Grade 9 Law of Sines.docxEMBODO Lesson Plan Grade 9 Law of Sines.docx
EMBODO Lesson Plan Grade 9 Law of Sines.docxElton John Embodo
 
TEACHER REFLECTION FORM (NEW SET........).docx
TEACHER REFLECTION FORM (NEW SET........).docxTEACHER REFLECTION FORM (NEW SET........).docx
TEACHER REFLECTION FORM (NEW SET........).docxruthvilladarez
 

Recently uploaded (20)

Textual Evidence in Reading and Writing of SHS
Textual Evidence in Reading and Writing of SHSTextual Evidence in Reading and Writing of SHS
Textual Evidence in Reading and Writing of SHS
 
4.18.24 Movement Legacies, Reflection, and Review.pptx
4.18.24 Movement Legacies, Reflection, and Review.pptx4.18.24 Movement Legacies, Reflection, and Review.pptx
4.18.24 Movement Legacies, Reflection, and Review.pptx
 
Oppenheimer Film Discussion for Philosophy and Film
Oppenheimer Film Discussion for Philosophy and FilmOppenheimer Film Discussion for Philosophy and Film
Oppenheimer Film Discussion for Philosophy and Film
 
LEFT_ON_C'N_ PRELIMS_EL_DORADO_2024.pptx
LEFT_ON_C'N_ PRELIMS_EL_DORADO_2024.pptxLEFT_ON_C'N_ PRELIMS_EL_DORADO_2024.pptx
LEFT_ON_C'N_ PRELIMS_EL_DORADO_2024.pptx
 
ClimART Action | eTwinning Project
ClimART Action    |    eTwinning ProjectClimART Action    |    eTwinning Project
ClimART Action | eTwinning Project
 
Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4
 
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONTHEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
 
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdfVirtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
 
The Contemporary World: The Globalization of World Politics
The Contemporary World: The Globalization of World PoliticsThe Contemporary World: The Globalization of World Politics
The Contemporary World: The Globalization of World Politics
 
Measures of Position DECILES for ungrouped data
Measures of Position DECILES for ungrouped dataMeasures of Position DECILES for ungrouped data
Measures of Position DECILES for ungrouped data
 
Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)
 
Transaction Management in Database Management System
Transaction Management in Database Management SystemTransaction Management in Database Management System
Transaction Management in Database Management System
 
How to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPHow to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERP
 
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdfGrade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
 
Expanded definition: technical and operational
Expanded definition: technical and operationalExpanded definition: technical and operational
Expanded definition: technical and operational
 
Dust Of Snow By Robert Frost Class-X English CBSE
Dust Of Snow By Robert Frost Class-X English CBSEDust Of Snow By Robert Frost Class-X English CBSE
Dust Of Snow By Robert Frost Class-X English CBSE
 
YOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptx
YOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptxYOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptx
YOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptx
 
ICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdfICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdf
 
EMBODO Lesson Plan Grade 9 Law of Sines.docx
EMBODO Lesson Plan Grade 9 Law of Sines.docxEMBODO Lesson Plan Grade 9 Law of Sines.docx
EMBODO Lesson Plan Grade 9 Law of Sines.docx
 
TEACHER REFLECTION FORM (NEW SET........).docx
TEACHER REFLECTION FORM (NEW SET........).docxTEACHER REFLECTION FORM (NEW SET........).docx
TEACHER REFLECTION FORM (NEW SET........).docx
 

