SlideShare a Scribd company logo
1 of 11
Guidelines for Competitive
Procurement of Power
Compiled by
Shreekant Dhuri
Electricity Act 2003
Preamble
• An Act to consolidate the laws relating to generation,
transmission, distribution, trading and use of
electricity and generally for taking measures
conducive to development of electricity industry,
promoting competition therein, protecting interest of
consumers and supply of electricity to all areas,
rationalization of electricity tariff, ensuring
transparent policies regarding subsidies, promotion
of efficient and environmentally benign policies,
constitution of Central Electricity Authority,
Regulatory Commissions and establishment of
Appellate Tribunal and for matters connected
therewith or incidental thereto.
Relevant Sections
Section 61 & 62:
Provide for tariff
regulation and
determination of tariff
of generation,
transmission, wheeling
and retail sale of
electricity by the
Appropriate
Commission.
Section 63:
Notwithstanding
anything contained in
section 62, the
Appropriate
Commission shall adopt
the tariff if such tariff
has been determined
through transparent
process of bidding in
accordance with the
guidelines issued by the
Central Government.
Objectives
Promote competitive
procurement of electricity
by distribution licensees
Facilitate transparency and
fairness in procurement
processes
Facilitate reduction of
information asymmetries
for various bidders
Protect consumer interests
by facilitating competitive
conditions in procurement
of electricity
Enhance standardization
and reduce ambiguity and
hence time for
materialization of projects
Provide flexibility to
suppliers on internal
operations while ensuring
certainty on availability of
power and tariffs for buyers
Tariff Policy 2006
Provides uniform guidelines to
SERCs for fixation of tariffs for
their respective entities as well as
CERC
Competitive Bidding: Distribution
licensee to procure power solely
through competitive bidding but
central & state owned units were
exempted. Tariff for public sector
projects to be decided through
bidding after a period of 5 years.
Scope
Period of Procurement
Long term
> 7 Years
Medium
term
1 to 7
Years
Procurementavailablefor
Base Load
Peak Load
Seasonal Power
Bidding Mechanisms
Case 1
• Location, Technology & Fuel
not specified by procurer.
• Bidder responsible for
clearances/ approvals etc.
• More relevant for States with
limited fuel sources
• Higher risk for developer
• Lower risk for state
Case 2
• For Hydro power projects, load
center projects or other
location specific projects with
specific fuel allocation such as
captive mines available, which
the procurer intends to setup
under tariff based bidding
process.
• Land/ Fuel provided by
Procurer
• More applicable for States
where fuel sources are
available or having coastal
areas
• Higher risk for State
• Lower risk for developer
Additional
• Procurement by more than
one distribution licensee
through a combined bid
process permitted through
authorized representative.
• In case distribution licensees
are located in more than one
State, CERC shall be the
Appropriate Commission
Preparation for Bid Invitation
Bid documentation
Approval of the
Appropriate
Commission in case
of deviations
Approval of the
Appropriate Commission –
a) quantum of capacity /
energy
b) transfer price of fuel
Project preparatory
activities
completion
Obtaining the
transmission
clearances
PPA and other
required project
agreements
Project
preparatory
activities
Site identification and land acquisition
Environmental clearance for the power
station
Forest Clearance
Fuel Arrangements
Water linkage
Requisite Hydrological, geological,
meteorological and seismological data
Tariff Structure
Medium Term
Long Term
One Part Tariff
Two Part Tariff
Capacity Charge Energy Charge
Non Escalable
(Firm Price)
Escalable
(Base Price
with Index)
Base Price (with
Index)
NQHR
Index notified by CERC
Optional
Bidding Process
Bid
Process
Two stage process for
Long term procurement:
Request for Qualification
(RFQ)
Request for Proposal
(RFP)
The bidding shall be
necessarily by way of
International
Competitive Bidding
(ICB).
For Medium term
the procurer has an
option to adopt a
single stage tender
process combining
the RFP & RFQ
process.
Bidding Process
Preparation of bid
documents and
technical analysis
done by procurer
RFQ invited and
qualified bidders
selected
Creates a common
platform and
removes
conditionality.
Doubt clearance
and feedback
Technical and
financial bids
evaluated
LOI issued PPA
signed
Timetable for Bidding Process
Event Elapsed Time from
Zero Date
Publication of RFQ Zero Date
Submission of responses of RFQ 60 days
Shortlisting based on responses &
issuances of RFQ
90 days
Bid clarification, conferences, etc. 150 days
Final clarification and revision of RFP 180 days
Technical and Price bid submission 360 days
Shortlisting of Bidder and issue of LOI 390 days
Signing of agreements 425 days
Event Elapsed Time from
Zero Date
Publication of RFQ Zero Date
Bid clarification,
conferences, etc.
90 days
Technical and Price bid
submission
180 days
Shortlisting of Bidder
and issue of LOI
210 days
Signing of agreements 240 days
(Single Stage Bid Process)
(Two Stage Bid Process)

