SlideShare a Scribd company logo
1 of 33
A
SUMMER TRAINING PRESENTATION
ON
UTTAR PRADESH POWER TRANSMISSION
CORPORATION LIMITED (UPPTCL)
A SEMINAR IN PARTIALLY FULFILLMENT OF THE REQUIREMENT FOR THE AWARD OF THE
DEGREE OF
BACHELOR OF TECHNOLOGY
IN
ELECTRICAL ENGINEERING
FROM
BABU BANARASI DAS NATIONAL INSTITUTE OF TECHNOLOGY & MANAGEMENT (LUCKNOW)
AFFILIATED WITH APJ AKTU
SUBMITTED BY
RISHASBH DEV SINGH
SUBMITTED TO
PROFF. MRS KALPNA KUREEL
CONTENTS
o INTRODUCTION
o ABOUT 220 KVA SUBSTATION
o COMPONENT OF SUBSTATION
o OVERVIEW & SINGLE LINE DIAGRAM OF SUBSTATION
o PROTECTION OF SUBSTATION
o MAINTENANCE OF SUBSTATION
o CONCLUSION
INTRODUCTION
Uttar Pradesh Power Transmission Corporation Limited
(UPPTCL) is the responsible for transmission above 33 KVA within the
Indian state of Uttar Pradesh. Its chairman is Mr. KAMRAN
REZVI(IAS).
In 14 January 2000 UPSEB divided into three part –
• GENERATING
• UPPTCL (TRANSMISSION)
• UPPCL (DISTRIBUTION)
UPPTCL BANDA has three substation is basically contains
three substation. One of 400 kv second is 220 kv & another is 132 kv
substation. 220/132 KVA substation established in 2002.
ABOUT THE SUBSTATION
There are three part of substation –
• CONTROL ROOM
• BATTERY ROOM
• SWITCH YARD
CONTROL ROOM
It contain panel related to controlling of instruments. Basically it
operate manually. It work as shield guard for all substation equipment &
electrical network. These panel are useful to control the flow of electrical
as per the voltage class and detect the faults in transmission line. E.g.
feeder panel, x-mar panel etc.
BATTERY ROOM
The control panels and relays of the sub-station required DC supply.
The sub-station Has Two set of 110 Volt and a set of 48 Volt DC Supply.
The DC supply is made with the help of battery bank reserve normally
kept in a separate room called battery room. The batteries used in this
sub-station are Nickel-Cadmium (NI-Cd) batteries. These batteries re
used due to their advantages like low maintenance, longer life (15-20
years) etc. Each cell is of 2 V and 300 Ah Capacity.
USE OF BATTERY ROOM
Storage battery system is used in emergency situation for the working of
electrical equipment:
• To open and close the switch gear
• For indication and control
• Emergency lighting
• Relay and interlocking equipment
• For working of alarm circuit.
SWITCH YARD
Switch yard has many things which is situate in openly. Switch
yard is combination of Wave trap, LA, CT, PT, Transformers, Bus bar,
Isolator, Insulator, Breakers, Bus coupler, MULSI fire room etc. switch
yard is connected with control room. In switch yard there are many
things connected.
ELEMENT OF SWITCH YARD
• WAVE TRAP
• LIGHTENING ARRESTER (LA)
• CURRENT TRANSFORMER (CT)
• POTENTIAL TRANSFORMER (PT)
• CIRCUIT BREAKER
• RELAY
• ISOLATOR
• TRANSFORMER
• INSULATOR
• CAPACITOR BANK
• CONDOCTOR
WAVE TRAP
Wave trap is an instrument using for tripping of the wave. The
function of this trap is that it traps the unwanted waves. Its function is of
trapping wave. Its shape is like a drum. It is connected to the main
incoming feeder so that it can trap the waves which may be dangerous to
the instruments here in the substation.
LIGHTENING ARRESTER
Lightening arrester is used to discharge surge which come from
cloud. LA protects devises from extra surge. To discharge the switching
and lightening voltage surges to earth. It provides low impedance path
for high frequency and high current supply.
CURRENT TRANSFORMER (CT)
CT is known as brain of substation. It is used for measure current.
CT is connected seriously. It is a step up transformer which is used to
measure the current, by stepping down the voltage level.
CURRENT TRANSFORMER (CT)
In CT the secondary current is proportional to the primary current.
In my substation the CT ratio is used 200:5.5 that shows secondary
current of 5.5A when primary current is 200A.
POTENTIAL TRANSFORMER (PT)
Voltage transformer also called potential transformer are a parallel
connected type of instrument transformer. They have designed to present
