SlideShare a Scribd company logo
1 of 2
Download to read offline
OBRA:
PROPIETARIO: MUNICIPALIDAD PROVINCIAL DE ANGARAES
RECURSOS PROPIOS PROVIAS DESCENTRALIZADO
MODALIDAD DE EJECUCIÓN: CONTRATA
EJECUTA: CONSORCIO UNÑEZ
SUPERVISOR DE OBRA ING. GUERRA A. GUERRA CORONEL
RESIDENTE: ING. GUIDO ROGER HUAYLLAS COSME
METRADO VALOR S/. % METRADO VALOR S/. % METRADO VALOR S/.
%
METRADO VALOR S/.
%
METRADO VALOR S/.
%
METRADO VALOR S/.
%
METRADO VALOR S/. % VALOR S/.
01.00.00
01.01.00 UND 1,00 6.274,96 6.274,96 1,00 6.274,96 100,00% - 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 1,00 6.274,96 100,00% 6.274,96
01.02.00 GLB 1,00 5.000,00 5.000,00 0,00 0,00% 0,75 3.750,00 75,00% 0,15 750,00 15,00% 0,00 0,00% 0,10 500,00 10,00% 0,00 0,00% 1,00 5.000,00 100,00% 5.000,00
01.03.00 UND 1,00 464,81 464,81 1,00 464,81 100,00% - 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 1,00 464,81 100,00% 464,81
01.04.00 KM 10,92 568,38 6.206,71 0,00 0,00% 9,28 5.274,57 84,98% 0,00 0,00% 0,00 0,00% 1,64 932,14 15,02% 0,00 0,00% 10,92 6.206,71 100,00% 6.206,71
01.05.00 M3 31,91 28,44 907,52 0,00 0,00 0,00% 31,91 907,52 100,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 31,91 907,52 100,00% 907,52
02.00.00
02.01.00
02.01.01 M3 13.949,55 4,02 56.077,19 0,00 0,00% 11.770,55 47.317,61 84,38% - 0,00 0,00% 0,00 0,00% 2.179,00 8.759,58 15,62% 0,00 0,00% 13.949,55 56.077,19 100,00% 56.077,19
02.02.00
02.02.01 M3 1.484,00 18,75 27.825,00 0,00 0,00% 1.318,09 24.714,19 88,82% 165,91 3.110,81 11,18% 0,00 0,00% 0,00 0,00% - 0,00 0,00% 1.484,00 27.825,00 100,00% 27.825,00
02.02.02 M3 1.060,00 4,20 4.452,00 0,00 0,00% 941,49 3.954,26 88,82% 118,51 497,74 11,18% 0,00 0,00% 0,00 0,00% - 0,00 0,00% 1.060,00 4.452,00 100,00% 4.452,00
02.03.00
02.03.01 M3 790,19 26,39 20.853,11 0,00 0,00% 698,45 18.432,10 88,39% 91,74 2.421,02 11,61% 0,00 0,00% 0,00 0,00% - 0,00 0,00% 790,19 20.853,11 100,00% 20.853,11
02.03.02 M3 564,42 4,48 2.528,60 0,00 0,00% 498,89 2.235,03 88,39% 65,53 293,57 11,61% 0,00 0,00% 0,00 0,00% - 0,00 0,00% 564,42 2.528,60 100,00% 2.528,60
02.04.00
02.04.01 M3 2.936,22 5,16 15.150,90 0,00 0,00% 2.638,59 13.615,12 89,86% 297,63 1.535,77 10,14% 0,00 0,00% 0,00 0,00% - 0,00 0,00% 2.936,22 15.150,89 100,00% 15.150,89
02.04.02 M2 43.697,96 1,22 53.311,51 0,00 0,00% 39.305,16 47.952,30 89,95% - 0,00 0,00% 0,00 0,00% 2.354,36 2.872,32 5,39% 2.038,44 2.486,90 4,66% 43.697,96 53.311,52 100,00% 53.311,52
02.05.00
02.05.01 M3 9.478,02 4,57 43.314,55 0,00 0,00% 8.046,31 36.771,64 84,89% - 0,00 0,00% 0,00 0,00% 0,00 0,00% 1.431,71 6.542,91 15,11% 9.478,02 43.314,55 100,00% 43.314,55
03.00.00
03.01.00 M3 8.369,73 10,26 85.873,43 0,00 0,00% 1.693,94 17.379,82 20,24% 0,00 0,00% 6.357,45 65.227,44 75,96% 318,34 3.266,17 3,80% 0,00 0,00% 8.369,73 85.873,43 100,00% 85.873,43
03.02.00 M3 8.369,73 3,53 29.545,15 0,00 0,00% 1.275,45 4.502,34 15,24% 0,00 0,00% 4.975,31 17.562,84 59,44% 2.118,97 7.479,96 25,32% 0,00 0,00% 8.369,73 29.545,15 100,00% 29.545,15
03.03.00 M3 8.369,73 2,26 18.915,59 0,00 0,00% 0,00 0,00% 0,00 0,00% 5.631,99 12.728,30 67,29% 2.737,74 6.187,29 32,71% 0,00 0,00% 8.369,73 18.915,59 100,00% 18.915,59
03.04.00 M3 8.369,73 4,78 40.007,31 0,00 0,00% 0,00 0,00% 0,00 0,00% 5.598,51 26.760,88 66,89% 2.771,22 13.246,43 33,11% 0,00 0,00% 8.369,73 40.007,31 100,00% 40.007,31
03.05.00 M2 42.921,69 1,82 78.117,48 0,00 0,00% 0,00 0,00% 0,00 0,00% 28.208,13 51.338,80 65,72% 14.713,56 26.778,68 34,28% 0,00 0,00% 42.921,69 78.117,48 100,00% 78.117,48
04.00.00
04.01.00 KM 21,85 755,46 16.506,80 0,00 0,00% 0,00 0,00% 0,00 0,00% 12,01 9.073,07 54,97% 9,84 7.433,73 45,03% 0,00 0,00% 21,85 16.506,80 100,00% 16.506,80
05.00.00
05.01.00
05.01.01
05.01.01.01 M2 553,28 1,46 807,79 0,00 0,00% 553,28 807,79 100,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 553,28 807,79 100,00% 807,79
05.01.01.02 M2 553,28 2,13 1.178,49 0,00 0,00% 553,28 1.178,49 100,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 553,28 1.178,49 100,00% 1.178,49
05.01.02
05.01.02.01 M3 1.833,94 2,62 4.804,92 0,00 0,00% 1.833,94 4.804,92 100,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 1.833,94 4.804,92 100,00% 4.804,92
05.01.02.02 M3 239,90 21,65 5.193,84 0,00 0,00% 239,90 5.193,84 100,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 239,90 5.193,84 100,00% 5.193,84
05.01.02.03 M3 1.833,94 4,43 8.124,35 0,00 0,00% 1.833,94 8.124,35 100,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 1.833,94 8.124,35 100,00% 8.124,35
05.01.02.04 M3 34,86 156,13 5.442,69 0,00 0,00% 34,86 5.442,69 100,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 34,86 5.442,69 100,00% 5.442,69
05.01.03
05.01.03.01 M3 123,17 374,33 46.106,23 0,00 0,00% 30,55 11.435,78 24,80% 92,25 34.531,94 74,90% 0,00 0,00% 0,37 138,50 0,30% 0,00 0,00% 123,17 46.106,23 100,00% 46.106,23
05.01.03.02 M2 71,37 32,96 2.352,36 0,00 0,00% 17,70 583,39 24,80% 51,27 1.689,86 71,84% 0,00 0,00% 2,40 79,10 3,36% 0,00 0,00% 71,37 2.352,36 100,00% 2.352,36
