SlideShare une entreprise Scribd logo
1  sur  17
Quality Engineering Development
Summary Updates
By Muhammad Ruzainy Musa
Date: 2011-Feb-22
RENE CORTEZ
(SPONSOR)
KAREN WOON
(MENTOR)
RUZAINY
MAINTENANCE
TEAM
ENGINEERING
TEAM
PRODUCTION
TEAM
TEAM STRUCTURE
TITLE: Quality Engineering Development Summary Updates. Mentor: Karen Woon
JULY AUG SEPT OCT NOV DEC JAN FEB
 
Introduction of QA Organization Chart & QE jobs and 
responsibility.
 
             
QUALITY ALERT
 
 
           
Defect Potential Assessment (DPA)
               
INTERNAL QUALITY ISSUE
 
 
           
Material review board (MRB)
               
Non-conformance report (NCR)
     
 
       
Voice of process (VOP)
               
CUSTOMER COMPLAINT
               
Voice of Customer (VOC)
 
 
           
Design of experiment (DOE)
               
AUDIT
               
TI BOAC Fan-out
         
 
   
MAXIM wire bond (broken stitch)  Fan-out
             
 
TRAINING
               
TSDC - Wirebond training
 
             
Problem solving technique
         
 
   
FMEA 4th Edition
       
 
   