negligible load to supply being measured and have an accurate voltage
ratio and phase relation.
POTENTIAL TRANSFORMER (PT)
In my substation the PT ratio is used 400:120 that shows secondary
current of 120V when primary current is 400V.
CIRCUIT BREAEKER
A circuit breaker is an automatically operated electrical switch
designed to protect an electrical circuit from damage caused by over-
current or overload or short circuit. In my substation SF6 & VACCUME
circuit breaker is used
TYPE OF CIRCUIT BREKER
• AIR BLAST CIRCUIT BREKER
• OIL CIRCUIT BERKER
• SF6 CIRCUIT BREKER
• VACCUME CIRCUIT BREKER
TYPES OF CIRCUIT BREAKERS
Oil circuit breakerAir-blast circuit breaker
Sulfur hexafluoride circuit breaker (SF6)Vacuum circuit breakers
OIL CIRCUIT BREAKER
It is designed for 11kv-765kv.
The contacts are immersed in oil bath.
Oil provides cooling by hydrogen created
by arc.
It acts as a good dielectric medium and
quenches the arc.
AIR BLAST CIRCUIT BREAKERS
This operates using high velocity blast of air which quenches the arc.
It consists of blast valve , blast tube & contacts.
Blast valve contains air at high pressure.
Blast tube carries the air at high pressure & opens the moving contact
attached to spring.
There is no carbonization of surface as in VCB.
Air should be kept clean & dry to operate it properly.
SF6 CIRCUIT BREAKERS
 It contains an arc interruption chamber containing SF6 gas.
 In closed position the contacts remain surrounded by SF6 gas at a pressure of 2.8 kg/cm2 .
 During opening high pressure SF6 gas at 14 kg/cm2 from its reservoir flows towards the
chamber by valve mechanism.
 SF6 rapidly absorbs the free electrons in the arc path to form immobile negative ions to build
up high dielectric strength.
 It also cools the arc and extinguishes it.
 After operation the valve is closed by the action of a set of springs.
 Absorbent materials are used to absorb the byproducts and moisture.
VACCUM CIRCUIT BREAKER
It is designed for medium voltage range (3.3-
33kv).
This consists of vacuum of pressure (1*10-6)
inside arc extinction chamber.
The arc burns in metal vapor when the contacts
are disconnected.
At high voltage , it’s rate of dielectric strength
recovery is very high.
Due to vacuum arc extinction is very fast.
The contacts loose metals gradually
due to formation of metal vapors.
RELAY
PROTECTIVE RELAY
Current
Voltage
Insulation
Temperature
Pick up levels
Time
Visual indication
Warning alarm
Remove power
output
input
setting
A relay is an electrically operated switch.
A relay is a sensing device which sense the abnormal condition and
then produce an alarm or open the breaker contact.
RELAY
In my substation used four type relay -
• DISTANCE RELAY
• DIRECTIONAL RELAY
• OVER CURRENT RELAY
• DIFFERENCE RELAY
ISOLATOR
Isolator is used to ensure that an electrical circuit is completely de-
energized for service or maintenance.
TRANSFORMER
The transformer is called the heart of transformer. A transformer is
an electrical device that transfers electrical energy between two or more
circuits through electromagnetic induction. In my substation has four
transformer two 160 MVA transformer and two 40 MVA. Both are step
down transformer. 160 MVA transformer convert 220 to 132 KVA & 40
MVA converts 132 to 33 KVA.
Transformer has three type-
• Auto transformer
• Step up transformer
• Step down transformer
COOLING OF TRANSFORMER
Continuous working of transformer goes to heat. Thus the cooling
of transformer various method are used.
• OIL COOLING
• NATURE COOLING
• AIR COOLING
• WATER COOLING
CAPACITOR BANK
It is used to improve the power factor from lagging to leading nature.
And it also maintain the power in substation. In my substation 48 MVA
capacitor bank is used.
INSULATOR
A material of such low conductivity that the flow of current through it is
negligible. In my substation mainly two type insulator are used-
glass insulator
porcelain insulator
CONDUCTOR
There are many types of conductor but my substation used 4 type
conductor -
Panther Conductor Moose Conductor
CONDUCTOR
Zebra Conductor Dog Conductor
THANK YOU…

