“Design and Build under the
FIDIC Contracts”
Presentation By-
Ranjit V Patil
M.Tech (Civil- Construction Management)
Rajarambapu Institute of Technology,
Islampur, Maharashtra.
Mob.No. 9503361010
 FIDIC?????
 It is a French short form of…
“Federation Internationale Des Ingenieurs – Counseils”
 In English it is referred as
“ International Federation of Consulting Engineers”
 FIDIC : “ International” Form of contract.
 Used by funders such as World Bank etc.
Introduction
 Origin:-
Founded in 1913 by three national associations of consulting
engineers within Europe.
 FIDIC currently has 99 Members Associations & Associates.
 CONSULTING ENGINEERS ASSOCIATION OF INDIA is the
member from India.
 FIDIC Vision:-
Enabling the development of a sustainable world as the recognised
global voice for the consulting engineering industry.
 FIDIC Mission :-
To work closely with our stakeholders to improve the
business climate in which we operate and enable our
members to contribute to making the world a better
place to live in, now and in the future.
 FIDIC Values :
1. Quality
2. Integrity
3. Sustainability
FIDIC LOGO
 What is Design and Built???
 It is procurement method which has been in use for long time.
 Before the emergence of architecture as profession clients
used to procure building by process of design and built.
 In Nineteenth Century-
It was the separation of responsibility for fabrication
from responsibility for design that led to the emergence
of so called ‘traditional general contracting’.
Design and Built
The Role
Employer
Contractor
Designers
Other Consultant
Quantity
Surveyor
Subcontractor Subcontractor
Traditional
Arrangement
The Role
Employer
Contractor
Employer’s
Representative
Designer and
Other
Consultants
Subcontractor Subcontractor
Design and Built
Arrangement
 Price Certainty
 Single Point Responsibility
 Good For “Non- Expert” clients
 Contractor’s Expertise
 Quicker Build Time
Advantages of Design and Built
 Contractor designs and builds to price.
 Employer’s reduced control of design and quality.
 Employer’s reduced control of change cost
 Not Good for complex projects
 Longer tender period
 Expensive to contractor to prepare tender.
Disadvantages of using Design and
Built
 The better the Employer’s requirements, the better the completed
project.
 Consider first of all what are the Employer’s needs??
 What???
What does he need???
 When?????
When does he need it????
 How?????
How much will/can he pay?????
 Which????
Which is the best contractual method to meet these needs???
 Is the Design and Built the Best method?? Weigh Up the advantages
and disadvantages.
The Employer’s Requirements
 Procurement refers to: the process of obtaining goods and services from another
for some consideration.
 The choice of procurement strategy identifies how the project is structured
 Design and coordination consideration have led to the development of following
procurement methods:
1. Traditional Procurement
2. Design and Build
3. Management Procurement
Procurement methods
1. General Provisions
2. The Employer
3. The Engineers (The employers
administration- EPC)
4. The Contractor
5. Nominated subcontractor
(Design- P & DB & EPC)
6. Staff and Labour
7. Plant, materials and workmanship
8. Commencement, delays and
suspension
9. Tests on completion
10. Employer’s Taking Over
11. Defects Liability
12. Measurement and evaluation
(Tests after completion- P & DB
& EPC)
13. Variations and adjustments
14. Contracts price and payments
15. Termination by Employer
16. Suspension and Termination by
Contractor
17. Risk and Responsibility
18. Insurance
19. Force Majeure
20. Claims, Disputes and Arbitration
Details of The Books for the Major Works:
If we take the conditions of contract for construction as an example:
 The employer should appoint an appropriately experienced and qualified
agent and necessary professional consultants.
 Design responsibility should be clearly defined.
 A standard form of contract should be used.
 The employer’s requirements should be clearly formulated by the time
tenders are invited and set out in the Employer's requirements upon which
the contractor’s proposals will depend.
 Care and attention should be paid to the procedure for the selection of
contractors to be invited to tender.
Preparing the Tenders:
 Information contained in the preliminary enquiry to prospective tenderers
should be as full and as clear as possible.
 Conditions of tendering should be clear so that all tenders are submitted on
the same basis.
 Adequate time should be given to selected tenderers to prepare their
proposals.
 Tenders should be assessed and adjusted in accordance with the terms of
the formal invitation to tender.
Preparing the Design and Build
Tenders
1. Employer’s requirements
2. Contractor’s proposals
3. Contract sum analysis
Major Documents In D&B Contracts:
 The purpose
 The scope
 The design
 Other technical criteria
Employer’s Requirements
1. Relatively small Value, short construction time or involving simple or
repetitive work
2. Large or more complex project
3. Contractor going to Most of design
4. For Process and Power Plant
5. The Infrastructure Project
6. The Privately Financed Project
Factors in deciding which form of
FIDIC form of Contract
1. Part I: Orange Book ( D&B and Turnkey Contracts)-
1995
2. Part II: The Yellow Book (Plant and D&B Contract)-
1999
Overview of FIDIC Conditions of
Contract:
 Both the book consists of 20 clauses in each.
 Every clause consist of number of sub clauses.
 Each clause is important to resolve the problems in contract.
 Clauses are grouped as per the their type of work and
requirement
1. The Contract
2. The Employer
3. The Employer’s representative
4. The Contractor
5. Design
6. Staff and labour
7. Plant, material and workmanship
8. Commencement, delays and
suspension
9. Test on completion
10. Employers taking over
11. Test after completion
12. Defects Liability
13. Contract price and payment
14. Variations
15. Default of contractor
16. Default of Employer
17. Risks and Responsibility
18. Insurance
19. Force Majeure
20. Claims, Disputes and Arbitrations
Clauses in Orange Book:
1. General provision
2. he Employer
3. The Engineer
4. The Contractor
5. Design
6. Staff and Labour
7. Plant, Material and Workmanship
8. Commencement, Delays and
Suspension
9. Tests on Completion
10. Employer's Taking Over
11. Defects Liability
12. Testes after Completion
13. Variations and Adjustments
14. Contract price and Payments
15. Termination by Employer
16. Suspension and Termination by
Contractor
17. Risks and Responsibility
18. Insurance
19. Force Majeure
20. Claims, Disputes and Arbitration
Clauses in Yellow Book
 A contract has been awarded to build a new project with
associated services and external works.
 Contract Details are as follow:
 Employer: ABC Development Co.
 Contractor: Buildit Construction Co.
 Commencement Date: 15January 2014
 Time for Completion: 104 Weeks
 Form of Contract: FIDIC 1995 Conditions of Contract for Design-
Build and Turnkey (Orange Book)
Case Study
Inconsistency between the Employer’s requirements and the
Contractor’s Proposal becomes apparent part of the way through
the works.
Which takes precedence? How is this dealt with under the
contract?
 Answer:
Clause 1.6 lists the priority of documents, the Employer’s
requirements being third in the list, the contractor’s proposal being
eighth; therefore Employer’s requirements take precedence.
Situation:
 Which of the contractor’s claim clauses allow the contractor to
claim cost and which allow cost plus reasonable profit?
Answer:
Clauses giving the contractor the right to recover Cost:
 Clause 4.11- Unforeseeable physical conditions
 Clause 4.24- Fossils
 Clause 8.8- Suspension
 Clause 13.16- Changes in legislation
 Clause 17.4- Employer’s Risks
 Clause 19.5- Force Majeure
Situation:
Clauses giving the Contractor the right to recover the cost plus
reasonable profit:
 Clause 2.2- Employers failure give access
 Clause 11.4- Employer not permitting access for testing
 Clause 12.8- Contractor instructed to search
 Clause 16.1- Default by Employer
 Reasonable profit is whatever profit the parties agree between
themselves as “reasonable”.
Cont’d
 The Employer’s representative has issued a verbal instruction to carry out
additional work
I. Does the contractor have to comply with the instruction?
II. How does the contract deal with verbal instruction?
Answer:
I. No, under clause 1.8, wherever provision is made for the giving of notice,
instruction, etc. unless otherwise specified such communication shall be in writing.
II. The Contract does not provide for the giving of verbal instructions (Note
that most other contracts provide for the contractor issue a written confirmation of
verbal instruction, which if not rejected, becomes an instruction)
Situation
 ABC Development Co. is late in paying a certified amount due to
Buildit construction.
What are Buildit Construction’s rights regarding this situation?
Answer:
Under clause 13.8, if payment is delayed, the contractor is entitled to
receive financing changes compounded monthly on the amount unpaid during
the delay. Unless part II states otherwise, this is 3% above the discount rate of
the central bank in the country of the currency of the payment. The contractor
is not required to give notice in order to receive this payment.
Situation
Buildit Construction wishes to be paid for the precast concrete
flooring units held at their subcontractor’s works 20km from the
site awaiting delivery to six weeks later.
Answer:
FIDIC 1995 conditions of contract for Design-Build and
Turnkey (Orange Book) does not provide for payment for materials
held off site.
Situation
Thank You

