SlideShare a Scribd company logo
1 of 10
दिकण रेलवे
SOUTHERN RAILWAY
कॆ दीय कमरशालायॆ, गोलडऩराक
Central Workshops, Goldenrock
ितरिचरापपिलल ६००००४/ Tiruchirappalli 620004
SR ACCN 99119
Anchor Link
Failure Analysis Report
COACH FAILURE ANALYSIS REPORT
1. Failure Reported:
Coach No. SR ACCN 99119 was detached en-route from train no. 12642 (NZM – CAPE,
Thirukkural Express) at Vijayawada on 27.01.2015 at about 13.30 hours, due to breakage of
Anchor Link in Trailing End Bogie No. RCF 032123/03 at housing end of Bogie Frame Transom and the
broken portion was hanging. This was found in Rolling-in-Examination when it arrived at PF-5 of
Vijayawada station and the coach was detached. The train resumed its service with a delay of about
100 minutes.
2. Detached Coach Details:
Coach No : SR ACCN 99119
Coach Make RCF
Date of put into service : 10.01.1999
POH : GOC – 10/11/2014
Return Date : 30.06.2016
No. of days worked : 77 days (Failure within 100 days)
Primary Maintenance : NCJ on 23.01.2015
Bogie Details in coach (As per
POH work diary)
: RCF 032123/03 & RCF 062760/06
(Date of POH of Bogies: 27.10.2014)
Owning Railway & Base Depot : S.Rly & TVC
3. Deputation of staff:
The following staff had been deputed & proceeded immediately for investigation of the failure.
1. Mr. P.Sureshkumar, SSE 2. Mr. Gnanasekaran, SSE
4. Joint investigation at Site:
Investigation was conducted at Vijayawada sick line on 28.01.2015 jointly by GOC team &
SSE/C&W/BZA/S.C.Rly. The observations are given below.
4.1 The failed Anchor Link stripped from Bogie No. RCF 032123/03 and put new anchor link.
4.2 The NPEV end of the coach ACCN 99119 left hand side Anchor Link pipe broken on the
welding joint to anchor link housing which is connected to bogie frame.
4.3 The other side of anchor link connected to bolster end. Welding joint is in good condition
and silent block is in slacked condition. The broken anchor link is new with black colour
paint and having sticker as “SGEW 06/13” on anchor link housing outside.
4.4 10% of breakage emanated from weld crack and pipe torn & broken.
4.5 Anchor link pin square end insertion in holding bracket on bogie end was found having
shim tack welding.
4.6 Locking plate was having corner hit marks as well as Anchor Link housing was having hit
marks on bottom.
4.7 Findings by the above team:
4.71 Micro play between Anchor Link housing and silent block coupled with weld defect
caused shearing force and breakage.
4.72 Broken anchor link taken by GOC shop for CMT testing & warranty claim on
supplier.
Page 1 of 7
5. Photographs taken at site (BZA):
6. CMT Lab Analysis at GOC of Breakage of Anchor Link:
The failed anchor link was subjected to CMT lab analysis and the nutshell of the report is given below.
6.1 Observations given in the Lab report:
a) Chemical composition of the Anchor Link is conforming to the specification IS:10748/2004.
b) At the transom end of anchor link, the pipe was broken from the housing along the welded area.
c) Remnants of weld metal are partially available on the anchor link housing with fractured piece of
the pipe.
d) At the bolster end side, the silent block is freely moving inside the housing.
e) The wall thickness of the anchor link pipe is not uniform and varies from 3.62 mm to 3.76 mm as
against the specified value of 4.05 to 4.50 mm as per IS:1161:98 mentioned in drawing no. T-0-7-
604, alt – j/13.
f) About 21% of the circumferential welded area along the housing suffers from lack of fusion/
penetration.
g) The macro examination of fractured surface of the pipe reveals 25% of the area having voids
characteristic of sudden brittle fracture and the remaining 75% is having formation of shearing lips
characteristic of ductile fracture involving high torsion stresses.
6.2 CMT Lab Report - Conclusion:
a) The wall thickness of the anchor link pipe is not uniform and varies from 3.62mm to 3.76mm as
against 4.05mm (4.5mm minus 10% tolerance) specified for Heavy grade mentioned in the
specification IS: 1161/98 referred in the drawing no. T-0-7-604, alt – j/13.
b) Lack of fusion/Penetration of the weld metal with the anchor link pipe along the periphery of the
housing (around 21 %.). It is leading to loss of strength of the weld.
c) The molten metal sputtering near the weldment affecting the region near the weld cast has acted as
an initiation site for the process of failure to occur.
d) The play between the anchor link housing and the coupled silent block on the bolster side has
created an imbalance on the other side of the anchor housing at the transom end.
Page 2 of 7
Broken tube
hanging
7. Dimensional Check of the failed components:
Anchor Link Housing Bore Silent Block
Inner Diameter of Anchor Link
Housing supplied by
M/s. Sugovri Engineering Works,
Howrah
Silent Block (Outer Diameter)
supplied by
M/s. MGM Rubber Co. Kolkata
Interference
Sample
Drawing
Size
(mm)
Side
Actual
(mm)
Sample
Drawing
Size
(mm)
Side
Actual
(mm)
As per
Drawing
Actual
І
90.470
to
90.515
1
1 90.520
І
90.525
to
90.550
1
1 90.260
0.01
to
0.08
0.210
to
0.760
(Clearance
fit)
2 90.490 2 90.280
3 90.510 3 90.280
1 90.520 1 89.760
2 90.460 2 90.140
3 90.450 3 90.130
Note: From the above table, the fit is only clearance fit and as against the force fit. Hence the silent block
is freely moving inside the housing.
90.520
90.490
90.51090.450
90.460
90.520
90.280
90.280
90.260
90.130
90.140
89.760
Anchor Link pipe: Thickness of Anchor Link pipe supplied by M/s. Sugovri Engineering
Works, Howrah
Sample
Drawing
Size
Thicknes
s (mm)
Side Location
Actual
Thickness
(mm)
1
4.05 mm
to
4.50 mm
1
1 3.660
2 3.620
3 3.640
4 3.680
5 3.700
6 3.760
7 3.720
8 3.740
Page 3 of 7
8. Traceability of failed components:
8.1 Anchor Link:
The failed anchor link was a new one as per the sticker “SGEW 06/13” available on the anchor link
housing. The procurement details of the item is given below.
Sl.
No.
Supplier Name P.O.No.
Supplied
Qty.
(Nos.)
Received
Date
Inspected
by
1.
M/s. Sugouri
Engineering
Works, Howrah
04.12.0161.1.01521
dated 27.05.2013
886
24.09.201
3
RITES
8.2 Silent Block:
The stamping of manufacturer details on the silent block indicates “MGM 06/14”. The procurement
details is given below.
Sl.
No.
Supplier Name P.O.No.
Supplied
Qty. (Nos.)
Received
Date
Inspected
by
1.
M/s. MGM Rubber
Company, Kolkata
04.13.0160.1.04425
dated 10.02.2014
2500 19.07.2014 RDSO
9. Preventive check on the items available at GOC belonging to the same consignment:
3.660
3.740
3.680
3.720
3.760
3.640
3.620
3.700
Anchor Link Silent Block
Inner Diameter of Anchor Link
Housing supplied by
M/s. Sugovri Engineering Works,
Howrah
Silent Block (Outer Diameter)
supplied by
M/s. MGM Rubber Co. Kolkata
Interference
Sample
Drawing
Size
(mm)
Side
Actual
(mm)
Sample
Drawing
Size
(mm)
Side
Actual
(mm)
As per
Drawing
Actual
I
90.470
to
90.515
1
1 90.400
I
90.525
to
90.550
1 90.526
0.01
to
0.08
0.020
to
0.200
2 90.440
2
1 90.510
2 90.602
2 90.510
II
1
1 90.430
II
1 90.602
2 90.510
2
1 90.480
2 90.551
2 90.510
Note: As per the tabulation given above, both the items are confirming to the drawing dimensions.
Page 4 of 7
10. Failure analysis based on the available evidences –Lab Report, dimensional check,
photographs and joint observation by SSEs/GOC & SSE/BZA:
10.1 Based on the identity on the failed components both Anchor Link and Silent Block were newly
fitted during POH.
10.2 Anchor Link housing bore diameter is 90.450 mm to 90.520 mm as against the drawing size of
90.470 mm to 90.515 mm (dimension checked at six locations as per table above).
10.3 Silent block outer diameter is 89.760 mm to 90.280 mm as against the drawing size of 90.525
mm to 90.550 mm. i.e. the silent block is undersize.
1
1
2
1
22
Side 1 Side 2
10.4 The silent block should be force fitted into the Anchor Link Housing. But as per Sl.No. 2 & 3
above, the fit is only clearance fit and hence the silent block is freely moving inside the housing.
10.5 The wall thickness of the anchor link pipe is not uniform and varies from 3.62 mm to 3.76 mm
as against the specified value of 4.05 to 4.50 mm as per IS:1161:98 mentioned in drawing no. T-
0-7-604, alt – j/13.
11. Conclusion:
11.1 The prime reason for the failure is the breakage of Anchor Link pipe at weld point due to lack of
fusion/ penetration. The firm M/s. Sugovri Engineering Works, Howrah had used pipe with
lesser wall thickness and failed to weld properly. The firm should have ensured correct usage of
items with proper quality control during manufacturing process.
11.2 The silent block is found undersize, which causes play between Anchor Link Housing and silent
block. This created imbalance on the other side of the Anchor Link Housing, where weld failure
happened. The firm M/s. MGM Rubber Company, Kolkata should have ensured strict quality
control of their manufacturing process.
11.3 Both the failed items are under warranty and the firms were asked to supply the items as
warranty replacement. The firms had been advised to depute their staff to GOC for joint
inspection of the failed components for further action.
Page 5 of 7
12. Corrective/ preventive actions taken:
The following corrective / preventive actions had been implemented.
Sl.
No.
Maintenance Instructions
as per CAMTECH manual
Clause
No.
Repair Practice followed
at GOC Workshops
Corrective / Preventive
Action taken
1. Replace the anchor link, if
worn or corroded. Repair
the anchor link, if found
cracked (normally at weld
joints) under magna flux
testing, by re welding after
316e (i)
Anchor
Link
Anchor Links dismantled
from POH Bogies are
100% stress relieved in
oven. Then, they are
subjected to chalk test
for welding crack.
a. Magna flux testing is
introduced now to
assess weld quality
of Anchor Link.
b. A Plug gauge has
gouging. Refit new silent
block in every POH.
The corroded/ bent/
cracked/ twisted Anchor
Links are disposed as
scrap. No repair is
undertaken in Anchor
Links. New Anchor Links
are replaced in place of
corroded/ bent/
cracked/ twisted ones.
been developed to
check the Anchor
Link Housing bore
before pressing with
silent block.
1 (a) Magna flux testing is introduced now to
assess weld quality of Anchor Link
1(b) Plug gauge has been developed to check the Anchor
Link Housing bore before pressing with silent block.
Page 6 of 7
Sl.
No.
Maintenance Instructions
as per CAMTECH manual
Clause
No.
Repair Practice followed
at GOC Workshops
Corrective / Preventive
Action taken
2. Replace the silent block, if
the rubber is perished
(indicated by fretting) or
loose in the anchor link
housing, or the silent block
pin is worn thin or loose in
silent block rubber.
It is a “Must change item”
in every POH (18 months)
as per CAMTECH/2008/
Coach-POH/1.0 issued
316e (ii)
Anchor
Link
Silent blocks are
renewed 100% during
POH. They are force
fitted in the Anchor Link
using Hydraulic press as
specified.
a. Pressure gauge has
been fitted in the
pressing machine to
observe the
pressing-on
pressure.
b. Ring gauge is made
available to check
the outer diameter
of the silent block
before pressing.
inJan-2008 by CAMTECH.
The silent block should be
force fit in the anchor link
and the silent block pin
should be slide fit in the
anchor link bracket.
Note: Corrective/ preventive action mentioned at sl. No. 1(b) & 2(b) ensures the correct
Interference for Force Fit.
Previously Pressing machine
without pressure gauge
Pressing machine with pressure gauge
after fitment
2(a) Pressure gauge has been fitted in the pressing machine to observe the pressing-on pressure
2(b) Ring gauge is made available to check the outer diameter of the silent block before pressing
********
Page 7 of 7
Ring
Gauge
inJan-2008 by CAMTECH.
The silent block should be
force fit in the anchor link
and the silent block pin
should be slide fit in the
anchor link bracket.
Note: Corrective/ preventive action mentioned at sl. No. 1(b) & 2(b) ensures the correct
Interference for Force Fit.
Previously Pressing machine
without pressure gauge
Pressing machine with pressure gauge
after fitment
2(a) Pressure gauge has been fitted in the pressing machine to observe the pressing-on pressure
2(b) Ring gauge is made available to check the outer diameter of the silent block before pressing
********
Page 7 of 7
Ring
Gauge

