10 Key Features of
Microsoft Project Plan
(MPP)
By: Sridhar SK, PMP
Purpose of Project Planning
 The objective of a project plan is to define the major tasks, estimate timelines and
resources, identify associated risks, negotiate commitments with stake holders,
and provide framework for review and control with a goal to deliver the project on
time & within budget
Project plan answers basic questions about the project:
 Why? - What is the problem or value proposition addressed by the project?
 What? - What is the work that will be performed for the project? What are the
deliverables ?
 Who? - Who will be involved and what will be their responsibilities within the
project? How will they be organized?
 When? - What is the project timeline and when will the milestones deliverable be
complete?
 By: Sridhar SK, PMP
Project Planning Metrics
SCOPE
Time Resource/Cost
Quality Risks
Customer
Expectations  By: Sridhar SK, PMP
Project Flow
Project Plan
Baseline
Initiate the work as per the
plan
Execute the plan
Project Charter
MonitorControl
 By: Sridhar SK, PMP
1. Project Information
PROJECT -> Project Information
 By: Sridhar SK, PMP
2. Set Calendar, Holidays and Working hours
PROJECT-> Change Working Time
PROJECT-> Change Working Time ->Options
 By: Sridhar SK, PMP
3. Adding Tasks, Setting Milestones
TASK-> Click on the editable grid to add the tasks
TASK- > Task Information ->Advanced - Mark task as milestone
 By: Sridhar SK, PMP
4. Setting Constrains
TASK- > Task Information ->General -> Auto Scheduled
TASK- > Task Information ->Advanced -> Constraint type
 By: Sridhar SK, PMP
5. Task Dependencies
TASK- > Task Information ->Predecessors
 By: Sridhar SK, PMP
6A. Adding Resource
RESOURCE-> Assign Resource
RESOURCE-> Assign Resource -> Resource Information->General
 By: Sridhar SK, PMP
6B. Adding Resource Rate
RESOURCE-> Assign Resource->Costs>Standard Rate
RESOURCE-> Assign Resource ->Costs
 By: Sridhar SK, PMP
7. Resource Usage/ Levelling
RESOURCE-> Resource Sheet >Resource Usage(Filter)
 By: Sridhar SK, PMP
8. Baseline
PROJECT->Set Baseline
 By: Sridhar SK, PMP
9. Progress Measurement with Gantt Chart
Gantt Chart->Add New Column > % Complete
 By: Sridhar SK, PMP
10. Report
REPORT->In Progress ->Milestone Report
 By: Sridhar SK, PMP
Thank You

More Related Content

What's hot

Chap 7.4 Control Cost
Chap 7.4   Control CostChap 7.4   Control Cost
Chap 7.4 Control CostAnand Bobade
 
PMP Chap 6 - Project Time management - Part1
PMP Chap 6 - Project Time management - Part1PMP Chap 6 - Project Time management - Part1
PMP Chap 6 - Project Time management - Part1Anand Bobade
 
Chap 6.1 Plan Schedule Management
Chap 6.1 Plan Schedule ManagementChap 6.1 Plan Schedule Management
Chap 6.1 Plan Schedule ManagementAnand Bobade
 
Chap 8.0 Quality Management Overview
Chap 8.0 Quality Management OverviewChap 8.0 Quality Management Overview
Chap 8.0 Quality Management OverviewAnand Bobade
 
Chap 8.1 Plan quality management
Chap 8.1 Plan quality managementChap 8.1 Plan quality management
Chap 8.1 Plan quality managementAnand Bobade
 
Chap 9.4 Develop Team
Chap 9.4  Develop TeamChap 9.4  Develop Team
Chap 9.4 Develop TeamAnand Bobade
 
PMP Exam Prep Module 1.pptx
PMP Exam Prep Module 1.pptxPMP Exam Prep Module 1.pptx
PMP Exam Prep Module 1.pptxAmjadAlk
 
Chap 7.1 Plan Cost Management
Chap 7.1  Plan Cost ManagementChap 7.1  Plan Cost Management
Chap 7.1 Plan Cost ManagementAnand Bobade
 
Bim Presentation
Bim PresentationBim Presentation
Bim Presentationrsalbin
 
Chap 6.2 Define Activity
Chap 6.2 Define ActivityChap 6.2 Define Activity
Chap 6.2 Define ActivityAnand Bobade
 