05.01.03.03 M3 17,68 286,36 5.062,84 0,00 0,00% 0,00 0,00% 5,31 1.520,57 30,03% 0,00 0,00% 12,37 3.542,27 69,97% 0,00 0,00% 17,68 5.062,84 100,00% 5.062,84
05.01.04
05.01.04.01 M3 100,18 449,20 45.000,86 0,00 0,00% 25,15 11.297,38 25,10% 70,34 31.596,73 70,21% 0,00 0,00% 4,69 2.106,75 4,68% 0,00 0,00% 100,18 45.000,86 100,00% 45.000,86
05.01.04.02 M2 500,92 32,96 16.510,32 0,00 0,00% 125,75 4.144,72 25,10% 352,24 11.609,83 70,32% 0,00 0,00% 22,93 755,77 4,58% 0,00 0,00% 500,92 16.510,32 100,00% 16.510,32
05.01.04.03 M3 2.874,39 6,37 18.309,86 0,00 0,00% 1.407,01 8.962,65 48,95% 1.324,52 8.437,19 46,08% 0,00 0,00% 142,86 910,02 4,97% 0,00 0,00% 2.874,39 18.309,86 100,00% 18.309,86
TRANSPORTE DE MATERIALES DE LASTRADO DM=2.56KM
AFIRMADO BASE GRANULAR (E=15CM)
ACERO DE REFUERZO FY=4200 KG/CM2
TRAZO Y REPLANTEO
CONFORMACION DE TERRAPLENES CON MATERIAL PROPIO
PERFILADO Y COMPACTACION DE LA SUB RASANTE EN ZONAS DE CORTE
EXTRACCION Y APILAMIENTO CON MAQUINARIA EN CANTERA
ZARANDEO
CARGUIO CON MAQUINARIA DE MATERIAL DE LASTRADO
PAVIMENTOS
CORTE EN ROCA FIJA
CORTE EN ROCA FIJA (PÉRFORACION Y DISPARO)
LIMPIEZA DE PLANTAFORMA Y DESQUINCHE DE TALUD EN ROCA FIJA
CONFORMACION DE TERRAPLENES O RELLENOS
CORTE DE MATERIAL SUELTO
CORTE EN MATERIAL SUELTO CON MAQUINARIA (INC. PEINADO DE TALUD)
CORTE EN ROCA SUELTA (PÉRFORACION Y DISPARO)
LIMPIEZA DE PLANTAFORMA Y DESQUINCHE DE TALUD EN ROCA SUELTA
CORTE EN ROCA SUELTA
LIQUIDACION DE OBRA
VALORIZACION Nº 3 TOTAL ACUMULADO
PRESUPUESTO EJECUTADO
PRESUP.
VALORIZACION Nº 2
P.UNIT.
VALORIZACION Nº1
CONTROL
CAMPAMENTO PROVISIONALES DE LA OBRA DE 8M X 10M
MOVILIZACION Y DESMOVILIZACION
ELIMINACION DE MATERIAL EXCEDENTE (CARGUIO) DM=0.85KM
ELIMINACION DE MATERIAL EXCEDENTE
VALORIZACION Nº 5
CARTEL DE IDENTIFICACION DE OBRA 3.60 m X 7.20 m.
TRAZO Y REPLANTEO DURANTE LA EJECUCION
DEMOLICION DE ALCANTARILLAS EXISTENTES
MOVIMIENTO DE TIERRAS
EXCAVACION PARA ESTRUCTURAS (MANUAL)
RELLENO CON MATERIAL PROPIO
CONCRETO F´C=210KG/CM2 (LOSA TAPA)
VALORIZACION Nº 4 VALORIZACION Nº 6
CUNETAS
CONFORMACION DE CUNETAS
RELLENO CON MATERIAL GRANULAR
LIMPIEZA DE TERRENO MANUAL
ALCANTARILLAS L=4.20M (28 UND)
OBRAS DE ARTE
TRABAJOS PRELIMINARES
ELIMINACION DE MATERIAL EXCEDENTE D MAX=30M
OBRAS DE CONCRETO SIMPLE
CONCRETO CICLOPIO FC=175KG/CM2+30%PM-ESTRIBOS Y ALETAS
ENCONFRADO Y DESENCOFRADO DE ESTRIBOS Y ALERO
EMBOQUILLADO DE PIEDRA CON MORTERO
OBRAS DE CONCRETO ARMADO
ITEM DESCRIPCIÓN
PRESUPUESTO OFERTADO
UND METRADO
ENCOFRADO Y DESENCOFRADO
OBRAS PRELIMINARES
TRABAJOS PRELIMINARES
“MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD DEL CAMINO VECINAL TRAMO: SANTA ELENA – PITIMPATA – PATAPATA – LLUMCHI, DISTRITO DE LIRCAY, PROVINCIA DE ANGARAES - HUANCAVELICA”
OBRA:
PROPIETARIO: MUNICIPALIDAD PROVINCIAL DE ANGARAES
RECURSOS PROPIOS PROVIAS DESCENTRALIZADO
MODALIDAD DE EJECUCIÓN: CONTRATA
EJECUTA: CONSORCIO UNÑEZ
SUPERVISOR DE OBRA ING. GUERRA A. GUERRA CORONEL
RESIDENTE: ING. GUIDO ROGER HUAYLLAS COSME
METRADO VALOR S/. % METRADO VALOR S/. % METRADO VALOR S/.
%
METRADO VALOR S/.
%
METRADO VALOR S/.
%
METRADO VALOR S/.
%
METRADO VALOR S/. % VALOR S/.
LIQUIDACION DE OBRA
VALORIZACION Nº 3 TOTAL ACUMULADO
PRESUPUESTO EJECUTADO
PRESUP.
VALORIZACION Nº 2
P.UNIT.
VALORIZACION Nº1
CONTROL
VALORIZACION Nº 5
VALORIZACION Nº 4 VALORIZACION Nº 6
ITEM DESCRIPCIÓN
PRESUPUESTO OFERTADO
UND METRADO
OBRAS PRELIMINARES
“MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD DEL CAMINO VECINAL TRAMO: SANTA ELENA – PITIMPATA – PATAPATA – LLUMCHI, DISTRITO DE LIRCAY, PROVINCIA DE ANGARAES - HUANCAVELICA”
05.01.05
05.01.05.01 M 123,20 461,25 56.826,00 0,00 0,00% 123,20 56.826,00 100,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 123,20 56.826,00 100,00% 56.826,00
05.01.06
05.01.06.01 M2 500,92 11,66 5.840,73 0,00 0,00% 0,00 0,00% 450,67 5.254,81 89,97% 0,00 0,00% 50,25 585,92 10,03% 0,00 0,00% 500,92 5.840,73 100,00% 5.840,73
05.01.06.02 M2 174,29 284,89 49.653,48 0,00 0,00% 0,00 0,00% 110,84 31.577,21 63,60% 0,00 0,00% 63,45 18.076,27 36,40% 0,00 0,00% 174,29 49.653,48 100,00% 49.653,48
05.01.07
05.01.07.01 M2 500,92 25,11 12.578,10 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 500,92 12.578,10 100,00% 0,00 0,00% 500,92 12.578,10 100,00% 12.578,10
05.02.00
05.02.01
05.02.01.01 M2 111,72 1,46 163,11 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 111,72 163,11 100,00% 111,72 163,11 100,00% 163,11
05.02.01.02 M2 111,72 18,09 2.021,01 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 111,72 2.021,01 100,00% 111,72 2.021,01 100,00% 2.021,01
05.02.02
05.02.02.01 M3 45,66 2,62 119,63 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 45,66 119,63 100,00% 45,66 119,63 100,00% 119,63
05.02.02.02 M3 2,84 21,65 61,49 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 2,84 61,49 100,00% 2,84 61,49 100,00% 61,49