More Related Content

What's hot

Rex and Link-Belt Spherical Roller Bearing Units Rexnord
Rex and Link-Belt Spherical Roller Bearing Units RexnordRex and Link-Belt Spherical Roller Bearing Units Rexnord
Rex and Link-Belt Spherical Roller Bearing Units RexnordArve
 
Twi welding training_6
Twi welding training_6Twi welding training_6
Twi welding training_6Alif Elhasani
 
Orbit valves-brochure
Orbit valves-brochureOrbit valves-brochure
Orbit valves-brochureANURAG GUPTA
 
2007 toyota fj cruiser service repair manual
2007 toyota fj cruiser service repair manual2007 toyota fj cruiser service repair manual
2007 toyota fj cruiser service repair manualdfjjsjekfkskemme
 
ACM user guide
ACM user guideACM user guide
ACM user guideKei Lim
 
Toyota 02 5 fg35 forklift service repair manual
Toyota 02 5 fg35 forklift service repair manualToyota 02 5 fg35 forklift service repair manual
Toyota 02 5 fg35 forklift service repair manualfjskekdmjekm
 
Toyota 5 fd40 forklift service repair manual
Toyota 5 fd40 forklift service repair manualToyota 5 fd40 forklift service repair manual
Toyota 5 fd40 forklift service repair manualfjjskekdm
 
Toyota 5 fde35 forklift service repair manual
Toyota 5 fde35 forklift service repair manualToyota 5 fde35 forklift service repair manual
Toyota 5 fde35 forklift service repair manualfjsjekkdmnem
 
Toyota 5 fd45 forklift service repair manual
Toyota 5 fd45 forklift service repair manualToyota 5 fd45 forklift service repair manual
Toyota 5 fd45 forklift service repair manualfjskemdme
 
Toyota 5 fd33 forklift service repair manual
Toyota 5 fd33 forklift service repair manualToyota 5 fd33 forklift service repair manual
Toyota 5 fd33 forklift service repair manualfjskekmdm
 
Diagonoses gearbox-in-field
Diagonoses gearbox-in-fieldDiagonoses gearbox-in-field
Diagonoses gearbox-in-fieldmkpq pasha
 
Hyundai hl760 (#1001 #1301) wheel loader service repair manual
Hyundai hl760 (#1001 #1301) wheel loader service repair manualHyundai hl760 (#1001 #1301) wheel loader service repair manual
Hyundai hl760 (#1001 #1301) wheel loader service repair manualdfujdjkskekmmd
 
Hyundai hl757 tm 7a wheel loader service repair manual
Hyundai hl757 tm 7a wheel loader service repair manualHyundai hl757 tm 7a wheel loader service repair manual
Hyundai hl757 tm 7a wheel loader service repair manualdfujdjkskekmmd
 
Hyundai hl750 tm 3 wheel loader service repair manual
Hyundai hl750 tm 3 wheel loader service repair manualHyundai hl750 tm 3 wheel loader service repair manual
Hyundai hl750 tm 3 wheel loader service repair manualdfujdjkskekmmd
 
Hyundai hl740(tm) 7 wheel loader service repair manual
Hyundai hl740(tm) 7 wheel loader service repair manualHyundai hl740(tm) 7 wheel loader service repair manual
Hyundai hl740(tm) 7 wheel loader service repair manualdfujdjkskekmmd
 
IRJET- Analysis of Static Load Bearing Capacity of the Ball Bearing – A Review
IRJET- Analysis of Static Load Bearing Capacity of the Ball Bearing – A ReviewIRJET- Analysis of Static Load Bearing Capacity of the Ball Bearing – A Review
IRJET- Analysis of Static Load Bearing Capacity of the Ball Bearing – A ReviewIRJET Journal
 
Hyundai hl780 9 wheel loader service repair manual
Hyundai hl780 9 wheel loader service repair manualHyundai hl780 9 wheel loader service repair manual
Hyundai hl780 9 wheel loader service repair manualdfujdjkskekmmd
 

What's hot (18)

Rex and Link-Belt Spherical Roller Bearing Units Rexnord
Rex and Link-Belt Spherical Roller Bearing Units RexnordRex and Link-Belt Spherical Roller Bearing Units Rexnord
Rex and Link-Belt Spherical Roller Bearing Units Rexnord
 
