SlideShare a Scribd company logo
1 of 37
Download to read offline
 District Cooling Plant for Rihan Heights 
Project Cash Flow Portfolio 
AWI 106 Att. 8 Rev. 2 06 Jul. 2009 Date/ Rev.
Index 
 Project Cash Flow 
 1 - Cash In Data --------------------------- Section 1 
 1.11 – Cash In-Value of Works & Monthly Invoices --------------------------- Section 1.11 
 1.12 – Cash In Histogram (EPC Project Period). --------------------------- Section 1.12 
 1.13 – Cash In Histogram (Operation and Maintenance Period). --------------------------- Section 1.13 
 2 - Cash Out Data --------------------------- Section 2 
 2.11 – Cash Out-Value of Works & Monthly Invoices --------------------------- Section 2.11 
 2.12 – Cash Out Histogram (EPC Project Period). --------------------------- Section 2.12 
 2.13 – Cash Out Histogram (Operation and Maintenance Period). -------------- Section 2.13 
 3 - Cash Flow ----------------------- Section 3 
 3.11 – Project Cash Flow Curve. --------------------------- Section 3.11 
 3.12 – Project Cash Liquidity. --------------------------- Section 3.12 
AWI 106 Att. 8 Rev. 2 06 Jul. 2009 Date/ Rev.
Section 1 
 Cash In Data 
AWI 106 Att. 8 Rev. 2 06 Jul. 2009 Date/ Rev.
Section 1.11 
 Cash In-Value of Works & Monthly Invoices 
AWI 106 Att. 8 Rev. 2 06 Jul. 2009 Date/ Rev.
Mubadala Capitaland Real Estate 
District Cooling Plant for Rihan Heights 
Cash In Value of Works 
Jul-10 Aug-10 Sep-10 Oct-10 Nov-10 Dec-10 Jan-11 Feb-11 Mar-11 Apr-11 May-11 Jun-11 Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 
Item 
No. Description Value of 
Work 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 
A Preliminaries- Design - Procurement- 
Construction - Testing & Commissioning 49,055,575 
A.1 Preliminaries (See Attachment.1) 7,663,699 29.36% 4.38% 5.71% 7.54% 8.68% 10.01% 14.72% 11.87% 7.74% 
A.2 Design (See Attachment.2) 1,452,016 50.00% 50.00% 
A.3 Procurement (See Attachment.2) 31,210,488 9.45% 4.39% 7.19% 1.04% 18.02% 27.81% 16.05% 16.05% 
A.4 Construction (See Attachment.2) 8,487,050 0.81% 3.75% 8.86% 11.91% 10.51% 25.44% 36.32% 2.40% 
A.5 
Testing & Commissioning (See 
Attachment.2) 242,322 36.98% 51.05% 11.96% 
B Temporary Generator 2,504,439 
B.1 Mobilization Charge 50,323 100.00% 
B.2 Monthly Charge 2,080,224 8.37% 8.33% 8% 8% 8% 8% 8% 8% 8% 8% 8% 8% 
B.3 Demobilization Charge 35,223 100% 
B.4 Generator Installation Charge 338,669 100.00% 
C Operation and Maintenance 1,606,003 
C.1 Operation & Maintenance for 12 motnhs after 
commissioing 1,606,003 8% 8% 8% 8% 8% 8% 8% 8% 8% 8% 8% 8% 
SUBTOTAL 53,166,017 5,924,236 2,500,867 2,999,945 1,655,753 7,298,559 10,336,991 8,775,786 9,300,088 999,740 307,384 307,384 307,063 307,063 307,063 307,063 307,063 307,063 307,063 342,286 133,780 133,780 
53,166,017 - - 5,924,236 2,500,867 2,999,945 1,655,753 7,298,559 10,336,991 8,775,786 9,300,088 999,740 307,384 307,384 307,063 307,063 307,063 307,063 307,063 307,063 307,063 342,286 133,780 133,780 
- - 5 ,924,236 8 ,425,102 1 1,425,048 1 3,080,801 2 0,379,360 3 0,716,351 3 9,492,137 4 8,792,225 4 9,791,964 5 0,099,348 5 0,406,732 5 0,713,795 5 1,020,858 5 1,327,920 5 1,634,983 5 1,942,046 5 2,249,108 5 2,556,171 5 2,898,457 5 3,032,237 5 3,166,017 
Plan. Value of Work - Month 
Plan. Value of Work - Cumulative 
Planned Percent. 11.14% 15.85% 21.49% 24.60% 38.33% 57.77% 74.28% 91.77% 93.65% 94.23% 94.81% 95.39% 95.97% 96.54% 97.12% 97.70% 98.28% 98.85% 99.50% 99.75% 100.00% 
File Name:Cash Flow Page 1 of 2 Printed On:10/20/10 at 1:06 PM
Mubadala Capitaland Real Estate 
District Cooling Plant for Rihan Heights 
Preliminaries (Attachement.1) 
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 
Item No. Description Value 1 2 3 4 5 6 7 8 9 10 11 
A PRELIMINARIES 7,648,386 
A.1 Contractual requirements 1 ,160,988 
A.1.1 Insurance 3 49,273 100% 
A.1.2 Contract Price and Payment 5 46,973 100% 
A.1.3 Enviromental Assessment 3 3,000 100% 
A.1.4 Defect Liability maintenance 2 31,742 100% 
A.2 Services for the Employer's 7 8,981 
A.2.1 Progress Photos 7 70 100% 
A.2.2 Sanitary 7 8,211 100% 
A.3 Temporary Works 2 0,700 
A.3.1 Gates 4 ,400 100% 
A.3.2 Fire Protection 6 ,204 11% 11% 11% 11% 11% 11% 11% 11% 11% 
A.3.3 Safety 1 0,096 11% 11% 11% 11% 11% 11% 11% 11% 11% 
A.4 Contractor Facilities 1 ,154,071 
A.4.1 Facilities Required by Contractor 1 ,154,071 90% 1% 1% 1% 1% 1% 1% 1% 3% 
A.5 Services for the contractor 3 93,049 
A.5.1 Transport of workforce 3 93,049 11% 11% 11% 11% 11% 11% 11% 11% 11% 
A.6 Plant for permanent works (not included in 
construction works) 2 18,244 
A.6.1 Small plant and tools. 3 ,494 11% 11% 11% 11% 11% 11% 11% 11% 11% 
A.6.2 Scaffolding. 2 0,173 14% 14% 14% 14% 14% 14% 14% 
A.6.3 Cranes and lifting plant. 1 94,577 14% 14% 14% 14% 14% 14% 14% 
A.7 Supervision and Labour 4 ,622,353 
A.7.1 Manual Manpower 2 ,909,987 3% 6% 11% 14% 17% 27% 19% 3% 
A.7.2 Non Mnaual Manpower 1 ,712,366 10% 10% 10% 10% 10% 10% 15% 15% 10% 
A.8 Surveys 
A.8.1 Topoghrapic Survey 3 ,123 100% 
A.8.2 Geotechnical Investigation 1 2,190 100% 
SUBTOTAL 7,663,699 2,249,979 335,733 437,314 578,047 664,985 766,940 1,127,722 909,563 593,417 
Plan. Value of Work - Month 7,663,699 - 2,249,979 335,733 437,314 578,047 664,985 766,940 1,127,722 909,563 593,417 - 
Plan. Value of Work - Cumulative - 2,249,979 2,585,712 3,023,026 3,601,073 4,266,058 5,032,998 6,160,719 7,070,282 7,663,699 - 
Planned Percent. 29.36% 33.74% 39.45% 46.99% 55.67% 65.67% 80.39% 92.26% 100.00%
Activity Name Start Finish Budgeted Cost Budgeted 
U 
Mubadala Capitaland Real Estate 
District Cooling Plant for Rihan Heights 
2010 2011 
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 
District Cooling Plant for Rihan Heights 05-Aug-10 12-May-11 49,055,575 15313 5908923 2500867 2999945 1655753 7298559 10336991 8386793 9125973 826457 
Cash Flow 05-Aug-10 12-May-11 49,055,575 15313 5908923 2500867 2999945 1655753 7298559 10336991 8386793 9125973 826457 
District Cooling Plant for Rihan Heights 05-Aug-10 12-May-11 49,055,575 15313 5908923 2500867 2999945 1655753 7298559 10336991 8386793 9125973 826457 
General 05-Aug-10 12-May-11 7,663,699 15313 2234666 335733 437314 578047 664985 766940 1127722 909563 593417 
Mobilization 05-Aug-10 12-May-11 7,663,699 15313 2234666 335733 437314 578047 664985 766940 1127722 909563 593417 
Soil Investigation 05-Aug-10 16-Aug-10 15,313 15313 
Topographic Survey 05-Aug-10 08-Aug-10 3,123 3123 
Geo Technical Investigation Report 14-Aug-10 16-Aug-10 12,190 12190 
Site Offices & Utilities 01-Sep-10 12-May-11 7,648,386 2234666 335733 437314 578047 664985 766940 1127722 909563 593417 
Preliminaries 01-Sep-10 12-May-11 7,648,386 2234666 335733 437314 578047 664985 766940 1127722 909563 593417 
Design and Engineering 01-Sep-10 14-Oct-10 1,452,016 726008 726008 
Design 01-Sep-10 14-Oct-10 1,452,016 726008 726008 
Concept & Schematic Design 01-Sep-10 01-Sep-10 726,008 726008 
Process Equipments 01-Sep-10 01-Sep-10 726,008 726008 
Approve Concept & Schematic Design by Capitala 01-Sep-10 01-Sep-10 726,008 726008 
Detailed Design 02-Oct-10 14-Oct-10 726,008 726008 
Process Equipments 02-Oct-10 14-Oct-10 726,008 726008 
Capitala Approve Detailed Engineering Package 02-Oct-10 14-Oct-10 726,008 726008 
Procurement 29-Sep-10 02-Apr-11 31,210,488 2948249 1370194 2244708 325602 5622982 8678142 5010306 5010306 
Mechanical 29-Sep-10 02-Apr-11 21,892,623 2948249 2244708 325602 2807300 3546152 5010306 5010306 
Procurement & Delivery 29-Sep-10 02-Apr-11 21,892,623 2948249 2244708 325602 2807300 3546152 5010306 5010306 
Plant Module Material 29-Sep-10 02-Apr-11 20,839,464 2948249 2244708 325602 2754642 2545652 5010306 5010306 
Process Equipments 29-Sep-10 02-Apr-11 14,741,247 2948249 886193 886193 5010306 5010306 
Procurement&Delivery of Chillers and Module Enclosure 30-Sep-10 02-Apr-11 10,020,611 2004122 4008245 4008245 
Procurement&Delivery of Chilled Water Pump 30-Sep-10 02-Apr-11 2,505,153 501031 1002061 1002061 
Delivery of Cooling Tower 29-Sep-10 04-Feb-11 2,215,482 443096 886193 886193 
Pipes & Valves 01-Nov-10 28-Feb-11 2,713,346 1953609 325602 434135 
Chilled&Condenser System 01-Nov-10 28-Feb-11 2,713,346 1953609 325602 434135 
Procurement&Delivery of Chilled&Condeser Water Pipes 18-Dec-10 18-Dec-10 325,602 325602 
Procurement&Delivery of Chilled Water Reticulation Polyethylene Pipes 01-Nov-10 07-Nov-10 1,953,609 1953609 
Procurement&Delivery of Chilled Water (Valves-Accessories-Fittings) 16-Feb-11 28-Feb-11 298,468 298468 
Procurement&Delivery of Buterflly Valves 16-Feb-11 28-Feb-11 135,667 135667 
Heat Exchanger 08-Nov-10 16-Feb-11 3,384,872 291099 1868449 1225324 
Procurement&Delivery of Heat Exchangers 08-Nov-10 16-Feb-11 1,455,495 291099 582198 582198 
Procurement&Delivery of Heat Exchanger Valves 16-Feb-11 16-Feb-11 643,126 643126 
Procurement&Delivery of Heat Exchanger Pipes 16-Jan-11 17-Jan-11 1,286,251 1286251 
Building Services Materials 16-Jan-11 21-Feb-11 1,053,158 52658 1000500 
Fire Fighting 16-Jan-11 21-Feb-11 1,053,158 52658 1000500 
Procurement&Delivery of Fire System (FM200 or Pre-Action) 16-Feb-11 21-Feb-11 947,843 947843 
Procurement&Delivery of Fire Sprinklers 16-Feb-11 21-Feb-11 52,658 52658 
Procurement&Delivery of Fire Pipes 16-Jan-11 16-Jan-11 52,658 52658 
Electrical 20-Oct-10 28-Feb-11 9,317,866 1370194 2815682 5131990 
Procurement & Delivery 20-Oct-10 28-Feb-11 9,317,866 1370194 2815682 5131990 
Plant Module Materials 20-Oct-10 28-Feb-11 9,317,866 1370194 2815682 5131990 
Process Equipments 20-Oct-10 28-Feb-11 8,614,975 1370194 2740388 4504393 
Procurement&Delivery of SCADA System 26-Feb-11 28-Feb-11 1,764,005 1764005 
Procurement&Delivery of Electrical Module Enclosure (LV-MV) 20-Oct-10 23-Feb-11 6,850,970 1370194 2740388 2740388 
Transformers 01-Feb-11 15-Feb-11 627,597 627597 
Procurement&Delivery of 11 KV Transformers (Dry Type) 01-Feb-11 15-Feb-11 627,597 627597 
Others 16-Jan-11 23-Jan-11 75,294 75294 
Procurement&Delivery of UPS 16-Jan-11 23-Jan-11 75,294 75294 
Construction 23-Oct-10 12-May-11 8,487,050 68932 317923 752104 1010593 891909 2159155 3082388 204047 
District Cooling Modular Plant 23-Oct-10 09-May-11 4,589,366 32655 100008 255298 192248 212353 1146293 2501219 149291 
Civil 23-Oct-10 10-Mar-11 656,575 32655 100008 255298 182945 47669 38000 
Cooling Tower Module 23-Oct-10 09-Jan-11 521,502 20130 100008 255298 146066 
Foundation Level 23-Oct-10 08-Dec-10 168,928 20130 100008 48791 
Earth Work 23-Oct-10 21-Nov-10 74,909 20130 54779 
Waterproofing Sheet & Screed over 13-Nov-10 21-Nov-10 31,843 31843 
Installation of Dewatering System Equipment 26-Oct-10 28-Oct-10 6,710 6710 
Initial Excavation 23-Oct-10 25-Oct-10 6,710 6710 
Formation and Blinding 07-Nov-10 11-Nov-10 11,752 11752 
Excavation 02-Nov-10 06-Nov-10 8,947 8947 
Draw down the Underground Water 29-Oct-10 01-Nov-10 8,947 6710 2237 
Foundations 22-Nov-10 08-Dec-10 94,020 45229 48791 
Steel Fixing 22-Nov-10 05-Dec-10 35,257 25642 9616 
Form Work 25-Nov-10 06-Dec-10 35,257 19587 15670 
Concrete Pouring 08-Dec-10 08-Dec-10 23,505 23505 
Ground Floor 09-Dec-10 09-Jan-11 352,574 206508 146066 
Walls 09-Dec-10 23-Dec-10 176,287 176287 
Steel Fixing of Tank Walls 09-Dec-10 15-Dec-10 70,515 70515 
Form Work of Tank Walls 13-Dec-10 22-Dec-10 70,515 70515 
Concrete Pouring 23-Dec-10 23-Dec-10 35,257 35257 
Slab 28-Dec-10 09-Jan-11 176,287 30221 146066 
Steel Fixing of Tank Slab 02-Jan-11 08-Jan-11 70,515 70515 
Form Work of Tank Slab 28-Dec-10 05-Jan-11 70,515 30221 40294 
Concrete Pouring 09-Jan-11 09-Jan-11 35,257 35257 
LV Switchgear Module 23-Oct-10 06-Feb-11 67,536 6263 36878 24395 
Foundation Level 23-Oct-10 06-Feb-11 67,536 6263 36878 24395 
Earth Work 23-Oct-10 22-Jan-11 20,526 6263 14264 
Waterproofing Sheet & Screed over 16-Jan-11 22-Jan-11 8,388 8388 
Formation and Blinding 10-Jan-11 15-Jan-11 5,876 5876 
Excavation 23-Oct-10 30-Oct-10 6,263 6263 
Foundations 23-Jan-11 06-Feb-11 47,010 22615 24395 
Steel Fixing 23-Jan-11 03-Feb-11 17,629 12821 4808 
Form Work 26-Jan-11 05-Feb-11 17,629 9794 7835 
Concrete Pouring 06-Feb-11 06-Feb-11 11,752 11752 
Chiller Module 23-Oct-10 10-Mar-11 67,536 6263 23274 38000 
Foundation Level 23-Oct-10 10-Mar-11 67,536 6263 23274 38000 
Earth Work 23-Oct-10 23-Feb-11 20,526 6263 14264 
Data Date : 18-Jul-10 
Page : 1 of 8 
Printed On : 22-Sep-10 
Project Implementation Schedule 
Value of Work in Dirhams (Attachment .2) 
Date Revision Checked Approved 
15-Aug-10 Project Implementation Schedule Rev.00 
21-Sep-10 Project Implementation Schedule Rev.01
Activity Name Start Finish Budgeted Cost Budgeted 
U 
Mubadala Capitaland Real Estate 
District Cooling Plant for Rihan Heights 
2010 2011 
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 
Waterproofing Sheet & Screed over 16-Feb-11 23-Feb-11 8,388 8388 
Formation and Blinding 07-Feb-11 14-Feb-11 5,876 5876 
Excavation 23-Oct-10 30-Oct-10 6,263 6263 
Foundations 24-Feb-11 10-Mar-11 47,010 9010 38000 
Steel Fixing 24-Feb-11 07-Mar-11 17,629 7051 10577 
Form Work 28-Feb-11 09-Mar-11 17,629 1959 15670 
Concrete Pouring 10-Mar-11 10-Mar-11 11,752 11752 
Architectural 27-Jan-11 25-Apr-11 174,405 9303 53494 62780 48829 
Make Up Water Tank 27-Jan-11 26-Feb-11 58,147 9303 48843 
GRP Lining for Make Up Water Tank 27-Jan-11 26-Feb-11 58,147 9303 48843 
Blow Down 27-Feb-11 27-Mar-11 58,129 4650 53479 
GRP Lining for Blow Down 27-Feb-11 27-Mar-11 58,129 4650 53479 
FireTank 28-Mar-11 25-Apr-11 58,129 9301 48829 
GRP Lining for Fire Tank 28-Mar-11 25-Apr-11 58,129 9301 48829 
Mechanical 05-Feb-11 07-May-11 1,923,871 21406 169441 1660908 72117 
Cooling Tower Module 05-Feb-11 23-Apr-11 246,165 21406 37674 187085 
Install Cooling Tower Components (FRP) 05-Feb-11 30-Mar-11 49,233 21406 27827 
Install Cooling Tower 31-Mar-11 23-Apr-11 196,932 9847 187085 
Chiller Module 03-Apr-11 23-Apr-11 362,588 362588 
Install Chiller Module Enclosure 13-Apr-11 23-Apr-11 296,663 296663 
Install Chiller Module Base Frame 03-Apr-11 12-Apr-11 65,925 65925 
Chilled Water Pumps 03-Apr-11 11-Apr-11 296,663 296663 
Install Chilled Water Pump 03-Apr-11 11-Apr-11 296,663 296663 
Make Up Water Pump 13-Mar-11 28-Mar-11 115,271 115271 
Install Make Up Water Pump 24-Mar-11 28-Mar-11 44,351 44351 
Install Make Up Water Pipes & Access. 13-Mar-11 23-Mar-11 70,920 70920 
Blow Down Pump 01-Mar-11 12-Mar-11 16,496 16496 
Install Blow Down Water Pipes & Access. 01-Mar-11 12-Mar-11 16,496 16496 
Other Systems 05-Apr-11 07-May-11 886,689 814572 72117 
Install the Process Instrument 24-Apr-11 07-May-11 144,233 72116 72117 
Install Expansion Tank-Outside the Modular 05-Apr-11 12-Apr-11 38,440 38440 
Install Chemical Water Treatment-Outside the Modular 14-Apr-11 21-Apr-11 510,697 510697 
Install Air Seperator 05-Apr-11 12-Apr-11 193,319 193319 
Electrical 24-Feb-11 09-May-11 1,834,515 89785 876073 791482 77175 
Attendance and Coordination by ADWEA 24-Feb-11 01-May-11 39,732 2788 18820 17426 697 
MV & LV Switchgear Module Foundation 24-Feb-11 10-Apr-11 761,219 86996 587226 86996 
Install MV Switch gear 26-Mar-11 10-Apr-11 152,244 65247 86996 
Install Electrical Module Enclosure (LV) 13-Mar-11 28-Mar-11 304,488 304488 
Install Electrical Module Base Frame (LV) 24-Feb-11 12-Mar-11 304,488 86996 217491 
Transformers 19-Mar-11 04-Apr-11 69,733 55786 13947 
Install Transformers 19-Mar-11 04-Apr-11 69,733 55786 13947 
Cables Works 03-Mar-11 09-May-11 870,015 214240 632906 22868 
Excavation 12-Mar-11 16-Mar-11 16,850 16850 
Excavation Cable Trenches 12-Mar-11 16-Mar-11 16,850 16850 
Cable Trays 03-Mar-11 19-Mar-11 67,401 67401 
Cable Trays at Transformer Room 03-Mar-11 07-Mar-11 25,276 25276 
Cable Trays at Pump Room 14-Mar-11 19-Mar-11 16,850 16850 
Cable Trays at ADDC Room 08-Mar-11 13-Mar-11 25,276 25276 
Cables 16-Mar-11 09-May-11 785,763 129988 632906 22868 
MV Cables 30-Mar-11 01-May-11 252,755 19258 231091 2407 
From ADDC Intake to 11 KV Switchgear 07-Apr-11 12-Apr-11 84,252 84252 
MV Cable Termination for 11 KV Switch gear 11-Apr-11 12-Apr-11 16,850 16850 
MV Cable Laying 07-Apr-11 10-Apr-11 67,401 67401 
From 11 KV Switchgear to Chiller Soft Starter 30-Mar-11 01-May-11 84,252 19258 62587 2407 
MV Cable Termination for Chiller Soft Starter 24-Apr-11 01-May-11 16,850 14443 2407 
MV Cable Laying 30-Mar-11 06-Apr-11 67,401 19258 48144 
From 11 KV Switchgear to Transformer 11-Apr-11 14-Apr-11 84,252 84252 
MV Cable Termination for Transformer 13-Apr-11 14-Apr-11 16,850 16850 
MV Cable Laying 11-Apr-11 12-Apr-11 67,401 67401 
LV Cables 24-Mar-11 03-May-11 252,755 96288 149246 7222 
From Transformer to LV Switchgear 24-Mar-11 20-Apr-11 84,252 67401 16850 
LV Cable Termination for LV Switch gear 05-Apr-11 20-Apr-11 16,850 16850 
LV Cable Laying 24-Mar-11 28-Mar-11 67,401 67401 
From LV Switchgear to Starter or VFD of Pump 29-Mar-11 03-May-11 84,252 28886 48144 7222 
LV Cable Termination for Starter or VFD of Pumps 26-Apr-11 03-May-11 16,850 9629 7222 
LV Cable Laying 29-Mar-11 05-Apr-11 67,401 28886 38515 
From LV Switchgear to Distribution Board 06-Apr-11 25-Apr-11 84,252 84252 
LV Cable Termination for Distribution Board 21-Apr-11 25-Apr-11 16,850 16850 
LV Cable Laying 06-Apr-11 10-Apr-11 67,401 67401 
Control & Fibre Optic Cables 16-Mar-11 09-May-11 280,252 14443 252570 13240 
Fibre Optic Cables 10-Apr-11 08-May-11 238,126 229701 8425 
Installation of Control System 14-Apr-11 30-Apr-11 196,001 196001 
Fibre Optic Cable Termination 01-May-11 08-May-11 8,425 8425 
Fibre Optic Cable Laying Inside Control Room 10-Apr-11 13-Apr-11 33,701 33701 
Control Cables 16-Mar-11 09-May-11 42,126 14443 22868 4814 
Control Cable Termination for Control Cables 24-Apr-11 09-May-11 8,425 3611 4814 
Control Cable Laying Outside Control Room 16-Mar-11 09-Apr-11 16,850 11234 5617 
Control Cable Laying Inside Control Room 28-Mar-11 20-Apr-11 16,850 3210 13641 
Earthing System 24-Apr-11 09-May-11 93,816 40207 53609 
Installation of Earthing System 24-Apr-11 09-May-11 93,816 40207 53609 
Ancillary Building 23-Oct-10 12-May-11 1,574,202 36277 78773 139081 240926 264970 450785 308634 54756 
Civil 23-Oct-10 17-Feb-11 641,962 36277 78773 139081 240926 146906 
Foundation Level 23-Oct-10 23-Dec-10 207,121 36277 78773 92071 
Earth Work 23-Oct-10 08-Nov-10 65,287 36277 29010 
Waterproofing Sheet & Screed over 03-Nov-10 08-Nov-10 24,309 24309 
Formation and Blinding 28-Oct-10 02-Nov-10 11,752 7051 4701 
Excavation 23-Oct-10 27-Oct-10 29,225 29225 
Foundations 09-Nov-10 23-Dec-10 141,834 49763 92071 
Water Proofing & Backfilling up to Slab on Grade Level 16-Dec-10 18-Dec-10 9,804 9804 
Data Date : 18-Jul-10 
Page : 2 of 8 
Printed On : 22-Sep-10 
Project Implementation Schedule 
Value of Work in Dirhams (Attachment .2) 
Date Revision Checked Approved 
15-Aug-10 Project Implementation Schedule Rev.00 
21-Sep-10 Project Implementation Schedule Rev.01
Activity Name Start Finish Budgeted Cost Budgeted 
U 
Mubadala Capitaland Real Estate 
District Cooling Plant for Rihan Heights 
2010 2011 
Data Date : 18-Jul-10 
Page : 3 of 8 
Printed On : 22-Sep-10 
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 
Water Proofing & Backfilling up to Grid Beam Level 28-Nov-10 29-Nov-10 9,804 9804 
Steel Fixing of Tie Beams 12-Dec-10 14-Dec-10 14,103 14103 
Steel Fixing of Nick Columns&Trenches 30-Nov-10 05-Dec-10 14,103 3526 10577 
Steel Fixing of Footings 13-Nov-10 25-Nov-10 14,103 14103 
Form Work of Tie Beams 09-Dec-10 13-Dec-10 14,103 14103 
Form Work of Nick Columns&Trenches 04-Dec-10 06-Dec-10 14,103 14103 
Form Work of Footings 09-Nov-10 22-Nov-10 14,103 14103 
Concrete Pouring of Tie Beams 15-Dec-10 15-Dec-10 8,227 8227 
Concrete Pouring of Slab on Grade 19-Dec-10 23-Dec-10 12,928 12928 
Concrete Pouring of Nick Columns&Trenches 08-Dec-10 08-Dec-10 8,227 8227 
Concrete Pouring of Footings 27-Nov-10 27-Nov-10 8,227 8227 
Ground Floor 25-Dec-10 08-Feb-11 188,040 47010 129277 11752 
Steel Fixing of Slab 10-Jan-11 13-Jan-11 47,010 47010 
Steel Fixing of Columns 25-Dec-10 27-Dec-10 23,505 23505 
R.C Plinths for Process Equipment 03-Feb-11 08-Feb-11 11,752 11752 
MEP Works Inside Slab 10-Jan-11 12-Jan-11 11,752 11752 
Form Work of Slab 05-Jan-11 09-Jan-11 47,010 47010 
Form Work of Columns 28-Dec-10 30-Dec-10 23,505 23505 
Concrete Pouring of Slab 15-Jan-11 15-Jan-11 11,752 11752 
Concrete Pouring of Columns 02-Jan-11 02-Jan-11 11,752 11752 
First Floor 16-Jan-11 06-Feb-11 188,040 111648 76391 
Steel Fixing of Slab 01-Feb-11 05-Feb-11 52,886 52886 
Steel Fixing of Columns 16-Jan-11 18-Jan-11 23,505 23505 
MEP Works Inside Slab 02-Feb-11 05-Feb-11 11,752 11752 
Form Work of Slab 26-Jan-11 31-Jan-11 52,886 52886 
Form Work of Columns 18-Jan-11 20-Jan-11 23,505 23505 
Concrete Pouring of Slab 06-Feb-11 06-Feb-11 11,752 11752 
Concrete Pouring of Columns 22-Jan-11 22-Jan-11 11,752 11752 
Roof Level 07-Feb-11 17-Feb-11 58,762 58762 
Steel Fixing of Parapits 07-Feb-11 13-Feb-11 23,505 23505 
Form Work of Parapets 10-Feb-11 16-Feb-11 23,505 23505 
Concrete Pouring of Parapets 17-Feb-11 17-Feb-11 11,752 11752 
Architectural 09-Feb-11 12-May-11 466,727 77317 197655 162238 29517 
Ground Floor 09-Feb-11 07-May-11 182,934 54215 124552 1018 3148 
ADDC Intake Room 09-Feb-11 04-May-11 61,196 20063 39285 1848 
Plaster Works 01-Mar-11 07-Mar-11 3,698 3698 
Install Windows and Doors Works 26-Mar-11 27-Mar-11 30,040 30040 
Install Windows & Doors Frames 23-Feb-11 24-Feb-11 3,338 3338 
Final Paint Coat Works 02-May-11 04-May-11 1,848 1848 
Epoxy Coating 14-Mar-11 17-Mar-11 3,698 3698 
Blocks Works 09-Feb-11 21-Feb-11 16,725 16725 
Base Paint Coat Works 21-Mar-11 23-Mar-11 1,848 1848 
Pumps Room 22-Feb-11 01-May-11 45,689 11179 32984 1018 509 
Plaster Works 09-Mar-11 13-Mar-11 3,055 3055 
Install Windows and Doors Works 30-Mar-11 31-Mar-11 25,347 25347 
Install Windows & Doors Frames 27-Feb-11 28-Feb-11 2,816 2816 
Final Paint Coat Works 28-Apr-11 01-May-11 1,527 1018 509 
Epoxy Coating 20-Mar-11 23-Mar-11 3,055 3055 
Blocks Works 22-Feb-11 26-Feb-11 8,362 8362 
Base Paint Coat Works 27-Mar-11 29-Mar-11 1,527 1527 
Transformers Room 09-Feb-11 07-May-11 76,049 22974 52284 791 
Plaster Works 27-Feb-11 02-Mar-11 1,583 792 792 
Install Windows and Doors Works 19-Mar-11 20-Mar-11 49,117 49117 
Install Windows & Doors Frames 23-Feb-11 24-Feb-11 5,457 5457 
Final Paint Coat Works 04-May-11 07-May-11 791 791 
Epoxy Coating 08-Mar-11 12-Mar-11 1,583 1583 
Blocks Works 09-Feb-11 16-Feb-11 16,725 16725 
Base Paint Coat Works 15-Mar-11 17-Mar-11 791 791 
First Floor 26-Feb-11 12-May-11 249,296 5854 55854 161220 26369 
Office 05-Mar-11 22-Apr-11 128,566 21163 107404 
Plaster Works 22-Mar-11 26-Mar-11 3,829 3829 
Install Windows and Doors 09-Apr-11 09-Apr-11 11,876 11876 
Install Windows & Doors Frames 14-Mar-11 15-Mar-11 1,320 1320 
Install Furniture 21-Apr-11 22-Apr-11 88,349 88349 
Install False Ceiling Tiles 10-Apr-11 11-Apr-11 1,914 1914 
Install False Ceiling Frames 05-Apr-11 07-Apr-11 1,914 1914 
Floor Tiles 27-Mar-11 30-Mar-11 3,829 3829 
Final Paint Coat Works 18-Apr-11 20-Apr-11 1,914 1914 
Blocks Works 05-Mar-11 10-Mar-11 11,707 11707 
Base Paint Coat Works 31-Mar-11 04-Apr-11 1,914 479 1436 
Control Room 26-Feb-11 12-May-11 27,570 5854 11578 9153 985 
Plaster Works 14-Mar-11 17-Mar-11 1,971 1971 
Install Windows and Doors 27-Apr-11 28-Apr-11 7,183 7183 
Install Windows & Doors Frames 07-Mar-11 08-Mar-11 798 798 
Install False Ceiling Tiles 25-Apr-11 26-Apr-11 985 985 
Install False Ceiling Frames 21-Apr-11 24-Apr-11 985 985 
Floor Tiles 19-Mar-11 22-Mar-11 1,971 1971 
Final Paint Coat Works 10-May-11 12-May-11 985 985 
Blocks Works 26-Feb-11 03-Mar-11 11,707 5854 5854 
Base Paint Coat Works 23-Mar-11 27-Mar-11 985 985 
Toilets 12-Mar-11 17-Apr-11 11,889 5005 6884 
Waterproofing Membrane for Toilet 26-Mar-11 26-Mar-11 671 671 
Install Windows and Doors 10-Apr-11 11-Apr-11 5,263 5263 
Install Windows & Doors Frames 15-Mar-11 16-Mar-11 585 585 
Install Toilet Accessories 14-Apr-11 17-Apr-11 405 405 
Install False Ceiling Tiles 12-Apr-11 13-Apr-11 405 405 
Install False Ceiling Frames 09-Apr-11 09-Apr-11 405 405 
Floor & Wall Tiles 31-Mar-11 02-Apr-11 810 405 405 
Blocks Works 12-Mar-11 14-Mar-11 3,345 3345 
Project Implementation Schedule 
Value of Work in Dirhams (Attachment .2) 
Date Revision Checked Approved 
15-Aug-10 Project Implementation Schedule Rev.00 
21-Sep-10 Project Implementation Schedule Rev.01
Activity Name Start Finish Budgeted Cost Budgeted 
U 
Mubadala Capitaland Real Estate 
District Cooling Plant for Rihan Heights 
2010 2011 
Data Date : 18-Jul-10 
