SlideShare une entreprise Scribd logo
1  sur  28
Goal:Goal:
Customer Satisfaction
Objective :Objective :
Meeting commitments on cost, schedule, quality
Milestones :Milestones :
 better control through change control, CM, monitoring etc.
 better predictability leading to commitments that can be met.
 lower cost through reduced rework, better resource management, better planning
 improved quality through proper quality planning and control
 better handling of risks reducing the chances of failure
2
Two Dimensional Approach
3
Small
Projects
Large
Projects
formalinformal
informal
formal
Execution
Project
Management
4
Organization
Project plan
Change management
Resources
People management
Team management
Cost Management
Project Variables
Quality management
Scope management
Risk Management
Communication
Project kick off
Status reporting
communication
Management
Project Governance
Project Governance Model
Project Management Process
planning, monitoring and control, and closureplanning, monitoring and control, and closure
 before the main execution life cycle (LC) and closure after the LC
 monitoring phase is in parallel with LC
Project Planning :Project Planning :
 defining suitable processes for executing the project
 estimating effort
 defining project milestones and create a schedule
 defining quality objectives and a quality plan
 identifying risks and make plans to mitigate them
 defining measurement plan, project-tracking procedures, training plan, team organization, etc
Process Planning :Process Planning :
 process to be followed
 process will decide the tasks, their ordering, milestones
 plan for LC as supporting process
Life Cycle Process:Life Cycle Process:
 NRE ,OJT, First Article
o adding, deleting, modifying some process steps
o fine-tuning to suit the project needs
Project Scheduling and Resource
Overall schedule and detailed scheduleOverall schedule and detailed schedule
 Overall schedule - major milestones and final date
 Detailed schedule - assignment of lowest level tasks to resources
Schedule and resource mappingSchedule and resource mapping
o the nominal delivery time for the schedule
o actual delivery time desired
o project effort as a function of project delivery time
o efforts calculation in man hour
o with effort and overall schedule decided, average project resources are fixed
o manpower ramp-up in a project for deciding the milestones
6
 consistent with milestones
 identifying lowest level tasks those can be done in less than 2-3 days
 deciding the tasks, assigning them while preserving high-level schedule
 modifying if cannot “fit” all tasks, must revisit high level schedule
 Identifying each task by name, date, duration, resource assigned
7
Detailed Scheduling
Manpower distribution – PM approach
8
TestPlan Build
Quality Planning
Defect Injection and RemovalDefect Injection and Removal
harness assembly is a labor intensive job
defects are injected at any stage
as quality goal is low delivered defect density, these defects are removed
done primarily by quality control (QC) activities of reviews and testing
Procedural approachProcedural approach
quality plan defines what QC tasks will be undertaken
main QC tasks - reviews and testing
guidelines and procedures for reviews and testing
adherence to the plan and procedures ensured
Quality PlanQuality Plan
drives the quality activities in the project
level of plan based on job criticality
defined QC tasks that have to be performed
specify defect levels for each QC tasks
Measurement of defect injection and removal rates, defect removal efficiency (DRE)
Continuous Improvement
 Process Mapping and Redesign
 Work Standardization
 Mistake Proofing
 Visibility Management Tools
 Cross-training and Certification