More Related Content

What's hot

Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)
Fakhar-un -Nisa
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
AYM1979
 
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
Arvind Solanki
 

What's hot (20)

Fidic comparison red yellow - silver book
Fidic comparison red   yellow - silver bookFidic comparison red   yellow - silver book
Fidic comparison red yellow - silver book
 
Extension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationExtension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentation
 
Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)
 
Lecture 4 - selection of contract forms
Lecture 4 - selection of contract formsLecture 4 - selection of contract forms
Lecture 4 - selection of contract forms
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time Management
 
Assignment - FIDIC Contract
Assignment - FIDIC ContractAssignment - FIDIC Contract
Assignment - FIDIC Contract
 
Tendering process, Bid Evaluation & Award Process
Tendering process, Bid Evaluation & Award ProcessTendering process, Bid Evaluation & Award Process
Tendering process, Bid Evaluation & Award Process
 
TENDER DOCUMENT
TENDER DOCUMENTTENDER DOCUMENT
TENDER DOCUMENT
 
Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)
 
Types of contract
Types of contractTypes of contract
Types of contract
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closure
 
# FIDIC Payment Flow Charts # By SN Panigrahi
# FIDIC Payment Flow Charts # By SN Panigrahi# FIDIC Payment Flow Charts # By SN Panigrahi
# FIDIC Payment Flow Charts # By SN Panigrahi
 
An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...
An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...
An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...
 
A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006
 
Tendering presenation
Tendering presenationTendering presenation
Tendering presenation
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
 
Construction tender process
Construction tender processConstruction tender process
Construction tender process
 
Classification of contracts
Classification of contractsClassification of contracts
Classification of contracts
 
Construction Claims
Construction ClaimsConstruction Claims
Construction Claims
 
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
 

Similar to Fidic

Pp 1-report-complete
Pp 1-report-completePp 1-report-complete
Pp 1-report-complete
Yong Sy
 
Construction Contracts Questions and Answers.pdf
Construction Contracts Questions and Answers.pdfConstruction Contracts Questions and Answers.pdf
Construction Contracts Questions and Answers.pdf
EyobMiteku
 
Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017
DarrenTofu
 

Similar to Fidic (20)

Ak contract management
Ak contract managementAk contract management
Ak contract management
 
Contracts PPT.pptx
Contracts PPT.pptxContracts PPT.pptx
Contracts PPT.pptx
 
Kandil_Sameh_AR50123
Kandil_Sameh_AR50123Kandil_Sameh_AR50123
Kandil_Sameh_AR50123
 
FIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshopFIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshop
 