Page : 4 of 8 
Printed On : 22-Sep-10 
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 
Kitchen 15-Mar-11 03-May-11 30,568 4600 8641 17327 
Waterproofing Membrane for Kitchen 30-Mar-11 30-Mar-11 671 671 
Install Windows and Doors 13-Apr-11 14-Apr-11 5,263 5263 
Install Windows & Doors Frames 19-Mar-11 20-Mar-11 585 585 
Install Kitchen Equipment 02-May-11 03-May-11 17,327 17327 
Install False Ceiling Tiles 16-Apr-11 16-Apr-11 845 845 
Install False Ceiling Frames 10-Apr-11 12-Apr-11 845 845 
Floor & Wall Tiles 03-Apr-11 04-Apr-11 1,689 1689 
Blocks Works 15-Mar-11 17-Mar-11 3,345 3345 
Mess Room 19-Mar-11 07-May-11 18,038 8947 8613 479 
Plaster Works 04-Apr-11 07-Apr-11 957 957 
Install Windows and Doors 21-Apr-11 23-Apr-11 5,263 5263 
Install Windows & Doors Frames 24-Mar-11 26-Mar-11 585 585 
Install False Ceiling Tiles 24-Apr-11 25-Apr-11 479 479 
Install False Ceiling Frames 18-Apr-11 20-Apr-11 479 479 
Floor Tiles 09-Apr-11 12-Apr-11 957 957 
Final Paint Coat Works 04-May-11 07-May-11 479 479 
Blocks Works 19-Mar-11 23-Mar-11 8,362 8362 
Base Paint Coat Works 13-Apr-11 17-Apr-11 479 479 
Store 24-Mar-11 12-May-11 32,664 4560 20526 7578 
Plaster Works 09-Apr-11 12-Apr-11 2,740 2740 
Install Windows and Doors 26-Apr-11 27-Apr-11 10,938 10938 
Install Windows & Doors Frames 30-Mar-11 31-Mar-11 1,215 1215 
Install Sinage 08-May-11 12-May-11 6,208 6208 
Install False Ceiling Tiles 28-Apr-11 30-Apr-11 1,370 1370 
Install False Ceiling Frames 23-Apr-11 25-Apr-11 1,370 1370 
Floor Tiles 13-Apr-11 17-Apr-11 2,740 2740 
Final Paint Coat Works 08-May-11 10-May-11 1,370 1370 
Blocks Works 24-Mar-11 29-Mar-11 3,345 3345 
Base Paint Coat Works 18-Apr-11 21-Apr-11 1,370 1370 
Roof Level 27-Feb-11 02-Mar-11 34,497 17249 17249 
Primer and Membrane 27-Feb-11 02-Mar-11 34,497 17249 17249 
Mechanical 27-Feb-11 07-May-11 388,617 35823 224410 108782 19601 
Ground Floor 27-Feb-11 03-May-11 160,836 35823 55884 65379 3750 
ADDC Intake Room 28-Mar-11 18-Apr-11 41,361 20060 21301 
Fire Fighting 28-Mar-11 04-Apr-11 35,105 20060 15045 
Install Fire System (FM200 or Pre-Action) 28-Mar-11 04-Apr-11 35,105 20060 15045 
HVAC 13-Apr-11 18-Apr-11 6,256 6256 
Install Split Unit 13-Apr-11 18-Apr-11 6,256 6256 
Pumps Room 27-Feb-11 27-Apr-11 78,120 35823 35823 6473 
Fire Fighting 19-Apr-11 21-Apr-11 223 223 
Install Extinguishers 19-Apr-11 21-Apr-11 223 223 
HVAC 23-Apr-11 27-Apr-11 6,250 6250 
Install Ventilation 23-Apr-11 27-Apr-11 6,250 6250 
Plumbing 27-Feb-11 02-Mar-11 71,647 35823 35823 
Install Water Supply System Pipes with Fittings 27-Feb-11 02-Mar-11 27,530 13765 13765 
Install Drain Pipes System Pipes with Fittings 27-Feb-11 02-Mar-11 44,117 22059 22059 
Transformers Room 05-Apr-11 03-May-11 41,355 37605 3750 
Fire Fighting 05-Apr-11 12-Apr-11 35,105 35105 
Install Fire System (FM200 or Pre-Action) 05-Apr-11 12-Apr-11 35,105 35105 
HVAC 28-Apr-11 03-May-11 6,250 2500 3750 
Install Ventilation 28-Apr-11 03-May-11 6,250 2500 3750 
First Floor 12-Mar-11 07-May-11 227,781 168527 43403 15851 
Office 12-Mar-11 17-Apr-11 15,611 7021 8590 
Fire Fighting 12-Mar-11 13-Apr-11 9,361 7021 2340 
Install Fire Sprinkler 12-Apr-11 13-Apr-11 2,340 2340 
Install Fire Pipes 12-Mar-11 16-Mar-11 7,021 7021 
HVAC 12-Apr-11 17-Apr-11 6,250 6250 
Install Split Unit 12-Apr-11 17-Apr-11 6,250 6250 
Control Room 17-Mar-11 02-May-11 15,611 7021 6090 2500 
Fire Fighting 17-Mar-11 28-Apr-11 9,361 7021 2340 
Install Fire Sprinkler 27-Apr-11 28-Apr-11 2,340 2340 
Install Fire Pipes 17-Mar-11 22-Mar-11 7,021 7021 
HVAC 27-Apr-11 02-May-11 6,250 3750 2500 
Install Split Unit 27-Apr-11 02-May-11 6,250 3750 2500 
Toilets 15-Mar-11 25-Apr-11 78,098 71626 6473 
Fire Fighting 23-Apr-11 25-Apr-11 223 223 
Install Extinguishers 23-Apr-11 25-Apr-11 223 223 
HVAC 14-Apr-11 19-Apr-11 6,250 6250 
Install Ventilation 14-Apr-11 19-Apr-11 6,250 6250 
Plumbing 15-Mar-11 19-Mar-11 71,626 71626 
Install Water Supply System Pipes with Fittings 15-Mar-11 19-Mar-11 27,521 27521 
Install Drain Pipes System Pipes with Fittings 15-Mar-11 19-Mar-11 44,104 44104 
Kitchen 20-Mar-11 01-May-11 87,237 78647 7420 1170 
Fire Fighting 23-Mar-11 01-May-11 9,361 7021 1170 1170 
Install Fire Sprinkler 30-Apr-11 01-May-11 2,340 1170 1170 
Install Fire Pipes 23-Mar-11 28-Mar-11 7,021 7021 
HVAC 17-Apr-11 21-Apr-11 6,250 6250 
Install Split Unit 17-Apr-11 21-Apr-11 6,250 6250 
Plumbing 20-Mar-11 23-Mar-11 71,626 71626 
Install Water Supply System Pipes with Fittings 20-Mar-11 23-Mar-11 27,521 27521 
Install Drain Pipes System Pipes with Fittings 20-Mar-11 23-Mar-11 44,104 44104 
Mess Room 29-Mar-11 03-May-11 15,611 4213 7808 3590 
Fire Fighting 29-Mar-11 03-May-11 9,361 4213 2808 2340 
Install Fire Sprinkler 02-May-11 03-May-11 2,340 2340 
Install Fire Pipes 29-Mar-11 03-Apr-11 7,021 4213 2808 
HVAC 26-Apr-11 01-May-11 6,250 5000 1250 
Install Split Unit 26-Apr-11 01-May-11 6,250 5000 1250 
Store 04-Apr-11 07-May-11 15,611 7021 8590 
Project Implementation Schedule 
Value of Work in Dirhams (Attachment .2) 
Date Revision Checked Approved 
15-Aug-10 Project Implementation Schedule Rev.00 
21-Sep-10 Project Implementation Schedule Rev.01
Activity Name Start Finish Budgeted Cost Budgeted 
U 
Mubadala Capitaland Real Estate 
District Cooling Plant for Rihan Heights 
2010 2011 
Data Date : 18-Jul-10 
Page : 5 of 8 
Printed On : 22-Sep-10 
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 
Fire Fighting 04-Apr-11 05-May-11 9,361 7021 2340 
Install Fire Sprinkler 04-May-11 05-May-11 2,340 2340 
Install Fire Pipes 04-Apr-11 09-Apr-11 7,021 7021 
HVAC 02-May-11 07-May-11 6,250 6250 
Install Split Unit 02-May-11 07-May-11 6,250 6250 
Electrical 17-Feb-11 08-May-11 76,895 4923 28720 37614 5638 
Ground Floor 17-Feb-11 13-Apr-11 25,741 4923 11421 9396 
ADDC Intake Room 19-Feb-11 02-Apr-11 9,400 2276 6857 267 
Electrical System 19-Feb-11 02-Apr-11 4,944 2276 2401 267 
PVC Conduits Installation for Electrical 19-Feb-11 23-Feb-11 942 942 
Pulling the Wires 24-Feb-11 28-Feb-11 1,334 1334 
Lighting & Power Fixtuers and Accessories installation 28-Mar-11 02-Apr-11 1,334 1067 267 
Distribution Board Installation 19-Mar-11 20-Mar-11 1,334 1334 
Fire Alarm 28-Mar-11 30-Mar-11 4,457 4457 
Installation of Fire Alram Devices 28-Mar-11 30-Mar-11 4,457 4457 
Pump Room 27-Feb-11 07-Apr-11 6,945 375 3230 3339 
Electrical System 27-Feb-11 07-Apr-11 4,939 375 3230 1334 
PVC Conduits Installation for Electrical 27-Feb-11 03-Mar-11 938 375 563 
Pulling the Wires 05-Mar-11 08-Mar-11 1,334 1334 
Lighting & Power Fixtuers and Accessories installation 03-Apr-11 07-Apr-11 1,334 1334 
Distribution Board Installation 24-Mar-11 26-Mar-11 1,334 1334 
Fire Alarm 02-Apr-11 04-Apr-11 2,005 2005 
Installation of Fire Alram Devices 02-Apr-11 04-Apr-11 2,005 2005 
Transformer Room 17-Feb-11 13-Apr-11 9,396 2272 1334 5790 
Electrical System 17-Feb-11 13-Apr-11 4,939 2272 1334 1334 
PVC Conduits Installation for Electrical 17-Feb-11 21-Feb-11 938 938 
Pulling the Wires 22-Feb-11 24-Feb-11 1,334 1334 
Lighting & Power Fixtuers and Accessories installation 09-Apr-11 13-Apr-11 1,334 1334 
Distribution Board Installation 13-Mar-11 14-Mar-11 1,334 1334 
Fire Alarm 05-Apr-11 07-Apr-11 4,457 4457 
Installation of Fire Alram Devices 05-Apr-11 07-Apr-11 4,457 4457 
First Floor 06-Mar-11 08-May-11 51,155 17299 28218 5638 
Office 13-Mar-11 16-Apr-11 9,402 3605 5797 
Electrical System 13-Mar-11 16-Apr-11 7,174 3605 3569 
PVC Conduits Installation for Electrical 13-Mar-11 16-Mar-11 1,827 1827 
Pulling the Wires 17-Mar-11 20-Mar-11 1,778 1778 
Lighting & Power Fixtuers and Accessories installation 12-Apr-11 16-Apr-11 1,334 1334 
Install Communication System 12-Apr-11 14-Apr-11 2,235 2235 
Fire Alarm 12-Apr-11 14-Apr-11 2,228 2228 
Installation of Fire Al ram Devices 12-Apr-11 14-Apr-11 2,228 2228 
Control Room 06-Mar-11 08-May-11 15,533 3605 9852 2076 
Electrical System 06-Mar-11 08-May-11 13,305 3605 8366 1334 
PVC Conduits Installation for Electrical 06-Mar-11 09-Mar-11 938 938 
Pulling the Wires 10-Mar-11 13-Mar-11 1,334 1334 
Lighting & Power Fixtuers and Accessories installation 04-May-11 08-May-11 1,334 1334 
Installation & Termination of UPS Panel 02-Apr-11 05-Apr-11 8,366 8366 
Distribution Board Installation to Light&Power 28-Mar-11 31-Mar-11 1,334 1334 
Fire Alarm 28-Apr-11 01-May-11 2,228 1486 743 
Installation of Fire Alram Devices 28-Apr-11 01-May-11 2,228 1486 743 
Toilets 17-Mar-11 20-Apr-11 5,830 3605 2225 
Electrical System 17-Mar-11 20-Apr-11 4,939 3605 1334 
PVC Conduits Installation for Electrical 17-Mar-11 21-Mar-11 1,827 1827 
Pulling the Wires 22-Mar-11 24-Mar-11 1,778 1778 
Lighting & Power Fixtuers and Accessories installation 17-Apr-11 20-Apr-11 1,334 1334 
Fire Alarm 16-Apr-11 18-Apr-11 891 891 
Installation of Fire Alram Devices 16-Apr-11 18-Apr-11 891 891 
Kitchen 22-Mar-11 25-Apr-11 6,053 3605 2448 
Electrical System 22-Mar-11 25-Apr-11 4,939 3605 1334 
PVC Conduits Installation for Electrical 22-Mar-11 26-Mar-11 1,827 1827 
Pulling the Wires 27-Mar-11 29-Mar-11 1,778 1778 
Lighting & Power Fixtuers and Accessories installation 21-Apr-11 25-Apr-11 1,334 1334 
Fire Alarm 19-Apr-11 21-Apr-11 1,114 1114 
Installation of Fire Alram Devices 19-Apr-11 21-Apr-11 1,114 1114 
Mess Room 27-Mar-11 30-Apr-11 7,167 2420 4748 
Electrical System 27-Mar-11 30-Apr-11 4,939 2420 2519 
PVC Conduits Installation for Electrical 27-Mar-11 30-Mar-11 1,827 1827 
Pulling the Wires 31-Mar-11 03-Apr-11 1,778 593 1186 
Lighting & Power Fixtuers and Accessories installation 26-Apr-11 30-Apr-11 1,334 1334 
Fire Alarm 26-Apr-11 27-Apr-11 2,228 2228 
Installation of Fire Alram Devices 26-Apr-11 27-Apr-11 2,228 2228 
Store 31-Mar-11 03-May-11 7,167 457 3149 3562 
Electrical System 31-Mar-11 03-May-11 4,939 457 3149 1334 
PVC Conduits Installation for Electrical 31-Mar-11 04-Apr-11 1,827 457 1370 
Pulling the Wires 05-Apr-11 07-Apr-11 1,778 1778 
Lighting & Power Fixtuers and Accessories installation 01-May-11 03-May-11 1,334 1334 
Fire Alarm 02-May-11 03-May-11 2,228 2228 
Installation of Fire Alram Devices 02-May-11 03-May-11 2,228 2228 
Compound Wall 14-Nov-10 10-Apr-11 317,707 43248 27984 200545 2192 20411 23327 
Civil 14-Nov-10 01-Feb-11 273,969 43248 27984 200545 2192 
Prepare Foundation Base 25-Nov-10 13-Dec-10 35,616 12720 22896 
Install the Pre cast Wall Panels 03-Jan-11 26-Jan-11 191,778 191778 
Excavation 14-Nov-10 04-Dec-10 35,616 30528 5088 
Backfilling 27-Jan-11 01-Feb-11 10,959 8767 2192 
Finishes 24-Mar-11 10-Apr-11 43,738 20411 23327 
Gate 24-Mar-11 10-Apr-11 43,738 20411 23327 
Install the Gate 24-Mar-11 10-Apr-11 43,738 20411 23327 
Reticulation Piping Network & Fibre Optic Cable 07-Nov-10 27-Apr-11 1,196,427 95894 329741 286610 208174 184989 91020 
Pipes & Cables 23-Nov-10 27-Apr-11 1,021,779 46993 279093 255174 174991 174510 91020 
Inside DCP Plot 19-Dec-10 19-Mar-11 72,356 4738 33701 15828 18089 
Project Implementation Schedule 
Value of Work in Dirhams (Attachment .2) 
Date Revision Checked Approved 
15-Aug-10 Project Implementation Schedule Rev.00 
21-Sep-10 Project Implementation Schedule Rev.01
Activity Name Start Finish Budgeted Cost Budgeted 
U 
Mubadala Capitaland Real Estate 
District Cooling Plant for Rihan Heights 
2010 2011 
Data Date : 18-Jul-10 
Page : 6 of 8 
Printed On : 22-Sep-10 
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 
X-Ray 29-Jan-11 10-Feb-11 9,044 2261 6783 
Insulation of Pipes 12-Feb-11 28-Feb-11 9,044 9044 
Install Valves and Accessories 01-Mar-11 07-Mar-11 9,044 9044 
Install the Pipes Supports 19-Dec-10 04-Jan-11 6,030 4738 1292 
Install the Pipes 05-Jan-11 27-Jan-11 30,148 30148 
Hydrostatic Test 08-Mar-11 19-Mar-11 9,044 9044 
Outside DCP Plot 23-Nov-10 27-Apr-11 949,423 46993 274355 221472 159163 156421 91020 
Fibre Optic Cable Laying 01-Mar-11 27-Apr-11 8,425 4550 3876 
Total Distance 200 m Pipes 23-Nov-10 06-Mar-11 147,882 46993 35260 60203 5427 
Reticulation Piping Network 23-Nov-10 06-Mar-11 120,921 46993 35260 33243 5427 
X-Ray Test 25-Dec-10 30-Dec-10 5,427 5427 
Warning Tape Installation 19-Jan-11 19-Jan-11 1,507 1507 
Soft Sand and Compaction Test 01-Dec-10 04-Dec-10 14,849 14849 
Laying the Pipes 11-Dec-10 23-Dec-10 14,984 14984 
Installation of Dewatering System Equipment 24-Nov-10 24-Nov-10 1,472 1472 
Install Butterfly Valve 01-Mar-11 06-Mar-11 5,427 5427 
Hydrostatic Test 02-Jan-11 06-Jan-11 5,427 5427 
Filled Joint Insulation 08-Jan-11 15-Jan-11 5,427 5427 
Excavation ( to be coordinated with hilalco) 23-Nov-10 23-Nov-10 41,763 41763 
Draw down the Underground Water 25-Nov-10 30-Nov-10 3,758 3758 
Backfilling with Soft Sand 16-Jan-11 18-Jan-11 20,882 20882 
Fibre Optic Cable 20-Jan-11 26-Jan-11 26,961 26961 
Warning Tape Installation 25-Jan-11 25-Jan-11 5,055 5055 
Installation of PVC Pipes 20-Jan-11 23-Jan-11 8,425 8425 
Final Backfilling 26-Jan-11 26-Jan-11 5,055 5055 
Backfilling with Soft Sand 24-Jan-11 24-Jan-11 8,425 8425 
Total Distance 400 m Pipes 01-Dec-10 09-Feb-11 147,654 71834 40391 35429 
Reticulation Piping Network 01-Dec-10 02-Feb-11 120,693 71834 40391 8468 
X-Ray Test 09-Jan-11 15-Jan-11 5,427 5427 
Warning Tape Installation 02-Feb-11 02-Feb-11 1,507 1507 
Soft Sand and Compaction Test 12-Dec-10 13-Dec-10 14,664 14664 
Laying the Pipes 25-Dec-10 08-Jan-11 20,380 10190 10190 
Installation of Dewatering System Equipment 04-Dec-10 04-Dec-10 1,459 1459 
Hydrostatic Test 16-Jan-11 20-Jan-11 5,427 5427 
Filled Joint Insulation 22-Jan-11 29-Jan-11 5,427 5427 
Excavation 01-Dec-10 01-Dec-10 41,763 41763 
Draw down the Underground Water 05-Dec-10 11-Dec-10 3,758 3758 
Backfilling with Soft Sand 30-Jan-11 01-Feb-11 20,882 13921 6961 
Fibre Optic Cable 03-Feb-11 09-Feb-11 26,961 26961 
Warning Tape Installation 08-Feb-11 08-Feb-11 5,055 5055 
Installation of PVC Pipes 03-Feb-11 06-Feb-11 8,425 8425 
Final Backfilling 09-Feb-11 09-Feb-11 5,055 5055 
Backfilling with Soft Sand 07-Feb-11 07-Feb-11 8,425 8425 
Total Distance 600 m Pipes 12-Dec-10 26-Feb-11 147,654 61644 27978 58032 
Reticulation Piping Network 12-Dec-10 17-Feb-11 120,693 61644 27978 31072 
X-Ray Test 23-Jan-11 29-Jan-11 5,427 5427 
Warning Tape Installation 17-Feb-11 17-Feb-11 1,507 1507 
Soft Sand and Compaction Test 20-Dec-10 21-Dec-10 14,664 14664 
Laying the Pipes 09-Jan-11 22-Jan-11 20,380 20380 
Installation of Dewatering System Equipment 13-Dec-10 13-Dec-10 1,459 1459 
Hydrostatic Test 30-Jan-11 03-Feb-11 5,427 2171 3256 
Filled Joint Insulation 05-Feb-11 12-Feb-11 5,427 5427 
Excavation 12-Dec-10 12-Dec-10 41,763 41763 
Draw down the Underground Water 14-Dec-10 19-Dec-10 3,758 3758 
Backfilling with Soft Sand 13-Feb-11 16-Feb-11 20,882 20882 
Fibre Optic Cable 19-Feb-11 26-Feb-11 26,961 26961 
Warning Tape Installation 23-Feb-11 23-Feb-11 5,055 5055 
Installation of PVC Pipes 19-Feb-11 21-Feb-11 8,425 8425 
Final Backfilling 24-Feb-11 26-Feb-11 5,055 5055 
Backfilling with Soft Sand 22-Feb-11 22-Feb-11 8,425 8425 
Total Distance 800 m Pipes 20-Dec-10 12-Mar-11 147,654 61644 13587 30034 42389 
Reticulation Piping Network 20-Dec-10 03-Mar-11 120,693 61644 13587 30034 15429 
X-Ray Test 06-Feb-11 12-Feb-11 5,427 5427 
Warning Tape Installation 03-Mar-11 03-Mar-11 1,507 1507 
Soft Sand and Compaction Test 28-Dec-10 29-Dec-10 14,664 14664 
Laying the Pipes 23-Jan-11 05-Feb-11 20,380 13587 6793 
Installation of Dewatering System Equipment 21-Dec-10 21-Dec-10 1,459 1459 
Hydrostatic Test 13-Feb-11 19-Feb-11 5,427 5427 
Filled Joint Insulation 20-Feb-11 27-Feb-11 5,427 5427 
Excavation 20-Dec-10 20-Dec-10 41,763 41763 
Draw down the Underground Water 22-Dec-10 27-Dec-10 3,758 3758 
Backfilling with Soft Sand 28-Feb-11 02-Mar-11 20,882 6961 13921 
Fibre Optic Cable 05-Mar-11 12-Mar-11 26,961 26961 
Warning Tape Installation 09-Mar-11 09-Mar-11 5,055 5055 
Installation of PVC Pipes 05-Mar-11 07-Mar-11 8,425 8425 
Final Backfilling 10-Mar-11 12-Mar-11 5,055 5055 
Backfilling with Soft Sand 08-Mar-11 08-Mar-11 8,425 8425 
Total Distance 1000 m Pipes 28-Dec-10 26-Mar-11 147,654 43974 17670 26892 59118 
Reticulation Piping Network 28-Dec-10 17-Mar-11 120,693 43974 17670 26892 32157 
X-Ray Test 21-Feb-11 27-Feb-11 5,427 5427 
Warning Tape Installation 17-Mar-11 17-Mar-11 1,507 1507 
Soft Sand and Compaction Test 06-Jan-11 08-Jan-11 14,664 14664 
Laying the Pipes 06-Feb-11 20-Feb-11 20,380 20380 
Installation of Dewatering System Equipment 29-Dec-10 29-Dec-10 1,459 1459 
Hydrostatic Test 28-Feb-11 05-Mar-11 5,427 1085 4341 
Filled Joint Insulation 06-Mar-11 13-Mar-11 5,427 5427 
Excavation 28-Dec-10 28-Dec-10 41,763 41763 
Draw down the Underground Water 30-Dec-10 05-Jan-11 3,758 752 3006 
Backfilling with Soft Sand 14-Mar-11 16-Mar-11 20,882 20882 
Project Implementation Schedule 
Value of Work in Dirhams (Attachment .2) 
Date Revision Checked Approved 
15-Aug-10 Project Implementation Schedule Rev.00 
21-Sep-10 Project Implementation Schedule Rev.01
Activity Name Start Finish Budgeted Cost Budgeted 
U 
Mubadala Capitaland Real Estate 
District Cooling Plant for Rihan Heights 
2010 2011 
Data Date : 18-Jul-10 
Page : 7 of 8 
Printed On : 22-Sep-10 
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 
Fibre Optic Cable 19-Mar-11 26-Mar-11 26,961 26961 
Warning Tape Installation 23-Mar-11 23-Mar-11 5,055 5055 
Installation of PVC Pipes 19-Mar-11 21-Mar-11 8,425 8425 
Final Backfilling 24-Mar-11 26-Mar-11 5,055 5055 
Backfilling with Soft Sand 22-Mar-11 22-Mar-11 8,425 8425 
Total Distance 1200 m Pipes 06-Jan-11 13-Apr-11 202,501 61644 8776 44938 87144 
Reticulation Piping Network 06-Jan-11 13-Apr-11 177,226 61644 8776 44938 61869 
X-Ray Test 07-Mar-11 13-Mar-11 5,427 5427 
Warning Tape Installation 31-Mar-11 31-Mar-11 1,507 1507 
Soft Sand and Compaction Test 15-Jan-11 16-Jan-11 14,664 14664 
Laying the Pipes 21-Feb-11 06-Mar-11 15,044 8776 6268 
Installation of Dewatering System Equipment 08-Jan-11 08-Jan-11 1,459 1459 
Install Butterfly Valve 07-Apr-11 13-Apr-11 5,427 5427 
Hydrostatic Test 14-Mar-11 19-Mar-11 5,427 5427 
Filled Joint Insulation 20-Mar-11 27-Mar-11 5,427 5427 
Excavation 06-Jan-11 06-Jan-11 41,763 41763 
Draw down the Underground Water 09-Jan-11 13-Jan-11 3,758 3758 
Construct Drain Chamber 07-Apr-11 10-Apr-11 21,163 21163 
Construct Air Vent Chamber 07-Apr-11 10-Apr-11 35,279 35279 
Backfilling with Soft Sand 28-Mar-11 30-Mar-11 20,882 20882 
Fibre Optic Cable 02-Apr-11 06-Apr-11 25,276 25276 
Warning Tape Installation 05-Apr-11 05-Apr-11 4,213 4213 
Installation of PVC Pipes 02-Apr-11 03-Apr-11 8,425 8425 
Final Backfilling 06-Apr-11 06-Apr-11 4,213 4213 
Backfilling with Soft Sand 04-Apr-11 04-Apr-11 8,425 8425 
Valve Chambers 07-Nov-10 13-Mar-11 174,648 48901 50648 31437 33183 10479 
Valve Chamber No.01 07-Nov-10 21-Dec-10 43,662 24451 19211 
Water Proofing 10-Nov-10 11-Nov-10 3,493 3493 
Walls 20-Nov-10 30-Nov-10 12,225 12225 
Slab 01-Dec-10 11-Dec-10 12,225 12225 
Foundation 13-Nov-10 18-Nov-10 5,239 5239 
External Water Proofing 12-Dec-10 19-Dec-10 3,493 3493 
Blinding 07-Nov-10 09-Nov-10 3,493 3493 
Backfilling 20-Dec-10 21-Dec-10 3,493 3493 
Valve Chamber No.02 07-Nov-10 21-Dec-10 43,662 24451 19211 
Water Proofing 10-Nov-10 11-Nov-10 3,493 3493 
Walls 20-Nov-10 30-Nov-10 12,225 12225 
Slab 01-Dec-10 11-Dec-10 12,225 12225 
Foundation 13-Nov-10 18-Nov-10 5,239 5239 
External Water Proofing 12-Dec-10 19-Dec-10 3,493 3493 
Blinding 07-Nov-10 09-Nov-10 3,493 3493 
Backfilling 20-Dec-10 21-Dec-10 3,493 3493 
Valve Chamber No.03 22-Dec-10 31-Jan-11 43,662 12225 31437 
Water Proofing 26-Dec-10 27-Dec-10 3,493 3493 
Walls 02-Jan-11 12-Jan-11 12,225 12225 
Slab 13-Jan-11 20-Jan-11 12,225 12225 
Foundation 28-Dec-10 30-Dec-10 5,239 5239 
External Water Proofing 22-Jan-11 29-Jan-11 3,493 3493 
Blinding 22-Dec-10 25-Dec-10 3,493 3493 
Backfilling 30-Jan-11 31-Jan-11 3,493 3493 
Valve Chamber No.04 01-Feb-11 13-Mar-11 43,662 33183 10479 
Water Proofing 05-Feb-11 06-Feb-11 3,493 3493 
Walls 10-Feb-11 22-Feb-11 12,225 12225 
Slab 23-Feb-11 02-Mar-11 12,225 8732 3493 
Foundation 07-Feb-11 09-Feb-11 5,239 5239 
External Water Proofing 03-Mar-11 10-Mar-11 3,493 3493 
Blinding 01-Feb-11 03-Feb-11 3,493 3493 
Backfilling 12-Mar-11 13-Mar-11 3,493 3493 
Energy Transfer Stations 18-Jan-11 16-Mar-11 376,097 90263 204221 81613 
ETS Room (Tower A,B) 18-Jan-11 06-Mar-11 167,476 38684 97707 31084 
Plant Pipes / Heat Exchangers Inside ETS Room 18-Jan-11 06-Mar-11 167,476 38684 97707 31084 
X-RayTest 03-Feb-11 08-Feb-11 15,044 15044 
Insulation of Pipes 09-Feb-11 17-Feb-11 15,044 15044 
Install Valves 19-Feb-11 22-Feb-11 18,805 18805 
Install Pipes 18-Jan-11 02-Feb-11 45,132 38684 6447 
Install Heat Exchanger Fitting & Accessories 23-Feb-11 06-Mar-11 15,044 7522 7522 
Install Heat Exchanger 23-Feb-11 06-Mar-11 47,125 23562 23562 
Hydrostatic for Tower A,B 09-Feb-11 21-Feb-11 11,283 11283 
ETS Room (Tower C,D) 18-Jan-11 06-Mar-11 140,397 38684 70252 31461 
Plant Pipes / Heat Exchangers Inside ETS Room 18-Jan-11 06-Mar-11 140,397 38684 70252 31461 
X-RayTest 03-Feb-11 08-Feb-11 7,522 7522 
Insulation of Pipes 09-Feb-11 17-Feb-11 7,522 7522 
Install Valves 19-Feb-11 22-Feb-11 15,044 15044 
Install Pipes 18-Jan-11 02-Feb-11 45,132 38684 6447 
Install Heat Exchanger Fitting & Accessories 23-Feb-11 06-Mar-11 7,522 3761 3761 
Install Heat Exchanger 23-Feb-11 06-Mar-11 46,373 23186 23186 
Hydrostatic for Tower C,D 22-Feb-11 05-Mar-11 11,283 6770 4513 
ETS Room (Tower E) 18-Jan-11 16-Mar-11 68,224 12895 36261 19068 
Plant Pipes / Heat Exchangers Inside ETS Room 18-Jan-11 16-Mar-11 68,224 12895 36261 19068 
X-RayTest 03-Feb-11 08-Feb-11 7,522 7522 
Insulation of Pipes 09-Feb-11 17-Feb-11 7,522 7522 
Install Valves 19-Feb-11 22-Feb-11 7,522 7522 
Install Pipes 18-Jan-11 02-Feb-11 15,044 12895 2149 
Install Heat Exchanger Fitting & Accessories 23-Feb-11 06-Mar-11 7,522 3761 3761 
Install Heat Exchanger 23-Feb-11 06-Mar-11 15,570 7785 7785 
Hydrostatic for Tower E 06-Mar-11 16-Mar-11 7,522 7522 
External Works 20-Mar-11 28-Apr-11 433,251 275064 158187 
Sewerage Network 20-Mar-11 05-Apr-11 207,439 152122 55317 
uPVC gravity sewers in trench with Manholes 20-Mar-11 05-Apr-11 207,439 152122 55317 
Project Implementation Schedule 
Value of Work in Dirhams (Attachment .2) 
Date Revision Checked Approved 
15-Aug-10 Project Implementation Schedule Rev.00 
21-Sep-10 Project Implementation Schedule Rev.01
Activity Name Start Finish Budgeted Cost Budgeted 
U 
Mubadala Capitaland Real Estate 
District Cooling Plant for Rihan Heights 
2010 2011 
Data Date : 18-Jul-10 
Page : 8 of 8 
Printed On : 22-Sep-10 
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 
Potable Water Network 20-Mar-11 05-Apr-11 167,648 122942 44706 
uPVC pipe work in trench with with Chambers 20-Mar-11 05-Apr-11 167,648 122942 44706 
External Lighting 11-Apr-11 27-Apr-11 41,556 41556 
External Lighting 11-Apr-11 27-Apr-11 41,556 41556 
Steel Stairs 12-Apr-11 28-Apr-11 16,608 16608 
Steel Staircase for Ancillary Building 12-Apr-11 28-Apr-11 16,608 16608 
Testing and Commissioning 17-Mar-11 11-May-11 242,322 89612 123717 28993 
Mechanical 17-Mar-11 11-May-11 242,322 89612 123717 28993 
Reticulation Piping Network 14-Apr-11 11-May-11 80,790 51797 28993 
Chemical Passivation 02-May-11 11-May-11 26,922 26922 
Chemical Cleaning 19-Apr-11 01-May-11 26,922 24851 2071 
Air Flushing 14-Apr-11 18-Apr-11 26,946 26946 
Energy Transfer Stations 17-Mar-11 06-Apr-11 80,766 51152 29614 
Chemical Passivation 03-Apr-11 06-Apr-11 26,922 26922 
Chemical Cleaning 22-Mar-11 02-Apr-11 26,922 24230 2692 
Air Flushing 17-Mar-11 21-Mar-11 26,922 26922 
District Cooling Modular Plant 20-Mar-11 18-Apr-11 80,766 38460 42306 
Chemical Passivation 09-Apr-11 18-Apr-11 26,922 26922 
Chemical Cleaning 26-Mar-11 08-Apr-11 26,922 11538 15384 
Air Flushing 20-Mar-11 25-Mar-11 26,922 26922 
Project Implementation Schedule 
Value of Work in Dirhams (Attachment .2) 
Date Revision Checked Approved 
15-Aug-10 Project Implementation Schedule Rev.00 
21-Sep-10 Project Implementation Schedule Rev.01
Mubadala Capitaland Real Estate 
District Cooling Plant for Rihan Heights 
Forecasting of Monthly Invoices 
Contract Amount : 5 3,166,016.00 
Advance Payment ( 10 % ) : 5,316,601.60 Advance Payment Bond Date : 
Change Orders Approved to Date : Retention Amount ( 5 % ) : 2,658,300.80 Performance Bond Date : 
Current Contract Amount : 5 3,166,016.00 
Contract Start Date : 18-Jul-10 Other Bonds : 
Invoice Currency : AED Contract Completion Date : 13-May-11 
Due Date Duration after Approval is : 56 Days 
