CCDC 2 — A FOCUS ON 3 TOPICS
    USING CASE STUDIES
                8:30am – 10:00am



                   Presenters:
    Oliver Hanson, Associate, Clark Wilson LLP
      Samantha Ip, Partner, Clark Wilson LLP
   Anna Sekunova, Associate, Clark Wilson LLP
Buildex 2011




           Presented by Samantha Ip
•   A change in the Work that is not included or contemplated in 
    the Contract Documents which adds to the scope of Contract 
    Work

•   Contract Documents is a defined term – documents listed in 
    Article A‐3

•   Article A‐3 – Contract, Definitions, GC’s, Plans, 
    Specifications, Drawings, etc…




                                                                    2
•   Objective test – proper interpretation of the Contract 
    Documents

•   Would a reasonable contractor, reviewing the Contract 
    Documents, realize he would be required to perform certain 
    Work?  If yes – then not an extra.

•   If it can be inferred from the Contract description that other 
    undescribed work will be necessary to perform the Contract, 
    then the undescribed Work is generally not an extra




                                                                      3
•   GC 6.1.1 – The Owner has a right to make changes to the 
    Work and changes to the Contract Time by Change Order


•   GC 6.1.2 ‐ Contractor shall not perform a change in the Work
    without a Change Order or Change Directive




                                                                   4
GC 6.2 – Change Order:

•   For when the Owner and the Contractor agree to 
    adjustments in the Contract Time and Contract Price, or the 
    method to be used to determine the adjustments

•   Separate agreement signed by the parties




                                                                   5
GC 6.3 – Change Directive:

  Owner compels Contractor to proceed with a change in the 
  Work

  No agreement on adjustment to Contract Price or Contract 
  Time

  CCDC2 ‐2008 added: “…Work within the general scope of 
  Contract Documents.”


                                                              6
GC 6.3 – Change Directive (con’t):

•   GC 6.3.7 – Cost of performing the work in the Change 
    Directive shall be limited to the actual cost of the following….

•   New 2008: Change Directive covers all costs and liabilities 
    attributable to the Change Directive …(GC 6.3.8)




                                                                       7
GC 6.3 – Change Directive (con’t):

•   GC 6.3.8 excludes costs caused by Contractor’s failure to 
    exercise reasonable care and diligence

•   New 2008: Contractor required to maintain full and detailed 
    accounts and records to “prove” the change (GC 6.3.9)




                                                                   8
GC 6.3 – Change Directive (con’t):



•   New 2008:  Owner has access rights to Contractor’s 
    “pertinent documents” related to the cost of performing the 
    work on the Change Directive  (GC 6.3.10)




                                                                   9
•   Incomplete, wrong, and incompatible designs;
•   Unclear or vague specifications;
•   Unexpected site conditions;
•   Shifting owner requirements for design, work scope or 
    scheduling;
•   Updated construction methods;
•   Changes to access and sequencing of the work;
•   emergencies; and
•   Changes mandated by regulatory authorities.




                                                             10
When there is agreement and documentation…

•   Signed and agreed upon Change Order

•   An agreed upon Change Directive

•   No change documentation, but parties agree to an 
    adjustment in Contract Time or Contract Price




                                                        11
12
•   Contractor has done extra work, but Owner has not issued 
    Change Order or Change Directive – will the extra work be 
    compensable?


•   CCDC 2:  Contractor shall not perform a change in the Work 
    without Change Order or Change Directive (GC 6.1.2)




                                                                  13
•   CCDC 2:  The Contract supersedes all prior negotiations, 
    representations, or agreements, either written or oral, 
    relating …to the Work…(Article A‐2)

•   CCDC 2:   The Contract may be amended only as provided in 
    the Contract Documents

    Is a change in the Work compensable as an extra when there 
    is no supporting “paperwork”?



                                                                  14
•   Owner wants to build a motel – asks a contractor to bid on 
    the project based on an original set of plans
•   Contractor bids on the project based on those plans
•   Owner then gives contractor additional specifications and 
    asked contractor to include specifications in the bid
•   CCDC 2 contract signed – attaches both the original plans 
    and  the additional specifications
•   There were conflicts in the work between original plans and 
    additional specifications
•   Some items in original plans were traded for items in 
    additional specifications
•   Contract price did not change  

                                                                   15
•   Other changes were made before and after contract was 
    signed – finished motel very different from original plans
•   Plans, contract and price were not amended to reflect 
    changes
•   Contractor was given a revised site plan after signing the 
    contract – owner told contractor he would pay for any extra 
    charges
•   Multiple disputes arise – contractor claims for unpaid 
    contract price and extras, and owner counterclaims for delay 
    and deficiencies – the ``Classic``or ``Sam`s Special``



