09 March 09 Report

Report on what I did during the week.
01/03/09 – 06/03/09
Compiled by: Tshepo Makgakge
Position: Industrial Engineering Trainee
Submission Date: 09 March 2009
1. Terms of reference
On the 24th
November 2008, Ms Charity Van Wyk the process engineer of Plastop
requested a report on what I (Tshepo Makgakge) did during the week and what I saw.
The report with recommendations is due on the 09 March 2009.
2. Procedure
Define- The activity under investigation was colour changing, apparently the colour
changes take too long and which cause machine down time.
Measure-The time it takes to change colours was measured and then recorded.
Analyze-The times recorded to information that can be used in coming up with an
improved method.
Interpret-the information in terms of drafting graphs.
3. Findings
Colour Change Durations
Machine Response to Colour
Change(hrs)
Colour Change(hrs) QC(hrs)
Total
(hours)
4 8.5 0.47 0.53 9.5
10 3 0.4 0.6 4
12 0.82 0.56 0.75 2.13
7 0.48 0.62 1.07 2.17
20 2.17 0.83 5.37 8.37
8 0.37 1.1 0.43 1.9
87 2.25 0.51 0.49 3.25
10 5.53 0.47 0.25 6.25
20 0.26 1.23 0.76 2.25
75 8.02 0.73 1.28 10.03
74 0.55 2.58 1.2 4.33
87 11 0.78 1.22 13
20 10.35 1.25 0.4 12
7 15.45 0.17 1.38 17
12 18.97 0.86 0.17 20
74 5.43 1.15 1.42 8
75 1.56 0.76 1.13 3.45
3 1.35 0.82 0.25 2.42
Total 96.06 15.29 18.7
Average 5.34 0.85 1.04
Colour Change Duration
0
5
10
15
20
25
4 10 12 7 20 8 87 10 20 75 74 87 20 7 12 74 75 3
Machine
Time(hrs)
QC(hrs)
Colour Change(hrs)
Response to Colour
Change(hrs)
From looking at the figures it becomes clear where the problem is, responding to the
colour changes. The reason that the setters take too long to respond to these colour
changes is they are busy at other machines which makes them to neglect the idle
machine.
4. Conclusion
Looking at how frequent these colour changes come, I took the average number of colour
changes for the month of February. The cost service is indirectly proportional the waiting
line cost, which is why I used the waiting line cost theory to illustrate my point. The
optimal cost is found where the two graphs intersect. Some of the values used are not
true.
Plastop Waiting Line Cost Analysis
Number of Setters on shift 1 2 3 4 5
Average number of Colour change/shift 2 2 2 2 2
Average time each machine waits to be serviced 8 6 4 2 1
Total Colour change hrs lost per shift 16 12 8 4 2
Estimated cost per hour of idle machine time in Rands 100 100 100 100 100
Value of machine's waiting cost 1600 1200 800 400 200
Setter salary or service cost(At R25/hour) 200 400 600 800 1000
Total expected cost 1800 1600 1400 1200 1200
Queing costs and service level
0
500
1000
1500
2000
1 2 3 4 5
Service level
Cost
Cost of waiting Cost of providing service Total expected cost
5. Recommendation
I believe that we should work with the setters we have now. The problem is that they
cannot attend to colour changes quickly because they are caught up in other machines. If
we can make sure that when the machine starts running production that the quality
inspectors work with the setters in order to make sure that the machine continues running
the correct and good quality product. We then make sure that the settings are recorded for
future reference when running the same colour. When the machine is running then the
setters can concentrate on the mould and colour changes.
08 March 2009
Tshepo Makgakge
Industrial Engineering Trainee
Clock no.: 368

Recommandé

Presentation1Presentation1
Presentation1Niki Khemani
814 vues14 diapositives
Odev 13Odev 13
Odev 13Şakir Sayın
151 vues1 diapositive
Odev 13Odev 13
Odev 13Ozan Srn
131 vues1 diapositive

Contenu connexe

Tendances

SAMA_RAGAVA REDDYSAMA_RAGAVA REDDY
SAMA_RAGAVA REDDYRagava Reddy Sama
259 vues9 diapositives
The pipelined processorsThe pipelined processors
The pipelined processorsBasel Mansour
216 vues18 diapositives
Process lossesProcess losses
Process lossessavina1319
859 vues10 diapositives

Tendances(20)

SAMA_RAGAVA REDDYSAMA_RAGAVA REDDY
SAMA_RAGAVA REDDY
Ragava Reddy Sama259 vues
The pipelined processorsThe pipelined processors
The pipelined processors
Basel Mansour216 vues
Process lossesProcess losses
Process losses
savina1319859 vues
Marginal CostingMarginal Costing
Marginal Costing
rukmini (Rohini) balnaik (Udapudi)153 vues
Operations management past papersOperations management past papers
Operations management past papers
Kinshook Chaturvedi2.9K vues
Handout 3 ma problem 1Handout 3 ma problem 1
Handout 3 ma problem 1
azmatmengal207 vues
costing processcosting process
costing process
Aashutosh Vatsa1.1K vues
Analysis of ratesAnalysis of rates
Analysis of rates
vikrant prajapati309 vues
Final ProjectFinal Project
Final Project
Chelsey Bertram MHA303 vues
AdbagAdbag
Adbag
kotha priyanka407 vues
Bricks and1Bricks and1
Bricks and1
MdAtikUllah351 vues
De assignment-finalized-28112017 2De assignment-finalized-28112017 2
De assignment-finalized-28112017 2
Arthur Wilson64 vues
Line balancingLine balancing
Line balancing
Ankur Shukla450 vues
Pattern productionPattern production
Pattern production
Jitesh Gaurav119 vues