More Related Content

What's hot

Aemo victoria to new south wales interconnector upgrade rit t padr 2019
Aemo victoria to new south wales interconnector upgrade rit t padr 2019Aemo victoria to new south wales interconnector upgrade rit t padr 2019
Aemo victoria to new south wales interconnector upgrade rit t padr 2019
Power System Operation
 
energy future holindings texas
energy future holindings texasenergy future holindings texas
energy future holindings texas
finance29
 
4 3-mcit-spectrum-rules-annex-c-3-spectrum-fees-11113
4 3-mcit-spectrum-rules-annex-c-3-spectrum-fees-111134 3-mcit-spectrum-rules-annex-c-3-spectrum-fees-11113
4 3-mcit-spectrum-rules-annex-c-3-spectrum-fees-11113
Fahim Ullah Shagiwal
 

What's hot (16)

Feasibility of Solar Project with Open Access in Maharashtra
Feasibility of Solar Project with Open Access in Maharashtra Feasibility of Solar Project with Open Access in Maharashtra
Feasibility of Solar Project with Open Access in Maharashtra
 
New Entrants in Electric Generation in Tennessee Valley
New Entrants in Electric Generation in Tennessee ValleyNew Entrants in Electric Generation in Tennessee Valley
New Entrants in Electric Generation in Tennessee Valley
 
Captive gen
Captive genCaptive gen
Captive gen
 
Group captive mechanism
Group captive mechanismGroup captive mechanism
Group captive mechanism
 
Tariff structure & Cerc tariff regulation
Tariff structure & Cerc tariff regulationTariff structure & Cerc tariff regulation
Tariff structure & Cerc tariff regulation
 
Uperc draft regulation on dsm
Uperc draft regulation on dsmUperc draft regulation on dsm
Uperc draft regulation on dsm
 
Aemo victoria to new south wales interconnector upgrade rit t padr 2019
Aemo victoria to new south wales interconnector upgrade rit t padr 2019Aemo victoria to new south wales interconnector upgrade rit t padr 2019
Aemo victoria to new south wales interconnector upgrade rit t padr 2019
 
Tariff information Himachal Pradesh and Jammu & Kashmir
Tariff information  Himachal Pradesh and Jammu & KashmirTariff information  Himachal Pradesh and Jammu & Kashmir
Tariff information Himachal Pradesh and Jammu & Kashmir
 
Open access charges chhattisgarh
Open access charges chhattisgarhOpen access charges chhattisgarh
Open access charges chhattisgarh
 
energy future holindings texas
energy future holindings texasenergy future holindings texas
energy future holindings texas
 
4 3-mcit-spectrum-rules-annex-c-3-spectrum-fees-11113
4 3-mcit-spectrum-rules-annex-c-3-spectrum-fees-111134 3-mcit-spectrum-rules-annex-c-3-spectrum-fees-11113
4 3-mcit-spectrum-rules-annex-c-3-spectrum-fees-11113
 