                                                                    16
•   Owner says:
     • most of the extras are not ``extra`` to the contract as 
       contractor knew that work was required before the 
       contract was entered into and included in contract price
     • Owner also says if work not included in contract then 
       not payable because no written change order 

•    The contract says:  ``…all deviations or additions from or to 
    the plans and specifications …shall be approved, in advance, 
    in writing and signed by the Owner and Contractor with 
    agreed costs for such deviations and conditions…``

                                                                      17
•   Contract had standard change order provisions

•   Defendant says:
      • Owner knew changes had to be in writing, but he did not 
        want to spend extra money on administration
      • Owner did not want to spend money revising plans
      • Contractor asked for confirmation of changes in writing, 
        but did not receive them, and had to carry on with work
      • He trusted the owner…



                                                                    18
•   General rule:  parol evidence is inadmissible to vary written 
    agreement if contradicts written agreement

•   If parties cannot stray from the written agreement, then 
    there should be no compensation for extras without written 
    change order or change directive

•   Any guesses on what happened?




                                                                     19
•   Our B.C. Supreme Court found in favour of the contractor

•   Key factors for decision:
      • Both parties aware of contract terms on changes, and 
        both chose to ignore them
      • Contractor requested written change orders and 
        revisions to plans but owner refused to provide
      • No consultant on site to administer changes – so could 
        not follow contract procedure
      • Owner supervised and requested changes


                                                                  20
•   In these circumstances, owner cannot rely on the contract 
    provisions that changes be in writing

•   Moral of the Kei‐Ron story:  

    1) Reduce risk by following the contract
    2) Be clear on what is included in contract work
    3) Trust should not negate contract requirements
    4) Confirm changes (or any issue) in writing, even if the form 
       of confirmation is not per contract requirements


                                                                      21
1.   Was the work performed actually extra work? (did work fall 
     within scope of work originally contemplated by contract?)

2.   If yes, did owner give instructions, either express or implied, 
                  In determining liability for the cost of extra
     that the work be done, or was the work otherwise 
                   work, the first question to be answered is
     authorized by the owner? performed was,extra11
                   whether the work                      in fact,


3.   Was the owner informed or necessarily aware that theextra
     work would increase the cost?

4.   Did the owner waive the provision requiring changes to be 
     made in writing or acquiesce in ignoring these provisions?

                                                                        22
1.   Ensure design is complete before tendering / bidding
2.   Address any ambiguities before tendering / bidding in 
     writing – do not assume
3.   Understand site conditions
4.   Owners – beware of the low bid – could result in additional 
     changes
5.   If other party refuses to confirm issue in writing, discuss 
     agreement and confirm it in writing to the other party
6.   Use the Consultant for determining issues (GC 2.2.7 & 2.2.8) 
     before issues become disputes
7.   Provide for quantification of changes as a supplementary 
     condition to avoid dispute

                                                                     23
8.    Use supplementary conditions to address delay scenarios 
      not addressed in CCDC2
9.    Avoid using Change Directive if possible – unresolved / 
      dispute
10.   Contractors should have detailed pricing with appropriate 
      back up – prevent owner from using “improper 
      documentation” as reason to delay approval of change
11.   Be clear on communications about the impact of a change
12.   Contractors do not proceed with a change until instructions 
      to proceed confirmed in writing
13.   Owners avoid verbal approval and expedite change 
      approval to avoid delay impact on project

                                                                     24
14.   If no change order or change directive, then contractors 
      can consider:

       • Seeking an agreement in writing to suspend the dispute 
         over the change and  allow the Contractor to do the 
         extra work while preserving the right to resolve the 
         dispute later; or




                                                                   25
If no change order or change directive, then contractors can 
   consider:
• Do the Work Under Protest:

  • Section 62 of B.C.’s Law and Equity Act
    – If dispute arises between parties to a contract respecting the 
      obligations of a party, the party whose obligations are disputed
      may, within a reasonable period of time after being informed that 
      performance is required, provide the demanding party with 
      notice of intention to perform the disputed requirements under 
      protest.  The right to claim payment is preserved.
    – Act allows contracting parties to specify rules for protest notice.

                                                                            26
•   CCDC 2 – GC 8.1.3:  If a dispute is not resolved promptly:

      • The Consultant must give any instructions necessary for the 
        proper performance of the Work to prevent delays pending 
        settlement of the dispute.
      • The parties are required to follow instructions immediately 
        but their rights to make claims are not jeopardized.
      • If it is subsequently determined that the Consultant’s
        instructions were in error or at variance with the Contract 
        Documents, the Owner must pay the Contractor the costs 
        incurred in carrying out the instructions beyond what the 
        Contract Documents properly required.