05.02.02.03 M3 57,07 4,43 252,82 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 57,07 252,82 100,00% 57,07 252,82 100,00% 252,82
05.02.03
05.02.03.01 M2 51,64 29,69 1.533,19 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 51,64 1.533,19 100,00% 51,64 1.533,19 100,00% 1.533,19
05.02.03.02 M3 10,09 286,36 2.889,37 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 10,09 2.889,37 100,00% 10,09 2.889,37 100,00% 2.889,37
05.02.03.03 M3 26,56 431,28 11.454,80 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 26,56 11.454,80 100,00% 26,56 11.454,80 100,00% 11.454,80
05.02.03.04 M2 75,03 32,96 2.472,99 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 75,03 2.472,99 100,00% 75,03 2.472,99 100,00% 2.472,99
05.02.04
05.02.04.01 M2 35,88 20,77 745,23 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 35,88 745,23 100,00% 35,88 745,23 100,00% 745,23
06.00.00
06.01.00 UND 2,00 400,00 800,00 0,00 0,00% 2,00 800,00 100,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 2,00 800,00 100,00% 800,00
06.02.00 UND 28,00 25,80 722,40 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 28,00 722,40 100,00% 28,00 722,40 100,00% 722,40
06.03.00 UND 44,00 80,00 3.520,00 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 44,00 3.520,00 100,00% 44,00 3.520,00 100,00% 3.520,00
07.00.00
07.01.00 GLB 1,00 1.000,00 1.000,00 0,00 0,00% 1,00 1.000,00 100,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 1,00 1.000,00 100,00% 1.000,00
07.02.00 GLB 1,00 2.597,50 2.597,50 0,00 0,00% 1,00 2.597,50 100,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 1,00 2.597,50 100,00% 2.597,50
08.00.00
08.01.00 GLB 1,00 14.000,00 14.000,00 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 1,00 14.000,00 100,00% 1,00 14.000,00 100,00% 14.000,00
09.00.00
09.01.00 UND 14,00 153,98 2.155,72 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 14,00 2.155,72 100,00% 0,00 0,00% 14,00 2.155,72 100,00% 2.155,72
09.02.00 UND 5,00 645,48 3.227,40 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 5,00 3.227,40 100,00% 0,00 0,00% 5,00 3.227,40 100,00% 3.227,40
09.03.00 UND 37,00 418,76 15.494,12 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 37,00 15.494,12 100,00% 0,00 0,00% 37,00 15.494,12 100,00% 15.494,12
10.00.00
10.01.00 M2 1.925,00 6,17 11.877,25 0,00 0,00% 1.606,25 9.910,56 83,44% 0,00 0,00% 0,00 0,00% 0,00 0,00% 318,75 1.966,69 16,56% 1.925,00 11.877,25 100,00% 11.877,25
10.02.00 M2 400,00 2,98 1.192,00 0,00 0,00% 175,00 521,50 43,75% 0,00 0,00% 0,00 0,00% 0,00 0,00% 225,00 670,50 56,25% 400,00 1.192,00 100,00% 1.192,00
10.03.00 M2 1.925,00 2,20 4.235,00 0,00 0,00% - 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 1.925,00 4.235,00 100,00% 1.925,00 4.235,00 100,00% 4.235,00
11.00.00
11.01.00 GLB 1,00 4.876,04 4.876,04 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00 0,00% 1,00 4.876,04 100,00% 1,00 4.876,04 100,00% 4.876,04
A 882.536,55 6.739,77 360.438,06 134.827,05 182.691,33 137.106,24 60.734,08 882.536,53 882.536,55 100,00% 882.536,55
B 36.272,24 277,00 14.814,00 5.541,39 7.508,61 5.635,07 2.496,17 36.272,24 36.272,24 36.272,24
C 22.945,95 175,23 9.371,39 3.505,50 4.749,97 3.564,76 1.579,09 22.945,94 22.945,95 22.945,95
D=(A+B+C) 941.754,74 7.192,00 384.623,45 143.873,94 194.949,91 146.306,07 64.809,34 941.754,71 941.754,74 941.754,74
E=(Dx0.18) 169.515,85 1.294,56 69.232,22 25.897,31 35.090,98 26.335,09 11.665,68 169.515,84 169.515,85 169.515,85
F=(D+E) 1.111.270,59 8.486,56 453.855,67 169.771,25 230.040,89 172.641,16 76.475,02 1.111.270,55 1.111.270,59 1.111.270,59
100,00% 0,76% 40,84% 15,28% 20,70% 15,54% 6,88% 1,0000 100,00% 100,00%
FLETE TERRESTRE
FLETE DE EXPLOSIVOS Y CUSTODIA POLICIAL
TRAMITES Y PERMISOS
DISEÑO DE MEZCLA DE CONCRETO
ROTURA DE TESTIGOS DE CONCRETO
ENSAYOS DE DENSIDAD DE CAMPO
FLETE DE MATERIALES
TRABAJOS PRELIMINARES
ENCOFRADO Y DESENCOFRADO
REVOQUES Y ENLUCIDOS
SOLADO DE CONCRETO 1:10 E=10CM
EMBOQUILLADO DE PIEDRA CON MORTERO
CONCRETO F´C=175 KG/CM+30%PM INCL. FROTACHADO
EXCAVACION PARA ESTRUCTURAS (MANUAL)
TARRAJEO EXTERIORES C/MORTERO 1;5 X 1,5CM
ALIVIADERO Y EMBOQUILLADO DE PIEDRA MORTERO 1:4,C:H
PINTURA
PINTURA EN ALCANTARILLAS
TUBERIA DE METAL CORRUGADO
TUBERIA DE METAL CORRUGADO D=48¨, E=2.5MM
MOVIMIENTO DE TIERRAS
BADENES L=6.45M (02UND)
REVOQUES Y ENLUCIDOS
CAPACITACION AL PERSONAL
OPERACIÓN Y MANTENIMIENTO DE LA INFRAESTRUCTURA
EQUIPAMIENTO Y SEÑALIZACION VIAL
ELIMINACION DE MATERIAL EXCEDENTE D MAX=30M
OBRAS DE CONCRETO SIMPLE
IGV ( 18% )
TOTAL PRESUPUESTO OFERTADO
RELLENO CON MATERIAL PROPIO
TRATAMIENTO DE CAMPAMENTO
POSTES KILOMETRICOS DE 20X15X100
SEÑALIZACION INFORMATIVA
SEÑALIZACION PREVENTIVA
TARRAJEO CON IMPERMEABILIZANTE, MEZCLA 1:1, E1,5
CONTROL DE CALIDAD
MONITOREO ARQUEOLOGICO Y PMA
REVEGETACION DE CANTERAS
MITIGACION AMBIENTAL
ACONDICIONAMIENTO DE BOTADEROS
LIMPIEZA DE TERRENO MANUAL
TRAZO Y REPLANTEO PRELIMINAR
PORCENTAJE DE AVANCE FISICO (%)
COSTO DIRECTO:
GASTOS GENERALES ( 4.109999%)
UTILIDAD ( 10% )
SUB TOTAL

