Improvements in
Vehicle Despatch Warehouse
Page No : 2Projects & ME - MIS April 2015
Objective
• To explain the current processes involved, their
time studies and difficulties.
• Improvements possible in process and equipment
to manage the increase in vehicle production
(from 800/day to 1200/day)
Page No : 3Projects & ME - MIS April 2015
Currentscenario
• Production in May’15 - 800 bikes per day
• These bikes are despatched in 3 shifts comfortably
• The average time taken to load one bike into the truck is 105 sec,
using one scissor lift, the bottleneck for the total process
• For improving the efficiency of the process and find the bottleneck,
following 3 major criterions to be considered
A. Hourly Backflush
B. Bike movement for packing
C. Scissor Lift operating Speed
Page No : 4Projects & ME - MIS April 2015
A) Backflush
• The hourly backflush data taken over the month of
April and Mid-May shows that there is inconsistency
in number of vehicles being sent to the warehouse.
39
14 3
30
1 4 6 13 14
22
16
34 33
46
83
29
37
46
30
34
19
39
26
46
23
1
71
33
0 10 11 12 2
39
17
45
1
89
47
25
38
17
32
27
23
7
35
53
0
22.5
45
67.5
90
112.5
12-1 am 1-2 am 2-3 am 3-4 am 4-5 am 5-6 am 6-7 am 7-8 am 8-9 am 9-10 am 10-11
am
11-12
pm
12-1 pm 1-2 pm 2-3 pm 3-4 pm 4-5 pm 5-6 pm 6-7 pm 7-8 pm 8-9 pm 9-10 pm 10-11
pm
11-12
am
April May
Hourly Backflush Data For April and May
Page No : 5Projects & ME - MIS April 2015
A1) Improvement In Backflush
• An average of 60 vehicles to be delivered each hour from
the assembly area to the warehouse is suggested to make
the packing and despatch process non-cumbersome.
Page No : 6Projects & ME - MIS April 2015
B) Bike Movement From Storage To Ready For Despatch Area
• It currently takes 50 sec to bring a packed bike to the
ready to despatch area.
• This process has 2 scopes of improvement. With time
studies conducted, the new process will deliver bikes
at a rate of one bike per 31 sec.
– Addition of 2-way opening VRC doors on 1st and 2nd floor
– Changing floor plan of warehouse on 1st and 2nd floor
Page No : 7Projects & ME - MIS April 2015
B1) Improvement In Bike Movement
• The current floor plan does not provide an efficient system of
loading and unloading the VRCs and hence it is time consuming. It
takes 100 seconds to take up a bare bike and bring down one
packed bike per VRC.
• By implementing both sides opening in VRC (on 1st and 2nd floor),
the process flow becomes streamlined and the time for VRCs
reduces to 62 sec per bike per VRC.
• Another essential process to be improved is taking out and re-
stocking of bikes in VRCs, this process has to be done instantly to
reduce idle time, reduce empty cycles and to maximise utilisation.
Page No : 9Projects & ME - MIS April 2015
C) Loading Of Bikes Into Trucks
• Currently it is measured that 105 sec are being taken
to load a bike using one scissor lift only.
• This is also one of the time consuming processes
• A suggested solution is to improve the scissor lift
speed from 1.8m/min to 3m/min
Page No : 10Projects & ME - MIS April 2015
C1) Improvement In Loading Process
• 15 mins per truck can be saved by reducing idle time of
trucks.
• By using 2 scissor lifts simultaneously 1200 bikes can be
despactched per day.
Page No : 12Projects & ME - MIS April 2015
Proposed Layouts For 1st & 2nd Floor
The following advantages can be
achieved with new floor plans:
• Capacity increase by 112
bikes(22%).
• Previous Capacity: 498
• New Capacity: 610
• More space for packing
provided
Requirements:
• Addition of doors for VRCs on
both floors
• New line marking to be done on
the floor
Page No : 13Projects & ME - MIS April 2015
VRC Door Addition
• As marked, there is a requirement
of motorized doors to be added on
the 1st and 2nd floors of the VRC.
• This will reduce number of empty
cycles
• Make the process flow stream lined
• Require less space for operations
Page No : 14Projects & ME - MIS April 2015
Gate Pass System
• A Gate Pass will be provided to the
truck driver upon entry, that needs to
be submitted to despatch office
• Only after all the required documents
are given to the driver, he be given
the Gate Pass with the seal
• No transport vehicle will leave
without depositing the Gate Pass at
the gate
• This will ensure proper
documentation
Page No : 15Projects & ME - MIS April 2015
Manpower Requirement (For Running 2 Shifts, Domestic Only)
• For VRC Operation : 8
• Responsibility: Complete movement of bikes between floors,
despatch area, waiting area and temporary storage.
• For Packing : 6
• For Loading: 12 (6 on each Scissor Lift)
• For marking and verification : 1 (Maximum 2)
• Total Manpower required(for domestic): (8+6+8+2)= 28(per shift)
Page No : 16Projects & ME - MIS April 2015
Processes Not Considered In Time Study
• Packing the bike is a time consuming process which
is carried out on the 1st and 2nd floor. But it can be
made faster by deploying more man power. This
process will not bottleneck the system as it is not
machine dependent
• Packed bikes storage time (holding time) is not
considered.
Page No : 17Projects & ME - MIS April 2015
Actions
• Lift doors to be added at first priority on upper floors
• Change layout of parking at upper floors
• Idle time of trucks in the loading bay to be reduced
• Introduction of a Gate Pass system is required to ensure the
truck is leaving with all required documents.
• No need to increase speed of scissor lifts. 4.9% improvement in
time is not a substantial improvement and the investment is not
justifiable.
• Backflushing process is required to be made more consistent
• More manpower is required for 2 scissor lifts to be used
simultaneously
• Parking space for 1200 bikes is required in total, proposed
space is the scrap area near the canteen
Page No : 18Projects & ME - MIS April 2015
Conclusions
Current scenario:
Bike Production:800 in 2 shifts
Despatch per day: 800 in 3* shifts
Storage space of packed Bikes:
498 nos.
(1 & 2 floor)
Manpower Requirement: 18/shift
Rate of bike despatch: 105 sec per
bike by using 1 scissor lift (2nd lift is
not utilized fully)
(Bottleneck due to loading)
Proposed:
Bike Production: 1200 in 3 shifts
Despatch per day: 1200 in 3 shifts
Storage space of packed Bikes : 610
nos.
(1 & 2 floor)
Manpower Requirement: 28/shift
Rate of bike despatch: 47 sec per bike
using 2 scissor lifts
(By reducing truck idle time and adding VRC
doors)
By reducing idle time, 1 truck can be
loaded in 100 mins instead of 114, and by
using 2 scissor lifts simultaneously 1 truck
can be filled in 50 mins.
Hence time required for loading per bike
reduces to 47 sec per bike.
*3rd shift is mostly used for model matching