Value of Work Retention Release Advance Payment Retention Money Others Total Deduction Net Invoice Actual 
A B C D E (F)=C+D+E Net =(A+B-F) Date Amount Difference 
(Days) 
1 Advance Payment 5,316,602 0 5,316,602 5,316,602 18-Aug-10 21-Sep-10 
2 30-Sep-2010 5,924,236 - 888,635 592,424 - 1,481,059 4,443,177 9,759,778 30-Sep-10 25-Nov-10 
3 31-Oct-2010 2,500,867 - 375,130 250,087 - 625,217 1,875,650 11,635,428 31-Oct-10 26-Dec-10 
4 30-Nov-2010 2,999,945 - 449,992 299,995 - 749,986 2,249,959 13,885,387 30-Nov-10 25-Jan-11 
5 31-Dec-2010 1,655,753 - 248,363 165,575 - 413,938 1,241,815 15,127,202 31-Dec-10 25-Feb-11 
6 31-Jan-2011 7,298,559 1,094,784 729,856 - 1,824,640 5,473,920 20,601,122 31-Jan-11 28-Mar-11 
7 28-Feb-2011 10,336,991 - 1,550,549 620,365 - 2,170,913 8,166,077 28,767,199 28-Feb-11 25-Apr-11 
8 31-Mar-2011 8,775,786 - 709,149 - - 709,149 8,066,637 36,833,836 31-Mar-11 26-May-11 
9 30-Apr-2011 9,300,088 - - - - 0 9,300,088 46,133,924 30-Apr-11 25-Jun-11 
10 31-May-2011 999,740 1 ,329,150.40 - - - 0 2,328,890 48,462,814 31-May-11 26-Jul-11 
11 30-Jun-2011 307,384 - - - - 0 307,384 48,770,198 30-Jun-11 25-Aug-11 
12 31-Jul-2011 307,384 - - - - 0 307,384 49,077,582 31-Jul-11 25-Sep-11 
13 31-Aug-2011 307,063 - - - - 0 307,063 49,384,644 31-Aug-11 26-Oct-11 
14 30-Sep-2011 307,063 - - - - 0 307,063 49,691,707 30-Sep-11 25-Nov-11 
15 31-Oct-2011 307,063 - - - - 0 307,063 49,998,770 31-Oct-11 26-Dec-11 
16 30-Nov-2011 307,063 - - - - 0 307,063 50,305,833 30-Nov-11 25-Jan-12 
17 31-Dec-2011 307,063 - - - - 0 307,063 50,612,895 31-Dec-11 25-Feb-12 
18 31-Jan-2012 307,063 - - - - 0 307,063 50,919,958 31-Jan-12 27-Mar-12 
19 29-Feb-2012 307,063 - - - - 0 307,063 51,227,021 29-Feb-12 25-Apr-12 
20 31-Mar-2012 342,286 - - - - 0 342,286 51,569,306 31-Mar-12 26-May-12 
21 30-Apr-2012 133,780 - - - - 0 133,780 51,703,086 30-Apr-12 25-Jun-12 
22 31-May-2012 133,780 1 ,329,150.40 - - - 0 1,462,930 53,166,017 31-May-12 26-Jul-12 
53,166,017 0 5,316,601.68 2,658,300.82 0.00 7,974,902 53,166,017 
Cert. / 
Invoice 
No. 
Month Cumulative Invoice Submitted 
Date 
Forcast Date of 
Releasing the 
Invoices 
Total 
GROSS INVOICE DEDUCTIONS 
Remarks 
Release of 5% of Retention Money 
Release of 5% of Retention Money 
File : Cash Flow Page 2 of 2 Printed On :10/20/10 at 1:06 PM
Section 1.12 
 Cash In Histogram (EPC Project Period) 
AWI 106 Att. 8 Rev. 2 06 Jul. 2009 Date/ Rev.
Sep-10 Oct-10 Nov-10 Dec-10 Jan-11 May-11 Jun-11 
Planned Monthly 5,316,602 4,443,177 1,875,650 2,249,959 1,241,815 5,473,920 8,166,077 8,066,637 9,300,088 2,328,890 
Planned Accum. 5,316,602 5,316,602 9,759,778 11,635,428 13,885,387 15,127,202 20,601,122 28,767,199 36,833,836 46,133,924 48,462,814 
Actual Monthly 
Actual Accum. 
Forecast Monthly 
Forecast Accum. 
Planned Actual Forecast 
Mubadala Capitaland Real Estate 
District Cooling Plant for Rihan Heights 
Cash In Histogram (EPC Project Period) 
Feb-11 Mar-11 Apr-11 Jul-11 
2,328,890 
8,166,077 
5,473,920 
4,443,177 
5,316,602 
1,875,650 
2,249,959 
1,241,815 
8,066,637 
9,300,088 
Sep-10 
Oct-10 
Nov-10 
Dec-10 
Jan-11 
Feb-11 
Mar-11 
Apr-11 
May-11 
Jun-11 
Jul-11 
Forecast Date of Releasing the Invoices 
AED 10,000,000.00 
AED 9,000,000.00 
AED 8,000,000.00 
AED 7,000,000.00 
AED 6,000,000.00 
AED 5,000,000.00 
AED 4,000,000.00 
AED 3,000,000.00 
AED 2,000,000.00 
AED 1,000,000.00 
AED 0.00 
Planned Monthly 
Actual Monthly 
Forecast Accum. 
Planned Accum. 
Actual Accum. 
Forecast Monthly 
File: Cash Flow Page 1 of 1 Printed On : 10/20/10 at 12:42 PM
Section 1.13 
 Cash In Histogram (Operation and 
Maintenance Period) 
AWI 106 Att. 8 Rev. 2 06 Jul. 2009 Date/ Rev.
Jan-12 Feb-12 Apr-12 
Planned Monthly 307,384 307,384 307,063 307,063 307,063 307,063 307,063 307,063 307,063 342,286 133,780 1,462,930 
Planned Accum. 307,384 614,768 921,831 1,228,893 1,535,956 1,843,019 2,150,081 2,457,144 2,764,207 3,106,492 3,240,273 4,703,203 
Actual Monthly 
Actual Accum. 
Forecast Monthly 
Forecast Accum. 
Forecast 
Aug-11 Nov-11 Dec-11 
Planned Actual 
Mubadala Capitaland Real Estate 
District Cooling Plant for Rihan Heights 
Cash In Histogram (Operation and Maintenance Period) 
Sep-11 Oct-11 Mar-12 May-12 Jun-12 Jul-12 
307,384 307,384 307,063 307,063 307,063 307,063 307,063 307,063 
307,063 
342,286 
Aug-11 
Sep-11 
Oct-11 
Nov-11 
Dec-11 
Jan-12 
Feb-12 
Mar-12 
Apr-12 
May-12 
Forecast Date of Releasing the Invoices 
AED 350,000.00 
AED 340,000.00 
AED 330,000.00 
AED 320,000.00 
AED 310,000.00 
AED 300,000.00 
AED 290,000.00 
AED 280,000.00 
Planned Monthly 
Actual Monthly 
Forecast Accum. 
Planned Accum. 
Actual Accum. 
Forecast Monthly 
File: Cash Flow Page 1 of 1 Printed On : 10/20/10 at 12:42 PM
Section 2 
 Cash Out Data 
AWI 106 Att. 8 Rev. 2 06 Jul. 2009 Date/ Rev.
Section 2.11 
 Cash Out-Value of Works & Monthly Invoices 
AWI 106 Att. 8 Rev. 2 06 Jul. 2009 Date/ Rev.
Mubadala Capitaland Real Estate 
District Cooling Plant for Rihan Heights 
Cash Out Value of Works & Monthly Invoices 
Jul-10 Aug-10 Sep-10 Oct-10 Nov-10 Dec-10 Jan-11 Feb-11 Mar-11 Apr-11 May-11 Jun-11 Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 
Description Original 
Budget 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 
1.0 - Materials 8,641,274 
Civil Works 
Imported fill 136,125 7.69% 23.08% 30.77% 15.38% 23.08% 
Sand Bedding/Padding 87,300 66.67% 33.33% 
Lean Concrete 29,295 50.00% 12.50% 12.50% 25.00% 
RC Concrete 376,740 14.29% 35.71% 21.43% 21.43% 7.14% 
Rebars 251,680 25.00% 28.57% 21.43% 25.00% 
Formworks 342,125 14.29% 35.71% 21.43% 21.43% 7.14% 
Blockworks 27,000 44.44% 55.56% 
Polythelene Sheets 6,555 100.00% 
Water Stop 9,000 100.00% 
Floor Screed 6,700 50.00% 25.00% 25.00% 
Steel Stairs 14,160 100.00% 
Ceramic Floor tiles 5,355 50.00% 50.00% 
Plastering 8,856 100.00% 
Painting 8,247 100.00% 
Manhole Cover 17,400 100.00% 
Aluminum Ladder 3,500 100.00% 
Pipe Sleeves Inserts 25,200 100.00% 
Cable Tiles / Warning Tapes 3,047 100.00% 
Furnishings 52,050 100.00% 
Geo-Textile Membrane 7,401 100.00% 
Electrical Works 
Plant Room 
MV Cables (Plant) 350,380 10.00% 90.00% 
Relay coordination Study and Local 
Authority Approvals for 11kv Switchgear , 
30,000 100.00% 
Testing 
Transformer (Plant) inclusive of Factory 
Witness Test 589,824 10.00% 90.00% 
Cables & Wires (Plants) 203,511 10.00% 55.00% 35.00% 
Contaiment (Cable Tray & Trunking) 20,894 100.00% 
Isolators (plant) 12,196 100.00% 
PVC Duct Bank 1,200 100.00% 
Earthing (Plant) 23,922 100.00% 
Lignhtning Protection (Plant) 41,466 100.00% 
UPS system (Plant) 76,271 100.00% 
Support for Electrical System 8,925 100.00% 
Miscellaneous (Cable Marker, Rubber 
Mats, Boards, Consumables) 3,720 100.00% 
Building Services 
File:Cash Flow Page1 of 7 Printed On:10/20/10 at 12:47 PM
Mubadala Capitaland Real Estate 
District Cooling Plant for Rihan Heights 
Cash Out Value of Works & Monthly Invoices 
Jul-10 Aug-10 Sep-10 Oct-10 Nov-10 Dec-10 Jan-11 Feb-11 Mar-11 Apr-11 May-11 Jun-11 Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 
Description Original 
Budget 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 
SMDB/Distribution Boards (BS) 14,500 100.00% 
Cables & Wires (BS) 56,126 100.00% 
Conduit fittings & accessories (BS) 22,286 100.00% 
Light Fittings -(BS) 26,602 100.00% 
Wiring accessories (BS) 4,188 100.00% 
Light Points (BS) 2,100 100.00% 
Support for Electrical System (BS) 4,052 100.00% 
Mechanical Works 
HVAC 
Process (DC Plant) 
Expansion Tank 32,972 100.00% 
Chemical Water Treatment System 
(Chilled & Condenser Water) 
454,500 10.00% 90.00% 
/Equipments 
Air Compressor 15,000 100.00% 
Refrigerant Recovery Unuit 75,000 100.00% 
Chilled Water /Condenser Water Pipe & 
Fittings 149,552 100.00% 
Chilled/Condenser Water Pipe Insulation 37,280 100.00% 
Valves 163,508 100.00% 
Aluminium Cladding 31,473 100.00% 
Hanger & Supports 42,729 100.00% 
Identification & Tag 3,670 100.00% 
Fire Stopping Material 10,014 100.00% 
Skid & Shed 5,000 100.00% 
Consumables-Piping 2,849 100.00% 
Consumables-HVAC 8,383 100.00% 
HVAC Reticulation Works 
Pre Insulated Chilled Water Pipes & 
Fittings 1,110,481 10.00% 90.00% 
Leak Detection System 80,000 100.00% 
Valves & Accessories 77,684 100.00% 
Radiography Test/ Welding Inspector 55,000 100.00% 
Stress Analysis 20,000 100.00% 
Aluminium Cladding 11,703 100.00% 
Consumables-Piping 32,359 100.00% 
Warning Tapes, Markup Plates 45,608 100.00% 
HVAC Works - ETS Room 
Heat Exchangers 1,154,575 10.00% 90.00% 
Chilled Water Pipe & Fittings 585,760 10.00% 90.00% 
Chilled Water Pipe Insulation 82,634 100.00% 
Valves 512,513 10.00% 90.00% 
File:Cash Flow Page2 of 7 Printed On:10/20/10 at 12:47 PM
Mubadala Capitaland Real Estate 
District Cooling Plant for Rihan Heights 
Cash Out Value of Works & Monthly Invoices 
Jul-10 Aug-10 Sep-10 Oct-10 Nov-10 Dec-10 Jan-11 Feb-11 Mar-11 Apr-11 May-11 Jun-11 Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 
Description Original 
Budget 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 
Aluminium Cladding 118,800 100.00% 
Hanger & Supports 174,922 100.00% 
Identification & Tag 4,008 100.00% 
Fire Stopping Material 50,000 100.00% 
Consumables-Piping 16,270 100.00% 
Consumables-HVAC 14,265 100.00% 
HVAC Works - Building Services 
Split Air Conditioning Units (BS) 33,718 100.00% 
Fans (BS) 3,952 100.00% 
Condensate Pipe & Fittings (BS) 385 100.00% 
Condensate Water Pipe Insulation (BS) 672 100.00% 
Vibration Isolator (BS) 600 100.00% 
Hanger & Supports (BS) 2,640 100.00% 
Identification & Tag (BS) 160 100.00% 
Plumbing 
Process (DC Plant) 
Make Up Water Pump 34,356 100.00% 
HDPE Pipes & Fittings 13,639 100.00% 
Steel Pipes & Fittings 24,175 100.00% 
Valves & Appurtenances 31,038 100.00% 
Drainage Specialities 8,140 100.00% 
Insulation 5,084 100.00% 
Aluminum Cladding 13,272 100.00% 
Supports 5,000 100.00% 
Consumables-Piping 1,853 100.00% 
Consumables-General 2,100 100.00% 
Building Services (BS) + External 
Booster Water Pump 22,200 100.00% 
HDPE Pipes & Fittings 38,813 100.00% 
Steel Pipes & Fittings 8,505 100.00% 
uPVC Pipes & Fittings 14,707 100.00% 
PPR Pipes & Fittings 2,149 100.00% 
Valves & Appurtenances 24,717 100.00% 
Drainage Specialities 9,110 100.00% 
Insulation 9,737 100.00% 
Aluminum Cladding 10,750 100.00% 
Sanitray Fixtures & Accessories 22,928 100.00% 
GRP Cylindrical Tank 2,100 100.00% 
Electrical Water Heaters 4,120 100.00% 
File:Cash Flow Page3 of 7 Printed On:10/20/10 at 12:47 PM
Mubadala Capitaland Real Estate 
District Cooling Plant for Rihan Heights 
Cash Out Value of Works & Monthly Invoices 
Jul-10 Aug-10 Sep-10 Oct-10 Nov-10 Dec-10 Jan-11 Feb-11 Mar-11 Apr-11 May-11 Jun-11 Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 
Description Original 
Budget 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 
Supports 13,000 100.00% 
Consumables-Piping 3,741 100.00% 
Consumables-General 3,400 100.00% 
Pantry Items 15,323 100.00% 
Supply Stationery 15,000 100.00% 
Office Supplies to Client 2,063 100.00% 
Safety Supplies 6,518 100.00% 
Scaffolding 32,457 33.34% 33.33% 33.33% 
Tools 9,236 100.00% 
Water for Testing 71,005 100.00% 
Gases 3,000 100.00% 
Office Equipment to Client 27,500 100.00% 
2.0 - Subcontract 26,301,274 
Civil Works 
Dewatering Works 76,500 100.00% 
Waterproofing 132,831 25.00% 25.00% 25.00% 25.00% 
Precast Boundary Wall 194,700 33.34% 33.33% 33.33% 
Steel Doors 89,676 50.00% 50.00% 
Wooden Doors 12,805 50.00% 50.00% 
Aluminum Windows, louver windows 40,200 50.00% 50.00% 
Metal Works 5,250 100.00% 
Suspended Ceiling 11,197 100.00% 
Epoxy Floor Coating 15,235 100.00% 
Steel Gates 38,750 50.00% 50.00% 
GRP Lining 182,280 33.34% 33.33% 33.33% 
Geotechnical Report 13,529 100.00% 
Material Testing 31,000 16.67% 16.67% 16.67% 16.67% 16.67% 16.67% 
GRP Ladder 10,712 100.00% 
Kitchen Equipments 15,804 50.00% 50.00% 
Electrical Works 
HV Cable Laying & Termination 45,500 100% 
Fire Alarm System 19,941 50.00% 50% 
Telecommunication System 2,000 100% 
Cabling 76,500 50.00% 50% 
HVAC Works 
HVAC Initial Start-up 15,017 100.00% 
25,000 100.00% 
75,000 100.00% 
File:Cash Flow Page4 of 7 Printed On:10/20/10 at 12:47 PM
Mubadala Capitaland Real Estate 
District Cooling Plant for Rihan Heights 
Cash Out Value of Works & Monthly Invoices 
Jul-10 Aug-10 Sep-10 Oct-10 Nov-10 Dec-10 Jan-11 Feb-11 Mar-11 Apr-11 May-11 Jun-11 Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 
Description Original 
Budget 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 
HVAC Testing, Balancing 40,018 100.00% 
10,000 100.00% 
30,000 100.00% 
Mechanical Works 
Fire Fighting System 122,425 10.00% 45.00% 45.00% 
Fire Fighting System 826,767 10.00% 45.00% 45.00% 
Electric Chain Hoist 40,843 100.00% 
Flushing /Chemical Flushing 35,000 50.00% 50.00% 
Testing & Commissioning 25,000 50.00% 50.00% 
Modular DCP Plant 
Modular District Cooling Plant (Stellar) 
Purchase Order-Pump 116,644 100.00% 
Purchase Order-Chiller 935,874 100.00% 
Purchase Order-Cooling Towers 311,427 100.00% 
Purchase Order-Electrical Module 864,016 100.00% 
Shipping Documents-Chiller 4,958,138 100.00% 
Shipping Documents-Cooling Towers 953,726 100.00% 
Shipping Documents-Electrical 
Module 2,999,975 100.00% 
Delivery-Pump 357,214 100.00% 
Delivery-Chiller 2,866,060 100.00% 
Delivery-Cooling Towers 953,726 100.00% 
Delivery-MV Switchgear 1,788,802 100.00% 
Delivery-LV Switchgear 857,196 100.00% 
Delivery-Chiller Base Frame 1,040,918 100.00% 
Delivery-Chiller Enclosure 693,945 100.00% 
Delivery-Electrical Module Base 
Frame 212,386 100.00% 
Delivery-Electrical Module Enclosure 141,591 100.00% 
Signing of Taking Over Certificate 2,227,959 100% 
Special System - SCADA Control & 
Automation (Stellar) 
Others /Misc 
Design (Stamping Purpose Only) 125,000 45.00% 15.00% 20.00% 10.00% 10.00% 
Environment Assessment Study 
(Budget) 30,000 100.00% 
Services during Defect Liability Period 210,675 100.00% 
Operation & Maintenance for 12 
Months 1,396,524 8% 8% 8% 8% 8% 8% 8% 8% 8% 8% 8% 8% 
3.0 - Manual Manpower 1,692,434 
Civil Works 507,503 6.36% 16.36% 18.18% 20.91% 19.09% 10.91% 6.36% 1.82% 
HVAC Works 840,899 11.00% 14.67% 18.00% 18.00% 17.00% 13.67% 7.67% 
Plumbing Works 83,027 25.00% 25.00% 25.00% 25.00% 
File:Cash Flow Page5 of 7 Printed On:10/20/10 at 12:47 PM
Mubadala Capitaland Real Estate 
District Cooling Plant for Rihan Heights 
Cash Out Value of Works & Monthly Invoices 
Jul-10 Aug-10 Sep-10 Oct-10 Nov-10 Dec-10 Jan-11 Feb-11 Mar-11 Apr-11 May-11 Jun-11 Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 
Description Original 
Budget 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 
Electrical Works 120,500 3.85% 3.85% 6.41% 8.97% 15.38% 20.51% 20.51% 20.51% 
Farash, Store Helper, Guards, 
Drivers, Courier, Tea Boy, Janitor 124,504 2.00% 12.25% 12.25% 12.25% 12.25% 12.25% 12.25% 12.25% 12.25% 
Welders Qualifications & Testing 16,000 16.67% 16.67% 16.67% 16.67% 16.67% 16.67% 
4.0 - Construction Equipment 1,350,439 
Operation 369,147 0.01% 0.57% 6.18% 10.02% 17.64% 19.99% 22.55% 19.72% 3.33% 
Equipment Outside Hire 84,151 4.00% 9.00% 15.00% 15.00% 15.00% 15.00% 15.00% 12.00% 
Fuels 233,136 2.00% 2.00% 9.00% 15.00% 15.00% 15.00% 15.00% 15.00% 12.00% 
481,617 0.01% 0.57% 6.18% 10.02% 17.64% 19.99% 22.55% 19.72% 3.33% 
Personal Cars 36,000 2.00% 2.00% 9.00% 15.00% 15.00% 15.00% 15.00% 15.00% 12.00% 
Pick - up 146,388 2.00% 2.00% 9.00% 15.00% 15.00% 15.00% 15.00% 15.00% 12.00% 
5.0 - Indirect Cost 2,513,857 
Purchase, Rental, Construction Cost 170,683 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 
Maintenance of Temp Facilities 171,786 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 
Utilities 277,389 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 
General Services 84,640 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 
Progress Photographs 700 100.00% 
Courier Service 5,000 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 
Mobile Telephone 25,000 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 
Communication (tel + fax + internet) 70,000 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 
Communication (Wireless Internet 
Access) 4,949 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 
Furniture 30,128 80.00% 2.50% 2.50% 2.50% 2.50% 2.50% 2.50% 2.50% 2.50% 
Furniture to Client 21,000 80.00% 2.50% 2.50% 2.50% 2.50% 2.50% 2.50% 2.50% 2.50% 
P&D Office Equipment 10,000 80.00% 2.50% 2.50% 2.50% 2.50% 2.50% 2.50% 2.50% 2.50% 
Ropes & Slings 10,000 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 
Bank Interest 55,000 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 
Contract Expenses 227,590 33.34% 33.33% 33.33% 
Costs of Bid Bond 7,532 33.34% 33.33% 33.33% 
Letter of Credit 281,250 33.34% 33.33% 33.33% 
Charges of CADD 375,000 33.34% 33.33% 33.33% 
Charges of IT 20,400 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 
Containers 40,000 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 
Insurance All Risk & 3rd party 209,295 33.34% 33.33% 33.33% 
Workmen's Compensation & 
Insurance 16,515 33.34% 33.33% 33.33% 
Professional Indemnity Insurance 400,000 33.34% 33.33% 33.33% 
6.0 - Non Manual Manpower 2,501,187 
Salary 2,501,187 7.46% 11.44% 12.44% 11.94% 11.94% 11.94% 10.95% 10.95% 10.95% 
7.0 - Management 
Overhead/Contingency/ G. 
10,165,550 
Expenses 
File:Cash Flow Page6 of 7 Printed On:10/20/10 at 12:47 PM
Mubadala Capitaland Real Estate 
District Cooling Plant for Rihan Heights 
Cash Out Value of Works & Monthly Invoices 
Jul-10 Aug-10 Sep-10 Oct-10 Nov-10 Dec-10 Jan-11 Feb-11 Mar-11 Apr-11 May-11 Jun-11 Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 
Description Original 
Budget 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 
Estimation Errors 300,615 11.85% 5.41% 6.35% 3.82% 14.43% 20.15% 17.21% 18.20% 2.59% 
Expected Cost Contingency - 
Currency Fluctuation 169,183 11.85% 5.41% 6.35% 3.82% 14.43% 20.15% 17.21% 18.20% 2.59% 
Provisional Sum 2,488,550 15.53% 6.92% 6.92% 6.92% 6.92% 6.92% 6.92% 6.92% 6.92% 6.92% 6.92% 6.92% 8.33% 
Area / division Overheads 1,594,980 11.85% 5.41% 6.35% 3.82% 14.43% 20.15% 17.21% 18.20% 2.59% 
Corporate Overheads 1,063,320 11.85% 5.41% 6.35% 3.82% 14.43% 20.15% 17.21% 18.20% 2.59% 
Management Overhead and Risk 4,548,902 
SUBTOTAL 53,166,015 - - 1,283,058 1,256,431 3,318,442 1,810,460 1,784,008 4,509,330 6,435,157 13,694,325 2,641,549 6,575,608 504,063 288,626 288,626 2,516,585 288,626 288,626 288,626 288,626 323,715 116,377 116,377 
48,617,243 - - 1,283,058 1,256,431 3,318,442 1,810,460 1,784,008 4,509,330 6,435,157 13,694,325 2,641,549 6,575,608 504,063 288,626 288,626 2,516,585 288,626 288,626 288,626 288,626 323,715 116,377 116,377 
- - 1 ,283,058 2 ,539,489 5 ,857,931 7 ,668,391 9 ,452,399 1 3,961,730 2 0,396,886 3 4,091,211 3 6,732,761 43,308,369 43,812,432 44,101,058 44,389,685 46,906,270 4 7,194,896 4 7,483,522 47,772,148 48,060,774 48,384,489 48,500,866 48,617,243 
0.00% 0.00% 2.41% 4.78% 11.02% 14.42% 17.78% 26.26% 38.36% 64.12% 69.09% 81.46% 82.41% 82.95% 83.49% 88.23% 88.77% 89.31% 89.85% 90.40% 91.01% 91.23% 91.44% 
Plan. Value of Work - Month 
Plan. Value of Work - Cumulative 
File:Cash Flow Page7 of 7 Printed On:10/20/10 at 12:47 PM
Section 2.12 
 Cash Out Histogram (EPC Project Period) 
AWI 106 Att. 8 Rev. 2 06 Jul. 2009 Date/ Rev.
Sep-10 Oct-10 Nov-10 Dec-10 Jan-11 May-11 Jun-11 
Planned Monthly 1,283,058 1,256,431 3,318,442 1,810,460 1,784,008 4,509,330 6,435,157 13,694,325 2,641,549 6,575,608 504,063 
Planned Accum. 1,283,058 2,539,489 5,857,931 7,668,391 9,452,399 13,961,730 20,396,886 34,091,211 36,732,761 43,308,369 43,812,432 
Actual Monthly 
Actual Accum. 
Forecast Monthly 
Forecast Accum. 
Planned Actual Forecast 
Mubadala Capitaland Real Estate 
District Cooling Plant for Rihan Heights 
Cash Out Histogram (EPC Project Period) 
Feb-11 Mar-11 Apr-11 Jul-11 
504,063 
13,694,325 
6,435,157 
3,318,442 
1,256,431 
1,283,058 
1,810,460 1,784,008 
4,509,330 
2,641,549 
6,575,608 
Sep-10 
Oct-10 
Nov-10 
Dec-10 
Jan-11 
Feb-11 
Mar-11 
Apr-11 
May-11 
Jun-11 
Jul-11 
Forecast Date of Releasing the Invoices 
AED 16,000,000.00 
AED 14,000,000.00 
AED 12,000,000.00 
AED 10,000,000.00 
AED 8,000,000.00 
AED 6,000,000.00 
AED 4,000,000.00 
AED 2,000,000.00 
AED 0.00 
Planned Monthly 
Actual Monthly 
Forecast Accum. 
Planned Accum. 
Actual Accum. 
Forecast Monthly 
File: Cash Flow Page 1 of 1 Printed On : 10/20/10 at 12:39 PM
Section 2.13 
 Cash Out Histogram (Operation and 
Maintenance Period) 
AWI 106 Att. 8 Rev. 2 06 Jul. 2009 Date/ Rev.
Jan-12 Feb-12 Apr-12 
Planned Monthly 288,626 288,626 2,516,585 288,626 288,626 288,626 288,626 323,715 116,377 116,377 
Planned Accum. 288,626 577,252 3,093,837 3,382,464 3,671,090 3,959,716 4,248,342 4,572,057 4,688,434 4,804,811 
Actual Monthly 
Actual Accum. 
Forecast Monthly 
Forecast Accum. 
Forecast 
Aug-11 Nov-11 Dec-11 
Planned Actual 
Mubadala Capitaland Real Estate 
District Cooling Plant for Rihan Heights 
Cash Out Histogram (Operation and Maintenance Period) 
Sep-11 Oct-11 Mar-12 May-12 Jun-12 Jul-12 
288,626 323,715 
2,516,585 
288,626 288,626 288,626 288,626 
288,626 
116,377 116,377 
Aug-11 
Sep-11 
Oct-11 
Nov-11 
Dec-11 
Jan-12 
Feb-12 
Mar-12 
Apr-12 
May-12 
Forecast Date of Releasing the Invoices 
AED 3,000,000.00 
AED 2,500,000.00 
AED 2,000,000.00 
AED 1,500,000.00 
AED 1,000,000.00 
AED 500,000.00 
AED 0.00 
Planned Monthly 
Actual Monthly 
Forecast Accum. 
Planned Accum. 
Actual Accum. 
Forecast Monthly 
File: Cash Flow Page 1 of 1 Printed On : 10/20/10 at 12:39 PM
Section 3 
 Cash Flow 
AWI 106 Att. 8 Rev. 2 06 Jul. 2009 Date/ Rev.
Section 3.11 
 Project Cash Flow Curve 
AWI 106 Att. 8 Rev. 2 06 Jul. 2009 Date/ Rev.
District Cooling Plant for Rihan Heights 
The Baseline of Project Cash Flow 
60,000,000 
50,000,000 
40,000,000 
30,000,000 
20,000,000 
10,000,000 
Month No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 
Cut-Off date Sep-10 Oct-10 Nov-10 Dec-10 Jan-11 Feb-11 Mar-11 Apr-11 May-11 Jun-11 Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 
16,000,000 
14,000,000 
12,000,000 
10,000,000 
8,000,000 
6,000,000 
4,000,000 
2,000,000 
Cash-In 5,316,602 4,443,177 1,875,650 2,249,959 1,241,815 5,473,920 8,166,077 8,066,637 9,300,088 2,328,890 307,384 307,384 307,063 307,063 307,063 307,063 307,063 307,063 307,063 342,286 133,780 1,462,930 
Cash-Out 1,283,058 1,256,431 3,318,442 1,810,460 1,784,008 4,509,330 6,435,157 13,694,325 2,641,549 6,575,608 504,063 288,626 288,626 2,516,585 288,626 288,626 288,626 288,626 323,715 116,377 116,377 
Variance 4,033,544 1,256,431 1,124,734 65,190 465,951 3,267,515 961,237 5,528,248 5,425,088 2,724,479 1,824,827 18,758 18,758 2,209,522 18,437 18,437 18,437 18,437 16,652 190,686 225,909 133,780 1,462,930 
Cash-in 5,316,602 5,316,602 9,759,778 11,635,428 13,885,387 15,127,202 20,601,122 28,767,199 36,833,836 46,133,924 48,462,814 48,770,198 49,077,582 49,384,644 49,691,707 49,998,770 50,305,833 50,612,895 50,919,958 51,227,021 51,569,306 51,703,086 53,166,017 
Cash-out 1,283,058 2,539,489 5,857,931 7,668,391 9,452,399 13,961,730 20,396,886 34,091,211 36,732,761 43,308,369 43,812,432 44,101,058 44,389,685 46,906,270 47,194,896 47,483,522 47,772,148 48,060,774 48,384,489 48,500,866 48,617,243 48,617,243 48,617,243 
Cash Flow 4,033,544 2,777,112 3,901,847 3,967,037 4,432,988 1,165,472 204,235 5,324,012 101,075 2,825,555 4,650,382 4,669,139 4,687,897 2,478,375 2,496,811 2,515,248 2,533,684 2,552,121 2,535,469 2,726,155 2,952,063 3,085,844 4,548,774 
CUMULATIVE MONTHLY 
0 
Sep-10 
Oct-10 
Nov-10 
Dec-10 
Jan-11 
Feb-11 
Mar-11 
Apr-11 
May-11 
Jun-11 
Jul-11 
Aug-11 
Sep-11 
Oct-11 
Nov-11 
Dec-11 
Jan-12 
Feb-12 
Mar-12 
Apr-12 
May-12 
Jun-12 
Jul-12 
MONTH 
Monthly 
0 
Cummulative 
Cash-In Cash-Out 
Cash-in Cash-out 
Cash Flow 
File:Cash Flow Page 1 of 1 Printed On:10/20/10 at 12:50 PM
Section 3.12 
 Project Cash Liquidity 
AWI 106 Att. 8 Rev. 2 06 Jul. 2009 Date/ Rev.
District Cooling Plant for Rihan Heights 
The Project Cash Liquidity 
Cash in & 
Cash out * (100,000) 
600 
550 
500 
450 
400 
350 
300 
250 
200 
150 
100 
50 
0 
Cash Net * (100,000) 
Sep-10 
Oct-10 
Nov-10 
Dec-10 
Jan-11 
Feb-11 
Mar-11 
Apr-11 
May-11 
Jun-11 
Jul-11 
Aug-11 
Sep-11 
Oct-11 
Nov-11 
Dec-11 
Jan-12 
Feb-12 
Mar-12 
Apr-12 
May-12 
Jun-12 
Jul-12 
80 
60 
40 
20 
0 
(20) 
(40) 
(60) 
(80) 
Cash Net 
Datum 
(100) 
(120) 
(140) 
(160) 
(180) 
(200) 
(220) 
(240) 
Months 
Cash net Cash in Cash out 
File:Cash Flow Page1 of 1 Printed On:10/20/10 at 12:07 PM