More Related Content

Similar to CALCULO DE LIQUIDACION DE OBRA POR CONTRATA.pdf

Costo referencial de posecion y operacion
Costo referencial de posecion y operacionCosto referencial de posecion y operacion
Costo referencial de posecion y operacionDeyvis Ubaldo
 
De assignment-finalized-28112017 4
De assignment-finalized-28112017 4De assignment-finalized-28112017 4
De assignment-finalized-28112017 4Arthur Wilson
 
The travertine at portico unit price list effective as of january 2017
The travertine at portico unit price list effective as of january 2017The travertine at portico unit price list effective as of january 2017
The travertine at portico unit price list effective as of january 2017Jhoi Jimenez
 
Renewable energy transmission [CSTP 2009]
Renewable energy transmission [CSTP 2009]Renewable energy transmission [CSTP 2009]
Renewable energy transmission [CSTP 2009]Smithers Apex
 
Seville Housing Market Summer 2010
Seville Housing Market Summer 2010Seville Housing Market Summer 2010
Seville Housing Market Summer 2010Ken Schmidt
 
Seville market summer 2010
Seville market summer 2010Seville market summer 2010
Seville market summer 2010Ken Schmidt
 
2000 BMW Z3 - M Roadster - Z3 - M Coupe Electrical Troubleshooting Manual.pdf
2000 BMW Z3 - M Roadster - Z3 - M Coupe Electrical Troubleshooting Manual.pdf2000 BMW Z3 - M Roadster - Z3 - M Coupe Electrical Troubleshooting Manual.pdf
2000 BMW Z3 - M Roadster - Z3 - M Coupe Electrical Troubleshooting Manual.pdfjuliovicencio5
 
01 cronograma valorizado
01 cronograma valorizado01 cronograma valorizado
01 cronograma valorizadoJIMMY PANDURO
 

Similar to CALCULO DE LIQUIDACION DE OBRA POR CONTRATA.pdf (19)

Practica 6
Practica 6Practica 6
Practica 6
 
valores fgts
valores fgtsvalores fgts
valores fgts
 
Costo referencial de posecion y operacion
Costo referencial de posecion y operacionCosto referencial de posecion y operacion
Costo referencial de posecion y operacion
 
De assignment-finalized-28112017 4
De assignment-finalized-28112017 4De assignment-finalized-28112017 4
De assignment-finalized-28112017 4
 
Cronograma valorizado saldo cutervo
Cronograma valorizado saldo cutervoCronograma valorizado saldo cutervo
Cronograma valorizado saldo cutervo
 
Pass Thru Pay
Pass Thru PayPass Thru Pay
Pass Thru Pay
 
Estructuras METRADO
Estructuras METRADOEstructuras METRADO
Estructuras METRADO
 
The travertine at portico unit price list effective as of january 2017
The travertine at portico unit price list effective as of january 2017The travertine at portico unit price list effective as of january 2017
The travertine at portico unit price list effective as of january 2017
 
Renewable energy transmission [CSTP 2009]
Renewable energy transmission [CSTP 2009]Renewable energy transmission [CSTP 2009]
Renewable energy transmission [CSTP 2009]
 
Seville Housing Market Summer 2010
Seville Housing Market Summer 2010Seville Housing Market Summer 2010
Seville Housing Market Summer 2010
 