Real Estate Development Guide

  • 1. Real Estate Development Commercial Real Estate Development Youmni Al Jrab, PhD c, MBA 29th November 2012
  • 2. 2 Objectives • List the components of the real estate development processes • Conduct market survey and examine the demand and supply of the real estate market • Determine the best and optimum commercial use of the lands • Shortlist and appoint consultants • Identify and evaluate the critical elements of a real estate development • Evaluate financial feasibility of real estate development • A general overview of each phase of the development process
  • 3. 3 Session Outline 1. Introduction 2. Real estate development phases 3. Land acquisition and site analysis 4. Land statistics & built-up area 5. Conduct real estate market study 6. Conduct market survey & survey analysis 7. Determine the best use of the land & develop project brief 8. Prepare initial budget 9. Submit development proposal & getting management approval 10. Shortlist consultants 11. Define consultant scope of work 12. Invite consultants 13. Single source consultant / open a tender 14. Receive consultants’ proposals 15. Tendering process & consultant award 16. Selection criteria of consultants 17. Selection of building concept design 18. Design process 19. Construction phase 20. Q & A
  • 4. 4 “Real estate or property development includes activities that range from the renovation and re- lease of existing buildings to the purchase of raw land and the sale of improved land or parcels to others. Developers are the coordinators of the activities, converting ideas on paper into real property. Real estate development is different from construction.” - Wikipedia Introduction
  • 5. 5 • Developers buy land, finance real estate deals, build or have builders, build projects, design, control and orchestrate the process of development from the beginning to the end. • Developers purchase a land, determine the sales & marketing of the property, develop the building program and design, obtain the necessary approvals and financing, build the structure, lease, manage, and ultimately sell it. • Developers work with many different counterparts along each step of this process, including architects, city planners, engineers, surveyors, inspectors, consultants, contractors, lenders, brokers, leasing agents and more. What Developers Do
  • 6. 6 Real Estate Development Phases Research & Development Phase Design Phase Construction Phase
  • 8. 8 • Land location • Strategic location of the land • Availability of tourist attraction and major public services • Land direction, visibility & accessibility • The land surrounding & overlooking • Major developments • Area infrastructure & environmental issues • Future developments • Land topography and soil type • Land regulations, classification & related statistics Land Description Land Acquisition and Site Analysis
  • 11. 11 Site Analysis To Achrafieh 4 1 13 2 5 6 2 3 4 5 6 The Lawyer’s house BLC Bank The Palace of Justice The Doctor’s house TVA Building The Pharmacists’ Syndicate 7 Adlieh Round About 7 Availability of major public services
  • 12. 12 Site Analysis Land Surrounding: Malls and cinemas: ABC, Sodeco, Galaxy, Abraj And Habtoor Le Mall Universities: USJ, AUST and Sagesse Schools: Lyccee Francais, Girls School Hospitals: Hotel Dieux Others: Hypodrom, National Museum, Palace of Justice, CCF and Sioufi Park
  • 16. 16 Site Analysis Site Back View Panoramic Back View
  • 21. 21 1) Land location and Zone #: Achrafieh Zone 4 2) Plot area: 1,300 sq.m. 3) Total exploitation coefficient: 3.5 4) Extra balconies’ area: 20% 5) Extra area due to land location on a corner: 20% 6) Extra area for shafts & ducts: 20% 7) Allowed gross floor area: GFA 7862 sq.m. 8) Average number of floors: 13 floors 9) Allowed average floor area: 605 sq.m. 10) Average apartment per floor: 2 apartments 11) Apartment floor area: 300 sq.m. 12) Number of car parking pre each apartment 13) Total area required for parking spaces 14) Total number of parking basements 15) No. of Basements+ Ground floor+ Technical floor+ Typical floors+ Roof floor (# B+GF+Tech.F+#TF+RF) Land Statistics & Built-Up Area