More Related Content

What's hot

What's hot (8)

rup-20151016-part-1-item07-victoria-station-upgrade
rup-20151016-part-1-item07-victoria-station-upgraderup-20151016-part-1-item07-victoria-station-upgrade
rup-20151016-part-1-item07-victoria-station-upgrade
 
Remote Cameras at Unmanned Landfills
Remote Cameras at Unmanned LandfillsRemote Cameras at Unmanned Landfills
Remote Cameras at Unmanned Landfills
 
Gecl casestudy
Gecl casestudyGecl casestudy
Gecl casestudy
 
Innovation@work mit Kaeser Kompressoren – Vom Digitalen Zwilling zur papierlo...
Innovation@work mit Kaeser Kompressoren – Vom Digitalen Zwilling zur papierlo...Innovation@work mit Kaeser Kompressoren – Vom Digitalen Zwilling zur papierlo...
Innovation@work mit Kaeser Kompressoren – Vom Digitalen Zwilling zur papierlo...
 
Crane presentation
Crane presentationCrane presentation
Crane presentation
 
Rena CV
Rena CVRena CV
Rena CV
 
How does Ajax Self-Loading Concrete Mixer works?
How does Ajax Self-Loading Concrete Mixer works?How does Ajax Self-Loading Concrete Mixer works?
How does Ajax Self-Loading Concrete Mixer works?
 
