SlideShare a Scribd company logo
1 of 10
Partial Backfill
  Alternative
       January 21, 2010
Cooperator’s Meeting Presentation
Partial Backfill Alternative

Considerations
•  Be responsive to an Issue
•  Minimize water that collects in the pit
•  Return waste rock to the pit
•  Minimize resources that are used in
   backfilling
•  Minimize air impacts
Partial Backfill Alternative
   Environmental Considerations

•  Compliance with all applicable regulations
   including ADEQ BADCT and air regulations
•  Maintain a Hydraulic Sink
•  Geochemical considerations with the addition of
   a mix of finer grained materials
•  Stormwater controls during backfill
•  Effect on concurrent reclamation and on
   reclamation planning
Pit Lake Development
Hydrogeologic Study Results
                              Pit Lake
                                             Pit Lake Depth
           Period            Elevation
                                                  (feet)
                             (ft amsl)

        Mine Closure          (None)               0

     Closure + 20 years        3,591              541

     Closure + 50 years        3,751              701

     Closure + 100 years       3,869              819


•  Backfill elevation – 3825 ft amsl (est.)
•  Elevation was estimated to maintain sink (modeling to confirm
   elevation estimation with operational adjustments as necessary)
Other Considerations

•  Heap Leach remains undisturbed
•  Haulage fleet used will be consistent in size
   to current fleet
•  Loading equipment (shovel used will
   be consistent with current loading
   equipment)
•  Waste rock density is 11.95 ft3/ton
•  Swell factor for the rock is 1.3
Other Considerations

•  Amount of material necessary for backfill is
   90 million tons (46 million cubic yards)
•  Allowance of 5% added for construction of
   ramps for downhill haulage
•  Total material rehandled 94 million tons
•  36-months required to complete backfill
•  Hauls will incorporate 3 switchbacks at
   -10% grade at a maximum 13 mph
Backfill and
Excavation Area
•  Excavation on 50 foot
   benches
•  Start elevation approx
   5429 ft amsl
•  Final elevation 5200
   ft amsl
•  Dumped into pit from
   3825 ft elevation
Productivity by Bench
         Bench	
                Tonnage	
  	
  	
  	
   Cumula+ve	
                    Haulage	
  
       Eleva+on	
  	
  	
  	
   (x	
  1,000)	
   Tonnage	
  	
  	
  	
  	
  	
  	
   Produc+on	
  	
  	
  
       (.	
  amsl)	
                                     (x	
  1,000)	
              (tons/hour)	
  
          5420                        8,938                    8,938                     379
          5400                     18,435                    27,373                      387
          5350                     18,689                   46,062                       395
          5300                     16,277                   62,338                       403
          5250                     12,977                   75,315                       411
          5200                        8,720                 84,036                       419


This information was used to determine the appropriate
haulage fleet for this activity matched to one shovel.
Required Haulage Hours and Units

                          Rehandle	
                              CAT	
  793C	
  Truck	
  Fleet	
  
        Post-­‐Mining	
  
                             Tons	
  	
  	
  	
  	
  	
  	
  
           Year	
                                               Opera+ng	
  
                          (x	
  1,000)	
                                                  Units	
  
                                                                 Hours	
  
                   1                       28,774                 74,740                  16
                   2                       28,853                 72,439                  16
                   3                       26,409                 64,021                  15
               Total                       84,036                211,201                  16



  Modeling indicates that 16 trucks will be required in the
  first 19 months of the project and 15 for the remainder.

More Related Content

What's hot

Alex Persico Power Point
Alex Persico Power PointAlex Persico Power Point
Alex Persico Power PointAlex Persico
 
Odc tank project bdq to za
Odc tank project bdq to za Odc tank project bdq to za
Odc tank project bdq to za Nitesh Desai
 
Kaybob 2014 v2
Kaybob 2014 v2Kaybob 2014 v2
Kaybob 2014 v2TGS
 
My contributions to indusries for 39 years
My contributions to indusries for 39 yearsMy contributions to indusries for 39 years
My contributions to indusries for 39 yearsMantrala Sastry
 
OptiSurface Landforming Technology
OptiSurface Landforming TechnologyOptiSurface Landforming Technology
OptiSurface Landforming TechnologyGraeme Cox
 
