Publicité

Servjit Aulak CV 2016.msg

10 Apr 2016
Servjit Aulak CV 2016.msg
Servjit Aulak CV 2016.msg
Servjit Aulak CV 2016.msg
Prochain SlideShare
Clayton Berkemeier Mining ResumeClayton Berkemeier Mining Resume
Chargement dans ... 3
1 sur 3
Publicité

Contenu connexe

Publicité

Servjit Aulak CV 2016.msg

  1. Servjit Aulak Foundations | Infrastructure | Environment Page 1 of 3 Superintendent Qualifications CSCS Civil Engineering Site Supervisor Other Training Workingat Heights Workplace FirstAid RiggingandSlinging Level 1 STMS Crane Co-Ordinator/ Appointed Person Temporary Works Supervisors (5 day course) I ama very skilled individual with many yearsin and around the civil construction industry.I have worked on a variety of projects such asroads, bridges, cofferdams and building works, always giving 100% to my role at all times. I have high levels of personal drive and commitment. Effective goal setting for self and others. With a successful track record of building and maintaining skilled teams. I pride myself on achieving excellent safety standardsand work well within a team. I amalso persistent and tenacious when faced with difficulties. Employment Record July 14 – Present Superintendent Brian Perry Civil Jan 14 – Jun 14 Construction Manager Trans-Tasman Civil May 12 – Apr13 General foreman Skanska Apr09 – May 12 General foreman Skanska Aug 08 – Apr09 Foreman Morgan Vinci Jul 06 – Aug 08 General Foreman Morgan Vinci Sep 05 – Jun 06 Foreman Atkinson Formwork May 03 –Sept 05 Section foreman Tunnelcraft Apr98 – Mar 02 Foreman O’Rourke’sand DLR Relevant Experience Project: NgaurangatoAotea Quay Date: July2014 – till Present Position: Superintendent Manageall sub-contractorson siteHigginsthe paving and drainage,also all works Manageourcrewwith piling, gantry bases,gantry erection on wholeproject. Manage ITS work activities, slip formed barriers, pre-cast barriers, drainage and street lights installation workon whole project. Advanced workplanning withconstruction managerand projectengineer. Daily managementof TMon site and staff and sub-contractors. Weekly planning and organising and achieving criticalmile stone
  2. Servjit Aulak Foundations | Infrastructure | Environment Page 2 of 3 Project: CharterisBay CV$ 3m Date: January2014 – June 2014 Position: Construction Manager Monitoring,executing and supervision of civilengineering works. Leads and manages appropriate resources for projectsand resolves issues of availability and performance as required Proactively identify and maintain strategicclient and sub-contractors relationship Identify assessand managethehazardsand riskassociated with projectactivities Safetymanagement,costcontroland purchasing Project: Crossrail PaddingtonStation CV250million pounds Date: May 2012 – April 2013 Position: General Foreman Overseesite workson C405 Crossrail project Contract involves the installation of a box measuring 260m long x25m wide and 23m deep. Consisting of diaphragmwall,plungecolumns,sheetpiling and RC installation. Relocation of utilityservicesand ensureallworksarecompleted withoutdamaging theGradeIIlisted façade of the station EnsureHealth and Safetyproceduresarefollowed.Winnerof gold award atRoSPAs2012 Excavating of 8000m3 and 16000m3 of clay Façadeof t he Project: M25 WideningJ16 to J23 CV 590 millionpounds Date: April 2009 – May 2012 Position: General Foreman Managea direct labourteamof approximately 16operativealong with numeroussub-contractors Managing the directional drilling operations, access steps to cabinets, blockwork and paving, technology installation worksincluding ducting installation and cabling installation. Gantry piling operations, gantry erection, street lighting installation and directional signage installation. Completion of grouting to gantry legsand protection worksto in-road detection loops Managesitelogistics for related section Project: M1 WideningJ25 to J28- Bridges 474, 475, 482 CV336millionPounds Date: August2008 – April 2009 Position: General Foreman Managesub-contractteamsin theconstruction of 5 numberroad bridges Installation of pre-castbeamsection 75ton craned into place Ensureworkwasundertaken in a safemannerand according to schedule Managesitelogistics for related section Project: KincardineBridge contract value120million pounds Date: July2006 – August2008 Position: General Foreman ManageCemetation forpiling works (1,000 piles installed) Management of work force 80 to 100 operative, consisting of carpenter ,steel fixers, general operatives, welders,scaffolders,engineersand pre-stressing Managesitelogistics for related section 1.2 Kilometrelong push launch,a triple cell systemof 40,000 ton of concreteand steel and 16.5metres wide
  3. Servjit Aulak Foundations | Infrastructure | Environment Page 3 of 3 Project: CliveAtkinsonFormwork CV 250k to 5m pounds Date: September2005 – June 2006 Position: Foreman Foreman on an improvementand extension of a watertreatmentplant Involved installing pumping station to chambers,circulartanksand diversion works Managesitelogistics and H&S for related section Project: Channel Tunnel Rail Link 310 RainhamCrossover Date: May 2003 -September2005 Position: Section Foreman Set up initial precastyard for fabrication 2.5x5m RC interlocking panels for retaining walls and RC capping beamforbridge at Botany Way Constructing thepierswith steel girders and RC slab for crossoverand box section over live railway line Manageearthworksstageand finishing worksto thebridgeinstallation Projectincluded:11.4km of track and 520m long viaductconstruction Project: Bluewater ShoppingCentre, DocklandLightRailway andMedway Viaduct CTRL 350/410 Date: April 1998 – March 2002 Position: Foreman
Publicité