Planning & controlling design &
    engineering projects
    An overview of
                                                      The TechnoCentre
                                                             Puma Way
                                                      Coventry CV1 2TW
                                                        United Kingdom

                                                 Tel: +44(0)24 7623 6929
                                                 Fax: +44(0)24 7623 6930
                               E-mail: enquiries@adeptmanagement.com
                                       URL: www.adeptmanagement.com




© Adept Management Ltd, 2009
Adept Management
                                                                                  Design & Bid Management
                                                                                  Interim Design Managers
                                                                               Strategic Planning & Monitoring

                                     ADePT                   Design           Process & Procedure Development


                                    Services               Management

            Integrated Design Planning
                 Process Control
        Design Team Performance Reporting




                                               ADePT Design
                                               Software Suite   ADePT Design Builder
                                                                ADePT Design Manager
                                                                  Software Training




© Adept Management Ltd, 2009
Characteristics of Design

        o Iterative
        o Driven by information
        o Highly complex
        o Not well understood
        o Broken into sub-problems
        o Involving many people
        o Undertaken in stages




© Adept Management Ltd, 2009
Poorly Managed Engineering - The Effect


        2008 Construction Performance

        o Fact – design / engineering projects overspend
             • 35% of design commissions overspend

        o Fact - design / engineering projects over-run
             • 42% of design commissions are late

        o Severe knock on effects in construction
             • 52% of construction projects overspend

             • 42% of construction work is late


                      Source: Office for National Statistics’ Construction Statistics Annual, 2008
© Adept Management Ltd, 2009
Overview of the        methodology




© Adept Management Ltd, 2009
Current & Recent Implementations of ADePT




© Adept Management Ltd, 2009
ADePT - Benefits Identified

        o      Identification and removal of “turbulence”
        o      Greater certainty of design co-ordination
        o      Ability to better prioritise design work
        o      Focus on task completion
        o      Effective integration of sub-contractor design
        o      Better change management
        o      Improved team collaboration
        o      Self-policing design team
        o      Design fee validation

© Adept Management Ltd, 2009
Generating an
                               Integrated Design Plan




© Adept Management Ltd, 2009
Overview of the        methodology




© Adept Management Ltd, 2009
A Typical Design Processes




© Adept Management Ltd, 2009
A Typical Design Processes




© Adept Management Ltd, 2009
A Typical Design Processes
               External Constraints




                   Deliverable                                                      External Constraints




                   Deliverable


                                                                                         External Constraints




  External Constraints




                         Deliverable                                 Deliverable.
                                         Deliverable


                                       Deliverable
                                                       External Constraints
© Adept Management Ltd, 2009
Taking a Hierarchical View




© Adept Management Ltd, 2009
Taking a Hierarchical View




© Adept Management Ltd, 2009
Taking a Hierarchical View




© Adept Management Ltd, 2009
Information exchanges




© Adept Management Ltd, 2009
Information exchanges




                                 Activity
                               properties




© Adept Management Ltd, 2009
Information exchanges




                                 Information
                               requirements
                                    Activity
                                  properties

                                Information
                                    outputs




© Adept Management Ltd, 2009
Information exchanges



                                Predecessor
                                   activities

                                 Information
                               requirements
                                    Activity
                                  properties

                                Information
                                    outputs

                                  Successor
                                   activities

© Adept Management Ltd, 2009
Setting up a matrix of the design process




             1. List design activities in the matrix rows in any arbitrary order, and repeat the list across the
             columns of the matrix.




© Adept Management Ltd, 2009
Representing dependencies




              2. Mark the matrix to indicate where the activity in the row depends on the activity in the
              column (e.g. requires information produced by, or requires a decision made from, the activity
              in the column).
             3. Classify the dependencies the show the strength of the requirement: A = vital (should
             have); B = important (would like to have); or C = nice to have.
© Adept Management Ltd, 2009
Identifying design assumptions
 Design process sequence




                             4. Assume the activities are to be undertaken in the order shown and identify any assumptions
                             to be made. For example: activity 3 depends on activities 1, 2, 4 & 13. In the order shown
                             activities 1 & 2 have been undertaken but 4 & 13 have not. So, to undertake activity 3
                             assumptions about the outputs from 4 & 13 must be made.

© Adept Management Ltd, 2009
Identifying iteration in the design process




                             Dependency classification
             5. Identify all assumptions and scale of iteration in the design process. For example: activity 3
             can only be undertaken if an assumption is made about = nice to have
                             A = vital; B = important; C the output from activity 13 and
             activity 13 itself requires assumptions to be made about the outputs from 15, 16 & 19. So,
             only when activity 19 has been undertaken can all assumptions be checked and any rework be
             undertaken. Therefore all activities from 3 to 19 are in an iterative rework loop.
© Adept Management Ltd, 2009
Optimizing the design sequence




             6. Optimize the sequence of the activities to minimize the number of assumptions which need
             to be made and ensure that assumptions which cannot be made with a high level of
             confidence (classified A & B) are included within iterative rework loops whilst assumptions
             which can be made with confidence (C) are not.

© Adept Management Ltd, 2009
Breaking down iterative rework loops




             7. If necessary (i.e. if the scale of iteration is greater than can be managed in the time
             available) identify assumptions which can reduce the scale of iteration further if made in such
             a way that the designers have confidence in them e.g. by over-estimating structural loadings
             or fixing a typical interface detail.

© Adept Management Ltd, 2009
Re-optimizing the design sequence




             8. Re-optimize the sequence of the activities and record any new assumptions which are now
             not included in iterative rework loops.