Morel industries section
Morel industries sectionMorel industries section
Morel industries section
 

Viewers also liked

[Smart industry 2016] MacLean-Fogg Uses IIoT to Gain Industry Advantage: Year...
[Smart industry 2016] MacLean-Fogg Uses IIoT to Gain Industry Advantage: Year...[Smart industry 2016] MacLean-Fogg Uses IIoT to Gain Industry Advantage: Year...
[Smart industry 2016] MacLean-Fogg Uses IIoT to Gain Industry Advantage: Year...Chris Misztur
 
Smart Industry 2015: MacLean-Fogg Uses IIOT To Gain Industry Advantage
Smart Industry 2015: MacLean-Fogg Uses IIOT To Gain Industry AdvantageSmart Industry 2015: MacLean-Fogg Uses IIOT To Gain Industry Advantage
Smart Industry 2015: MacLean-Fogg Uses IIOT To Gain Industry AdvantageChris Misztur
 
Digital Supply Chain – Where Virtual and Physical Converge
Digital Supply Chain – Where Virtual and Physical ConvergeDigital Supply Chain – Where Virtual and Physical Converge
Digital Supply Chain – Where Virtual and Physical ConvergeCapgemini
 
Discrete MFG IoT Factory of the Future
Discrete MFG IoT Factory of the FutureDiscrete MFG IoT Factory of the Future
Discrete MFG IoT Factory of the FutureMainstay
 
Cognizant SAP Manufacturing Success Report 2014
Cognizant SAP Manufacturing Success Report 2014Cognizant SAP Manufacturing Success Report 2014
Cognizant SAP Manufacturing Success Report 2014Cognizant
 
Technology Vision 2014 by Accenture
Technology Vision 2014 by AccentureTechnology Vision 2014 by Accenture
Technology Vision 2014 by AccentureTaufikurrahman .
 
Discrete manufacturing Industry- Connect, Transform, and Reimagine: Help Your...
Discrete manufacturing Industry- Connect, Transform, and Reimagine: Help Your...Discrete manufacturing Industry- Connect, Transform, and Reimagine: Help Your...
Discrete manufacturing Industry- Connect, Transform, and Reimagine: Help Your...Shivakumar Vishwanath
 
AWS Partner Presentation - Accenture Digital Supply Chain In The Cloud
AWS Partner Presentation - Accenture Digital Supply Chain In The CloudAWS Partner Presentation - Accenture Digital Supply Chain In The Cloud
AWS Partner Presentation - Accenture Digital Supply Chain In The CloudAmazon Web Services
 
Igniting Growth in Consumer Technology - Accenture
Igniting Growth in Consumer Technology - AccentureIgniting Growth in Consumer Technology - Accenture
Igniting Growth in Consumer Technology - AccentureAccenture Italia
 
Digital transformation of supply chain
Digital transformation of supply chainDigital transformation of supply chain
Digital transformation of supply chainSandip Besra
 
Technology Vision 2016 - Infografica
Technology Vision 2016 - InfograficaTechnology Vision 2016 - Infografica
Technology Vision 2016 - InfograficaAccenture Italia
 
Supply Chain Talent Study - MARCH 2017 - Preliminary Summary Charts
Supply Chain Talent Study - MARCH 2017 - Preliminary Summary ChartsSupply Chain Talent Study - MARCH 2017 - Preliminary Summary Charts
Supply Chain Talent Study - MARCH 2017 - Preliminary Summary ChartsLora Cecere
 
Imagine the Digital Supply Chain
Imagine the Digital Supply ChainImagine the Digital Supply Chain
Imagine the Digital Supply ChainLora Cecere
 
Digital Supply Chain Transformation in the Networked Economy
Digital Supply Chain Transformation in the Networked EconomyDigital Supply Chain Transformation in the Networked Economy
Digital Supply Chain Transformation in the Networked EconomySAP Ariba
 
Accenture Technology Vision 2017 - Infografica
Accenture Technology Vision 2017 - InfograficaAccenture Technology Vision 2017 - Infografica
Accenture Technology Vision 2017 - InfograficaAccenture Italia
 
