Extension of Time (EOT) and Related Costs
in Construction
•Time is of Essence
•Delays are inevitable on construction projects
•Time and Money go hand-in-hand. When projects get delayed,
additional costs are incurred to all the parties .
•This makes it imperative to take control of project delays; timely and
effectively.
FIDIC

FIDIC

FIDIC

FIDIC

FIDIC

•Majority of construction projects worldwide are administered by the
FIDIC forms of contract.
•FIDIC recognises delay and related costs and has provisions related
thereto. For example;
Sub-Clauses 8.4 & 20.1 (FIDIC 1999 Edition)
Clauses 44 & 53 (FIDIC 1987 Edition)

http://www.ibclegal.com
The FIDIC Provisions define the conditions where delay may be
claimed as the basis for an Extension of Time (EOT). Some examples are;
Late provision of design or drawings
Unforeseeable Physical Conditions encountered on Site
Inclement Weather
Variations instructed by the Engineer (Additional Works etc.)

http://www.ibclegal.com
Meanwhile the principles of how delay and related
costs should be calculated are not defined by FIDIC.
This leads to issues;
issues which are usually contentious due to various
'schools of thoughts' and varied interpretations
existing worldwide.

Disputes are the usual outcome.

http://www.ibclegal.com
Contentious Issues in Delay Analysis
resulting in Disputes
– Critical Path
– Who owns the Float?
– Concurrent (or Contractor) Delays and how these effect
Entitlement
– EOT and its relation with Compensation for Delay
– Which is the best Method of Delay Analysis?
»
»
»
»
»

As-Planned Vs. As-Built Comparison
Impacted As-Planned
Collapsed As-Built / But-For
Time Slice / Sub-Networks / Time-Impact
Etc.

http://www.ibclegal.com
In order to eliminate disputes or facilitate settlement of
disputes, there are now certain standards used worldwide.
The leading standards are;
Society of Construction Law’s
Delay and Disruption Protocol (SCL Protocol)

AACE 29R-03 (Forensic Schedule Analysis)
http://www.ibclegal.com
The SCL Protocol was
finalized in October 2002 after
several years of deliberations
and considerable debate and
agreement between experts
from different backgrounds

http://www.ibclegal.com
The objective of the SCL Protocol
was to bring reasonableness and
fairness into the delay assessment
process and to eliminate
widespread manipulation of
complex delay issues
http://www.ibcl
egal.com
The SCL Protocol tried to standardize
the issues such that disputes would be
reduced or eliminated

http://www.ibcl
egal.com
It is recommended that;

should be adopted as a Standard
and should be, where possible,
incorporated in the Construction
Contracts

http://www.ibcl
egal.com
The SCL Protocol can be downloaded from:

www.eotprotocol.com
http://www.ibclegal.com
The remaining slides of this lecture will
review and discuss the basic Principles
suggested and recommended by the
SCL Protocol
http://www.ibcl
egal.com
Basic Principles
suggested and recommended by
the SCL Protocol

http://www.ibcl
egal.com
The Principles suggested by the
SCL Protocol are simple.

Some of the key principles suggested
by the Protocol are;

http://www.ibcl
egal.com
RULE NO. 1
If there is an Employer’s delay, which is beyond the Contractor’s
control, and if this delay impacts the Completion Date of the Works,

the Contractor should be entitled to receive an
Extension of Time (EOT).
[This will effectively result in an extended Time for Completion and will
relieve the Contractor from having to pay penalties for delay (or
Delay Damages under FIDIC)]

http://www.ibcl
egal.com
RULE NO. 2
For the case of recovery of delay (or prolongation) costs incurred due to
the Employer delays, the Contractor must be able to prove that there has
been no other delay, which is in his own control, and which is equally
(or partly) contributing for delaying the Time for Completion.