© Adept Management Ltd, 2009
In practice: clusters represent systems

                                          Detailed Locker Room Co-ordination


                                                      Sub-structure
                                                      Co-ordination


                                                  Ceiling Voids &
                                                  RCP Co-ordination




                               Envelope / Structure
                               Interface


© Adept Management Ltd, 2009
A view of all clusters / systems




© Adept Management Ltd, 2009
Create the Programme




© Adept Management Ltd, 2009
Co-ordination loops
identified in ADePT
  and shown in the
design programme



© Adept Management Ltd, 2009
Variance: construction vs. design dates
                                                       Target Tender
           Procurement Packages
                                                           Date      -100 -80   -60   -40   -20   0   20   40   60   80   100

           Bicycle Enclosures                           13/07/2009
           Vehicle Barriers                             13/07/2009
           Soft Landscaping                             19/01/2009
           Internal Signage                             06/04/2009
           Floor Screed                                 09/02/2009
           External Signage                             23/03/2009
           Decorations                                  06/04/2009
           External Render                              05/01/2009
           Floor & Wall Tiling                          23/03/2009
           Soft Flooring                                23/03/2009
           Lifts                                        09/02/2009
           Internal Glazed Screening                    10/11/2008
           FF&E inc. White Goods                        02/03/2009
           Catering / Kitchen Equipment                 15/12/2008
           Small Kitchen Fitout                         16/02/2009
           Fixed Furniture inc. Reception Desk          03/11/2008
           Security Fencing                             06/10/2008
           Floor Painting / Epoxy Flooring              19/01/2009
           Hard Landscaping                             04/08/2008
           Internal Joinery                             15/12/2008
           Plumberwork / Sanitary / Toilet Fitout       17/10/2008
           BWIC                                         24/11/2008
           Toilet & Kitchen Pods                        17/10/2008
           Internal Doors & Ironmongery                 17/11/2008
           Roof Mansafe                                 18/08/2008
           Brick & Blockwork inc. Windposts             28/07/2008
           RainWater System                             11/08/2008
           Dry Lining / Plasterboard / Fire Stopping    25/08/2008
           Flat Roof Coverings                          23/06/2008
           Raised Flooring                              04/08/2008
           Roof Cladding / Finishes                     26/05/2008
           Roller Shutter Doors                         02/06/2008
           Suspended Ceilings                           22/09/2008
           Sports Pitches                               07/04/2008
           Architectural & General Metalwork            18/08/2008
           Sliding / Folding Partitions                 10/11/2008
           Curtain Walling                              28/04/2008
           Insitu Concrete Frames                       30/06/2008
           External Windows / Doors / Glazing           19/05/2008
           M&E Building Services                        11/02/2008
           Retaining walls / Structures                 05/11/2007
           Precast Cladding                             17/03/2008
           Site enabling / Ground works                 05/11/2007
           Drainage SW / FW                             02/11/2007
           Substructures inc. Ground Slabs              14/04/2008
           Structural Steelwork / Decking / Purlings    31/03/2008
           Precast Concrete: Slabs, Stairs, Column      28/04/2008
           External Crib Walling                        05/11/2007

© Adept Management Ltd, 2009
           External Services
           External CIS Pit & Ducting
                                                        21/10/2007
                                                        02/11/2007
Imposing Constraints




© Adept Management Ltd, 2009
Understanding the impact




                          Impact understood and a managed
                           decision can be made to resolve
                                      this issue
© Adept Management Ltd, 2009
Result: aligned construction & design dates
                                                       Target Tender
           Procurement Packages
                                                           Date      -100 -80   -60   -40   -20   0   20   40   60   80   100 -100   -80   -60   -40   -20   0   20

           Bicycle Enclosures                           13/07/2009
           Vehicle Barriers                             13/07/2009
           Soft Landscaping                             19/01/2009
           Internal Signage                             06/04/2009
           Floor Screed                                 09/02/2009
           External Signage                             23/03/2009
           Decorations                                  06/04/2009
           External Render                              05/01/2009
           Floor & Wall Tiling                          23/03/2009
           Soft Flooring                                23/03/2009
           Lifts                                        09/02/2009
           Internal Glazed Screening                    10/11/2008
           FF&E inc. White Goods                        02/03/2009
           Catering / Kitchen Equipment                 15/12/2008
           Small Kitchen Fitout                         16/02/2009
           Fixed Furniture inc. Reception Desk          03/11/2008
           Security Fencing                             06/10/2008
           Floor Painting / Epoxy Flooring              19/01/2009
           Hard Landscaping                             04/08/2008
           Internal Joinery                             15/12/2008
           Plumberwork / Sanitary / Toilet Fitout       17/10/2008
           BWIC                                         24/11/2008
           Toilet & Kitchen Pods                        17/10/2008
           Internal Doors & Ironmongery                 17/11/2008
           Roof Mansafe                                 18/08/2008
           Brick & Blockwork inc. Windposts             28/07/2008
           RainWater System                             11/08/2008
           Dry Lining / Plasterboard / Fire Stopping    25/08/2008
           Flat Roof Coverings                          23/06/2008
           Raised Flooring                              04/08/2008
           Roof Cladding / Finishes                     26/05/2008
           Roller Shutter Doors                         02/06/2008
           Suspended Ceilings                           22/09/2008
           Sports Pitches                               07/04/2008
           Architectural & General Metalwork            18/08/2008
           Sliding / Folding Partitions                 10/11/2008
           Curtain Walling                              28/04/2008
           Insitu Concrete Frames                       30/06/2008
           External Windows / Doors / Glazing           19/05/2008
           M&E Building Services                        11/02/2008
           Retaining walls / Structures                 05/11/2007
           Precast Cladding                             17/03/2008
           Site enabling / Ground works                 05/11/2007
           Drainage SW / FW                             02/11/2007
           Substructures inc. Ground Slabs              14/04/2008
           Structural Steelwork / Decking / Purlings    31/03/2008
           Precast Concrete: Slabs, Stairs, Column      28/04/2008
           External Crib Walling                        05/11/2007

© Adept Management Ltd, 2009
           External Services
           External CIS Pit & Ducting
                                                        21/10/2007
                                                        02/11/2007
Key decisions required to integrate design & procurement




© Adept Management Ltd, 2009
Programme for one design discipline




© Adept Management Ltd, 2009
Programme for one project stage




© Adept Management Ltd, 2009
Controlling a Design Project




© Adept Management Ltd, 2009
Overview of the        methodology




© Adept Management Ltd, 2009
80%
                                                                                  70%




                                                              % P lan Com plete
                                                                                  60%
                                                                                  50%




       Select tasks to add to the work plan for this period
                                                                                  40%
                                                                                  30%
                                                                                  20%
                                                                                  10%
                                                                                  0%
                                                                                        Aug   Sep   Oct   Nov   Dec