Accenture Technology Vision 2014—Every Business is a Digital Business
Accenture Technology Vision 2014—Every Business is a Digital BusinessAccenture Technology Vision 2014—Every Business is a Digital Business
Accenture Technology Vision 2014—Every Business is a Digital Businessaccenture
 
Building the Business Case for SAP S/4HANA
Building the Business Case for SAP S/4HANABuilding the Business Case for SAP S/4HANA
Building the Business Case for SAP S/4HANABluefin Solutions
 
SAP S/4HANA: Everything you need to know for a successul implementation
SAP S/4HANA: Everything you need to know for a successul implementationSAP S/4HANA: Everything you need to know for a successul implementation
SAP S/4HANA: Everything you need to know for a successul implementationBluefin Solutions
 

Viewers also liked (20)

[Smart industry 2016] MacLean-Fogg Uses IIoT to Gain Industry Advantage: Year...
[Smart industry 2016] MacLean-Fogg Uses IIoT to Gain Industry Advantage: Year...[Smart industry 2016] MacLean-Fogg Uses IIoT to Gain Industry Advantage: Year...
[Smart industry 2016] MacLean-Fogg Uses IIoT to Gain Industry Advantage: Year...
 
Smart Industry 2015: MacLean-Fogg Uses IIOT To Gain Industry Advantage
Smart Industry 2015: MacLean-Fogg Uses IIOT To Gain Industry AdvantageSmart Industry 2015: MacLean-Fogg Uses IIOT To Gain Industry Advantage
Smart Industry 2015: MacLean-Fogg Uses IIOT To Gain Industry Advantage
 
Digital Supply Chain – Where Virtual and Physical Converge
Digital Supply Chain – Where Virtual and Physical ConvergeDigital Supply Chain – Where Virtual and Physical Converge
Digital Supply Chain – Where Virtual and Physical Converge
 
Discrete MFG IoT Factory of the Future
Discrete MFG IoT Factory of the FutureDiscrete MFG IoT Factory of the Future
Discrete MFG IoT Factory of the Future
 
Cognizant SAP Manufacturing Success Report 2014
Cognizant SAP Manufacturing Success Report 2014Cognizant SAP Manufacturing Success Report 2014
Cognizant SAP Manufacturing Success Report 2014
 
Technology Vision 2014 by Accenture
Technology Vision 2014 by AccentureTechnology Vision 2014 by Accenture
Technology Vision 2014 by Accenture
 
Discrete manufacturing Industry- Connect, Transform, and Reimagine: Help Your...
Discrete manufacturing Industry- Connect, Transform, and Reimagine: Help Your...Discrete manufacturing Industry- Connect, Transform, and Reimagine: Help Your...
Discrete manufacturing Industry- Connect, Transform, and Reimagine: Help Your...
 
AWS Partner Presentation - Accenture Digital Supply Chain In The Cloud
AWS Partner Presentation - Accenture Digital Supply Chain In The CloudAWS Partner Presentation - Accenture Digital Supply Chain In The Cloud
AWS Partner Presentation - Accenture Digital Supply Chain In The Cloud
 
Igniting Growth in Consumer Technology - Accenture
Igniting Growth in Consumer Technology - AccentureIgniting Growth in Consumer Technology - Accenture
Igniting Growth in Consumer Technology - Accenture
 
Digital transformation of supply chain
Digital transformation of supply chainDigital transformation of supply chain
Digital transformation of supply chain
 
Technology Vision 2016 - Infografica
Technology Vision 2016 - InfograficaTechnology Vision 2016 - Infografica
Technology Vision 2016 - Infografica
 
Supply Chain Talent Study - MARCH 2017 - Preliminary Summary Charts
Supply Chain Talent Study - MARCH 2017 - Preliminary Summary ChartsSupply Chain Talent Study - MARCH 2017 - Preliminary Summary Charts
Supply Chain Talent Study - MARCH 2017 - Preliminary Summary Charts
 
CRM Trends to Watch for in 2017
CRM Trends to Watch for in 2017CRM Trends to Watch for in 2017
CRM Trends to Watch for in 2017
 
Innovation in maintenance - Accenture
Innovation in maintenance - AccentureInnovation in maintenance - Accenture
Innovation in maintenance - Accenture
 