Zonnedaken op bedrijfsgebouwen klimaatplein event
Zonnedaken op bedrijfsgebouwen klimaatplein eventZonnedaken op bedrijfsgebouwen klimaatplein event
Zonnedaken op bedrijfsgebouwen klimaatplein eventwww.klimaatplein.com
 
Blasting inprovement techniques
Blasting inprovement techniquesBlasting inprovement techniques
Blasting inprovement techniquesKrishna Deo Prasad
 
Master Student Presentation in Construction Technology Course
Master Student Presentation in Construction Technology CourseMaster Student Presentation in Construction Technology Course
Master Student Presentation in Construction Technology CourseSevar Dilkhaz
 
2D seismic analysis of Chalk play in the northern Dutch offshore
2D seismic analysis of Chalk play in the northern Dutch offshore2D seismic analysis of Chalk play in the northern Dutch offshore
2D seismic analysis of Chalk play in the northern Dutch offshoreDick Stegers
 
Productivity analysis of Burried/underground cable laying Activity
Productivity analysis of Burried/underground cable laying ActivityProductivity analysis of Burried/underground cable laying Activity
Productivity analysis of Burried/underground cable laying ActivityManish Kumar PGP - NICMAR Pune
 
Metode Konstruksi - Proyek Persiapan Lahan Parkir Jurusan Teknik Sipil UNS
Metode Konstruksi - Proyek Persiapan Lahan Parkir Jurusan Teknik Sipil UNSMetode Konstruksi - Proyek Persiapan Lahan Parkir Jurusan Teknik Sipil UNS
Metode Konstruksi - Proyek Persiapan Lahan Parkir Jurusan Teknik Sipil UNSHimamul A'la
 

What's hot (14)

Alex Persico Power Point
Alex Persico Power PointAlex Persico Power Point
Alex Persico Power Point
 
Odc tank project bdq to za
Odc tank project bdq to za Odc tank project bdq to za
Odc tank project bdq to za
 
Kaybob 2014 v2
Kaybob 2014 v2Kaybob 2014 v2
Kaybob 2014 v2
 
My contributions to indusries for 39 years
My contributions to indusries for 39 yearsMy contributions to indusries for 39 years
My contributions to indusries for 39 years
 
Attachments 23 12_2010
Attachments 23 12_2010Attachments 23 12_2010
Attachments 23 12_2010
 
OptiSurface Landforming Technology
OptiSurface Landforming TechnologyOptiSurface Landforming Technology
OptiSurface Landforming Technology
 
Zonnedaken op bedrijfsgebouwen klimaatplein event
Zonnedaken op bedrijfsgebouwen klimaatplein eventZonnedaken op bedrijfsgebouwen klimaatplein event
Zonnedaken op bedrijfsgebouwen klimaatplein event
 
Blasting inprovement techniques
Blasting inprovement techniquesBlasting inprovement techniques
Blasting inprovement techniques
 
Master Student Presentation in Construction Technology Course
Master Student Presentation in Construction Technology CourseMaster Student Presentation in Construction Technology Course
Master Student Presentation in Construction Technology Course
 
2D seismic analysis of Chalk play in the northern Dutch offshore
2D seismic analysis of Chalk play in the northern Dutch offshore2D seismic analysis of Chalk play in the northern Dutch offshore
2D seismic analysis of Chalk play in the northern Dutch offshore
 
Productivity analysis of Burried/underground cable laying Activity
Productivity analysis of Burried/underground cable laying ActivityProductivity analysis of Burried/underground cable laying Activity
Productivity analysis of Burried/underground cable laying Activity
 
Metode Konstruksi - Proyek Persiapan Lahan Parkir Jurusan Teknik Sipil UNS
Metode Konstruksi - Proyek Persiapan Lahan Parkir Jurusan Teknik Sipil UNSMetode Konstruksi - Proyek Persiapan Lahan Parkir Jurusan Teknik Sipil UNS
Metode Konstruksi - Proyek Persiapan Lahan Parkir Jurusan Teknik Sipil UNS
 
ditching
ditchingditching
ditching
 
Seal-One Cantarell-418
Seal-One Cantarell-418Seal-One Cantarell-418
Seal-One Cantarell-418
 

Viewers also liked

Development Length Hook Splice Of Reinforcements
Development Length Hook Splice Of ReinforcementsDevelopment Length Hook Splice Of Reinforcements
Development Length Hook Splice Of ReinforcementsSHERAZ HAMEED
 