© Adept Management Ltd, 2009
80%
                                                                         70%




                                                     % P lan Com plete
                                                                         60%
                                                                         50%




        Task Priorities
                                                                         40%
                                                                         30%
                                                                         20%
                                                                         10%
                                                                         0%
                                                                               Aug   Sep   Oct   Nov   Dec




                                        End of
            Current                     Focus
             Date                       Period

     Late

                 Due to be completed



                                        Due to be
                                        progressed




                         Focus Period

© Adept Management Ltd, 2009
80%
                                                                                                             70%




                                                                                         % P lan Com plete
                                                                                                             60%
                                                                                                             50%




        Task Priorities
                                                                                                             40%
                                                                                                             30%
                                                                                                             20%
                                                                                                             10%
                                                                                                             0%
                                                                                                                   Aug   Sep   Oct   Nov   Dec




                                        End of                                   End of
            Current                     Focus                                  Look-Ahead
             Date                       Period                                   Period

     Late

                 Due to be completed



                                        Due to be
                                        progressed
                                                     Due to be completed in
                                                     the next period


                                                                              Due to be progressed
                                                                              in the next period




                                                     Look-Ahead
                         Focus Period
                                                       Period
© Adept Management Ltd, 2009
80%
                                                                                  70%




                                                              % P lan Com plete
                                                                                  60%
                                                                                  50%




       Select tasks to add to the work plan for this period
                                                                                  40%
                                                                                  30%
                                                                                  20%
                                                                                  10%
                                                                                  0%
                                                                                        Aug   Sep   Oct   Nov   Dec




                                   Due to be completed



                                   Due to be progressed




© Adept Management Ltd, 2009
80%
                                                                                                70%




                                                                            % P lan Com plete
                                                                                                60%
                                                                                                50%




       Select tasks to add to the work plan for this period
                                                                                                40%
                                                                                                30%
                                                                                                20%
                                                                                                10%
                                                                                                0%
                                                                                                      Aug   Sep   Oct   Nov   Dec




                                   Due to be completed



                                   Due to be progressed


                                   Due to be completed in the next period


© Adept Management Ltd, 2009
80%
                                                                       70%




                                                   % P lan Com plete
                                                                       60%
                                                                       50%




        Publish the work plan to the design team
                                                                       40%
                                                                       30%
                                                                       20%
                                                                       10%
                                                                       0%
                                                                             Aug   Sep   Oct   Nov   Dec




© Adept Management Ltd, 2009
80%
                                                               70%




                                           % P lan Com plete
                                                               60%
                                                               50%




        Output for Designers to Complete
                                                               40%
                                                               30%
                                                               20%
                                                               10%
                                                               0%
                                                                     Aug   Sep   Oct   Nov   Dec




© Adept Management Ltd, 2009
80%
                                                                            70%




                                                        % P lan Com plete
                                                                            60%
                                                                            50%




        Manage any constraints identified by the team
                                                                            40%
                                                                            30%
                                                                            20%
                                                                            10%
                                                                            0%
                                                                                  Aug   Sep   Oct   Nov   Dec




© Adept Management Ltd, 2009
80%
                                                                             70%




                                                         % P lan Com plete
                                                                             60%
                                                                             50%




        Validate the progress given by the design team
                                                                             40%
                                                                             30%
                                                                             20%
                                                                             10%
                                                                             0%
                                                                                   Aug   Sep   Oct   Nov   Dec




© Adept Management Ltd, 2009
80%
                                                                          70%




                                                      % P lan Com plete
        Write progress back to the design programme
                                                                          60%
                                                                          50%
                                                                          40%
                                                                          30%




        so that it can be rescheduled
                                                                          20%
                                                                          10%
                                                                          0%
                                                                                Aug   Sep   Oct   Nov   Dec




© Adept Management Ltd, 2009
80%
                                                                                                                70%




                                                                                            % P lan Com plete
                                                                                                                60%
                                                                                                                50%




        Workflow process in practice
                                                                                                                40%
                                                                                                                30%
                                                                                                                20%
                                                                                                                10%
                                                                                                                0%
                                                                                                                      Aug   Sep   Oct   Nov   Dec




                               Start of Focus period
                                                                            2. Publish
                                                         1. Generate
                                                                           Workplan to
                                                          Workplan
                                                                           design team


           Reschedule
           programme


                                                           4. Update         3. Update
                                                                           Workplan with
                                                         programme &
                                                                          team’s progress
                               End of Focus period




                                                       archive Workplan
                                                                           & constraints




© Adept Management Ltd, 2009
80%
                                                              70%




        Update the programme and report




                                          % P lan Com plete
                                                              60%
                                                              50%
                                                              40%
                                                              30%




        performance
                                                              20%
                                                              10%
                                                              0%
                                                                    Aug   Sep   Oct   Nov   Dec




© Adept Management Ltd, 2009
80%
                                                           70%




                                       % P lan Com plete
                                                           60%
                                                           50%




        Understand and report trends
                                                           40%
                                                           30%
                                                           20%
                                                           10%
                                                           0%
                                                                 Aug   Sep   Oct   Nov   Dec




© Adept Management Ltd, 2009
80%
                                                                   70%




                                               % P lan Com plete
        Report overall progress:
                                                                   60%
                                                                   50%
                                                                   40%
                                                                   30%




        activities, information or documents
                                                                   20%
                                                                   10%
                                                                   0%
                                                                         Aug   Sep   Oct   Nov   Dec




                   • Activities completed
                   • Information produced
                   • Documentation issued




© Adept Management Ltd, 2009
80%
                                                                            70%




                                                        % P lan Com plete
                                                                            60%
                                                                            50%




        Overall Reporting
                                                                            40%
                                                                            30%
                                                                            20%
                                                                            10%
                                                                            0%
                                                                                  Aug   Sep   Oct   Nov   Dec




   o    What did we plan to achieve?
   o    What did we complete?
   o    What did we fail?                       Looking Back
   o    Why did we fail?
   o    Fix problem and re-plan!


   o What do we need to start / complete the
     activity in the future?
   o What could stop us?
                                               Looking Forward
   o How can we mitigate the risks?
   o Ensure that we plan to deliver?