 
SPC- Method 1
QUALITY ALERT
Defect Potential Assessment - FMEA Approach (Do differently)
- Receive/acknowledge
- Do containment actions
- Examine the unit, it’s “failure mode & mechanism”
- Generate Quality Alert OPL (with Photo of Defect & details)
- Discuss in DBS the Quality Alert issue with the Line team
(Sensitize to detect it, containment, prevent escape).
- Validate Containment implementation & effectiveness.
VOC Rec’d
Samples 
Validation
Containment  
3D
Defect Potential 
Assessment
Root cause 
Validation
CAPA Validation
Voice of Customer (VOC)
• Receive complaint and provide 8D report.
• Quality issue assign by Customer.
• Coordinate the complaint with the respective team member within 7 calendar days.
CUSTOMER QUALITY ISSUE
SKYWORKS/ SIGE
• Depress wire
• Material without label and ESD bag
TIM
• Foreign Material on die
• Oxide Layer Fault - Invalidate
• Ball short to metal
• Abnormal Mark - Invalidate
• Mold flash
• Package contamination
SITIME • Lifted Bond
ELMOS
• Delamination
• Wafer map offset picking
• Misalignment Marking
• Burrs on terminals, Epoxy height - Invalidate
• Top side chipping & Back side chipping
MAXIM • Broken wedge
MELEXIS • Different size tube
TAO
• Color filter void - DOE
• Sticky wafer ring - DOE
CUSTOMER COMPLAINT
Receive complaint
D0: Review current OCAP & FMEA
D1: Team Member
D2: Background/ FA analysis
D3: Containment Actions
D4: Fishbone analysis / Fault
tree analysis
D5: Permanent corrective
action plan
D6: Verification of
effectiveness
D7: Prevent recurrence
D8: Congratulate team
8D Format flow
CUSTOMER COMPLAINT
Cust Ref# / Date code
/ Package
Problem description Root cause / finding Action taken
Carsem Reference # :
ALPCML111101-1
Package type / Part
description :
MLPQ2.3X2.3_X1A
Part Date Code : 1121
Feedback from Skyworks end customer, Samsung on
the SKY13397. 2 units show crushed wires that
passed the original ATE test, but then failed after the
customer reflow. Three SKY13397-11 devices were
sent for Failure Analysis. The devices reportedly
failed for having shorted VBAT to GND.
Two devices (S/N 1, S/N 2) had bond wire mechanical
damage resulting in short circuit from VDD to GND
on the die. The short was relieved when the devices
were decapsulated and they were then normal.
Device S/N 3
had electrical damage (EOS) on the OUT1A
transistor. The electrical damage was the closest
channel to the IN1
connection, indicating that there may have been EOS
applied to IN1 Pin.
Lot details
Carsem Lot : ALP*E-J104ZFT-01F7
MES ID : S201114022002-01
Device : EN13397-388LF-1
Package : MLPQ2.3X2.3_X1A
Lot Quantity : 5560 units
Technician accidentally hit the wires of
defective units when
removing jammed lead-frame from machine
track of wire bond.
To establish a proper lead-frame handling procedure for
removing jammed lead-frame from machine track by
pushing the lead-frame at bottom of lead-frame rail.
Resp : BT Chong
Date : 2011 Nov 21
Status : Done
2. To define jammed lead-frame as critical event at wire
bond operation and update in wire bond spec to alert 3rd
optical operator to perform 100% inspection for the
affected strip. ( QCG000013)
Resp : CK Yiow
Date : 2011 Nov 21
Status : Done
3. To study machine indexer track sensitivity to improve
lead frame jam incident.
Resp : Dalmeet
Date : 2011 Nov 25
Status : Done. Please refer attachment on the
improvement study.
4. Conduct training for item 1 & 2.
Resp : BT Chong/CK Yiow
Date : 2011 Nov 30
Status : Done. Brief to all the process tech for 3 shifts.
1
2
Jammed Leadframe
Improvement.ppt
Briefing List
ALPCML111101-1.jpg
- Tweezer cross on the bond ball
(Similar to the complaint unit)
Handling!!!
CUSTOMER COMPLAINT
SIT SIMULATION
RESULT.PPT
Machine!!!
CUSTOMER COMPLAINT
Cust Ref# / Date code
/ Package
Problem description Root cause / finding Action taken
Carsem Reference # :
ALPCML111101-1
Package type / Part
description :
MLPQ2.3X2.3_X1A
Part Date Code / : 1121
Maxim Test feedback on lot # SDJTBBX that
encountered low yield during set-up. It was only
yielding 66% with contact open. Rejects were also
verified valid using hand test socket. 5 sample units
were submitted to FA for analysis. Out of the 5
units, 1 unit was decapsulated for internal wire
dressing assessment. Broken wedge was found on
this decapsulated unit.
Affected Lot Details
Device/Pkg : MAX8686ETL+, 40L 6x6 TQFN
Failure rate : 66%
Lot numbers : SDJTBB
Datecode : 1150
Combination factors which includes steep
landing angle, with high end parameters
and bonding sequence.
Possible – Based on the simulations results
a similar signature crack on the affected
pins was produced, the crack tends to
further worsen and break when adjacent
unit (leads with multiple bonding) are
bonded.
Steep landing angle on 2nd bond
1) Optimize the looping profile/parameter to minimize
trajectory/landing angle. This will lessen the
concentration of stress at the heel of the stitch that
causes broken stitch.
Responsible : BT Chong
Status : On-going (actual dies will be required)
3) To update spec ASYML3101 FMEA.
Responsible : BT Chong
Status : On-going
Date : Upon completion items D5.1 & D5.2.
To perform DOE plan to study and understand the steep
landing angle / looping profile with relation to crack /
broken wedge on lead and also to put in related controls
to prevent crack / broken wedge.
Responsible: Prem Chand/BT Chong
Status: On-going. DOE plan just drafted and awaiting for
the arrival of dices from customer to start up. Refer the
attached preliminary DOE plan as attached below. For
the DOE run estimated qty required are 790 units.
Method!!!
CUSTOMER COMPLAINT
Design Of Experiment
• To involved in proactively reducing variation and eliminating defects
• Formal way of maximizing information gained while resources required.
• A series of structured tests are designed in which planned changes are made to the input
variables of a process or system.
• The effects of these changes on a pre-defined output are then assessed.
TAO - color filter void
Design Of Experiment
TAO - Drop test
simulation on
the packaging
DOE result:
AUDIT
• Performed to ascertain the validity and reliability of information or control in the MLP line.
• Also to provide an assessment of a system’s internal control.
• Conducted several customer audit :
 TIM – BOAC wafer fan-out
 Maxim – Broken stitch fan-out
Carsem Response
TIM – BOAC wafer fan-out
AUDIT FAN OUT ITEM
FAN OUT ACTIONS
DESCRIPTION OF BEST PRACTICES
Items
CARSEM
(Elias / Anselm)
1. Tighten Lead Placement Requirement