More Related Content

What's hot

PPt on 220 kV substation
PPt on 220 kV substationPPt on 220 kV substation
PPt on 220 kV substation
Ishank Ranjan
 
Uttar pradesh power corparation ltd. training report
Uttar pradesh power corparation ltd. training reportUttar pradesh power corparation ltd. training report
Uttar pradesh power corparation ltd. training report
19saurabh89
 

What's hot (20)

Shashikdoc
ShashikdocShashikdoc
Shashikdoc
 
220KV Substation Training Report
220KV Substation Training Report220KV Substation Training Report
220KV Substation Training Report
 
Electrical 132kv substation project .. shakir
Electrical 132kv substation project .. shakirElectrical 132kv substation project .. shakir
Electrical 132kv substation project .. shakir
 
PPt on 220 kV substation
PPt on 220 kV substationPPt on 220 kV substation
PPt on 220 kV substation
 
Madan mohan malaviya
Madan mohan malaviyaMadan mohan malaviya
Madan mohan malaviya
 
132 kv
132 kv132 kv
132 kv
 
132KV SUBSTATION UPPTCL
132KV SUBSTATION UPPTCL132KV SUBSTATION UPPTCL
132KV SUBSTATION UPPTCL
 
presentation on 400kv gss heerapura @mnit
presentation on 400kv gss heerapura @mnitpresentation on 400kv gss heerapura @mnit
presentation on 400kv gss heerapura @mnit
 
Powergrid Corporation India Limited industrial training
Powergrid Corporation India Limited industrial trainingPowergrid Corporation India Limited industrial training
Powergrid Corporation India Limited industrial training
 
Training report on 400 kV GSS
Training report on 400 kV GSSTraining report on 400 kV GSS
Training report on 400 kV GSS
 
substation internship report
substation internship report substation internship report
substation internship report
 
Uttar pradesh power corparation ltd. training report
Uttar pradesh power corparation ltd. training reportUttar pradesh power corparation ltd. training report
Uttar pradesh power corparation ltd. training report
 
220kv GSS, VKIA, jaipur
220kv GSS, VKIA, jaipur 220kv GSS, VKIA, jaipur
220kv GSS, VKIA, jaipur
 
Summer Internship Report -By Rahul Mehra
Summer Internship Report -By Rahul MehraSummer Internship Report -By Rahul Mehra
Summer Internship Report -By Rahul Mehra
 
industrial Training report in PTCUL Substation dehradun
industrial Training report in PTCUL Substation dehradunindustrial Training report in PTCUL Substation dehradun
industrial Training report in PTCUL Substation dehradun
 
Presentation on 132/33 KVSubstation Training
Presentation on 132/33 KVSubstation Training Presentation on 132/33 KVSubstation Training
Presentation on 132/33 KVSubstation Training
 
PPT ON 33/11KV SUBSTATION
PPT ON 33/11KV SUBSTATIONPPT ON 33/11KV SUBSTATION
PPT ON 33/11KV SUBSTATION
 
PPT on 33/11 sub-station uppcl
PPT on 33/11 sub-station uppclPPT on 33/11 sub-station uppcl
PPT on 33/11 sub-station uppcl
 
132kV GSS ppt
132kV GSS ppt132kV GSS ppt
132kV GSS ppt
 
Substation Training presentation
Substation Training presentationSubstation Training presentation
Substation Training presentation
 

Similar to PRESENTATION ON UPPTCL 220 KV TRANSMISSION SUMMER TRAINING BANDA, BANDA FROM BBDNITM

industrialsummertrainingon220kvsubstationppt-170413134021.pdf
industrialsummertrainingon220kvsubstationppt-170413134021.pdfindustrialsummertrainingon220kvsubstationppt-170413134021.pdf
industrialsummertrainingon220kvsubstationppt-170413134021.pdf
Devesh54
 
Uttar pradesh power corporation limited
Uttar pradesh power corporation limitedUttar pradesh power corporation limited
Uttar pradesh power corporation limited
VSRAGHU
 
Amanppt 140826070457-phpapp02
Amanppt 140826070457-phpapp02Amanppt 140826070457-phpapp02
Amanppt 140826070457-phpapp02
Md Hasan
 