10
Risk Management Tasks
11
Risk Identification
Risk Management
Risk Assessment
Risk Control
Risk Analysis
Risk Prioritization
Risk Management Planning
Risk Resolution
Risk Monitoring
Risk Identification, Analysis and Prioritization
 “what ifs”, checklists, past experience
 list of “top 10” risks similar projects have seen in past
o shortage of technically trained manpower
o too many requirement changes
o unclear requirements
o not meeting performance requirements
o unrealistic schedules
o insufficient business knowledge
o working on new technology
 Risk Exposure (RE) = probability of risk occurring * risk impact
o RE considered as expected value of loss for a risk
o Prioritization done based on risk exposure value
 Plans are made to handle high RE risks
 REs revisited periodically
12
Tracking
Activity level monitoringActivity level monitoring
 Each activity in detailed schedule is getting done
 daily review
Status reportsStatus reports
 weekly to take stock
 Summary of activities completed, pending
 Issues to be resolved
Milestone analysisMilestone analysis
 A bigger review at milestones
 Actual vs estimated for effort and sched is done
 Risks are revisited
 Changes to product and their impact may be analyzed
Cost-schedule milestone graph is another way of doing this
13
14
Prioritization
Review&Approval
PMOMonitoring
DemandDemand
ManagementManagement
Charter development, resource requirements
and Business Case
ProjectProject
ManagementManagement
Plan, collaborate and deliver
ResourceResource
ManagementManagement
Capacity estimate, resource assignments
and utilization monitoring
FinancialFinancial
ManagementManagement
Labour and non-labour spend
Strategic plan for the project
Team structure
Customer
Project Manager
Project Coordinator
Material
Planning Rep
Product
Engineering Rep
Production
Team Lead
QA Team Lead
Goal:Goal:
Global Optimization and managing uncertainty
Objective :Objective :
 supply in the right quantities at right time
 minimize total system cost
 satisfy customer service requirements
Milestones :Milestones :
 Purchasing - Supplier alliances, supplier management, strategic sourcing
 Operations - Demand management, TQM
 Distribution - Transportation management, customer relationship management,
logistics
 Integration - Coordination/Integration activities, global sourcing problems,
performance measurement
17
Supply Chain Organization in Sasmos
Supply Chain Manager
Procurement Logistics SCM admin
• KAP identification
• Volume driven
• Audit
• Spend areas-future
• Critical components
• Strategies
• Efficiencies
• Process review
• Demand &
forecasting
• Warehousing
• Inventory
• Transportation
• Release orders
• Spot orders
• Non-repetitive orders
• Non critical
components
Strategic Sourcing Tactical
Contract Management
Project Manger
Is viewed asIs viewed as effective, relevant, valued ,part of the Management Team
KAP = Key Alliance Partners
PurchasingPurchasing
Receiving Storage Operations Storage
ProductionProduction SupplySupply
Sourcing Procuring
short lead time
long lead time
predictable unpredictable
plan and optimize
quick responseplan and
replenishment
postponement
strategy
supply
demand
Responsive
SupplyChain
Certain
Demand
Responsiveness
Spectrum
Efficient
SupplyChain
Implied
uncertainty
Spectrum
Uncertain
Demand
Zone
of
Strategic
Fit
Purchase
Cost
Demand Drivers
Specifications Standardization
Inventory Practices
Warehousing Costs
Maintenance Expense
Quality Costs
Procurement Practices
Warranty Terms
Freight
Volume
Perceived cost
Actual
cost
Sasmos Trends:Sasmos Trends:
 long term relationships
 improve performance through
 determining supplier capabilities
 self or internal certification to assure product quality and service
requirements
 strategic partnerships- successful and trusting relationships with
top-performing suppliers
Quick wins as well as longer-term opportunities that could form the basis of a
structured plan of activities over the coming years to deliver the benefits.
considering the development of detailed category strategies
looking at the best geographic location for sourcing
looking across the full range of procurement levers all of which help manage
and reduce cost but also lead to reduced supply chain risk, such as
o strategic sourcing
o cost modelling
o inflation management
o Dollar fluctuation
o fixed rate contract with partners
Reducing Supply Chain CostsReducing Supply Chain Costs
 Reduced purchasing costs
 Reducing waste
 Reducing excess inventory, and
 Reducing non-value added activities
Continuous ImprovementContinuous Improvement
 Benchmarking- improve over competitors’ performance
 Trial & error
 Increased knowledge of supply chain processes
Cost Reduction –Current Practice
 Demand management - matching demand to available capacity
 Linking suppliers via MRP and ERP systems
 Use JIT to improve the pull of materials to reduce inventory levels
 Employ TQM to improve quality compliance among suppliers
 Use TCO as a tool
Cost Reduction –Plan
• Performance measurement
• Framework for cost analysis
• Benchmarking performance
• More informed decision making
• Communication of cost issues internally and with suppliers
• Cross-functional interaction
• Better insight/understanding of cost drivers
• Outsourcing analysis
• Continuous improvement
• Cost savings opportunities
• Focus on high potential opportunities
27
Total cost ownership(TCO) Analysis
Total cost ownership(TCO) decisions
• low-cost commodity items
• large purchases of items in competitive markets
• large purchases from important suppliers
• large dollar volume infrequent purchase
• Procurements with significant unrecognized transaction costs
• transactions costs, via negotiation, changing suppliers, and/or improving internal operations
• cross-functional involvement in understanding item or service cost structure
• capital purchases

Contenu connexe

Tendances

Project Quality Management - PMBOK 5th Edition
Project Quality Management - PMBOK 5th EditionProject Quality Management - PMBOK 5th Edition
Project Quality Management - PMBOK 5th Editionpankajsh10
 