Urjanet's Guide to Utility Tariffs
Urjanet's Guide to Utility TariffsUrjanet's Guide to Utility Tariffs
Urjanet's Guide to Utility Tariffs
 
Power Market regulation
Power Market regulationPower Market regulation
Power Market regulation
 
Overview of Variable Renewable Energy Regulatory Issues
Overview of Variable Renewable Energy Regulatory IssuesOverview of Variable Renewable Energy Regulatory Issues
Overview of Variable Renewable Energy Regulatory Issues
 
Elec act
Elec actElec act
Elec act
 
Day-3, Mr. Ajay raj
Day-3, Mr. Ajay rajDay-3, Mr. Ajay raj
Day-3, Mr. Ajay raj
 

Similar to Power Procurement Guidelines in India

Competitive Selection and Support for Renewable Energy
Competitive Selection and Support for Renewable EnergyCompetitive Selection and Support for Renewable Energy
Competitive Selection and Support for Renewable Energy
energydialog
 
K a-sivaram-chitale-policy-framework-for-transmission-distribution
K a-sivaram-chitale-policy-framework-for-transmission-distributionK a-sivaram-chitale-policy-framework-for-transmission-distribution
K a-sivaram-chitale-policy-framework-for-transmission-distribution
srinivasdeepak
 
Umpp(ultra mega power plant and international bidding )
Umpp(ultra mega power plant and international bidding )Umpp(ultra mega power plant and international bidding )
Umpp(ultra mega power plant and international bidding )
Gurparvesh kaur
 
Esci rec presentation 13 feb 2013
Esci rec presentation   13 feb 2013Esci rec presentation   13 feb 2013
Esci rec presentation 13 feb 2013
Sandeep Melana
 
Solar power projects under rec mechanism in india
Solar power projects under rec mechanism in indiaSolar power projects under rec mechanism in india
Solar power projects under rec mechanism in india
Bhargav Parmar
 

Similar to Power Procurement Guidelines in India (20)

Day-3, Mr. Vimal Kirti Singh, IAS
Day-3, Mr. Vimal Kirti Singh, IASDay-3, Mr. Vimal Kirti Singh, IAS
Day-3, Mr. Vimal Kirti Singh, IAS
 
VENTURES_NPTI-EE_ACT_ESCO&DSM.ppt presentation
VENTURES_NPTI-EE_ACT_ESCO&DSM.ppt presentationVENTURES_NPTI-EE_ACT_ESCO&DSM.ppt presentation
VENTURES_NPTI-EE_ACT_ESCO&DSM.ppt presentation
 
Competitive Selection and Support for Renewable Energy
Competitive Selection and Support for Renewable EnergyCompetitive Selection and Support for Renewable Energy
Competitive Selection and Support for Renewable Energy
 
brief policies.pptx
brief policies.pptxbrief policies.pptx
brief policies.pptx
 
Distribution In India for better understanding.pptx
Distribution In India for better understanding.pptxDistribution In India for better understanding.pptx
Distribution In India for better understanding.pptx
 
TBCB_29032019.pptx
TBCB_29032019.pptxTBCB_29032019.pptx
TBCB_29032019.pptx
 
K a-sivaram-chitale-policy-framework-for-transmission-distribution
K a-sivaram-chitale-policy-framework-for-transmission-distributionK a-sivaram-chitale-policy-framework-for-transmission-distribution
K a-sivaram-chitale-policy-framework-for-transmission-distribution
 
Day-3, Mr. SC Shrivastav connectivity MTOA & lTA and concept of GNA
Day-3, Mr. SC Shrivastav connectivity MTOA & lTA and concept of GNADay-3, Mr. SC Shrivastav connectivity MTOA & lTA and concept of GNA
Day-3, Mr. SC Shrivastav connectivity MTOA & lTA and concept of GNA
 
Umpp(ultra mega power plant and international bidding )
Umpp(ultra mega power plant and international bidding )Umpp(ultra mega power plant and international bidding )
Umpp(ultra mega power plant and international bidding )
 
Connexting Renewables & The Power Purchase Agreement - Tim Foster (Smartest ...
Connexting Renewables & The Power Purchase Agreement  - Tim Foster (Smartest ...Connexting Renewables & The Power Purchase Agreement  - Tim Foster (Smartest ...
Connexting Renewables & The Power Purchase Agreement - Tim Foster (Smartest ...
 