© Adept Management Ltd, 2009
Managing change (emerging need for
        re-design)




© Adept Management Ltd, 2009
Understanding the impact




                Impact understood and an evidence-based decision
© Adept Management Ltd, 2009 made to resolve this by all parties
Planning & controlling design &
    engineering projects
    An overview of
                                                      The TechnoCentre
                                                             Puma Way
                                                      Coventry CV1 2TW
                                                        United Kingdom

                                                 Tel: +44(0)24 7623 6929
                                                 Fax: +44(0)24 7623 6930
                               E-mail: enquiries@adeptmanagement.com
                                       URL: www.adeptmanagement.com




© Adept Management Ltd, 2009

More Related Content

What's hot

Probase Road System (18 slides)
Probase Road System  (18 slides)Probase Road System  (18 slides)
Probase Road System (18 slides)Harshad Master
 
Chunnel Project_Development Phase
Chunnel Project_Development PhaseChunnel Project_Development Phase
Chunnel Project_Development PhaseKhyati Tewari
 
Chunnel project project cost management
Chunnel  project project cost managementChunnel  project project cost management
Chunnel project project cost managementSagar Rana
 
Construction Management full lecture note-By Melese Mengistu.pdf
Construction Management full lecture note-By Melese Mengistu.pdfConstruction Management full lecture note-By Melese Mengistu.pdf
Construction Management full lecture note-By Melese Mengistu.pdfMeleseMengistu
 
Project Delivery Methods
Project Delivery MethodsProject Delivery Methods
Project Delivery MethodsStacy Abernathy
 
PERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTPERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTsalsa moyara
 
Construction Equipment Management
Construction Equipment ManagementConstruction Equipment Management
Construction Equipment ManagementAhmed Ezz-eldin
 
Pm first presentation
Pm first presentationPm first presentation
Pm first presentationcarlobisio
 
Qualities of an effective project manager
Qualities of an effective project managerQualities of an effective project manager
Qualities of an effective project managerArdniel Baladjay
 
03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling03 Construction Project Planning and Scheduling
03 Construction Project Planning and Schedulingakashpadole
 
Hot mix plant report - **HOT MIX ASPHALT PLANTS EMISSION ASSESSMENT REPORT**
Hot mix plant report - **HOT MIX ASPHALT PLANTS EMISSION ASSESSMENT REPORT**Hot mix plant report - **HOT MIX ASPHALT PLANTS EMISSION ASSESSMENT REPORT**
Hot mix plant report - **HOT MIX ASPHALT PLANTS EMISSION ASSESSMENT REPORT**Parth Desani
 
Summary chunnel tunnel project management
Summary chunnel tunnel project managementSummary chunnel tunnel project management
Summary chunnel tunnel project managementNilesh Dhotre
 
Variation: it’s Regulation & Management under the MDB-FIDIC (2006) & the PPA ...
Variation: it’s Regulation & Management under the MDB-FIDIC (2006) & the PPA ...Variation: it’s Regulation & Management under the MDB-FIDIC (2006) & the PPA ...
Variation: it’s Regulation & Management under the MDB-FIDIC (2006) & the PPA ...MMS presentation firm
 
Construction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential BuildingConstruction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential BuildingSHAZEBALIKHAN1
 
Project Engineer and Deputy project manger
Project Engineer and Deputy project manger Project Engineer and Deputy project manger
Project Engineer and Deputy project manger Adil Mehmoood
 
Project Management Professional PMI-PMP Based on PMBOK 6th Edition
Project Management Professional PMI-PMP Based on PMBOK 6th EditionProject Management Professional PMI-PMP Based on PMBOK 6th Edition
Project Management Professional PMI-PMP Based on PMBOK 6th EditionJohn Khateeb
 
Project Execution PowerPoint Presentation Slides
Project Execution PowerPoint Presentation SlidesProject Execution PowerPoint Presentation Slides
Project Execution PowerPoint Presentation SlidesSlideTeam
 

What's hot (20)

Probase Road System (18 slides)
Probase Road System  (18 slides)Probase Road System  (18 slides)
Probase Road System (18 slides)
 
Airport Construction
Airport ConstructionAirport Construction
Airport Construction
 
Chunnel Project_Development Phase
Chunnel Project_Development PhaseChunnel Project_Development Phase
Chunnel Project_Development Phase
 
Chunnel project project cost management
Chunnel  project project cost managementChunnel  project project cost management
Chunnel project project cost management
 
Construction Management full lecture note-By Melese Mengistu.pdf
Construction Management full lecture note-By Melese Mengistu.pdfConstruction Management full lecture note-By Melese Mengistu.pdf
Construction Management full lecture note-By Melese Mengistu.pdf
 
Project Delivery Methods
Project Delivery MethodsProject Delivery Methods
Project Delivery Methods
 
PERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTPERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENT
 
Construction Equipment Management
Construction Equipment ManagementConstruction Equipment Management
Construction Equipment Management
 
Pm first presentation
Pm first presentationPm first presentation
Pm first presentation
 
Qualities of an effective project manager
Qualities of an effective project managerQualities of an effective project manager
Qualities of an effective project manager
 
03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling
 
Hot mix plant report - **HOT MIX ASPHALT PLANTS EMISSION ASSESSMENT REPORT**
Hot mix plant report - **HOT MIX ASPHALT PLANTS EMISSION ASSESSMENT REPORT**Hot mix plant report - **HOT MIX ASPHALT PLANTS EMISSION ASSESSMENT REPORT**
Hot mix plant report - **HOT MIX ASPHALT PLANTS EMISSION ASSESSMENT REPORT**
 
Summary chunnel tunnel project management
Summary chunnel tunnel project managementSummary chunnel tunnel project management
Summary chunnel tunnel project management
 
Variation: it’s Regulation & Management under the MDB-FIDIC (2006) & the PPA ...
Variation: it’s Regulation & Management under the MDB-FIDIC (2006) & the PPA ...Variation: it’s Regulation & Management under the MDB-FIDIC (2006) & the PPA ...
Variation: it’s Regulation & Management under the MDB-FIDIC (2006) & the PPA ...
 