This category of delay is called a ‘Concurrent’
(or Contractor’s) Delay
[In order to win a Delay Costs Claim, the Contractor must be able to
prove that he has not been responsible for Concurrent Delays to
the Time for Completion]

http://www.ibcl
egal.com
RULE NO. 3
Where Contractor’s Delay to Completion
occurs concurrently with Employer’s Delay
to Completion, the Contractor’s concurrent
delay should NOT reduce any
Extension of Time (EOT), which is due.
[Result of Rule No. 1 will not change and is irrespective of the result
of Rule No. 2]

http://www.ibcl
egal.com
The foregoing Rules proposed by the SCL Protocol are
meant to bring fairness and reasonableness into the
delay assessment process.
[The emphasis of the SCL Protocol is that no one Party
should benefit from default of the other Party]

http://www.ibcl
egal.com
The Illustrations demonstrating the principles of the SCL
Protocol are contained in the following Figures A to G

http://www.ibcl
egal.com
Figure A - Accepted Contract Programme

1 2 3
Path 1

4

5

6

7

8

Weeks
9 10 11 12 13 14 15 16 17 18 19 20 21 22

Path 1 Float = 3.5 Weeks
Contract Start
Date

Contract
Completion Date

Path 2

Path 2 Float = 5.5 Weeks

http://www.ibcl
egal.com
Figure B - Delay Impact 1

1

2

3

4

5

6

7

8

9

10

Weeks
11 12 13

14

15

16

17

18

19

20

21 22

PRIOR TO EXCUSABLE DELAY (UPDATE WITH ACTUAL PROGRESS)
Path 1
<=Date of Excusable Delay
Path 1 Float = 3.0 Weeks
Contract Start
Date

Contract
Completion Date

Path 2

Path 2 Float = 5.5 Weeks

AFTER EXCUSABLE DELAY
Path 1
Impact on Path 1
= 2.0 Weeks

Excusable Delay

Contract
Completion Date
Path 1 Float = 1.0 Week

Path 2

Path 2 Float = 5.5 Weeks

(1) EOT Entitlement
(a) 2.0 Weeks
(b) 1.0 Weeks
(c) 0 Weeks
(d) 5.5 Weeks

(2) Period of Prolongation Costs
(a) 5.5 Weeks
(b) 0 Weeks
(c) 1.0 Weeks
(d) 2.0 Weeks

(3) Compensation for Delay to
Progress
(a) 2.0 Weeks
(b) 1.0 Weeks
(c) 0 Weeks
(d) 5.5 Weeks

(4) Other Compensation
(a) 0.1% of Contract Price
(b) Direct Costs of Excusable Delay
(c) NIL
(d) (a) plus (b)

http://www.ibcl
egal.com
Principles & Provisions of the SCL Protocol
relevant to Figure B

Core Principle No. 7 - Float as it relates to time
Unless there is express provision to the contrary in the contract, where there is remaining
float in the programme at the time of an Employer Risk Event, an EOT should only be
granted to the extent that the Employer Delay is predicted to reduce to below zero the total
float on the activity paths affected by the Employer Delay.
Guidance Section 1.12.1
If as a result of an Employer Delay, the Contractor is prevented from completing the works
by the Contractor’s planned completion date (being a date earlier than the contract
completion date), the Contractor should in principle be entitled to be paid the costs
directly caused by the Employer Delay, notwithstanding that there is no delay to the
contract completion date (and therefore no entitlement to an EOT), provided also that at
the time they enter into the contract, the Employer is aware of the Contractor’s intention to
complete the works prior to the contract completion date, and that intention is realistic and
achievable.
http://www.ibcl
egal.com
Figure C - Delay Impact 2

1

2

3

4

5

6

7

8

9

10

Weeks
11 12 13

14

15

16

17

18

19

20

21 22

PRIOR TO EXCUSABLE DELAY (UPDATE WITH ACTUAL PROGRESS)
Path 1
<=Date of Excusable Delay
Path 1 Float = 3.0 Weeks
Contract Start
Date

Contract
Completion Date

Path 2

Path 2 Float = 5.5 Weeks

AFTER EXCUSABLE DELAY
Path 1
Impact on Path 1
= 3.5 Weeks

Excusable Delay

Contract
Completion Date
Float = -0.5 Week

Path 2

(1) EOT Entitlement
(a) 0.5 Weeks
(b) 3.5 Weeks
(c) 0 Weeks
(d) 5.5 Weeks

(2) Period of Prolongation Costs
(a) 5.5 Weeks
(b) 0.5 Weeks
(c) 3.5 Weeks
(d) 0 Weeks