Imagine the Digital Supply Chain
Imagine the Digital Supply ChainImagine the Digital Supply Chain
Imagine the Digital Supply Chain
 
Digital Supply Chain Transformation in the Networked Economy
Digital Supply Chain Transformation in the Networked EconomyDigital Supply Chain Transformation in the Networked Economy
Digital Supply Chain Transformation in the Networked Economy
 
Accenture Technology Vision 2017 - Infografica
Accenture Technology Vision 2017 - InfograficaAccenture Technology Vision 2017 - Infografica
Accenture Technology Vision 2017 - Infografica
 
Accenture Technology Vision 2014—Every Business is a Digital Business
Accenture Technology Vision 2014—Every Business is a Digital BusinessAccenture Technology Vision 2014—Every Business is a Digital Business
Accenture Technology Vision 2014—Every Business is a Digital Business
 
Building the Business Case for SAP S/4HANA
Building the Business Case for SAP S/4HANABuilding the Business Case for SAP S/4HANA
Building the Business Case for SAP S/4HANA
 
SAP S/4HANA: Everything you need to know for a successul implementation
SAP S/4HANA: Everything you need to know for a successul implementationSAP S/4HANA: Everything you need to know for a successul implementation
SAP S/4HANA: Everything you need to know for a successul implementation
 

Similar to VW Project Presentation

Development Of Tipper Unloading Mechanism
Development Of Tipper Unloading MechanismDevelopment Of Tipper Unloading Mechanism
Development Of Tipper Unloading MechanismIRJET Journal
 
Construction Equipment Fleet Management
Construction Equipment Fleet ManagementConstruction Equipment Fleet Management
Construction Equipment Fleet ManagementIJMER
 
IRJET- Design and Implementation of Kitting Trolley for Just in Time Producti...
IRJET- Design and Implementation of Kitting Trolley for Just in Time Producti...IRJET- Design and Implementation of Kitting Trolley for Just in Time Producti...
IRJET- Design and Implementation of Kitting Trolley for Just in Time Producti...IRJET Journal
 
Automated Assembly Systems
Automated Assembly SystemsAutomated Assembly Systems
Automated Assembly Systemschethan kumar
 
FC VSM Presentation Future State Aug 5 -7 2013
FC VSM Presentation Future State Aug 5 -7  2013FC VSM Presentation Future State Aug 5 -7  2013
FC VSM Presentation Future State Aug 5 -7 2013Donna Skala
 
Implementation of Lean - Case Study
Implementation of Lean - Case StudyImplementation of Lean - Case Study
Implementation of Lean - Case StudyAmeer Hasan Malik
 
Where Glencore Coal Assets Australia stands - Mark Winchester
Where Glencore Coal Assets Australia stands - Mark WinchesterWhere Glencore Coal Assets Australia stands - Mark Winchester
Where Glencore Coal Assets Australia stands - Mark WinchesterNSW Environment and Planning
 
Vital Vitamins Facility Planning & Designing
Vital Vitamins Facility  Planning & DesigningVital Vitamins Facility  Planning & Designing
Vital Vitamins Facility Planning & Designingusamaashfaq12
 
CEMEX_SeniorDesignPosterUpdate4.21.3.pptx
CEMEX_SeniorDesignPosterUpdate4.21.3.pptxCEMEX_SeniorDesignPosterUpdate4.21.3.pptx
CEMEX_SeniorDesignPosterUpdate4.21.3.pptxArda Onkol
 
Real time shovel payload feedback for improved productivity, MineWare
Real time shovel payload feedback for improved productivity, MineWare  Real time shovel payload feedback for improved productivity, MineWare
Real time shovel payload feedback for improved productivity, MineWare claremasters
 
B-Logistics wagon maintenance
B-Logistics wagon maintenanceB-Logistics wagon maintenance
B-Logistics wagon maintenanceKris Peeters
 
Ashok Leyland July'11
Ashok Leyland July'11Ashok Leyland July'11
Ashok Leyland July'11Jitendra Shah
 
Trend Talk Warsaw - Propergate
Trend Talk Warsaw - PropergateTrend Talk Warsaw - Propergate
Trend Talk Warsaw - PropergatePlaceTech
 