                                                                       27
Sam’s modus operandi for minimizing risk from 
 changes:

   Expect
   Prepare
   Minimize 
   Manage
   Resolve

                                                 28
These materials are necessarily of a general
   nature and do not take into consideration
   any specific matter, client or fact pattern.

     Please direct inquiries or comments to:

                      Samantha Ip, Partner
                         Clark Wilson LLP
          ssi@cwilson.com | 604.643.3172

                          www.cwilson.com

Contenu connexe

Tendances

Can a work in a contract be omitted
Can a work in a contract be omittedCan a work in a contract be omitted
Can a work in a contract be omittedAMILA GAYAN
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2ahmong4
 
Contract administration iowa AGC
Contract administration iowa AGCContract administration iowa AGC
Contract administration iowa AGCCordell Parvin
 
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMDIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMAnep Botak
 
Construction Contracts: Basics of Contracts and Contract Administration
Construction Contracts:  Basics of Contracts and Contract AdministrationConstruction Contracts:  Basics of Contracts and Contract Administration
Construction Contracts: Basics of Contracts and Contract AdministrationGerald R. (Jerry) Genge
 
Laporan Latihan Industri Bab 4
Laporan Latihan Industri Bab 4Laporan Latihan Industri Bab 4
Laporan Latihan Industri Bab 4CikBeyla Nabiella
 
Seminar - Partial Possession by Employer
Seminar - Partial Possession by EmployerSeminar - Partial Possession by Employer
Seminar - Partial Possession by EmployerKai Yun Pang
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variationVj NiroSh
 
Nuts and bolts of builders liens (Independent Contractors and Businesses Asso...
Nuts and bolts of builders liens (Independent Contractors and Businesses Asso...Nuts and bolts of builders liens (Independent Contractors and Businesses Asso...
Nuts and bolts of builders liens (Independent Contractors and Businesses Asso...SHKLaw
 
Key terms to consider when negotiating cm at-risk agreements + gmp amendments
Key terms to consider when negotiating cm at-risk agreements + gmp amendmentsKey terms to consider when negotiating cm at-risk agreements + gmp amendments
Key terms to consider when negotiating cm at-risk agreements + gmp amendmentsKegler Brown Hill + Ritter
 
Variations in works contracts
Variations in works contractsVariations in works contracts
Variations in works contractsDr K M SONI
 
Construction Law - Presentation - Construction Contractual Claims
Construction Law - Presentation - Construction Contractual ClaimsConstruction Law - Presentation - Construction Contractual Claims
Construction Law - Presentation - Construction Contractual ClaimsYee Len Wan
 
Drafting Construction Contracts
Drafting Construction ContractsDrafting Construction Contracts
Drafting Construction ContractsMelissa Brumback
 
Professional Practice II
Professional Practice IIProfessional Practice II
Professional Practice IIseenyeeyong
 
Fidic conditions of contract presentation
Fidic conditions of contract presentationFidic conditions of contract presentation
Fidic conditions of contract presentationJeff B
 
Effective contract administration may 2014
Effective contract administration may 2014Effective contract administration may 2014
Effective contract administration may 2014SHKLaw
 

Tendances (20)

Can a work in a contract be omitted
Can a work in a contract be omittedCan a work in a contract be omitted
Can a work in a contract be omitted
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2
 
Contract administration iowa AGC
Contract administration iowa AGCContract administration iowa AGC
Contract administration iowa AGC
 
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMDIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
 
Construction Contracts: Basics of Contracts and Contract Administration
Construction Contracts:  Basics of Contracts and Contract AdministrationConstruction Contracts:  Basics of Contracts and Contract Administration
Construction Contracts: Basics of Contracts and Contract Administration
 
Laporan Latihan Industri Bab 4
Laporan Latihan Industri Bab 4Laporan Latihan Industri Bab 4
Laporan Latihan Industri Bab 4
 
Seminar - Partial Possession by Employer
Seminar - Partial Possession by EmployerSeminar - Partial Possession by Employer
Seminar - Partial Possession by Employer
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variation
 
Construction contracts
Construction contractsConstruction contracts
Construction contracts
 
Nuts and bolts of builders liens (Independent Contractors and Businesses Asso...
Nuts and bolts of builders liens (Independent Contractors and Businesses Asso...Nuts and bolts of builders liens (Independent Contractors and Businesses Asso...
Nuts and bolts of builders liens (Independent Contractors and Businesses Asso...
 