Requirement - No bond allowed on half etch area. Bond must be placed on center of the effective solid part of the lead.
Actions:
a. Sub must implement Video Lead Locator (VLL) or any
equivalent lead locator feature of the bonder to improve the
machine detection on the wedge placement centering during
wire bond process.
1
Carsem Practise:
During 1st time programing (Master recipe generated), technician need to visually confirm that the
wedge placement is at the center of the lead finger.
When the golden recipe downloaded from RMS (recipe management system, the wedge placement
location is limited to have 2mil tolerance for adjustment (control under parameter "bond point
tolerance").
The downloaded program pattern need to be align back to the actual leadframe location using the
leadframe alignment points. (Top left connection bar & Bottom right connection bar)
b. Sub must define the effective solid part of the lead for
bonding (no half etch) per package code/leadframe type.
Include actual drawing and X-ray shots.
2
During setup, technician will visually confirm the wedge location located on the center of the lead.
Note: Carsem MLP is using etch leadframe, once the wedge placement is program at the center, the
wedge place can be control within 1 mil.
c. Each bonding diagram must be reviewed and revised to
show effective bonding area and the correct lead placement.
3
Carsem had set a guideline for the maximum wire that a lead can support / allow based on the lead
length.
d. Sub must define controls to ensure the requirement is met
during machine set-up, machine repair, device change,
capillary change, or when changes are made to already
qualified set-up.
4
For every machine set-up, device change, parameter change & capillary change, ball shear test and
wire pull test are required.
2. Eliminate High Ultrasonic Power Setting at Second Bond
Requirement - high ultrasonic power setting must be avoided to prevent micro vibration or high resonance effect to the bonds that causes bond fatigue (stitch stress marks).
Actions:
a. Sub must review current bonding parameters and revalidate
parameters from RSM DOE performed particularly those that
have high 2nd ultrasonic energy settings.
5
Carsem is using Thermal Compression for all wire sizes. (on 2nd bond / Wedge bond)
Bonding Temperature is 200 ± 0.5 °C
b. RE must audit all parameters and report areas needing
reoptimization to achieve reliable bonds with less ultrasonic
power.
6
c. Submit RSM DOE plan on problem areas.
7
3. Eliminate Steep Loop Trajectory/Steep bond landing
Requirement - Reject any stitch bond that is landing in an angle (steep loop) and will finish with more than 20 deg angle on the
heel of stitch bond to prevent stress related damage . This is prone to bonds that are short.
Actions:
a. Review all bonding diagrams and identify products that are susceptible to steep looping trajectory and verify
actual looping trajectory. Any product what will violate requirement must be validated using actual bonding and
necessary adjustment will be made accordingly.
8 DOE is on going to have the steep looping study.
b. Review and revise assembly design rule spec and incorporate criteria for shortest wire without steep loop
trajectory issue.
9 DOE is on going to have the steep looping study.
4. Revamp SPC on Wirebond Bond Pull Test
Requirement - Change Bond Pull test procedure to include long wires, short wires, corner wires, down/ground bonds, double or
multiple bonds and the wire of adjacent unit opposite them to the samples of wires to be bond pull tested.
Actions:
a. Recalculate LCL and UCL and bring closer to the centerline. Redefine current SPC requirement to include
OCAP on readings that drifted, failed set-up, monitors and inspection.
10
SPC show that the SPC data is within LCL and UCL
for Maxim 2.0mil wire device. Carsem do have OCAP
for SPC OOC situation.
5. Improve Visual Monitor to check quality of the bonds
Requirement - Reject for any stress mark on the stitch bond. Quality monitors and set-up buy-offs must include visual inspection
of the bonds. To check for quality of the stitch bond, inspection at high magnification (200X and above) is a must.
Actions:
a. Reinforce SEM inspection or 200X minimum optical inspection during machine set-up, change of device, change
of wire or changes to already qualified parameter setting.
11
QA do have inspection on wedge formation using
minimum 200X.
6. Implement Lead placement monitor by utilizing X-ray monitor done during mold set-up
Requirement - Reject any bond that is placed on any part of the half etched area of the lead. Utilize the existing mold X-ray
monitor that is currently in place.
Actions:
a. Revise mold monitor spec to include criteria for bond placement in addition to existing criteria for wire sweeping,
internal voids, etc. and frequency of monitor required.
12
Based on current monitoring, Carsem do not monitor
for lead placement. Attach are the criteria that
Carsem monitor at Mold x-ray.b. Define Mold mold monitor - add criteria on lead placement, in addition to wiresweep, voids, etc. Update OCAP
accordingly.
13
AUDIT FAN OUT ITEM
DONE ON-GOING NOT APPLICABLE WITH CONCERNS
7 3 0 2 13
PROCESS FMEA CONVERSION
QA Engineering Roles:
• Coordinate with Process Engineers, Production & Maintenance to establish a Macro-Micro process flow.
• Weekly meeting with team to mitigate the risk of each process step.
• Target completion by end of Mac 2012.
• Weekly Reporting (every Friday) by package lines / process to Quality system engineer.
• QE been assign to follow up on certain process:
PROCESS STATUS SPEC NO. REMARK
Wire bond ~ 30% ASYML3101
Molding ~ 10% ASYML4102
Pick & place ~ 90% ASYML5601
Tape attach 100% ASYML1602
Status:
Completed / Buy-Off Accepted & Released
In-Progress & within schedule / Pending for ECN approval
PROBLEM SOLVING TECHNIQUE
 Identify & select problem
 Understand on the feedback / complaint receive
 Use historical data to look into the trend problem. ( Downtime, Yield, Processing
time)
 Understand and present situation
 Identify root cause
 4M method (Man, Method, Machine & Material)
 Fishbone diagram
 Plan improvement
 Work out solution for potential risk
 Evaluate improvement actions (validation in assy line)
 Execute Improvement
 Confirm results
 Standardize improvement
 Documentation (SOP / Spec)
 FMEA
.Proliferation (Best practices are deployed)
 Future plan
 Monitor the effectiveness of the implementation by Goal PPM / repeated issue.
TRAINING
Benefits /
Gain
Analytical thinking
LeadershipTeam work/ player
Communication skills
SUMMARY
END of PRESENTATION

