BEDC
Irrua Service Units
Monthly Performance Review
Sessions’ Framework
July, 2015.
Objectives of the Presentation
 To highlight basic performance indices of the Service unit
 To highlight various challenges that affected the Service unit in the review
period
 To highlight strategies adopted for the achievement of planned
performance
Table of Content
Objectives of the Presentation
Part 1: Introduction
Part 2: Balance Score Card Perspectives
 Financial Perspective
 Customer Perspective
 Internal Processes Perspective
 Learning & Growth
Part 3: Conclusion
Questions & Answers
Part 1 : Introduction
 Service Unit’s Name: Irrua Business Unit: uromi State:Edo
 Area of Operation’s Coverage
[The Service Unit Covers ...........number of Local Governments Areas in ..............State,
namely; ....................................with total area of ...............1km2]
SERVICE
CENTRE
LOCATIONS
LOCAL
GOVERNMENT
HOUSEHOLD
POPULATIO
N
NO OF COMMUNITIES SERVED
TOTAL CUSTOMER
POPULATION
Bulk Billed
Non Bulk
Billed
TOTAL
Metered Unmetered
OPOJI IRRUA ESAN
CENTRAL
596 1 2 3 557
EWU IRRUA ESAN
CENTRAL
2418 3 3 1836
IRRUA IRRUA ESAN
CENTRAL
2870 2 2 2662
PPM IRRUA ESAN
CENTRAL
75
TOTAL 5884 1 7 8 5132
Energy to Collection Highlights
Part 2:
Financial Perspective
Service
Unit
Customer
Population
Energy Input
(MWH)
Cost of Energy
(N’million)
Energy Billed
(MWh)
Amount Billed
(N’million)
Amount
Collected
(N’million)
Total
Outstanding
Debt (N’million)
ATC & C
Losses (%)
A B C D E F G H = 1 - N
Irrua May-15 5105 924948 21353388.52565232 13203800.91 7079553 162367785 67.2
Jun-15
5132 1004498 26254641.39741041 17497690.11 9058328.05 182192473.00 62.98
Jul-15 4208 1202398.78 28300645.18625656 14854598.39 11231940.71 128655294.39 60.66
Number of
Book
No of
Customer
Response
Outstanding as at
previous month
(N’ million)
% Cost of
Energy
Collected
Billing Efficiency
(%)
Marketing
Efficiency (%)
Collection
Efficiency (%)
Debt Recovery
Index
(%)
ATC & C
Losses
(Naira)
I J K L = ( F/C)* 100 M = (D/B) * 100 N = M * O O = (F/E) * 100
P = { (K - G)/K) *
100
Q = H * C
May-15 48
993 154674604.3 33.15 61.11 32.77 53.62 -4.92 14349477.09
Jun-15 48
1716 171915621.99 34.573.77 38.19 51.77 -5.98 15412686.87
Jul-15 48
2095 182192473.00 39.6952.03 39.34 75.61 29.39 17166828.6
Financial Perspective
Service
Unit
Customer
Type
Amount Billed (N’million)
Cash collected from Current
billing (N’million)
Collection from Outstanding
Debt (N’million)
% of cash collected from Amount
billed
May-15 Jun-15 Jul-15 May-15 Jun-15 Jul-15 May-15 Jun-15 Jul-15 May-15 Jun-15 Jul-15
irrua
MD
3421695.
62
348596
8.41
3530729.
31
3904865.
05
3639685.
05
3839661.
18 - - - 114.12 104.41 108.75
Prime
404591.1
9
454707.
74
528557.1
4
365455.0
0
322090.0
0
323650.0
0 - - - 90.33 70.83 61.23
Non-MD
1320380
0.91
135570
13.96
10795311
.94
2809233.
00
4909200.
00
7068629.
73 - - - 21.28 36.21 65.48