29 JUN-2015 - ACI SP66 (040 RE-BAR DETAILING MANUALl
29 JUN-2015 - ACI SP66 (040 RE-BAR DETAILING MANUALl29 JUN-2015 - ACI SP66 (040 RE-BAR DETAILING MANUALl
29 JUN-2015 - ACI SP66 (040 RE-BAR DETAILING MANUALlpeakpilgrim
 
Design of reinforced concrete as per aci 318
Design of reinforced concrete as per aci 318Design of reinforced concrete as per aci 318
Design of reinforced concrete as per aci 318Jose Fabricio
 
F3 Subsoil drainage and installation
F3 Subsoil drainage and installationF3 Subsoil drainage and installation
F3 Subsoil drainage and installationtoverwater
 
Sp 34-1987 handbook on reinforcement and detailing
Sp 34-1987 handbook on reinforcement and detailingSp 34-1987 handbook on reinforcement and detailing
Sp 34-1987 handbook on reinforcement and detailingjemmabarsby
 
Reinforcement detailing
Reinforcement  detailingReinforcement  detailing
Reinforcement detailingAli Ishaqi
 
Bar bending schedule(by akhil)
Bar bending schedule(by akhil)Bar bending schedule(by akhil)
Bar bending schedule(by akhil)Lamdade Akhil
 
Civil Engineering (Beams,Columns)
Civil Engineering (Beams,Columns)Civil Engineering (Beams,Columns)
Civil Engineering (Beams,Columns)mbrsalman
 

Viewers also liked (11)

Ashuppt
AshupptAshuppt
Ashuppt
 
Development Length Hook Splice Of Reinforcements
Development Length Hook Splice Of ReinforcementsDevelopment Length Hook Splice Of Reinforcements
Development Length Hook Splice Of Reinforcements
 
29 JUN-2015 - ACI SP66 (040 RE-BAR DETAILING MANUALl
29 JUN-2015 - ACI SP66 (040 RE-BAR DETAILING MANUALl29 JUN-2015 - ACI SP66 (040 RE-BAR DETAILING MANUALl
29 JUN-2015 - ACI SP66 (040 RE-BAR DETAILING MANUALl
 
Design of reinforced concrete as per aci 318
Design of reinforced concrete as per aci 318Design of reinforced concrete as per aci 318
Design of reinforced concrete as per aci 318
 
F3 Subsoil drainage and installation
F3 Subsoil drainage and installationF3 Subsoil drainage and installation
F3 Subsoil drainage and installation
 
Reinfocing details of column
Reinfocing details of columnReinfocing details of column
Reinfocing details of column
 
Sp 34-1987 handbook on reinforcement and detailing
Sp 34-1987 handbook on reinforcement and detailingSp 34-1987 handbook on reinforcement and detailing
Sp 34-1987 handbook on reinforcement and detailing
 
Reinforcement detailing
Reinforcement  detailingReinforcement  detailing
Reinforcement detailing
 
Bar bending schedule(by akhil)
Bar bending schedule(by akhil)Bar bending schedule(by akhil)
Bar bending schedule(by akhil)
 
Field Compaction
Field CompactionField Compaction
Field Compaction
 
Civil Engineering (Beams,Columns)
Civil Engineering (Beams,Columns)Civil Engineering (Beams,Columns)
Civil Engineering (Beams,Columns)
 

Similar to Partial Pit Backfill Alternative

Kope winder or friction winder ppt
Kope winder or friction winder pptKope winder or friction winder ppt
Kope winder or friction winder pptAMIT SAHU
 
Underground cavern project
Underground cavern projectUnderground cavern project
Underground cavern projectManveer Shetty
 
TAG WOOHOOPRESENTAION
TAG WOOHOOPRESENTAIONTAG WOOHOOPRESENTAION
TAG WOOHOOPRESENTAIONDwight Nava
 
2022HT-79523 Bench Marking J Naveen Kumar reddy.pdf
2022HT-79523  Bench Marking J Naveen Kumar reddy.pdf2022HT-79523  Bench Marking J Naveen Kumar reddy.pdf
2022HT-79523 Bench Marking J Naveen Kumar reddy.pdfnaveen211425
 