More Related Content

What's hot

-The PERT Chart-The tendering time schedule for Adar Produced Water Re-injec...
-The PERT Chart-The tendering time schedule for Adar Produced  Water Re-injec...-The PERT Chart-The tendering time schedule for Adar Produced  Water Re-injec...
-The PERT Chart-The tendering time schedule for Adar Produced Water Re-injec...yang lu
 
61T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 20141129
61T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 2014112961T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 20141129
61T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 20141129James Zhang (Chi, Zhang)
 
Project Controls planning & Scheduling Engineer-Portfolio
Project Controls planning & Scheduling Engineer-PortfolioProject Controls planning & Scheduling Engineer-Portfolio
Project Controls planning & Scheduling Engineer-PortfolioSyed Arafath, PMI-SP certified
 
Harmal Field Development Phase 1 and Phase 2 Final-10.10.2013-R2
Harmal Field Development Phase 1 and Phase 2 Final-10.10.2013-R2Harmal Field Development Phase 1 and Phase 2 Final-10.10.2013-R2
Harmal Field Development Phase 1 and Phase 2 Final-10.10.2013-R2Arun Bharadwaj
 
Checklist for Cost Control Dept in Contracting Company
Checklist for Cost Control Dept in Contracting CompanyChecklist for Cost Control Dept in Contracting Company
Checklist for Cost Control Dept in Contracting Companykashif khawja
 
Payment Method for Work item Studies and Design November 26, 2010.
Payment Method for Work item Studies and Design November 26, 2010.Payment Method for Work item Studies and Design November 26, 2010.
Payment Method for Work item Studies and Design November 26, 2010.Mourad Iskandar
 
Dada enterprise cost management solution comparisons
Dada enterprise cost management solution comparisonsDada enterprise cost management solution comparisons
Dada enterprise cost management solution comparisonsSachin Melwani
 
1414424205 1.vize programı_2014-2015_güz_ver3.0
1414424205 1.vize programı_2014-2015_güz_ver3.01414424205 1.vize programı_2014-2015_güz_ver3.0
1414424205 1.vize programı_2014-2015_güz_ver3.0cerenimo_818
 
-Strategy Planning Report
-Strategy Planning Report-Strategy Planning Report
-Strategy Planning Reportyang lu
 
NGS Owners Initial Proposal Timeline Discussion
NGS Owners Initial Proposal Timeline DiscussionNGS Owners Initial Proposal Timeline Discussion
NGS Owners Initial Proposal Timeline Discussionen3pro
 
Project management proposal climate observation station, mittagong -nsw
Project management proposal   climate observation station, mittagong -nswProject management proposal   climate observation station, mittagong -nsw
Project management proposal climate observation station, mittagong -nswAlper Bender
 
Petronas drilling operations guideline
Petronas drilling operations guidelinePetronas drilling operations guideline
Petronas drilling operations guidelineEaswaran Kanason
 
TQMI project Updated
TQMI project UpdatedTQMI project Updated
TQMI project UpdatedGunjan Naik
 

What's hot (19)

-The PERT Chart-The tendering time schedule for Adar Produced Water Re-injec...
-The PERT Chart-The tendering time schedule for Adar Produced  Water Re-injec...-The PERT Chart-The tendering time schedule for Adar Produced  Water Re-injec...
-The PERT Chart-The tendering time schedule for Adar Produced Water Re-injec...
 
61T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 20141129
61T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 2014112961T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 20141129
61T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 20141129
 
DAMAC Heights Project
DAMAC Heights ProjectDAMAC Heights Project
DAMAC Heights Project
 
Project Controls planning & Scheduling Engineer-Portfolio
Project Controls planning & Scheduling Engineer-PortfolioProject Controls planning & Scheduling Engineer-Portfolio
Project Controls planning & Scheduling Engineer-Portfolio
 
Harmal Field Development Phase 1 and Phase 2 Final-10.10.2013-R2
Harmal Field Development Phase 1 and Phase 2 Final-10.10.2013-R2Harmal Field Development Phase 1 and Phase 2 Final-10.10.2013-R2
Harmal Field Development Phase 1 and Phase 2 Final-10.10.2013-R2
 
NNP Shutdown 2014 Plans - Scurve and npt graph
NNP Shutdown 2014 Plans - Scurve and npt graphNNP Shutdown 2014 Plans - Scurve and npt graph
NNP Shutdown 2014 Plans - Scurve and npt graph
 
Monitoring Programme Review
Monitoring Programme ReviewMonitoring Programme Review
Monitoring Programme Review
 
Checklist for Cost Control Dept in Contracting Company
Checklist for Cost Control Dept in Contracting CompanyChecklist for Cost Control Dept in Contracting Company
Checklist for Cost Control Dept in Contracting Company
 
Payment Method for Work item Studies and Design November 26, 2010.
Payment Method for Work item Studies and Design November 26, 2010.Payment Method for Work item Studies and Design November 26, 2010.
Payment Method for Work item Studies and Design November 26, 2010.
 