Renewable energy
Renewable energyRenewable energy
Renewable energy
 
Esci rec presentation 13 feb 2013
Esci rec presentation   13 feb 2013Esci rec presentation   13 feb 2013
Esci rec presentation 13 feb 2013
 
Electricity policies
Electricity policiesElectricity policies
Electricity policies
 
Competitive metering in the National Electricity Market
Competitive metering in the National Electricity MarketCompetitive metering in the National Electricity Market
Competitive metering in the National Electricity Market
 
Competitive metering in the National Electricity Market
Competitive metering in the National Electricity MarketCompetitive metering in the National Electricity Market
Competitive metering in the National Electricity Market
 
Solar power projects under rec mechanism in india
Solar power projects under rec mechanism in indiaSolar power projects under rec mechanism in india
Solar power projects under rec mechanism in india
 
SmartestEnergy: Introduction to the Electricity Market
SmartestEnergy: Introduction to the Electricity MarketSmartestEnergy: Introduction to the Electricity Market
SmartestEnergy: Introduction to the Electricity Market
 
SmartestEnergy: Introduction to the Electricity Market
SmartestEnergy: Introduction to the Electricity MarketSmartestEnergy: Introduction to the Electricity Market
SmartestEnergy: Introduction to the Electricity Market
 
Draft Feed-In Tariffs
Draft Feed-In TariffsDraft Feed-In Tariffs
Draft Feed-In Tariffs
 
The future of energy procurement - Magnus Walker at PfH Live 2015
The future of energy procurement - Magnus Walker at PfH Live 2015The future of energy procurement - Magnus Walker at PfH Live 2015
The future of energy procurement - Magnus Walker at PfH Live 2015
 

Recently uploaded

一比一原版(OhioStateU毕业证书)美国俄亥俄州立大学毕业证如何办理
一比一原版(OhioStateU毕业证书)美国俄亥俄州立大学毕业证如何办理一比一原版(OhioStateU毕业证书)美国俄亥俄州立大学毕业证如何办理
一比一原版(OhioStateU毕业证书)美国俄亥俄州立大学毕业证如何办理
e9733fc35af6
 
买(rice毕业证书)莱斯大学毕业证本科文凭证书原版质量
买(rice毕业证书)莱斯大学毕业证本科文凭证书原版质量买(rice毕业证书)莱斯大学毕业证本科文凭证书原版质量
买(rice毕业证书)莱斯大学毕业证本科文凭证书原版质量
acyefsa
 
一比一原版(UWA毕业证书)西澳大学毕业证如何办理
一比一原版(UWA毕业证书)西澳大学毕业证如何办理一比一原版(UWA毕业证书)西澳大学毕业证如何办理
一比一原版(UWA毕业证书)西澳大学毕业证如何办理
bd2c5966a56d
 
一比一原版(MelbourneU毕业证书)墨尔本大学毕业证学位证书
一比一原版(MelbourneU毕业证书)墨尔本大学毕业证学位证书一比一原版(MelbourneU毕业证书)墨尔本大学毕业证学位证书
一比一原版(MelbourneU毕业证书)墨尔本大学毕业证学位证书
irst
 
一比一原版(UM毕业证书)密苏里大学毕业证如何办理
一比一原版(UM毕业证书)密苏里大学毕业证如何办理一比一原版(UM毕业证书)密苏里大学毕业证如何办理
一比一原版(UM毕业证书)密苏里大学毕业证如何办理
F La
 