Atlas Senior Deisgn Presentation
Atlas Senior Deisgn PresentationAtlas Senior Deisgn Presentation
Atlas Senior Deisgn PresentationSteven Polowy
 
AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)
AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)
AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)coderweb
 
The productivity of lhd in underground coal mines
The productivity of   lhd in underground coal minesThe productivity of   lhd in underground coal mines
The productivity of lhd in underground coal minesSafdar Ali
 
Rodrigo edgard tesis_bachiller_2019_part.2
Rodrigo edgard tesis_bachiller_2019_part.2Rodrigo edgard tesis_bachiller_2019_part.2
Rodrigo edgard tesis_bachiller_2019_part.2BibianLeaTicona
 
SECL training presentation
SECL training presentationSECL training presentation
SECL training presentationravi8492
 
COOP training-Bokhari
COOP training-BokhariCOOP training-Bokhari
COOP training-BokhariAssad Bokhari
 
Production calculation.ppt
Production calculation.pptProduction calculation.ppt
Production calculation.pptJSathish3
 
Joint Operation Mining Plan (28 Ha) - PT Jagad Rayatama.pptx
Joint Operation Mining Plan (28 Ha) - PT Jagad Rayatama.pptxJoint Operation Mining Plan (28 Ha) - PT Jagad Rayatama.pptx
Joint Operation Mining Plan (28 Ha) - PT Jagad Rayatama.pptxHafidzQadli1
 
Development Of Tipper Unloading Mechanism
Development Of Tipper Unloading MechanismDevelopment Of Tipper Unloading Mechanism
Development Of Tipper Unloading MechanismIRJET Journal
 
SARNATH-PROFILE-CAE
SARNATH-PROFILE-CAESARNATH-PROFILE-CAE
SARNATH-PROFILE-CAESarnath R
 

Similar to Partial Pit Backfill Alternative (20)

Kope winder or friction winder ppt
Kope winder or friction winder pptKope winder or friction winder ppt
Kope winder or friction winder ppt
 
Underground cavern project
Underground cavern projectUnderground cavern project
Underground cavern project
 
TAG WOOHOOPRESENTAION
TAG WOOHOOPRESENTAIONTAG WOOHOOPRESENTAION
TAG WOOHOOPRESENTAION
 
FAST Ship Slides B
FAST Ship Slides BFAST Ship Slides B
FAST Ship Slides B
 
2022HT-79523 Bench Marking J Naveen Kumar reddy.pdf
2022HT-79523  Bench Marking J Naveen Kumar reddy.pdf2022HT-79523  Bench Marking J Naveen Kumar reddy.pdf
2022HT-79523 Bench Marking J Naveen Kumar reddy.pdf
 
Atlas Senior Deisgn Presentation
Atlas Senior Deisgn PresentationAtlas Senior Deisgn Presentation
Atlas Senior Deisgn Presentation
 
AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)
AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)
AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)
 
The productivity of lhd in underground coal mines
The productivity of   lhd in underground coal minesThe productivity of   lhd in underground coal mines
The productivity of lhd in underground coal mines
 
Rodrigo edgard tesis_bachiller_2019_part.2
Rodrigo edgard tesis_bachiller_2019_part.2Rodrigo edgard tesis_bachiller_2019_part.2
Rodrigo edgard tesis_bachiller_2019_part.2
 
SECL training presentation
SECL training presentationSECL training presentation
SECL training presentation
 
African hawk 2 part 1
African hawk 2 part 1African hawk 2 part 1
African hawk 2 part 1
 
My PG Project presentation
My PG Project presentationMy PG Project presentation
My PG Project presentation
 
B012420715
B012420715B012420715
B012420715
 
COOP training-Bokhari
COOP training-BokhariCOOP training-Bokhari
COOP training-Bokhari
 
Production calculation.ppt
Production calculation.pptProduction calculation.ppt
Production calculation.ppt
 
Ch21
Ch21Ch21
Ch21
 
Joint Operation Mining Plan (28 Ha) - PT Jagad Rayatama.pptx
Joint Operation Mining Plan (28 Ha) - PT Jagad Rayatama.pptxJoint Operation Mining Plan (28 Ha) - PT Jagad Rayatama.pptx
Joint Operation Mining Plan (28 Ha) - PT Jagad Rayatama.pptx
 
Grant nov99
Grant nov99Grant nov99
Grant nov99
 
Development Of Tipper Unloading Mechanism
Development Of Tipper Unloading MechanismDevelopment Of Tipper Unloading Mechanism
Development Of Tipper Unloading Mechanism
 
SARNATH-PROFILE-CAE
SARNATH-PROFILE-CAESARNATH-PROFILE-CAE
SARNATH-PROFILE-CAE
 

More from Hudbay Minerals Inc.