Monthly Progress Report - September 2014
Monthly Progress Report - September 2014Monthly Progress Report - September 2014
Monthly Progress Report - September 2014
 
Dada enterprise cost management solution comparisons
Dada enterprise cost management solution comparisonsDada enterprise cost management solution comparisons
Dada enterprise cost management solution comparisons
 
1414424205 1.vize programı_2014-2015_güz_ver3.0
1414424205 1.vize programı_2014-2015_güz_ver3.01414424205 1.vize programı_2014-2015_güz_ver3.0
1414424205 1.vize programı_2014-2015_güz_ver3.0
 
-Strategy Planning Report
-Strategy Planning Report-Strategy Planning Report
-Strategy Planning Report
 
NGS Owners Initial Proposal Timeline Discussion
NGS Owners Initial Proposal Timeline DiscussionNGS Owners Initial Proposal Timeline Discussion
NGS Owners Initial Proposal Timeline Discussion
 
Project management proposal climate observation station, mittagong -nsw
Project management proposal   climate observation station, mittagong -nswProject management proposal   climate observation station, mittagong -nsw
Project management proposal climate observation station, mittagong -nsw
 
Petronas drilling operations guideline
Petronas drilling operations guidelinePetronas drilling operations guideline
Petronas drilling operations guideline
 
Manish Engineering Works
Manish Engineering WorksManish Engineering Works
Manish Engineering Works
 
jahangir
jahangirjahangir
jahangir
 
TQMI project Updated
TQMI project UpdatedTQMI project Updated
TQMI project Updated
 

Viewers also liked

0125262011 Abdulhamid Al Mansour
0125262011 Abdulhamid Al Mansour0125262011 Abdulhamid Al Mansour
0125262011 Abdulhamid Al MansourSarah El Akkad
 
District Heating & Cooling - A vision towards 2020 - 2030 - 2050
District Heating & Cooling - A vision towards 2020 - 2030 - 2050District Heating & Cooling - A vision towards 2020 - 2030 - 2050
District Heating & Cooling - A vision towards 2020 - 2030 - 2050Pôle Réseaux de Chaleur - Cerema
 
Dc summit jeddah 2010 george berbari presentation
Dc summit jeddah 2010   george berbari presentationDc summit jeddah 2010   george berbari presentation
Dc summit jeddah 2010 george berbari presentationOliviaModisakeng
 
George hoetricks, evapco
George hoetricks, evapcoGeorge hoetricks, evapco
George hoetricks, evapcoSarah El Akkad
 
Presentation DCP(revised)
Presentation DCP(revised)Presentation DCP(revised)
Presentation DCP(revised)Daniel udau
 
Co-Generation Plant Reverse Engineering
Co-Generation Plant Reverse EngineeringCo-Generation Plant Reverse Engineering
Co-Generation Plant Reverse EngineeringDerek Dodge
 
0125262011 Fadi hashem, dc pro engineer
0125262011 Fadi hashem, dc pro engineer0125262011 Fadi hashem, dc pro engineer
0125262011 Fadi hashem, dc pro engineerSarah El Akkad
 
Chapter 6 : Smart District heating/cooling, Summer Course, AUST 2015
Chapter 6 : Smart District heating/cooling, Summer Course, AUST 2015Chapter 6 : Smart District heating/cooling, Summer Course, AUST 2015
Chapter 6 : Smart District heating/cooling, Summer Course, AUST 2015Isam Shahrour
 
Chilled water plants
Chilled water plantsChilled water plants
Chilled water plantsAwais Jalali
 
High performance-chilled-water-systems ashrae-chicago
High performance-chilled-water-systems ashrae-chicagoHigh performance-chilled-water-systems ashrae-chicago
High performance-chilled-water-systems ashrae-chicagoIllinois ASHRAE
 
District cooling design & case study
District cooling design & case studyDistrict cooling design & case study
District cooling design & case studyAbdelrahim Ramadan
 
Hvac chilled water distribution schemes
Hvac chilled water distribution schemesHvac chilled water distribution schemes
Hvac chilled water distribution schemesMazhar Sheikh
 
New Microsoft Word Document
New Microsoft Word DocumentNew Microsoft Word Document
New Microsoft Word Documentamr hussien
 
Chilled water piping basics
Chilled water piping basicsChilled water piping basics
Chilled water piping basicsAp Naseem
 

Viewers also liked (16)

0125262011 Abdulhamid Al Mansour
0125262011 Abdulhamid Al Mansour0125262011 Abdulhamid Al Mansour
0125262011 Abdulhamid Al Mansour
 
District Heating & Cooling - A vision towards 2020 - 2030 - 2050
District Heating & Cooling - A vision towards 2020 - 2030 - 2050District Heating & Cooling - A vision towards 2020 - 2030 - 2050
District Heating & Cooling - A vision towards 2020 - 2030 - 2050
 
Dc summit jeddah 2010 george berbari presentation
Dc summit jeddah 2010   george berbari presentationDc summit jeddah 2010   george berbari presentation
Dc summit jeddah 2010 george berbari presentation
 
George hoetricks, evapco
George hoetricks, evapcoGeorge hoetricks, evapco
George hoetricks, evapco
 
Presentation DCP(revised)
Presentation DCP(revised)Presentation DCP(revised)
Presentation DCP(revised)
 
Co-Generation Plant Reverse Engineering
Co-Generation Plant Reverse EngineeringCo-Generation Plant Reverse Engineering
Co-Generation Plant Reverse Engineering
 
0125262011 Fadi hashem, dc pro engineer
0125262011 Fadi hashem, dc pro engineer0125262011 Fadi hashem, dc pro engineer
0125262011 Fadi hashem, dc pro engineer
 
Chapter 6 : Smart District heating/cooling, Summer Course, AUST 2015
Chapter 6 : Smart District heating/cooling, Summer Course, AUST 2015Chapter 6 : Smart District heating/cooling, Summer Course, AUST 2015
Chapter 6 : Smart District heating/cooling, Summer Course, AUST 2015
 
Roger Baroudi, SSHI
Roger Baroudi, SSHIRoger Baroudi, SSHI
Roger Baroudi, SSHI
 
Jeevan joy, spig
Jeevan joy, spigJeevan joy, spig
Jeevan joy, spig
 
Chilled water plants
Chilled water plantsChilled water plants
Chilled water plants
 
High performance-chilled-water-systems ashrae-chicago
High performance-chilled-water-systems ashrae-chicagoHigh performance-chilled-water-systems ashrae-chicago
High performance-chilled-water-systems ashrae-chicago
 
District cooling design & case study
District cooling design & case studyDistrict cooling design & case study
District cooling design & case study
 
Hvac chilled water distribution schemes
Hvac chilled water distribution schemesHvac chilled water distribution schemes
Hvac chilled water distribution schemes
 
New Microsoft Word Document
New Microsoft Word DocumentNew Microsoft Word Document
New Microsoft Word Document
 
Chilled water piping basics
Chilled water piping basicsChilled water piping basics
Chilled water piping basics
 

Similar to Cash Flow Portfolio

Natural gas processing and technology costing
Natural gas processing and technology costingNatural gas processing and technology costing
Natural gas processing and technology costingchumaco83
 
Review W 26 & Plan Week 27 2022_MUM.pptx
Review W 26 & Plan Week 27 2022_MUM.pptxReview W 26 & Plan Week 27 2022_MUM.pptx
Review W 26 & Plan Week 27 2022_MUM.pptxssuserb71d4d
 
ccl-weekly report week8.pptx
ccl-weekly report week8.pptxccl-weekly report week8.pptx
ccl-weekly report week8.pptxssuser3e37d9
 
Review W24 & Plan Week 25 2022 MUM_BAS.pptx
Review W24 & Plan Week 25 2022 MUM_BAS.pptxReview W24 & Plan Week 25 2022 MUM_BAS.pptx
Review W24 & Plan Week 25 2022 MUM_BAS.pptxnoelmanroe1
 
Presentation for DHA on project progress(08-09-22).pptx
Presentation for DHA on project progress(08-09-22).pptxPresentation for DHA on project progress(08-09-22).pptx
Presentation for DHA on project progress(08-09-22).pptxFaisalGulzar19
 
PROJECT REPORT ON Engineers india limited's share movement
PROJECT REPORT ON Engineers india limited's share movementPROJECT REPORT ON Engineers india limited's share movement
PROJECT REPORT ON Engineers india limited's share movementAxis Bank
 
PM Performamnec report- Jan'23.pptx
PM Performamnec report- Jan'23.pptxPM Performamnec report- Jan'23.pptx
PM Performamnec report- Jan'23.pptxsantosh509014
 
City council 8 6-13 ai 32 vv ground water group presentation
City council 8 6-13 ai 32 vv ground water group presentationCity council 8 6-13 ai 32 vv ground water group presentation
City council 8 6-13 ai 32 vv ground water group presentationCity of San Angelo Texas
 
23. CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)
23.  CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)23.  CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)
23. CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)hepemod733
 
Review Week_12_Customer_PulauPanggung (PT.BAS).pptx
Review Week_12_Customer_PulauPanggung (PT.BAS).pptxReview Week_12_Customer_PulauPanggung (PT.BAS).pptx
Review Week_12_Customer_PulauPanggung (PT.BAS).pptxnoelmanroe1
 
Dmi performance analysis Flettner rotor updated_t_hiii_nk_220112
Dmi performance analysis Flettner rotor updated_t_hiii_nk_220112Dmi performance analysis Flettner rotor updated_t_hiii_nk_220112
Dmi performance analysis Flettner rotor updated_t_hiii_nk_220112www.thiiink.com
 
Project Performance Report August 2018.pptx
Project Performance Report August 2018.pptxProject Performance Report August 2018.pptx
Project Performance Report August 2018.pptxChinelo Ezenwa
 
Beauty clinic (Business Loan) urdu
Beauty clinic (Business Loan) urduBeauty clinic (Business Loan) urdu
Beauty clinic (Business Loan) urdukmjahanger
 
MONTHLY REPORT_MARITIM PRIMA 1
MONTHLY REPORT_MARITIM PRIMA 1MONTHLY REPORT_MARITIM PRIMA 1
MONTHLY REPORT_MARITIM PRIMA 1Eko Untung
 

Similar to Cash Flow Portfolio (20)

CPM
CPMCPM
CPM
 
Natural gas processing and technology costing
Natural gas processing and technology costingNatural gas processing and technology costing
Natural gas processing and technology costing
 
Review W 26 & Plan Week 27 2022_MUM.pptx
Review W 26 & Plan Week 27 2022_MUM.pptxReview W 26 & Plan Week 27 2022_MUM.pptx
Review W 26 & Plan Week 27 2022_MUM.pptx
 
ccl-weekly report week8.pptx
ccl-weekly report week8.pptxccl-weekly report week8.pptx
ccl-weekly report week8.pptx
 
Review W24 & Plan Week 25 2022 MUM_BAS.pptx
Review W24 & Plan Week 25 2022 MUM_BAS.pptxReview W24 & Plan Week 25 2022 MUM_BAS.pptx
Review W24 & Plan Week 25 2022 MUM_BAS.pptx
 
Presentation for DHA on project progress(08-09-22).pptx
Presentation for DHA on project progress(08-09-22).pptxPresentation for DHA on project progress(08-09-22).pptx
Presentation for DHA on project progress(08-09-22).pptx
 
PROJECT REPORT ON Engineers india limited's share movement
PROJECT REPORT ON Engineers india limited's share movementPROJECT REPORT ON Engineers india limited's share movement
PROJECT REPORT ON Engineers india limited's share movement
 
PM Performamnec report- Jan'23.pptx
PM Performamnec report- Jan'23.pptxPM Performamnec report- Jan'23.pptx
PM Performamnec report- Jan'23.pptx
 
WORKING PORTFOLIO - 01
WORKING PORTFOLIO - 01WORKING PORTFOLIO - 01
WORKING PORTFOLIO - 01
 
City council 8 6-13 ai 32 vv ground water group presentation
City council 8 6-13 ai 32 vv ground water group presentationCity council 8 6-13 ai 32 vv ground water group presentation
City council 8 6-13 ai 32 vv ground water group presentation
 
23. CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)
23.  CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)23.  CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)
23. CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)
 
FYP Structure.pdf
FYP Structure.pdfFYP Structure.pdf
FYP Structure.pdf
 
Review Week_12_Customer_PulauPanggung (PT.BAS).pptx
Review Week_12_Customer_PulauPanggung (PT.BAS).pptxReview Week_12_Customer_PulauPanggung (PT.BAS).pptx
Review Week_12_Customer_PulauPanggung (PT.BAS).pptx
 
Flight Test Analysis Final
Flight Test Analysis FinalFlight Test Analysis Final
Flight Test Analysis Final
 
Dmi performance analysis Flettner rotor updated_t_hiii_nk_220112
Dmi performance analysis Flettner rotor updated_t_hiii_nk_220112Dmi performance analysis Flettner rotor updated_t_hiii_nk_220112
Dmi performance analysis Flettner rotor updated_t_hiii_nk_220112
 
Cp 24062018 2241
Cp 24062018 2241Cp 24062018 2241
Cp 24062018 2241
 
Project Performance Report August 2018.pptx
Project Performance Report August 2018.pptxProject Performance Report August 2018.pptx
Project Performance Report August 2018.pptx
 
Beauty clinic (Business Loan) urdu
Beauty clinic (Business Loan) urduBeauty clinic (Business Loan) urdu
Beauty clinic (Business Loan) urdu
 
Project 1
Project 1Project 1
Project 1
 
MONTHLY REPORT_MARITIM PRIMA 1
MONTHLY REPORT_MARITIM PRIMA 1MONTHLY REPORT_MARITIM PRIMA 1
MONTHLY REPORT_MARITIM PRIMA 1
 

More from Sam Kendall, MSc, BSc Civil Eng., PMP®, MIEAust

More from Sam Kendall, MSc, BSc Civil Eng., PMP®, MIEAust (20)

Kandil Mohammed Ibrahim_Sameh_Dissertation
Kandil Mohammed Ibrahim_Sameh_DissertationKandil Mohammed Ibrahim_Sameh_Dissertation
Kandil Mohammed Ibrahim_Sameh_Dissertation
 
Summary Progress Of Facade Works
Summary Progress Of Facade WorksSummary Progress Of Facade Works
Summary Progress Of Facade Works
 
Summary Progress Of Concrete Works
Summary Progress Of Concrete WorksSummary Progress Of Concrete Works
Summary Progress Of Concrete Works
 
Progress Of Ceiling Per Floors
Progress Of Ceiling Per FloorsProgress Of Ceiling Per Floors
Progress Of Ceiling Per Floors
 
N1
N1N1
N1
 
Progress Of Slab
Progress Of SlabProgress Of Slab
Progress Of Slab
 
Overall Progress S-Curve For Ceiling
Overall Progress S-Curve For CeilingOverall Progress S-Curve For Ceiling
Overall Progress S-Curve For Ceiling
 
Overall Progress S-Curve For Facades
Overall Progress S-Curve For FacadesOverall Progress S-Curve For Facades
Overall Progress S-Curve For Facades
 
Overall Progress S-Curve For Elevators
Overall Progress S-Curve For ElevatorsOverall Progress S-Curve For Elevators
Overall Progress S-Curve For Elevators
 
Overall Progres S-Curve For Concrete Works
Overall Progres S-Curve For Concrete WorksOverall Progres S-Curve For Concrete Works
Overall Progres S-Curve For Concrete Works
 
13. Overall S-Curve
13. Overall S-Curve13. Overall S-Curve
13. Overall S-Curve
 
Building-Structure Planning Model
Building-Structure Planning ModelBuilding-Structure Planning Model
Building-Structure Planning Model
 
Rihan Height Project Execution Plan-Rev00
Rihan Height Project Execution Plan-Rev00Rihan Height Project Execution Plan-Rev00
Rihan Height Project Execution Plan-Rev00
 
Final Submission EOT 1
Final Submission EOT 1Final Submission EOT 1
Final Submission EOT 1
 
Resources Histograms
Resources HistogramsResources Histograms
Resources Histograms
 
Resources Calculations for Bldg. A
Resources Calculations for Bldg. AResources Calculations for Bldg. A
Resources Calculations for Bldg. A
 
Monthly Progress Report No.05 - June-2012
Monthly Progress Report No.05 - June-2012Monthly Progress Report No.05 - June-2012
Monthly Progress Report No.05 - June-2012
 
Kandil_Sameh_AR50123
Kandil_Sameh_AR50123Kandil_Sameh_AR50123
Kandil_Sameh_AR50123
 
Kandil_Sameh_CPMPart 3 _b
Kandil_Sameh_CPMPart 3 _bKandil_Sameh_CPMPart 3 _b
Kandil_Sameh_CPMPart 3 _b
 
Kandil_Sameh_CPMPart 5 _b
Kandil_Sameh_CPMPart 5 _bKandil_Sameh_CPMPart 5 _b
Kandil_Sameh_CPMPart 5 _b
 