(3) Compensation for Delay to
Progress
(a) 3.5 Weeks
(b) 0.5 Weeks
(c) 0 Weeks
(d) 3.0 Weeks

(4) Other Compensation
(a) 0.15% of Contract Price
(b) Direct Costs of Excusable Delay
(c) (a) plus (b)
(d) NIL

http://www.ibcl
egal.com
Principles & Provisions of the SCL Protocol
relevant to Figure C
Core Principle No. 4 - Procedure for granting extension of time
The EOT should be granted to the extent that the Employer Risk Event is
reasonably predicted to prevent the works being completed by the then
prevailing contract completion date…..The goal of the EOT procedure is
the ascertainment of the appropriate contractual entitlement to an EOT; the
procedure is not to be based on whether or not the Contractor needs an
EOT in order not to be liable for liquidated damages.
Core Principle No. 5 – Effect of delay
For an EOT to be granted, it is not necessary for the Employer Risk Event
already to have begun to affect the Contractor’s progress with the works,
or for the effect of the Employer Risk Event to have ended.

http://www.ibcl
egal.com
Figure D - Delay Impact 3

1

2

3

4

5

6

7

8

9

10

Weeks
11 12 13

14

15

16

17

18

19

20

21 22

PRIOR TO EXCUSABLE DELAY (UPDATE WITH ACTUAL PROGRESS)
Path 1
<=Date of Excusable Delay
Path 1 Float = 3.0 Weeks
Contract Start
Date

Contract
Completion Date

Path 2

Path 2 Float = 5.5 Weeks

AFTER EXCUSABLE DELAY
Path 1
Contract
Completion Date
Float = -0.5 Week

Path 2

Excusable Delay
Impact on Path 2 = 6.0 Weeks

(1) EOT Entitlement
(a) 0 Weeks
(b) 6.0 Weeks
(c) 0.5 Weeks
(d) 5.5 Weeks

(2) Period of Prolongation Costs
(a) 5.5 Weeks
(b) 0 Weeks
(c) 6.0 Weeks
(d) 0.5 Weeks

(3) Compensation for Delay to
Progress
(a) 3.5 Weeks
(b) 0.5 Weeks
(c) 6.0 Weeks
(d) 3.0 Weeks

(4) Other Compensation
(a) (d) minus (c)
(b) Direct Costs of Excusable Delay
NIL
(c) Direct Costs of Excusable Delay
(d) 0.2% of Contract Price

http://www.ibcl
egal.com
Principles & Provisions of the SCL Protocol
relevant to Figure D
Core Principle No. 4 - Procedure for granting extension of time
The EOT should be granted to the extent that the Employer Risk Event is
reasonably predicted to prevent the works being completed by the then
prevailing contract completion date…..The goal of the EOT procedure is
the ascertainment of the appropriate contractual entitlement to an EOT; the
procedure is not to be based on whether or not the Contractor needs an
EOT in order not to be liable for liquidated damages.
Core Principle No. 5 – Effect of delay
For an EOT to be granted, it is not necessary for the Employer Risk Event
already to have begun to affect the Contractor’s progress with the works,
or for the effect of the Employer Risk Event to have ended.

http://www.ibcl
egal.com
Figure E - Delay Impact 4

1

2

3

4

5

6

7

8

9

10

Weeks
11 12 13

14

15

16

17

18

19

20

21 22

PRIOR TO EXCUSABLE DELAY (UPDATE WITH ACTUAL PROGRESS)
Path 1
<=Date

of

Excusable Delay
Contract Completion Date

Contract Start
Date

Float = -1.5 Weeks

Path 2

AFTER EXCUSABLE DELAY
Path 1
Contract Completion Date
Excusable Delay

Impact on Path 1 = 2.0 Weeks
Float = -3.5 Weeks

Path 2

(1) EOT Entitlement
(a) 3.5 Weeks
(b) 2.0 Weeks
(c) 1.5 Weeks
(d) 0 Weeks

(2) Period of Prolongation Costs
(a) 2.0 Weeks
(b) 0 Weeks
(c) 3.5 Weeks
(d) 1.5 Weeks