Total
1703008
7.7
174976
90.11
14854598
.39
7079553.
05
9058328.
05
1123194
0.91 - - - 41.57 51.77 75.61
Financial Perspective
STRATEGIES AND PROPOSED CASH COLLECTION PLAN TO COVER THE GAP
•946 Nos Nmd Customers will pay 2.9m in the next two two weeks.
•10 Nos Md customers will pay 2.6m in the next two weeks.
•30 Nos Pmd customers will pay 450,000.00 in the next two weeks.
•Customers response will improve henceforth.
GAP ANALYSIS AND STRATEGIES
Month Total Cash Collection
Gaps before the Review
Month (from Jan 2015)
(N’million)
Review
Month Cash
Collection
(N’million)
Review Month
Cash
Collection
Target
(N’million)
Review Month
Cash
Collection
Shortfall
(N’million)
Present Month
Cash
Collection as
at Date
(N’million)
Present
Month Cash
Collection
Target
(N’million)
Present Month
Cash Collection
Shortfall as at
Date (N’million)
Cash
Collection Gap
as at Date
(N’million)
Outstandin
g Debt
Balance
(N’million)
A B C D = C - A E F G = F - E H = A+D + G I
May-15 46262911.10 7079553.05 21353388.52 24909523.00 776080 21353388.5
2
20577308.50 41930696.6 1623677
85.21
Jun-15 61675579.96 9058328.05 26254641.39 35420957.00 3098315.00 28300645.1
8
25202330.2 51456971.00 1821924
73.00
Jul-15 78744302.23 11231940.9
1
28300645.18 -33374953 327365 31444252.9
7
31116888 59417533.00 1286552
94.39
Customer Base Overview for the Month: Performance with Period Comparative
Customer Perspective
SERVIC
E UNIT
CUSTO
MER
TYPE
UNMETERED CUSTOMER PRE-PAID CUSTOMER READ CUSTOMER MINIMUM BILLING ESTIMATED CUSTOMER
May-15 Jun-15 Jul-15 May-15 Jun-15 Jul-15 May-15 Jun-15 Jul-15 May-15 Jun-15 Jul-15 May-15 Jun-15 Jul-15
SUMMARY OF CUSTOMER BASE
irrua MD 3 3 3 - - - 9 10 8 2 1 3 - - -
PRIME 20 19 19 - - 15 15 14 11 12 13 - - -
NON-
MD
609 608 386 66 75 75 1194 962 1020 641 740 631 2535 2687 2036
SUMMARY OF ENERGY BILLED (MWH)
irrua MD
13287
0
134952 135909
PRIME 17395 14638 17153 BREAK DOWN NOT AVAILAB LE
NON-
MD
56523
2
591416 47259
4
SUMMARY OF AMOUNT BILLED (N’million)
irrua MD
34216
95.62
348596
8.41
353072
9.3
PRIME
40459
1.91
454707
.74
52855
7.14
BREAK DOWN NOT AVAILAB LE
NON-
MD
13203
800.00
135670
13.96
10795
311.94
July-15 Customer Base Overview for the Month: Performance with Period Comparative
Customer Perspective
CUSTOMER
TYPE
NUMBER OF
BILL
PRINTED
NUMBER OF
DELIVERED
BILLS
NUMBER OF
UNDELIVERED
BILLS
REASONS FOR NON-DELIVERY OF BILLS
REASON 1 LDNP and
failed S/s.
REASON 2 PPM, OTHERS REASON 3
COUNT % COUNT % COUNT %
MD 14 12 2 2 100 - - - -
PRIME 46 40 6 6 100 - - - -
NON-MD 4148 3780 368 300 81.52 68 18.48 - -
Service Unit Customer type Customer Population % Population
MD 14 0.33
Prime 46 1.09
Non-MD 4073 96.79
Pre-Paid 75 1.78
Total 4208 100
Customer Perspective
ILLEGAL CUSTOMER CAPTURED
Service
Unit
May -15 CAPTURED CUSTOMER Jun -15 CAPTURED CUSTOMER Jul -15 CAPTURED CUSTOMER
Count
Amount Billed
(₦’Thousand)
Amount paid
(₦’Thousand)