Cash Flow Portfolio

  • 1.  District Cooling Plant for Rihan Heights Project Cash Flow Portfolio AWI 106 Att. 8 Rev. 2 06 Jul. 2009 Date/ Rev.
  • 2. Index  Project Cash Flow  1 - Cash In Data --------------------------- Section 1  1.11 – Cash In-Value of Works & Monthly Invoices --------------------------- Section 1.11  1.12 – Cash In Histogram (EPC Project Period). --------------------------- Section 1.12  1.13 – Cash In Histogram (Operation and Maintenance Period). --------------------------- Section 1.13  2 - Cash Out Data --------------------------- Section 2  2.11 – Cash Out-Value of Works & Monthly Invoices --------------------------- Section 2.11  2.12 – Cash Out Histogram (EPC Project Period). --------------------------- Section 2.12  2.13 – Cash Out Histogram (Operation and Maintenance Period). -------------- Section 2.13  3 - Cash Flow ----------------------- Section 3  3.11 – Project Cash Flow Curve. --------------------------- Section 3.11  3.12 – Project Cash Liquidity. --------------------------- Section 3.12 AWI 106 Att. 8 Rev. 2 06 Jul. 2009 Date/ Rev.
  • 3. Section 1  Cash In Data AWI 106 Att. 8 Rev. 2 06 Jul. 2009 Date/ Rev.
  • 4. Section 1.11  Cash In-Value of Works & Monthly Invoices AWI 106 Att. 8 Rev. 2 06 Jul. 2009 Date/ Rev.
  • 5. Mubadala Capitaland Real Estate District Cooling Plant for Rihan Heights Cash In Value of Works Jul-10 Aug-10 Sep-10 Oct-10 Nov-10 Dec-10 Jan-11 Feb-11 Mar-11 Apr-11 May-11 Jun-11 Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Item No. Description Value of Work 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 A Preliminaries- Design - Procurement- Construction - Testing & Commissioning 49,055,575 A.1 Preliminaries (See Attachment.1) 7,663,699 29.36% 4.38% 5.71% 7.54% 8.68% 10.01% 14.72% 11.87% 7.74% A.2 Design (See Attachment.2) 1,452,016 50.00% 50.00% A.3 Procurement (See Attachment.2) 31,210,488 9.45% 4.39% 7.19% 1.04% 18.02% 27.81% 16.05% 16.05% A.4 Construction (See Attachment.2) 8,487,050 0.81% 3.75% 8.86% 11.91% 10.51% 25.44% 36.32% 2.40% A.5 Testing & Commissioning (See Attachment.2) 242,322 36.98% 51.05% 11.96% B Temporary Generator 2,504,439 B.1 Mobilization Charge 50,323 100.00% B.2 Monthly Charge 2,080,224 8.37% 8.33% 8% 8% 8% 8% 8% 8% 8% 8% 8% 8% B.3 Demobilization Charge 35,223 100% B.4 Generator Installation Charge 338,669 100.00% C Operation and Maintenance 1,606,003 C.1 Operation & Maintenance for 12 motnhs after commissioing 1,606,003 8% 8% 8% 8% 8% 8% 8% 8% 8% 8% 8% 8% SUBTOTAL 53,166,017 5,924,236 2,500,867 2,999,945 1,655,753 7,298,559 10,336,991 8,775,786 9,300,088 999,740 307,384 307,384 307,063 307,063 307,063 307,063 307,063 307,063 307,063 342,286 133,780 133,780 53,166,017 - - 5,924,236 2,500,867 2,999,945 1,655,753 7,298,559 10,336,991 8,775,786 9,300,088 999,740 307,384 307,384 307,063 307,063 307,063 307,063 307,063 307,063 307,063 342,286 133,780 133,780 - - 5 ,924,236 8 ,425,102 1 1,425,048 1 3,080,801 2 0,379,360 3 0,716,351 3 9,492,137 4 8,792,225 4 9,791,964 5 0,099,348 5 0,406,732 5 0,713,795 5 1,020,858 5 1,327,920 5 1,634,983 5 1,942,046 5 2,249,108 5 2,556,171 5 2,898,457 5 3,032,237 5 3,166,017 Plan. Value of Work - Month Plan. Value of Work - Cumulative Planned Percent. 11.14% 15.85% 21.49% 24.60% 38.33% 57.77% 74.28% 91.77% 93.65% 94.23% 94.81% 95.39% 95.97% 96.54% 97.12% 97.70% 98.28% 98.85% 99.50% 99.75% 100.00% File Name:Cash Flow Page 1 of 2 Printed On:10/20/10 at 1:06 PM
  • 6. Mubadala Capitaland Real Estate District Cooling Plant for Rihan Heights Preliminaries (Attachement.1) Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Item No. Description Value 1 2 3 4 5 6 7 8 9 10 11 A PRELIMINARIES 7,648,386 A.1 Contractual requirements 1 ,160,988 A.1.1 Insurance 3 49,273 100% A.1.2 Contract Price and Payment 5 46,973 100% A.1.3 Enviromental Assessment 3 3,000 100% A.1.4 Defect Liability maintenance 2 31,742 100% A.2 Services for the Employer's 7 8,981 A.2.1 Progress Photos 7 70 100% A.2.2 Sanitary 7 8,211 100% A.3 Temporary Works 2 0,700 A.3.1 Gates 4 ,400 100% A.3.2 Fire Protection 6 ,204 11% 11% 11% 11% 11% 11% 11% 11% 11% A.3.3 Safety 1 0,096 11% 11% 11% 11% 11% 11% 11% 11% 11% A.4 Contractor Facilities 1 ,154,071 A.4.1 Facilities Required by Contractor 1 ,154,071 90% 1% 1% 1% 1% 1% 1% 1% 3% A.5 Services for the contractor 3 93,049 A.5.1 Transport of workforce 3 93,049 11% 11% 11% 11% 11% 11% 11% 11% 11% A.6 Plant for permanent works (not included in construction works) 2 18,244 A.6.1 Small plant and tools. 3 ,494 11% 11% 11% 11% 11% 11% 11% 11% 11% A.6.2 Scaffolding. 2 0,173 14% 14% 14% 14% 14% 14% 14% A.6.3 Cranes and lifting plant. 1 94,577 14% 14% 14% 14% 14% 14% 14% A.7 Supervision and Labour 4 ,622,353 A.7.1 Manual Manpower 2 ,909,987 3% 6% 11% 14% 17% 27% 19% 3% A.7.2 Non Mnaual Manpower 1 ,712,366 10% 10% 10% 10% 10% 10% 15% 15% 10% A.8 Surveys A.8.1 Topoghrapic Survey 3 ,123 100% A.8.2 Geotechnical Investigation 1 2,190 100% SUBTOTAL 7,663,699 2,249,979 335,733 437,314 578,047 664,985 766,940 1,127,722 909,563 593,417 Plan. Value of Work - Month 7,663,699 - 2,249,979 335,733 437,314 578,047 664,985 766,940 1,127,722 909,563 593,417 - Plan. Value of Work - Cumulative - 2,249,979 2,585,712 3,023,026 3,601,073 4,266,058 5,032,998 6,160,719 7,070,282 7,663,699 - Planned Percent. 29.36% 33.74% 39.45% 46.99% 55.67% 65.67% 80.39% 92.26% 100.00%
  • 7. Activity Name Start Finish Budgeted Cost Budgeted U Mubadala Capitaland Real Estate District Cooling Plant for Rihan Heights 2010 2011 Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun District Cooling Plant for Rihan Heights 05-Aug-10 12-May-11 49,055,575 15313 5908923 2500867 2999945 1655753 7298559 10336991 8386793 9125973 826457 Cash Flow 05-Aug-10 12-May-11 49,055,575 15313 5908923 2500867 2999945 1655753 7298559 10336991 8386793 9125973 826457 District Cooling Plant for Rihan Heights 05-Aug-10 12-May-11 49,055,575 15313 5908923 2500867 2999945 1655753 7298559 10336991 8386793 9125973 826457 General 05-Aug-10 12-May-11 7,663,699 15313 2234666 335733 437314 578047 664985 766940 1127722 909563 593417 Mobilization 05-Aug-10 12-May-11 7,663,699 15313 2234666 335733 437314 578047 664985 766940 1127722 909563 593417 Soil Investigation 05-Aug-10 16-Aug-10 15,313 15313 Topographic Survey 05-Aug-10 08-Aug-10 3,123 3123 Geo Technical Investigation Report 14-Aug-10 16-Aug-10 12,190 12190 Site Offices & Utilities 01-Sep-10 12-May-11 7,648,386 2234666 335733 437314 578047 664985 766940 1127722 909563 593417 Preliminaries 01-Sep-10 12-May-11 7,648,386 2234666 335733 437314 578047 664985 766940 1127722 909563 593417 Design and Engineering 01-Sep-10 14-Oct-10 1,452,016 726008 726008 Design 01-Sep-10 14-Oct-10 1,452,016 726008 726008 Concept & Schematic Design 01-Sep-10 01-Sep-10 726,008 726008 Process Equipments 01-Sep-10 01-Sep-10 726,008 726008 Approve Concept & Schematic Design by Capitala 01-Sep-10 01-Sep-10 726,008 726008 Detailed Design 02-Oct-10 14-Oct-10 726,008 726008 Process Equipments 02-Oct-10 14-Oct-10 726,008 726008 Capitala Approve Detailed Engineering Package 02-Oct-10 14-Oct-10 726,008 726008 Procurement 29-Sep-10 02-Apr-11 31,210,488 2948249 1370194 2244708 325602 5622982 8678142 5010306 5010306 Mechanical 29-Sep-10 02-Apr-11 21,892,623 2948249 2244708 325602 2807300 3546152 5010306 5010306 Procurement & Delivery 29-Sep-10 02-Apr-11 21,892,623 2948249 2244708 325602 2807300 3546152 5010306 5010306 Plant Module Material 29-Sep-10 02-Apr-11 20,839,464 2948249 2244708 325602 2754642 2545652 5010306 5010306 Process Equipments 29-Sep-10 02-Apr-11 14,741,247 2948249 886193 886193 5010306 5010306 Procurement&Delivery of Chillers and Module Enclosure 30-Sep-10 02-Apr-11 10,020,611 2004122 4008245 4008245 Procurement&Delivery of Chilled Water Pump 30-Sep-10 02-Apr-11 2,505,153 501031 1002061 1002061 Delivery of Cooling Tower 29-Sep-10 04-Feb-11 2,215,482 443096 886193 886193 Pipes & Valves 01-Nov-10 28-Feb-11 2,713,346 1953609 325602 434135 Chilled&Condenser System 01-Nov-10 28-Feb-11 2,713,346 1953609 325602 434135 Procurement&Delivery of Chilled&Condeser Water Pipes 18-Dec-10 18-Dec-10 325,602 325602 Procurement&Delivery of Chilled Water Reticulation Polyethylene Pipes 01-Nov-10 07-Nov-10 1,953,609 1953609 Procurement&Delivery of Chilled Water (Valves-Accessories-Fittings) 16-Feb-11 28-Feb-11 298,468 298468 Procurement&Delivery of Buterflly Valves 16-Feb-11 28-Feb-11 135,667 135667 Heat Exchanger 08-Nov-10 16-Feb-11 3,384,872 291099 1868449 1225324 Procurement&Delivery of Heat Exchangers 08-Nov-10 16-Feb-11 1,455,495 291099 582198 582198 Procurement&Delivery of Heat Exchanger Valves 16-Feb-11 16-Feb-11 643,126 643126 Procurement&Delivery of Heat Exchanger Pipes 16-Jan-11 17-Jan-11 1,286,251 1286251 Building Services Materials 16-Jan-11 21-Feb-11 1,053,158 52658 1000500 Fire Fighting 16-Jan-11 21-Feb-11 1,053,158 52658 1000500 Procurement&Delivery of Fire System (FM200 or Pre-Action) 16-Feb-11 21-Feb-11 947,843 947843 Procurement&Delivery of Fire Sprinklers 16-Feb-11 21-Feb-11 52,658 52658 Procurement&Delivery of Fire Pipes 16-Jan-11 16-Jan-11 52,658 52658 Electrical 20-Oct-10 28-Feb-11 9,317,866 1370194 2815682 5131990 Procurement & Delivery 20-Oct-10 28-Feb-11 9,317,866 1370194 2815682 5131990 Plant Module Materials 20-Oct-10 28-Feb-11 9,317,866 1370194 2815682 5131990 Process Equipments 20-Oct-10 28-Feb-11 8,614,975 1370194 2740388 4504393 Procurement&Delivery of SCADA System 26-Feb-11 28-Feb-11 1,764,005 1764005 Procurement&Delivery of Electrical Module Enclosure (LV-MV) 20-Oct-10 23-Feb-11 6,850,970 1370194 2740388 2740388 Transformers 01-Feb-11 15-Feb-11 627,597 627597 Procurement&Delivery of 11 KV Transformers (Dry Type) 01-Feb-11 15-Feb-11 627,597 627597 Others 16-Jan-11 23-Jan-11 75,294 75294 Procurement&Delivery of UPS 16-Jan-11 23-Jan-11 75,294 75294 Construction 23-Oct-10 12-May-11 8,487,050 68932 317923 752104 1010593 891909 2159155 3082388 204047 District Cooling Modular Plant 23-Oct-10 09-May-11 4,589,366 32655 100008 255298 192248 212353 1146293 2501219 149291 Civil 23-Oct-10 10-Mar-11 656,575 32655 100008 255298 182945 47669 38000 Cooling Tower Module 23-Oct-10 09-Jan-11 521,502 20130 100008 255298 146066 Foundation Level 23-Oct-10 08-Dec-10 168,928 20130 100008 48791 Earth Work 23-Oct-10 21-Nov-10 74,909 20130 54779 Waterproofing Sheet & Screed over 13-Nov-10 21-Nov-10 31,843 31843 Installation of Dewatering System Equipment 26-Oct-10 28-Oct-10 6,710 6710 Initial Excavation 23-Oct-10 25-Oct-10 6,710 6710 Formation and Blinding 07-Nov-10 11-Nov-10 11,752 11752 Excavation 02-Nov-10 06-Nov-10 8,947 8947 Draw down the Underground Water 29-Oct-10 01-Nov-10 8,947 6710 2237 Foundations 22-Nov-10 08-Dec-10 94,020 45229 48791 Steel Fixing 22-Nov-10 05-Dec-10 35,257 25642 9616 Form Work 25-Nov-10 06-Dec-10 35,257 19587 15670 Concrete Pouring 08-Dec-10 08-Dec-10 23,505 23505 Ground Floor 09-Dec-10 09-Jan-11 352,574 206508 146066 Walls 09-Dec-10 23-Dec-10 176,287 176287 Steel Fixing of Tank Walls 09-Dec-10 15-Dec-10 70,515 70515 Form Work of Tank Walls 13-Dec-10 22-Dec-10 70,515 70515 Concrete Pouring 23-Dec-10 23-Dec-10 35,257 35257 Slab 28-Dec-10 09-Jan-11 176,287 30221 146066 Steel Fixing of Tank Slab 02-Jan-11 08-Jan-11 70,515 70515 Form Work of Tank Slab 28-Dec-10 05-Jan-11 70,515 30221 40294 Concrete Pouring 09-Jan-11 09-Jan-11 35,257 35257 LV Switchgear Module 23-Oct-10 06-Feb-11 67,536 6263 36878 24395 Foundation Level 23-Oct-10 06-Feb-11 67,536 6263 36878 24395 Earth Work 23-Oct-10 22-Jan-11 20,526 6263 14264 Waterproofing Sheet & Screed over 16-Jan-11 22-Jan-11 8,388 8388 Formation and Blinding 10-Jan-11 15-Jan-11 5,876 5876 Excavation 23-Oct-10 30-Oct-10 6,263 6263 Foundations 23-Jan-11 06-Feb-11 47,010 22615 24395 Steel Fixing 23-Jan-11 03-Feb-11 17,629 12821 4808 Form Work 26-Jan-11 05-Feb-11 17,629 9794 7835 Concrete Pouring 06-Feb-11 06-Feb-11 11,752 11752 Chiller Module 23-Oct-10 10-Mar-11 67,536 6263 23274 38000 Foundation Level 23-Oct-10 10-Mar-11 67,536 6263 23274 38000 Earth Work 23-Oct-10 23-Feb-11 20,526 6263 14264 Data Date : 18-Jul-10 Page : 1 of 8 Printed On : 22-Sep-10 Project Implementation Schedule Value of Work in Dirhams (Attachment .2) Date Revision Checked Approved 15-Aug-10 Project Implementation Schedule Rev.00 21-Sep-10 Project Implementation Schedule Rev.01
  • 8. Activity Name Start Finish Budgeted Cost Budgeted U Mubadala Capitaland Real Estate District Cooling Plant for Rihan Heights 2010 2011 Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Waterproofing Sheet & Screed over 16-Feb-11 23-Feb-11 8,388 8388 Formation and Blinding 07-Feb-11 14-Feb-11 5,876 5876 Excavation 23-Oct-10 30-Oct-10 6,263 6263 Foundations 24-Feb-11 10-Mar-11 47,010 9010 38000 Steel Fixing 24-Feb-11 07-Mar-11 17,629 7051 10577 Form Work 28-Feb-11 09-Mar-11 17,629 1959 15670 Concrete Pouring 10-Mar-11 10-Mar-11 11,752 11752 Architectural 27-Jan-11 25-Apr-11 174,405 9303 53494 62780 48829 Make Up Water Tank 27-Jan-11 26-Feb-11 58,147 9303 48843 GRP Lining for Make Up Water Tank 27-Jan-11 26-Feb-11 58,147 9303 48843 Blow Down 27-Feb-11 27-Mar-11 58,129 4650 53479 GRP Lining for Blow Down 27-Feb-11 27-Mar-11 58,129 4650 53479 FireTank 28-Mar-11 25-Apr-11 58,129 9301 48829 GRP Lining for Fire Tank 28-Mar-11 25-Apr-11 58,129 9301 48829 Mechanical 05-Feb-11 07-May-11 1,923,871 21406 169441 1660908 72117 Cooling Tower Module 05-Feb-11 23-Apr-11 246,165 21406 37674 187085 Install Cooling Tower Components (FRP) 05-Feb-11 30-Mar-11 49,233 21406 27827 Install Cooling Tower 31-Mar-11 23-Apr-11 196,932 9847 187085 Chiller Module 03-Apr-11 23-Apr-11 362,588 362588 Install Chiller Module Enclosure 13-Apr-11 23-Apr-11 296,663 296663 Install Chiller Module Base Frame 03-Apr-11 12-Apr-11 65,925 65925 Chilled Water Pumps 03-Apr-11 11-Apr-11 296,663 296663 Install Chilled Water Pump 03-Apr-11 11-Apr-11 296,663 296663 Make Up Water Pump 13-Mar-11 28-Mar-11 115,271 115271 Install Make Up Water Pump 24-Mar-11 28-Mar-11 44,351 44351 Install Make Up Water Pipes & Access. 13-Mar-11 23-Mar-11 70,920 70920 Blow Down Pump 01-Mar-11 12-Mar-11 16,496 16496 Install Blow Down Water Pipes & Access. 01-Mar-11 12-Mar-11 16,496 16496 Other Systems 05-Apr-11 07-May-11 886,689 814572 72117 Install the Process Instrument 24-Apr-11 07-May-11 144,233 72116 72117 Install Expansion Tank-Outside the Modular 05-Apr-11 12-Apr-11 38,440 38440 Install Chemical Water Treatment-Outside the Modular 14-Apr-11 21-Apr-11 510,697 510697 Install Air Seperator 05-Apr-11 12-Apr-11 193,319 193319 Electrical 24-Feb-11 09-May-11 1,834,515 89785 876073 791482 77175 Attendance and Coordination by ADWEA 24-Feb-11 01-May-11 39,732 2788 18820 17426 697 MV & LV Switchgear Module Foundation 24-Feb-11 10-Apr-11 761,219 86996 587226 86996 Install MV Switch gear 26-Mar-11 10-Apr-11 152,244 65247 86996 Install Electrical Module Enclosure (LV) 13-Mar-11 28-Mar-11 304,488 304488 Install Electrical Module Base Frame (LV) 24-Feb-11 12-Mar-11 304,488 86996 217491 Transformers 19-Mar-11 04-Apr-11 69,733 55786 13947 Install Transformers 19-Mar-11 04-Apr-11 69,733 55786 13947 Cables Works 03-Mar-11 09-May-11 870,015 214240 632906 22868 Excavation 12-Mar-11 16-Mar-11 16,850 16850 Excavation Cable Trenches 12-Mar-11 16-Mar-11 16,850 16850 Cable Trays 03-Mar-11 19-Mar-11 67,401 67401 Cable Trays at Transformer Room 03-Mar-11 07-Mar-11 25,276 25276 Cable Trays at Pump Room 14-Mar-11 19-Mar-11 16,850 16850 Cable Trays at ADDC Room 08-Mar-11 13-Mar-11 25,276 25276 Cables 16-Mar-11 09-May-11 785,763 129988 632906 22868 MV Cables 30-Mar-11 01-May-11 252,755 19258 231091 2407 From ADDC Intake to 11 KV Switchgear 07-Apr-11 12-Apr-11 84,252 84252 MV Cable Termination for 11 KV Switch gear 11-Apr-11 12-Apr-11 16,850 16850 MV Cable Laying 07-Apr-11 10-Apr-11 67,401 67401 From 11 KV Switchgear to Chiller Soft Starter 30-Mar-11 01-May-11 84,252 19258 62587 2407 MV Cable Termination for Chiller Soft Starter 24-Apr-11 01-May-11 16,850 14443 2407 MV Cable Laying 30-Mar-11 06-Apr-11 67,401 19258 48144 From 11 KV Switchgear to Transformer 11-Apr-11 14-Apr-11 84,252 84252 MV Cable Termination for Transformer 13-Apr-11 14-Apr-11 16,850 16850 MV Cable Laying 11-Apr-11 12-Apr-11 67,401 67401 LV Cables 24-Mar-11 03-May-11 252,755 96288 149246 7222 From Transformer to LV Switchgear 24-Mar-11 20-Apr-11 84,252 67401 16850 LV Cable Termination for LV Switch gear 05-Apr-11 20-Apr-11 16,850 16850 LV Cable Laying 24-Mar-11 28-Mar-11 67,401 67401 From LV Switchgear to Starter or VFD of Pump 29-Mar-11 03-May-11 84,252 28886 48144 7222 LV Cable Termination for Starter or VFD of Pumps 26-Apr-11 03-May-11 16,850 9629 7222 LV Cable Laying 29-Mar-11 05-Apr-11 67,401 28886 38515 From LV Switchgear to Distribution Board 06-Apr-11 25-Apr-11 84,252 84252 LV Cable Termination for Distribution Board 21-Apr-11 25-Apr-11 16,850 16850 LV Cable Laying 06-Apr-11 10-Apr-11 67,401 67401 Control & Fibre Optic Cables 16-Mar-11 09-May-11 280,252 14443 252570 13240 Fibre Optic Cables 10-Apr-11 08-May-11 238,126 229701 8425 Installation of Control System 14-Apr-11 30-Apr-11 196,001 196001 Fibre Optic Cable Termination 01-May-11 08-May-11 8,425 8425 Fibre Optic Cable Laying Inside Control Room 10-Apr-11 13-Apr-11 33,701 33701 Control Cables 16-Mar-11 09-May-11 42,126 14443 22868 4814 Control Cable Termination for Control Cables 24-Apr-11 09-May-11 8,425 3611 4814 Control Cable Laying Outside Control Room 16-Mar-11 09-Apr-11 16,850 11234 5617 Control Cable Laying Inside Control Room 28-Mar-11 20-Apr-11 16,850 3210 13641 Earthing System 24-Apr-11 09-May-11 93,816 40207 53609 Installation of Earthing System 24-Apr-11 09-May-11 93,816 40207 53609 Ancillary Building 23-Oct-10 12-May-11 1,574,202 36277 78773 139081 240926 264970 450785 308634 54756 Civil 23-Oct-10 17-Feb-11 641,962 36277 78773 139081 240926 146906 Foundation Level 23-Oct-10 23-Dec-10 207,121 36277 78773 92071 Earth Work 23-Oct-10 08-Nov-10 65,287 36277 29010 Waterproofing Sheet & Screed over 03-Nov-10 08-Nov-10 24,309 24309 Formation and Blinding 28-Oct-10 02-Nov-10 11,752 7051 4701 Excavation 23-Oct-10 27-Oct-10 29,225 29225 Foundations 09-Nov-10 23-Dec-10 141,834 49763 92071 Water Proofing & Backfilling up to Slab on Grade Level 16-Dec-10 18-Dec-10 9,804 9804 Data Date : 18-Jul-10 Page : 2 of 8 Printed On : 22-Sep-10 Project Implementation Schedule Value of Work in Dirhams (Attachment .2) Date Revision Checked Approved 15-Aug-10 Project Implementation Schedule Rev.00 21-Sep-10 Project Implementation Schedule Rev.01
  • 9. Activity Name Start Finish Budgeted Cost Budgeted U Mubadala Capitaland Real Estate District Cooling Plant for Rihan Heights 2010 2011 Data Date : 18-Jul-10 Page : 3 of 8 Printed On : 22-Sep-10 Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Water Proofing & Backfilling up to Grid Beam Level 28-Nov-10 29-Nov-10 9,804 9804 Steel Fixing of Tie Beams 12-Dec-10 14-Dec-10 14,103 14103 Steel Fixing of Nick Columns&Trenches 30-Nov-10 05-Dec-10 14,103 3526 10577 Steel Fixing of Footings 13-Nov-10 25-Nov-10 14,103 14103 Form Work of Tie Beams 09-Dec-10 13-Dec-10 14,103 14103 Form Work of Nick Columns&Trenches 04-Dec-10 06-Dec-10 14,103 14103 Form Work of Footings 09-Nov-10 22-Nov-10 14,103 14103 Concrete Pouring of Tie Beams 15-Dec-10 15-Dec-10 8,227 8227 Concrete Pouring of Slab on Grade 19-Dec-10 23-Dec-10 12,928 12928 Concrete Pouring of Nick Columns&Trenches 08-Dec-10 08-Dec-10 8,227 8227 Concrete Pouring of Footings 27-Nov-10 27-Nov-10 8,227 8227 Ground Floor 25-Dec-10 08-Feb-11 188,040 47010 129277 11752 Steel Fixing of Slab 10-Jan-11 13-Jan-11 47,010 47010 Steel Fixing of Columns 25-Dec-10 27-Dec-10 23,505 23505 R.C Plinths for Process Equipment 03-Feb-11 08-Feb-11 11,752 11752 MEP Works Inside Slab 10-Jan-11 12-Jan-11 11,752 11752 Form Work of Slab 05-Jan-11 09-Jan-11 47,010 47010 Form Work of Columns 28-Dec-10 30-Dec-10 23,505 23505 Concrete Pouring of Slab 15-Jan-11 15-Jan-11 11,752 11752 Concrete Pouring of Columns 02-Jan-11 02-Jan-11 11,752 11752 First Floor 16-Jan-11 06-Feb-11 188,040 111648 76391 Steel Fixing of Slab 01-Feb-11 05-Feb-11 52,886 52886 Steel Fixing of Columns 16-Jan-11 18-Jan-11 23,505 23505 MEP Works Inside Slab 02-Feb-11 05-Feb-11 11,752 11752 Form Work of Slab 26-Jan-11 31-Jan-11 52,886 52886 Form Work of Columns 18-Jan-11 20-Jan-11 23,505 23505 Concrete Pouring of Slab 06-Feb-11 06-Feb-11 11,752 11752 Concrete Pouring of Columns 22-Jan-11 22-Jan-11 11,752 11752 Roof Level 07-Feb-11 17-Feb-11 58,762 58762 Steel Fixing of Parapits 07-Feb-11 13-Feb-11 23,505 23505 Form Work of Parapets 10-Feb-11 16-Feb-11 23,505 23505 Concrete Pouring of Parapets 17-Feb-11 17-Feb-11 11,752 11752 Architectural 09-Feb-11 12-May-11 466,727 77317 197655 162238 29517 Ground Floor 09-Feb-11 07-May-11 182,934 54215 124552 1018 3148 ADDC Intake Room 09-Feb-11 04-May-11 61,196 20063 39285 1848 Plaster Works 01-Mar-11 07-Mar-11 3,698 3698 Install Windows and Doors Works 26-Mar-11 27-Mar-11 30,040 30040 Install Windows & Doors Frames 23-Feb-11 24-Feb-11 3,338 3338 Final Paint Coat Works 02-May-11 04-May-11 1,848 1848 Epoxy Coating 14-Mar-11 17-Mar-11 3,698 3698 Blocks Works 09-Feb-11 21-Feb-11 16,725 16725 Base Paint Coat Works 21-Mar-11 23-Mar-11 1,848 1848 Pumps Room 22-Feb-11 01-May-11 45,689 11179 32984 1018 509 Plaster Works 09-Mar-11 13-Mar-11 3,055 3055 Install Windows and Doors Works 30-Mar-11 31-Mar-11 25,347 25347 Install Windows & Doors Frames 27-Feb-11 28-Feb-11 2,816 2816 Final Paint Coat Works 28-Apr-11 01-May-11 1,527 1018 509 Epoxy Coating 20-Mar-11 23-Mar-11 3,055 3055 Blocks Works 22-Feb-11 26-Feb-11 8,362 8362 Base Paint Coat Works 27-Mar-11 29-Mar-11 1,527 1527 Transformers Room 09-Feb-11 07-May-11 76,049 22974 52284 791 Plaster Works 27-Feb-11 02-Mar-11 1,583 792 792 Install Windows and Doors Works 19-Mar-11 20-Mar-11 49,117 49117 Install Windows & Doors Frames 23-Feb-11 24-Feb-11 5,457 5457 Final Paint Coat Works 04-May-11 07-May-11 791 791 Epoxy Coating 08-Mar-11 12-Mar-11 1,583 1583 Blocks Works 09-Feb-11 16-Feb-11 16,725 16725 Base Paint Coat Works 15-Mar-11 17-Mar-11 791 791 First Floor 26-Feb-11 12-May-11 249,296 5854 55854 161220 26369 Office 05-Mar-11 22-Apr-11 128,566 21163 107404 Plaster Works 22-Mar-11 26-Mar-11 3,829 3829 Install Windows and Doors 09-Apr-11 09-Apr-11 11,876 11876 Install Windows & Doors Frames 14-Mar-11 15-Mar-11 1,320 1320 Install Furniture 21-Apr-11 22-Apr-11 88,349 88349 Install False Ceiling Tiles 10-Apr-11 11-Apr-11 1,914 1914 Install False Ceiling Frames 05-Apr-11 07-Apr-11 1,914 1914 Floor Tiles 27-Mar-11 30-Mar-11 3,829 3829 Final Paint Coat Works 18-Apr-11 20-Apr-11 1,914 1914 Blocks Works 05-Mar-11 10-Mar-11 11,707 11707 Base Paint Coat Works 31-Mar-11 04-Apr-11 1,914 479 1436 Control Room 26-Feb-11 12-May-11 27,570 5854 11578 9153 985 Plaster Works 14-Mar-11 17-Mar-11 1,971 1971 Install Windows and Doors 27-Apr-11 28-Apr-11 7,183 7183 Install Windows & Doors Frames 07-Mar-11 08-Mar-11 798 798 Install False Ceiling Tiles 25-Apr-11 26-Apr-11 985 985 Install False Ceiling Frames 21-Apr-11 24-Apr-11 985 985 Floor Tiles 19-Mar-11 22-Mar-11 1,971 1971 Final Paint Coat Works 10-May-11 12-May-11 985 985 Blocks Works 26-Feb-11 03-Mar-11 11,707 5854 5854 Base Paint Coat Works 23-Mar-11 27-Mar-11 985 985 Toilets 12-Mar-11 17-Apr-11 11,889 5005 6884 Waterproofing Membrane for Toilet 26-Mar-11 26-Mar-11 671 671 Install Windows and Doors 10-Apr-11 11-Apr-11 5,263 5263 Install Windows & Doors Frames 15-Mar-11 16-Mar-11 585 585 Install Toilet Accessories 14-Apr-11 17-Apr-11 405 405 Install False Ceiling Tiles 12-Apr-11 13-Apr-11 405 405 Install False Ceiling Frames 09-Apr-11 09-Apr-11 405 405 Floor & Wall Tiles 31-Mar-11 02-Apr-11 810 405 405 Blocks Works 12-Mar-11 14-Mar-11 3,345 3345 Project Implementation Schedule Value of Work in Dirhams (Attachment .2) Date Revision Checked Approved 15-Aug-10 Project Implementation Schedule Rev.00 21-Sep-10 Project Implementation Schedule Rev.01