Twi welding training_6
Twi welding training_6Twi welding training_6
Twi welding training_6
 
Orbit valves-brochure
Orbit valves-brochureOrbit valves-brochure
Orbit valves-brochure
 
2007 toyota fj cruiser service repair manual
2007 toyota fj cruiser service repair manual2007 toyota fj cruiser service repair manual
2007 toyota fj cruiser service repair manual
 
ACM user guide
ACM user guideACM user guide
ACM user guide
 
Toyota 02 5 fg35 forklift service repair manual
Toyota 02 5 fg35 forklift service repair manualToyota 02 5 fg35 forklift service repair manual
Toyota 02 5 fg35 forklift service repair manual
 
Toyota 5 fd40 forklift service repair manual
Toyota 5 fd40 forklift service repair manualToyota 5 fd40 forklift service repair manual
Toyota 5 fd40 forklift service repair manual
 
Toyota 5 fde35 forklift service repair manual
Toyota 5 fde35 forklift service repair manualToyota 5 fde35 forklift service repair manual
Toyota 5 fde35 forklift service repair manual
 
Toyota 5 fd45 forklift service repair manual
Toyota 5 fd45 forklift service repair manualToyota 5 fd45 forklift service repair manual
Toyota 5 fd45 forklift service repair manual
 
Toyota 5 fd33 forklift service repair manual
Toyota 5 fd33 forklift service repair manualToyota 5 fd33 forklift service repair manual
Toyota 5 fd33 forklift service repair manual
 
Diagonoses gearbox-in-field
Diagonoses gearbox-in-fieldDiagonoses gearbox-in-field
Diagonoses gearbox-in-field
 
Hyundai hl760 (#1001 #1301) wheel loader service repair manual
Hyundai hl760 (#1001 #1301) wheel loader service repair manualHyundai hl760 (#1001 #1301) wheel loader service repair manual
Hyundai hl760 (#1001 #1301) wheel loader service repair manual
 
Hyundai hl757 tm 7a wheel loader service repair manual
Hyundai hl757 tm 7a wheel loader service repair manualHyundai hl757 tm 7a wheel loader service repair manual
Hyundai hl757 tm 7a wheel loader service repair manual
 
Hyundai hl750 tm 3 wheel loader service repair manual
Hyundai hl750 tm 3 wheel loader service repair manualHyundai hl750 tm 3 wheel loader service repair manual
Hyundai hl750 tm 3 wheel loader service repair manual
 
General Extruder Audit Information
General Extruder Audit InformationGeneral Extruder Audit Information
General Extruder Audit Information
 
Hyundai hl740(tm) 7 wheel loader service repair manual
Hyundai hl740(tm) 7 wheel loader service repair manualHyundai hl740(tm) 7 wheel loader service repair manual
Hyundai hl740(tm) 7 wheel loader service repair manual
 
IRJET- Analysis of Static Load Bearing Capacity of the Ball Bearing – A Review
IRJET- Analysis of Static Load Bearing Capacity of the Ball Bearing – A ReviewIRJET- Analysis of Static Load Bearing Capacity of the Ball Bearing – A Review
IRJET- Analysis of Static Load Bearing Capacity of the Ball Bearing – A Review
 
Hyundai hl780 9 wheel loader service repair manual
Hyundai hl780 9 wheel loader service repair manualHyundai hl780 9 wheel loader service repair manual
Hyundai hl780 9 wheel loader service repair manual
 

Viewers also liked

Report writing
Report writingReport writing
Report writingICAB
 
Improvement Report-Tungsten Torch Setting
Improvement Report-Tungsten Torch SettingImprovement Report-Tungsten Torch Setting
Improvement Report-Tungsten Torch SettingScott Grewcock
 
Presentation on common weld dicontinuities
Presentation on common weld dicontinuitiesPresentation on common weld dicontinuities
Presentation on common weld dicontinuitiesabdul khaliq siddiqui
 
Guide to understanding welding procedure specification (wps
Guide to understanding welding procedure specification (wpsGuide to understanding welding procedure specification (wps
Guide to understanding welding procedure specification (wpsTonni Bruce
 
Procedure qualification
Procedure qualificationProcedure qualification
Procedure qualificationvaasuBandaru
 
REPORT WRITING:TYPES, FORMAT, STRUCTURE AND RELEVANCE
REPORT WRITING:TYPES, FORMAT, STRUCTURE AND RELEVANCEREPORT WRITING:TYPES, FORMAT, STRUCTURE AND RELEVANCE
REPORT WRITING:TYPES, FORMAT, STRUCTURE AND RELEVANCETulika Paul
 

Viewers also liked (10)

Report writing
Report writingReport writing
Report writing
 
Improvement Report-Tungsten Torch Setting
Improvement Report-Tungsten Torch SettingImprovement Report-Tungsten Torch Setting
Improvement Report-Tungsten Torch Setting
 
Stephen Kennett
Stephen KennettStephen Kennett
Stephen Kennett
 
The Case Study Method
The  Case  Study  MethodThe  Case  Study  Method
The Case Study Method
 
Presentation on common weld dicontinuities
Presentation on common weld dicontinuitiesPresentation on common weld dicontinuities
Presentation on common weld dicontinuities
 
Guide to understanding welding procedure specification (wps
Guide to understanding welding procedure specification (wpsGuide to understanding welding procedure specification (wps
Guide to understanding welding procedure specification (wps
 
Procedure qualification
Procedure qualificationProcedure qualification
Procedure qualification
 
Presentation on non destructive testing
Presentation on non destructive testingPresentation on non destructive testing
Presentation on non destructive testing
 
Welding Defects
Welding DefectsWelding Defects
Welding Defects
 
REPORT WRITING:TYPES, FORMAT, STRUCTURE AND RELEVANCE
REPORT WRITING:TYPES, FORMAT, STRUCTURE AND RELEVANCEREPORT WRITING:TYPES, FORMAT, STRUCTURE AND RELEVANCE
REPORT WRITING:TYPES, FORMAT, STRUCTURE AND RELEVANCE
 