Project Quality Management - PMBOK
Project Quality Management - PMBOKProject Quality Management - PMBOK
Project Quality Management - PMBOKArief Rahmana
 
Project Quality Management
Project Quality ManagementProject Quality Management
Project Quality ManagementGiO Friginal
 
Benchmarking Project Schedules
Benchmarking Project SchedulesBenchmarking Project Schedules
Benchmarking Project SchedulesAcumen
 
Construction quality management plan (Construction Productivity Analysis)
Construction quality management plan (Construction Productivity Analysis)Construction quality management plan (Construction Productivity Analysis)
Construction quality management plan (Construction Productivity Analysis)Jayson Narito
 
Quality in project management
Quality in project management Quality in project management
Quality in project management Zeeshan Azhar
 
Project Quality Management
Project Quality ManagementProject Quality Management
Project Quality Managementasim78
 
Project quality management
Project quality managementProject quality management
Project quality managementsyeda zoya mehdi
 
Project managemenet knowledge areas
Project managemenet knowledge areasProject managemenet knowledge areas
Project managemenet knowledge areaslinajarruti
 
Project Quality Management
 Project Quality Management Project Quality Management
Project Quality ManagementSerdar Temiz
 
Pmp – pmbok 5th edition chapter7 project cost management
Pmp – pmbok 5th edition chapter7 project cost managementPmp – pmbok 5th edition chapter7 project cost management
Pmp – pmbok 5th edition chapter7 project cost managementYudha Pratama, PMP
 
A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost managementImran Jamil
 
Project Quality Management powerpoint
Project Quality Management powerpointProject Quality Management powerpoint
Project Quality Management powerpointDjamadaMuhamedKAGUSU
 

Tendances (20)

Project Quality Management - PMBOK 5th Edition
Project Quality Management - PMBOK 5th EditionProject Quality Management - PMBOK 5th Edition
Project Quality Management - PMBOK 5th Edition
 
Project Quality Management - PMBOK
Project Quality Management - PMBOKProject Quality Management - PMBOK
Project Quality Management - PMBOK
 
Project Quality Management
Project Quality ManagementProject Quality Management
Project Quality Management
 
Benchmarking Project Schedules
Benchmarking Project SchedulesBenchmarking Project Schedules
Benchmarking Project Schedules
 
Construction quality management plan (Construction Productivity Analysis)
Construction quality management plan (Construction Productivity Analysis)Construction quality management plan (Construction Productivity Analysis)
Construction quality management plan (Construction Productivity Analysis)
 
Project management
Project managementProject management
Project management
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Quality in project management
Quality in project management Quality in project management
Quality in project management
 
Project Quality Management
Project Quality ManagementProject Quality Management
Project Quality Management
 
Close Loop MRP
Close Loop MRPClose Loop MRP
Close Loop MRP
 
Project quality management
Project quality managementProject quality management
Project quality management
 
Project managemenet knowledge areas
Project managemenet knowledge areasProject managemenet knowledge areas
Project managemenet knowledge areas
 
08 project quality management
08 project quality management08 project quality management
08 project quality management
 
Project Quality Management
 Project Quality Management Project Quality Management
Project Quality Management
 
Pmp – pmbok 5th edition chapter7 project cost management
Pmp – pmbok 5th edition chapter7 project cost managementPmp – pmbok 5th edition chapter7 project cost management
Pmp – pmbok 5th edition chapter7 project cost management
 
7- PMP Training - Quality Management
7- PMP Training - Quality Management7- PMP Training - Quality Management
7- PMP Training - Quality Management
 
Project Metrics & Measures
Project Metrics & MeasuresProject Metrics & Measures
Project Metrics & Measures
 
PMP_Project Cost Management
PMP_Project Cost ManagementPMP_Project Cost Management
PMP_Project Cost Management
 
A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost management
 
Project Quality Management powerpoint
Project Quality Management powerpointProject Quality Management powerpoint
Project Quality Management powerpoint
 

En vedette

Antes y después Ana Maria
Antes y después Ana MariaAntes y después Ana Maria
Antes y después Ana MariaSergio Breitfeld
 
The Power of Digital Self
The Power of Digital SelfThe Power of Digital Self
The Power of Digital SelfVijayanta Gupta
 
Rise of the data driven marketer
Rise of the data driven marketerRise of the data driven marketer
Rise of the data driven marketerVijayanta Gupta
 