Capacity at intersection
Capacity at intersectionCapacity at intersection
Capacity at intersection
 
Construction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential BuildingConstruction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential Building
 
UNIT 1
UNIT 1UNIT 1
UNIT 1
 
Project Engineer and Deputy project manger
Project Engineer and Deputy project manger Project Engineer and Deputy project manger
Project Engineer and Deputy project manger
 
Project Management Professional PMI-PMP Based on PMBOK 6th Edition
Project Management Professional PMI-PMP Based on PMBOK 6th EditionProject Management Professional PMI-PMP Based on PMBOK 6th Edition
Project Management Professional PMI-PMP Based on PMBOK 6th Edition
 
Project Execution PowerPoint Presentation Slides
Project Execution PowerPoint Presentation SlidesProject Execution PowerPoint Presentation Slides
Project Execution PowerPoint Presentation Slides
 

Similar to Planning & controlling design projects

Asset information management for design build r novak arc 2008
Asset information management for design build r novak arc 2008Asset information management for design build r novak arc 2008
Asset information management for design build r novak arc 2008ARC Advisory Group
 
Considerations in Selecting and Protecting Your IT Investment
Considerations in Selecting and Protecting Your IT InvestmentConsiderations in Selecting and Protecting Your IT Investment
Considerations in Selecting and Protecting Your IT InvestmentHelene Heller, PMP
 
Kepner Tregoe Developing Your Hr Project Management Skills
Kepner Tregoe  Developing Your Hr Project Management SkillsKepner Tregoe  Developing Your Hr Project Management Skills
Kepner Tregoe Developing Your Hr Project Management SkillsJessica Booth
 
Skyward Erp Presentation
Skyward Erp PresentationSkyward Erp Presentation
Skyward Erp Presentationvishalnvora1
 
Business PMO & IT Pmo What Is The Difference
Business PMO & IT Pmo What Is The DifferenceBusiness PMO & IT Pmo What Is The Difference
Business PMO & IT Pmo What Is The DifferenceStefan Rank
 
David Chan Profile And Experience
David Chan Profile And ExperienceDavid Chan Profile And Experience
David Chan Profile And ExperienceDavid Chan
 
Exploiting Tools for Faster, More Acceptable Process Improvement Initiatives
Exploiting Tools for Faster, More Acceptable Process Improvement InitiativesExploiting Tools for Faster, More Acceptable Process Improvement Initiatives
Exploiting Tools for Faster, More Acceptable Process Improvement InitiativesMahesh Singh
 
Safety in special environments - solutions developed by swiss IT-Factory
Safety in special environments - solutions developed by swiss IT-FactorySafety in special environments - solutions developed by swiss IT-Factory
Safety in special environments - solutions developed by swiss IT-FactoryMinnovarc
 
G2 It Services Overview 09.07.01
G2 It Services Overview 09.07.01G2 It Services Overview 09.07.01
G2 It Services Overview 09.07.01wdgleaton
 
MOF 4 Overviewv - ITSM Academy Webinar
MOF 4 Overviewv - ITSM Academy WebinarMOF 4 Overviewv - ITSM Academy Webinar
MOF 4 Overviewv - ITSM Academy WebinarITSM Academy, Inc.
 
Att consulting external deck
Att consulting external deckAtt consulting external deck
Att consulting external deckEric Sineath
 
Tml Deployment Strategy Overview V 1
Tml Deployment Strategy Overview V 1Tml Deployment Strategy Overview V 1
Tml Deployment Strategy Overview V 1Sukumar Daniel
 
Enterprise Applications
Enterprise ApplicationsEnterprise Applications
Enterprise Applicationsswamysenthil
 
Maximizing EA Impact: Using Business Architecture to Achieve Alignment
Maximizing EA Impact: Using Business Architecture to Achieve AlignmentMaximizing EA Impact: Using Business Architecture to Achieve Alignment
Maximizing EA Impact: Using Business Architecture to Achieve AlignmentDavid Baker
 
Infusing EPM in people and process
Infusing EPM in people and processInfusing EPM in people and process
Infusing EPM in people and processRavi Tirumalai
 
ISSUE & WIKI based Integration of Project Management
ISSUE & WIKI based Integration of Project ManagementISSUE & WIKI based Integration of Project Management
ISSUE & WIKI based Integration of Project ManagementPeter Kim
 

Similar to Planning & controlling design projects (20)

Asset information management for design build r novak arc 2008
Asset information management for design build r novak arc 2008Asset information management for design build r novak arc 2008
Asset information management for design build r novak arc 2008
 
Considerations in Selecting and Protecting Your IT Investment
Considerations in Selecting and Protecting Your IT InvestmentConsiderations in Selecting and Protecting Your IT Investment
Considerations in Selecting and Protecting Your IT Investment
 
Kepner Tregoe Developing Your Hr Project Management Skills
Kepner Tregoe  Developing Your Hr Project Management SkillsKepner Tregoe  Developing Your Hr Project Management Skills
Kepner Tregoe Developing Your Hr Project Management Skills
 
Skyward Erp Presentation
Skyward Erp PresentationSkyward Erp Presentation
Skyward Erp Presentation
 
EA Roadmapping
EA RoadmappingEA Roadmapping
EA Roadmapping
 
Business PMO & IT Pmo What Is The Difference
Business PMO & IT Pmo What Is The DifferenceBusiness PMO & IT Pmo What Is The Difference
Business PMO & IT Pmo What Is The Difference
 
EA Benefits
EA BenefitsEA Benefits
EA Benefits
 
David Chan Profile And Experience
David Chan Profile And ExperienceDavid Chan Profile And Experience
David Chan Profile And Experience
 
Exploiting Tools for Faster, More Acceptable Process Improvement Initiatives
Exploiting Tools for Faster, More Acceptable Process Improvement InitiativesExploiting Tools for Faster, More Acceptable Process Improvement Initiatives
Exploiting Tools for Faster, More Acceptable Process Improvement Initiatives
 
Safety in special environments - solutions developed by swiss IT-Factory
Safety in special environments - solutions developed by swiss IT-FactorySafety in special environments - solutions developed by swiss IT-Factory
Safety in special environments - solutions developed by swiss IT-Factory
 