Similar to SR ACCN 99119 Anchor Link Failure Analysis

API-653 Tank Inspection Sample Report
API-653 Tank Inspection Sample ReportAPI-653 Tank Inspection Sample Report
API-653 Tank Inspection Sample ReportAllison Thompson
 
Equipment failure - a liability or an asset? - Roger Costanzi
Equipment failure - a liability or an asset? - Roger CostanziEquipment failure - a liability or an asset? - Roger Costanzi
Equipment failure - a liability or an asset? - Roger CostanziNSW Environment and Planning
 
Report, Vibration Testing Machine-1
Report, Vibration Testing Machine-1Report, Vibration Testing Machine-1
Report, Vibration Testing Machine-1James Herriot
 
Failure Analysis of a Tongue Rail
Failure Analysis of a Tongue RailFailure Analysis of a Tongue Rail
Failure Analysis of a Tongue RailAbhilash Agnihotri
 
IRJET - Experimental Investigation of flexural member of Beam Opening in ...
IRJET -  	  Experimental Investigation of flexural member of Beam Opening in ...IRJET -  	  Experimental Investigation of flexural member of Beam Opening in ...
IRJET - Experimental Investigation of flexural member of Beam Opening in ...IRJET Journal
 
Geometric specification of bevel wrapping of double walled tubes, prediction ...
Geometric specification of bevel wrapping of double walled tubes, prediction ...Geometric specification of bevel wrapping of double walled tubes, prediction ...
Geometric specification of bevel wrapping of double walled tubes, prediction ...eSAT Journals
 
CV not functioning CA report_linkedIn
CV not functioning CA report_linkedInCV not functioning CA report_linkedIn
CV not functioning CA report_linkedInGopi nadh
 
IRJET- Behaviour of Cold Formed Steel Built-Up Columns by using Fasteners
IRJET- Behaviour of Cold Formed Steel Built-Up Columns by using FastenersIRJET- Behaviour of Cold Formed Steel Built-Up Columns by using Fasteners
IRJET- Behaviour of Cold Formed Steel Built-Up Columns by using FastenersIRJET Journal
 
Presentation "Use of coupler Splices for Reinforcement"
Presentation "Use of coupler Splices for Reinforcement"Presentation "Use of coupler Splices for Reinforcement"
Presentation "Use of coupler Splices for Reinforcement"Pralhad Kore
 
Determination of Critical Flaw Size in Gun Launched 40mm Grenade
Determination of Critical Flaw Size in Gun Launched 40mm GrenadeDetermination of Critical Flaw Size in Gun Launched 40mm Grenade
Determination of Critical Flaw Size in Gun Launched 40mm GrenadeSIMULIA
 
BOILER TUBE FAILURE ANALYSIS IN 210MW POWER PLANT STEAM BOILER
BOILER TUBE FAILURE ANALYSIS IN 210MW POWER PLANT STEAM BOILERBOILER TUBE FAILURE ANALYSIS IN 210MW POWER PLANT STEAM BOILER
BOILER TUBE FAILURE ANALYSIS IN 210MW POWER PLANT STEAM BOILERIRJET Journal
 
A checking fixture design of corrugated pieces in Clutch assembly of automobi...
A checking fixture design of corrugated pieces in Clutch assembly of automobi...A checking fixture design of corrugated pieces in Clutch assembly of automobi...
A checking fixture design of corrugated pieces in Clutch assembly of automobi...IJRES Journal
 
Optimization of tube-flange welded joints under Torsional loading
Optimization of tube-flange welded joints under Torsional loadingOptimization of tube-flange welded joints under Torsional loading
Optimization of tube-flange welded joints under Torsional loadingIRJET Journal
 
Experimental Investigation on Effect of Curtailed reinforcement in R.C beams
Experimental Investigation on Effect of Curtailed reinforcement in R.C beamsExperimental Investigation on Effect of Curtailed reinforcement in R.C beams
Experimental Investigation on Effect of Curtailed reinforcement in R.C beamsIRJET Journal
 
SafeSeals Tech Article
SafeSeals Tech ArticleSafeSeals Tech Article
SafeSeals Tech ArticleScott Chambers
 
SafeSeals Tech Article
SafeSeals Tech ArticleSafeSeals Tech Article
SafeSeals Tech ArticleScott Chambers
 

Similar to SR ACCN 99119 Anchor Link Failure Analysis (20)

API-653 Tank Inspection Sample Report
API-653 Tank Inspection Sample ReportAPI-653 Tank Inspection Sample Report
API-653 Tank Inspection Sample Report
 
Cane V2
Cane V2Cane V2
Cane V2
 
Equipment failure - a liability or an asset? - Roger Costanzi
Equipment failure - a liability or an asset? - Roger CostanziEquipment failure - a liability or an asset? - Roger Costanzi
Equipment failure - a liability or an asset? - Roger Costanzi
 
M1
M1M1
M1
 
Report, Vibration Testing Machine-1
Report, Vibration Testing Machine-1Report, Vibration Testing Machine-1
Report, Vibration Testing Machine-1
 
Failure Analysis of a Tongue Rail
Failure Analysis of a Tongue RailFailure Analysis of a Tongue Rail
Failure Analysis of a Tongue Rail
 
IRJET - Experimental Investigation of flexural member of Beam Opening in ...
IRJET -  	  Experimental Investigation of flexural member of Beam Opening in ...IRJET -  	  Experimental Investigation of flexural member of Beam Opening in ...
IRJET - Experimental Investigation of flexural member of Beam Opening in ...
 