Count
Amount Billed
(₦’Thousand)
Amount paid
(₦’Thousand)
Count
Amount Billed
(N’Thousand)
Loss of Revenue
Charged
(₦’Thousand)
Loss of Revenue
Paid
(₦’Thousand)
84 357,638.65 323,262.42 18 79,998.03 10,000.00 2,000.
00
75456.09 50,000.00 2000.00
NEW SERVICE CONNECTION
RECLASSIFICATION
Service Unit
Credit Customer Pre-paid Customer
May-15 Jun-15 Jul-15 May-15 Jun-15 Jul-15
Business Unit
Number of
Reclassification
Done May-15 Jun-15 Jul-15
18 10 18 66 75 75 UROMI - - - -
Service Unit
Month
CUSTOMER COMPLAINTS
Billing Issues Metering Issues Supply Issues Average
Resolution
Time
Count No Resolved
Response
Rate
Count No Resolved
Response
Rate
Count No Resolved
Response
Rate
May -15 14 12 85.71 11 9 81.81 25 19 76.00
Jun -15 16 15 93.75 II 9 81.82 19 16 84.21 -
Jul -15 14 10 71.43 6 4 66.66 24 18 75.00 -
Customer Perspective
KEY CUSTOMERS ISSUES & EXPERIENCE IMPROVEMENT STRATEGIES
CUSTOMER
PERSPECTIVE
IDENTIFIED ISSUES & CONSTRAINTS STRATEGIES TO IMPROVE CUSTOMERS EXPERIENCE
BANK PAYMENT CHALLENGES. THE SERVICE UNIT
HAS JUST ONE BANK AVAILABLEBBBBANK
ENCOURAGEMENT OF BANK MANAGERS TO
ENSURE POSTING OF PAYMENTS MADE**
HOSTILITY AND ILLEGAL RECONNECTION BY
DISCONNECTED CUSTOMER.
MONITORS DISCONNECTED CUSTOMER AND
ENLIGHTEMENT OF CUSTOMERS
Customer Perspective
July 2015 Customer Population Gap Analysis
Customer Population Household Population Population Gap Strategies and Proposed Plan to Cover the Gap
A B C = B-A D
4208 5884 1676
CONSTANT CAPTURING OF ILLEGAL CUSTOMERS IN OUR
NETWORK
July 2015 MD and Prime Population Gap Analysis
MD Pop.
MD % Pop.
to the Total
Popn
MD %
Pop.
Target
MD %
Pop. Gap
Prime
Pop.
Prime % Pop.
to the Total
Pop.
Prime %
Pop.
Target
Prime %
Pop. Gap
Strategies and Proposed Plan to Cover the
Gaps
E F = (E/A) * 100 G = 1% H = G- F I J = (I/A) * 100 K = 5% L =K- J M
14 0.33 1.00% 0.67 46 1.09 5% 3.91
WE HOPE TO INTENSIFY OUR EFFORT ON
RECLASSIFICATION
July 2015 Metering Gap Analysis
Number of metered Customer Metering Gap Strategies and Proposed Plan to Cover the Gap
N O = A-N P
1689 2519
THE LIFTING OF EMBARGO ON METER PROCESSING WILL ENCOURAGE CUSTOMERS TO
PAY FOR METERS HENCEFORTH
GAP ANALYSIS AND STRATEGIES
Safety Reports
SAFETY REPORTS
Service Unit Month
No of Safety talk
done
No of Near Misses
No of Minor
Incidence
No of Major
Incidence/Fatality
Total No of
Incidents/
Accidents
Causes of major
Accidents
May -15 1 - - - - -
Jun -15 1 - - - - -
Jul -15 1 - - - - -
Staff Distribution
Department Total No of Staff
No of Staff
Service Unit
Office
Service Centre Fault Centre Cash Offices
Distribution 6 4 2
Marketing/Commercial 1 1
Financial & Account
HR/Admin
Customer Care
Corporate Affairs
Store
TOTAL 7 5 2
Part 3: Conclusion
 The service unit looks forward to a better
improvement on its value to business on monthly
basis. So help us Lord.
Questions & Answers
 Open Floor Question & Answers from the Floor