To Lead, Or Not To Lead
To Lead, Or Not To LeadTo Lead, Or Not To Lead
To Lead, Or Not To Leadsvanesch
 
Rupesh Mathur Updated (New)
Rupesh Mathur Updated (New)Rupesh Mathur Updated (New)
Rupesh Mathur Updated (New)Roopesh Mathur
 
Contenido inteligencias verbal
Contenido inteligencias verbalContenido inteligencias verbal
Contenido inteligencias verbalmagdalenamas
 
Integrated Treatment for ARLD: Making it happen, 2 February 2017 Presentation...
Integrated Treatment for ARLD: Making it happen, 2 February 2017 Presentation...Integrated Treatment for ARLD: Making it happen, 2 February 2017 Presentation...
Integrated Treatment for ARLD: Making it happen, 2 February 2017 Presentation...Health Innovation Wessex
 
Elements, Compounds and Mixtures
Elements, Compounds and MixturesElements, Compounds and Mixtures
Elements, Compounds and Mixturespakidoctors
 
Integrated Treatment for ARLD: making it happen, 2nd February 2017 Presentat...
Integrated Treatment for ARLD:  making it happen, 2nd February 2017 Presentat...Integrated Treatment for ARLD:  making it happen, 2nd February 2017 Presentat...
Integrated Treatment for ARLD: making it happen, 2nd February 2017 Presentat...Health Innovation Wessex
 
Integrated Treatment for ARLD: Making it happen, 2 February 2017, Presentatio...
Integrated Treatment for ARLD: Making it happen, 2 February 2017, Presentatio...Integrated Treatment for ARLD: Making it happen, 2 February 2017, Presentatio...
Integrated Treatment for ARLD: Making it happen, 2 February 2017, Presentatio...Health Innovation Wessex
 

En vedette (12)

new resume (2)
new resume (2)new resume (2)
new resume (2)
 
Antes y después Ana Maria
Antes y después Ana MariaAntes y después Ana Maria
Antes y después Ana Maria
 
1
11
1
 
The Power of Digital Self
The Power of Digital SelfThe Power of Digital Self
The Power of Digital Self
 
Rise of the data driven marketer
Rise of the data driven marketerRise of the data driven marketer
Rise of the data driven marketer
 
To Lead, Or Not To Lead
To Lead, Or Not To LeadTo Lead, Or Not To Lead
To Lead, Or Not To Lead
 
Rupesh Mathur Updated (New)
Rupesh Mathur Updated (New)Rupesh Mathur Updated (New)
Rupesh Mathur Updated (New)
 
Contenido inteligencias verbal
Contenido inteligencias verbalContenido inteligencias verbal
Contenido inteligencias verbal
 
Integrated Treatment for ARLD: Making it happen, 2 February 2017 Presentation...
Integrated Treatment for ARLD: Making it happen, 2 February 2017 Presentation...Integrated Treatment for ARLD: Making it happen, 2 February 2017 Presentation...
Integrated Treatment for ARLD: Making it happen, 2 February 2017 Presentation...
 
Elements, Compounds and Mixtures
Elements, Compounds and MixturesElements, Compounds and Mixtures
Elements, Compounds and Mixtures
 
Integrated Treatment for ARLD: making it happen, 2nd February 2017 Presentat...
Integrated Treatment for ARLD:  making it happen, 2nd February 2017 Presentat...Integrated Treatment for ARLD:  making it happen, 2nd February 2017 Presentat...
Integrated Treatment for ARLD: making it happen, 2nd February 2017 Presentat...
 
Integrated Treatment for ARLD: Making it happen, 2 February 2017, Presentatio...
Integrated Treatment for ARLD: Making it happen, 2 February 2017, Presentatio...Integrated Treatment for ARLD: Making it happen, 2 February 2017, Presentatio...
Integrated Treatment for ARLD: Making it happen, 2 February 2017, Presentatio...
 