Dynamic Fleet Sizing Problem for an E-Scooter Valet Service
Dynamic Fleet Sizing Problem for an E-Scooter Valet ServiceDynamic Fleet Sizing Problem for an E-Scooter Valet Service
Dynamic Fleet Sizing Problem for an E-Scooter Valet ServiceJoseph Chow
 
IRJET - Increasing the Maintenance Work Rate of LHB and ICF Wheel using C...
IRJET -  	  Increasing the Maintenance Work Rate of LHB and ICF Wheel using C...IRJET -  	  Increasing the Maintenance Work Rate of LHB and ICF Wheel using C...
IRJET - Increasing the Maintenance Work Rate of LHB and ICF Wheel using C...IRJET Journal
 
Computer Simulation: Quantifying and Substantiating a Claim for Extension of ...
Computer Simulation: Quantifying and Substantiating a Claim for Extension of ...Computer Simulation: Quantifying and Substantiating a Claim for Extension of ...
Computer Simulation: Quantifying and Substantiating a Claim for Extension of ...CCT International
 
Resource partnership case study
Resource partnership   case studyResource partnership   case study
Resource partnership case studyZubin Poonawalla
 
Resource partnership case study
Resource partnership   case studyResource partnership   case study
Resource partnership case studyZubin Poonawalla
 

Similar to VW Project Presentation (20)

Development Of Tipper Unloading Mechanism
Development Of Tipper Unloading MechanismDevelopment Of Tipper Unloading Mechanism
Development Of Tipper Unloading Mechanism
 
Construction Equipment Fleet Management
Construction Equipment Fleet ManagementConstruction Equipment Fleet Management
Construction Equipment Fleet Management
 
IRJET- Design and Implementation of Kitting Trolley for Just in Time Producti...
IRJET- Design and Implementation of Kitting Trolley for Just in Time Producti...IRJET- Design and Implementation of Kitting Trolley for Just in Time Producti...
IRJET- Design and Implementation of Kitting Trolley for Just in Time Producti...
 
ANDREW BIRD: Better Connected Live 2016
ANDREW BIRD: Better Connected Live 2016ANDREW BIRD: Better Connected Live 2016
ANDREW BIRD: Better Connected Live 2016
 
ANDREW BIRD: Better Connected Live 2016
ANDREW BIRD: Better Connected Live 2016ANDREW BIRD: Better Connected Live 2016
ANDREW BIRD: Better Connected Live 2016
 
Automated Assembly Systems
Automated Assembly SystemsAutomated Assembly Systems
Automated Assembly Systems
 
FC VSM Presentation Future State Aug 5 -7 2013
FC VSM Presentation Future State Aug 5 -7  2013FC VSM Presentation Future State Aug 5 -7  2013
FC VSM Presentation Future State Aug 5 -7 2013
 
Implementation of Lean - Case Study
Implementation of Lean - Case StudyImplementation of Lean - Case Study
Implementation of Lean - Case Study
 
Where Glencore Coal Assets Australia stands - Mark Winchester
Where Glencore Coal Assets Australia stands - Mark WinchesterWhere Glencore Coal Assets Australia stands - Mark Winchester
Where Glencore Coal Assets Australia stands - Mark Winchester
 
Vital Vitamins Facility Planning & Designing
Vital Vitamins Facility  Planning & DesigningVital Vitamins Facility  Planning & Designing
Vital Vitamins Facility Planning & Designing
 
CEMEX_SeniorDesignPosterUpdate4.21.3.pptx
CEMEX_SeniorDesignPosterUpdate4.21.3.pptxCEMEX_SeniorDesignPosterUpdate4.21.3.pptx
CEMEX_SeniorDesignPosterUpdate4.21.3.pptx
 
Real time shovel payload feedback for improved productivity, MineWare
Real time shovel payload feedback for improved productivity, MineWare  Real time shovel payload feedback for improved productivity, MineWare
Real time shovel payload feedback for improved productivity, MineWare
 
B-Logistics wagon maintenance
B-Logistics wagon maintenanceB-Logistics wagon maintenance
B-Logistics wagon maintenance
 
Ashok Leyland July'11
Ashok Leyland July'11Ashok Leyland July'11
Ashok Leyland July'11
 