一比一原版(Warwick毕业证书)华威大学毕业证如何办理
一比一原版(Warwick毕业证书)华威大学毕业证如何办理一比一原版(Warwick毕业证书)华威大学毕业证如何办理
一比一原版(Warwick毕业证书)华威大学毕业证如何办理
Fir La
 
ASMA JILANI EXPLAINED CASE PLD 1972 FOR CSS
ASMA JILANI EXPLAINED CASE PLD 1972 FOR CSSASMA JILANI EXPLAINED CASE PLD 1972 FOR CSS
ASMA JILANI EXPLAINED CASE PLD 1972 FOR CSS
CssSpamx
 
一比一原版伦敦南岸大学毕业证如何办理
一比一原版伦敦南岸大学毕业证如何办理一比一原版伦敦南岸大学毕业证如何办理
一比一原版伦敦南岸大学毕业证如何办理
Airst S
 
一比一原版(CQU毕业证书)中央昆士兰大学毕业证如何办理
一比一原版(CQU毕业证书)中央昆士兰大学毕业证如何办理一比一原版(CQU毕业证书)中央昆士兰大学毕业证如何办理
一比一原版(CQU毕业证书)中央昆士兰大学毕业证如何办理
Airst S
 
一比一原版(Griffith毕业证书)格里菲斯大学毕业证如何办理
一比一原版(Griffith毕业证书)格里菲斯大学毕业证如何办理一比一原版(Griffith毕业证书)格里菲斯大学毕业证如何办理
一比一原版(Griffith毕业证书)格里菲斯大学毕业证如何办理
bd2c5966a56d
 
一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理
一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理
一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理
Airst S
 

Recently uploaded (20)

A SHORT HISTORY OF LIBERTY'S PROGREE THROUGH HE EIGHTEENTH CENTURY
A SHORT HISTORY OF LIBERTY'S PROGREE THROUGH HE EIGHTEENTH CENTURYA SHORT HISTORY OF LIBERTY'S PROGREE THROUGH HE EIGHTEENTH CENTURY
A SHORT HISTORY OF LIBERTY'S PROGREE THROUGH HE EIGHTEENTH CENTURY
 
一比一原版(OhioStateU毕业证书)美国俄亥俄州立大学毕业证如何办理
一比一原版(OhioStateU毕业证书)美国俄亥俄州立大学毕业证如何办理一比一原版(OhioStateU毕业证书)美国俄亥俄州立大学毕业证如何办理
一比一原版(OhioStateU毕业证书)美国俄亥俄州立大学毕业证如何办理
 
买(rice毕业证书)莱斯大学毕业证本科文凭证书原版质量
买(rice毕业证书)莱斯大学毕业证本科文凭证书原版质量买(rice毕业证书)莱斯大学毕业证本科文凭证书原版质量
买(rice毕业证书)莱斯大学毕业证本科文凭证书原版质量
 
一比一原版(UWA毕业证书)西澳大学毕业证如何办理
一比一原版(UWA毕业证书)西澳大学毕业证如何办理一比一原版(UWA毕业证书)西澳大学毕业证如何办理
一比一原版(UWA毕业证书)西澳大学毕业证如何办理
 
一比一原版(MelbourneU毕业证书)墨尔本大学毕业证学位证书
一比一原版(MelbourneU毕业证书)墨尔本大学毕业证学位证书一比一原版(MelbourneU毕业证书)墨尔本大学毕业证学位证书
一比一原版(MelbourneU毕业证书)墨尔本大学毕业证学位证书
 
一比一原版(UM毕业证书)密苏里大学毕业证如何办理
一比一原版(UM毕业证书)密苏里大学毕业证如何办理一比一原版(UM毕业证书)密苏里大学毕业证如何办理
一比一原版(UM毕业证书)密苏里大学毕业证如何办理
 