Key terms to consider when negotiating cm at-risk agreements + gmp amendments
Key terms to consider when negotiating cm at-risk agreements + gmp amendmentsKey terms to consider when negotiating cm at-risk agreements + gmp amendments
Key terms to consider when negotiating cm at-risk agreements + gmp amendments
 
ACH 216 Lecture 12 (Closeut & Turnover)
ACH 216 Lecture 12 (Closeut & Turnover)ACH 216 Lecture 12 (Closeut & Turnover)
ACH 216 Lecture 12 (Closeut & Turnover)
 
ACH 216 Lecture 04c (Project Award)
ACH 216 Lecture 04c (Project Award)ACH 216 Lecture 04c (Project Award)
ACH 216 Lecture 04c (Project Award)
 
Variations in works contracts
Variations in works contractsVariations in works contracts
Variations in works contracts
 
Chapter 5- Contract Management
Chapter 5- Contract ManagementChapter 5- Contract Management
Chapter 5- Contract Management
 
Construction Law - Presentation - Construction Contractual Claims
Construction Law - Presentation - Construction Contractual ClaimsConstruction Law - Presentation - Construction Contractual Claims
Construction Law - Presentation - Construction Contractual Claims
 
Drafting Construction Contracts
Drafting Construction ContractsDrafting Construction Contracts
Drafting Construction Contracts
 
Professional Practice II
Professional Practice IIProfessional Practice II
Professional Practice II
 
Fidic conditions of contract presentation
Fidic conditions of contract presentationFidic conditions of contract presentation
Fidic conditions of contract presentation
 
Effective contract administration may 2014
Effective contract administration may 2014Effective contract administration may 2014
Effective contract administration may 2014
 

En vedette

Construction Defect Claims: The Ins & The Outs, The Do's & The Don'ts
Construction Defect Claims: The Ins & The Outs, The Do's & The Don'tsConstruction Defect Claims: The Ins & The Outs, The Do's & The Don'ts
Construction Defect Claims: The Ins & The Outs, The Do's & The Don'tsSamantha Ip
 
Limitation Act Reform: The Canadian Perspective
Limitation Act Reform: The Canadian PerspectiveLimitation Act Reform: The Canadian Perspective
Limitation Act Reform: The Canadian PerspectiveSamantha Ip
 
Limitation Act Reform - The Canadian Perspective
Limitation Act Reform - The Canadian PerspectiveLimitation Act Reform - The Canadian Perspective
Limitation Act Reform - The Canadian PerspectiveSamantha Ip
 
Sexual Misconduct in Professional Liability Cases: Key Strategies in Defendin...
Sexual Misconduct in Professional Liability Cases: Key Strategies in Defendin...Sexual Misconduct in Professional Liability Cases: Key Strategies in Defendin...
Sexual Misconduct in Professional Liability Cases: Key Strategies in Defendin...Samantha Ip
 
Insurance Broker Liability - Is the U.S. adopting a Canadian Perspection on s...
Insurance Broker Liability - Is the U.S. adopting a Canadian Perspection on s...Insurance Broker Liability - Is the U.S. adopting a Canadian Perspection on s...
Insurance Broker Liability - Is the U.S. adopting a Canadian Perspection on s...Samantha Ip
 
Errors & Omissions Insurance Update: Brokers' E&O Exposure
Errors & Omissions Insurance Update: Brokers' E&O ExposureErrors & Omissions Insurance Update: Brokers' E&O Exposure
Errors & Omissions Insurance Update: Brokers' E&O ExposureSamantha Ip
 
Consultant Agreements and the Role of the Consultant
Consultant Agreements and the Role of the ConsultantConsultant Agreements and the Role of the Consultant
Consultant Agreements and the Role of the ConsultantSamantha Ip
 

En vedette (8)

Construction Defect Claims: The Ins & The Outs, The Do's & The Don'ts
Construction Defect Claims: The Ins & The Outs, The Do's & The Don'tsConstruction Defect Claims: The Ins & The Outs, The Do's & The Don'ts
Construction Defect Claims: The Ins & The Outs, The Do's & The Don'ts
 
Limitation Act Reform: The Canadian Perspective
Limitation Act Reform: The Canadian PerspectiveLimitation Act Reform: The Canadian Perspective
Limitation Act Reform: The Canadian Perspective
 
Limitation Act Reform - The Canadian Perspective
Limitation Act Reform - The Canadian PerspectiveLimitation Act Reform - The Canadian Perspective
Limitation Act Reform - The Canadian Perspective
 
Sports & Events
Sports & EventsSports & Events
Sports & Events
 
Sexual Misconduct in Professional Liability Cases: Key Strategies in Defendin...
Sexual Misconduct in Professional Liability Cases: Key Strategies in Defendin...Sexual Misconduct in Professional Liability Cases: Key Strategies in Defendin...
Sexual Misconduct in Professional Liability Cases: Key Strategies in Defendin...
 