  • 10. Activity Name Start Finish Budgeted Cost Budgeted U Mubadala Capitaland Real Estate District Cooling Plant for Rihan Heights 2010 2011 Data Date : 18-Jul-10 Page : 4 of 8 Printed On : 22-Sep-10 Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Kitchen 15-Mar-11 03-May-11 30,568 4600 8641 17327 Waterproofing Membrane for Kitchen 30-Mar-11 30-Mar-11 671 671 Install Windows and Doors 13-Apr-11 14-Apr-11 5,263 5263 Install Windows & Doors Frames 19-Mar-11 20-Mar-11 585 585 Install Kitchen Equipment 02-May-11 03-May-11 17,327 17327 Install False Ceiling Tiles 16-Apr-11 16-Apr-11 845 845 Install False Ceiling Frames 10-Apr-11 12-Apr-11 845 845 Floor & Wall Tiles 03-Apr-11 04-Apr-11 1,689 1689 Blocks Works 15-Mar-11 17-Mar-11 3,345 3345 Mess Room 19-Mar-11 07-May-11 18,038 8947 8613 479 Plaster Works 04-Apr-11 07-Apr-11 957 957 Install Windows and Doors 21-Apr-11 23-Apr-11 5,263 5263 Install Windows & Doors Frames 24-Mar-11 26-Mar-11 585 585 Install False Ceiling Tiles 24-Apr-11 25-Apr-11 479 479 Install False Ceiling Frames 18-Apr-11 20-Apr-11 479 479 Floor Tiles 09-Apr-11 12-Apr-11 957 957 Final Paint Coat Works 04-May-11 07-May-11 479 479 Blocks Works 19-Mar-11 23-Mar-11 8,362 8362 Base Paint Coat Works 13-Apr-11 17-Apr-11 479 479 Store 24-Mar-11 12-May-11 32,664 4560 20526 7578 Plaster Works 09-Apr-11 12-Apr-11 2,740 2740 Install Windows and Doors 26-Apr-11 27-Apr-11 10,938 10938 Install Windows & Doors Frames 30-Mar-11 31-Mar-11 1,215 1215 Install Sinage 08-May-11 12-May-11 6,208 6208 Install False Ceiling Tiles 28-Apr-11 30-Apr-11 1,370 1370 Install False Ceiling Frames 23-Apr-11 25-Apr-11 1,370 1370 Floor Tiles 13-Apr-11 17-Apr-11 2,740 2740 Final Paint Coat Works 08-May-11 10-May-11 1,370 1370 Blocks Works 24-Mar-11 29-Mar-11 3,345 3345 Base Paint Coat Works 18-Apr-11 21-Apr-11 1,370 1370 Roof Level 27-Feb-11 02-Mar-11 34,497 17249 17249 Primer and Membrane 27-Feb-11 02-Mar-11 34,497 17249 17249 Mechanical 27-Feb-11 07-May-11 388,617 35823 224410 108782 19601 Ground Floor 27-Feb-11 03-May-11 160,836 35823 55884 65379 3750 ADDC Intake Room 28-Mar-11 18-Apr-11 41,361 20060 21301 Fire Fighting 28-Mar-11 04-Apr-11 35,105 20060 15045 Install Fire System (FM200 or Pre-Action) 28-Mar-11 04-Apr-11 35,105 20060 15045 HVAC 13-Apr-11 18-Apr-11 6,256 6256 Install Split Unit 13-Apr-11 18-Apr-11 6,256 6256 Pumps Room 27-Feb-11 27-Apr-11 78,120 35823 35823 6473 Fire Fighting 19-Apr-11 21-Apr-11 223 223 Install Extinguishers 19-Apr-11 21-Apr-11 223 223 HVAC 23-Apr-11 27-Apr-11 6,250 6250 Install Ventilation 23-Apr-11 27-Apr-11 6,250 6250 Plumbing 27-Feb-11 02-Mar-11 71,647 35823 35823 Install Water Supply System Pipes with Fittings 27-Feb-11 02-Mar-11 27,530 13765 13765 Install Drain Pipes System Pipes with Fittings 27-Feb-11 02-Mar-11 44,117 22059 22059 Transformers Room 05-Apr-11 03-May-11 41,355 37605 3750 Fire Fighting 05-Apr-11 12-Apr-11 35,105 35105 Install Fire System (FM200 or Pre-Action) 05-Apr-11 12-Apr-11 35,105 35105 HVAC 28-Apr-11 03-May-11 6,250 2500 3750 Install Ventilation 28-Apr-11 03-May-11 6,250 2500 3750 First Floor 12-Mar-11 07-May-11 227,781 168527 43403 15851 Office 12-Mar-11 17-Apr-11 15,611 7021 8590 Fire Fighting 12-Mar-11 13-Apr-11 9,361 7021 2340 Install Fire Sprinkler 12-Apr-11 13-Apr-11 2,340 2340 Install Fire Pipes 12-Mar-11 16-Mar-11 7,021 7021 HVAC 12-Apr-11 17-Apr-11 6,250 6250 Install Split Unit 12-Apr-11 17-Apr-11 6,250 6250 Control Room 17-Mar-11 02-May-11 15,611 7021 6090 2500 Fire Fighting 17-Mar-11 28-Apr-11 9,361 7021 2340 Install Fire Sprinkler 27-Apr-11 28-Apr-11 2,340 2340 Install Fire Pipes 17-Mar-11 22-Mar-11 7,021 7021 HVAC 27-Apr-11 02-May-11 6,250 3750 2500 Install Split Unit 27-Apr-11 02-May-11 6,250 3750 2500 Toilets 15-Mar-11 25-Apr-11 78,098 71626 6473 Fire Fighting 23-Apr-11 25-Apr-11 223 223 Install Extinguishers 23-Apr-11 25-Apr-11 223 223 HVAC 14-Apr-11 19-Apr-11 6,250 6250 Install Ventilation 14-Apr-11 19-Apr-11 6,250 6250 Plumbing 15-Mar-11 19-Mar-11 71,626 71626 Install Water Supply System Pipes with Fittings 15-Mar-11 19-Mar-11 27,521 27521 Install Drain Pipes System Pipes with Fittings 15-Mar-11 19-Mar-11 44,104 44104 Kitchen 20-Mar-11 01-May-11 87,237 78647 7420 1170 Fire Fighting 23-Mar-11 01-May-11 9,361 7021 1170 1170 Install Fire Sprinkler 30-Apr-11 01-May-11 2,340 1170 1170 Install Fire Pipes 23-Mar-11 28-Mar-11 7,021 7021 HVAC 17-Apr-11 21-Apr-11 6,250 6250 Install Split Unit 17-Apr-11 21-Apr-11 6,250 6250 Plumbing 20-Mar-11 23-Mar-11 71,626 71626 Install Water Supply System Pipes with Fittings 20-Mar-11 23-Mar-11 27,521 27521 Install Drain Pipes System Pipes with Fittings 20-Mar-11 23-Mar-11 44,104 44104 Mess Room 29-Mar-11 03-May-11 15,611 4213 7808 3590 Fire Fighting 29-Mar-11 03-May-11 9,361 4213 2808 2340 Install Fire Sprinkler 02-May-11 03-May-11 2,340 2340 Install Fire Pipes 29-Mar-11 03-Apr-11 7,021 4213 2808 HVAC 26-Apr-11 01-May-11 6,250 5000 1250 Install Split Unit 26-Apr-11 01-May-11 6,250 5000 1250 Store 04-Apr-11 07-May-11 15,611 7021 8590 Project Implementation Schedule Value of Work in Dirhams (Attachment .2) Date Revision Checked Approved 15-Aug-10 Project Implementation Schedule Rev.00 21-Sep-10 Project Implementation Schedule Rev.01
  • 11. Activity Name Start Finish Budgeted Cost Budgeted U Mubadala Capitaland Real Estate District Cooling Plant for Rihan Heights 2010 2011 Data Date : 18-Jul-10 Page : 5 of 8 Printed On : 22-Sep-10 Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Fire Fighting 04-Apr-11 05-May-11 9,361 7021 2340 Install Fire Sprinkler 04-May-11 05-May-11 2,340 2340 Install Fire Pipes 04-Apr-11 09-Apr-11 7,021 7021 HVAC 02-May-11 07-May-11 6,250 6250 Install Split Unit 02-May-11 07-May-11 6,250 6250 Electrical 17-Feb-11 08-May-11 76,895 4923 28720 37614 5638 Ground Floor 17-Feb-11 13-Apr-11 25,741 4923 11421 9396 ADDC Intake Room 19-Feb-11 02-Apr-11 9,400 2276 6857 267 Electrical System 19-Feb-11 02-Apr-11 4,944 2276 2401 267 PVC Conduits Installation for Electrical 19-Feb-11 23-Feb-11 942 942 Pulling the Wires 24-Feb-11 28-Feb-11 1,334 1334 Lighting & Power Fixtuers and Accessories installation 28-Mar-11 02-Apr-11 1,334 1067 267 Distribution Board Installation 19-Mar-11 20-Mar-11 1,334 1334 Fire Alarm 28-Mar-11 30-Mar-11 4,457 4457 Installation of Fire Alram Devices 28-Mar-11 30-Mar-11 4,457 4457 Pump Room 27-Feb-11 07-Apr-11 6,945 375 3230 3339 Electrical System 27-Feb-11 07-Apr-11 4,939 375 3230 1334 PVC Conduits Installation for Electrical 27-Feb-11 03-Mar-11 938 375 563 Pulling the Wires 05-Mar-11 08-Mar-11 1,334 1334 Lighting & Power Fixtuers and Accessories installation 03-Apr-11 07-Apr-11 1,334 1334 Distribution Board Installation 24-Mar-11 26-Mar-11 1,334 1334 Fire Alarm 02-Apr-11 04-Apr-11 2,005 2005 Installation of Fire Alram Devices 02-Apr-11 04-Apr-11 2,005 2005 Transformer Room 17-Feb-11 13-Apr-11 9,396 2272 1334 5790 Electrical System 17-Feb-11 13-Apr-11 4,939 2272 1334 1334 PVC Conduits Installation for Electrical 17-Feb-11 21-Feb-11 938 938 Pulling the Wires 22-Feb-11 24-Feb-11 1,334 1334 Lighting & Power Fixtuers and Accessories installation 09-Apr-11 13-Apr-11 1,334 1334 Distribution Board Installation 13-Mar-11 14-Mar-11 1,334 1334 Fire Alarm 05-Apr-11 07-Apr-11 4,457 4457 Installation of Fire Alram Devices 05-Apr-11 07-Apr-11 4,457 4457 First Floor 06-Mar-11 08-May-11 51,155 17299 28218 5638 Office 13-Mar-11 16-Apr-11 9,402 3605 5797 Electrical System 13-Mar-11 16-Apr-11 7,174 3605 3569 PVC Conduits Installation for Electrical 13-Mar-11 16-Mar-11 1,827 1827 Pulling the Wires 17-Mar-11 20-Mar-11 1,778 1778 Lighting & Power Fixtuers and Accessories installation 12-Apr-11 16-Apr-11 1,334 1334 Install Communication System 12-Apr-11 14-Apr-11 2,235 2235 Fire Alarm 12-Apr-11 14-Apr-11 2,228 2228 Installation of Fire Al ram Devices 12-Apr-11 14-Apr-11 2,228 2228 Control Room 06-Mar-11 08-May-11 15,533 3605 9852 2076 Electrical System 06-Mar-11 08-May-11 13,305 3605 8366 1334 PVC Conduits Installation for Electrical 06-Mar-11 09-Mar-11 938 938 Pulling the Wires 10-Mar-11 13-Mar-11 1,334 1334 Lighting & Power Fixtuers and Accessories installation 04-May-11 08-May-11 1,334 1334 Installation & Termination of UPS Panel 02-Apr-11 05-Apr-11 8,366 8366 Distribution Board Installation to Light&Power 28-Mar-11 31-Mar-11 1,334 1334 Fire Alarm 28-Apr-11 01-May-11 2,228 1486 743 Installation of Fire Alram Devices 28-Apr-11 01-May-11 2,228 1486 743 Toilets 17-Mar-11 20-Apr-11 5,830 3605 2225 Electrical System 17-Mar-11 20-Apr-11 4,939 3605 1334 PVC Conduits Installation for Electrical 17-Mar-11 21-Mar-11 1,827 1827 Pulling the Wires 22-Mar-11 24-Mar-11 1,778 1778 Lighting & Power Fixtuers and Accessories installation 17-Apr-11 20-Apr-11 1,334 1334 Fire Alarm 16-Apr-11 18-Apr-11 891 891 Installation of Fire Alram Devices 16-Apr-11 18-Apr-11 891 891 Kitchen 22-Mar-11 25-Apr-11 6,053 3605 2448 Electrical System 22-Mar-11 25-Apr-11 4,939 3605 1334 PVC Conduits Installation for Electrical 22-Mar-11 26-Mar-11 1,827 1827 Pulling the Wires 27-Mar-11 29-Mar-11 1,778 1778 Lighting & Power Fixtuers and Accessories installation 21-Apr-11 25-Apr-11 1,334 1334 Fire Alarm 19-Apr-11 21-Apr-11 1,114 1114 Installation of Fire Alram Devices 19-Apr-11 21-Apr-11 1,114 1114 Mess Room 27-Mar-11 30-Apr-11 7,167 2420 4748 Electrical System 27-Mar-11 30-Apr-11 4,939 2420 2519 PVC Conduits Installation for Electrical 27-Mar-11 30-Mar-11 1,827 1827 Pulling the Wires 31-Mar-11 03-Apr-11 1,778 593 1186 Lighting & Power Fixtuers and Accessories installation 26-Apr-11 30-Apr-11 1,334 1334 Fire Alarm 26-Apr-11 27-Apr-11 2,228 2228 Installation of Fire Alram Devices 26-Apr-11 27-Apr-11 2,228 2228 Store 31-Mar-11 03-May-11 7,167 457 3149 3562 Electrical System 31-Mar-11 03-May-11 4,939 457 3149 1334 PVC Conduits Installation for Electrical 31-Mar-11 04-Apr-11 1,827 457 1370 Pulling the Wires 05-Apr-11 07-Apr-11 1,778 1778 Lighting & Power Fixtuers and Accessories installation 01-May-11 03-May-11 1,334 1334 Fire Alarm 02-May-11 03-May-11 2,228 2228 Installation of Fire Alram Devices 02-May-11 03-May-11 2,228 2228 Compound Wall 14-Nov-10 10-Apr-11 317,707 43248 27984 200545 2192 20411 23327 Civil 14-Nov-10 01-Feb-11 273,969 43248 27984 200545 2192 Prepare Foundation Base 25-Nov-10 13-Dec-10 35,616 12720 22896 Install the Pre cast Wall Panels 03-Jan-11 26-Jan-11 191,778 191778 Excavation 14-Nov-10 04-Dec-10 35,616 30528 5088 Backfilling 27-Jan-11 01-Feb-11 10,959 8767 2192 Finishes 24-Mar-11 10-Apr-11 43,738 20411 23327 Gate 24-Mar-11 10-Apr-11 43,738 20411 23327 Install the Gate 24-Mar-11 10-Apr-11 43,738 20411 23327 Reticulation Piping Network & Fibre Optic Cable 07-Nov-10 27-Apr-11 1,196,427 95894 329741 286610 208174 184989 91020 Pipes & Cables 23-Nov-10 27-Apr-11 1,021,779 46993 279093 255174 174991 174510 91020 Inside DCP Plot 19-Dec-10 19-Mar-11 72,356 4738 33701 15828 18089 Project Implementation Schedule Value of Work in Dirhams (Attachment .2) Date Revision Checked Approved 15-Aug-10 Project Implementation Schedule Rev.00 21-Sep-10 Project Implementation Schedule Rev.01
  • 12. Activity Name Start Finish Budgeted Cost Budgeted U Mubadala Capitaland Real Estate District Cooling Plant for Rihan Heights 2010 2011 Data Date : 18-Jul-10 Page : 6 of 8 Printed On : 22-Sep-10 Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun X-Ray 29-Jan-11 10-Feb-11 9,044 2261 6783 Insulation of Pipes 12-Feb-11 28-Feb-11 9,044 9044 Install Valves and Accessories 01-Mar-11 07-Mar-11 9,044 9044 Install the Pipes Supports 19-Dec-10 04-Jan-11 6,030 4738 1292 Install the Pipes 05-Jan-11 27-Jan-11 30,148 30148 Hydrostatic Test 08-Mar-11 19-Mar-11 9,044 9044 Outside DCP Plot 23-Nov-10 27-Apr-11 949,423 46993 274355 221472 159163 156421 91020 Fibre Optic Cable Laying 01-Mar-11 27-Apr-11 8,425 4550 3876 Total Distance 200 m Pipes 23-Nov-10 06-Mar-11 147,882 46993 35260 60203 5427 Reticulation Piping Network 23-Nov-10 06-Mar-11 120,921 46993 35260 33243 5427 X-Ray Test 25-Dec-10 30-Dec-10 5,427 5427 Warning Tape Installation 19-Jan-11 19-Jan-11 1,507 1507 Soft Sand and Compaction Test 01-Dec-10 04-Dec-10 14,849 14849 Laying the Pipes 11-Dec-10 23-Dec-10 14,984 14984 Installation of Dewatering System Equipment 24-Nov-10 24-Nov-10 1,472 1472 Install Butterfly Valve 01-Mar-11 06-Mar-11 5,427 5427 Hydrostatic Test 02-Jan-11 06-Jan-11 5,427 5427 Filled Joint Insulation 08-Jan-11 15-Jan-11 5,427 5427 Excavation ( to be coordinated with hilalco) 23-Nov-10 23-Nov-10 41,763 41763 Draw down the Underground Water 25-Nov-10 30-Nov-10 3,758 3758 Backfilling with Soft Sand 16-Jan-11 18-Jan-11 20,882 20882 Fibre Optic Cable 20-Jan-11 26-Jan-11 26,961 26961 Warning Tape Installation 25-Jan-11 25-Jan-11 5,055 5055 Installation of PVC Pipes 20-Jan-11 23-Jan-11 8,425 8425 Final Backfilling 26-Jan-11 26-Jan-11 5,055 5055 Backfilling with Soft Sand 24-Jan-11 24-Jan-11 8,425 8425 Total Distance 400 m Pipes 01-Dec-10 09-Feb-11 147,654 71834 40391 35429 Reticulation Piping Network 01-Dec-10 02-Feb-11 120,693 71834 40391 8468 X-Ray Test 09-Jan-11 15-Jan-11 5,427 5427 Warning Tape Installation 02-Feb-11 02-Feb-11 1,507 1507 Soft Sand and Compaction Test 12-Dec-10 13-Dec-10 14,664 14664 Laying the Pipes 25-Dec-10 08-Jan-11 20,380 10190 10190 Installation of Dewatering System Equipment 04-Dec-10 04-Dec-10 1,459 1459 Hydrostatic Test 16-Jan-11 20-Jan-11 5,427 5427 Filled Joint Insulation 22-Jan-11 29-Jan-11 5,427 5427 Excavation 01-Dec-10 01-Dec-10 41,763 41763 Draw down the Underground Water 05-Dec-10 11-Dec-10 3,758 3758 Backfilling with Soft Sand 30-Jan-11 01-Feb-11 20,882 13921 6961 Fibre Optic Cable 03-Feb-11 09-Feb-11 26,961 26961 Warning Tape Installation 08-Feb-11 08-Feb-11 5,055 5055 Installation of PVC Pipes 03-Feb-11 06-Feb-11 8,425 8425 Final Backfilling 09-Feb-11 09-Feb-11 5,055 5055 Backfilling with Soft Sand 07-Feb-11 07-Feb-11 8,425 8425 Total Distance 600 m Pipes 12-Dec-10 26-Feb-11 147,654 61644 27978 58032 Reticulation Piping Network 12-Dec-10 17-Feb-11 120,693 61644 27978 31072 X-Ray Test 23-Jan-11 29-Jan-11 5,427 5427 Warning Tape Installation 17-Feb-11 17-Feb-11 1,507 1507 Soft Sand and Compaction Test 20-Dec-10 21-Dec-10 14,664 14664 Laying the Pipes 09-Jan-11 22-Jan-11 20,380 20380 Installation of Dewatering System Equipment 13-Dec-10 13-Dec-10 1,459 1459 Hydrostatic Test 30-Jan-11 03-Feb-11 5,427 2171 3256 Filled Joint Insulation 05-Feb-11 12-Feb-11 5,427 5427 Excavation 12-Dec-10 12-Dec-10 41,763 41763 Draw down the Underground Water 14-Dec-10 19-Dec-10 3,758 3758 Backfilling with Soft Sand 13-Feb-11 16-Feb-11 20,882 20882 Fibre Optic Cable 19-Feb-11 26-Feb-11 26,961 26961 Warning Tape Installation 23-Feb-11 23-Feb-11 5,055 5055 Installation of PVC Pipes 19-Feb-11 21-Feb-11 8,425 8425 Final Backfilling 24-Feb-11 26-Feb-11 5,055 5055 Backfilling with Soft Sand 22-Feb-11 22-Feb-11 8,425 8425 Total Distance 800 m Pipes 20-Dec-10 12-Mar-11 147,654 61644 13587 30034 42389 Reticulation Piping Network 20-Dec-10 03-Mar-11 120,693 61644 13587 30034 15429 X-Ray Test 06-Feb-11 12-Feb-11 5,427 5427 Warning Tape Installation 03-Mar-11 03-Mar-11 1,507 1507 Soft Sand and Compaction Test 28-Dec-10 29-Dec-10 14,664 14664 Laying the Pipes 23-Jan-11 05-Feb-11 20,380 13587 6793 Installation of Dewatering System Equipment 21-Dec-10 21-Dec-10 1,459 1459 Hydrostatic Test 13-Feb-11 19-Feb-11 5,427 5427 Filled Joint Insulation 20-Feb-11 27-Feb-11 5,427 5427 Excavation 20-Dec-10 20-Dec-10 41,763 41763 Draw down the Underground Water 22-Dec-10 27-Dec-10 3,758 3758 Backfilling with Soft Sand 28-Feb-11 02-Mar-11 20,882 6961 13921 Fibre Optic Cable 05-Mar-11 12-Mar-11 26,961 26961 Warning Tape Installation 09-Mar-11 09-Mar-11 5,055 5055 Installation of PVC Pipes 05-Mar-11 07-Mar-11 8,425 8425 Final Backfilling 10-Mar-11 12-Mar-11 5,055 5055 Backfilling with Soft Sand 08-Mar-11 08-Mar-11 8,425 8425 Total Distance 1000 m Pipes 28-Dec-10 26-Mar-11 147,654 43974 17670 26892 59118 Reticulation Piping Network 28-Dec-10 17-Mar-11 120,693 43974 17670 26892 32157 X-Ray Test 21-Feb-11 27-Feb-11 5,427 5427 Warning Tape Installation 17-Mar-11 17-Mar-11 1,507 1507 Soft Sand and Compaction Test 06-Jan-11 08-Jan-11 14,664 14664 Laying the Pipes 06-Feb-11 20-Feb-11 20,380 20380 Installation of Dewatering System Equipment 29-Dec-10 29-Dec-10 1,459 1459 Hydrostatic Test 28-Feb-11 05-Mar-11 5,427 1085 4341 Filled Joint Insulation 06-Mar-11 13-Mar-11 5,427 5427 Excavation 28-Dec-10 28-Dec-10 41,763 41763 Draw down the Underground Water 30-Dec-10 05-Jan-11 3,758 752 3006 Backfilling with Soft Sand 14-Mar-11 16-Mar-11 20,882 20882 Project Implementation Schedule Value of Work in Dirhams (Attachment .2) Date Revision Checked Approved 15-Aug-10 Project Implementation Schedule Rev.00 21-Sep-10 Project Implementation Schedule Rev.01
  • 13. Activity Name Start Finish Budgeted Cost Budgeted U Mubadala Capitaland Real Estate District Cooling Plant for Rihan Heights 2010 2011 Data Date : 18-Jul-10 Page : 7 of 8 Printed On : 22-Sep-10 Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Fibre Optic Cable 19-Mar-11 26-Mar-11 26,961 26961 Warning Tape Installation 23-Mar-11 23-Mar-11 5,055 5055 Installation of PVC Pipes 19-Mar-11 21-Mar-11 8,425 8425 Final Backfilling 24-Mar-11 26-Mar-11 5,055 5055 Backfilling with Soft Sand 22-Mar-11 22-Mar-11 8,425 8425 Total Distance 1200 m Pipes 06-Jan-11 13-Apr-11 202,501 61644 8776 44938 87144 Reticulation Piping Network 06-Jan-11 13-Apr-11 177,226 61644 8776 44938 61869 X-Ray Test 07-Mar-11 13-Mar-11 5,427 5427 Warning Tape Installation 31-Mar-11 31-Mar-11 1,507 1507 Soft Sand and Compaction Test 15-Jan-11 16-Jan-11 14,664 14664 Laying the Pipes 21-Feb-11 06-Mar-11 15,044 8776 6268 Installation of Dewatering System Equipment 08-Jan-11 08-Jan-11 1,459 1459 Install Butterfly Valve 07-Apr-11 13-Apr-11 5,427 5427 Hydrostatic Test 14-Mar-11 19-Mar-11 5,427 5427 Filled Joint Insulation 20-Mar-11 27-Mar-11 5,427 5427 Excavation 06-Jan-11 06-Jan-11 41,763 41763 Draw down the Underground Water 09-Jan-11 13-Jan-11 3,758 3758 Construct Drain Chamber 07-Apr-11 10-Apr-11 21,163 21163 Construct Air Vent Chamber 07-Apr-11 10-Apr-11 35,279 35279 Backfilling with Soft Sand 28-Mar-11 30-Mar-11 20,882 20882 Fibre Optic Cable 02-Apr-11 06-Apr-11 25,276 25276 Warning Tape Installation 05-Apr-11 05-Apr-11 4,213 4213 Installation of PVC Pipes 02-Apr-11 03-Apr-11 8,425 8425 Final Backfilling 06-Apr-11 06-Apr-11 4,213 4213 Backfilling with Soft Sand 04-Apr-11 04-Apr-11 8,425 8425 Valve Chambers 07-Nov-10 13-Mar-11 174,648 48901 50648 31437 33183 10479 Valve Chamber No.01 07-Nov-10 21-Dec-10 43,662 24451 19211 Water Proofing 10-Nov-10 11-Nov-10 3,493 3493 Walls 20-Nov-10 30-Nov-10 12,225 12225 Slab 01-Dec-10 11-Dec-10 12,225 12225 Foundation 13-Nov-10 18-Nov-10 5,239 5239 External Water Proofing 12-Dec-10 19-Dec-10 3,493 3493 Blinding 07-Nov-10 09-Nov-10 3,493 3493 Backfilling 20-Dec-10 21-Dec-10 3,493 3493 Valve Chamber No.02 07-Nov-10 21-Dec-10 43,662 24451 19211 Water Proofing 10-Nov-10 11-Nov-10 3,493 3493 Walls 20-Nov-10 30-Nov-10 12,225 12225 Slab 01-Dec-10 11-Dec-10 12,225 12225 Foundation 13-Nov-10 18-Nov-10 5,239 5239 External Water Proofing 12-Dec-10 19-Dec-10 3,493 3493 Blinding 07-Nov-10 09-Nov-10 3,493 3493 Backfilling 20-Dec-10 21-Dec-10 3,493 3493 Valve Chamber No.03 22-Dec-10 31-Jan-11 43,662 12225 31437 Water Proofing 26-Dec-10 27-Dec-10 3,493 3493 Walls 02-Jan-11 12-Jan-11 12,225 12225 Slab 13-Jan-11 20-Jan-11 12,225 12225 Foundation 28-Dec-10 30-Dec-10 5,239 5239 External Water Proofing 22-Jan-11 29-Jan-11 3,493 3493 Blinding 22-Dec-10 25-Dec-10 3,493 3493 Backfilling 30-Jan-11 31-Jan-11 3,493 3493 Valve Chamber No.04 01-Feb-11 13-Mar-11 43,662 33183 10479 Water Proofing 05-Feb-11 06-Feb-11 3,493 3493 Walls 10-Feb-11 22-Feb-11 12,225 12225 Slab 23-Feb-11 02-Mar-11 12,225 8732 3493 Foundation 07-Feb-11 09-Feb-11 5,239 5239 External Water Proofing 03-Mar-11 10-Mar-11 3,493 3493 Blinding 01-Feb-11 03-Feb-11 3,493 3493 Backfilling 12-Mar-11 13-Mar-11 3,493 3493 Energy Transfer Stations 18-Jan-11 16-Mar-11 376,097 90263 204221 81613 ETS Room (Tower A,B) 18-Jan-11 06-Mar-11 167,476 38684 97707 31084 Plant Pipes / Heat Exchangers Inside ETS Room 18-Jan-11 06-Mar-11 167,476 38684 97707 31084 X-RayTest 03-Feb-11 08-Feb-11 15,044 15044 Insulation of Pipes 09-Feb-11 17-Feb-11 15,044 15044 Install Valves 19-Feb-11 22-Feb-11 18,805 18805 Install Pipes 18-Jan-11 02-Feb-11 45,132 38684 6447 Install Heat Exchanger Fitting & Accessories 23-Feb-11 06-Mar-11 15,044 7522 7522 Install Heat Exchanger 23-Feb-11 06-Mar-11 47,125 23562 23562 Hydrostatic for Tower A,B 09-Feb-11 21-Feb-11 11,283 11283 ETS Room (Tower C,D) 18-Jan-11 06-Mar-11 140,397 38684 70252 31461 Plant Pipes / Heat Exchangers Inside ETS Room 18-Jan-11 06-Mar-11 140,397 38684 70252 31461 X-RayTest 03-Feb-11 08-Feb-11 7,522 7522 Insulation of Pipes 09-Feb-11 17-Feb-11 7,522 7522 Install Valves 19-Feb-11 22-Feb-11 15,044 15044 Install Pipes 18-Jan-11 02-Feb-11 45,132 38684 6447 Install Heat Exchanger Fitting & Accessories 23-Feb-11 06-Mar-11 7,522 3761 3761 Install Heat Exchanger 23-Feb-11 06-Mar-11 46,373 23186 23186 Hydrostatic for Tower C,D 22-Feb-11 05-Mar-11 11,283 6770 4513 ETS Room (Tower E) 18-Jan-11 16-Mar-11 68,224 12895 36261 19068 Plant Pipes / Heat Exchangers Inside ETS Room 18-Jan-11 16-Mar-11 68,224 12895 36261 19068 X-RayTest 03-Feb-11 08-Feb-11 7,522 7522 Insulation of Pipes 09-Feb-11 17-Feb-11 7,522 7522 Install Valves 19-Feb-11 22-Feb-11 7,522 7522 Install Pipes 18-Jan-11 02-Feb-11 15,044 12895 2149 Install Heat Exchanger Fitting & Accessories 23-Feb-11 06-Mar-11 7,522 3761 3761 Install Heat Exchanger 23-Feb-11 06-Mar-11 15,570 7785 7785 Hydrostatic for Tower E 06-Mar-11 16-Mar-11 7,522 7522 External Works 20-Mar-11 28-Apr-11 433,251 275064 158187 Sewerage Network 20-Mar-11 05-Apr-11 207,439 152122 55317 uPVC gravity sewers in trench with Manholes 20-Mar-11 05-Apr-11 207,439 152122 55317 Project Implementation Schedule Value of Work in Dirhams (Attachment .2) Date Revision Checked Approved 15-Aug-10 Project Implementation Schedule Rev.00 21-Sep-10 Project Implementation Schedule Rev.01
  • 14. Activity Name Start Finish Budgeted Cost Budgeted U Mubadala Capitaland Real Estate District Cooling Plant for Rihan Heights 2010 2011 Data Date : 18-Jul-10 Page : 8 of 8 Printed On : 22-Sep-10 Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Potable Water Network 20-Mar-11 05-Apr-11 167,648 122942 44706 uPVC pipe work in trench with with Chambers 20-Mar-11 05-Apr-11 167,648 122942 44706 External Lighting 11-Apr-11 27-Apr-11 41,556 41556 External Lighting 11-Apr-11 27-Apr-11 41,556 41556 Steel Stairs 12-Apr-11 28-Apr-11 16,608 16608 Steel Staircase for Ancillary Building 12-Apr-11 28-Apr-11 16,608 16608 Testing and Commissioning 17-Mar-11 11-May-11 242,322 89612 123717 28993 Mechanical 17-Mar-11 11-May-11 242,322 89612 123717 28993 Reticulation Piping Network 14-Apr-11 11-May-11 80,790 51797 28993 Chemical Passivation 02-May-11 11-May-11 26,922 26922 Chemical Cleaning 19-Apr-11 01-May-11 26,922 24851 2071 Air Flushing 14-Apr-11 18-Apr-11 26,946 26946 Energy Transfer Stations 17-Mar-11 06-Apr-11 80,766 51152 29614 Chemical Passivation 03-Apr-11 06-Apr-11 26,922 26922 Chemical Cleaning 22-Mar-11 02-Apr-11 26,922 24230 2692 Air Flushing 17-Mar-11 21-Mar-11 26,922 26922 District Cooling Modular Plant 20-Mar-11 18-Apr-11 80,766 38460 42306 Chemical Passivation 09-Apr-11 18-Apr-11 26,922 26922 Chemical Cleaning 26-Mar-11 08-Apr-11 26,922 11538 15384 Air Flushing 20-Mar-11 25-Mar-11 26,922 26922 Project Implementation Schedule Value of Work in Dirhams (Attachment .2) Date Revision Checked Approved 15-Aug-10 Project Implementation Schedule Rev.00 21-Sep-10 Project Implementation Schedule Rev.01