Similaire à Proj mgmt and scm

Topic 8 - Project Quality Management.pdf
Topic 8 - Project Quality Management.pdfTopic 8 - Project Quality Management.pdf
Topic 8 - Project Quality Management.pdfHuyNguyen657394
 
PJM6000Project Management PracticesWeek 5Deb Cote,.docx
PJM6000Project Management PracticesWeek 5Deb Cote,.docxPJM6000Project Management PracticesWeek 5Deb Cote,.docx
PJM6000Project Management PracticesWeek 5Deb Cote,.docxARIV4
 
PJM6000Project Management PracticesWeek 5Deb Cote,.docx
PJM6000Project Management PracticesWeek 5Deb Cote,.docxPJM6000Project Management PracticesWeek 5Deb Cote,.docx
PJM6000Project Management PracticesWeek 5Deb Cote,.docxstilliegeorgiana
 
Lean Six Sigma Projects & Strategy Linkage
Lean Six Sigma Projects & Strategy LinkageLean Six Sigma Projects & Strategy Linkage
Lean Six Sigma Projects & Strategy LinkageAnand Subramaniam
 
Project management
Project managementProject management
Project managementAnshu Suri
 
Introduction To Project Management
Introduction To Project ManagementIntroduction To Project Management
Introduction To Project ManagementTrue Corporation
 
Project management presentation
Project management presentationProject management presentation
Project management presentationPACF
 
Intro to Project Management
Intro to Project ManagementIntro to Project Management
Intro to Project ManagementNoman Aftab
 
CMMI Capability Maturity Model Integration
CMMI   Capability Maturity Model Integration CMMI   Capability Maturity Model Integration
CMMI Capability Maturity Model Integration Anand Subramaniam
 
Hi Performance Manufacturing
Hi Performance ManufacturingHi Performance Manufacturing
Hi Performance ManufacturingAlex Diong
 
CMM L2- Quality Management System
CMM L2- Quality Management SystemCMM L2- Quality Management System
CMM L2- Quality Management SystemSuyog Raut
 
Building Quality Into Your Technical Communications Department
Building Quality Into Your Technical Communications DepartmentBuilding Quality Into Your Technical Communications Department
Building Quality Into Your Technical Communications DepartmentAmy S. Friend
 
Lect.02.09.13
Lect.02.09.13Lect.02.09.13
Lect.02.09.13h_tixid
 

Similaire à Proj mgmt and scm (20)

Topic 8 - Project Quality Management.pdf
Topic 8 - Project Quality Management.pdfTopic 8 - Project Quality Management.pdf
Topic 8 - Project Quality Management.pdf
 
PJM6000Project Management PracticesWeek 5Deb Cote,.docx
PJM6000Project Management PracticesWeek 5Deb Cote,.docxPJM6000Project Management PracticesWeek 5Deb Cote,.docx
PJM6000Project Management PracticesWeek 5Deb Cote,.docx
 
PJM6000Project Management PracticesWeek 5Deb Cote,.docx
PJM6000Project Management PracticesWeek 5Deb Cote,.docxPJM6000Project Management PracticesWeek 5Deb Cote,.docx
PJM6000Project Management PracticesWeek 5Deb Cote,.docx
 
Project plan overview
Project plan overviewProject plan overview
Project plan overview
 
Lean Six Sigma Projects & Strategy Linkage
Lean Six Sigma Projects & Strategy LinkageLean Six Sigma Projects & Strategy Linkage
Lean Six Sigma Projects & Strategy Linkage
 
Project Management
Project ManagementProject Management
Project Management
 
Project management
Project managementProject management
Project management
 
Introduction To Project Management
Introduction To Project ManagementIntroduction To Project Management
Introduction To Project Management
 
Project management presentation
Project management presentationProject management presentation
Project management presentation
 
Intro to Project Management
Intro to Project ManagementIntro to Project Management
Intro to Project Management
 
CMMI Capability Maturity Model Integration
CMMI   Capability Maturity Model Integration CMMI   Capability Maturity Model Integration
CMMI Capability Maturity Model Integration
 
Hi Performance Manufacturing
Hi Performance ManufacturingHi Performance Manufacturing
Hi Performance Manufacturing
 
CMM L2- Quality Management System
CMM L2- Quality Management SystemCMM L2- Quality Management System
CMM L2- Quality Management System
 
Building Quality Into Your Technical Communications Department
Building Quality Into Your Technical Communications DepartmentBuilding Quality Into Your Technical Communications Department
Building Quality Into Your Technical Communications Department
 
Session 12 4th edition PMP
Session  12 4th edition PMPSession  12 4th edition PMP
Session 12 4th edition PMP
 
The path to planning
The path to planningThe path to planning
The path to planning
 
Lect.02.09.13
Lect.02.09.13Lect.02.09.13
Lect.02.09.13
 
PMRolesResponsibilities.ppt
PMRolesResponsibilities.pptPMRolesResponsibilities.ppt
PMRolesResponsibilities.ppt
 