More Related Content

Similar to MOSES 2.ppt

Director's Report
Director's ReportDirector's Report
Director's Reportjo bitonio
 
Factory Monthly ACCL (U-3&4).ppt
Factory Monthly ACCL (U-3&4).pptFactory Monthly ACCL (U-3&4).ppt
Factory Monthly ACCL (U-3&4).pptNittamallik216
 
Evaluation of Service Performance & Analysis of Scope of Market
Evaluation of Service Performance & Analysis of Scope of MarketEvaluation of Service Performance & Analysis of Scope of Market
Evaluation of Service Performance & Analysis of Scope of MarketSarvajeet Halder
 
PNB Analyst presentation Mar`22 (3).pdf
PNB Analyst presentation Mar`22 (3).pdfPNB Analyst presentation Mar`22 (3).pdf
PNB Analyst presentation Mar`22 (3).pdfEVERESTANALYTICALSME
 
Fiscal Year-ending March 2015 Briefing on the Results for the Second Quarter
Fiscal Year-ending March 2015 Briefing on the Results for the Second  QuarterFiscal Year-ending March 2015 Briefing on the Results for the Second  Quarter
Fiscal Year-ending March 2015 Briefing on the Results for the Second QuarterRicohLease
 
financialsnapshot
financialsnapshotfinancialsnapshot
financialsnapshotfinance14
 
Business Plan Case Study 22 May 2016 v1
Business Plan Case Study 22 May 2016 v1Business Plan Case Study 22 May 2016 v1
Business Plan Case Study 22 May 2016 v1CA. MOHIT MAKHIJA
 
Business Plan Case Study 22 May 2016 v1
Business Plan Case Study 22 May 2016 v1Business Plan Case Study 22 May 2016 v1
Business Plan Case Study 22 May 2016 v1CA. MOHIT MAKHIJA
 
AH City Council Meeting 10/12/15 - Item #7
AH City Council Meeting 10/12/15 - Item #7AH City Council Meeting 10/12/15 - Item #7
AH City Council Meeting 10/12/15 - Item #7Marian Vargas Mendoza
 
Snam 1Q 2015 Consolidated Results
Snam 1Q 2015 Consolidated ResultsSnam 1Q 2015 Consolidated Results
Snam 1Q 2015 Consolidated ResultsSnam
 
Financial results-March31-2014
Financial results-March31-2014Financial results-March31-2014
Financial results-March31-2014HDFC Bank
 
Fixed Capital Analysis PowerPoint Presentation Slides
Fixed Capital Analysis PowerPoint Presentation SlidesFixed Capital Analysis PowerPoint Presentation Slides
Fixed Capital Analysis PowerPoint Presentation SlidesSlideTeam
 
Financing Forecasting Process And Methods PowerPoint Presentation Slides
Financing Forecasting Process And Methods PowerPoint Presentation SlidesFinancing Forecasting Process And Methods PowerPoint Presentation Slides
Financing Forecasting Process And Methods PowerPoint Presentation SlidesSlideTeam
 
Snam 2015 Interim Results
Snam 2015 Interim ResultsSnam 2015 Interim Results
Snam 2015 Interim ResultsSnam
 
Rickmers Maritime Trust Q2 2013 results presentation
Rickmers Maritime Trust Q2 2013 results presentationRickmers Maritime Trust Q2 2013 results presentation
Rickmers Maritime Trust Q2 2013 results presentationTradeWindsnews
 
Meeting with Investors - June 2015
Meeting with Investors - June 2015Meeting with Investors - June 2015
Meeting with Investors - June 2015TIM RI
 
Research report first source solution
Research report first source solutionResearch report first source solution
Research report first source solutionPreeti Srivastava
 

Similar to MOSES 2.ppt (20)

Director's Report
Director's ReportDirector's Report
Director's Report
 
Factory Monthly ACCL (U-3&4).ppt
Factory Monthly ACCL (U-3&4).pptFactory Monthly ACCL (U-3&4).ppt
Factory Monthly ACCL (U-3&4).ppt
 