(3) Compensation for Delay to
Progress
(a) 3.5 Weeks
(b) 2.0 Weeks
(c) 3.0 Weeks
(d) 0 Weeks

(4) Other Compensation
(a) (c) plus (d)
(b) Direct Costs of Excusable Delay
NIL
(c) Direct Costs of Excusable Delay
(d) 0.1% of Contract Price

http://www.ibclegal.com
Principles & Provisions of the SCL Protocol
relevant to Figure E
Guidance Section 1.2.11
…an EOT should be granted to the extent that the Employer Risk Event is
predicted to prevent the works being completed by the then prevailing
contract completion date. This process requires consideration of the
available float…
Guidance Section 1.4.12
…Where there has been Employer Delay, this may prevent the Employer
charging the Contractor with LDs for failure to achieve a contract
completion date…

http://www.ibclegal.com
Figure F - Delay Impact 5

1

2

3

4

5

6

7

8

9

10

Weeks
11 12 13

14

15

16

17

18

19

20

21 22

PRIOR TO EXCUSABLE DELAY (UPDATE WITH ACTUAL PROGRESS)
Path 1
<=Date of Excusable Delay
Contract Completion Date
Contract Start
Date

Float = -1.5 Weeks

Path 2

AFTER EXCUSABLE DELAY
Path 1
Contract Completion Date
Impact on Path 1 = 2.0 Weeks
Excusable Delay
Float = -3.5 Weeks

Path 2

(1) EOT Entitlement
(a) 2.0 Weeks
(b) 3.5 Weeks
(c) 1.5 Weeks
(d) 0 Weeks

(2) Period of Prolongation Costs
(a) 0 Weeks
(b) 2.0 Weeks
(c) 3.5 Weeks
(d) 1.5 Weeks

(3) Compensation for Delay to
Progress
(a) 3.5 Weeks
(b) 2.0 Weeks
(c) 3.0 Weeks
(d) 0 Weeks

(4) Other Compensation
(a) (c) plus (d)
(b) Direct Costs of Excusable Delay
NIL
(c) Direct Costs of Excusable Delay
(d) 0.1% of Contract Price

http://www.ibclegal.com
Principles & Provisions of the SCL Protocol
relevant to Figure F
Guidance Section 1.4.8
Where an Employer Risk Event occurs after the contract completion date, in a
situation where failure to complete by the contract completion date has been caused
by Contractor Delays, the principle set out in Section 1.4.7 above should apply,
except where the Employer Risk Event is a non-compensable Employer Risk Event.
In such an event, no EOT (or compensation) should be due. Where an EOT is due
after the contract completion date, the Employer Risk Event does not exonerate the
Contractor for all its delays prior to the Employer Risk Event occurring. The effect
of the Employer Risk Event should be assessed as described above and any EOT
found due should simply be added to the contract completion date.

http://www.ibclegal.com
Figure G - Delay Impact 6

1

2

3

4

5

6

7

8

9

10

Weeks
11 12 13

14

15

16

17

18

19

20 21 22

PRIOR TO EXCUSABLE DELAY (UPDATE WITH ACTUAL PROGRESS)
Path 1
<=Date of Excusable Delay
Contract Completion Date
Contract Start
Date

Float = -1.5 Weeks

Path 2
Path 2 Float = 2.5 Weeks

AFTER EXCUSABLE DELAY
Path 1
Contract Completion Date

Float = -1.5 Weeks

Path 2

Excusable Delay = 3.5 Weeks

(1) EOT Entitlement
(a) 2.5 Weeks
(b) 3.5 Weeks
(c) 1.0 Weeks
(d) 1.5 Weeks

(2) Period of Prolongation Costs
(a) 0 Weeks
(b) 2.5 Weeks
(c) 3.5 Weeks
(d) 1.5 Weeks

(3) Compensation for Delay to
Progress
(a) 0 Weeks
(b) 2.0 Weeks
(c) 3.0 Weeks
(d) 3.5 Weeks