Insurance Broker Liability - Is the U.S. adopting a Canadian Perspection on s...
Insurance Broker Liability - Is the U.S. adopting a Canadian Perspection on s...Insurance Broker Liability - Is the U.S. adopting a Canadian Perspection on s...
Insurance Broker Liability - Is the U.S. adopting a Canadian Perspection on s...
 
Errors & Omissions Insurance Update: Brokers' E&O Exposure
Errors & Omissions Insurance Update: Brokers' E&O ExposureErrors & Omissions Insurance Update: Brokers' E&O Exposure
Errors & Omissions Insurance Update: Brokers' E&O Exposure
 
Consultant Agreements and the Role of the Consultant
Consultant Agreements and the Role of the ConsultantConsultant Agreements and the Role of the Consultant
Consultant Agreements and the Role of the Consultant
 

Similaire à CCDC2 - A Focus on 3 Topics Using Case Studies

Extra Work, Changes and Termination of the Contract
Extra Work, Changes and Termination of the ContractExtra Work, Changes and Termination of the Contract
Extra Work, Changes and Termination of the ContractSHKLaw
 
CONTRACT ADMINISTRATION Updated.pptx
CONTRACT ADMINISTRATION Updated.pptxCONTRACT ADMINISTRATION Updated.pptx
CONTRACT ADMINISTRATION Updated.pptxAditya Mane
 
Session-02 17-09-2011
Session-02 17-09-2011Session-02 17-09-2011
Session-02 17-09-2011Tahir B Mirza
 
Preserving Your Bottom Line
Preserving Your Bottom LinePreserving Your Bottom Line
Preserving Your Bottom LineCallPM
 
Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)Melvin Lim
 
Post Award Requirements and Issues Change Orders 2012 fedcon
Post Award Requirements and Issues Change Orders 2012 fedconPost Award Requirements and Issues Change Orders 2012 fedcon
Post Award Requirements and Issues Change Orders 2012 fedconNC Military Business Center
 
Disputes and Claims in Engineering Contracts - 18.07.07.ppt
Disputes and Claims in Engineering Contracts - 18.07.07.pptDisputes and Claims in Engineering Contracts - 18.07.07.ppt
Disputes and Claims in Engineering Contracts - 18.07.07.pptNesrElhandasa1
 
NEC4 overview: key changes and impacts - London, September 2017
NEC4 overview: key changes and impacts - London, September 2017NEC4 overview: key changes and impacts - London, September 2017
NEC4 overview: key changes and impacts - London, September 2017Browne Jacobson LLP
 
05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITIONByishimoBTCChef
 
NEC4 overview: key changes and impacts - Birmingham, September 2017
NEC4 overview: key changes and impacts - Birmingham, September 2017NEC4 overview: key changes and impacts - Birmingham, September 2017
NEC4 overview: key changes and impacts - Birmingham, September 2017Browne Jacobson LLP
 
Planning and development club - May 2017, Nottingham
Planning and development club - May 2017, NottinghamPlanning and development club - May 2017, Nottingham
Planning and development club - May 2017, NottinghamBrowne Jacobson LLP
 
Construction contract
Construction contract Construction contract
Construction contract Rakshith Reddy
 
Arbitration Dispute Cross Arguments: Asia NGPipeline -Substance of EPC contra...
Arbitration Dispute Cross Arguments: Asia NGPipeline -Substance of EPC contra...Arbitration Dispute Cross Arguments: Asia NGPipeline -Substance of EPC contra...
Arbitration Dispute Cross Arguments: Asia NGPipeline -Substance of EPC contra...César del Riego y Fuentes
 
types of contracts
 types of contracts types of contracts
types of contractsKEVINMISTRY8
 
NEC4 overview: key changes and impacts - Nottingham, September 2017
NEC4 overview: key changes and impacts - Nottingham, September 2017NEC4 overview: key changes and impacts - Nottingham, September 2017
NEC4 overview: key changes and impacts - Nottingham, September 2017Browne Jacobson LLP
 

Similaire à CCDC2 - A Focus on 3 Topics Using Case Studies (20)

Pp1 seminar
Pp1 seminarPp1 seminar
Pp1 seminar
 
Extra Work, Changes and Termination of the Contract
Extra Work, Changes and Termination of the ContractExtra Work, Changes and Termination of the Contract
Extra Work, Changes and Termination of the Contract
 
CONTRACT ADMINISTRATION Updated.pptx
CONTRACT ADMINISTRATION Updated.pptxCONTRACT ADMINISTRATION Updated.pptx
CONTRACT ADMINISTRATION Updated.pptx
 
TOPIC7.pdf
TOPIC7.pdfTOPIC7.pdf
TOPIC7.pdf
 
Contracts and-tenders
Contracts and-tendersContracts and-tenders
Contracts and-tenders
 