一比一原版(Warwick毕业证书)华威大学毕业证如何办理
一比一原版(Warwick毕业证书)华威大学毕业证如何办理一比一原版(Warwick毕业证书)华威大学毕业证如何办理
一比一原版(Warwick毕业证书)华威大学毕业证如何办理
 
judicial remedies against administrative actions.pptx
judicial remedies against administrative actions.pptxjudicial remedies against administrative actions.pptx
judicial remedies against administrative actions.pptx
 
ASMA JILANI EXPLAINED CASE PLD 1972 FOR CSS
ASMA JILANI EXPLAINED CASE PLD 1972 FOR CSSASMA JILANI EXPLAINED CASE PLD 1972 FOR CSS
ASMA JILANI EXPLAINED CASE PLD 1972 FOR CSS
 
一比一原版伦敦南岸大学毕业证如何办理
一比一原版伦敦南岸大学毕业证如何办理一比一原版伦敦南岸大学毕业证如何办理
一比一原版伦敦南岸大学毕业证如何办理
 
Reason Behind the Success of Law Firms in India
Reason Behind the Success of Law Firms in IndiaReason Behind the Success of Law Firms in India
Reason Behind the Success of Law Firms in India
 
一比一原版(CQU毕业证书)中央昆士兰大学毕业证如何办理
一比一原版(CQU毕业证书)中央昆士兰大学毕业证如何办理一比一原版(CQU毕业证书)中央昆士兰大学毕业证如何办理
一比一原版(CQU毕业证书)中央昆士兰大学毕业证如何办理
 
一比一原版(Griffith毕业证书)格里菲斯大学毕业证如何办理
一比一原版(Griffith毕业证书)格里菲斯大学毕业证如何办理一比一原版(Griffith毕业证书)格里菲斯大学毕业证如何办理
一比一原版(Griffith毕业证书)格里菲斯大学毕业证如何办理
 
Hely-Hutchinson v. Brayhead Ltd .pdf
Hely-Hutchinson v. Brayhead Ltd         .pdfHely-Hutchinson v. Brayhead Ltd         .pdf
Hely-Hutchinson v. Brayhead Ltd .pdf
 
Cyber Laws : National and International Perspective.
Cyber Laws : National and International Perspective.Cyber Laws : National and International Perspective.
Cyber Laws : National and International Perspective.
 
Shubh_Burden of proof_Indian Evidence Act.pptx
Shubh_Burden of proof_Indian Evidence Act.pptxShubh_Burden of proof_Indian Evidence Act.pptx
Shubh_Burden of proof_Indian Evidence Act.pptx
 
一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理
一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理
一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理
 
Sangyun Lee, Duplicate Powers in the Criminal Referral Process and the Overla...
Sangyun Lee, Duplicate Powers in the Criminal Referral Process and the Overla...Sangyun Lee, Duplicate Powers in the Criminal Referral Process and the Overla...
Sangyun Lee, Duplicate Powers in the Criminal Referral Process and the Overla...
 
Career As Legal Reporters for Law Students
Career As Legal Reporters for Law StudentsCareer As Legal Reporters for Law Students
Career As Legal Reporters for Law Students
 
Philippine FIRE CODE REVIEWER for Architecture Board Exam Takers
Philippine FIRE CODE REVIEWER for Architecture Board Exam TakersPhilippine FIRE CODE REVIEWER for Architecture Board Exam Takers
Philippine FIRE CODE REVIEWER for Architecture Board Exam Takers
 