Similar to PRESENTATION ON UPPTCL 220 KV TRANSMISSION SUMMER TRAINING BANDA, BANDA FROM BBDNITM (20)

Gss ppt by kanhaiya
Gss ppt  by kanhaiyaGss ppt  by kanhaiya
Gss ppt by kanhaiya
 
industrialsummertrainingon220kvsubstationppt-170413134021.pdf
industrialsummertrainingon220kvsubstationppt-170413134021.pdfindustrialsummertrainingon220kvsubstationppt-170413134021.pdf
industrialsummertrainingon220kvsubstationppt-170413134021.pdf
 
Sharavati receiving station
Sharavati  receiving stationSharavati  receiving station
Sharavati receiving station
 
rough.pptx
rough.pptxrough.pptx
rough.pptx
 
Summer Training Report Ntpc barh (ajeet)
Summer Training Report Ntpc barh (ajeet)Summer Training Report Ntpc barh (ajeet)
Summer Training Report Ntpc barh (ajeet)
 
Ashish.pptx
Ashish.pptxAshish.pptx
Ashish.pptx
 
Uttar pradesh power corporation limited
Uttar pradesh power corporation limitedUttar pradesh power corporation limited
Uttar pradesh power corporation limited
 
132 kV uppcl
132 kV uppcl132 kV uppcl
132 kV uppcl
 
ntpc ppt
ntpc pptntpc ppt
ntpc ppt
 
Amanppt 140826070457-phpapp02
Amanppt 140826070457-phpapp02Amanppt 140826070457-phpapp02
Amanppt 140826070457-phpapp02
 
pptravi-191011011024 (1).pdf
pptravi-191011011024 (1).pdfpptravi-191011011024 (1).pdf
pptravi-191011011024 (1).pdf
 
Presentation on BSPTCL Grid Sub-Station
Presentation on BSPTCL Grid Sub-StationPresentation on BSPTCL Grid Sub-Station
Presentation on BSPTCL Grid Sub-Station
 
Summer Training presentation on 132/33 KV sub-station Minto park, Allahabad
Summer Training presentation on 132/33 KV sub-station Minto park, AllahabadSummer Training presentation on 132/33 KV sub-station Minto park, Allahabad
Summer Training presentation on 132/33 KV sub-station Minto park, Allahabad
 
sub subsation seminar ppt.pptx
sub subsation seminar ppt.pptxsub subsation seminar ppt.pptx
sub subsation seminar ppt.pptx
 
Rajasthan Rajya Vidyut Prasaran Nigam.pptx
Rajasthan Rajya Vidyut Prasaran Nigam.pptxRajasthan Rajya Vidyut Prasaran Nigam.pptx
Rajasthan Rajya Vidyut Prasaran Nigam.pptx
 
UPPCL,33/11KV H.A.L SUBSTATION,INDIRANAGAR(LUCKNOW)
UPPCL,33/11KV H.A.L SUBSTATION,INDIRANAGAR(LUCKNOW)UPPCL,33/11KV H.A.L SUBSTATION,INDIRANAGAR(LUCKNOW)
UPPCL,33/11KV H.A.L SUBSTATION,INDIRANAGAR(LUCKNOW)
 
Jagdeesh ppt
Jagdeesh pptJagdeesh ppt
Jagdeesh ppt
 
220kv gss pindwara(sirohi)
220kv gss pindwara(sirohi)220kv gss pindwara(sirohi)
220kv gss pindwara(sirohi)
 
132 kv substation
132 kv substation132 kv substation
132 kv substation
 
Ashwani kumar
Ashwani kumarAshwani kumar
Ashwani kumar
 

Recently uploaded

Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
jaanualu31
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Kandungan 087776558899
 
DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakes
MayuraD1
 
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
HenryBriggs2
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
mphochane1998
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
Epec Engineered Technologies
 

Recently uploaded (20)

Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
 
Rums floating Omkareshwar FSPV IM_16112021.pdf
Rums floating Omkareshwar FSPV IM_16112021.pdfRums floating Omkareshwar FSPV IM_16112021.pdf
Rums floating Omkareshwar FSPV IM_16112021.pdf
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
Computer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to ComputersComputer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to Computers
 
Engineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planesEngineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planes
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna Municipality
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakes
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdf
 