Session-02 17-09-2011
Session-02 17-09-2011Session-02 17-09-2011
Session-02 17-09-2011
 
Preserving Your Bottom Line
Preserving Your Bottom LinePreserving Your Bottom Line
Preserving Your Bottom Line
 
Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)
 
Cl presentation
Cl presentationCl presentation
Cl presentation
 
Post Award Requirements and Issues Change Orders 2012 fedcon
Post Award Requirements and Issues Change Orders 2012 fedconPost Award Requirements and Issues Change Orders 2012 fedcon
Post Award Requirements and Issues Change Orders 2012 fedcon
 
Disputes and Claims in Engineering Contracts - 18.07.07.ppt
Disputes and Claims in Engineering Contracts - 18.07.07.pptDisputes and Claims in Engineering Contracts - 18.07.07.ppt
Disputes and Claims in Engineering Contracts - 18.07.07.ppt
 
NEC4 overview: key changes and impacts - London, September 2017
NEC4 overview: key changes and impacts - London, September 2017NEC4 overview: key changes and impacts - London, September 2017
NEC4 overview: key changes and impacts - London, September 2017
 
05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION
 
NEC4 overview: key changes and impacts - Birmingham, September 2017
NEC4 overview: key changes and impacts - Birmingham, September 2017NEC4 overview: key changes and impacts - Birmingham, September 2017
NEC4 overview: key changes and impacts - Birmingham, September 2017
 
contract procedure
contract procedurecontract procedure
contract procedure
 
Planning and development club - May 2017, Nottingham
Planning and development club - May 2017, NottinghamPlanning and development club - May 2017, Nottingham
Planning and development club - May 2017, Nottingham
 
Construction contract
Construction contract Construction contract
Construction contract
 
Arbitration Dispute Cross Arguments: Asia NGPipeline -Substance of EPC contra...
Arbitration Dispute Cross Arguments: Asia NGPipeline -Substance of EPC contra...Arbitration Dispute Cross Arguments: Asia NGPipeline -Substance of EPC contra...
Arbitration Dispute Cross Arguments: Asia NGPipeline -Substance of EPC contra...
 
types of contracts
 types of contracts types of contracts
types of contracts
 
NEC4 overview: key changes and impacts - Nottingham, September 2017
NEC4 overview: key changes and impacts - Nottingham, September 2017NEC4 overview: key changes and impacts - Nottingham, September 2017
NEC4 overview: key changes and impacts - Nottingham, September 2017
 

Dernier

Guide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDFGuide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDFChandresh Chudasama
 
Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMintel Group
 
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxmbikashkanyari
 
International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...ssuserf63bd7
 
Kenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby AfricaKenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby Africaictsugar
 
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCRashishs7044
 
Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy Verified Accounts
 
PSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationPSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationAnamaria Contreras
 
Cyber Security Training in Office Environment
Cyber Security Training in Office EnvironmentCyber Security Training in Office Environment
Cyber Security Training in Office Environmentelijahj01012
 
Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMVoces Mineras
 
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607dollysharma2066
 
Chapter 9 PPT 4th edition.pdf internal audit
Chapter 9 PPT 4th edition.pdf internal auditChapter 9 PPT 4th edition.pdf internal audit
Chapter 9 PPT 4th edition.pdf internal auditNhtLNguyn9
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Kirill Klimov
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCRashishs7044
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCRashishs7044
 
Financial-Statement-Analysis-of-Coca-cola-Company.pptx
Financial-Statement-Analysis-of-Coca-cola-Company.pptxFinancial-Statement-Analysis-of-Coca-cola-Company.pptx
Financial-Statement-Analysis-of-Coca-cola-Company.pptxsaniyaimamuddin
 
Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Americas Got Grants
 
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!Doge Mining Website
 

Dernier (20)

Guide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDFGuide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDF
 
Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 Edition
 
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
 
International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...
 
Kenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby AfricaKenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby Africa
 
Call Us ➥9319373153▻Call Girls In North Goa
Call Us ➥9319373153▻Call Girls In North GoaCall Us ➥9319373153▻Call Girls In North Goa
Call Us ➥9319373153▻Call Girls In North Goa
 
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
 
Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail Accounts
 
PSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationPSCC - Capability Statement Presentation
PSCC - Capability Statement Presentation
 
Cyber Security Training in Office Environment
Cyber Security Training in Office EnvironmentCyber Security Training in Office Environment
Cyber Security Training in Office Environment
 
Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQM
 
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
 
Chapter 9 PPT 4th edition.pdf internal audit
Chapter 9 PPT 4th edition.pdf internal auditChapter 9 PPT 4th edition.pdf internal audit
Chapter 9 PPT 4th edition.pdf internal audit
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
 
Financial-Statement-Analysis-of-Coca-cola-Company.pptx
Financial-Statement-Analysis-of-Coca-cola-Company.pptxFinancial-Statement-Analysis-of-Coca-cola-Company.pptx
Financial-Statement-Analysis-of-Coca-cola-Company.pptx
 
Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...
 
Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)
 
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
 

CCDC2 - A Focus on 3 Topics Using Case Studies

  • 1. CCDC 2 — A FOCUS ON 3 TOPICS USING CASE STUDIES 8:30am – 10:00am Presenters: Oliver Hanson, Associate, Clark Wilson LLP Samantha Ip, Partner, Clark Wilson LLP Anna Sekunova, Associate, Clark Wilson LLP
  • 2. Buildex 2011 Presented by Samantha Ip
  • 3. A change in the Work that is not included or contemplated in  the Contract Documents which adds to the scope of Contract  Work • Contract Documents is a defined term – documents listed in  Article A‐3 • Article A‐3 – Contract, Definitions, GC’s, Plans,  Specifications, Drawings, etc… 2
  • 4. Objective test – proper interpretation of the Contract  Documents • Would a reasonable contractor, reviewing the Contract  Documents, realize he would be required to perform certain  Work?  If yes – then not an extra. • If it can be inferred from the Contract description that other  undescribed work will be necessary to perform the Contract,  then the undescribed Work is generally not an extra 3
  • 5. GC 6.1.1 – The Owner has a right to make changes to the  Work and changes to the Contract Time by Change Order • GC 6.1.2 ‐ Contractor shall not perform a change in the Work without a Change Order or Change Directive 4
  • 6. GC 6.2 – Change Order: • For when the Owner and the Contractor agree to  adjustments in the Contract Time and Contract Price, or the  method to be used to determine the adjustments • Separate agreement signed by the parties 5
  • 7. GC 6.3 – Change Directive: Owner compels Contractor to proceed with a change in the  Work No agreement on adjustment to Contract Price or Contract  Time CCDC2 ‐2008 added: “…Work within the general scope of  Contract Documents.” 6
  • 8. GC 6.3 – Change Directive (con’t): • GC 6.3.7 – Cost of performing the work in the Change  Directive shall be limited to the actual cost of the following…. • New 2008: Change Directive covers all costs and liabilities  attributable to the Change Directive …(GC 6.3.8) 7
  • 9. GC 6.3 – Change Directive (con’t): • GC 6.3.8 excludes costs caused by Contractor’s failure to  exercise reasonable care and diligence • New 2008: Contractor required to maintain full and detailed  accounts and records to “prove” the change (GC 6.3.9) 8
  • 10. GC 6.3 – Change Directive (con’t): • New 2008:  Owner has access rights to Contractor’s  “pertinent documents” related to the cost of performing the  work on the Change Directive  (GC 6.3.10) 9
  • 11. Incomplete, wrong, and incompatible designs; • Unclear or vague specifications; • Unexpected site conditions; • Shifting owner requirements for design, work scope or  scheduling; • Updated construction methods; • Changes to access and sequencing of the work; • emergencies; and • Changes mandated by regulatory authorities. 10
  • 12. When there is agreement and documentation… • Signed and agreed upon Change Order • An agreed upon Change Directive • No change documentation, but parties agree to an  adjustment in Contract Time or Contract Price 11
  • 13. 12
  • 14. Contractor has done extra work, but Owner has not issued  Change Order or Change Directive – will the extra work be  compensable? • CCDC 2:  Contractor shall not perform a change in the Work  without Change Order or Change Directive (GC 6.1.2) 13
  • 15. CCDC 2:  The Contract supersedes all prior negotiations,  representations, or agreements, either written or oral,  relating …to the Work…(Article A‐2) • CCDC 2:   The Contract may be amended only as provided in  the Contract Documents Is a change in the Work compensable as an extra when there  is no supporting “paperwork”? 14
  • 16. Owner wants to build a motel – asks a contractor to bid on  the project based on an original set of plans • Contractor bids on the project based on those plans • Owner then gives contractor additional specifications and  asked contractor to include specifications in the bid • CCDC 2 contract signed – attaches both the original plans  and  the additional specifications • There were conflicts in the work between original plans and  additional specifications • Some items in original plans were traded for items in  additional specifications • Contract price did not change   15
  • 17. Other changes were made before and after contract was  signed – finished motel very different from original plans • Plans, contract and price were not amended to reflect  changes • Contractor was given a revised site plan after signing the  contract – owner told contractor he would pay for any extra  charges • Multiple disputes arise – contractor claims for unpaid  contract price and extras, and owner counterclaims for delay  and deficiencies – the ``Classic``or ``Sam`s Special`` 16
  • 18. Owner says: • most of the extras are not ``extra`` to the contract as  contractor knew that work was required before the  contract was entered into and included in contract price • Owner also says if work not included in contract then  not payable because no written change order  • The contract says:  ``…all deviations or additions from or to  the plans and specifications …shall be approved, in advance,  in writing and signed by the Owner and Contractor with  agreed costs for such deviations and conditions…`` 17
