Publicité

Project Report on House Construction under PMAY

29 Mar 2023
Project Report on House Construction under PMAY
Project Report on House Construction under PMAY
Project Report on House Construction under PMAY
Project Report on House Construction under PMAY
Publicité
Project Report on House Construction under PMAY
Project Report on House Construction under PMAY
Project Report on House Construction under PMAY
Project Report on House Construction under PMAY
Project Report on House Construction under PMAY
Publicité
Project Report on House Construction under PMAY
Project Report on House Construction under PMAY
Project Report on House Construction under PMAY
Project Report on House Construction under PMAY
Project Report on House Construction under PMAY
Publicité
Project Report on House Construction under PMAY
Project Report on House Construction under PMAY
Project Report on House Construction under PMAY
Project Report on House Construction under PMAY
Project Report on House Construction under PMAY
Publicité
Project Report on House Construction under PMAY
Prochain SlideShare
@ETCONp Construction Exam 8  .DOCX@ETCONp Construction Exam 8 .DOCX
Chargement dans ... 3
1 sur 20
Publicité

Contenu connexe

Similaire à Project Report on House Construction under PMAY(20)

Publicité

Project Report on House Construction under PMAY

  1. Page 1 of 20 INDIAN INSTITUTE OF TECHNOLOGY MADRAS DEPARTMENT OF CIVIL ENGINEERING CE5020: Construction Planning and Control TASK-9 Report Writing Submitted By: SOURABH KUMAR SINGH (CE21M126) LAL ANKIT NATH SHAHDEO (CE21M118) CTaM’21
  2. Page 2 of 20 Contents Abstract................................................................................................................3 Introduction.........................................................................................................4 Construction Materials.......................................................................................6 Analysis of project...............................................................................................9 Work Breakdown System of the project .......................................................9 Project Scheduling .........................................................................................10 Bill of Quantities ............................................................................................12 Costing and Budgeting ..................................................................................13 Time-Cost Trade off ......................................................................................17 Labour Resources ..........................................................................................18 Earned Value Analysis ..................................................................................19 Conclusion..........................................................................................................20
  3. Page 3 of 20 Abstract This project is a model sketch of various aspects of project planning and monitoring of a house to be built under Prime Minister’s Awaas Yojana. PMAY was launched in 2015 with an aim to provide housing for all by 2022. This scheme provides a house of 30 sqm carpet area to an economically weaker section (EWS) household. Houses are supported with basic civil amenities. This report covers the planning, scheduling, and monitoring of progress in hypothetical cases of a single EWS house.