Sdg latest
Sdg  latestSdg  latest
Sdg latest
 
6396901
63969016396901
6396901
 

Dernier

Technical Leaders - Working with the Management Team
Technical Leaders - Working with the Management TeamTechnical Leaders - Working with the Management Team
Technical Leaders - Working with the Management TeamArik Fletcher
 
How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...
How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...
How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...Hector Del Castillo, CPM, CPMM
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Anamaria Contreras
 
Welding Electrode Making Machine By Deccan Dynamics
Welding Electrode Making Machine By Deccan DynamicsWelding Electrode Making Machine By Deccan Dynamics
Welding Electrode Making Machine By Deccan DynamicsIndiaMART InterMESH Limited
 
Send Files | Sendbig.comSend Files | Sendbig.com
Send Files | Sendbig.comSend Files | Sendbig.comSend Files | Sendbig.comSend Files | Sendbig.com
Send Files | Sendbig.comSend Files | Sendbig.comSendBig4
 
1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdf1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdfShaun Heinrichs
 
How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...
How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...
How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...SOFTTECHHUB
 
Darshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfDarshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfShashank Mehta
 
Pitch Deck Teardown: Xpanceo's $40M Seed deck
Pitch Deck Teardown: Xpanceo's $40M Seed deckPitch Deck Teardown: Xpanceo's $40M Seed deck
Pitch Deck Teardown: Xpanceo's $40M Seed deckHajeJanKamps
 
GUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdf
GUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdfGUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdf
GUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdfDanny Diep To
 
Appkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptxAppkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptxappkodes
 
1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdf1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdfShaun Heinrichs
 
WSMM Media and Entertainment Feb_March_Final.pdf
WSMM Media and Entertainment Feb_March_Final.pdfWSMM Media and Entertainment Feb_March_Final.pdf
WSMM Media and Entertainment Feb_March_Final.pdfJamesConcepcion7
 
Driving Business Impact for PMs with Jon Harmer
Driving Business Impact for PMs with Jon HarmerDriving Business Impact for PMs with Jon Harmer
Driving Business Impact for PMs with Jon HarmerAggregage
 
20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdf
20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdf20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdf
20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdfChris Skinner
 
APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfRbc Rbcua
 
Supercharge Your eCommerce Stores-acowebs
Supercharge Your eCommerce Stores-acowebsSupercharge Your eCommerce Stores-acowebs
Supercharge Your eCommerce Stores-acowebsGOKUL JS
 
Unveiling the Soundscape Music for Psychedelic Experiences
Unveiling the Soundscape Music for Psychedelic ExperiencesUnveiling the Soundscape Music for Psychedelic Experiences
Unveiling the Soundscape Music for Psychedelic ExperiencesDoe Paoro
 

Dernier (20)

Technical Leaders - Working with the Management Team
Technical Leaders - Working with the Management TeamTechnical Leaders - Working with the Management Team
Technical Leaders - Working with the Management Team
 
How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...
How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...
How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.
 
Welding Electrode Making Machine By Deccan Dynamics
Welding Electrode Making Machine By Deccan DynamicsWelding Electrode Making Machine By Deccan Dynamics
Welding Electrode Making Machine By Deccan Dynamics
 
Send Files | Sendbig.comSend Files | Sendbig.com
Send Files | Sendbig.comSend Files | Sendbig.comSend Files | Sendbig.comSend Files | Sendbig.com
Send Files | Sendbig.comSend Files | Sendbig.com
 
1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdf1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdf
 
How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...
How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...
How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...
 
Darshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfDarshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdf
 
Pitch Deck Teardown: Xpanceo's $40M Seed deck
Pitch Deck Teardown: Xpanceo's $40M Seed deckPitch Deck Teardown: Xpanceo's $40M Seed deck
Pitch Deck Teardown: Xpanceo's $40M Seed deck
 
GUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdf
GUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdfGUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdf
GUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdf
 
Appkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptxAppkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptx
 
1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdf1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdf
 
The Bizz Quiz-E-Summit-E-Cell-IITPatna.pptx
The Bizz Quiz-E-Summit-E-Cell-IITPatna.pptxThe Bizz Quiz-E-Summit-E-Cell-IITPatna.pptx
The Bizz Quiz-E-Summit-E-Cell-IITPatna.pptx
 
WSMM Media and Entertainment Feb_March_Final.pdf
WSMM Media and Entertainment Feb_March_Final.pdfWSMM Media and Entertainment Feb_March_Final.pdf
WSMM Media and Entertainment Feb_March_Final.pdf
 