Contenu connexe

Similaire à GEP presentation-rev1

Jiang huihua Resume
Jiang huihua ResumeJiang huihua Resume
Jiang huihua Resumehuihua Jiang
 
EME 185 Poster
EME 185 PosterEME 185 Poster
EME 185 Postertonygom
 
Lessons Learned of AC Arc Flash Studies for Station Auxiliary Service Systems
Lessons Learned of AC Arc Flash Studies for Station Auxiliary Service SystemsLessons Learned of AC Arc Flash Studies for Station Auxiliary Service Systems
Lessons Learned of AC Arc Flash Studies for Station Auxiliary Service SystemsPower System Operation
 
Results of DigitArc Electrode Regulator and SmartArc power input optimization...
Results of DigitArc Electrode Regulator and SmartArc power input optimization...Results of DigitArc Electrode Regulator and SmartArc power input optimization...
Results of DigitArc Electrode Regulator and SmartArc power input optimization...AMI GE International
 
Jiang huihua Resume
Jiang huihua ResumeJiang huihua Resume
Jiang huihua Resumehuihua Jiang
 
Root Cause Of Piping Failures | COMPRESSORtech2
Root Cause Of Piping Failures | COMPRESSORtech2 Root Cause Of Piping Failures | COMPRESSORtech2
Root Cause Of Piping Failures | COMPRESSORtech2 dieselpub
 
Investigating the Effect of Prestressing CFRP Laminate and Mechanical Anchora...
Investigating the Effect of Prestressing CFRP Laminate and Mechanical Anchora...Investigating the Effect of Prestressing CFRP Laminate and Mechanical Anchora...
Investigating the Effect of Prestressing CFRP Laminate and Mechanical Anchora...IRJET Journal
 
GENOA and HyperWorks Integration for Advance Composite Product Design and Ana...
GENOA and HyperWorks Integration for Advance Composite Product Design and Ana...GENOA and HyperWorks Integration for Advance Composite Product Design and Ana...
GENOA and HyperWorks Integration for Advance Composite Product Design and Ana...Altair
 
2022 Quality Control & Document Design
2022 Quality Control & Document Design2022 Quality Control & Document Design
2022 Quality Control & Document DesignBen Walters
 
SCFT-Training_v8.2-1
SCFT-Training_v8.2-1SCFT-Training_v8.2-1
SCFT-Training_v8.2-1mahesh savita
 
IRJET-Design and Analysis of torque limiter timer belt spindle drive for over...
IRJET-Design and Analysis of torque limiter timer belt spindle drive for over...IRJET-Design and Analysis of torque limiter timer belt spindle drive for over...
IRJET-Design and Analysis of torque limiter timer belt spindle drive for over...IRJET Journal
 
Hcd 70 Split Waveguide
Hcd 70 Split WaveguideHcd 70 Split Waveguide
Hcd 70 Split Waveguideguest36ea6a77
 
WELDLINE STRENGTH ANALYSIS THEORETICAL PREDICTIVE MODEL WITH THE USE OF MOLDL...
WELDLINE STRENGTH ANALYSIS THEORETICAL PREDICTIVE MODEL WITH THE USE OF MOLDL...WELDLINE STRENGTH ANALYSIS THEORETICAL PREDICTIVE MODEL WITH THE USE OF MOLDL...
WELDLINE STRENGTH ANALYSIS THEORETICAL PREDICTIVE MODEL WITH THE USE OF MOLDL...IRJET Journal
 
Failure Analysis, benefits, logistics and limitations
Failure Analysis, benefits, logistics and limitationsFailure Analysis, benefits, logistics and limitations
Failure Analysis, benefits, logistics and limitationsAccendo Reliability
 