Well Protection Program - Groundwater Modeling Presentation
Well Protection Program - Groundwater Modeling PresentationWell Protection Program - Groundwater Modeling Presentation
Well Protection Program - Groundwater Modeling PresentationHudbay Minerals Inc.
 
Rosemont Copper Cooperating Agencies - 2009
Rosemont Copper Cooperating Agencies - 2009Rosemont Copper Cooperating Agencies - 2009
Rosemont Copper Cooperating Agencies - 2009Hudbay Minerals Inc.
 
Rosemont Copper - Mining Law of 1872
Rosemont Copper - Mining Law of 1872Rosemont Copper - Mining Law of 1872
Rosemont Copper - Mining Law of 1872Hudbay Minerals Inc.
 
Rosemont Copper - Tailings: Reused Mine Rock
Rosemont Copper - Tailings: Reused Mine RockRosemont Copper - Tailings: Reused Mine Rock
Rosemont Copper - Tailings: Reused Mine RockHudbay Minerals Inc.
 
Rosemont Copper Dry Stack Presentation 2009
Rosemont Copper Dry Stack Presentation 2009Rosemont Copper Dry Stack Presentation 2009
Rosemont Copper Dry Stack Presentation 2009Hudbay Minerals Inc.
 
Rosemont Reclamation Plan July 2007
Rosemont Reclamation Plan July 2007Rosemont Reclamation Plan July 2007
Rosemont Reclamation Plan July 2007Hudbay Minerals Inc.
 
Reclamation Examples - Before and After
Reclamation Examples - Before and AfterReclamation Examples - Before and After
Reclamation Examples - Before and AfterHudbay Minerals Inc.
 
Mine Rock Geochemistry and Pit Lake Model
Mine Rock Geochemistry and Pit Lake ModelMine Rock Geochemistry and Pit Lake Model
Mine Rock Geochemistry and Pit Lake ModelHudbay Minerals Inc.
 
Water Supply Plan & Hydrogeology "Westside Presentation"
Water Supply Plan & Hydrogeology "Westside Presentation"Water Supply Plan & Hydrogeology "Westside Presentation"
Water Supply Plan & Hydrogeology "Westside Presentation"Hudbay Minerals Inc.
 
Rosemont Project Hydrogeology & Water Supply
Rosemont Project Hydrogeology & Water SupplyRosemont Project Hydrogeology & Water Supply
Rosemont Project Hydrogeology & Water SupplyHudbay Minerals Inc.
 
Facilities Engineering Presentation
Facilities Engineering PresentationFacilities Engineering Presentation
Facilities Engineering PresentationHudbay Minerals Inc.
 
Aquifer Protection Permitting: Rosemont Mine
Aquifer Protection Permitting:  Rosemont MineAquifer Protection Permitting:  Rosemont Mine
Aquifer Protection Permitting: Rosemont MineHudbay Minerals Inc.
 

More from Hudbay Minerals Inc. (20)

Well Protection Program - Groundwater Modeling Presentation
Well Protection Program - Groundwater Modeling PresentationWell Protection Program - Groundwater Modeling Presentation
Well Protection Program - Groundwater Modeling Presentation
 
Rosemont Copper Cooperating Agencies - 2009
Rosemont Copper Cooperating Agencies - 2009Rosemont Copper Cooperating Agencies - 2009
Rosemont Copper Cooperating Agencies - 2009
 
Rosemont Copper - Mining Law of 1872
Rosemont Copper - Mining Law of 1872Rosemont Copper - Mining Law of 1872
Rosemont Copper - Mining Law of 1872
 
Rosemont Copper - Tailings: Reused Mine Rock
Rosemont Copper - Tailings: Reused Mine RockRosemont Copper - Tailings: Reused Mine Rock
Rosemont Copper - Tailings: Reused Mine Rock
 