  • 22. 22 • Review of the real estate market in the area • Examine historical figures of demand and supply • Projection of the upcoming demand • Upcoming projects and types of supplied units • Types of the existing projects • Full description of the surrounding projects (areas, selling prices, facilities, services, amenities, parking, finishing, no. of floors…..) • Performance of the existing projects • Benchmark Real Estate Market Study
  • 24. 24 J. Towers: - J. Towers is a 4 luxurious residential buildings built on a 4,000m2 land. - Location: Sioufi - Floors: varies between 14 and 21 floors. - Area of the apartments: 160, 230, 240, 250 & 300m2. - Prices: 2,550$ additional 50$/m2 for each higher floor. - Underground Cave for an additional 25,000$. - Bank Facilities with Bank Audi. - Extra Facilities: Gym and Garden - Actual status: Excavation. Done in 32months. Surrounding Projects
  • 25. 25 Ashrafieh 4748: - Ashrafieh 4748 is a 3 residential towers project. - Location: Nahr ElMoot, facing Fattal. - Floors: varies between 26 and 31 floors. - Area of the apartments: from 185, 230 till 330 m2. - Prices: 2,100$ additional 40$/m2 for each higher floor. - 3 Stores: 1,000m2 each with a mezzanine. - Bank Facilities with Bank Al-Mawared. - Extra Facilities: Gym, Pool and Garden. - Actual status: Excavation. Done in Dec 2013. Surrounding Projects
  • 26. 26 Landmark Tower: - Landmark tower is a 2 residential tower project built on a 3285m2 Land. - Location: Facing the Palace of Justice of Beirut. - Floors: 32 floors each building. - Area of the apartments: 350m2. - Prices: 3000$ for 10% of the project. 4000$ for 70% of the project. 5000$ for 20% of the project. - Actual status: Design and legal Permit. Surrounding Projects
  • 27. 27 Ashrafieh 2270: - Ashrafieh 2270 is a residential Building. - Location: Behind the Palace of Justice. - Floors: 10 floors. - Area of the apartment: 175sm, 2 apartment per floor. - Prices: 2,200$ additional 15,000$ for each higher floor. - Bank Facilities with Bloom Bank. - Actual status: Excavation. Surrounding Projects
  • 28. 28 Market Survey Site Analysis Real Estate Market Study Land Description Recommended Land Use & Project Type Market Survey
  • 29. 29 Market Survey • Select group of people of different (age, gender, marital status, social status, income) • Introduce the land, its description and its location • Ask questions related to the recommended land use: 1) Project types & building functions 2) Unit sizes 3) Expected selling price 4) Finance options 5) Parking 6) Finishing type 7) Facilities, services and amenities required 8) Etc……
  • 30. 30 Survey Analysis Age Range 21 to 30 yrs 42% 31 to 40 yrs 44% 41 to 50yrs 11% 50yrs & above 3% 21 to 30 yrs 31 to 40 yrs 41 to 50yrs 50yrs & above single 45% married 18% Married/1child 14% Married/2&above 23% single married Married/1child Married/2&above Marital Status Work Position Owner 13% Top mngt 13% Mid mngt 33% employee 41% Owner Top mngt Mid mngt employee where do they live? Beirut 78% south 4% North 4% Mountains 14% Beirut south North Mountains Demographics
  • 31. 31 Survey Analysis 0 20 40 60 Less than 75 m2 75m2 - 100m2 100 m2 - 125m2 More than 125 m2 S1 Office Area Series1 0 20 40 60 Less than 120 m2 120m2 - 150m2 150 m2 - 200m2 More than 200 m2 S1 Residential Area Series1 Market Demand
  • 32. 32 Survey Analysis Residential Price per M2 28% 47% 18% 7% Less than 2,200$ 2,200$-2,500$ 2,500$-2,800$ More than 2,800$ Office Price per M2 42% 47% 11% 0% Less than 2,500$ 2,500$-3,000$ 3,000$-3,500$ More than 3,500$ Price per sq.m.
  • 33. 33 Survey Analysis 0 5 10 15 20 25 30 35 40 Dependant Less than 2000$ 2,000$ - 3,500$Above 3,500$ Monthy Income Series1 Income
  • 34. 34 Survvey Analysis 63 26 37 74 0 10 20 30 40 50 60 70 80 Residential to buy vs to Rent Offices to buy vs to rent Options Percentage Series1 Series2 Buy Vs. Rent