PMP Chap 7 - Project Cost Management - Part 2
PMP Chap 7 - Project Cost Management - Part 2PMP Chap 7 - Project Cost Management - Part 2
PMP Chap 7 - Project Cost Management - Part 2Anand Bobade
 
chap 4.4 Manage knowledge
chap 4.4 Manage knowledgechap 4.4 Manage knowledge
chap 4.4 Manage knowledgeAnand Bobade
 
Chap 9.5 Manage Team
Chap 9.5  Manage TeamChap 9.5  Manage Team
Chap 9.5 Manage TeamAnand Bobade
 
Chap 5.4 Create WBS
Chap 5.4 Create WBSChap 5.4 Create WBS
Chap 5.4 Create WBSAnand Bobade
 
Chap 7.2 Estimate Cost
Chap 7.2 Estimate CostChap 7.2 Estimate Cost
Chap 7.2 Estimate CostAnand Bobade
 
Chap 5.3 define scope
Chap 5.3 define scopeChap 5.3 define scope
Chap 5.3 define scopeAnand Bobade
 
Chap 4.6 Perform Integrated Change Control
Chap 4.6 Perform Integrated Change ControlChap 4.6 Perform Integrated Change Control
Chap 4.6 Perform Integrated Change ControlAnand Bobade
 

What's hot (20)

Chap 7.4 Control Cost
Chap 7.4   Control CostChap 7.4   Control Cost
Chap 7.4 Control Cost
 
PMP Chap 6 - Project Time management - Part1
PMP Chap 6 - Project Time management - Part1PMP Chap 6 - Project Time management - Part1
PMP Chap 6 - Project Time management - Part1
 
Chap 6.1 Plan Schedule Management
Chap 6.1 Plan Schedule ManagementChap 6.1 Plan Schedule Management
Chap 6.1 Plan Schedule Management
 
Chap 8.0 Quality Management Overview
Chap 8.0 Quality Management OverviewChap 8.0 Quality Management Overview
Chap 8.0 Quality Management Overview
 
Chap 8.1 Plan quality management
Chap 8.1 Plan quality managementChap 8.1 Plan quality management
Chap 8.1 Plan quality management
 
PMP MINDMAP
PMP MINDMAPPMP MINDMAP
PMP MINDMAP
 
Chap 9.4 Develop Team
Chap 9.4  Develop TeamChap 9.4  Develop Team
Chap 9.4 Develop Team
 
PMP Exam Prep Module 1.pptx
PMP Exam Prep Module 1.pptxPMP Exam Prep Module 1.pptx
PMP Exam Prep Module 1.pptx
 
Chap 7.1 Plan Cost Management
Chap 7.1  Plan Cost ManagementChap 7.1  Plan Cost Management
Chap 7.1 Plan Cost Management
 
Bim Presentation
Bim PresentationBim Presentation
Bim Presentation
 
Pmp formulas pmbok6
Pmp formulas pmbok6Pmp formulas pmbok6
Pmp formulas pmbok6
 
Chap 6.2 Define Activity
Chap 6.2 Define ActivityChap 6.2 Define Activity
Chap 6.2 Define Activity
 
PMP Chap 7 - Project Cost Management - Part 2
PMP Chap 7 - Project Cost Management - Part 2PMP Chap 7 - Project Cost Management - Part 2
PMP Chap 7 - Project Cost Management - Part 2
 
chap 4.4 Manage knowledge
chap 4.4 Manage knowledgechap 4.4 Manage knowledge
chap 4.4 Manage knowledge
 
Chap 9.5 Manage Team
Chap 9.5  Manage TeamChap 9.5  Manage Team
Chap 9.5 Manage Team
 
Chap 5.4 Create WBS
Chap 5.4 Create WBSChap 5.4 Create WBS
Chap 5.4 Create WBS
 
06 pmp time management exam
06 pmp time  management exam06 pmp time  management exam
06 pmp time management exam
 
Chap 7.2 Estimate Cost
Chap 7.2 Estimate CostChap 7.2 Estimate Cost
Chap 7.2 Estimate Cost
 
Chap 5.3 define scope
Chap 5.3 define scopeChap 5.3 define scope
Chap 5.3 define scope
 