Rosemont Copper Dry Stack Presentation 2009
Rosemont Copper Dry Stack Presentation 2009Rosemont Copper Dry Stack Presentation 2009
Rosemont Copper Dry Stack Presentation 2009
 
Dry Stack Tailings Overview
Dry Stack Tailings OverviewDry Stack Tailings Overview
Dry Stack Tailings Overview
 
Rosemont Reclamation Plan July 2007
Rosemont Reclamation Plan July 2007Rosemont Reclamation Plan July 2007
Rosemont Reclamation Plan July 2007
 
Reclamation Requirements
Reclamation RequirementsReclamation Requirements
Reclamation Requirements
 
Reclamation Examples - Before and After
Reclamation Examples - Before and AfterReclamation Examples - Before and After
Reclamation Examples - Before and After
 
Regional Groundwater Flow Models
Regional Groundwater Flow ModelsRegional Groundwater Flow Models
Regional Groundwater Flow Models
 
Baseline Traffic Study
Baseline Traffic StudyBaseline Traffic Study
Baseline Traffic Study
 
Baseline Noise Study
Baseline Noise StudyBaseline Noise Study
Baseline Noise Study
 
Heap Leach Facilities
Heap Leach FacilitiesHeap Leach Facilities
Heap Leach Facilities
 
Geotechnical Study
Geotechnical StudyGeotechnical Study
Geotechnical Study
 
Mine Rock Geochemistry and Pit Lake Model
Mine Rock Geochemistry and Pit Lake ModelMine Rock Geochemistry and Pit Lake Model
Mine Rock Geochemistry and Pit Lake Model
 
Rosemont Project Orientation
Rosemont Project OrientationRosemont Project Orientation
Rosemont Project Orientation
 
Water Supply Plan & Hydrogeology "Westside Presentation"
Water Supply Plan & Hydrogeology "Westside Presentation"Water Supply Plan & Hydrogeology "Westside Presentation"
Water Supply Plan & Hydrogeology "Westside Presentation"
 
Rosemont Project Hydrogeology & Water Supply
Rosemont Project Hydrogeology & Water SupplyRosemont Project Hydrogeology & Water Supply
Rosemont Project Hydrogeology & Water Supply
 
Facilities Engineering Presentation
Facilities Engineering PresentationFacilities Engineering Presentation
Facilities Engineering Presentation
 
Aquifer Protection Permitting: Rosemont Mine
Aquifer Protection Permitting:  Rosemont MineAquifer Protection Permitting:  Rosemont Mine
Aquifer Protection Permitting: Rosemont Mine
 

Recently uploaded

SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptx
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptxSKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptx
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptxAmanpreet Kaur
 
Spellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please PractiseSpellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please PractiseAnaAcapella
 
Vishram Singh - Textbook of Anatomy Upper Limb and Thorax.. Volume 1 (1).pdf
Vishram Singh - Textbook of Anatomy  Upper Limb and Thorax.. Volume 1 (1).pdfVishram Singh - Textbook of Anatomy  Upper Limb and Thorax.. Volume 1 (1).pdf
Vishram Singh - Textbook of Anatomy Upper Limb and Thorax.. Volume 1 (1).pdfssuserdda66b
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxVishalSingh1417
 
Micro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdfMicro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdfPoh-Sun Goh
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfciinovamais
 
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17  How to Extend Models Using Mixin ClassesMixin Classes in Odoo 17  How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17 How to Extend Models Using Mixin ClassesCeline George
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsTechSoup
 
Food safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdfFood safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdfSherif Taha
 
ComPTIA Overview | Comptia Security+ Book SY0-701
ComPTIA Overview | Comptia Security+ Book SY0-701ComPTIA Overview | Comptia Security+ Book SY0-701
ComPTIA Overview | Comptia Security+ Book SY0-701bronxfugly43
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfagholdier
 
Graduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - EnglishGraduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - Englishneillewis46
 
Dyslexia AI Workshop for Slideshare.pptx
Dyslexia AI Workshop for Slideshare.pptxDyslexia AI Workshop for Slideshare.pptx
Dyslexia AI Workshop for Slideshare.pptxcallscotland1987
 
ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxAreebaZafar22
 
Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Jisc
 
Towards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptxTowards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptxJisc
 
Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.pptRamjanShidvankar
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdfQucHHunhnh
 
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptxMaritesTamaniVerdade
 
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfUGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfNirmal Dwivedi
 