(4) Other Compensation
(a) (b) plus (d)
(b) Direct Costs of Excusable Delay
(c) NIL
(d) 0.2% of Contract Price

http://www.ibclegal.com
Principles & Provisions of the SCL Protocol
relevant to Figure G – Slide 1/2
Guidance Section 1.4.1
Where Contractor Delay to Completion occurs concurrently with Employer Delay to
Completion, the Contractor’s concurrent delay should not reduce any EOT due.
Guidance Section 1.4.7
Where Employer Risk Events and Contractor Risk Events occur sequentially but
have concurrent effects, here again any Contractor Delay should not reduce the
amount of EOT due to the Contractor as a result of the Employer Delay.
Concurrency (Appendix A – Definations and Glossary)
True concurrent delay is the occurrence of two or more delay events at the same
time, one an Employer Risk Event, the other a Contractor Risk Event and the effects
of which are felt at the same time. The term ‘concurrent delay’ is often used to
describe the situation where two or more delay events arise at different times, but
the effects of them are felt (in whole or in part) at the same time. To avoid
confusion, this is more correctly termed the ‘concurrent effect’ of sequential delay
events.

http://www.ibclegal.com
Principles & Provisions of the SCL Protocol
relevant to Figure G – Slide 2/2
Core Principle No. 9 - Concurrent delay – its effect on entitlement to extension of time
Where Contractor Delay to Completion occurs or has effect concurrently with Employer
Delay to Completion, the Contractor’s concurrent delay should not reduce any EOT
due.
Core Principle No. 14 - Link between extension of time and compensation
Entitlement to an EOT does not automatically lead to entitlement to compensation (and
vice versa).
Core Principle No. 10 - Concurrent delay – its effect on entitlement to compensation for
prolongation
If the Contractor incurs additional costs that are caused both by Employer Delay and
concurrent Contractor Delay, then the Contractor should only recover compensation to
the extent it is able to separately identify the additional costs caused by the Employer
Delay from those caused by the Contractor Delay. If it would have incurred the
additional costs in any event as a result of Contractor Delays, the Contractor will not be
entitled to recover those additional costs.

http://www.ibclegal.com
Key Guideline, Suggestion and Advice of the
SCL Protocol
Guidance Section 3.2.13
Although the programme should be the primary tool for guiding the
CA in his determination of EOT, it should be used in conjunction
with the contemporary evidence to ensure that the resulting EOT is
fair and reasonable. It will also be necessary for the parties to apply
common sense and experience to the process to ensure that all
relevant factors are taken into account, and that any anomalous
results generated by the programme analysis are managed properly.

http://www.ibclegal.com
Correct Responses for Figures B to G
Figure No.

Question 1

Question 2

Question 3

Question 4

B

(c)

(b)

(a)

(b)

C

(a)

(b)

(d)

(b)

D

(c)

(d)

(d)

(c)

E

(b)

(a)

(d)

(c)

F

(a)

(b)

(d)

(c)

G

(c)

(a)

(a)

(b)

http://www.ibclegal.com
Congratulations we
have come to the end of
the Lecture.
You are now a
Qualified and Certified
Delay Claims Analyst
and Expert.

http://www.ibclegal.com
FIDIC and Construction Solutions
thank you for your attendance and contribution.

We wish you all Good Luck.

http://www.ibclegal.com
We urge all participants to review the SCL Protocol on their own.
Construction Solutions’ Claims Management Division
(http://www.ibclegal.com) will remain available for further
discussions on the foregoing and any other relevant issue.

http://www.ibcl
egal.com

More Related Content

What's hot

Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)mohamed Ismail
 
Update Delay Analysis
Update Delay AnalysisUpdate Delay Analysis
Update Delay AnalysisChris Carson
 
Construction Contracts: Basics of Contracts and Contract Administration
Construction Contracts:  Basics of Contracts and Contract AdministrationConstruction Contracts:  Basics of Contracts and Contract Administration
Construction Contracts: Basics of Contracts and Contract AdministrationGerald R. (Jerry) Genge
 
Construction Claims Explained
Construction Claims ExplainedConstruction Claims Explained
Construction Claims Explainedclaimsconsultancy
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementASHISH KUMAR SINGH
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variationVj NiroSh
 
Fidic conditions of contract presentation
Fidic conditions of contract presentationFidic conditions of contract presentation
Fidic conditions of contract presentationJeff B
 