Chap 4.6 Perform Integrated Change Control
Chap 4.6 Perform Integrated Change ControlChap 4.6 Perform Integrated Change Control
Chap 4.6 Perform Integrated Change Control
 

Similar to 10 key features of microsoft project plan (mpp)

Chap 6.4 Estimate Activity Duration
Chap 6.4 Estimate Activity DurationChap 6.4 Estimate Activity Duration
Chap 6.4 Estimate Activity DurationAnand Bobade
 
Microsoft Project Course with PMP Concepts
Microsoft Project Course with PMP ConceptsMicrosoft Project Course with PMP Concepts
Microsoft Project Course with PMP ConceptsHari Thapliyal
 
Project Management Discipline - Brown Bag CXB V03 Jun 2009 SAN
Project Management Discipline - Brown Bag CXB V03 Jun 2009 SANProject Management Discipline - Brown Bag CXB V03 Jun 2009 SAN
Project Management Discipline - Brown Bag CXB V03 Jun 2009 SANcj_barbosa
 
Project Management Project Assignment - Project Schedule & Resource Allocatio...
Project Management Project Assignment - Project Schedule & Resource Allocatio...Project Management Project Assignment - Project Schedule & Resource Allocatio...
Project Management Project Assignment - Project Schedule & Resource Allocatio...Shuchi Joshi
 
Project Management for Training - Class 2
Project Management for Training - Class 2Project Management for Training - Class 2
Project Management for Training - Class 2Jeffrey Keefer
 
Building a Credible Performance Measurement Baseline (v3)
Building a Credible Performance Measurement Baseline (v3)Building a Credible Performance Measurement Baseline (v3)
Building a Credible Performance Measurement Baseline (v3)Glen Alleman
 
NCV 3 Project Management Hands-On Support Slide Show - Module 5
NCV 3 Project Management Hands-On Support Slide Show - Module 5NCV 3 Project Management Hands-On Support Slide Show - Module 5
NCV 3 Project Management Hands-On Support Slide Show - Module 5Future Managers
 
Chap 9.3 Acquire Resources
Chap 9.3   Acquire ResourcesChap 9.3   Acquire Resources
Chap 9.3 Acquire ResourcesAnand Bobade
 
Project-Scope-Statement
Project-Scope-StatementProject-Scope-Statement
Project-Scope-StatementJeremy Heady
 
Software Project Management: Project Summary
Software Project Management: Project SummarySoftware Project Management: Project Summary
Software Project Management: Project SummaryMinhas Kamal
 

Similar to 10 key features of microsoft project plan (mpp) (20)

Chap 6.4 Estimate Activity Duration
Chap 6.4 Estimate Activity DurationChap 6.4 Estimate Activity Duration
Chap 6.4 Estimate Activity Duration
 
C.V of Prasanta
C.V of PrasantaC.V of Prasanta
C.V of Prasanta
 
Ch 8(spi)cm mi-pp
Ch 8(spi)cm mi-ppCh 8(spi)cm mi-pp
Ch 8(spi)cm mi-pp
 
3 project life cycle
3   project life cycle3   project life cycle
3 project life cycle
 
Microsoft Project Course with PMP Concepts
Microsoft Project Course with PMP ConceptsMicrosoft Project Course with PMP Concepts
Microsoft Project Course with PMP Concepts
 
Project Management Discipline - Brown Bag CXB V03 Jun 2009 SAN
Project Management Discipline - Brown Bag CXB V03 Jun 2009 SANProject Management Discipline - Brown Bag CXB V03 Jun 2009 SAN
Project Management Discipline - Brown Bag CXB V03 Jun 2009 SAN
 
Ravi teja
Ravi tejaRavi teja
Ravi teja
 
Ravi teja
Ravi tejaRavi teja
Ravi teja
 
Project Management Project Assignment - Project Schedule & Resource Allocatio...
Project Management Project Assignment - Project Schedule & Resource Allocatio...Project Management Project Assignment - Project Schedule & Resource Allocatio...
Project Management Project Assignment - Project Schedule & Resource Allocatio...
 