Recently uploaded (20)

SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptx
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptxSKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptx
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptx
 
Spellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please PractiseSpellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please Practise
 
Vishram Singh - Textbook of Anatomy Upper Limb and Thorax.. Volume 1 (1).pdf
Vishram Singh - Textbook of Anatomy  Upper Limb and Thorax.. Volume 1 (1).pdfVishram Singh - Textbook of Anatomy  Upper Limb and Thorax.. Volume 1 (1).pdf
Vishram Singh - Textbook of Anatomy Upper Limb and Thorax.. Volume 1 (1).pdf
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptx
 
Micro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdfMicro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdf
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17  How to Extend Models Using Mixin ClassesMixin Classes in Odoo 17  How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The Basics
 
Food safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdfFood safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdf
 
ComPTIA Overview | Comptia Security+ Book SY0-701
ComPTIA Overview | Comptia Security+ Book SY0-701ComPTIA Overview | Comptia Security+ Book SY0-701
ComPTIA Overview | Comptia Security+ Book SY0-701
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 
Graduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - EnglishGraduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - English
 
Dyslexia AI Workshop for Slideshare.pptx
Dyslexia AI Workshop for Slideshare.pptxDyslexia AI Workshop for Slideshare.pptx
Dyslexia AI Workshop for Slideshare.pptx
 
ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptx
 
Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)
 
Towards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptxTowards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptx
 
Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.ppt
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
 
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
 
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfUGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
 

Partial Pit Backfill Alternative

  • 1. Partial Backfill Alternative January 21, 2010 Cooperator’s Meeting Presentation
  • 2. Partial Backfill Alternative Considerations •  Be responsive to an Issue •  Minimize water that collects in the pit •  Return waste rock to the pit •  Minimize resources that are used in backfilling •  Minimize air impacts
  • 3. Partial Backfill Alternative Environmental Considerations •  Compliance with all applicable regulations including ADEQ BADCT and air regulations •  Maintain a Hydraulic Sink •  Geochemical considerations with the addition of a mix of finer grained materials •  Stormwater controls during backfill •  Effect on concurrent reclamation and on reclamation planning
  • 5. Hydrogeologic Study Results Pit Lake Pit Lake Depth Period Elevation (feet) (ft amsl) Mine Closure (None) 0 Closure + 20 years 3,591 541 Closure + 50 years 3,751 701 Closure + 100 years 3,869 819 •  Backfill elevation – 3825 ft amsl (est.) •  Elevation was estimated to maintain sink (modeling to confirm elevation estimation with operational adjustments as necessary)
  • 6. Other Considerations •  Heap Leach remains undisturbed •  Haulage fleet used will be consistent in size to current fleet •  Loading equipment (shovel used will be consistent with current loading equipment) •  Waste rock density is 11.95 ft3/ton •  Swell factor for the rock is 1.3
  • 7. Other Considerations •  Amount of material necessary for backfill is 90 million tons (46 million cubic yards) •  Allowance of 5% added for construction of ramps for downhill haulage •  Total material rehandled 94 million tons •  36-months required to complete backfill •  Hauls will incorporate 3 switchbacks at -10% grade at a maximum 13 mph
  • 8. Backfill and Excavation Area •  Excavation on 50 foot benches •  Start elevation approx 5429 ft amsl •  Final elevation 5200 ft amsl •  Dumped into pit from 3825 ft elevation
  • 9. Productivity by Bench Bench   Tonnage         Cumula+ve   Haulage   Eleva+on         (x  1,000)   Tonnage               Produc+on       (.  amsl)   (x  1,000)   (tons/hour)   5420 8,938 8,938 379 5400 18,435 27,373 387 5350 18,689 46,062 395 5300 16,277 62,338 403 5250 12,977 75,315 411 5200 8,720 84,036 419 This information was used to determine the appropriate haulage fleet for this activity matched to one shovel.
  • 10. Required Haulage Hours and Units Rehandle   CAT  793C  Truck  Fleet   Post-­‐Mining   Tons               Year   Opera+ng   (x  1,000)   Units   Hours   1 28,774 74,740 16 2 28,853 72,439 16 3 26,409 64,021 15 Total 84,036 211,201 16 Modeling indicates that 16 trucks will be required in the first 19 months of the project and 15 for the remainder.