  • 15. Mubadala Capitaland Real Estate District Cooling Plant for Rihan Heights Forecasting of Monthly Invoices Contract Amount : 5 3,166,016.00 Advance Payment ( 10 % ) : 5,316,601.60 Advance Payment Bond Date : Change Orders Approved to Date : Retention Amount ( 5 % ) : 2,658,300.80 Performance Bond Date : Current Contract Amount : 5 3,166,016.00 Contract Start Date : 18-Jul-10 Other Bonds : Invoice Currency : AED Contract Completion Date : 13-May-11 Due Date Duration after Approval is : 56 Days Value of Work Retention Release Advance Payment Retention Money Others Total Deduction Net Invoice Actual A B C D E (F)=C+D+E Net =(A+B-F) Date Amount Difference (Days) 1 Advance Payment 5,316,602 0 5,316,602 5,316,602 18-Aug-10 21-Sep-10 2 30-Sep-2010 5,924,236 - 888,635 592,424 - 1,481,059 4,443,177 9,759,778 30-Sep-10 25-Nov-10 3 31-Oct-2010 2,500,867 - 375,130 250,087 - 625,217 1,875,650 11,635,428 31-Oct-10 26-Dec-10 4 30-Nov-2010 2,999,945 - 449,992 299,995 - 749,986 2,249,959 13,885,387 30-Nov-10 25-Jan-11 5 31-Dec-2010 1,655,753 - 248,363 165,575 - 413,938 1,241,815 15,127,202 31-Dec-10 25-Feb-11 6 31-Jan-2011 7,298,559 1,094,784 729,856 - 1,824,640 5,473,920 20,601,122 31-Jan-11 28-Mar-11 7 28-Feb-2011 10,336,991 - 1,550,549 620,365 - 2,170,913 8,166,077 28,767,199 28-Feb-11 25-Apr-11 8 31-Mar-2011 8,775,786 - 709,149 - - 709,149 8,066,637 36,833,836 31-Mar-11 26-May-11 9 30-Apr-2011 9,300,088 - - - - 0 9,300,088 46,133,924 30-Apr-11 25-Jun-11 10 31-May-2011 999,740 1 ,329,150.40 - - - 0 2,328,890 48,462,814 31-May-11 26-Jul-11 11 30-Jun-2011 307,384 - - - - 0 307,384 48,770,198 30-Jun-11 25-Aug-11 12 31-Jul-2011 307,384 - - - - 0 307,384 49,077,582 31-Jul-11 25-Sep-11 13 31-Aug-2011 307,063 - - - - 0 307,063 49,384,644 31-Aug-11 26-Oct-11 14 30-Sep-2011 307,063 - - - - 0 307,063 49,691,707 30-Sep-11 25-Nov-11 15 31-Oct-2011 307,063 - - - - 0 307,063 49,998,770 31-Oct-11 26-Dec-11 16 30-Nov-2011 307,063 - - - - 0 307,063 50,305,833 30-Nov-11 25-Jan-12 17 31-Dec-2011 307,063 - - - - 0 307,063 50,612,895 31-Dec-11 25-Feb-12 18 31-Jan-2012 307,063 - - - - 0 307,063 50,919,958 31-Jan-12 27-Mar-12 19 29-Feb-2012 307,063 - - - - 0 307,063 51,227,021 29-Feb-12 25-Apr-12 20 31-Mar-2012 342,286 - - - - 0 342,286 51,569,306 31-Mar-12 26-May-12 21 30-Apr-2012 133,780 - - - - 0 133,780 51,703,086 30-Apr-12 25-Jun-12 22 31-May-2012 133,780 1 ,329,150.40 - - - 0 1,462,930 53,166,017 31-May-12 26-Jul-12 53,166,017 0 5,316,601.68 2,658,300.82 0.00 7,974,902 53,166,017 Cert. / Invoice No. Month Cumulative Invoice Submitted Date Forcast Date of Releasing the Invoices Total GROSS INVOICE DEDUCTIONS Remarks Release of 5% of Retention Money Release of 5% of Retention Money File : Cash Flow Page 2 of 2 Printed On :10/20/10 at 1:06 PM
  • 16. Section 1.12  Cash In Histogram (EPC Project Period) AWI 106 Att. 8 Rev. 2 06 Jul. 2009 Date/ Rev.
  • 17. Sep-10 Oct-10 Nov-10 Dec-10 Jan-11 May-11 Jun-11 Planned Monthly 5,316,602 4,443,177 1,875,650 2,249,959 1,241,815 5,473,920 8,166,077 8,066,637 9,300,088 2,328,890 Planned Accum. 5,316,602 5,316,602 9,759,778 11,635,428 13,885,387 15,127,202 20,601,122 28,767,199 36,833,836 46,133,924 48,462,814 Actual Monthly Actual Accum. Forecast Monthly Forecast Accum. Planned Actual Forecast Mubadala Capitaland Real Estate District Cooling Plant for Rihan Heights Cash In Histogram (EPC Project Period) Feb-11 Mar-11 Apr-11 Jul-11 2,328,890 8,166,077 5,473,920 4,443,177 5,316,602 1,875,650 2,249,959 1,241,815 8,066,637 9,300,088 Sep-10 Oct-10 Nov-10 Dec-10 Jan-11 Feb-11 Mar-11 Apr-11 May-11 Jun-11 Jul-11 Forecast Date of Releasing the Invoices AED 10,000,000.00 AED 9,000,000.00 AED 8,000,000.00 AED 7,000,000.00 AED 6,000,000.00 AED 5,000,000.00 AED 4,000,000.00 AED 3,000,000.00 AED 2,000,000.00 AED 1,000,000.00 AED 0.00 Planned Monthly Actual Monthly Forecast Accum. Planned Accum. Actual Accum. Forecast Monthly File: Cash Flow Page 1 of 1 Printed On : 10/20/10 at 12:42 PM
  • 18. Section 1.13  Cash In Histogram (Operation and Maintenance Period) AWI 106 Att. 8 Rev. 2 06 Jul. 2009 Date/ Rev.
  • 19. Jan-12 Feb-12 Apr-12 Planned Monthly 307,384 307,384 307,063 307,063 307,063 307,063 307,063 307,063 307,063 342,286 133,780 1,462,930 Planned Accum. 307,384 614,768 921,831 1,228,893 1,535,956 1,843,019 2,150,081 2,457,144 2,764,207 3,106,492 3,240,273 4,703,203 Actual Monthly Actual Accum. Forecast Monthly Forecast Accum. Forecast Aug-11 Nov-11 Dec-11 Planned Actual Mubadala Capitaland Real Estate District Cooling Plant for Rihan Heights Cash In Histogram (Operation and Maintenance Period) Sep-11 Oct-11 Mar-12 May-12 Jun-12 Jul-12 307,384 307,384 307,063 307,063 307,063 307,063 307,063 307,063 307,063 342,286 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Forecast Date of Releasing the Invoices AED 350,000.00 AED 340,000.00 AED 330,000.00 AED 320,000.00 AED 310,000.00 AED 300,000.00 AED 290,000.00 AED 280,000.00 Planned Monthly Actual Monthly Forecast Accum. Planned Accum. Actual Accum. Forecast Monthly File: Cash Flow Page 1 of 1 Printed On : 10/20/10 at 12:42 PM
  • 20. Section 2  Cash Out Data AWI 106 Att. 8 Rev. 2 06 Jul. 2009 Date/ Rev.
  • 21. Section 2.11  Cash Out-Value of Works & Monthly Invoices AWI 106 Att. 8 Rev. 2 06 Jul. 2009 Date/ Rev.
  • 22. Mubadala Capitaland Real Estate District Cooling Plant for Rihan Heights Cash Out Value of Works & Monthly Invoices Jul-10 Aug-10 Sep-10 Oct-10 Nov-10 Dec-10 Jan-11 Feb-11 Mar-11 Apr-11 May-11 Jun-11 Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Description Original Budget 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 1.0 - Materials 8,641,274 Civil Works Imported fill 136,125 7.69% 23.08% 30.77% 15.38% 23.08% Sand Bedding/Padding 87,300 66.67% 33.33% Lean Concrete 29,295 50.00% 12.50% 12.50% 25.00% RC Concrete 376,740 14.29% 35.71% 21.43% 21.43% 7.14% Rebars 251,680 25.00% 28.57% 21.43% 25.00% Formworks 342,125 14.29% 35.71% 21.43% 21.43% 7.14% Blockworks 27,000 44.44% 55.56% Polythelene Sheets 6,555 100.00% Water Stop 9,000 100.00% Floor Screed 6,700 50.00% 25.00% 25.00% Steel Stairs 14,160 100.00% Ceramic Floor tiles 5,355 50.00% 50.00% Plastering 8,856 100.00% Painting 8,247 100.00% Manhole Cover 17,400 100.00% Aluminum Ladder 3,500 100.00% Pipe Sleeves Inserts 25,200 100.00% Cable Tiles / Warning Tapes 3,047 100.00% Furnishings 52,050 100.00% Geo-Textile Membrane 7,401 100.00% Electrical Works Plant Room MV Cables (Plant) 350,380 10.00% 90.00% Relay coordination Study and Local Authority Approvals for 11kv Switchgear , 30,000 100.00% Testing Transformer (Plant) inclusive of Factory Witness Test 589,824 10.00% 90.00% Cables & Wires (Plants) 203,511 10.00% 55.00% 35.00% Contaiment (Cable Tray & Trunking) 20,894 100.00% Isolators (plant) 12,196 100.00% PVC Duct Bank 1,200 100.00% Earthing (Plant) 23,922 100.00% Lignhtning Protection (Plant) 41,466 100.00% UPS system (Plant) 76,271 100.00% Support for Electrical System 8,925 100.00% Miscellaneous (Cable Marker, Rubber Mats, Boards, Consumables) 3,720 100.00% Building Services File:Cash Flow Page1 of 7 Printed On:10/20/10 at 12:47 PM
  • 23. Mubadala Capitaland Real Estate District Cooling Plant for Rihan Heights Cash Out Value of Works & Monthly Invoices Jul-10 Aug-10 Sep-10 Oct-10 Nov-10 Dec-10 Jan-11 Feb-11 Mar-11 Apr-11 May-11 Jun-11 Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Description Original Budget 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 SMDB/Distribution Boards (BS) 14,500 100.00% Cables & Wires (BS) 56,126 100.00% Conduit fittings & accessories (BS) 22,286 100.00% Light Fittings -(BS) 26,602 100.00% Wiring accessories (BS) 4,188 100.00% Light Points (BS) 2,100 100.00% Support for Electrical System (BS) 4,052 100.00% Mechanical Works HVAC Process (DC Plant) Expansion Tank 32,972 100.00% Chemical Water Treatment System (Chilled & Condenser Water) 454,500 10.00% 90.00% /Equipments Air Compressor 15,000 100.00% Refrigerant Recovery Unuit 75,000 100.00% Chilled Water /Condenser Water Pipe & Fittings 149,552 100.00% Chilled/Condenser Water Pipe Insulation 37,280 100.00% Valves 163,508 100.00% Aluminium Cladding 31,473 100.00% Hanger & Supports 42,729 100.00% Identification & Tag 3,670 100.00% Fire Stopping Material 10,014 100.00% Skid & Shed 5,000 100.00% Consumables-Piping 2,849 100.00% Consumables-HVAC 8,383 100.00% HVAC Reticulation Works Pre Insulated Chilled Water Pipes & Fittings 1,110,481 10.00% 90.00% Leak Detection System 80,000 100.00% Valves & Accessories 77,684 100.00% Radiography Test/ Welding Inspector 55,000 100.00% Stress Analysis 20,000 100.00% Aluminium Cladding 11,703 100.00% Consumables-Piping 32,359 100.00% Warning Tapes, Markup Plates 45,608 100.00% HVAC Works - ETS Room Heat Exchangers 1,154,575 10.00% 90.00% Chilled Water Pipe & Fittings 585,760 10.00% 90.00% Chilled Water Pipe Insulation 82,634 100.00% Valves 512,513 10.00% 90.00% File:Cash Flow Page2 of 7 Printed On:10/20/10 at 12:47 PM
  • 24. Mubadala Capitaland Real Estate District Cooling Plant for Rihan Heights Cash Out Value of Works & Monthly Invoices Jul-10 Aug-10 Sep-10 Oct-10 Nov-10 Dec-10 Jan-11 Feb-11 Mar-11 Apr-11 May-11 Jun-11 Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Description Original Budget 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 Aluminium Cladding 118,800 100.00% Hanger & Supports 174,922 100.00% Identification & Tag 4,008 100.00% Fire Stopping Material 50,000 100.00% Consumables-Piping 16,270 100.00% Consumables-HVAC 14,265 100.00% HVAC Works - Building Services Split Air Conditioning Units (BS) 33,718 100.00% Fans (BS) 3,952 100.00% Condensate Pipe & Fittings (BS) 385 100.00% Condensate Water Pipe Insulation (BS) 672 100.00% Vibration Isolator (BS) 600 100.00% Hanger & Supports (BS) 2,640 100.00% Identification & Tag (BS) 160 100.00% Plumbing Process (DC Plant) Make Up Water Pump 34,356 100.00% HDPE Pipes & Fittings 13,639 100.00% Steel Pipes & Fittings 24,175 100.00% Valves & Appurtenances 31,038 100.00% Drainage Specialities 8,140 100.00% Insulation 5,084 100.00% Aluminum Cladding 13,272 100.00% Supports 5,000 100.00% Consumables-Piping 1,853 100.00% Consumables-General 2,100 100.00% Building Services (BS) + External Booster Water Pump 22,200 100.00% HDPE Pipes & Fittings 38,813 100.00% Steel Pipes & Fittings 8,505 100.00% uPVC Pipes & Fittings 14,707 100.00% PPR Pipes & Fittings 2,149 100.00% Valves & Appurtenances 24,717 100.00% Drainage Specialities 9,110 100.00% Insulation 9,737 100.00% Aluminum Cladding 10,750 100.00% Sanitray Fixtures & Accessories 22,928 100.00% GRP Cylindrical Tank 2,100 100.00% Electrical Water Heaters 4,120 100.00% File:Cash Flow Page3 of 7 Printed On:10/20/10 at 12:47 PM
  • 25. Mubadala Capitaland Real Estate District Cooling Plant for Rihan Heights Cash Out Value of Works & Monthly Invoices Jul-10 Aug-10 Sep-10 Oct-10 Nov-10 Dec-10 Jan-11 Feb-11 Mar-11 Apr-11 May-11 Jun-11 Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Description Original Budget 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 Supports 13,000 100.00% Consumables-Piping 3,741 100.00% Consumables-General 3,400 100.00% Pantry Items 15,323 100.00% Supply Stationery 15,000 100.00% Office Supplies to Client 2,063 100.00% Safety Supplies 6,518 100.00% Scaffolding 32,457 33.34% 33.33% 33.33% Tools 9,236 100.00% Water for Testing 71,005 100.00% Gases 3,000 100.00% Office Equipment to Client 27,500 100.00% 2.0 - Subcontract 26,301,274 Civil Works Dewatering Works 76,500 100.00% Waterproofing 132,831 25.00% 25.00% 25.00% 25.00% Precast Boundary Wall 194,700 33.34% 33.33% 33.33% Steel Doors 89,676 50.00% 50.00% Wooden Doors 12,805 50.00% 50.00% Aluminum Windows, louver windows 40,200 50.00% 50.00% Metal Works 5,250 100.00% Suspended Ceiling 11,197 100.00% Epoxy Floor Coating 15,235 100.00% Steel Gates 38,750 50.00% 50.00% GRP Lining 182,280 33.34% 33.33% 33.33% Geotechnical Report 13,529 100.00% Material Testing 31,000 16.67% 16.67% 16.67% 16.67% 16.67% 16.67% GRP Ladder 10,712 100.00% Kitchen Equipments 15,804 50.00% 50.00% Electrical Works HV Cable Laying & Termination 45,500 100% Fire Alarm System 19,941 50.00% 50% Telecommunication System 2,000 100% Cabling 76,500 50.00% 50% HVAC Works HVAC Initial Start-up 15,017 100.00% 25,000 100.00% 75,000 100.00% File:Cash Flow Page4 of 7 Printed On:10/20/10 at 12:47 PM
  • 26. Mubadala Capitaland Real Estate District Cooling Plant for Rihan Heights Cash Out Value of Works & Monthly Invoices Jul-10 Aug-10 Sep-10 Oct-10 Nov-10 Dec-10 Jan-11 Feb-11 Mar-11 Apr-11 May-11 Jun-11 Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Description Original Budget 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 HVAC Testing, Balancing 40,018 100.00% 10,000 100.00% 30,000 100.00% Mechanical Works Fire Fighting System 122,425 10.00% 45.00% 45.00% Fire Fighting System 826,767 10.00% 45.00% 45.00% Electric Chain Hoist 40,843 100.00% Flushing /Chemical Flushing 35,000 50.00% 50.00% Testing & Commissioning 25,000 50.00% 50.00% Modular DCP Plant Modular District Cooling Plant (Stellar) Purchase Order-Pump 116,644 100.00% Purchase Order-Chiller 935,874 100.00% Purchase Order-Cooling Towers 311,427 100.00% Purchase Order-Electrical Module 864,016 100.00% Shipping Documents-Chiller 4,958,138 100.00% Shipping Documents-Cooling Towers 953,726 100.00% Shipping Documents-Electrical Module 2,999,975 100.00% Delivery-Pump 357,214 100.00% Delivery-Chiller 2,866,060 100.00% Delivery-Cooling Towers 953,726 100.00% Delivery-MV Switchgear 1,788,802 100.00% Delivery-LV Switchgear 857,196 100.00% Delivery-Chiller Base Frame 1,040,918 100.00% Delivery-Chiller Enclosure 693,945 100.00% Delivery-Electrical Module Base Frame 212,386 100.00% Delivery-Electrical Module Enclosure 141,591 100.00% Signing of Taking Over Certificate 2,227,959 100% Special System - SCADA Control & Automation (Stellar) Others /Misc Design (Stamping Purpose Only) 125,000 45.00% 15.00% 20.00% 10.00% 10.00% Environment Assessment Study (Budget) 30,000 100.00% Services during Defect Liability Period 210,675 100.00% Operation & Maintenance for 12 Months 1,396,524 8% 8% 8% 8% 8% 8% 8% 8% 8% 8% 8% 8% 3.0 - Manual Manpower 1,692,434 Civil Works 507,503 6.36% 16.36% 18.18% 20.91% 19.09% 10.91% 6.36% 1.82% HVAC Works 840,899 11.00% 14.67% 18.00% 18.00% 17.00% 13.67% 7.67% Plumbing Works 83,027 25.00% 25.00% 25.00% 25.00% File:Cash Flow Page5 of 7 Printed On:10/20/10 at 12:47 PM
  • 27. Mubadala Capitaland Real Estate District Cooling Plant for Rihan Heights Cash Out Value of Works & Monthly Invoices Jul-10 Aug-10 Sep-10 Oct-10 Nov-10 Dec-10 Jan-11 Feb-11 Mar-11 Apr-11 May-11 Jun-11 Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Description Original Budget 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 Electrical Works 120,500 3.85% 3.85% 6.41% 8.97% 15.38% 20.51% 20.51% 20.51% Farash, Store Helper, Guards, Drivers, Courier, Tea Boy, Janitor 124,504 2.00% 12.25% 12.25% 12.25% 12.25% 12.25% 12.25% 12.25% 12.25% Welders Qualifications & Testing 16,000 16.67% 16.67% 16.67% 16.67% 16.67% 16.67% 4.0 - Construction Equipment 1,350,439 Operation 369,147 0.01% 0.57% 6.18% 10.02% 17.64% 19.99% 22.55% 19.72% 3.33% Equipment Outside Hire 84,151 4.00% 9.00% 15.00% 15.00% 15.00% 15.00% 15.00% 12.00% Fuels 233,136 2.00% 2.00% 9.00% 15.00% 15.00% 15.00% 15.00% 15.00% 12.00% 481,617 0.01% 0.57% 6.18% 10.02% 17.64% 19.99% 22.55% 19.72% 3.33% Personal Cars 36,000 2.00% 2.00% 9.00% 15.00% 15.00% 15.00% 15.00% 15.00% 12.00% Pick - up 146,388 2.00% 2.00% 9.00% 15.00% 15.00% 15.00% 15.00% 15.00% 12.00% 5.0 - Indirect Cost 2,513,857 Purchase, Rental, Construction Cost 170,683 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% Maintenance of Temp Facilities 171,786 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% Utilities 277,389 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% General Services 84,640 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% Progress Photographs 700 100.00% Courier Service 5,000 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% Mobile Telephone 25,000 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% Communication (tel + fax + internet) 70,000 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% Communication (Wireless Internet Access) 4,949 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% Furniture 30,128 80.00% 2.50% 2.50% 2.50% 2.50% 2.50% 2.50% 2.50% 2.50% Furniture to Client 21,000 80.00% 2.50% 2.50% 2.50% 2.50% 2.50% 2.50% 2.50% 2.50% P&D Office Equipment 10,000 80.00% 2.50% 2.50% 2.50% 2.50% 2.50% 2.50% 2.50% 2.50% Ropes & Slings 10,000 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% Bank Interest 55,000 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% Contract Expenses 227,590 33.34% 33.33% 33.33% Costs of Bid Bond 7,532 33.34% 33.33% 33.33% Letter of Credit 281,250 33.34% 33.33% 33.33% Charges of CADD 375,000 33.34% 33.33% 33.33% Charges of IT 20,400 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% Containers 40,000 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% 11.11% Insurance All Risk & 3rd party 209,295 33.34% 33.33% 33.33% Workmen's Compensation & Insurance 16,515 33.34% 33.33% 33.33% Professional Indemnity Insurance 400,000 33.34% 33.33% 33.33% 6.0 - Non Manual Manpower 2,501,187 Salary 2,501,187 7.46% 11.44% 12.44% 11.94% 11.94% 11.94% 10.95% 10.95% 10.95% 7.0 - Management Overhead/Contingency/ G. 10,165,550 Expenses File:Cash Flow Page6 of 7 Printed On:10/20/10 at 12:47 PM
  • 28. Mubadala Capitaland Real Estate District Cooling Plant for Rihan Heights Cash Out Value of Works & Monthly Invoices Jul-10 Aug-10 Sep-10 Oct-10 Nov-10 Dec-10 Jan-11 Feb-11 Mar-11 Apr-11 May-11 Jun-11 Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Description Original Budget 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 Estimation Errors 300,615 11.85% 5.41% 6.35% 3.82% 14.43% 20.15% 17.21% 18.20% 2.59% Expected Cost Contingency - Currency Fluctuation 169,183 11.85% 5.41% 6.35% 3.82% 14.43% 20.15% 17.21% 18.20% 2.59% Provisional Sum 2,488,550 15.53% 6.92% 6.92% 6.92% 6.92% 6.92% 6.92% 6.92% 6.92% 6.92% 6.92% 6.92% 8.33% Area / division Overheads 1,594,980 11.85% 5.41% 6.35% 3.82% 14.43% 20.15% 17.21% 18.20% 2.59% Corporate Overheads 1,063,320 11.85% 5.41% 6.35% 3.82% 14.43% 20.15% 17.21% 18.20% 2.59% Management Overhead and Risk 4,548,902 SUBTOTAL 53,166,015 - - 1,283,058 1,256,431 3,318,442 1,810,460 1,784,008 4,509,330 6,435,157 13,694,325 2,641,549 6,575,608 504,063 288,626 288,626 2,516,585 288,626 288,626 288,626 288,626 323,715 116,377 116,377 48,617,243 - - 1,283,058 1,256,431 3,318,442 1,810,460 1,784,008 4,509,330 6,435,157 13,694,325 2,641,549 6,575,608 504,063 288,626 288,626 2,516,585 288,626 288,626 288,626 288,626 323,715 116,377 116,377 - - 1 ,283,058 2 ,539,489 5 ,857,931 7 ,668,391 9 ,452,399 1 3,961,730 2 0,396,886 3 4,091,211 3 6,732,761 43,308,369 43,812,432 44,101,058 44,389,685 46,906,270 4 7,194,896 4 7,483,522 47,772,148 48,060,774 48,384,489 48,500,866 48,617,243 0.00% 0.00% 2.41% 4.78% 11.02% 14.42% 17.78% 26.26% 38.36% 64.12% 69.09% 81.46% 82.41% 82.95% 83.49% 88.23% 88.77% 89.31% 89.85% 90.40% 91.01% 91.23% 91.44% Plan. Value of Work - Month Plan. Value of Work - Cumulative File:Cash Flow Page7 of 7 Printed On:10/20/10 at 12:47 PM
  • 29. Section 2.12  Cash Out Histogram (EPC Project Period) AWI 106 Att. 8 Rev. 2 06 Jul. 2009 Date/ Rev.
  • 30. Sep-10 Oct-10 Nov-10 Dec-10 Jan-11 May-11 Jun-11 Planned Monthly 1,283,058 1,256,431 3,318,442 1,810,460 1,784,008 4,509,330 6,435,157 13,694,325 2,641,549 6,575,608 504,063 Planned Accum. 1,283,058 2,539,489 5,857,931 7,668,391 9,452,399 13,961,730 20,396,886 34,091,211 36,732,761 43,308,369 43,812,432 Actual Monthly Actual Accum. Forecast Monthly Forecast Accum. Planned Actual Forecast Mubadala Capitaland Real Estate District Cooling Plant for Rihan Heights Cash Out Histogram (EPC Project Period) Feb-11 Mar-11 Apr-11 Jul-11 504,063 13,694,325 6,435,157 3,318,442 1,256,431 1,283,058 1,810,460 1,784,008 4,509,330 2,641,549 6,575,608 Sep-10 Oct-10 Nov-10 Dec-10 Jan-11 Feb-11 Mar-11 Apr-11 May-11 Jun-11 Jul-11 Forecast Date of Releasing the Invoices AED 16,000,000.00 AED 14,000,000.00 AED 12,000,000.00 AED 10,000,000.00 AED 8,000,000.00 AED 6,000,000.00 AED 4,000,000.00 AED 2,000,000.00 AED 0.00 Planned Monthly Actual Monthly Forecast Accum. Planned Accum. Actual Accum. Forecast Monthly File: Cash Flow Page 1 of 1 Printed On : 10/20/10 at 12:39 PM
  • 31. Section 2.13  Cash Out Histogram (Operation and Maintenance Period) AWI 106 Att. 8 Rev. 2 06 Jul. 2009 Date/ Rev.
  • 32. Jan-12 Feb-12 Apr-12 Planned Monthly 288,626 288,626 2,516,585 288,626 288,626 288,626 288,626 323,715 116,377 116,377 Planned Accum. 288,626 577,252 3,093,837 3,382,464 3,671,090 3,959,716 4,248,342 4,572,057 4,688,434 4,804,811 Actual Monthly Actual Accum. Forecast Monthly Forecast Accum. Forecast Aug-11 Nov-11 Dec-11 Planned Actual Mubadala Capitaland Real Estate District Cooling Plant for Rihan Heights Cash Out Histogram (Operation and Maintenance Period) Sep-11 Oct-11 Mar-12 May-12 Jun-12 Jul-12 288,626 323,715 2,516,585 288,626 288,626 288,626 288,626 288,626 116,377 116,377 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Forecast Date of Releasing the Invoices AED 3,000,000.00 AED 2,500,000.00 AED 2,000,000.00 AED 1,500,000.00 AED 1,000,000.00 AED 500,000.00 AED 0.00 Planned Monthly Actual Monthly Forecast Accum. Planned Accum. Actual Accum. Forecast Monthly File: Cash Flow Page 1 of 1 Printed On : 10/20/10 at 12:39 PM
  • 33. Section 3  Cash Flow AWI 106 Att. 8 Rev. 2 06 Jul. 2009 Date/ Rev.
  • 34. Section 3.11  Project Cash Flow Curve AWI 106 Att. 8 Rev. 2 06 Jul. 2009 Date/ Rev.
  • 35. District Cooling Plant for Rihan Heights The Baseline of Project Cash Flow 60,000,000 50,000,000 40,000,000 30,000,000 20,000,000 10,000,000 Month No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 Cut-Off date Sep-10 Oct-10 Nov-10 Dec-10 Jan-11 Feb-11 Mar-11 Apr-11 May-11 Jun-11 Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 16,000,000 14,000,000 12,000,000 10,000,000 8,000,000 6,000,000 4,000,000 2,000,000 Cash-In 5,316,602 4,443,177 1,875,650 2,249,959 1,241,815 5,473,920 8,166,077 8,066,637 9,300,088 2,328,890 307,384 307,384 307,063 307,063 307,063 307,063 307,063 307,063 307,063 342,286 133,780 1,462,930 Cash-Out 1,283,058 1,256,431 3,318,442 1,810,460 1,784,008 4,509,330 6,435,157 13,694,325 2,641,549 6,575,608 504,063 288,626 288,626 2,516,585 288,626 288,626 288,626 288,626 323,715 116,377 116,377 Variance 4,033,544 1,256,431 1,124,734 65,190 465,951 3,267,515 961,237 5,528,248 5,425,088 2,724,479 1,824,827 18,758 18,758 2,209,522 18,437 18,437 18,437 18,437 16,652 190,686 225,909 133,780 1,462,930 Cash-in 5,316,602 5,316,602 9,759,778 11,635,428 13,885,387 15,127,202 20,601,122 28,767,199 36,833,836 46,133,924 48,462,814 48,770,198 49,077,582 49,384,644 49,691,707 49,998,770 50,305,833 50,612,895 50,919,958 51,227,021 51,569,306 51,703,086 53,166,017 Cash-out 1,283,058 2,539,489 5,857,931 7,668,391 9,452,399 13,961,730 20,396,886 34,091,211 36,732,761 43,308,369 43,812,432 44,101,058 44,389,685 46,906,270 47,194,896 47,483,522 47,772,148 48,060,774 48,384,489 48,500,866 48,617,243 48,617,243 48,617,243 Cash Flow 4,033,544 2,777,112 3,901,847 3,967,037 4,432,988 1,165,472 204,235 5,324,012 101,075 2,825,555 4,650,382 4,669,139 4,687,897 2,478,375 2,496,811 2,515,248 2,533,684 2,552,121 2,535,469 2,726,155 2,952,063 3,085,844 4,548,774 CUMULATIVE MONTHLY 0 Sep-10 Oct-10 Nov-10 Dec-10 Jan-11 Feb-11 Mar-11 Apr-11 May-11 Jun-11 Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 MONTH Monthly 0 Cummulative Cash-In Cash-Out Cash-in Cash-out Cash Flow File:Cash Flow Page 1 of 1 Printed On:10/20/10 at 12:50 PM
  • 36. Section 3.12  Project Cash Liquidity AWI 106 Att. 8 Rev. 2 06 Jul. 2009 Date/ Rev.
  • 37. District Cooling Plant for Rihan Heights The Project Cash Liquidity Cash in & Cash out * (100,000) 600 550 500 450 400 350 300 250 200 150 100 50 0 Cash Net * (100,000) Sep-10 Oct-10 Nov-10 Dec-10 Jan-11 Feb-11 Mar-11 Apr-11 May-11 Jun-11 Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 80 60 40 20 0 (20) (40) (60) (80) Cash Net Datum (100) (120) (140) (160) (180) (200) (220) (240) Months Cash net Cash in Cash out File:Cash Flow Page1 of 1 Printed On:10/20/10 at 12:07 PM