Project Management for Training - Class 2
Project Management for Training - Class 2Project Management for Training - Class 2
Project Management for Training - Class 2
 
Microsot project basics
Microsot project basicsMicrosot project basics
Microsot project basics
 
Session 8 4th edition PMP
Session 8 4th edition PMPSession 8 4th edition PMP
Session 8 4th edition PMP
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 
Building a Credible Performance Measurement Baseline (v3)
Building a Credible Performance Measurement Baseline (v3)Building a Credible Performance Measurement Baseline (v3)
Building a Credible Performance Measurement Baseline (v3)
 
NCV 3 Project Management Hands-On Support Slide Show - Module 5
NCV 3 Project Management Hands-On Support Slide Show - Module 5NCV 3 Project Management Hands-On Support Slide Show - Module 5
NCV 3 Project Management Hands-On Support Slide Show - Module 5
 
Chap 9.3 Acquire Resources
Chap 9.3   Acquire ResourcesChap 9.3   Acquire Resources
Chap 9.3 Acquire Resources
 
PG Diploma in PPM
PG Diploma in PPMPG Diploma in PPM
PG Diploma in PPM
 
Project-Scope-Statement
Project-Scope-StatementProject-Scope-Statement
Project-Scope-Statement
 
Practical project management based on PMBOK5
Practical project management based on PMBOK5Practical project management based on PMBOK5
Practical project management based on PMBOK5
 
Software Project Management: Project Summary
Software Project Management: Project SummarySoftware Project Management: Project Summary
Software Project Management: Project Summary
 

Recently uploaded

The Psychology Of Motivation - Richard Brown
The Psychology Of Motivation - Richard BrownThe Psychology Of Motivation - Richard Brown
The Psychology Of Motivation - Richard BrownSandaliGurusinghe2
 
digital Human resource management presentation.pdf
digital Human resource management presentation.pdfdigital Human resource management presentation.pdf
digital Human resource management presentation.pdfArtiSrivastava23
 
Beyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable developmentBeyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable developmentNimot Muili
 
internship thesis pakistan aeronautical complex kamra
internship thesis pakistan aeronautical complex kamrainternship thesis pakistan aeronautical complex kamra
internship thesis pakistan aeronautical complex kamraAllTops
 
Siliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime Siliguri
Siliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime SiliguriSiliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime Siliguri
Siliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime Siligurimeghakumariji156
 
International Ocean Transportation p.pdf
International Ocean Transportation p.pdfInternational Ocean Transportation p.pdf
International Ocean Transportation p.pdfAlejandromexEspino
 
How Software Developers Destroy Business Value.pptx
How Software Developers Destroy Business Value.pptxHow Software Developers Destroy Business Value.pptx
How Software Developers Destroy Business Value.pptxAaron Stannard
 
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professional
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professionalW.H.Bender Quote 62 - Always strive to be a Hospitality Service professional
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professionalWilliam (Bill) H. Bender, FCSI
 
Information Technology Project Management, Revised 7th edition test bank.docx
Information Technology Project Management, Revised 7th edition test bank.docxInformation Technology Project Management, Revised 7th edition test bank.docx
Information Technology Project Management, Revised 7th edition test bank.docxssuserf63bd7
 
Gautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Gautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot ModelGautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Gautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot ModelNitya salvi
 
Persuasive and Communication is the art of negotiation.
Persuasive and Communication is the art of negotiation.Persuasive and Communication is the art of negotiation.
Persuasive and Communication is the art of negotiation.aruny7087
 
Marketing Management 16th edition by Philip Kotler test bank.docx
Marketing Management 16th edition by Philip Kotler test bank.docxMarketing Management 16th edition by Philip Kotler test bank.docx
Marketing Management 16th edition by Philip Kotler test bank.docxssuserf63bd7
 
Safety T fire missions army field Artillery
Safety T fire missions army field ArtillerySafety T fire missions army field Artillery
Safety T fire missions army field ArtilleryKennethSwanberg
 

Recently uploaded (14)

Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTECAbortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
 
The Psychology Of Motivation - Richard Brown
The Psychology Of Motivation - Richard BrownThe Psychology Of Motivation - Richard Brown
The Psychology Of Motivation - Richard Brown
 
digital Human resource management presentation.pdf
digital Human resource management presentation.pdfdigital Human resource management presentation.pdf
digital Human resource management presentation.pdf
 
Beyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable developmentBeyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable development
 
internship thesis pakistan aeronautical complex kamra
internship thesis pakistan aeronautical complex kamrainternship thesis pakistan aeronautical complex kamra
internship thesis pakistan aeronautical complex kamra
 
Siliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime Siliguri
Siliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime SiliguriSiliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime Siliguri
Siliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime Siliguri
 
International Ocean Transportation p.pdf
International Ocean Transportation p.pdfInternational Ocean Transportation p.pdf
International Ocean Transportation p.pdf
 
How Software Developers Destroy Business Value.pptx
How Software Developers Destroy Business Value.pptxHow Software Developers Destroy Business Value.pptx
How Software Developers Destroy Business Value.pptx
 
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professional
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professionalW.H.Bender Quote 62 - Always strive to be a Hospitality Service professional
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professional
 
Information Technology Project Management, Revised 7th edition test bank.docx
Information Technology Project Management, Revised 7th edition test bank.docxInformation Technology Project Management, Revised 7th edition test bank.docx
Information Technology Project Management, Revised 7th edition test bank.docx
 
Gautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Gautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot ModelGautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Gautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot Model
 
Persuasive and Communication is the art of negotiation.
Persuasive and Communication is the art of negotiation.Persuasive and Communication is the art of negotiation.
Persuasive and Communication is the art of negotiation.
 
Marketing Management 16th edition by Philip Kotler test bank.docx
Marketing Management 16th edition by Philip Kotler test bank.docxMarketing Management 16th edition by Philip Kotler test bank.docx
Marketing Management 16th edition by Philip Kotler test bank.docx
 
Safety T fire missions army field Artillery
Safety T fire missions army field ArtillerySafety T fire missions army field Artillery
Safety T fire missions army field Artillery
 

10 key features of microsoft project plan (mpp)

  • 1. 10 Key Features of Microsoft Project Plan (MPP) By: Sridhar SK, PMP
  • 2. Purpose of Project Planning  The objective of a project plan is to define the major tasks, estimate timelines and resources, identify associated risks, negotiate commitments with stake holders, and provide framework for review and control with a goal to deliver the project on time & within budget Project plan answers basic questions about the project:  Why? - What is the problem or value proposition addressed by the project?  What? - What is the work that will be performed for the project? What are the deliverables ?  Who? - Who will be involved and what will be their responsibilities within the project? How will they be organized?  When? - What is the project timeline and when will the milestones deliverable be complete?  By: Sridhar SK, PMP
  • 3. Project Planning Metrics SCOPE Time Resource/Cost Quality Risks Customer Expectations  By: Sridhar SK, PMP
  • 4. Project Flow Project Plan Baseline Initiate the work as per the plan Execute the plan Project Charter MonitorControl  By: Sridhar SK, PMP
  • 5. 1. Project Information PROJECT -> Project Information  By: Sridhar SK, PMP
  • 6. 2. Set Calendar, Holidays and Working hours PROJECT-> Change Working Time PROJECT-> Change Working Time ->Options  By: Sridhar SK, PMP
  • 7. 3. Adding Tasks, Setting Milestones TASK-> Click on the editable grid to add the tasks TASK- > Task Information ->Advanced - Mark task as milestone  By: Sridhar SK, PMP
  • 8. 4. Setting Constrains TASK- > Task Information ->General -> Auto Scheduled TASK- > Task Information ->Advanced -> Constraint type  By: Sridhar SK, PMP
  • 9. 5. Task Dependencies TASK- > Task Information ->Predecessors  By: Sridhar SK, PMP
  • 10. 6A. Adding Resource RESOURCE-> Assign Resource RESOURCE-> Assign Resource -> Resource Information->General  By: Sridhar SK, PMP
  • 11. 6B. Adding Resource Rate RESOURCE-> Assign Resource->Costs>Standard Rate RESOURCE-> Assign Resource ->Costs  By: Sridhar SK, PMP
  • 12. 7. Resource Usage/ Levelling RESOURCE-> Resource Sheet >Resource Usage(Filter)  By: Sridhar SK, PMP
  • 14. 9. Progress Measurement with Gantt Chart Gantt Chart->Add New Column > % Complete  By: Sridhar SK, PMP
  • 15. 10. Report REPORT->In Progress ->Milestone Report  By: Sridhar SK, PMP