Similaire à GEP presentation-rev1 (20)

Jiang huihua Resume
Jiang huihua ResumeJiang huihua Resume
Jiang huihua Resume
 
EME 185 Poster
EME 185 PosterEME 185 Poster
EME 185 Poster
 
Lessons Learned of AC Arc Flash Studies for Station Auxiliary Service Systems
Lessons Learned of AC Arc Flash Studies for Station Auxiliary Service SystemsLessons Learned of AC Arc Flash Studies for Station Auxiliary Service Systems
Lessons Learned of AC Arc Flash Studies for Station Auxiliary Service Systems
 
Results of DigitArc Electrode Regulator and SmartArc power input optimization...
Results of DigitArc Electrode Regulator and SmartArc power input optimization...Results of DigitArc Electrode Regulator and SmartArc power input optimization...
Results of DigitArc Electrode Regulator and SmartArc power input optimization...
 
Jiang huihua Resume
Jiang huihua ResumeJiang huihua Resume
Jiang huihua Resume
 
Integrating Laser Scan Data into FEA Model to Perform Level 3 FFS
Integrating Laser Scan Data into FEA Model to Perform Level 3 FFSIntegrating Laser Scan Data into FEA Model to Perform Level 3 FFS
Integrating Laser Scan Data into FEA Model to Perform Level 3 FFS
 
Root Cause Of Piping Failures | COMPRESSORtech2
Root Cause Of Piping Failures | COMPRESSORtech2 Root Cause Of Piping Failures | COMPRESSORtech2
Root Cause Of Piping Failures | COMPRESSORtech2
 
Mill & Kiln Gear Asset Management
Mill & Kiln Gear Asset ManagementMill & Kiln Gear Asset Management
Mill & Kiln Gear Asset Management
 
Investigating the Effect of Prestressing CFRP Laminate and Mechanical Anchora...
Investigating the Effect of Prestressing CFRP Laminate and Mechanical Anchora...Investigating the Effect of Prestressing CFRP Laminate and Mechanical Anchora...
Investigating the Effect of Prestressing CFRP Laminate and Mechanical Anchora...
 
ahsan elahi CV3
ahsan elahi CV3ahsan elahi CV3
ahsan elahi CV3
 
GENOA and HyperWorks Integration for Advance Composite Product Design and Ana...
GENOA and HyperWorks Integration for Advance Composite Product Design and Ana...GENOA and HyperWorks Integration for Advance Composite Product Design and Ana...
GENOA and HyperWorks Integration for Advance Composite Product Design and Ana...
 
FEA Based Level 3 Assessment of Deformed Tanks
FEA Based Level 3 Assessment of Deformed TanksFEA Based Level 3 Assessment of Deformed Tanks
FEA Based Level 3 Assessment of Deformed Tanks
 
2022 Quality Control & Document Design
2022 Quality Control & Document Design2022 Quality Control & Document Design
2022 Quality Control & Document Design
 
SCFT-Training_v8.2-1
SCFT-Training_v8.2-1SCFT-Training_v8.2-1
SCFT-Training_v8.2-1
 
IRJET-Design and Analysis of torque limiter timer belt spindle drive for over...
IRJET-Design and Analysis of torque limiter timer belt spindle drive for over...IRJET-Design and Analysis of torque limiter timer belt spindle drive for over...
IRJET-Design and Analysis of torque limiter timer belt spindle drive for over...
 
Hcd 70 Split Waveguide
Hcd 70 Split WaveguideHcd 70 Split Waveguide
Hcd 70 Split Waveguide
 
Notes for scft
Notes for scftNotes for scft
Notes for scft
 
Ken Lee: 2013 Sandia National Laboratoies Wind Plant Reliability Workshop
Ken Lee: 2013 Sandia National Laboratoies Wind Plant Reliability WorkshopKen Lee: 2013 Sandia National Laboratoies Wind Plant Reliability Workshop
Ken Lee: 2013 Sandia National Laboratoies Wind Plant Reliability Workshop
 
WELDLINE STRENGTH ANALYSIS THEORETICAL PREDICTIVE MODEL WITH THE USE OF MOLDL...
WELDLINE STRENGTH ANALYSIS THEORETICAL PREDICTIVE MODEL WITH THE USE OF MOLDL...WELDLINE STRENGTH ANALYSIS THEORETICAL PREDICTIVE MODEL WITH THE USE OF MOLDL...
WELDLINE STRENGTH ANALYSIS THEORETICAL PREDICTIVE MODEL WITH THE USE OF MOLDL...
 