Seville market summer 2010
Seville market summer 2010Seville market summer 2010
Seville market summer 2010
 
Z distribution
Z distribution Z distribution
Z distribution
 
2000 BMW Z3 - M Roadster - Z3 - M Coupe Electrical Troubleshooting Manual.pdf
2000 BMW Z3 - M Roadster - Z3 - M Coupe Electrical Troubleshooting Manual.pdf2000 BMW Z3 - M Roadster - Z3 - M Coupe Electrical Troubleshooting Manual.pdf
2000 BMW Z3 - M Roadster - Z3 - M Coupe Electrical Troubleshooting Manual.pdf
 
INGRESOS DE LA POLICIA NACIONAL DEL PERU
INGRESOS DE LA POLICIA NACIONAL DEL PERUINGRESOS DE LA POLICIA NACIONAL DEL PERU
INGRESOS DE LA POLICIA NACIONAL DEL PERU
 
Informe final riegos i
Informe final riegos iInforme final riegos i
Informe final riegos i
 
Equipo
EquipoEquipo
Equipo
 
01 cronograma valorizado
01 cronograma valorizado01 cronograma valorizado
01 cronograma valorizado
 
P33TotalNal.pdf
P33TotalNal.pdfP33TotalNal.pdf
P33TotalNal.pdf
 
P33TotalNal.pdf
P33TotalNal.pdfP33TotalNal.pdf
P33TotalNal.pdf
 

Recently uploaded

US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionMebane Rash
 
National Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdfNational Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdfRajuKanojiya4
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substationstephanwindworld
 
Steel Structures - Building technology.pptx
Steel Structures - Building technology.pptxSteel Structures - Building technology.pptx
Steel Structures - Building technology.pptxNikhil Raut
 
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONjhunlian
 
Internet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptxInternet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptxVelmuruganTECE
 
Indian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptIndian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptMadan Karki
 
Research Methodology for Engineering pdf
Research Methodology for Engineering pdfResearch Methodology for Engineering pdf
Research Methodology for Engineering pdfCaalaaAbdulkerim
 
Virtual memory management in Operating System
Virtual memory management in Operating SystemVirtual memory management in Operating System
Virtual memory management in Operating SystemRashmi Bhat
 
Main Memory Management in Operating System
Main Memory Management in Operating SystemMain Memory Management in Operating System
Main Memory Management in Operating SystemRashmi Bhat
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
Input Output Management in Operating System
Input Output Management in Operating SystemInput Output Management in Operating System
Input Output Management in Operating SystemRashmi Bhat
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...121011101441
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
home automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasadhome automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasadaditya806802
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 

Recently uploaded (20)

US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of Action
 
National Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdfNational Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdf
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substation
 
Steel Structures - Building technology.pptx
Steel Structures - Building technology.pptxSteel Structures - Building technology.pptx
Steel Structures - Building technology.pptx
 
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
 
Internet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptxInternet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptx
 
Indian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptIndian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.ppt
 
Research Methodology for Engineering pdf
Research Methodology for Engineering pdfResearch Methodology for Engineering pdf
Research Methodology for Engineering pdf
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Virtual memory management in Operating System
Virtual memory management in Operating SystemVirtual memory management in Operating System
Virtual memory management in Operating System
 
Main Memory Management in Operating System
Main Memory Management in Operating SystemMain Memory Management in Operating System
Main Memory Management in Operating System
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
Input Output Management in Operating System
Input Output Management in Operating SystemInput Output Management in Operating System
Input Output Management in Operating System
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
home automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasadhome automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasad
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 