Geometric specification of bevel wrapping of double walled tubes, prediction ...
Geometric specification of bevel wrapping of double walled tubes, prediction ...Geometric specification of bevel wrapping of double walled tubes, prediction ...
Geometric specification of bevel wrapping of double walled tubes, prediction ...
 
Ijariie1175
Ijariie1175Ijariie1175
Ijariie1175
 
CV not functioning CA report_linkedIn
CV not functioning CA report_linkedInCV not functioning CA report_linkedIn
CV not functioning CA report_linkedIn
 
IRJET- Behaviour of Cold Formed Steel Built-Up Columns by using Fasteners
IRJET- Behaviour of Cold Formed Steel Built-Up Columns by using FastenersIRJET- Behaviour of Cold Formed Steel Built-Up Columns by using Fasteners
IRJET- Behaviour of Cold Formed Steel Built-Up Columns by using Fasteners
 
Presentation "Use of coupler Splices for Reinforcement"
Presentation "Use of coupler Splices for Reinforcement"Presentation "Use of coupler Splices for Reinforcement"
Presentation "Use of coupler Splices for Reinforcement"
 
Determination of Critical Flaw Size in Gun Launched 40mm Grenade
Determination of Critical Flaw Size in Gun Launched 40mm GrenadeDetermination of Critical Flaw Size in Gun Launched 40mm Grenade
Determination of Critical Flaw Size in Gun Launched 40mm Grenade
 
BOILER TUBE FAILURE ANALYSIS IN 210MW POWER PLANT STEAM BOILER
BOILER TUBE FAILURE ANALYSIS IN 210MW POWER PLANT STEAM BOILERBOILER TUBE FAILURE ANALYSIS IN 210MW POWER PLANT STEAM BOILER
BOILER TUBE FAILURE ANALYSIS IN 210MW POWER PLANT STEAM BOILER
 
A checking fixture design of corrugated pieces in Clutch assembly of automobi...
A checking fixture design of corrugated pieces in Clutch assembly of automobi...A checking fixture design of corrugated pieces in Clutch assembly of automobi...
A checking fixture design of corrugated pieces in Clutch assembly of automobi...
 
Truline Plastic Piling Specifications 2014
Truline Plastic Piling Specifications 2014Truline Plastic Piling Specifications 2014
Truline Plastic Piling Specifications 2014
 
Optimization of tube-flange welded joints under Torsional loading
Optimization of tube-flange welded joints under Torsional loadingOptimization of tube-flange welded joints under Torsional loading
Optimization of tube-flange welded joints under Torsional loading
 
Experimental Investigation on Effect of Curtailed reinforcement in R.C beams
Experimental Investigation on Effect of Curtailed reinforcement in R.C beamsExperimental Investigation on Effect of Curtailed reinforcement in R.C beams
Experimental Investigation on Effect of Curtailed reinforcement in R.C beams
 
SafeSeals Tech Article
SafeSeals Tech ArticleSafeSeals Tech Article
SafeSeals Tech Article
 
SafeSeals Tech Article
SafeSeals Tech ArticleSafeSeals Tech Article
SafeSeals Tech Article
 

Recently uploaded

CNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of ServiceCNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of Servicegiselly40
 
A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024Results
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerThousandEyes
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsMaria Levchenko
 
Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024The Digital Insurer
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptxHampshireHUG
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024The Digital Insurer
 
Breaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountBreaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountPuma Security, LLC
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationRadu Cotescu
 
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Miguel Araújo
 
Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024The Digital Insurer
 
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc
 
Top 5 Benefits OF Using Muvi Live Paywall For Live Streams
Top 5 Benefits OF Using Muvi Live Paywall For Live StreamsTop 5 Benefits OF Using Muvi Live Paywall For Live Streams
Top 5 Benefits OF Using Muvi Live Paywall For Live StreamsRoshan Dwivedi
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...apidays
 
How to convert PDF to text with Nanonets
How to convert PDF to text with NanonetsHow to convert PDF to text with Nanonets
How to convert PDF to text with Nanonetsnaman860154
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationSafe Software
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Drew Madelung
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking MenDelhi Call girls
 
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxFactors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxKatpro Technologies
 
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...Neo4j
 

Recently uploaded (20)

CNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of ServiceCNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of Service
 
A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed texts
 
Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024
 
Breaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountBreaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path Mount
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organization
 
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
 
Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024
 
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
 
Top 5 Benefits OF Using Muvi Live Paywall For Live Streams
Top 5 Benefits OF Using Muvi Live Paywall For Live StreamsTop 5 Benefits OF Using Muvi Live Paywall For Live Streams
Top 5 Benefits OF Using Muvi Live Paywall For Live Streams
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
 
How to convert PDF to text with Nanonets
How to convert PDF to text with NanonetsHow to convert PDF to text with Nanonets
How to convert PDF to text with Nanonets
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
 
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxFactors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
 