G2 It Services Overview 09.07.01
G2 It Services Overview 09.07.01G2 It Services Overview 09.07.01
G2 It Services Overview 09.07.01
 
MOF 4 Overviewv - ITSM Academy Webinar
MOF 4 Overviewv - ITSM Academy WebinarMOF 4 Overviewv - ITSM Academy Webinar
MOF 4 Overviewv - ITSM Academy Webinar
 
Att consulting external deck
Att consulting external deckAtt consulting external deck
Att consulting external deck
 
Tml Deployment Strategy Overview V 1
Tml Deployment Strategy Overview V 1Tml Deployment Strategy Overview V 1
Tml Deployment Strategy Overview V 1
 
Enterprise Applications
Enterprise ApplicationsEnterprise Applications
Enterprise Applications
 
SP_BTPM
SP_BTPMSP_BTPM
SP_BTPM
 
Maximizing EA Impact: Using Business Architecture to Achieve Alignment
Maximizing EA Impact: Using Business Architecture to Achieve AlignmentMaximizing EA Impact: Using Business Architecture to Achieve Alignment
Maximizing EA Impact: Using Business Architecture to Achieve Alignment
 
Methodology
MethodologyMethodology
Methodology
 
Infusing EPM in people and process
Infusing EPM in people and processInfusing EPM in people and process
Infusing EPM in people and process
 
ISSUE & WIKI based Integration of Project Management
ISSUE & WIKI based Integration of Project ManagementISSUE & WIKI based Integration of Project Management
ISSUE & WIKI based Integration of Project Management
 

Recently uploaded

The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxmbikashkanyari
 
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort ServiceCall US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Servicecallgirls2057
 
Innovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfInnovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfrichard876048
 
Investment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy CheruiyotInvestment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy Cheruiyotictsugar
 
Kenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby AfricaKenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby Africaictsugar
 
Guide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDFGuide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDFChandresh Chudasama
 
PSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationPSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationAnamaria Contreras
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Kirill Klimov
 
MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?Olivia Kresic
 
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607dollysharma2066
 
8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCRashishs7044
 
Darshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfDarshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfShashank Mehta
 
8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCR8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCRashishs7044
 
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!Doge Mining Website
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCRashishs7044
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCRashishs7044
 
Marketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent ChirchirMarketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent Chirchirictsugar
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Seta Wicaksana
 
Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy Verified Accounts
 

Recently uploaded (20)

The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
 
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort ServiceCall US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
 
Innovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfInnovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdf
 
Investment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy CheruiyotInvestment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy Cheruiyot
 
Kenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby AfricaKenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby Africa
 
Guide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDFGuide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDF
 
PSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationPSCC - Capability Statement Presentation
PSCC - Capability Statement Presentation
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024
 
Call Us ➥9319373153▻Call Girls In North Goa
Call Us ➥9319373153▻Call Girls In North GoaCall Us ➥9319373153▻Call Girls In North Goa
Call Us ➥9319373153▻Call Girls In North Goa
 
MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?
 
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
 
8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR
 
Darshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfDarshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdf
 
8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCR8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCR
 
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
 
Marketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent ChirchirMarketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent Chirchir
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...
 
Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail Accounts
 

Planning & controlling design projects

  • 1. Planning & controlling design & engineering projects An overview of The TechnoCentre Puma Way Coventry CV1 2TW United Kingdom Tel: +44(0)24 7623 6929 Fax: +44(0)24 7623 6930 E-mail: enquiries@adeptmanagement.com URL: www.adeptmanagement.com © Adept Management Ltd, 2009
  • 2. Adept Management Design & Bid Management Interim Design Managers Strategic Planning & Monitoring ADePT Design Process & Procedure Development Services Management Integrated Design Planning Process Control Design Team Performance Reporting ADePT Design Software Suite ADePT Design Builder ADePT Design Manager Software Training © Adept Management Ltd, 2009
  • 3. Characteristics of Design o Iterative o Driven by information o Highly complex o Not well understood o Broken into sub-problems o Involving many people o Undertaken in stages © Adept Management Ltd, 2009
  • 4. Poorly Managed Engineering - The Effect 2008 Construction Performance o Fact – design / engineering projects overspend • 35% of design commissions overspend o Fact - design / engineering projects over-run • 42% of design commissions are late o Severe knock on effects in construction • 52% of construction projects overspend • 42% of construction work is late Source: Office for National Statistics’ Construction Statistics Annual, 2008 © Adept Management Ltd, 2009
  • 5. Overview of the methodology © Adept Management Ltd, 2009
  • 6. Current & Recent Implementations of ADePT © Adept Management Ltd, 2009
  • 7. ADePT - Benefits Identified o Identification and removal of “turbulence” o Greater certainty of design co-ordination o Ability to better prioritise design work o Focus on task completion o Effective integration of sub-contractor design o Better change management o Improved team collaboration o Self-policing design team o Design fee validation © Adept Management Ltd, 2009
  • 8. Generating an Integrated Design Plan © Adept Management Ltd, 2009
  • 9. Overview of the methodology © Adept Management Ltd, 2009
  • 10. A Typical Design Processes © Adept Management Ltd, 2009
  • 11. A Typical Design Processes © Adept Management Ltd, 2009
  • 12. A Typical Design Processes External Constraints Deliverable External Constraints Deliverable External Constraints External Constraints Deliverable Deliverable. Deliverable Deliverable External Constraints © Adept Management Ltd, 2009
  • 13. Taking a Hierarchical View © Adept Management Ltd, 2009
  • 14. Taking a Hierarchical View © Adept Management Ltd, 2009
  • 15. Taking a Hierarchical View © Adept Management Ltd, 2009
  • 16. Information exchanges © Adept Management Ltd, 2009
  • 17. Information exchanges Activity properties © Adept Management Ltd, 2009
  • 18. Information exchanges Information requirements Activity properties Information outputs © Adept Management Ltd, 2009
  • 19. Information exchanges Predecessor activities Information requirements Activity properties Information outputs Successor activities © Adept Management Ltd, 2009
  • 20. Setting up a matrix of the design process 1. List design activities in the matrix rows in any arbitrary order, and repeat the list across the columns of the matrix. © Adept Management Ltd, 2009
  • 21. Representing dependencies 2. Mark the matrix to indicate where the activity in the row depends on the activity in the column (e.g. requires information produced by, or requires a decision made from, the activity in the column). 3. Classify the dependencies the show the strength of the requirement: A = vital (should have); B = important (would like to have); or C = nice to have. © Adept Management Ltd, 2009
  • 22. Identifying design assumptions Design process sequence 4. Assume the activities are to be undertaken in the order shown and identify any assumptions to be made. For example: activity 3 depends on activities 1, 2, 4 & 13. In the order shown activities 1 & 2 have been undertaken but 4 & 13 have not. So, to undertake activity 3 assumptions about the outputs from 4 & 13 must be made. © Adept Management Ltd, 2009
  • 23. Identifying iteration in the design process Dependency classification 5. Identify all assumptions and scale of iteration in the design process. For example: activity 3 can only be undertaken if an assumption is made about = nice to have A = vital; B = important; C the output from activity 13 and activity 13 itself requires assumptions to be made about the outputs from 15, 16 & 19. So, only when activity 19 has been undertaken can all assumptions be checked and any rework be undertaken. Therefore all activities from 3 to 19 are in an iterative rework loop. © Adept Management Ltd, 2009
  • 24. Optimizing the design sequence 6. Optimize the sequence of the activities to minimize the number of assumptions which need to be made and ensure that assumptions which cannot be made with a high level of confidence (classified A & B) are included within iterative rework loops whilst assumptions which can be made with confidence (C) are not. © Adept Management Ltd, 2009
  • 25. Breaking down iterative rework loops 7. If necessary (i.e. if the scale of iteration is greater than can be managed in the time available) identify assumptions which can reduce the scale of iteration further if made in such a way that the designers have confidence in them e.g. by over-estimating structural loadings or fixing a typical interface detail. © Adept Management Ltd, 2009
  • 26. Re-optimizing the design sequence 8. Re-optimize the sequence of the activities and record any new assumptions which are now not included in iterative rework loops. © Adept Management Ltd, 2009
  • 27. In practice: clusters represent systems Detailed Locker Room Co-ordination Sub-structure Co-ordination Ceiling Voids & RCP Co-ordination Envelope / Structure Interface © Adept Management Ltd, 2009
  • 28. A view of all clusters / systems © Adept Management Ltd, 2009
  • 29. Create the Programme © Adept Management Ltd, 2009
  • 30. Co-ordination loops identified in ADePT and shown in the design programme © Adept Management Ltd, 2009
  • 31. Variance: construction vs. design dates Target Tender Procurement Packages Date -100 -80 -60 -40 -20 0 20 40 60 80 100 Bicycle Enclosures 13/07/2009 Vehicle Barriers 13/07/2009 Soft Landscaping 19/01/2009 Internal Signage 06/04/2009 Floor Screed 09/02/2009 External Signage 23/03/2009 Decorations 06/04/2009 External Render 05/01/2009 Floor & Wall Tiling 23/03/2009 Soft Flooring 23/03/2009 Lifts 09/02/2009 Internal Glazed Screening 10/11/2008 FF&E inc. White Goods 02/03/2009 Catering / Kitchen Equipment 15/12/2008 Small Kitchen Fitout 16/02/2009 Fixed Furniture inc. Reception Desk 03/11/2008 Security Fencing 06/10/2008 Floor Painting / Epoxy Flooring 19/01/2009 Hard Landscaping 04/08/2008 Internal Joinery 15/12/2008 Plumberwork / Sanitary / Toilet Fitout 17/10/2008 BWIC 24/11/2008 Toilet & Kitchen Pods 17/10/2008 Internal Doors & Ironmongery 17/11/2008 Roof Mansafe 18/08/2008 Brick & Blockwork inc. Windposts 28/07/2008 RainWater System 11/08/2008 Dry Lining / Plasterboard / Fire Stopping 25/08/2008 Flat Roof Coverings 23/06/2008 Raised Flooring 04/08/2008 Roof Cladding / Finishes 26/05/2008 Roller Shutter Doors 02/06/2008 Suspended Ceilings 22/09/2008 Sports Pitches 07/04/2008 Architectural & General Metalwork 18/08/2008 Sliding / Folding Partitions 10/11/2008 Curtain Walling 28/04/2008 Insitu Concrete Frames 30/06/2008 External Windows / Doors / Glazing 19/05/2008 M&E Building Services 11/02/2008 Retaining walls / Structures 05/11/2007 Precast Cladding 17/03/2008 Site enabling / Ground works 05/11/2007 Drainage SW / FW 02/11/2007 Substructures inc. Ground Slabs 14/04/2008 Structural Steelwork / Decking / Purlings 31/03/2008 Precast Concrete: Slabs, Stairs, Column 28/04/2008 External Crib Walling 05/11/2007 © Adept Management Ltd, 2009 External Services External CIS Pit & Ducting 21/10/2007 02/11/2007