05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION
 
AN EXAMPLE OF HOW PREPARING A CLAIM STEP BY STEP.pdf
AN EXAMPLE OF HOW PREPARING A CLAIM STEP BY STEP.pdfAN EXAMPLE OF HOW PREPARING A CLAIM STEP BY STEP.pdf
AN EXAMPLE OF HOW PREPARING A CLAIM STEP BY STEP.pdf
 
Tendering documentation
Tendering documentationTendering documentation
Tendering documentation
 
Cl report final
Cl report finalCl report final
Cl report final
 
Pp 1-report-complete
Pp 1-report-completePp 1-report-complete
Pp 1-report-complete
 
Kandil_Sameh_AR50360
Kandil_Sameh_AR50360Kandil_Sameh_AR50360
Kandil_Sameh_AR50360
 
Construction Contracts Questions and Answers.pdf
Construction Contracts Questions and Answers.pdfConstruction Contracts Questions and Answers.pdf
Construction Contracts Questions and Answers.pdf
 
contract_management.ppt
contract_management.pptcontract_management.ppt
contract_management.ppt
 
Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...
Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...
Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...
 
Tender & Tender Notice
Tender & Tender NoticeTender & Tender Notice
Tender & Tender Notice
 
Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017
 
Construction Futures Wales - NEC Contracts Overview Workshop
Construction Futures Wales  - NEC Contracts Overview WorkshopConstruction Futures Wales  - NEC Contracts Overview Workshop
Construction Futures Wales - NEC Contracts Overview Workshop
 
Common Mistakes Attorneys [and Their Clients] Make Drafting and Negotating Co...
Common Mistakes Attorneys [and Their Clients] Make Drafting and Negotating Co...Common Mistakes Attorneys [and Their Clients] Make Drafting and Negotating Co...
Common Mistakes Attorneys [and Their Clients] Make Drafting and Negotating Co...
 
Professional Practice 1 Proposal Report
Professional Practice 1 Proposal ReportProfessional Practice 1 Proposal Report
Professional Practice 1 Proposal Report
 
dokumen.tips_fidic-power-point-presentation.pdf
dokumen.tips_fidic-power-point-presentation.pdfdokumen.tips_fidic-power-point-presentation.pdf
dokumen.tips_fidic-power-point-presentation.pdf
 
Arunkumar_Proc & Contr_25.12.2014
Arunkumar_Proc & Contr_25.12.2014Arunkumar_Proc & Contr_25.12.2014
Arunkumar_Proc & Contr_25.12.2014
 

Recently uploaded

Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Dr.Costas Sachpazis
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
rknatarajan
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
ankushspencer015
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
dharasingh5698
 

Recently uploaded (20)

Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Vivazz, Mieres Social Housing Design Spain
Vivazz, Mieres Social Housing Design SpainVivazz, Mieres Social Housing Design Spain
Vivazz, Mieres Social Housing Design Spain
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineering
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELLPVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
UNIT-IFLUID PROPERTIES & FLOW CHARACTERISTICS
UNIT-IFLUID PROPERTIES & FLOW CHARACTERISTICSUNIT-IFLUID PROPERTIES & FLOW CHARACTERISTICS
UNIT-IFLUID PROPERTIES & FLOW CHARACTERISTICS
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 