  4. Page 4 of 20 Introduction Project plan: The project consists of planning all the stages of construction of 324 sq. ft house for the families affected by tsunami in Tamil Nādu. The house is single storey and has 1 bedroom, 1 hall, 1 kitchen and open verandah space. Purpose of the project: The project is about planning the different phases of construction of Residential Home Construction. This includes preparing of WBS, BOQ, Gantt chart, Network diagram, Cost analysis, budgeting, time cost trade off analysis, resource planning and earned value analysis. Project planning-scheduling-execution: The planning includes, listing all the activities and preparing the work breakdown structure for all the construction activities and non-construction activities and dividing them in several packages. After that, AON network diagram is prepared and project duration, float and critical path is calculated using forward and backward pass. A detailed Gantt chart is prepared to follow for all the phases of construction. After calculating the time required for the project, a detailed costing and budgeting is done for every work packages. Time-cost trade off analysis is done to check the effect on budget cost on crashing several activities. To manage the resources in the site, resource histogram is prepared for all the human resources. And, finally Earned Value analysis is done to check the schedule performance and cost performance for 25%, 50% and 75% of project duration. Stakeholders: This is the project to give permanent households for people living in tsunami affected areas. So, the major stakeholders include: 1. SEVAI(Client) 2. Contractor 3. Sub-contractors 4. Planner 5. Architects 6. Engineers 7. Government authorities 8. Workers and Suppliers 9. Local residents 10. End Users (People affected by tsunami)
  5. Page 5 of 20 Risk and contingencies: Several points are discussed before the project approval for minimizing the risks and timely completion of the project: 1. The risk of obtaining planning permission or other statutory approvals: This might be mitigated by early consultation with statutory authorities prior to design, or by employing ex-statutory authority employees, or consultants familiar with the statutory authority. 2. Non-delivery of materials: An alternative design might be prepared, or bulk or specific items could be pre-ordered before contractors are appointed 3. Lack of available work force. This could be tackled by the provision of a site labor camp or by overseas recruitment. 4. Illness: This could be mitigated by insurance cover for key personnel. 5. Failure of power or water supply: This might be mitigated by the duplication of supply, uninterrupted power supplies or the provision of standby generators.
  6. Page 6 of 20 Construction Materials Common construction materials are: 1. Steel – TMT rolled bars – 8 mm, 10 mm, 12 mm, 16 mm, 20 mm, 25 mm, 32 mm dia. 2. Concrete – PCC and RCC – M5, M10, M15, M20, M25, M30 etc. 3. Shuttering Ply Boards – 12 mm thick, 1.22 m x 2.44 m 4. Brick – Non modular brick – 230 mm x 110 mm x 70 mm Other materials: 1. Bamboo 2. Binding wire 3. Shuttering oil 4. Hessian Cloth 5. Polythene sheet 6. Construction Water 7. Lime powder 8. Glass 9. Paint 10. Nails 11. Water hose pipe Price of some common construction materials: Item UOM Price Rebar MT 55000.00 Cement Kg 8.00 Sand Cft 30.00 Coarse Agg. Cft 30.00 Shutter Ply Sqm 400.00 Brick Nos 6.00 Bamboo Nos 95.00 Binding wire kg 50.00 Shuttering oil L 70.00 Nails kg 45.00 Paint L 50.00 Lime powder kg 20.00 Hessian cloth Rmt 20.00 Polythene sheet kg 110.00 Water hose pipe kg 145.00
  7. Page 7 of 20 Price Escalation: Escalation is the change in cost or price of specific goods or services in a given economy over a period. For any project, budget for materials shall be prepared by considering the price during procurement in future. For estimating escalation, trend in price increase is studied and extrapolated. Month Price of Hot Rolled Coil TMT Sep-20 39500 Oct-20 42000 Nov-20 44250 Dec-20 47000 Jan-21 54500 Feb-21 52000 Mar-21 52000 Apr-21 56600 May-21 61500 Jun-21 64000 Jul-21 62600 0 10000 20000 30000 40000 50000 60000 70000 Aug-20 Sep-20 Nov-20 Jan-21 Feb-21 Apr-21 Jun-21 Jul-21 COST IN RS. MONTH Hot Rolled Coil