  • 19. Contract had standard change order provisions • Defendant says: • Owner knew changes had to be in writing, but he did not  want to spend extra money on administration • Owner did not want to spend money revising plans • Contractor asked for confirmation of changes in writing,  but did not receive them, and had to carry on with work • He trusted the owner… 18
  • 20. General rule:  parol evidence is inadmissible to vary written  agreement if contradicts written agreement • If parties cannot stray from the written agreement, then  there should be no compensation for extras without written  change order or change directive • Any guesses on what happened? 19
  • 21. Our B.C. Supreme Court found in favour of the contractor • Key factors for decision: • Both parties aware of contract terms on changes, and  both chose to ignore them • Contractor requested written change orders and  revisions to plans but owner refused to provide • No consultant on site to administer changes – so could  not follow contract procedure • Owner supervised and requested changes 20
  • 22. In these circumstances, owner cannot rely on the contract  provisions that changes be in writing • Moral of the Kei‐Ron story:   1) Reduce risk by following the contract 2) Be clear on what is included in contract work 3) Trust should not negate contract requirements 4) Confirm changes (or any issue) in writing, even if the form  of confirmation is not per contract requirements 21
  • 23. 1. Was the work performed actually extra work? (did work fall  within scope of work originally contemplated by contract?) 2. If yes, did owner give instructions, either express or implied,  In determining liability for the cost of extra that the work be done, or was the work otherwise  work, the first question to be answered is authorized by the owner? performed was,extra11 whether the work in fact, 3. Was the owner informed or necessarily aware that theextra work would increase the cost? 4. Did the owner waive the provision requiring changes to be  made in writing or acquiesce in ignoring these provisions? 22
  • 24. 1. Ensure design is complete before tendering / bidding 2. Address any ambiguities before tendering / bidding in  writing – do not assume 3. Understand site conditions 4. Owners – beware of the low bid – could result in additional  changes 5. If other party refuses to confirm issue in writing, discuss  agreement and confirm it in writing to the other party 6. Use the Consultant for determining issues (GC 2.2.7 & 2.2.8)  before issues become disputes 7. Provide for quantification of changes as a supplementary  condition to avoid dispute 23
  • 25. 8. Use supplementary conditions to address delay scenarios  not addressed in CCDC2 9. Avoid using Change Directive if possible – unresolved /  dispute 10. Contractors should have detailed pricing with appropriate  back up – prevent owner from using “improper  documentation” as reason to delay approval of change 11. Be clear on communications about the impact of a change 12. Contractors do not proceed with a change until instructions  to proceed confirmed in writing 13. Owners avoid verbal approval and expedite change  approval to avoid delay impact on project 24
  • 26. 14. If no change order or change directive, then contractors  can consider: • Seeking an agreement in writing to suspend the dispute  over the change and  allow the Contractor to do the  extra work while preserving the right to resolve the  dispute later; or 25
  • 27. If no change order or change directive, then contractors can  consider: • Do the Work Under Protest: • Section 62 of B.C.’s Law and Equity Act – If dispute arises between parties to a contract respecting the  obligations of a party, the party whose obligations are disputed may, within a reasonable period of time after being informed that  performance is required, provide the demanding party with  notice of intention to perform the disputed requirements under  protest.  The right to claim payment is preserved. – Act allows contracting parties to specify rules for protest notice. 26
  • 28. CCDC 2 – GC 8.1.3:  If a dispute is not resolved promptly: • The Consultant must give any instructions necessary for the  proper performance of the Work to prevent delays pending  settlement of the dispute. • The parties are required to follow instructions immediately  but their rights to make claims are not jeopardized. • If it is subsequently determined that the Consultant’s instructions were in error or at variance with the Contract  Documents, the Owner must pay the Contractor the costs  incurred in carrying out the instructions beyond what the  Contract Documents properly required. 27
  • 29. Sam’s modus operandi for minimizing risk from  changes: Expect Prepare Minimize  Manage Resolve 28
  • 30. These materials are necessarily of a general nature and do not take into consideration any specific matter, client or fact pattern. Please direct inquiries or comments to: Samantha Ip, Partner Clark Wilson LLP ssi@cwilson.com | 604.643.3172 www.cwilson.com