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
 

SR ACCN 99119 Anchor Link Failure Analysis

  • 1. दिकण रेलवे SOUTHERN RAILWAY कॆ दीय कमरशालायॆ, गोलडऩराक Central Workshops, Goldenrock ितरिचरापपिलल ६००००४/ Tiruchirappalli 620004 SR ACCN 99119 Anchor Link Failure Analysis Report
  • 2. COACH FAILURE ANALYSIS REPORT 1. Failure Reported: Coach No. SR ACCN 99119 was detached en-route from train no. 12642 (NZM – CAPE, Thirukkural Express) at Vijayawada on 27.01.2015 at about 13.30 hours, due to breakage of Anchor Link in Trailing End Bogie No. RCF 032123/03 at housing end of Bogie Frame Transom and the broken portion was hanging. This was found in Rolling-in-Examination when it arrived at PF-5 of Vijayawada station and the coach was detached. The train resumed its service with a delay of about 100 minutes. 2. Detached Coach Details: Coach No : SR ACCN 99119 Coach Make RCF Date of put into service : 10.01.1999 POH : GOC – 10/11/2014 Return Date : 30.06.2016 No. of days worked : 77 days (Failure within 100 days) Primary Maintenance : NCJ on 23.01.2015 Bogie Details in coach (As per POH work diary) : RCF 032123/03 & RCF 062760/06 (Date of POH of Bogies: 27.10.2014) Owning Railway & Base Depot : S.Rly & TVC 3. Deputation of staff: The following staff had been deputed & proceeded immediately for investigation of the failure. 1. Mr. P.Sureshkumar, SSE 2. Mr. Gnanasekaran, SSE 4. Joint investigation at Site: Investigation was conducted at Vijayawada sick line on 28.01.2015 jointly by GOC team & SSE/C&W/BZA/S.C.Rly. The observations are given below. 4.1 The failed Anchor Link stripped from Bogie No. RCF 032123/03 and put new anchor link. 4.2 The NPEV end of the coach ACCN 99119 left hand side Anchor Link pipe broken on the welding joint to anchor link housing which is connected to bogie frame. 4.3 The other side of anchor link connected to bolster end. Welding joint is in good condition and silent block is in slacked condition. The broken anchor link is new with black colour paint and having sticker as “SGEW 06/13” on anchor link housing outside. 4.4 10% of breakage emanated from weld crack and pipe torn & broken. 4.5 Anchor link pin square end insertion in holding bracket on bogie end was found having shim tack welding. 4.6 Locking plate was having corner hit marks as well as Anchor Link housing was having hit marks on bottom. 4.7 Findings by the above team: 4.71 Micro play between Anchor Link housing and silent block coupled with weld defect caused shearing force and breakage. 4.72 Broken anchor link taken by GOC shop for CMT testing & warranty claim on supplier. Page 1 of 7
  • 3. 5. Photographs taken at site (BZA): 6. CMT Lab Analysis at GOC of Breakage of Anchor Link: The failed anchor link was subjected to CMT lab analysis and the nutshell of the report is given below. 6.1 Observations given in the Lab report: a) Chemical composition of the Anchor Link is conforming to the specification IS:10748/2004. b) At the transom end of anchor link, the pipe was broken from the housing along the welded area. c) Remnants of weld metal are partially available on the anchor link housing with fractured piece of the pipe. d) At the bolster end side, the silent block is freely moving inside the housing. e) The wall thickness of the anchor link pipe is not uniform and varies from 3.62 mm to 3.76 mm as against the specified value of 4.05 to 4.50 mm as per IS:1161:98 mentioned in drawing no. T-0-7- 604, alt – j/13. f) About 21% of the circumferential welded area along the housing suffers from lack of fusion/ penetration. g) The macro examination of fractured surface of the pipe reveals 25% of the area having voids characteristic of sudden brittle fracture and the remaining 75% is having formation of shearing lips characteristic of ductile fracture involving high torsion stresses. 6.2 CMT Lab Report - Conclusion: a) The wall thickness of the anchor link pipe is not uniform and varies from 3.62mm to 3.76mm as against 4.05mm (4.5mm minus 10% tolerance) specified for Heavy grade mentioned in the specification IS: 1161/98 referred in the drawing no. T-0-7-604, alt – j/13. b) Lack of fusion/Penetration of the weld metal with the anchor link pipe along the periphery of the housing (around 21 %.). It is leading to loss of strength of the weld. c) The molten metal sputtering near the weldment affecting the region near the weld cast has acted as an initiation site for the process of failure to occur. d) The play between the anchor link housing and the coupled silent block on the bolster side has created an imbalance on the other side of the anchor housing at the transom end. Page 2 of 7 Broken tube hanging
  • 4. 7. Dimensional Check of the failed components: Anchor Link Housing Bore Silent Block Inner Diameter of Anchor Link Housing supplied by M/s. Sugovri Engineering Works, Howrah Silent Block (Outer Diameter) supplied by M/s. MGM Rubber Co. Kolkata Interference Sample Drawing Size (mm) Side Actual (mm) Sample Drawing Size (mm) Side Actual (mm) As per Drawing Actual І 90.470 to 90.515 1 1 90.520 І 90.525 to 90.550 1 1 90.260 0.01 to 0.08 0.210 to 0.760 (Clearance fit) 2 90.490 2 90.280 3 90.510 3 90.280 1 90.520 1 89.760 2 90.460 2 90.140 3 90.450 3 90.130 Note: From the above table, the fit is only clearance fit and as against the force fit. Hence the silent block is freely moving inside the housing. 90.520 90.490 90.51090.450 90.460 90.520 90.280 90.280 90.260 90.130 90.140 89.760
  • 5. Anchor Link pipe: Thickness of Anchor Link pipe supplied by M/s. Sugovri Engineering Works, Howrah Sample Drawing Size Thicknes s (mm) Side Location Actual Thickness (mm) 1 4.05 mm to 4.50 mm 1 1 3.660 2 3.620 3 3.640 4 3.680 5 3.700 6 3.760 7 3.720 8 3.740 Page 3 of 7 8. Traceability of failed components: 8.1 Anchor Link: The failed anchor link was a new one as per the sticker “SGEW 06/13” available on the anchor link housing. The procurement details of the item is given below. Sl. No. Supplier Name P.O.No. Supplied Qty. (Nos.) Received Date Inspected by 1. M/s. Sugouri Engineering Works, Howrah 04.12.0161.1.01521 dated 27.05.2013 886 24.09.201 3 RITES 8.2 Silent Block: The stamping of manufacturer details on the silent block indicates “MGM 06/14”. The procurement details is given below. Sl. No. Supplier Name P.O.No. Supplied Qty. (Nos.) Received Date Inspected by 1. M/s. MGM Rubber Company, Kolkata 04.13.0160.1.04425 dated 10.02.2014 2500 19.07.2014 RDSO 9. Preventive check on the items available at GOC belonging to the same consignment: 3.660 3.740 3.680 3.720 3.760 3.640 3.620 3.700