2015 04 investor presentation
2015 04 investor presentation2015 04 investor presentation
2015 04 investor presentation
 
Evaluation of Service Performance & Analysis of Scope of Market
Evaluation of Service Performance & Analysis of Scope of MarketEvaluation of Service Performance & Analysis of Scope of Market
Evaluation of Service Performance & Analysis of Scope of Market
 
PNB Analyst presentation Mar`22 (3).pdf
PNB Analyst presentation Mar`22 (3).pdfPNB Analyst presentation Mar`22 (3).pdf
PNB Analyst presentation Mar`22 (3).pdf
 
Fiscal Year-ending March 2015 Briefing on the Results for the Second Quarter
Fiscal Year-ending March 2015 Briefing on the Results for the Second  QuarterFiscal Year-ending March 2015 Briefing on the Results for the Second  Quarter
Fiscal Year-ending March 2015 Briefing on the Results for the Second Quarter
 
Dpr
DprDpr
Dpr
 
financialsnapshot
financialsnapshotfinancialsnapshot
financialsnapshot
 
Business Plan Case Study 22 May 2016 v1
Business Plan Case Study 22 May 2016 v1Business Plan Case Study 22 May 2016 v1
Business Plan Case Study 22 May 2016 v1
 
Business Plan Case Study 22 May 2016 v1
Business Plan Case Study 22 May 2016 v1Business Plan Case Study 22 May 2016 v1
Business Plan Case Study 22 May 2016 v1
 
AH City Council Meeting 10/12/15 - Item #7
AH City Council Meeting 10/12/15 - Item #7AH City Council Meeting 10/12/15 - Item #7
AH City Council Meeting 10/12/15 - Item #7
 
Snam 1Q 2015 Consolidated Results
Snam 1Q 2015 Consolidated ResultsSnam 1Q 2015 Consolidated Results
Snam 1Q 2015 Consolidated Results
 
Financial results-March31-2014
Financial results-March31-2014Financial results-March31-2014
Financial results-March31-2014
 
Fixed Capital Analysis PowerPoint Presentation Slides
Fixed Capital Analysis PowerPoint Presentation SlidesFixed Capital Analysis PowerPoint Presentation Slides
Fixed Capital Analysis PowerPoint Presentation Slides
 
Financing Forecasting Process And Methods PowerPoint Presentation Slides
Financing Forecasting Process And Methods PowerPoint Presentation SlidesFinancing Forecasting Process And Methods PowerPoint Presentation Slides
Financing Forecasting Process And Methods PowerPoint Presentation Slides
 
Snam 2015 Interim Results
Snam 2015 Interim ResultsSnam 2015 Interim Results
Snam 2015 Interim Results
 
Rickmers Maritime Trust Q2 2013 results presentation
Rickmers Maritime Trust Q2 2013 results presentationRickmers Maritime Trust Q2 2013 results presentation
Rickmers Maritime Trust Q2 2013 results presentation
 
Cc 3 t17_eng
Cc 3 t17_engCc 3 t17_eng
Cc 3 t17_eng
 
Meeting with Investors - June 2015
Meeting with Investors - June 2015Meeting with Investors - June 2015
Meeting with Investors - June 2015
 
Research report first source solution
Research report first source solutionResearch report first source solution
Research report first source solution
 

Recently uploaded

Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptNANDHAKUMARA10
 
Engineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planesEngineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planesRAJNEESHKUMAR341697
 
Verification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptxVerification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptxchumtiyababu
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationBhangaleSonal
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTbhaskargani46
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Call Girls Mumbai
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdfAldoGarca30
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdfKamal Acharya
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxJuliansyahHarahap1
 
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLEGEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLEselvakumar948
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.Kamal Acharya
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"mphochane1998
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . pptDineshKumar4165
 
