17WC:
BRAND NEW WATER TREATMENT SYSTEM FOR AN
EXISTING POWER PLANT. A WATER SAVING PROJECT
Mr. Karim Azat & Mr. Juan de Beristain
57951
August 30 – September 4, 2015 | San
Diego California
Thermoelectric power plant with two combined cycles 740 MWe
Water source: 18 deep wells with variable sulfate (SO4
-2) concentration
Cooling towers typical make-up with 350 ppm sulfate = 760 m3/h
Blow-down must comply with regulation of maximum 1,000 ppm sulfate
During drought condition wells´ sulfate concentration increases
As concentration increases, i.e. 550 ppm sulfate, make-up water must be
increased up to 1,140 m3/h to comply with blowdown quality requirement
At this level water from wells is not enough and a solution must be found.
BACKGROUND
August 30 – September 4, 2015 | San
Diego California
BACKGROUND
Evaporation: ~ 456 m3/h
Blow-Down: ~ 684 m3/h
Total Make-Up: ~ 1140 m3/h
Insufficient water from wells
August 30 – September 4, 2015 | San
Diego California
Initially implemented solutions
Increase water supply from external wells
Blow-down treatment: salinity reduction to allow disposal
Selected solution, Make-up treatment
Salinity reduction to increase concentration cycles & reduce blow-
down
ON THE WAY TO THE SOLUTION
August 30 – September 4, 2015 | San
Diego California
EXPECTED SCENARIO
Evaporation: ~ 456 m3/h
Blow-down: ~ 50 m3/h
RO Reject: ~ 60 m3/h
Total consumption: ~ 566 m3/h
Self-sufficient water supply.
Blow Down
Reduction 92,7%
Water Reduction
47,4%
August 30 – September 4, 2015 | San
Diego California
Feed both cooling towers with permeate water to reduce blow-
down to a minimum
Reverse Osmosis as water treatment technology
Permeate water 540 m3/h
60 m3/h of concentrate stream (maximum disposal capacity)
Inlet flow 600 m3/h 90% recovery rate
Permeate water conductivity less than 50 μS/cm
Permeate water sulfate content less than 20 ppm
SOLUTION DESCRIPTION
August 30 – September 4, 2015 | San
Diego California
CHALLENGES & SOLUTIONS
High recovery rate
Reduced lay-out
High flexibility & variable quality of water supply
No new chemicals nor CIP procedures allowed inside the
complex
Bonus challenge: replace boiler water treatment plant
August 30 – September 4, 2015 | San
Diego California
CHALLENGES & SOLUTIONS: HIGH
RECOVERY RATE REQUIRED
90% global recovery rate on cooling water production system
First & second stage at 80% recovery rate, third stage at 50%
recovery rate
Third stage = Sacrifice stage
Scaling potential bounded to the third stage
Strict monitoring of critical parameters to trigger preventive CIP
procedures at the third stage
August 30 – September 4, 2015 | San
Diego California
CHALLENGES & SOLUTIONS: LAY-OUT
New plant to be installed in the same area where the previous boiler
water plant used to be (Ion Exchange, 30 m3/h capacity, ~ 500 m2 useful area)
N+1 redundancy required for all critical components (even RO trains)
Future expansion for the new boiler water plant (+50%)
How was this achieved?
Horizontal filters
Operating platforms on the top of RO skids
Intensive use of pipe trenches
August 30 – September 4, 2015 | San
Diego California
CHALLENGES & SOLUTIONS: HIGH FLEXIBILITY
& VARIABLE QUALITY OF WATER SUPPLY
Make-up water demand is variable around the year
Source water quality is expected to continue to change, so plant must be
able to operate under different salinity conditions
How was this achieved?
Operating points (25%, 50%, 75%, 100%)
Able to operate at up to 50% more pressure, from low to high pressure membranes
Pumping groups & other components designed to face such demanding conditions
August 30 – September 4, 2015 | San
Diego California
15 m3/h @ 18 MΩcm
< 3 ppb Silica
100% availability
Zero chemical consumption
How was this achieved?
Second pass RO fed from cooling water treatment plant (first pass)
EDI as polisher
Two trains of 15 m3/h each. Design allows to operate both trains simultaneously
Inline Silica measurement at critical points
REPLACE IX BOILER WATER TREATMENT
PLANT WITH RO+EDI
August 30 – September 4, 2015 | San
Diego California
RESULTS & SUMMARY
Cooling Water Treatment Plant
Product < 20 µS/cm
Lack of space: SOLVED
High recovery rate (90%)
Low OPEX (40% lower than expected)
Cooling Towers System
No pH correction (H2SO4) at the cooling towers
No biocides
No anti-scalant
And what about
water saving…?
August 30 – September 4, 2015 | San
Diego California
RESULTS & SUMMARY: COOLING WATER SYSTEM
Make Up = 350 m3/hr
Blow Down = 175 m3/hr
August 30 – September 4, 2015 | San
Diego California
RESULTS & SUMMARY: COOLING WATER SYSTEM
Make Up = 175 m3/hr
Blow Down = 0 m3/hr
50% reduction
August 30 – September 4, 2015 | San
Diego California
PICTURES
August 30 – September 4, 2015 | San
Diego California
PICTURES
August 30 – September 4, 2015 | San
Diego California
PICTURES
August 30 – September 4, 2015 | San
Diego California
THANKS FOR YOUR ATTENTION
Notes de l'éditeur
KA:
Consumo Agua TE 97%
Aumento Sulfatos nos obligó
Enfasis en 1,7 ciclos de TE (Diseño de 4)
Ajuste continuo del equipo de Osmosis Inversa del Blow Down
Incremento de ciclos de 1,7 a 10 veces
Imposibilidad de mayor descarte
Agregar fotos de las trincheras
Imposibilidad de construir estanques de acumulación intermedios por falta de espacio -> booster systems
VALE LA PENA PONER ESTE GRAFICO???? ES DIFERENTE A LOS RESULTADOS REALES OBTENIDOS