  • 35. 35 Survey Analysis 0 5 10 15 20 25 1 Single vs. Married Choices single married Floor Choices
  • 36. 36 Survey Analysis Living in a Multi function Building 0 10 20 30 40 50 60 70 80 Residential & Offices Residential & Commercial Residential, Commercial & Offices None Series1 Building Specifications 0 10 20 30 40 50 60 Basic Medium High Luxurious Series1 Extra Facilities 0 5 10 15 20 25 30 35 40 45 50 Pool Garden Gym All of them Series1 Extra Parking 0 10 20 30 40 50 60 70 80 5,000$ - 10,000$ 10,000$ - 15,000$ 15,000$ - 20,000$ More than 20,000$ Series1 Facilities, Amenities & Additional Needs
  • 37. 37 Best Use of Land Market Survey The Best Use of Land & Project Brief Project Brief Project Brief: - Site description - Design Intent - Building types mix - BUA & floor areas - Floors Description - Areas - Unit Sizes - Room Sizes - Architectural Style - Interior Mood - Amenities - Facilities - Services - Finishing - Common areas - Exterior spaces - Car parking - Elevators - Etc…
  • 38. 38 1) Develop building structure 2) Identify cost assumptions (construction, consultancy, marketing and sales, overhead, management, financial, utilities, legal, etc….) 3) Assumed selling prices 4) Allocate direct construction costs 5) Allocate indirect cost 6) Sensitivity to cost & break-even point 7) Sales projection 8) Sensitivity to sales & break-even point 9) Cash flow projection 10) Profit & loss 11) Financial indicators (ROI, IRR, GPM, Pay back, etc…) Initial budget
  • 39. 39 Development Proposal & Management Approval Project Brief Project Initial Budget Land Description & Best Use Development Proposal GO AHEAD STOP
  • 41. 41 Prepare consultant selection criteria based on: 1) Consultant profile 2) Types of performed projects 3) Types of projects’ designs 4) Number of years in consultancy 5) Awards achieved 6) Staff qualifications 7) Consultancy fees 8) Available resources 9) Delivery period 10) Projects Designs Shortlist Consultants
  • 42. 42 • Design & supervision • Getting local permits • Geotechnical services • Civil / structural engineering • Mechanical / electrical / plumbing (MEP) engineering • IT network • Waste management • Security / safety / control system • Environmental study • Vertical transportation consultancy • Traffic assessment study & traffic management • Façade consultancy Consultant Scope Definition • Building maintenance consultancy • Fire engineering consultancy • Interior design • Landscaping design • Water feature design • Specialist lighting design • Technical review • Third party structural review • Value management • Wind tunnel analysis • Acoustic consultancy • Topographical surveys • Water filtration • Sewage treatment
  • 43. 43 Send invitations to shortlisted consultants including:  Project Brief  Scope of work  Terms & conditions of proposal  Plot certificate  Demarcation plan  Site development statistics  Guidelines  Leveling drawings  Secrecy undertaking Invitation of Consultants
  • 44. 44 Reasons of appointing one consultant without going through tendering process: 1) Repetition of same building design already built 2) Competencies of consultant in special designs 3) Uniqueness of the project 4) Follow management’s instruction 5) Other reasons: financial, time, resources, special equipment, staff, etc…… Single Source / Tender Opening
  • 45. 45 Consultancy proposal should include: 1) Understanding of the project 2) Scope of services 3) Proposed design stages & schedule 4) Fee proposal 5) Schedule of payment 6) Payment terms 7) Additional services & reimbursable costs 8) Scope exclusions 9) Provision of site facilities 10) Working hours 11) Termination Receiving Consultants' Proposals