Moment Distribution Method For Btech Civil
Moment Distribution Method For Btech CivilMoment Distribution Method For Btech Civil
Moment Distribution Method For Btech CivilVinayVitekari
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayEpec Engineered Technologies
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxSCMS School of Architecture
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapRishantSharmaFr
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptxJIT KUMAR GUPTA
 

Recently uploaded (20)

Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.ppt
 
Engineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planesEngineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planes
 
Verification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptxVerification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptx
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdf
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLEGEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
Moment Distribution Method For Btech Civil
Moment Distribution Method For Btech CivilMoment Distribution Method For Btech Civil
Moment Distribution Method For Btech Civil
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 

MOSES 2.ppt

  • 1. BEDC Irrua Service Units Monthly Performance Review Sessions’ Framework July, 2015.
  • 2. Objectives of the Presentation  To highlight basic performance indices of the Service unit  To highlight various challenges that affected the Service unit in the review period  To highlight strategies adopted for the achievement of planned performance
  • 3. Table of Content Objectives of the Presentation Part 1: Introduction Part 2: Balance Score Card Perspectives  Financial Perspective  Customer Perspective  Internal Processes Perspective  Learning & Growth Part 3: Conclusion Questions & Answers
  • 4. Part 1 : Introduction  Service Unit’s Name: Irrua Business Unit: uromi State:Edo  Area of Operation’s Coverage [The Service Unit Covers ...........number of Local Governments Areas in ..............State, namely; ....................................with total area of ...............1km2] SERVICE CENTRE LOCATIONS LOCAL GOVERNMENT HOUSEHOLD POPULATIO N NO OF COMMUNITIES SERVED TOTAL CUSTOMER POPULATION Bulk Billed Non Bulk Billed TOTAL Metered Unmetered OPOJI IRRUA ESAN CENTRAL 596 1 2 3 557 EWU IRRUA ESAN CENTRAL 2418 3 3 1836 IRRUA IRRUA ESAN CENTRAL 2870 2 2 2662 PPM IRRUA ESAN CENTRAL 75 TOTAL 5884 1 7 8 5132
  • 5. Energy to Collection Highlights Part 2: Financial Perspective Service Unit Customer Population Energy Input (MWH) Cost of Energy (N’million) Energy Billed (MWh) Amount Billed (N’million) Amount Collected (N’million) Total Outstanding Debt (N’million) ATC & C Losses (%) A B C D E F G H = 1 - N Irrua May-15 5105 924948 21353388.52565232 13203800.91 7079553 162367785 67.2 Jun-15 5132 1004498 26254641.39741041 17497690.11 9058328.05 182192473.00 62.98 Jul-15 4208 1202398.78 28300645.18625656 14854598.39 11231940.71 128655294.39 60.66 Number of Book No of Customer Response Outstanding as at previous month (N’ million) % Cost of Energy Collected Billing Efficiency (%) Marketing Efficiency (%) Collection Efficiency (%) Debt Recovery Index (%) ATC & C Losses (Naira) I J K L = ( F/C)* 100 M = (D/B) * 100 N = M * O O = (F/E) * 100 P = { (K - G)/K) * 100 Q = H * C May-15 48 993 154674604.3 33.15 61.11 32.77 53.62 -4.92 14349477.09 Jun-15 48 1716 171915621.99 34.573.77 38.19 51.77 -5.98 15412686.87 Jul-15 48 2095 182192473.00 39.6952.03 39.34 75.61 29.39 17166828.6