CALCULO DE LIQUIDACION DE OBRA POR CONTRATA.pdf

  • 1. OBRA: PROPIETARIO: MUNICIPALIDAD PROVINCIAL DE ANGARAES RECURSOS PROPIOS PROVIAS DESCENTRALIZADO MODALIDAD DE EJECUCIÓN: CONTRATA EJECUTA: CONSORCIO UNÑEZ SUPERVISOR DE OBRA ING. GUERRA A. GUERRA CORONEL RESIDENTE: ING. GUIDO ROGER HUAYLLAS COSME METRADO VALOR S/. % METRADO VALOR S/. % METRADO VALOR S/. % METRADO VALOR S/. % METRADO VALOR S/. % METRADO VALOR S/. % METRADO VALOR S/. % VALOR S/. 01.00.00 01.01.00 UND 1,00 6.274,96 6.274,96 1,00 6.274,96 100,00% - 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 1,00 6.274,96 100,00% 6.274,96 01.02.00 GLB 1,00 5.000,00 5.000,00 0,00 0,00% 0,75 3.750,00 75,00% 0,15 750,00 15,00% 0,00 0,00% 0,10 500,00 10,00% 0,00 0,00% 1,00 5.000,00 100,00% 5.000,00 01.03.00 UND 1,00 464,81 464,81 1,00 464,81 100,00% - 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 1,00 464,81 100,00% 464,81 01.04.00 KM 10,92 568,38 6.206,71 0,00 0,00% 9,28 5.274,57 84,98% 0,00 0,00% 0,00 0,00% 1,64 932,14 15,02% 0,00 0,00% 10,92 6.206,71 100,00% 6.206,71 01.05.00 M3 31,91 28,44 907,52 0,00 0,00 0,00% 31,91 907,52 100,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 31,91 907,52 100,00% 907,52 02.00.00 02.01.00 02.01.01 M3 13.949,55 4,02 56.077,19 0,00 0,00% 11.770,55 47.317,61 84,38% - 0,00 0,00% 0,00 0,00% 2.179,00 8.759,58 15,62% 0,00 0,00% 13.949,55 56.077,19 100,00% 56.077,19 02.02.00 02.02.01 M3 1.484,00 18,75 27.825,00 0,00 0,00% 1.318,09 24.714,19 88,82% 165,91 3.110,81 11,18% 0,00 0,00% 0,00 0,00% - 0,00 0,00% 1.484,00 27.825,00 100,00% 27.825,00 02.02.02 M3 1.060,00 4,20 4.452,00 0,00 0,00% 941,49 3.954,26 88,82% 118,51 497,74 11,18% 0,00 0,00% 0,00 0,00% - 0,00 0,00% 1.060,00 4.452,00 100,00% 4.452,00 02.03.00 02.03.01 M3 790,19 26,39 20.853,11 0,00 0,00% 698,45 18.432,10 88,39% 91,74 2.421,02 11,61% 0,00 0,00% 0,00 0,00% - 0,00 0,00% 790,19 20.853,11 100,00% 20.853,11 02.03.02 M3 564,42 4,48 2.528,60 0,00 0,00% 498,89 2.235,03 88,39% 65,53 293,57 11,61% 0,00 0,00% 0,00 0,00% - 0,00 0,00% 564,42 2.528,60 100,00% 2.528,60 02.04.00 02.04.01 M3 2.936,22 5,16 15.150,90 0,00 0,00% 2.638,59 13.615,12 89,86% 297,63 1.535,77 10,14% 0,00 0,00% 0,00 0,00% - 0,00 0,00% 2.936,22 15.150,89 100,00% 15.150,89 02.04.02 M2 43.697,96 1,22 53.311,51 0,00 0,00% 39.305,16 47.952,30 89,95% - 0,00 0,00% 0,00 0,00% 2.354,36 2.872,32 5,39% 2.038,44 2.486,90 4,66% 43.697,96 53.311,52 100,00% 53.311,52 02.05.00 02.05.01 M3 9.478,02 4,57 43.314,55 0,00 0,00% 8.046,31 36.771,64 84,89% - 0,00 0,00% 0,00 0,00% 0,00 0,00% 1.431,71 6.542,91 15,11% 9.478,02 43.314,55 100,00% 43.314,55 03.00.00 03.01.00 M3 8.369,73 10,26 85.873,43 0,00 0,00% 1.693,94 17.379,82 20,24% 0,00 0,00% 6.357,45 65.227,44 75,96% 318,34 3.266,17 3,80% 0,00 0,00% 8.369,73 85.873,43 100,00% 85.873,43 03.02.00 M3 8.369,73 3,53 29.545,15 0,00 0,00% 1.275,45 4.502,34 15,24% 0,00 0,00% 4.975,31 17.562,84 59,44% 2.118,97 7.479,96 25,32% 0,00 0,00% 8.369,73 29.545,15 100,00% 29.545,15 03.03.00 M3 8.369,73 2,26 18.915,59 0,00 0,00% 0,00 0,00% 0,00 0,00% 5.631,99 12.728,30 67,29% 2.737,74 6.187,29 32,71% 0,00 0,00% 8.369,73 18.915,59 100,00% 18.915,59 03.04.00 M3 8.369,73 4,78 40.007,31 0,00 0,00% 0,00 0,00% 0,00 0,00% 5.598,51 26.760,88 66,89% 2.771,22 13.246,43 33,11% 0,00 0,00% 8.369,73 40.007,31 100,00% 40.007,31 03.05.00 M2 42.921,69 1,82 78.117,48 0,00 0,00% 0,00 0,00% 0,00 0,00% 28.208,13 51.338,80 65,72% 14.713,56 26.778,68 34,28% 0,00 0,00% 42.921,69 78.117,48 100,00% 78.117,48 04.00.00 04.01.00 KM 21,85 755,46 16.506,80 0,00 0,00% 0,00 0,00% 0,00 0,00% 12,01 9.073,07 54,97% 9,84 7.433,73 45,03% 0,00 0,00% 21,85 16.506,80 100,00% 16.506,80 05.00.00 05.01.00 05.01.01 05.01.01.01 M2 553,28 1,46 807,79 0,00 0,00% 553,28 807,79 100,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 553,28 807,79 100,00% 807,79 05.01.01.02 M2 553,28 2,13 1.178,49 0,00 0,00% 553,28 1.178,49 100,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 553,28 1.178,49 100,00% 1.178,49 05.01.02 05.01.02.01 M3 1.833,94 2,62 4.804,92 0,00 0,00% 1.833,94 4.804,92 100,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 1.833,94 4.804,92 100,00% 4.804,92 05.01.02.02 M3 239,90 21,65 5.193,84 0,00 0,00% 239,90 5.193,84 100,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 239,90 5.193,84 100,00% 5.193,84 05.01.02.03 M3 1.833,94 4,43 8.124,35 0,00 0,00% 1.833,94 8.124,35 100,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 1.833,94 8.124,35 100,00% 8.124,35 05.01.02.04 M3 34,86 156,13 5.442,69 0,00 0,00% 34,86 5.442,69 100,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 34,86 5.442,69 100,00% 5.442,69 05.01.03 05.01.03.01 M3 123,17 374,33 46.106,23 0,00 0,00% 30,55 11.435,78 24,80% 92,25 34.531,94 74,90% 0,00 0,00% 0,37 138,50 0,30% 0,00 0,00% 123,17 46.106,23 100,00% 46.106,23 05.01.03.02 M2 71,37 32,96 2.352,36 0,00 0,00% 17,70 583,39 24,80% 51,27 1.689,86 71,84% 0,00 0,00% 2,40 79,10 3,36% 0,00 0,00% 