  8. Page 8 of 20 Strength of construction materials: Material Grade Strength Remark Cement M33 33 N/mm2 Compressive strength M43 43 N/mm2 Compressive strength M53 43 N/mm2 Compressive strength Concrete M5 5N/mm2 Compressive strength M7.5 7.5N/mm2 Compressive strength M10 10N/mm2 Compressive strength M15 15N/mm2 Compressive strength M20 20N/mm2 Compressive strength M25 25N/mm2 Compressive strength M30 30N/mm2 Compressive strength Steel TMT FE250 250N/mm2 Tensile strength FE415 415N/mm2 Tensile strength FE500 500N/mm2 Tensile strength Shuttering board Along the grain 32.5 N/mm2 Tensile strength Across the grain 22.5 N/mm2 Tensile strength Sum of both 60.0 N/mm2 Tensile strength Brick First class 105 kg/cm2 Compressive strength Second class 70 kg/cm2 Compressive strength third class 35 kg/cm2 Compressive strength Fly ash 90 kg/cm2 Compressive strength
  9. Page 9 of 20 Analysis of project Work Breakdown System of the project The project has been divided into two parts i.e., Planning phase and Construction phase. Planning phase is comprised of Site survey, Field tests, Design and Approvals. Construction phase is divided in four parts – Structure, Masonry, Electrical and Plumbing, and Finishing. Figure – WBS of EWS housing project
  10. Page 10 of 20 Project Scheduling Project scheduling is done by two methods: • AON diagram: ▪ AON diagram is prepared for the project considering duration calculated of each activity and appropriate predecessor and successor of each activity. ▪ Backward and forward pass method is used to calculate the total duration for the completion of the project and float available for each activity. ▪ No of work packages in the pre-construction phase: 1 ▪ No of work packages in the construction phase: 4 ▪ Total no of work packages: 8 ▪ No of activities in the pre-construction phase: 4 ▪ No of activities in the construction phase: 40 ▪ Total no of activities: 44 ▪ Duration of pre-construction phase (days): 33 days ▪ Duration of construction phase (days): 96 days ▪ Total duration (days): 129 days ▪ Number of non-critical activities: 7 ▪ No of critical paths: 2 • Gantt Chart: ▪ Gantt chart for the project is prepared to schedule each activity over the calendar to show the interrelation between the activities and to track the progress of the construction. 33 days 96 days Total Duration= 129 days Pre construction phase Contruction phase 4 40 Total Activities No of activities in the pre-construction phase: No of activities in the construction phase
  11. Page 11 of 20
  12. Page 12 of 20 Bill of Quantities Activity UOM BOQ Foundation Trenching Cum 11.41 Foundation PCC Cum 0.50 Foundation Rebar MT 0.32 Foundation Shutter Sqm 13.68 Foundation Concrete Cum 1.83 Foundation Deshutter Sqm 13.68 Foundation Backfilling Cum 9.09 Plinth Rebar MT 0.24 Plinth Shutter Sqm 21.00 Plinth Concrete Cum 2.14 Plinth Deshutter Sqm 21.00 Ground Floor PCC Cum 6.02 Column Rebar MT 0.23 Column Shutter Sqm 33.67 Column Concrete Cum 1.94 Column Deshutter Sqm 33.67 Roof Slab Staging Cum 91.20 Roof Slab Shutter Sqm 33.33 Roof Slab Rebar MT 0.58 Roof Slab Concrete Cum 4.49 Roof Slab Destaging Cum 91.20 Staircase Staging Cum 7.97 Staircase Shutter Sqm 5.92 Staircase Rebar MT 0.08 Staircase Concrete Cum 0.59 Staircase Destaging Cum 7.97 Masonry Cum 20.37 Wiring LS 1 Plumbing fixtures LS 1 Plaster Sqm 224.73 Floor Finish Sqm 30.10 Door & window fixing Nos 11 Painting Sqm 291.45
  13. Page 13 of 20 Costing and Budgeting Direct Costs of the project: Planning and Construction costs Project Phase Planning Work Package Site Survey Field test Design Approvals Labour cost ₹ - ₹ - ₹ - ₹ - Material cost ₹ - ₹ - ₹ - ₹ - Sub-contracted ₹ - ₹ 20,000.00 ₹ - ₹ - Cost of Package ₹ - ₹ 20,000.00 ₹ - ₹ - Project Phase Construction Work Package Structure Masonry Electrical & Plumbing Finishing Labour cost ₹ 1,25,300.00 ₹ 35,200.00 ₹ - ₹ 59,400.00 Material cost ₹ 1,57,612.16 ₹ 7,374.53 ₹ - ₹ 21,329.49 Sub-contracted ₹ - ₹ - ₹ 35,000.00 ₹ 15,000.00 Cost of Package ₹ 2,82,912.16 ₹ 42,574.53 ₹ 35,000.00 ₹ 95,729.49 Total Direct Cost = ₹ 4,76,216.18 Indirect cost of project: Item Amount Staff Salaries ₹ 1,29,000.00 Site office setup ₹ 20,000.00 Staff Transportation allowance ₹ 4,300.00 Site office electricity ₹ 316.67 Site office water supply ₹ 158.33 Snacks ₹ 9,000.00 Documentation ₹ 1,290.00 Total ₹ 1,64,065.00 Total Direct Cost = ₹ 1,64,065.00 Total Budget = ₹ 6,40,281.18