Power Procurement Guidelines in India

  • 1. Guidelines for Competitive Procurement of Power Compiled by Shreekant Dhuri
  • 2. Electricity Act 2003 Preamble • An Act to consolidate the laws relating to generation, transmission, distribution, trading and use of electricity and generally for taking measures conducive to development of electricity industry, promoting competition therein, protecting interest of consumers and supply of electricity to all areas, rationalization of electricity tariff, ensuring transparent policies regarding subsidies, promotion of efficient and environmentally benign policies, constitution of Central Electricity Authority, Regulatory Commissions and establishment of Appellate Tribunal and for matters connected therewith or incidental thereto. Relevant Sections Section 61 & 62: Provide for tariff regulation and determination of tariff of generation, transmission, wheeling and retail sale of electricity by the Appropriate Commission. Section 63: Notwithstanding anything contained in section 62, the Appropriate Commission shall adopt the tariff if such tariff has been determined through transparent process of bidding in accordance with the guidelines issued by the Central Government.
  • 3. Objectives Promote competitive procurement of electricity by distribution licensees Facilitate transparency and fairness in procurement processes Facilitate reduction of information asymmetries for various bidders Protect consumer interests by facilitating competitive conditions in procurement of electricity Enhance standardization and reduce ambiguity and hence time for materialization of projects Provide flexibility to suppliers on internal operations while ensuring certainty on availability of power and tariffs for buyers
  • 4. Tariff Policy 2006 Provides uniform guidelines to SERCs for fixation of tariffs for their respective entities as well as CERC Competitive Bidding: Distribution licensee to procure power solely through competitive bidding but central & state owned units were exempted. Tariff for public sector projects to be decided through bidding after a period of 5 years.
  • 5. Scope Period of Procurement Long term > 7 Years Medium term 1 to 7 Years Procurementavailablefor Base Load Peak Load Seasonal Power
  • 6. Bidding Mechanisms Case 1 • Location, Technology & Fuel not specified by procurer. • Bidder responsible for clearances/ approvals etc. • More relevant for States with limited fuel sources • Higher risk for developer • Lower risk for state Case 2 • For Hydro power projects, load center projects or other location specific projects with specific fuel allocation such as captive mines available, which the procurer intends to setup under tariff based bidding process. • Land/ Fuel provided by Procurer • More applicable for States where fuel sources are available or having coastal areas • Higher risk for State • Lower risk for developer Additional • Procurement by more than one distribution licensee through a combined bid process permitted through authorized representative. • In case distribution licensees are located in more than one State, CERC shall be the Appropriate Commission
  • 7. Preparation for Bid Invitation Bid documentation Approval of the Appropriate Commission in case of deviations Approval of the Appropriate Commission – a) quantum of capacity / energy b) transfer price of fuel Project preparatory activities completion Obtaining the transmission clearances PPA and other required project agreements Project preparatory activities Site identification and land acquisition Environmental clearance for the power station Forest Clearance Fuel Arrangements Water linkage Requisite Hydrological, geological, meteorological and seismological data
  • 8. Tariff Structure Medium Term Long Term One Part Tariff Two Part Tariff Capacity Charge Energy Charge Non Escalable (Firm Price) Escalable (Base Price with Index) Base Price (with Index) NQHR Index notified by CERC Optional
  • 9. Bidding Process Bid Process Two stage process for Long term procurement: Request for Qualification (RFQ) Request for Proposal (RFP) The bidding shall be necessarily by way of International Competitive Bidding (ICB). For Medium term the procurer has an option to adopt a single stage tender process combining the RFP & RFQ process.
  • 10. Bidding Process Preparation of bid documents and technical analysis done by procurer RFQ invited and qualified bidders selected Creates a common platform and removes conditionality. Doubt clearance and feedback Technical and financial bids evaluated LOI issued PPA signed
  • 11. Timetable for Bidding Process Event Elapsed Time from Zero Date Publication of RFQ Zero Date Submission of responses of RFQ 60 days Shortlisting based on responses & issuances of RFQ 90 days Bid clarification, conferences, etc. 150 days Final clarification and revision of RFP 180 days Technical and Price bid submission 360 days Shortlisting of Bidder and issue of LOI 390 days Signing of agreements 425 days Event Elapsed Time from Zero Date Publication of RFQ Zero Date Bid clarification, conferences, etc. 90 days Technical and Price bid submission 180 days Shortlisting of Bidder and issue of LOI 210 days Signing of agreements 240 days (Single Stage Bid Process) (Two Stage Bid Process)