71,37 2.352,36 100,00% 2.352,36 05.01.03.03 M3 17,68 286,36 5.062,84 0,00 0,00% 0,00 0,00% 5,31 1.520,57 30,03% 0,00 0,00% 12,37 3.542,27 69,97% 0,00 0,00% 17,68 5.062,84 100,00% 5.062,84 05.01.04 05.01.04.01 M3 100,18 449,20 45.000,86 0,00 0,00% 25,15 11.297,38 25,10% 70,34 31.596,73 70,21% 0,00 0,00% 4,69 2.106,75 4,68% 0,00 0,00% 100,18 45.000,86 100,00% 45.000,86 05.01.04.02 M2 500,92 32,96 16.510,32 0,00 0,00% 125,75 4.144,72 25,10% 352,24 11.609,83 70,32% 0,00 0,00% 22,93 755,77 4,58% 0,00 0,00% 500,92 16.510,32 100,00% 16.510,32 05.01.04.03 M3 2.874,39 6,37 18.309,86 0,00 0,00% 1.407,01 8.962,65 48,95% 1.324,52 8.437,19 46,08% 0,00 0,00% 142,86 910,02 4,97% 0,00 0,00% 2.874,39 18.309,86 100,00% 18.309,86 TRANSPORTE DE MATERIALES DE LASTRADO DM=2.56KM AFIRMADO BASE GRANULAR (E=15CM) ACERO DE REFUERZO FY=4200 KG/CM2 TRAZO Y REPLANTEO CONFORMACION DE TERRAPLENES CON MATERIAL PROPIO PERFILADO Y COMPACTACION DE LA SUB RASANTE EN ZONAS DE CORTE EXTRACCION Y APILAMIENTO CON MAQUINARIA EN CANTERA ZARANDEO CARGUIO CON MAQUINARIA DE MATERIAL DE LASTRADO PAVIMENTOS CORTE EN ROCA FIJA CORTE EN ROCA FIJA (PÉRFORACION Y DISPARO) LIMPIEZA DE PLANTAFORMA Y DESQUINCHE DE TALUD EN ROCA FIJA CONFORMACION DE TERRAPLENES O RELLENOS CORTE DE MATERIAL SUELTO CORTE EN MATERIAL SUELTO CON MAQUINARIA (INC. PEINADO DE TALUD) CORTE EN ROCA SUELTA (PÉRFORACION Y DISPARO) LIMPIEZA DE PLANTAFORMA Y DESQUINCHE DE TALUD EN ROCA SUELTA CORTE EN ROCA SUELTA LIQUIDACION DE OBRA VALORIZACION Nº 3 TOTAL ACUMULADO PRESUPUESTO EJECUTADO PRESUP. VALORIZACION Nº 2 P.UNIT. VALORIZACION Nº1 CONTROL CAMPAMENTO PROVISIONALES DE LA OBRA DE 8M X 10M MOVILIZACION Y DESMOVILIZACION ELIMINACION DE MATERIAL EXCEDENTE (CARGUIO) DM=0.85KM ELIMINACION DE MATERIAL EXCEDENTE VALORIZACION Nº 5 CARTEL DE IDENTIFICACION DE OBRA 3.60 m X 7.20 m. TRAZO Y REPLANTEO DURANTE LA EJECUCION DEMOLICION DE ALCANTARILLAS EXISTENTES MOVIMIENTO DE TIERRAS EXCAVACION PARA ESTRUCTURAS (MANUAL) RELLENO CON MATERIAL PROPIO CONCRETO F´C=210KG/CM2 (LOSA TAPA) VALORIZACION Nº 4 VALORIZACION Nº 6 CUNETAS CONFORMACION DE CUNETAS RELLENO CON MATERIAL GRANULAR LIMPIEZA DE TERRENO MANUAL ALCANTARILLAS L=4.20M (28 UND) OBRAS DE ARTE TRABAJOS PRELIMINARES ELIMINACION DE MATERIAL EXCEDENTE D MAX=30M OBRAS DE CONCRETO SIMPLE CONCRETO CICLOPIO FC=175KG/CM2+30%PM-ESTRIBOS Y ALETAS ENCONFRADO Y DESENCOFRADO DE ESTRIBOS Y ALERO EMBOQUILLADO DE PIEDRA CON MORTERO OBRAS DE CONCRETO ARMADO ITEM DESCRIPCIÓN PRESUPUESTO OFERTADO UND METRADO ENCOFRADO Y DESENCOFRADO OBRAS PRELIMINARES TRABAJOS PRELIMINARES “MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD DEL CAMINO VECINAL TRAMO: SANTA ELENA – PITIMPATA – PATAPATA – LLUMCHI, DISTRITO DE LIRCAY, PROVINCIA DE ANGARAES - HUANCAVELICA”
  • 2. OBRA: PROPIETARIO: MUNICIPALIDAD PROVINCIAL DE ANGARAES RECURSOS PROPIOS PROVIAS DESCENTRALIZADO MODALIDAD DE EJECUCIÓN: CONTRATA EJECUTA: CONSORCIO UNÑEZ SUPERVISOR DE OBRA ING. GUERRA A. GUERRA CORONEL RESIDENTE: ING. GUIDO ROGER HUAYLLAS COSME METRADO VALOR S/. % METRADO VALOR S/. % METRADO VALOR S/. % METRADO VALOR S/. % METRADO VALOR S/. % METRADO VALOR S/. % METRADO VALOR S/. % VALOR S/. LIQUIDACION DE OBRA VALORIZACION Nº 3 TOTAL ACUMULADO PRESUPUESTO EJECUTADO PRESUP. VALORIZACION Nº 2 P.UNIT. VALORIZACION Nº1 CONTROL VALORIZACION Nº 5 VALORIZACION Nº 4 VALORIZACION Nº 6 ITEM DESCRIPCIÓN PRESUPUESTO OFERTADO UND METRADO OBRAS PRELIMINARES “MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD DEL CAMINO VECINAL TRAMO: SANTA ELENA – PITIMPATA – PATAPATA – LLUMCHI, DISTRITO DE LIRCAY, PROVINCIA DE ANGARAES - HUANCAVELICA” 05.01.05 05.01.05.01 M 123,20 461,25 56.826,00 0,00 0,00% 123,20 56.826,00 100,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 123,20 56.826,00 100,00% 56.826,00 05.01.06 05.01.06.01 M2 500,92 11,66 5.840,73 0,00 0,00% 0,00 0,00% 450,67 5.254,81 89,97% 0,00 0,00% 50,25 585,92 10,03% 0,00 0,00% 500,92 5.840,73 100,00% 5.840,73 05.01.06.02 M2 174,29 284,89 49.653,48 0,00 0,00% 0,00 0,00% 110,84 31.577,21 63,60% 0,00 0,00% 63,45 18.076,27 36,40% 0,00 0,00% 174,29 49.653,48 100,00% 49.653,48 05.01.07 05.01.07.01 M2 500,92 25,11 12.578,10 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 500,92 12.578,10 100,00% 0,00 0,00% 500,92 12.578,10 100,00% 12.578,10 05.02.00 05.02.01 05.02.01.01 M2 111,72 1,46 163,11 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 111,72 163,11 100,00% 111,72 163,11 100,00% 163,11 05.02.01.02 M2 111,72 18,09 2.021,01 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 111,72 2.021,01 100,00% 111,72 2.021,01 100,00% 2.021,01 05.02.02 05.02.02.01 M3 45,66 2,62 119,63 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 45,66 119,63 100,00% 45,66 119,63 100,00% 119,63 05.02.02.02 M3 2,84 21,65 61,49 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 2,84 61,49 100,00% 2,84 61,49 100,00% 61,49 05.02.02.03 M3 57,07 4,43 252,82 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 