  • 6. Anchor Link Silent Block Inner Diameter of Anchor Link Housing supplied by M/s. Sugovri Engineering Works, Howrah Silent Block (Outer Diameter) supplied by M/s. MGM Rubber Co. Kolkata Interference Sample Drawing Size (mm) Side Actual (mm) Sample Drawing Size (mm) Side Actual (mm) As per Drawing Actual I 90.470 to 90.515 1 1 90.400 I 90.525 to 90.550 1 90.526 0.01 to 0.08 0.020 to 0.200 2 90.440 2 1 90.510 2 90.602 2 90.510 II 1 1 90.430 II 1 90.602 2 90.510 2 1 90.480 2 90.551 2 90.510 Note: As per the tabulation given above, both the items are confirming to the drawing dimensions. Page 4 of 7 10. Failure analysis based on the available evidences –Lab Report, dimensional check, photographs and joint observation by SSEs/GOC & SSE/BZA: 10.1 Based on the identity on the failed components both Anchor Link and Silent Block were newly fitted during POH. 10.2 Anchor Link housing bore diameter is 90.450 mm to 90.520 mm as against the drawing size of 90.470 mm to 90.515 mm (dimension checked at six locations as per table above). 10.3 Silent block outer diameter is 89.760 mm to 90.280 mm as against the drawing size of 90.525 mm to 90.550 mm. i.e. the silent block is undersize. 1 1 2 1 22 Side 1 Side 2
  • 7. 10.4 The silent block should be force fitted into the Anchor Link Housing. But as per Sl.No. 2 & 3 above, the fit is only clearance fit and hence the silent block is freely moving inside the housing. 10.5 The wall thickness of the anchor link pipe is not uniform and varies from 3.62 mm to 3.76 mm as against the specified value of 4.05 to 4.50 mm as per IS:1161:98 mentioned in drawing no. T- 0-7-604, alt – j/13. 11. Conclusion: 11.1 The prime reason for the failure is the breakage of Anchor Link pipe at weld point due to lack of fusion/ penetration. The firm M/s. Sugovri Engineering Works, Howrah had used pipe with lesser wall thickness and failed to weld properly. The firm should have ensured correct usage of items with proper quality control during manufacturing process. 11.2 The silent block is found undersize, which causes play between Anchor Link Housing and silent block. This created imbalance on the other side of the Anchor Link Housing, where weld failure happened. The firm M/s. MGM Rubber Company, Kolkata should have ensured strict quality control of their manufacturing process. 11.3 Both the failed items are under warranty and the firms were asked to supply the items as warranty replacement. The firms had been advised to depute their staff to GOC for joint inspection of the failed components for further action. Page 5 of 7 12. Corrective/ preventive actions taken: The following corrective / preventive actions had been implemented. Sl. No. Maintenance Instructions as per CAMTECH manual Clause No. Repair Practice followed at GOC Workshops Corrective / Preventive Action taken 1. Replace the anchor link, if worn or corroded. Repair the anchor link, if found cracked (normally at weld joints) under magna flux testing, by re welding after 316e (i) Anchor Link Anchor Links dismantled from POH Bogies are 100% stress relieved in oven. Then, they are subjected to chalk test for welding crack. a. Magna flux testing is introduced now to assess weld quality of Anchor Link. b. A Plug gauge has
  • 8. gouging. Refit new silent block in every POH. The corroded/ bent/ cracked/ twisted Anchor Links are disposed as scrap. No repair is undertaken in Anchor Links. New Anchor Links are replaced in place of corroded/ bent/ cracked/ twisted ones. been developed to check the Anchor Link Housing bore before pressing with silent block. 1 (a) Magna flux testing is introduced now to assess weld quality of Anchor Link 1(b) Plug gauge has been developed to check the Anchor Link Housing bore before pressing with silent block. Page 6 of 7 Sl. No. Maintenance Instructions as per CAMTECH manual Clause No. Repair Practice followed at GOC Workshops Corrective / Preventive Action taken 2. Replace the silent block, if the rubber is perished (indicated by fretting) or loose in the anchor link housing, or the silent block pin is worn thin or loose in silent block rubber. It is a “Must change item” in every POH (18 months) as per CAMTECH/2008/ Coach-POH/1.0 issued 316e (ii) Anchor Link Silent blocks are renewed 100% during POH. They are force fitted in the Anchor Link using Hydraulic press as specified. a. Pressure gauge has been fitted in the pressing machine to observe the pressing-on pressure. b. Ring gauge is made available to check the outer diameter of the silent block before pressing.
  • 9. inJan-2008 by CAMTECH. The silent block should be force fit in the anchor link and the silent block pin should be slide fit in the anchor link bracket. Note: Corrective/ preventive action mentioned at sl. No. 1(b) & 2(b) ensures the correct Interference for Force Fit. Previously Pressing machine without pressure gauge Pressing machine with pressure gauge after fitment 2(a) Pressure gauge has been fitted in the pressing machine to observe the pressing-on pressure 2(b) Ring gauge is made available to check the outer diameter of the silent block before pressing ******** Page 7 of 7 Ring Gauge
  • 10. inJan-2008 by CAMTECH. The silent block should be force fit in the anchor link and the silent block pin should be slide fit in the anchor link bracket. Note: Corrective/ preventive action mentioned at sl. No. 1(b) & 2(b) ensures the correct Interference for Force Fit. Previously Pressing machine without pressure gauge Pressing machine with pressure gauge after fitment 2(a) Pressure gauge has been fitted in the pressing machine to observe the pressing-on pressure 2(b) Ring gauge is made available to check the outer diameter of the silent block before pressing ******** Page 7 of 7 Ring Gauge