Fidic

  • 1. “Design and Build under the FIDIC Contracts” Presentation By- Ranjit V Patil M.Tech (Civil- Construction Management) Rajarambapu Institute of Technology, Islampur, Maharashtra. Mob.No. 9503361010
  • 2.  FIDIC?????  It is a French short form of… “Federation Internationale Des Ingenieurs – Counseils”  In English it is referred as “ International Federation of Consulting Engineers”  FIDIC : “ International” Form of contract.  Used by funders such as World Bank etc. Introduction
  • 3.  Origin:- Founded in 1913 by three national associations of consulting engineers within Europe.  FIDIC currently has 99 Members Associations & Associates.  CONSULTING ENGINEERS ASSOCIATION OF INDIA is the member from India.
  • 4.  FIDIC Vision:- Enabling the development of a sustainable world as the recognised global voice for the consulting engineering industry.  FIDIC Mission :- To work closely with our stakeholders to improve the business climate in which we operate and enable our members to contribute to making the world a better place to live in, now and in the future.  FIDIC Values : 1. Quality 2. Integrity 3. Sustainability
  • 6.  What is Design and Built???  It is procurement method which has been in use for long time.  Before the emergence of architecture as profession clients used to procure building by process of design and built.  In Nineteenth Century- It was the separation of responsibility for fabrication from responsibility for design that led to the emergence of so called ‘traditional general contracting’. Design and Built
  • 9.  Price Certainty  Single Point Responsibility  Good For “Non- Expert” clients  Contractor’s Expertise  Quicker Build Time Advantages of Design and Built
  • 10.  Contractor designs and builds to price.  Employer’s reduced control of design and quality.  Employer’s reduced control of change cost  Not Good for complex projects  Longer tender period  Expensive to contractor to prepare tender. Disadvantages of using Design and Built
  • 11.  The better the Employer’s requirements, the better the completed project.  Consider first of all what are the Employer’s needs??  What??? What does he need???  When????? When does he need it????  How????? How much will/can he pay?????  Which???? Which is the best contractual method to meet these needs???  Is the Design and Built the Best method?? Weigh Up the advantages and disadvantages. The Employer’s Requirements
  • 12.  Procurement refers to: the process of obtaining goods and services from another for some consideration.  The choice of procurement strategy identifies how the project is structured  Design and coordination consideration have led to the development of following procurement methods: 1. Traditional Procurement 2. Design and Build 3. Management Procurement Procurement methods
  • 13. 1. General Provisions 2. The Employer 3. The Engineers (The employers administration- EPC) 4. The Contractor 5. Nominated subcontractor (Design- P & DB & EPC) 6. Staff and Labour 7. Plant, materials and workmanship 8. Commencement, delays and suspension 9. Tests on completion 10. Employer’s Taking Over 11. Defects Liability 12. Measurement and evaluation (Tests after completion- P & DB & EPC) 13. Variations and adjustments 14. Contracts price and payments 15. Termination by Employer 16. Suspension and Termination by Contractor 17. Risk and Responsibility 18. Insurance 19. Force Majeure 20. Claims, Disputes and Arbitration Details of The Books for the Major Works: If we take the conditions of contract for construction as an example:
  • 14.  The employer should appoint an appropriately experienced and qualified agent and necessary professional consultants.  Design responsibility should be clearly defined.  A standard form of contract should be used.  The employer’s requirements should be clearly formulated by the time tenders are invited and set out in the Employer's requirements upon which the contractor’s proposals will depend.  Care and attention should be paid to the procedure for the selection of contractors to be invited to tender. Preparing the Tenders:
  • 15.  Information contained in the preliminary enquiry to prospective tenderers should be as full and as clear as possible.  Conditions of tendering should be clear so that all tenders are submitted on the same basis.  Adequate time should be given to selected tenderers to prepare their proposals.  Tenders should be assessed and adjusted in accordance with the terms of the formal invitation to tender. Preparing the Design and Build Tenders
  • 16. 1. Employer’s requirements 2. Contractor’s proposals 3. Contract sum analysis Major Documents In D&B Contracts:
  • 17.  The purpose  The scope  The design  Other technical criteria Employer’s Requirements