  • 46. 46 Tendering Process & Consultant Award Tendering Process ProjectManager/ Development Manager TenderCo- ordinator ContractorConsultant Senior Contracts Manager Quantity Surveyor Prepare and send the following to consultants/ contractors approved on PRE 001: 1. Inquiry Fax signed by the Chairman of the Tender committee 2. Form for Secrecy Undertaking 3. Letter of Invitation (only after signing the Secrecy undertaking) File a copy of each form in the Projects file 1. Prepare the Tender documents using Emaar Standard Tender Documentation Preparation of list of contractors/consultants Preparation of Tender documents Distribute Tender to interested tenderers and obtain receipt Issue Tender Documents Issue Letter of Invitation signed by Chairman of Tender Committee Select Consultant / Contractor / Supplier from the Registered List of Contractors with regard to competency, experience and past performance etc and Prepare ‘List of Tenderers - Approval Form’ (PRE 001) and send for approval to the prescribed signatories as per Form PRE 001. Finalise the list (PRE 001) based on signing of Secrecy undertakingRetain the original approved list. A START Refer PRO S.O.P C.1 and C.2 Refer PRO S.O.P C.6 KPI Tenders to be floated within specified time of receipt of complete tender documents from Development. Process No: UAE/PDT/PDD/PRO 1.9Version No: 4 (25 Feb 2007) Process Owner: Senior Contracts ManagerDept Name: Project (Contracts)
  • 47. 47 Tendering Process & Consultant Award Tendering Process ProjectManager/ Development Manager TenderCo- ordinator Contractor Quantity Surveyor Senior Contracts Manager Consultant Issue Submission receipt to tenderer 1. Compile clarifications to queries. 2. Attach all addendums, circulars, bulletins etc to the clarification letter 3. Ensure it is signed by the Chairman of the Tender Committee B Receive tender queries from prospective tenderers and forward it to the PM Tender Submission Send clarifications with all addendums, circulars, bulletins etc to all tenderers and obtain collection receipt and acknowledgement slip from tenderer Submit four (4) copies of the bid to Emaar (Contracts department) Provide clarifications on the queries posed by the tenderers to the Tender Coordinator with copy to Project Manager / Development Manager Tender Queries and Addendum, Circulars and Bulletins A Keep Tenders in secure area till Tender opening Process No: UAE/PDT/PDD/PRO 1.9Version No: 4 (25 Feb 2007) Process Owner: Senior Contracts ManagerDept Name: Project (Contracts) Refer PRO S.O.P C.7 and C.8 Refer PRO S.O.P C.9 Review and get Consultant to respond
  • 48. 48 Tendering Process & Consultant Award Tendering Process Tender Committ ee ProjectManager/ Development Manager TenderCo- ordinator ConsultantContractor Quantity Surveyor Senior Contracts Manager Tender Opening by Tender Committee B Respond to Post Tender Clarifications to the Chairman of the Tender Committee Review the Tender Reports Provide supplemental Tender Reports to Chairman of the Tender committee Submit final Tender Report recommendations to Chairman of the Tender Committee Clarifications satisfactory? 1. Register and maintain the safe custody of Tender Bond 2. Make entries in Tender Opening Register. 3. Monitor the validity of the Tender bonds and arrange for extension as required. 1. Prepare ‘Tender Opening - Record Form’ (PRE 002) 2. Extract Tender Bond 3. Send copies to Technical Consultant and Commercial Consultants for review Submit 4 copies of Technical and Commercial Tender Reports to Chairman of Tender Committee Conduct detailed technical and commercial evaluations Open the Tender on behalf of the Tender Committee and record name, and price. Receive the Tender Report on behalf of Tender Committee and forward to Project Manager and Senior Contracts Manager for review Review the Tender Reports Issue post-Tender queries to tenderers Yes C No Tender evaluation, clarifications and negotiations Submit soft copy of technical and commercial questionnaires to Tender Co-ordinator Is clarification from tenderer required? No Yes Process No: UAE/PDT/PDD/PRO 1.9Version No: 4 (25 Feb 2007) Process Owner: Senior Contracts ManagerDept Name: Project (Contracts) Refer PRO S.O.P C.10 and C.11 Refer PRO S.O.P C.12 and C.13 KPI Recommendation to Award of Contract within specified time of receipt of Tender bids. KPI KPI : 1. Recommendation to Award of Contract within specified time of receipt of Tender bids. 2. Ensure procurement of Best Price for each project.