Trend Talk Warsaw - Propergate
Trend Talk Warsaw - PropergateTrend Talk Warsaw - Propergate
Trend Talk Warsaw - Propergate
 
Dynamic Fleet Sizing Problem for an E-Scooter Valet Service
Dynamic Fleet Sizing Problem for an E-Scooter Valet ServiceDynamic Fleet Sizing Problem for an E-Scooter Valet Service
Dynamic Fleet Sizing Problem for an E-Scooter Valet Service
 
IRJET - Increasing the Maintenance Work Rate of LHB and ICF Wheel using C...
IRJET -  	  Increasing the Maintenance Work Rate of LHB and ICF Wheel using C...IRJET -  	  Increasing the Maintenance Work Rate of LHB and ICF Wheel using C...
IRJET - Increasing the Maintenance Work Rate of LHB and ICF Wheel using C...
 
Computer Simulation: Quantifying and Substantiating a Claim for Extension of ...
Computer Simulation: Quantifying and Substantiating a Claim for Extension of ...Computer Simulation: Quantifying and Substantiating a Claim for Extension of ...
Computer Simulation: Quantifying and Substantiating a Claim for Extension of ...
 
Resource partnership case study
Resource partnership   case studyResource partnership   case study
Resource partnership case study
 
Resource partnership case study
Resource partnership   case studyResource partnership   case study
Resource partnership case study
 