  • 6. Financial Perspective Service Unit Customer Type Amount Billed (N’million) Cash collected from Current billing (N’million) Collection from Outstanding Debt (N’million) % of cash collected from Amount billed May-15 Jun-15 Jul-15 May-15 Jun-15 Jul-15 May-15 Jun-15 Jul-15 May-15 Jun-15 Jul-15 irrua MD 3421695. 62 348596 8.41 3530729. 31 3904865. 05 3639685. 05 3839661. 18 - - - 114.12 104.41 108.75 Prime 404591.1 9 454707. 74 528557.1 4 365455.0 0 322090.0 0 323650.0 0 - - - 90.33 70.83 61.23 Non-MD 1320380 0.91 135570 13.96 10795311 .94 2809233. 00 4909200. 00 7068629. 73 - - - 21.28 36.21 65.48 Total 1703008 7.7 174976 90.11 14854598 .39 7079553. 05 9058328. 05 1123194 0.91 - - - 41.57 51.77 75.61
  • 7. Financial Perspective STRATEGIES AND PROPOSED CASH COLLECTION PLAN TO COVER THE GAP •946 Nos Nmd Customers will pay 2.9m in the next two two weeks. •10 Nos Md customers will pay 2.6m in the next two weeks. •30 Nos Pmd customers will pay 450,000.00 in the next two weeks. •Customers response will improve henceforth. GAP ANALYSIS AND STRATEGIES Month Total Cash Collection Gaps before the Review Month (from Jan 2015) (N’million) Review Month Cash Collection (N’million) Review Month Cash Collection Target (N’million) Review Month Cash Collection Shortfall (N’million) Present Month Cash Collection as at Date (N’million) Present Month Cash Collection Target (N’million) Present Month Cash Collection Shortfall as at Date (N’million) Cash Collection Gap as at Date (N’million) Outstandin g Debt Balance (N’million) A B C D = C - A E F G = F - E H = A+D + G I May-15 46262911.10 7079553.05 21353388.52 24909523.00 776080 21353388.5 2 20577308.50 41930696.6 1623677 85.21 Jun-15 61675579.96 9058328.05 26254641.39 35420957.00 3098315.00 28300645.1 8 25202330.2 51456971.00 1821924 73.00 Jul-15 78744302.23 11231940.9 1 28300645.18 -33374953 327365 31444252.9 7 31116888 59417533.00 1286552 94.39
  • 8. Customer Base Overview for the Month: Performance with Period Comparative Customer Perspective SERVIC E UNIT CUSTO MER TYPE UNMETERED CUSTOMER PRE-PAID CUSTOMER READ CUSTOMER MINIMUM BILLING ESTIMATED CUSTOMER May-15 Jun-15 Jul-15 May-15 Jun-15 Jul-15 May-15 Jun-15 Jul-15 May-15 Jun-15 Jul-15 May-15 Jun-15 Jul-15 SUMMARY OF CUSTOMER BASE irrua MD 3 3 3 - - - 9 10 8 2 1 3 - - - PRIME 20 19 19 - - 15 15 14 11 12 13 - - - NON- MD 609 608 386 66 75 75 1194 962 1020 641 740 631 2535 2687 2036 SUMMARY OF ENERGY BILLED (MWH) irrua MD 13287 0 134952 135909 PRIME 17395 14638 17153 BREAK DOWN NOT AVAILAB LE NON- MD 56523 2 591416 47259 4 SUMMARY OF AMOUNT BILLED (N’million) irrua MD 34216 95.62 348596 8.41 353072 9.3 PRIME 40459 1.91 454707 .74 52855 7.14 BREAK DOWN NOT AVAILAB LE NON- MD 13203 800.00 135670 13.96 10795 311.94
  • 9. July-15 Customer Base Overview for the Month: Performance with Period Comparative Customer Perspective CUSTOMER TYPE NUMBER OF BILL PRINTED NUMBER OF DELIVERED BILLS NUMBER OF UNDELIVERED BILLS REASONS FOR NON-DELIVERY OF BILLS REASON 1 LDNP and failed S/s. REASON 2 PPM, OTHERS REASON 3 COUNT % COUNT % COUNT % MD 14 12 2 2 100 - - - - PRIME 46 40 6 6 100 - - - - NON-MD 4148 3780 368 300 81.52 68 18.48 - - Service Unit Customer type Customer Population % Population MD 14 0.33 Prime 46 1.09 Non-MD 4073 96.79 Pre-Paid 75 1.78 Total 4208 100