Failure Analysis, benefits, logistics and limitations
Failure Analysis, benefits, logistics and limitationsFailure Analysis, benefits, logistics and limitations
Failure Analysis, benefits, logistics and limitations
 

GEP presentation-rev1

  • 1. Quality Engineering Development Summary Updates By Muhammad Ruzainy Musa Date: 2011-Feb-22
  • 3. TITLE: Quality Engineering Development Summary Updates. Mentor: Karen Woon JULY AUG SEPT OCT NOV DEC JAN FEB   Introduction of QA Organization Chart & QE jobs and  responsibility.                 QUALITY ALERT                 Defect Potential Assessment (DPA)                 INTERNAL QUALITY ISSUE                 Material review board (MRB)                 Non-conformance report (NCR)                 Voice of process (VOP)                 CUSTOMER COMPLAINT                 Voice of Customer (VOC)                 Design of experiment (DOE)                 AUDIT                 TI BOAC Fan-out                 MAXIM wire bond (broken stitch)  Fan-out                 TRAINING                 TSDC - Wirebond training                 Problem solving technique                 FMEA 4th Edition                 SPC- Method 1
  • 4. QUALITY ALERT Defect Potential Assessment - FMEA Approach (Do differently) - Receive/acknowledge - Do containment actions - Examine the unit, it’s “failure mode & mechanism” - Generate Quality Alert OPL (with Photo of Defect & details) - Discuss in DBS the Quality Alert issue with the Line team (Sensitize to detect it, containment, prevent escape). - Validate Containment implementation & effectiveness. VOC Rec’d Samples  Validation Containment   3D Defect Potential  Assessment Root cause  Validation CAPA Validation
  • 5. Voice of Customer (VOC) • Receive complaint and provide 8D report. • Quality issue assign by Customer. • Coordinate the complaint with the respective team member within 7 calendar days. CUSTOMER QUALITY ISSUE SKYWORKS/ SIGE • Depress wire • Material without label and ESD bag TIM • Foreign Material on die • Oxide Layer Fault - Invalidate • Ball short to metal • Abnormal Mark - Invalidate • Mold flash • Package contamination SITIME • Lifted Bond ELMOS • Delamination • Wafer map offset picking • Misalignment Marking • Burrs on terminals, Epoxy height - Invalidate • Top side chipping & Back side chipping MAXIM • Broken wedge MELEXIS • Different size tube TAO • Color filter void - DOE • Sticky wafer ring - DOE CUSTOMER COMPLAINT Receive complaint D0: Review current OCAP & FMEA D1: Team Member D2: Background/ FA analysis D3: Containment Actions D4: Fishbone analysis / Fault tree analysis D5: Permanent corrective action plan D6: Verification of effectiveness D7: Prevent recurrence D8: Congratulate team 8D Format flow
  • 6. CUSTOMER COMPLAINT Cust Ref# / Date code / Package Problem description Root cause / finding Action taken Carsem Reference # : ALPCML111101-1 Package type / Part description : MLPQ2.3X2.3_X1A Part Date Code : 1121 Feedback from Skyworks end customer, Samsung on the SKY13397. 2 units show crushed wires that passed the original ATE test, but then failed after the customer reflow. Three SKY13397-11 devices were sent for Failure Analysis. The devices reportedly failed for having shorted VBAT to GND. Two devices (S/N 1, S/N 2) had bond wire mechanical damage resulting in short circuit from VDD to GND on the die. The short was relieved when the devices were decapsulated and they were then normal. Device S/N 3 had electrical damage (EOS) on the OUT1A transistor. The electrical damage was the closest channel to the IN1 connection, indicating that there may have been EOS applied to IN1 Pin. Lot details Carsem Lot : ALP*E-J104ZFT-01F7 MES ID : S201114022002-01 Device : EN13397-388LF-1 Package : MLPQ2.3X2.3_X1A Lot Quantity : 5560 units Technician accidentally hit the wires of defective units when removing jammed lead-frame from machine track of wire bond. To establish a proper lead-frame handling procedure for removing jammed lead-frame from machine track by pushing the lead-frame at bottom of lead-frame rail. Resp : BT Chong Date : 2011 Nov 21 Status : Done 2. To define jammed lead-frame as critical event at wire bond operation and update in wire bond spec to alert 3rd optical operator to perform 100% inspection for the affected strip. ( QCG000013) Resp : CK Yiow Date : 2011 Nov 21 Status : Done 3. To study machine indexer track sensitivity to improve lead frame jam incident. Resp : Dalmeet Date : 2011 Nov 25 Status : Done. Please refer attachment on the improvement study. 4. Conduct training for item 1 & 2. Resp : BT Chong/CK Yiow Date : 2011 Nov 30 Status : Done. Brief to all the process tech for 3 shifts. 1 2 Jammed Leadframe Improvement.ppt Briefing List ALPCML111101-1.jpg - Tweezer cross on the bond ball (Similar to the complaint unit) Handling!!!