En vedette

PhotosPhotos
Photossarah1013
308 vues12 diapositives
Adaptación del cormo cinthiaAdaptación del cormo cinthia
Adaptación del cormo cinthia12ca12
230 vues8 diapositives
Resume_Feb 2015Resume_Feb 2015
Resume_Feb 2015B V Manjunath Rao
315 vues6 diapositives
Trc Finance PlusTrc Finance Plus
Trc Finance PlusLaurentTRC
102 vues2 diapositives

En vedette(11)

PhotosPhotos
Photos
sarah1013308 vues
Resume_Feb 2015Resume_Feb 2015
Resume_Feb 2015
B V Manjunath Rao315 vues
Trc Finance PlusTrc Finance Plus
Trc Finance Plus
LaurentTRC102 vues
Mapa conceptual14Mapa conceptual14
Mapa conceptual14
dilsyabmansilla80 vues
Img015Img015
Img015
javiinformatica4b27 vues
Statistik Angka Indeks Statistik Angka Indeks
Statistik Angka Indeks
Rizki Amalia30.2K vues
Pendidikan KewarganegaraanPendidikan Kewarganegaraan
Pendidikan Kewarganegaraan
Santi Rukmala7K vues

09 March 09 Report

  • 1. Report on what I did during the week. 01/03/09 – 06/03/09 Compiled by: Tshepo Makgakge Position: Industrial Engineering Trainee Submission Date: 09 March 2009
  • 2. 1. Terms of reference On the 24th November 2008, Ms Charity Van Wyk the process engineer of Plastop requested a report on what I (Tshepo Makgakge) did during the week and what I saw. The report with recommendations is due on the 09 March 2009. 2. Procedure Define- The activity under investigation was colour changing, apparently the colour changes take too long and which cause machine down time. Measure-The time it takes to change colours was measured and then recorded. Analyze-The times recorded to information that can be used in coming up with an improved method. Interpret-the information in terms of drafting graphs. 3. Findings Colour Change Durations Machine Response to Colour Change(hrs) Colour Change(hrs) QC(hrs) Total (hours) 4 8.5 0.47 0.53 9.5 10 3 0.4 0.6 4 12 0.82 0.56 0.75 2.13 7 0.48 0.62 1.07 2.17 20 2.17 0.83 5.37 8.37 8 0.37 1.1 0.43 1.9 87 2.25 0.51 0.49 3.25 10 5.53 0.47 0.25 6.25 20 0.26 1.23 0.76 2.25 75 8.02 0.73 1.28 10.03 74 0.55 2.58 1.2 4.33 87 11 0.78 1.22 13 20 10.35 1.25 0.4 12 7 15.45 0.17 1.38 17 12 18.97 0.86 0.17 20 74 5.43 1.15 1.42 8 75 1.56 0.76 1.13 3.45 3 1.35 0.82 0.25 2.42 Total 96.06 15.29 18.7 Average 5.34 0.85 1.04
  • 3. Colour Change Duration 0 5 10 15 20 25 4 10 12 7 20 8 87 10 20 75 74 87 20 7 12 74 75 3 Machine Time(hrs) QC(hrs) Colour Change(hrs) Response to Colour Change(hrs) From looking at the figures it becomes clear where the problem is, responding to the colour changes. The reason that the setters take too long to respond to these colour changes is they are busy at other machines which makes them to neglect the idle machine. 4. Conclusion Looking at how frequent these colour changes come, I took the average number of colour changes for the month of February. The cost service is indirectly proportional the waiting line cost, which is why I used the waiting line cost theory to illustrate my point. The optimal cost is found where the two graphs intersect. Some of the values used are not true. Plastop Waiting Line Cost Analysis Number of Setters on shift 1 2 3 4 5 Average number of Colour change/shift 2 2 2 2 2 Average time each machine waits to be serviced 8 6 4 2 1 Total Colour change hrs lost per shift 16 12 8 4 2 Estimated cost per hour of idle machine time in Rands 100 100 100 100 100 Value of machine's waiting cost 1600 1200 800 400 200 Setter salary or service cost(At R25/hour) 200 400 600 800 1000 Total expected cost 1800 1600 1400 1200 1200
  • 4. Queing costs and service level 0 500 1000 1500 2000 1 2 3 4 5 Service level Cost Cost of waiting Cost of providing service Total expected cost 5. Recommendation I believe that we should work with the setters we have now. The problem is that they cannot attend to colour changes quickly because they are caught up in other machines. If we can make sure that when the machine starts running production that the quality inspectors work with the setters in order to make sure that the machine continues running the correct and good quality product. We then make sure that the settings are recorded for future reference when running the same colour. When the machine is running then the setters can concentrate on the mould and colour changes. 08 March 2009 Tshepo Makgakge Industrial Engineering Trainee Clock no.: 368