  • 10. Customer Perspective ILLEGAL CUSTOMER CAPTURED Service Unit May -15 CAPTURED CUSTOMER Jun -15 CAPTURED CUSTOMER Jul -15 CAPTURED CUSTOMER Count Amount Billed (₦’Thousand) Amount paid (₦’Thousand) Count Amount Billed (₦’Thousand) Amount paid (₦’Thousand) Count Amount Billed (N’Thousand) Loss of Revenue Charged (₦’Thousand) Loss of Revenue Paid (₦’Thousand) 84 357,638.65 323,262.42 18 79,998.03 10,000.00 2,000. 00 75456.09 50,000.00 2000.00 NEW SERVICE CONNECTION RECLASSIFICATION Service Unit Credit Customer Pre-paid Customer May-15 Jun-15 Jul-15 May-15 Jun-15 Jul-15 Business Unit Number of Reclassification Done May-15 Jun-15 Jul-15 18 10 18 66 75 75 UROMI - - - - Service Unit Month CUSTOMER COMPLAINTS Billing Issues Metering Issues Supply Issues Average Resolution Time Count No Resolved Response Rate Count No Resolved Response Rate Count No Resolved Response Rate May -15 14 12 85.71 11 9 81.81 25 19 76.00 Jun -15 16 15 93.75 II 9 81.82 19 16 84.21 - Jul -15 14 10 71.43 6 4 66.66 24 18 75.00 -
  • 11. Customer Perspective KEY CUSTOMERS ISSUES & EXPERIENCE IMPROVEMENT STRATEGIES CUSTOMER PERSPECTIVE IDENTIFIED ISSUES & CONSTRAINTS STRATEGIES TO IMPROVE CUSTOMERS EXPERIENCE BANK PAYMENT CHALLENGES. THE SERVICE UNIT HAS JUST ONE BANK AVAILABLEBBBBANK ENCOURAGEMENT OF BANK MANAGERS TO ENSURE POSTING OF PAYMENTS MADE** HOSTILITY AND ILLEGAL RECONNECTION BY DISCONNECTED CUSTOMER. MONITORS DISCONNECTED CUSTOMER AND ENLIGHTEMENT OF CUSTOMERS
  • 12. Customer Perspective July 2015 Customer Population Gap Analysis Customer Population Household Population Population Gap Strategies and Proposed Plan to Cover the Gap A B C = B-A D 4208 5884 1676 CONSTANT CAPTURING OF ILLEGAL CUSTOMERS IN OUR NETWORK July 2015 MD and Prime Population Gap Analysis MD Pop. MD % Pop. to the Total Popn MD % Pop. Target MD % Pop. Gap Prime Pop. Prime % Pop. to the Total Pop. Prime % Pop. Target Prime % Pop. Gap Strategies and Proposed Plan to Cover the Gaps E F = (E/A) * 100 G = 1% H = G- F I J = (I/A) * 100 K = 5% L =K- J M 14 0.33 1.00% 0.67 46 1.09 5% 3.91 WE HOPE TO INTENSIFY OUR EFFORT ON RECLASSIFICATION July 2015 Metering Gap Analysis Number of metered Customer Metering Gap Strategies and Proposed Plan to Cover the Gap N O = A-N P 1689 2519 THE LIFTING OF EMBARGO ON METER PROCESSING WILL ENCOURAGE CUSTOMERS TO PAY FOR METERS HENCEFORTH GAP ANALYSIS AND STRATEGIES
  • 13. Safety Reports SAFETY REPORTS Service Unit Month No of Safety talk done No of Near Misses No of Minor Incidence No of Major Incidence/Fatality Total No of Incidents/ Accidents Causes of major Accidents May -15 1 - - - - - Jun -15 1 - - - - - Jul -15 1 - - - - - Staff Distribution Department Total No of Staff No of Staff Service Unit Office Service Centre Fault Centre Cash Offices Distribution 6 4 2 Marketing/Commercial 1 1 Financial & Account HR/Admin Customer Care Corporate Affairs Store TOTAL 7 5 2
  • 14. Part 3: Conclusion  The service unit looks forward to a better improvement on its value to business on monthly basis. So help us Lord.
  • 15. Questions & Answers  Open Floor Question & Answers from the Floor