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 

PRESENTATION ON UPPTCL 220 KV TRANSMISSION SUMMER TRAINING BANDA, BANDA FROM BBDNITM

  • 1. A SUMMER TRAINING PRESENTATION ON UTTAR PRADESH POWER TRANSMISSION CORPORATION LIMITED (UPPTCL) A SEMINAR IN PARTIALLY FULFILLMENT OF THE REQUIREMENT FOR THE AWARD OF THE DEGREE OF BACHELOR OF TECHNOLOGY IN ELECTRICAL ENGINEERING FROM BABU BANARASI DAS NATIONAL INSTITUTE OF TECHNOLOGY & MANAGEMENT (LUCKNOW) AFFILIATED WITH APJ AKTU SUBMITTED BY RISHASBH DEV SINGH SUBMITTED TO PROFF. MRS KALPNA KUREEL
  • 2. CONTENTS o INTRODUCTION o ABOUT 220 KVA SUBSTATION o COMPONENT OF SUBSTATION o OVERVIEW & SINGLE LINE DIAGRAM OF SUBSTATION o PROTECTION OF SUBSTATION o MAINTENANCE OF SUBSTATION o CONCLUSION
  • 3. INTRODUCTION Uttar Pradesh Power Transmission Corporation Limited (UPPTCL) is the responsible for transmission above 33 KVA within the Indian state of Uttar Pradesh. Its chairman is Mr. KAMRAN REZVI(IAS). In 14 January 2000 UPSEB divided into three part – • GENERATING • UPPTCL (TRANSMISSION) • UPPCL (DISTRIBUTION) UPPTCL BANDA has three substation is basically contains three substation. One of 400 kv second is 220 kv & another is 132 kv substation. 220/132 KVA substation established in 2002.
  • 4. ABOUT THE SUBSTATION There are three part of substation – • CONTROL ROOM • BATTERY ROOM • SWITCH YARD
  • 5. CONTROL ROOM It contain panel related to controlling of instruments. Basically it operate manually. It work as shield guard for all substation equipment & electrical network. These panel are useful to control the flow of electrical as per the voltage class and detect the faults in transmission line. E.g. feeder panel, x-mar panel etc.
  • 6. BATTERY ROOM The control panels and relays of the sub-station required DC supply. The sub-station Has Two set of 110 Volt and a set of 48 Volt DC Supply. The DC supply is made with the help of battery bank reserve normally kept in a separate room called battery room. The batteries used in this sub-station are Nickel-Cadmium (NI-Cd) batteries. These batteries re used due to their advantages like low maintenance, longer life (15-20 years) etc. Each cell is of 2 V and 300 Ah Capacity.
  • 7. USE OF BATTERY ROOM Storage battery system is used in emergency situation for the working of electrical equipment: • To open and close the switch gear • For indication and control • Emergency lighting • Relay and interlocking equipment • For working of alarm circuit.
  • 8. SWITCH YARD Switch yard has many things which is situate in openly. Switch yard is combination of Wave trap, LA, CT, PT, Transformers, Bus bar, Isolator, Insulator, Breakers, Bus coupler, MULSI fire room etc. switch yard is connected with control room. In switch yard there are many things connected.
  • 9. ELEMENT OF SWITCH YARD • WAVE TRAP • LIGHTENING ARRESTER (LA) • CURRENT TRANSFORMER (CT) • POTENTIAL TRANSFORMER (PT) • CIRCUIT BREAKER • RELAY • ISOLATOR • TRANSFORMER • INSULATOR • CAPACITOR BANK • CONDOCTOR
  • 10. WAVE TRAP Wave trap is an instrument using for tripping of the wave. The function of this trap is that it traps the unwanted waves. Its function is of trapping wave. Its shape is like a drum. It is connected to the main incoming feeder so that it can trap the waves which may be dangerous to the instruments here in the substation.
  • 11. LIGHTENING ARRESTER Lightening arrester is used to discharge surge which come from cloud. LA protects devises from extra surge. To discharge the switching and lightening voltage surges to earth. It provides low impedance path for high frequency and high current supply.
  • 12. CURRENT TRANSFORMER (CT) CT is known as brain of substation. It is used for measure current. CT is connected seriously. It is a step up transformer which is used to measure the current, by stepping down the voltage level.
  • 13. CURRENT TRANSFORMER (CT) In CT the secondary current is proportional to the primary current. In my substation the CT ratio is used 200:5.5 that shows secondary current of 5.5A when primary current is 200A.
  • 14. POTENTIAL TRANSFORMER (PT) Voltage transformer also called potential transformer are a parallel connected type of instrument transformer. They have designed to present negligible load to supply being measured and have an accurate voltage ratio and phase relation.