  14. Page 14 of 20 4% 60% 9% 7% 20% Direct Cost Site Survey Field test Design Approvals Structure Masonry Electrical & Plumbing Finishing 79% 12% 3% 5% 1% Indirect Cost Staff Salaries Site office setup Staff Transportation allowance Site office electricity Site office water supply Snacks Documetation
  15. Page 15 of 20 74% 26% Total Budget Direct Cost Indirect Cost 46% 39% 15% Component of Direct Cost Labour cost Material cost Sub-contracted
  16. Page 16 of 20 Material Costing: Material UOM Quantity Rate Amount Shutter Ply Sqm 21.52 400.00 8608.31 Rebar MT 1.45 55000.00 79823.47 Cement Kg 7053.11 8.00 56424.88 Sand Cft 451.43 30.00 13542.81 Coarse Agg. Cft 540.07 30.00 16202.18 Water Lt 2141.82 0.00 0.00 Bricks Nos 1000.00 6.00 6000.00 Paint Lt 58.29 50.00 2914.53 Rope Rmt 30 20 600 Lime powder Kg 20 10 200 Measuring Chain LS 1 2000 2000 Total cost of materials ₹ 1,86,316.18 5% 43% 30% 7% 9% 0% 3% 2% 0% 0% 1% Material Cost Shutter Ply Rebar Cement Sand Coarse Agg. Water Bricks Paint Rope Lime powder Measuring Chain
  17. Page 17 of 20 Time-Cost Trade off Original duration of project = 129 days Crashed duration of project = 87 days Due to crashing direct cost has increased by 23% and indirect cost has decreased by 37%. Overall effect on budget is an increase of 14%. Original Budget Crashed Budget % Change Direct Cost ₹ 4,76,216.18 ₹ 6,22,109.18 23% Indirect Cost ₹ 1,64,065.00 ₹ 1,20,115.00 -37% Total ₹ 6,40,281.18 ₹ 7,42,224.18 14% ₹4,76,216.18 ₹1,64,065.00 ₹6,40,281.18 ₹6,22,109.18 ₹1,20,115.00 ₹7,42,224.18 ₹- ₹1,00,000.00 ₹2,00,000.00 ₹3,00,000.00 ₹4,00,000.00 ₹5,00,000.00 ₹6,00,000.00 ₹7,00,000.00 ₹8,00,000.00 Direct Cost Indirect Cost Total Original vs Crashed Budget Original Budget Crashed Budget 74% 26% Original Budget Direct Cost Indirect Cost 84% 16% Crashed Budget Direct Cost Indirect Cost
  18. Page 18 of 20 Labour Resources All the human resources required for the completion of all the activities are calculated using appropriate methods and is listed below. Resource histogram is also prepared for all the human resources required for the project. 1 44 28 16 75 76 54 6 Mate Mason Carpenter Fitter Mazdoor Helper Bhisti Painter Surveying & Layout 4 Trenching 1 6 PCC 1 1 1 Rebar 3 3 Shutter 3 3 Concrete 1 4 1 Deshutter 2 Curing Backfilling 2 Rebar 3 3 Shutter 6 6 Concrete 1 5 2 Deshutter 2 Curing PCC 1 1 1 Curing Rebar 3 3 Shutter 8 8 Concrete 1 4 2 Deshutter 3 Curing Staging 6 Shutter 9 9 Rebar 6 6 Concrete 1 10 3 Curing Destaging 9 Staging 2 Shutter 2 2 Rebar 1 1 Concrete 1 1 1 Curing Destaging 2 Masonry 16 16 16 Wiring Plumbing fixtures Plaster 18 24 24 Floor Finish 3 3 3 Door & window fixing Painting 6 Subcontracted Total Mandays Subcontracted Subcontracted Construction Activities Column Roof Slab Staircase Activity Foundation Plinth Ground Floor
  19. Page 19 of 20 Earned Value Analysis Earned Value Analysis for the project is done for 3 situations, 1. For 25% of the project duration (i.e., 34 days) 2. For 50% of the project duration (i.e., 65 days) 3. For 75% of the project duration (i.e., 98 days) The plot between SPI and CPI shows that the project is Behind Schedule and Over Budget.
  20. Page 20 of 20 Conclusion The Planning. Scheduling and Estimation of a residential house project using MS-excel software has been done along with the estimation of various quantities of materials and labour required for all the phases of the project has also been calculated. The human resources required are properly planned for all the activities. The total budget was properly estimated and it come around 6.4 lakhs.