  • 8. CUSTOMER COMPLAINT Cust Ref# / Date code / Package Problem description Root cause / finding Action taken Carsem Reference # : ALPCML111101-1 Package type / Part description : MLPQ2.3X2.3_X1A Part Date Code / : 1121 Maxim Test feedback on lot # SDJTBBX that encountered low yield during set-up. It was only yielding 66% with contact open. Rejects were also verified valid using hand test socket. 5 sample units were submitted to FA for analysis. Out of the 5 units, 1 unit was decapsulated for internal wire dressing assessment. Broken wedge was found on this decapsulated unit. Affected Lot Details Device/Pkg : MAX8686ETL+, 40L 6x6 TQFN Failure rate : 66% Lot numbers : SDJTBB Datecode : 1150 Combination factors which includes steep landing angle, with high end parameters and bonding sequence. Possible – Based on the simulations results a similar signature crack on the affected pins was produced, the crack tends to further worsen and break when adjacent unit (leads with multiple bonding) are bonded. Steep landing angle on 2nd bond 1) Optimize the looping profile/parameter to minimize trajectory/landing angle. This will lessen the concentration of stress at the heel of the stitch that causes broken stitch. Responsible : BT Chong Status : On-going (actual dies will be required) 3) To update spec ASYML3101 FMEA. Responsible : BT Chong Status : On-going Date : Upon completion items D5.1 & D5.2. To perform DOE plan to study and understand the steep landing angle / looping profile with relation to crack / broken wedge on lead and also to put in related controls to prevent crack / broken wedge. Responsible: Prem Chand/BT Chong Status: On-going. DOE plan just drafted and awaiting for the arrival of dices from customer to start up. Refer the attached preliminary DOE plan as attached below. For the DOE run estimated qty required are 790 units. Method!!!
  • 9. CUSTOMER COMPLAINT Design Of Experiment • To involved in proactively reducing variation and eliminating defects • Formal way of maximizing information gained while resources required. • A series of structured tests are designed in which planned changes are made to the input variables of a process or system. • The effects of these changes on a pre-defined output are then assessed. TAO - color filter void
  • 10. Design Of Experiment TAO - Drop test simulation on the packaging DOE result:
  • 11. AUDIT • Performed to ascertain the validity and reliability of information or control in the MLP line. • Also to provide an assessment of a system’s internal control. • Conducted several customer audit :  TIM – BOAC wafer fan-out  Maxim – Broken stitch fan-out Carsem Response TIM – BOAC wafer fan-out
  • 12. AUDIT FAN OUT ITEM FAN OUT ACTIONS DESCRIPTION OF BEST PRACTICES Items CARSEM (Elias / Anselm) 1. Tighten Lead Placement Requirement Requirement - No bond allowed on half etch area. Bond must be placed on center of the effective solid part of the lead. Actions: a. Sub must implement Video Lead Locator (VLL) or any equivalent lead locator feature of the bonder to improve the machine detection on the wedge placement centering during wire bond process. 1 Carsem Practise: During 1st time programing (Master recipe generated), technician need to visually confirm that the wedge placement is at the center of the lead finger. When the golden recipe downloaded from RMS (recipe management system, the wedge placement location is limited to have 2mil tolerance for adjustment (control under parameter "bond point tolerance"). The downloaded program pattern need to be align back to the actual leadframe location using the leadframe alignment points. (Top left connection bar & Bottom right connection bar) b. Sub must define the effective solid part of the lead for bonding (no half etch) per package code/leadframe type. Include actual drawing and X-ray shots. 2 During setup, technician will visually confirm the wedge location located on the center of the lead. Note: Carsem MLP is using etch leadframe, once the wedge placement is program at the center, the wedge place can be control within 1 mil. c. Each bonding diagram must be reviewed and revised to show effective bonding area and the correct lead placement. 3 Carsem had set a guideline for the maximum wire that a lead can support / allow based on the lead length. d. Sub must define controls to ensure the requirement is met during machine set-up, machine repair, device change, capillary change, or when changes are made to already qualified set-up. 4 For every machine set-up, device change, parameter change & capillary change, ball shear test and wire pull test are required. 2. Eliminate High Ultrasonic Power Setting at Second Bond Requirement - high ultrasonic power setting must be avoided to prevent micro vibration or high resonance effect to the bonds that causes bond fatigue (stitch stress marks). Actions: a. Sub must review current bonding parameters and revalidate parameters from RSM DOE performed particularly those that have high 2nd ultrasonic energy settings. 5 Carsem is using Thermal Compression for all wire sizes. (on 2nd bond / Wedge bond) Bonding Temperature is 200 ± 0.5 °C b. RE must audit all parameters and report areas needing reoptimization to achieve reliable bonds with less ultrasonic power. 6 c. Submit RSM DOE plan on problem areas. 7