  • 49. 49 Tendering Process & Consultant Award Tendering Process Tender Committe e ProjectManager/ Development Manager Administrative Assistant Contractor Quantity Surveyor Senior Contracts Manager Consultant Inform unsuccessful tenderers and return Tender Bond Receive LOA and distribute as follows: i. Contractor (Original) ii. Project Cost Administrator (Copy) iii. Project Manager (Copy) iv. Insurance Administrator (Copy) V. Contracts Department Prepare the Award of contract - Approval form (PRE 003 / 003A / 003B as applicable) and attach with the form : i. Explanatory covering memo to Senior Management and Board (if applicable) ii. Summary of Tender Report submitted by consultant iii. Budget Reconciliation C Arrange for Consultant review, Verify and forward the Performance Bond to Quantity Surveyor for filing Performance Bond Receive Performance bond from Contractor Schedule a Kick-off meeting to be attended by successful contractor, Consultant and Project Manager Return countersigned LOA Prepare LOA for signature by authorised management personnel Return Tender bond Prepare the Draft Contract based on the tender submission, subsequent clarifications and agreement reached Review the contract document Review drawings and specifications 1. Prepare ‘Contracts Document - Approval Form’ (PRE 004) 2. Get ED (Projects) to sign on both copies of the Contract 3. Keep one original and return one original to contractor. Prepare 2 original sets of Contract document and send to contractor to be signed END Award of Contract and Preparation of Contract Documents Distribute PRE 003 / 003A / 003B as applicable with supporting documents for remaining signatures as per Authority Matrix Register and maintain safe custody of Performance Bond Forward the signed PRE 003 / 003A / 003B as applicable and supporting documentation to Senior Contracts Manager. Refer PRO S.O.P C.14 and C.16 Refer PRO S.O.P D.2 Review the PRE 003 / 003A / 003B as applicable with supporting documentation and recommend to Tender Committee Keep the original documentation and file. Process No: UAE/PDT/PDD/PRO 1.9Version No: 4 (25 Feb 2007) Process Owner: Senior Contracts ManagerDept Name: Project (Contracts) Monitor the validity of the bonds and arrange for extension, if necessary Refer PRO S.O.P D.1 KPI Issue LOA within specified time of receipt of contract award of aproval. KPI Contract to be signed within specified time of LOA. Review the recommendations provided and approve or reject.(in cases of rejection, process to be repeated until approval is granted.)
  • 50. 50 Selection Criteria of Consultants Grade is given for each criteria based on the objective of the developer and the consultant who gets the highest total grade is selected: Grade (1-10) Coeff.% T. Grade 1) Consultant profile 5 7 % 0.35 2) Types of performed projects 7 5 % 0.35 3) Types of projects’ designs 8 7 % 0.56 4) Number of years in consultancy 8 8 % 0.64 5) Awards achieved 4 3 % 0.12 6) Staff qualifications 7 10 % 0.70 7) Consultancy fees 9 17 % 1.53 8) Available resources 6 3 % 0.18 9) Delivery period 9 15 % 1.35 10)Design 9 25% 2.25 -------- --------- 100% 8.03
  • 51. 51 Selection of Building Concept Design 1) Compare design to the design intent mentioned in project brief 2) Compare consultant fee to budget (support of quantity surveyor QS) 3) Specialists’ opinions and management approval
  • 52. 52 1) Concept Design Sign-Off 2) Schematic Design Sign-Off 3) Commence Design Development 4) Design NOCs to Authorities 5) Complete Soils Report & Tests 6) Shoring & Excavation Permits & Commence Shoring & Excavation 7) Design Budget 8) Design Development Sign Off 9) Commence Working Drawings 10) Commence Piling Package 11) Prepare BOQ 12) Piling Permit & commence piling 13) Working Drawings & Tender Documents Sign-Off 14) Contractors invitation and appoint contractor 15) Contract Award Budget 16) Commence Building Construction Design Process
  • 54. 54