Driving Business Impact for PMs with Jon Harmer
Driving Business Impact for PMs with Jon HarmerDriving Business Impact for PMs with Jon Harmer
Driving Business Impact for PMs with Jon Harmer
 
WAM Corporate Presentation April 12 2024.pdf
WAM Corporate Presentation April 12 2024.pdfWAM Corporate Presentation April 12 2024.pdf
WAM Corporate Presentation April 12 2024.pdf
 
20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdf
20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdf20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdf
20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdf
 
APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdf
 
Supercharge Your eCommerce Stores-acowebs
Supercharge Your eCommerce Stores-acowebsSupercharge Your eCommerce Stores-acowebs
Supercharge Your eCommerce Stores-acowebs
 
Unveiling the Soundscape Music for Psychedelic Experiences
Unveiling the Soundscape Music for Psychedelic ExperiencesUnveiling the Soundscape Music for Psychedelic Experiences
Unveiling the Soundscape Music for Psychedelic Experiences
 

Proj mgmt and scm

  • 1.
  • 2. Goal:Goal: Customer Satisfaction Objective :Objective : Meeting commitments on cost, schedule, quality Milestones :Milestones :  better control through change control, CM, monitoring etc.  better predictability leading to commitments that can be met.  lower cost through reduced rework, better resource management, better planning  improved quality through proper quality planning and control  better handling of risks reducing the chances of failure 2
  • 4. 4 Organization Project plan Change management Resources People management Team management Cost Management Project Variables Quality management Scope management Risk Management Communication Project kick off Status reporting communication Management Project Governance Project Governance Model
  • 5. Project Management Process planning, monitoring and control, and closureplanning, monitoring and control, and closure  before the main execution life cycle (LC) and closure after the LC  monitoring phase is in parallel with LC Project Planning :Project Planning :  defining suitable processes for executing the project  estimating effort  defining project milestones and create a schedule  defining quality objectives and a quality plan  identifying risks and make plans to mitigate them  defining measurement plan, project-tracking procedures, training plan, team organization, etc Process Planning :Process Planning :  process to be followed  process will decide the tasks, their ordering, milestones  plan for LC as supporting process Life Cycle Process:Life Cycle Process:  NRE ,OJT, First Article o adding, deleting, modifying some process steps o fine-tuning to suit the project needs
  • 6. Project Scheduling and Resource Overall schedule and detailed scheduleOverall schedule and detailed schedule  Overall schedule - major milestones and final date  Detailed schedule - assignment of lowest level tasks to resources Schedule and resource mappingSchedule and resource mapping o the nominal delivery time for the schedule o actual delivery time desired o project effort as a function of project delivery time o efforts calculation in man hour o with effort and overall schedule decided, average project resources are fixed o manpower ramp-up in a project for deciding the milestones 6
  • 7.  consistent with milestones  identifying lowest level tasks those can be done in less than 2-3 days  deciding the tasks, assigning them while preserving high-level schedule  modifying if cannot “fit” all tasks, must revisit high level schedule  Identifying each task by name, date, duration, resource assigned 7 Detailed Scheduling
  • 8. Manpower distribution – PM approach 8 TestPlan Build
  • 9. Quality Planning Defect Injection and RemovalDefect Injection and Removal harness assembly is a labor intensive job defects are injected at any stage as quality goal is low delivered defect density, these defects are removed done primarily by quality control (QC) activities of reviews and testing Procedural approachProcedural approach quality plan defines what QC tasks will be undertaken main QC tasks - reviews and testing guidelines and procedures for reviews and testing adherence to the plan and procedures ensured Quality PlanQuality Plan drives the quality activities in the project level of plan based on job criticality defined QC tasks that have to be performed specify defect levels for each QC tasks Measurement of defect injection and removal rates, defect removal efficiency (DRE)
  • 10. Continuous Improvement  Process Mapping and Redesign  Work Standardization  Mistake Proofing  Visibility Management Tools  Cross-training and Certification  10
  • 11. Risk Management Tasks 11 Risk Identification Risk Management Risk Assessment Risk Control Risk Analysis Risk Prioritization Risk Management Planning Risk Resolution Risk Monitoring
  • 12. Risk Identification, Analysis and Prioritization  “what ifs”, checklists, past experience  list of “top 10” risks similar projects have seen in past o shortage of technically trained manpower o too many requirement changes o unclear requirements o not meeting performance requirements o unrealistic schedules o insufficient business knowledge o working on new technology  Risk Exposure (RE) = probability of risk occurring * risk impact o RE considered as expected value of loss for a risk o Prioritization done based on risk exposure value  Plans are made to handle high RE risks  REs revisited periodically 12