  • 13. 3. Eliminate Steep Loop Trajectory/Steep bond landing Requirement - Reject any stitch bond that is landing in an angle (steep loop) and will finish with more than 20 deg angle on the heel of stitch bond to prevent stress related damage . This is prone to bonds that are short. Actions: a. Review all bonding diagrams and identify products that are susceptible to steep looping trajectory and verify actual looping trajectory. Any product what will violate requirement must be validated using actual bonding and necessary adjustment will be made accordingly. 8 DOE is on going to have the steep looping study. b. Review and revise assembly design rule spec and incorporate criteria for shortest wire without steep loop trajectory issue. 9 DOE is on going to have the steep looping study. 4. Revamp SPC on Wirebond Bond Pull Test Requirement - Change Bond Pull test procedure to include long wires, short wires, corner wires, down/ground bonds, double or multiple bonds and the wire of adjacent unit opposite them to the samples of wires to be bond pull tested. Actions: a. Recalculate LCL and UCL and bring closer to the centerline. Redefine current SPC requirement to include OCAP on readings that drifted, failed set-up, monitors and inspection. 10 SPC show that the SPC data is within LCL and UCL for Maxim 2.0mil wire device. Carsem do have OCAP for SPC OOC situation. 5. Improve Visual Monitor to check quality of the bonds Requirement - Reject for any stress mark on the stitch bond. Quality monitors and set-up buy-offs must include visual inspection of the bonds. To check for quality of the stitch bond, inspection at high magnification (200X and above) is a must. Actions: a. Reinforce SEM inspection or 200X minimum optical inspection during machine set-up, change of device, change of wire or changes to already qualified parameter setting. 11 QA do have inspection on wedge formation using minimum 200X. 6. Implement Lead placement monitor by utilizing X-ray monitor done during mold set-up Requirement - Reject any bond that is placed on any part of the half etched area of the lead. Utilize the existing mold X-ray monitor that is currently in place. Actions: a. Revise mold monitor spec to include criteria for bond placement in addition to existing criteria for wire sweeping, internal voids, etc. and frequency of monitor required. 12 Based on current monitoring, Carsem do not monitor for lead placement. Attach are the criteria that Carsem monitor at Mold x-ray.b. Define Mold mold monitor - add criteria on lead placement, in addition to wiresweep, voids, etc. Update OCAP accordingly. 13 AUDIT FAN OUT ITEM DONE ON-GOING NOT APPLICABLE WITH CONCERNS 7 3 0 2 13
  • 14. PROCESS FMEA CONVERSION QA Engineering Roles: • Coordinate with Process Engineers, Production & Maintenance to establish a Macro-Micro process flow. • Weekly meeting with team to mitigate the risk of each process step. • Target completion by end of Mac 2012. • Weekly Reporting (every Friday) by package lines / process to Quality system engineer. • QE been assign to follow up on certain process: PROCESS STATUS SPEC NO. REMARK Wire bond ~ 30% ASYML3101 Molding ~ 10% ASYML4102 Pick & place ~ 90% ASYML5601 Tape attach 100% ASYML1602 Status: Completed / Buy-Off Accepted & Released In-Progress & within schedule / Pending for ECN approval
  • 15. PROBLEM SOLVING TECHNIQUE  Identify & select problem  Understand on the feedback / complaint receive  Use historical data to look into the trend problem. ( Downtime, Yield, Processing time)  Understand and present situation  Identify root cause  4M method (Man, Method, Machine & Material)  Fishbone diagram  Plan improvement  Work out solution for potential risk  Evaluate improvement actions (validation in assy line)  Execute Improvement  Confirm results  Standardize improvement  Documentation (SOP / Spec)  FMEA .Proliferation (Best practices are deployed)  Future plan  Monitor the effectiveness of the implementation by Goal PPM / repeated issue. TRAINING
  • 16. Benefits / Gain Analytical thinking LeadershipTeam work/ player Communication skills SUMMARY