Publicité

IDA17WC-57951_Azat Rev1.pptx

21 Mar 2023
Publicité

Contenu connexe

Similaire à IDA17WC-57951_Azat Rev1.pptx(20)

Publicité

IDA17WC-57951_Azat Rev1.pptx

  1. 17WC: BRAND NEW WATER TREATMENT SYSTEM FOR AN EXISTING POWER PLANT. A WATER SAVING PROJECT Mr. Karim Azat & Mr. Juan de Beristain 57951
  2. August 30 – September 4, 2015 | San Diego California  Thermoelectric power plant with two combined cycles 740 MWe  Water source: 18 deep wells with variable sulfate (SO4 -2) concentration  Cooling towers typical make-up with 350 ppm sulfate = 760 m3/h  Blow-down must comply with regulation of maximum 1,000 ppm sulfate  During drought condition wells´ sulfate concentration increases  As concentration increases, i.e. 550 ppm sulfate, make-up water must be increased up to 1,140 m3/h to comply with blowdown quality requirement  At this level water from wells is not enough and a solution must be found. BACKGROUND
  3. August 30 – September 4, 2015 | San Diego California BACKGROUND Evaporation: ~ 456 m3/h Blow-Down: ~ 684 m3/h Total Make-Up: ~ 1140 m3/h Insufficient water from wells
  4. August 30 – September 4, 2015 | San Diego California  Initially implemented solutions  Increase water supply from external wells  Blow-down treatment: salinity reduction to allow disposal  Selected solution, Make-up treatment  Salinity reduction to increase concentration cycles & reduce blow- down ON THE WAY TO THE SOLUTION
  5. August 30 – September 4, 2015 | San Diego California EXPECTED SCENARIO Evaporation: ~ 456 m3/h Blow-down: ~ 50 m3/h RO Reject: ~ 60 m3/h Total consumption: ~ 566 m3/h Self-sufficient water supply. Blow Down Reduction 92,7% Water Reduction 47,4%
  6. August 30 – September 4, 2015 | San Diego California  Feed both cooling towers with permeate water to reduce blow- down to a minimum  Reverse Osmosis as water treatment technology  Permeate water 540 m3/h  60 m3/h of concentrate stream (maximum disposal capacity)  Inlet flow 600 m3/h 90% recovery rate  Permeate water conductivity less than 50 μS/cm  Permeate water sulfate content less than 20 ppm SOLUTION DESCRIPTION
  7. August 30 – September 4, 2015 | San Diego California CHALLENGES & SOLUTIONS  High recovery rate  Reduced lay-out  High flexibility & variable quality of water supply  No new chemicals nor CIP procedures allowed inside the complex  Bonus challenge: replace boiler water treatment plant
  8. August 30 – September 4, 2015 | San Diego California CHALLENGES & SOLUTIONS: HIGH RECOVERY RATE REQUIRED  90% global recovery rate on cooling water production system  First & second stage at 80% recovery rate, third stage at 50% recovery rate  Third stage = Sacrifice stage  Scaling potential bounded to the third stage  Strict monitoring of critical parameters to trigger preventive CIP procedures at the third stage
  9. August 30 – September 4, 2015 | San Diego California CHALLENGES & SOLUTIONS: LAY-OUT  New plant to be installed in the same area where the previous boiler water plant used to be (Ion Exchange, 30 m3/h capacity, ~ 500 m2 useful area)  N+1 redundancy required for all critical components (even RO trains)  Future expansion for the new boiler water plant (+50%) How was this achieved?  Horizontal filters  Operating platforms on the top of RO skids  Intensive use of pipe trenches
  10. August 30 – September 4, 2015 | San Diego California CHALLENGES & SOLUTIONS: HIGH FLEXIBILITY & VARIABLE QUALITY OF WATER SUPPLY  Make-up water demand is variable around the year  Source water quality is expected to continue to change, so plant must be able to operate under different salinity conditions How was this achieved?  Operating points (25%, 50%, 75%, 100%)  Able to operate at up to 50% more pressure, from low to high pressure membranes  Pumping groups & other components designed to face such demanding conditions
  11. August 30 – September 4, 2015 | San Diego California  15 m3/h @ 18 MΩcm  < 3 ppb Silica  100% availability  Zero chemical consumption How was this achieved?  Second pass RO fed from cooling water treatment plant (first pass)  EDI as polisher  Two trains of 15 m3/h each. Design allows to operate both trains simultaneously  Inline Silica measurement at critical points REPLACE IX BOILER WATER TREATMENT PLANT WITH RO+EDI
  12. August 30 – September 4, 2015 | San Diego California RESULTS & SUMMARY Cooling Water Treatment Plant  Product < 20 µS/cm  Lack of space: SOLVED  High recovery rate (90%)  Low OPEX (40% lower than expected) Cooling Towers System  No pH correction (H2SO4) at the cooling towers  No biocides  No anti-scalant And what about water saving…?
  13. August 30 – September 4, 2015 | San Diego California RESULTS & SUMMARY: COOLING WATER SYSTEM Make Up = 350 m3/hr Blow Down = 175 m3/hr
  14. August 30 – September 4, 2015 | San Diego California RESULTS & SUMMARY: COOLING WATER SYSTEM Make Up = 175 m3/hr Blow Down = 0 m3/hr 50% reduction
  15. August 30 – September 4, 2015 | San Diego California PICTURES
  16. August 30 – September 4, 2015 | San Diego California PICTURES
  17. August 30 – September 4, 2015 | San Diego California PICTURES
  18. August 30 – September 4, 2015 | San Diego California THANKS FOR YOUR ATTENTION

Notes de l'éditeur

  1. KA: Consumo Agua TE 97% Aumento Sulfatos nos obligó
  2. Enfasis en 1,7 ciclos de TE (Diseño de 4)
  3. Ajuste continuo del equipo de Osmosis Inversa del Blow Down
  4. Incremento de ciclos de 1,7 a 10 veces
  5. Imposibilidad de mayor descarte
  6. Agregar fotos de las trincheras
  7. Imposibilidad de construir estanques de acumulación intermedios por falta de espacio -> booster systems
  8. VALE LA PENA PONER ESTE GRAFICO???? ES DIFERENTE A LOS RESULTADOS REALES OBTENIDOS
  9. Ciclos de concentración = 2
Publicité