  • 13. Tracking Activity level monitoringActivity level monitoring  Each activity in detailed schedule is getting done  daily review Status reportsStatus reports  weekly to take stock  Summary of activities completed, pending  Issues to be resolved Milestone analysisMilestone analysis  A bigger review at milestones  Actual vs estimated for effort and sched is done  Risks are revisited  Changes to product and their impact may be analyzed Cost-schedule milestone graph is another way of doing this 13
  • 14. 14 Prioritization Review&Approval PMOMonitoring DemandDemand ManagementManagement Charter development, resource requirements and Business Case ProjectProject ManagementManagement Plan, collaborate and deliver ResourceResource ManagementManagement Capacity estimate, resource assignments and utilization monitoring FinancialFinancial ManagementManagement Labour and non-labour spend Strategic plan for the project
  • 15. Team structure Customer Project Manager Project Coordinator Material Planning Rep Product Engineering Rep Production Team Lead QA Team Lead
  • 16.
  • 17. Goal:Goal: Global Optimization and managing uncertainty Objective :Objective :  supply in the right quantities at right time  minimize total system cost  satisfy customer service requirements Milestones :Milestones :  Purchasing - Supplier alliances, supplier management, strategic sourcing  Operations - Demand management, TQM  Distribution - Transportation management, customer relationship management, logistics  Integration - Coordination/Integration activities, global sourcing problems, performance measurement 17
  • 18. Supply Chain Organization in Sasmos Supply Chain Manager Procurement Logistics SCM admin • KAP identification • Volume driven • Audit • Spend areas-future • Critical components • Strategies • Efficiencies • Process review • Demand & forecasting • Warehousing • Inventory • Transportation • Release orders • Spot orders • Non-repetitive orders • Non critical components Strategic Sourcing Tactical Contract Management Project Manger Is viewed asIs viewed as effective, relevant, valued ,part of the Management Team KAP = Key Alliance Partners
  • 19. PurchasingPurchasing Receiving Storage Operations Storage ProductionProduction SupplySupply Sourcing Procuring
  • 20. short lead time long lead time predictable unpredictable plan and optimize quick responseplan and replenishment postponement strategy supply demand
  • 22. Purchase Cost Demand Drivers Specifications Standardization Inventory Practices Warehousing Costs Maintenance Expense Quality Costs Procurement Practices Warranty Terms Freight Volume Perceived cost Actual cost
  • 23. Sasmos Trends:Sasmos Trends:  long term relationships  improve performance through  determining supplier capabilities  self or internal certification to assure product quality and service requirements  strategic partnerships- successful and trusting relationships with top-performing suppliers
  • 24. Quick wins as well as longer-term opportunities that could form the basis of a structured plan of activities over the coming years to deliver the benefits. considering the development of detailed category strategies looking at the best geographic location for sourcing looking across the full range of procurement levers all of which help manage and reduce cost but also lead to reduced supply chain risk, such as o strategic sourcing o cost modelling o inflation management o Dollar fluctuation o fixed rate contract with partners
  • 25. Reducing Supply Chain CostsReducing Supply Chain Costs  Reduced purchasing costs  Reducing waste  Reducing excess inventory, and  Reducing non-value added activities Continuous ImprovementContinuous Improvement  Benchmarking- improve over competitors’ performance  Trial & error  Increased knowledge of supply chain processes Cost Reduction –Current Practice
  • 26.  Demand management - matching demand to available capacity  Linking suppliers via MRP and ERP systems  Use JIT to improve the pull of materials to reduce inventory levels  Employ TQM to improve quality compliance among suppliers  Use TCO as a tool Cost Reduction –Plan
  • 27. • Performance measurement • Framework for cost analysis • Benchmarking performance • More informed decision making • Communication of cost issues internally and with suppliers • Cross-functional interaction • Better insight/understanding of cost drivers • Outsourcing analysis • Continuous improvement • Cost savings opportunities • Focus on high potential opportunities 27 Total cost ownership(TCO) Analysis
  • 28. Total cost ownership(TCO) decisions • low-cost commodity items • large purchases of items in competitive markets • large purchases from important suppliers • large dollar volume infrequent purchase • Procurements with significant unrecognized transaction costs • transactions costs, via negotiation, changing suppliers, and/or improving internal operations • cross-functional involvement in understanding item or service cost structure • capital purchases