  • 32. Imposing Constraints © Adept Management Ltd, 2009
  • 33. Understanding the impact Impact understood and a managed decision can be made to resolve this issue © Adept Management Ltd, 2009
  • 34. Result: aligned construction & design dates Target Tender Procurement Packages Date -100 -80 -60 -40 -20 0 20 40 60 80 100 -100 -80 -60 -40 -20 0 20 Bicycle Enclosures 13/07/2009 Vehicle Barriers 13/07/2009 Soft Landscaping 19/01/2009 Internal Signage 06/04/2009 Floor Screed 09/02/2009 External Signage 23/03/2009 Decorations 06/04/2009 External Render 05/01/2009 Floor & Wall Tiling 23/03/2009 Soft Flooring 23/03/2009 Lifts 09/02/2009 Internal Glazed Screening 10/11/2008 FF&E inc. White Goods 02/03/2009 Catering / Kitchen Equipment 15/12/2008 Small Kitchen Fitout 16/02/2009 Fixed Furniture inc. Reception Desk 03/11/2008 Security Fencing 06/10/2008 Floor Painting / Epoxy Flooring 19/01/2009 Hard Landscaping 04/08/2008 Internal Joinery 15/12/2008 Plumberwork / Sanitary / Toilet Fitout 17/10/2008 BWIC 24/11/2008 Toilet & Kitchen Pods 17/10/2008 Internal Doors & Ironmongery 17/11/2008 Roof Mansafe 18/08/2008 Brick & Blockwork inc. Windposts 28/07/2008 RainWater System 11/08/2008 Dry Lining / Plasterboard / Fire Stopping 25/08/2008 Flat Roof Coverings 23/06/2008 Raised Flooring 04/08/2008 Roof Cladding / Finishes 26/05/2008 Roller Shutter Doors 02/06/2008 Suspended Ceilings 22/09/2008 Sports Pitches 07/04/2008 Architectural & General Metalwork 18/08/2008 Sliding / Folding Partitions 10/11/2008 Curtain Walling 28/04/2008 Insitu Concrete Frames 30/06/2008 External Windows / Doors / Glazing 19/05/2008 M&E Building Services 11/02/2008 Retaining walls / Structures 05/11/2007 Precast Cladding 17/03/2008 Site enabling / Ground works 05/11/2007 Drainage SW / FW 02/11/2007 Substructures inc. Ground Slabs 14/04/2008 Structural Steelwork / Decking / Purlings 31/03/2008 Precast Concrete: Slabs, Stairs, Column 28/04/2008 External Crib Walling 05/11/2007 © Adept Management Ltd, 2009 External Services External CIS Pit & Ducting 21/10/2007 02/11/2007
  • 35. Key decisions required to integrate design & procurement © Adept Management Ltd, 2009
  • 36. Programme for one design discipline © Adept Management Ltd, 2009
  • 37. Programme for one project stage © Adept Management Ltd, 2009
  • 38. Controlling a Design Project © Adept Management Ltd, 2009
  • 39. Overview of the methodology © Adept Management Ltd, 2009
  • 40. 80% 70% % P lan Com plete 60% 50% Select tasks to add to the work plan for this period 40% 30% 20% 10% 0% Aug Sep Oct Nov Dec © Adept Management Ltd, 2009
  • 41. 80% 70% % P lan Com plete 60% 50% Task Priorities 40% 30% 20% 10% 0% Aug Sep Oct Nov Dec End of Current Focus Date Period Late Due to be completed Due to be progressed Focus Period © Adept Management Ltd, 2009
  • 42. 80% 70% % P lan Com plete 60% 50% Task Priorities 40% 30% 20% 10% 0% Aug Sep Oct Nov Dec End of End of Current Focus Look-Ahead Date Period Period Late Due to be completed Due to be progressed Due to be completed in the next period Due to be progressed in the next period Look-Ahead Focus Period Period © Adept Management Ltd, 2009
  • 43. 80% 70% % P lan Com plete 60% 50% Select tasks to add to the work plan for this period 40% 30% 20% 10% 0% Aug Sep Oct Nov Dec Due to be completed Due to be progressed © Adept Management Ltd, 2009
  • 44. 80% 70% % P lan Com plete 60% 50% Select tasks to add to the work plan for this period 40% 30% 20% 10% 0% Aug Sep Oct Nov Dec Due to be completed Due to be progressed Due to be completed in the next period © Adept Management Ltd, 2009
  • 45. 80% 70% % P lan Com plete 60% 50% Publish the work plan to the design team 40% 30% 20% 10% 0% Aug Sep Oct Nov Dec © Adept Management Ltd, 2009
  • 46. 80% 70% % P lan Com plete 60% 50% Output for Designers to Complete 40% 30% 20% 10% 0% Aug Sep Oct Nov Dec © Adept Management Ltd, 2009
  • 47. 80% 70% % P lan Com plete 60% 50% Manage any constraints identified by the team 40% 30% 20% 10% 0% Aug Sep Oct Nov Dec © Adept Management Ltd, 2009
  • 48. 80% 70% % P lan Com plete 60% 50% Validate the progress given by the design team 40% 30% 20% 10% 0% Aug Sep Oct Nov Dec © Adept Management Ltd, 2009
  • 49. 80% 70% % P lan Com plete Write progress back to the design programme 60% 50% 40% 30% so that it can be rescheduled 20% 10% 0% Aug Sep Oct Nov Dec © Adept Management Ltd, 2009
  • 50. 80% 70% % P lan Com plete 60% 50% Workflow process in practice 40% 30% 20% 10% 0% Aug Sep Oct Nov Dec Start of Focus period 2. Publish 1. Generate Workplan to Workplan design team Reschedule programme 4. Update 3. Update Workplan with programme & team’s progress End of Focus period archive Workplan & constraints © Adept Management Ltd, 2009
  • 51. 80% 70% Update the programme and report % P lan Com plete 60% 50% 40% 30% performance 20% 10% 0% Aug Sep Oct Nov Dec © Adept Management Ltd, 2009
  • 52. 80% 70% % P lan Com plete 60% 50% Understand and report trends 40% 30% 20% 10% 0% Aug Sep Oct Nov Dec © Adept Management Ltd, 2009
  • 53. 80% 70% % P lan Com plete Report overall progress: 60% 50% 40% 30% activities, information or documents 20% 10% 0% Aug Sep Oct Nov Dec • Activities completed • Information produced • Documentation issued © Adept Management Ltd, 2009
  • 54. 80% 70% % P lan Com plete 60% 50% Overall Reporting 40% 30% 20% 10% 0% Aug Sep Oct Nov Dec o What did we plan to achieve? o What did we complete? o What did we fail? Looking Back o Why did we fail? o Fix problem and re-plan! o What do we need to start / complete the activity in the future? o What could stop us? Looking Forward o How can we mitigate the risks? o Ensure that we plan to deliver? © Adept Management Ltd, 2009
  • 55. Managing change (emerging need for re-design) © Adept Management Ltd, 2009
  • 56. Understanding the impact Impact understood and an evidence-based decision © Adept Management Ltd, 2009 made to resolve this by all parties
  • 57. Planning & controlling design & engineering projects An overview of The TechnoCentre Puma Way Coventry CV1 2TW United Kingdom Tel: +44(0)24 7623 6929 Fax: +44(0)24 7623 6930 E-mail: enquiries@adeptmanagement.com URL: www.adeptmanagement.com © Adept Management Ltd, 2009