VW Project Presentation

  • 1. Page No : 1Projects & ME - MIS April 2015 Improvements in Vehicle Despatch Warehouse
  • 2. Page No : 2Projects & ME - MIS April 2015 Objective • To explain the current processes involved, their time studies and difficulties. • Improvements possible in process and equipment to manage the increase in vehicle production (from 800/day to 1200/day)
  • 3. Page No : 3Projects & ME - MIS April 2015 Currentscenario • Production in May’15 - 800 bikes per day • These bikes are despatched in 3 shifts comfortably • The average time taken to load one bike into the truck is 105 sec, using one scissor lift, the bottleneck for the total process • For improving the efficiency of the process and find the bottleneck, following 3 major criterions to be considered A. Hourly Backflush B. Bike movement for packing C. Scissor Lift operating Speed
  • 4. Page No : 4Projects & ME - MIS April 2015 A) Backflush • The hourly backflush data taken over the month of April and Mid-May shows that there is inconsistency in number of vehicles being sent to the warehouse. 39 14 3 30 1 4 6 13 14 22 16 34 33 46 83 29 37 46 30 34 19 39 26 46 23 1 71 33 0 10 11 12 2 39 17 45 1 89 47 25 38 17 32 27 23 7 35 53 0 22.5 45 67.5 90 112.5 12-1 am 1-2 am 2-3 am 3-4 am 4-5 am 5-6 am 6-7 am 7-8 am 8-9 am 9-10 am 10-11 am 11-12 pm 12-1 pm 1-2 pm 2-3 pm 3-4 pm 4-5 pm 5-6 pm 6-7 pm 7-8 pm 8-9 pm 9-10 pm 10-11 pm 11-12 am April May Hourly Backflush Data For April and May
  • 5. Page No : 5Projects & ME - MIS April 2015 A1) Improvement In Backflush • An average of 60 vehicles to be delivered each hour from the assembly area to the warehouse is suggested to make the packing and despatch process non-cumbersome.
  • 6. Page No : 6Projects & ME - MIS April 2015 B) Bike Movement From Storage To Ready For Despatch Area • It currently takes 50 sec to bring a packed bike to the ready to despatch area. • This process has 2 scopes of improvement. With time studies conducted, the new process will deliver bikes at a rate of one bike per 31 sec. – Addition of 2-way opening VRC doors on 1st and 2nd floor – Changing floor plan of warehouse on 1st and 2nd floor
  • 7. Page No : 7Projects & ME - MIS April 2015 B1) Improvement In Bike Movement • The current floor plan does not provide an efficient system of loading and unloading the VRCs and hence it is time consuming. It takes 100 seconds to take up a bare bike and bring down one packed bike per VRC. • By implementing both sides opening in VRC (on 1st and 2nd floor), the process flow becomes streamlined and the time for VRCs reduces to 62 sec per bike per VRC. • Another essential process to be improved is taking out and re- stocking of bikes in VRCs, this process has to be done instantly to reduce idle time, reduce empty cycles and to maximise utilisation.
  • 8. Page No : 9Projects & ME - MIS April 2015 C) Loading Of Bikes Into Trucks • Currently it is measured that 105 sec are being taken to load a bike using one scissor lift only. • This is also one of the time consuming processes • A suggested solution is to improve the scissor lift speed from 1.8m/min to 3m/min
  • 9. Page No : 10Projects & ME - MIS April 2015 C1) Improvement In Loading Process • 15 mins per truck can be saved by reducing idle time of trucks. • By using 2 scissor lifts simultaneously 1200 bikes can be despactched per day.
  • 10. Page No : 12Projects & ME - MIS April 2015 Proposed Layouts For 1st & 2nd Floor The following advantages can be achieved with new floor plans: • Capacity increase by 112 bikes(22%). • Previous Capacity: 498 • New Capacity: 610 • More space for packing provided Requirements: • Addition of doors for VRCs on both floors • New line marking to be done on the floor
  • 11. Page No : 13Projects & ME - MIS April 2015 VRC Door Addition • As marked, there is a requirement of motorized doors to be added on the 1st and 2nd floors of the VRC. • This will reduce number of empty cycles • Make the process flow stream lined • Require less space for operations
  • 12. Page No : 14Projects & ME - MIS April 2015 Gate Pass System • A Gate Pass will be provided to the truck driver upon entry, that needs to be submitted to despatch office • Only after all the required documents are given to the driver, he be given the Gate Pass with the seal • No transport vehicle will leave without depositing the Gate Pass at the gate • This will ensure proper documentation
  • 13. Page No : 15Projects & ME - MIS April 2015 Manpower Requirement (For Running 2 Shifts, Domestic Only) • For VRC Operation : 8 • Responsibility: Complete movement of bikes between floors, despatch area, waiting area and temporary storage. • For Packing : 6 • For Loading: 12 (6 on each Scissor Lift) • For marking and verification : 1 (Maximum 2) • Total Manpower required(for domestic): (8+6+8+2)= 28(per shift)
  • 14. Page No : 16Projects & ME - MIS April 2015 Processes Not Considered In Time Study • Packing the bike is a time consuming process which is carried out on the 1st and 2nd floor. But it can be made faster by deploying more man power. This process will not bottleneck the system as it is not machine dependent • Packed bikes storage time (holding time) is not considered.
  • 15. Page No : 17Projects & ME - MIS April 2015 Actions • Lift doors to be added at first priority on upper floors • Change layout of parking at upper floors • Idle time of trucks in the loading bay to be reduced • Introduction of a Gate Pass system is required to ensure the truck is leaving with all required documents. • No need to increase speed of scissor lifts. 4.9% improvement in time is not a substantial improvement and the investment is not justifiable. • Backflushing process is required to be made more consistent • More manpower is required for 2 scissor lifts to be used simultaneously • Parking space for 1200 bikes is required in total, proposed space is the scrap area near the canteen
  • 16. Page No : 18Projects & ME - MIS April 2015 Conclusions Current scenario: Bike Production:800 in 2 shifts Despatch per day: 800 in 3* shifts Storage space of packed Bikes: 498 nos. (1 & 2 floor) Manpower Requirement: 18/shift Rate of bike despatch: 105 sec per bike by using 1 scissor lift (2nd lift is not utilized fully) (Bottleneck due to loading) Proposed: Bike Production: 1200 in 3 shifts Despatch per day: 1200 in 3 shifts Storage space of packed Bikes : 610 nos. (1 & 2 floor) Manpower Requirement: 28/shift Rate of bike despatch: 47 sec per bike using 2 scissor lifts (By reducing truck idle time and adding VRC doors) By reducing idle time, 1 truck can be loaded in 100 mins instead of 114, and by using 2 scissor lifts simultaneously 1 truck can be filled in 50 mins. Hence time required for loading per bike reduces to 47 sec per bike. *3rd shift is mostly used for model matching