57,07 252,82 100,00% 57,07 252,82 100,00% 252,82 05.02.03 05.02.03.01 M2 51,64 29,69 1.533,19 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 51,64 1.533,19 100,00% 51,64 1.533,19 100,00% 1.533,19 05.02.03.02 M3 10,09 286,36 2.889,37 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 10,09 2.889,37 100,00% 10,09 2.889,37 100,00% 2.889,37 05.02.03.03 M3 26,56 431,28 11.454,80 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 26,56 11.454,80 100,00% 26,56 11.454,80 100,00% 11.454,80 05.02.03.04 M2 75,03 32,96 2.472,99 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 75,03 2.472,99 100,00% 75,03 2.472,99 100,00% 2.472,99 05.02.04 05.02.04.01 M2 35,88 20,77 745,23 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 35,88 745,23 100,00% 35,88 745,23 100,00% 745,23 06.00.00 06.01.00 UND 2,00 400,00 800,00 0,00 0,00% 2,00 800,00 100,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 2,00 800,00 100,00% 800,00 06.02.00 UND 28,00 25,80 722,40 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 28,00 722,40 100,00% 28,00 722,40 100,00% 722,40 06.03.00 UND 44,00 80,00 3.520,00 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 44,00 3.520,00 100,00% 44,00 3.520,00 100,00% 3.520,00 07.00.00 07.01.00 GLB 1,00 1.000,00 1.000,00 0,00 0,00% 1,00 1.000,00 100,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 1,00 1.000,00 100,00% 1.000,00 07.02.00 GLB 1,00 2.597,50 2.597,50 0,00 0,00% 1,00 2.597,50 100,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 1,00 2.597,50 100,00% 2.597,50 08.00.00 08.01.00 GLB 1,00 14.000,00 14.000,00 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 1,00 14.000,00 100,00% 1,00 14.000,00 100,00% 14.000,00 09.00.00 09.01.00 UND 14,00 153,98 2.155,72 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 14,00 2.155,72 100,00% 0,00 0,00% 14,00 2.155,72 100,00% 2.155,72 09.02.00 UND 5,00 645,48 3.227,40 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 5,00 3.227,40 100,00% 0,00 0,00% 5,00 3.227,40 100,00% 3.227,40 09.03.00 UND 37,00 418,76 15.494,12 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 37,00 15.494,12 100,00% 0,00 0,00% 37,00 15.494,12 100,00% 15.494,12 10.00.00 10.01.00 M2 1.925,00 6,17 11.877,25 0,00 0,00% 1.606,25 9.910,56 83,44% 0,00 0,00% 0,00 0,00% 0,00 0,00% 318,75 1.966,69 16,56% 1.925,00 11.877,25 100,00% 11.877,25 10.02.00 M2 400,00 2,98 1.192,00 0,00 0,00% 175,00 521,50 43,75% 0,00 0,00% 0,00 0,00% 0,00 0,00% 225,00 670,50 56,25% 400,00 1.192,00 100,00% 1.192,00 10.03.00 M2 1.925,00 2,20 4.235,00 0,00 0,00% - 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 1.925,00 4.235,00 100,00% 1.925,00 4.235,00 100,00% 4.235,00 11.00.00 11.01.00 GLB 1,00 4.876,04 4.876,04 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00% 0,00 0,00 0,00% 1,00 4.876,04 100,00% 1,00 4.876,04 100,00% 4.876,04 A 882.536,55 6.739,77 360.438,06 134.827,05 182.691,33 137.106,24 60.734,08 882.536,53 882.536,55 100,00% 882.536,55 B 36.272,24 277,00 14.814,00 5.541,39 7.508,61 5.635,07 2.496,17 36.272,24 36.272,24 36.272,24 C 22.945,95 175,23 9.371,39 3.505,50 4.749,97 3.564,76 1.579,09 22.945,94 22.945,95 22.945,95 D=(A+B+C) 941.754,74 7.192,00 384.623,45 143.873,94 194.949,91 146.306,07 64.809,34 941.754,71 941.754,74 941.754,74 E=(Dx0.18) 169.515,85 1.294,56 69.232,22 25.897,31 35.090,98 26.335,09 11.665,68 169.515,84 169.515,85 169.515,85 F=(D+E) 1.111.270,59 8.486,56 453.855,67 169.771,25 230.040,89 172.641,16 76.475,02 1.111.270,55 1.111.270,59 1.111.270,59 100,00% 0,76% 40,84% 15,28% 20,70% 15,54% 6,88% 1,0000 100,00% 100,00% FLETE TERRESTRE FLETE DE EXPLOSIVOS Y CUSTODIA POLICIAL TRAMITES Y PERMISOS DISEÑO DE MEZCLA DE CONCRETO ROTURA DE TESTIGOS DE CONCRETO ENSAYOS DE DENSIDAD DE CAMPO FLETE DE MATERIALES TRABAJOS PRELIMINARES ENCOFRADO Y DESENCOFRADO REVOQUES Y ENLUCIDOS SOLADO DE CONCRETO 1:10 E=10CM EMBOQUILLADO DE PIEDRA CON MORTERO CONCRETO F´C=175 KG/CM+30%PM INCL. FROTACHADO EXCAVACION PARA ESTRUCTURAS (MANUAL) TARRAJEO EXTERIORES C/MORTERO 1;5 X 1,5CM ALIVIADERO Y EMBOQUILLADO DE PIEDRA MORTERO 1:4,C:H PINTURA PINTURA EN ALCANTARILLAS TUBERIA DE METAL CORRUGADO TUBERIA DE METAL CORRUGADO D=48¨, E=2.5MM MOVIMIENTO DE TIERRAS BADENES L=6.45M (02UND) REVOQUES Y ENLUCIDOS CAPACITACION AL PERSONAL OPERACIÓN Y MANTENIMIENTO DE LA INFRAESTRUCTURA EQUIPAMIENTO Y SEÑALIZACION VIAL ELIMINACION DE MATERIAL EXCEDENTE D MAX=30M OBRAS DE CONCRETO SIMPLE IGV ( 18% ) TOTAL PRESUPUESTO OFERTADO RELLENO CON MATERIAL PROPIO TRATAMIENTO DE CAMPAMENTO POSTES KILOMETRICOS DE 20X15X100 SEÑALIZACION INFORMATIVA SEÑALIZACION PREVENTIVA TARRAJEO CON IMPERMEABILIZANTE, MEZCLA 1:1, E1,5 CONTROL DE CALIDAD MONITOREO ARQUEOLOGICO Y PMA REVEGETACION DE CANTERAS MITIGACION AMBIENTAL ACONDICIONAMIENTO DE BOTADEROS LIMPIEZA DE TERRENO MANUAL TRAZO Y REPLANTEO PRELIMINAR PORCENTAJE DE AVANCE FISICO (%) COSTO DIRECTO: GASTOS GENERALES ( 4.109999%) UTILIDAD ( 10% ) SUB TOTAL