  • 18. 1. Relatively small Value, short construction time or involving simple or repetitive work 2. Large or more complex project 3. Contractor going to Most of design 4. For Process and Power Plant 5. The Infrastructure Project 6. The Privately Financed Project Factors in deciding which form of FIDIC form of Contract
  • 19. 1. Part I: Orange Book ( D&B and Turnkey Contracts)- 1995 2. Part II: The Yellow Book (Plant and D&B Contract)- 1999 Overview of FIDIC Conditions of Contract:
  • 20.  Both the book consists of 20 clauses in each.  Every clause consist of number of sub clauses.  Each clause is important to resolve the problems in contract.  Clauses are grouped as per the their type of work and requirement
  • 21. 1. The Contract 2. The Employer 3. The Employer’s representative 4. The Contractor 5. Design 6. Staff and labour 7. Plant, material and workmanship 8. Commencement, delays and suspension 9. Test on completion 10. Employers taking over 11. Test after completion 12. Defects Liability 13. Contract price and payment 14. Variations 15. Default of contractor 16. Default of Employer 17. Risks and Responsibility 18. Insurance 19. Force Majeure 20. Claims, Disputes and Arbitrations Clauses in Orange Book:
  • 22. 1. General provision 2. he Employer 3. The Engineer 4. The Contractor 5. Design 6. Staff and Labour 7. Plant, Material and Workmanship 8. Commencement, Delays and Suspension 9. Tests on Completion 10. Employer's Taking Over 11. Defects Liability 12. Testes after Completion 13. Variations and Adjustments 14. Contract price and Payments 15. Termination by Employer 16. Suspension and Termination by Contractor 17. Risks and Responsibility 18. Insurance 19. Force Majeure 20. Claims, Disputes and Arbitration Clauses in Yellow Book
  • 23.  A contract has been awarded to build a new project with associated services and external works.  Contract Details are as follow:  Employer: ABC Development Co.  Contractor: Buildit Construction Co.  Commencement Date: 15January 2014  Time for Completion: 104 Weeks  Form of Contract: FIDIC 1995 Conditions of Contract for Design- Build and Turnkey (Orange Book) Case Study
  • 24. Inconsistency between the Employer’s requirements and the Contractor’s Proposal becomes apparent part of the way through the works. Which takes precedence? How is this dealt with under the contract?  Answer: Clause 1.6 lists the priority of documents, the Employer’s requirements being third in the list, the contractor’s proposal being eighth; therefore Employer’s requirements take precedence. Situation:
  • 25.  Which of the contractor’s claim clauses allow the contractor to claim cost and which allow cost plus reasonable profit? Answer: Clauses giving the contractor the right to recover Cost:  Clause 4.11- Unforeseeable physical conditions  Clause 4.24- Fossils  Clause 8.8- Suspension  Clause 13.16- Changes in legislation  Clause 17.4- Employer’s Risks  Clause 19.5- Force Majeure Situation:
  • 26. Clauses giving the Contractor the right to recover the cost plus reasonable profit:  Clause 2.2- Employers failure give access  Clause 11.4- Employer not permitting access for testing  Clause 12.8- Contractor instructed to search  Clause 16.1- Default by Employer  Reasonable profit is whatever profit the parties agree between themselves as “reasonable”. Cont’d
  • 27.  The Employer’s representative has issued a verbal instruction to carry out additional work I. Does the contractor have to comply with the instruction? II. How does the contract deal with verbal instruction? Answer: I. No, under clause 1.8, wherever provision is made for the giving of notice, instruction, etc. unless otherwise specified such communication shall be in writing. II. The Contract does not provide for the giving of verbal instructions (Note that most other contracts provide for the contractor issue a written confirmation of verbal instruction, which if not rejected, becomes an instruction) Situation
  • 28.  ABC Development Co. is late in paying a certified amount due to Buildit construction. What are Buildit Construction’s rights regarding this situation? Answer: Under clause 13.8, if payment is delayed, the contractor is entitled to receive financing changes compounded monthly on the amount unpaid during the delay. Unless part II states otherwise, this is 3% above the discount rate of the central bank in the country of the currency of the payment. The contractor is not required to give notice in order to receive this payment. Situation
  • 29. Buildit Construction wishes to be paid for the precast concrete flooring units held at their subcontractor’s works 20km from the site awaiting delivery to six weeks later. Answer: FIDIC 1995 conditions of contract for Design-Build and Turnkey (Orange Book) does not provide for payment for materials held off site. Situation