  • 15. POTENTIAL TRANSFORMER (PT) In my substation the PT ratio is used 400:120 that shows secondary current of 120V when primary current is 400V.
  • 16. CIRCUIT BREAEKER A circuit breaker is an automatically operated electrical switch designed to protect an electrical circuit from damage caused by over- current or overload or short circuit. In my substation SF6 & VACCUME circuit breaker is used TYPE OF CIRCUIT BREKER • AIR BLAST CIRCUIT BREKER • OIL CIRCUIT BERKER • SF6 CIRCUIT BREKER • VACCUME CIRCUIT BREKER
  • 17. TYPES OF CIRCUIT BREAKERS Oil circuit breakerAir-blast circuit breaker Sulfur hexafluoride circuit breaker (SF6)Vacuum circuit breakers
  • 18. OIL CIRCUIT BREAKER It is designed for 11kv-765kv. The contacts are immersed in oil bath. Oil provides cooling by hydrogen created by arc. It acts as a good dielectric medium and quenches the arc.
  • 19. AIR BLAST CIRCUIT BREAKERS This operates using high velocity blast of air which quenches the arc. It consists of blast valve , blast tube & contacts. Blast valve contains air at high pressure. Blast tube carries the air at high pressure & opens the moving contact attached to spring. There is no carbonization of surface as in VCB. Air should be kept clean & dry to operate it properly.
  • 20. SF6 CIRCUIT BREAKERS  It contains an arc interruption chamber containing SF6 gas.  In closed position the contacts remain surrounded by SF6 gas at a pressure of 2.8 kg/cm2 .  During opening high pressure SF6 gas at 14 kg/cm2 from its reservoir flows towards the chamber by valve mechanism.  SF6 rapidly absorbs the free electrons in the arc path to form immobile negative ions to build up high dielectric strength.  It also cools the arc and extinguishes it.  After operation the valve is closed by the action of a set of springs.  Absorbent materials are used to absorb the byproducts and moisture.
  • 21. VACCUM CIRCUIT BREAKER It is designed for medium voltage range (3.3- 33kv). This consists of vacuum of pressure (1*10-6) inside arc extinction chamber. The arc burns in metal vapor when the contacts are disconnected. At high voltage , it’s rate of dielectric strength recovery is very high. Due to vacuum arc extinction is very fast. The contacts loose metals gradually due to formation of metal vapors.
  • 22. RELAY PROTECTIVE RELAY Current Voltage Insulation Temperature Pick up levels Time Visual indication Warning alarm Remove power output input setting A relay is an electrically operated switch. A relay is a sensing device which sense the abnormal condition and then produce an alarm or open the breaker contact.
  • 23. RELAY In my substation used four type relay - • DISTANCE RELAY • DIRECTIONAL RELAY • OVER CURRENT RELAY • DIFFERENCE RELAY
  • 24. ISOLATOR Isolator is used to ensure that an electrical circuit is completely de- energized for service or maintenance.
  • 25. TRANSFORMER The transformer is called the heart of transformer. A transformer is an electrical device that transfers electrical energy between two or more circuits through electromagnetic induction. In my substation has four transformer two 160 MVA transformer and two 40 MVA. Both are step down transformer. 160 MVA transformer convert 220 to 132 KVA & 40 MVA converts 132 to 33 KVA. Transformer has three type- • Auto transformer • Step up transformer • Step down transformer
  • 26.
  • 27. COOLING OF TRANSFORMER Continuous working of transformer goes to heat. Thus the cooling of transformer various method are used. • OIL COOLING • NATURE COOLING • AIR COOLING • WATER COOLING
  • 28.
  • 29. CAPACITOR BANK It is used to improve the power factor from lagging to leading nature. And it also maintain the power in substation. In my substation 48 MVA capacitor bank is used.
  • 30. INSULATOR A material of such low conductivity that the flow of current through it is negligible. In my substation mainly two type insulator are used- glass insulator porcelain insulator
  • 31. CONDUCTOR There are many types of conductor but my substation used 4 type conductor - Panther Conductor Moose Conductor