Extension of time in construction contracts
Extension of time in construction contractsExtension of time in construction contracts
Extension of time in construction contractsKheng Hoe Advocates
 
fidic-flow-chart.pptx
fidic-flow-chart.pptxfidic-flow-chart.pptx
fidic-flow-chart.pptxssuserb337ce1
 
Delay analysis ... wise after the event.
Delay analysis ... wise after the event.Delay analysis ... wise after the event.
Delay analysis ... wise after the event.Tim Lloyd
 
Literature review on_ extension of time
Literature review on_ extension of timeLiterature review on_ extension of time
Literature review on_ extension of timeJoseph Sangpang
 
Quantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficienciesQuantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficienciesMichael Pink
 
time bar clauses
time bar clausestime bar clauses
time bar clausesAMILA GAYAN
 
Construction delays
Construction delaysConstruction delays
Construction delaysSaida Njim
 

What's hot (20)

FIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshopFIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshop
 
Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)
 
claims management framework
 claims management framework claims management framework
claims management framework
 
Update Delay Analysis
Update Delay AnalysisUpdate Delay Analysis
Update Delay Analysis
 
Construction Contracts: Basics of Contracts and Contract Administration
Construction Contracts:  Basics of Contracts and Contract AdministrationConstruction Contracts:  Basics of Contracts and Contract Administration
Construction Contracts: Basics of Contracts and Contract Administration
 
Construction Claims Explained
Construction Claims ExplainedConstruction Claims Explained
Construction Claims Explained
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time Management
 
Claim Presentation Rev 03 FINAL
Claim Presentation Rev 03 FINALClaim Presentation Rev 03 FINAL
Claim Presentation Rev 03 FINAL
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variation
 
Prolongation and HOOH Costs
Prolongation and HOOH CostsProlongation and HOOH Costs
Prolongation and HOOH Costs
 
Fidic conditions of contract presentation
Fidic conditions of contract presentationFidic conditions of contract presentation
Fidic conditions of contract presentation
 
Payment terms in construction industry
Payment terms in construction industryPayment terms in construction industry
Payment terms in construction industry
 
Extension of time in construction contracts
Extension of time in construction contractsExtension of time in construction contracts
Extension of time in construction contracts
 
fidic-flow-chart.pptx
fidic-flow-chart.pptxfidic-flow-chart.pptx
fidic-flow-chart.pptx
 
Delay analysis ... wise after the event.
Delay analysis ... wise after the event.Delay analysis ... wise after the event.
Delay analysis ... wise after the event.
 
Literature review on_ extension of time
Literature review on_ extension of timeLiterature review on_ extension of time
Literature review on_ extension of time
 
Quantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficienciesQuantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficiencies
 
Forensic schedule analysis acesss
Forensic schedule analysis acesssForensic schedule analysis acesss
Forensic schedule analysis acesss
 
time bar clauses
time bar clausestime bar clauses
time bar clauses
 
Construction delays
Construction delaysConstruction delays
Construction delays
 

Viewers also liked

Methods of delay analysis
Methods of delay analysisMethods of delay analysis
Methods of delay analysiskatrin enders
 
Construction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedConstruction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedMichael Pink
 
Time Impact Analysis
Time Impact AnalysisTime Impact Analysis
Time Impact AnalysisChris Carson
 
Delay, dispute (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
Delay, dispute  (1st annual conf. of planning in cairo 23-8-2014) engr. m magedDelay, dispute  (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
Delay, dispute (1st annual conf. of planning in cairo 23-8-2014) engr. m magedM Maged Hegazy, LLM, MBA, CCP, P3O
 
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanFIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanAdrias TAN
 
"Types and Causes of Construction Claims"
"Types and Causes of Construction Claims""Types and Causes of Construction Claims"
"Types and Causes of Construction Claims"Abhishek Shah
 
Fidic flow charts final
Fidic flow charts finalFidic flow charts final
Fidic flow charts finalFitBlar Mit
 
FIDIC & Dispute Boards
FIDIC & Dispute BoardsFIDIC & Dispute Boards
FIDIC & Dispute BoardsFIDIC
 
M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...
M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...
M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...Project Controls Expo
 
Fidic conditions of subcontract agreement
Fidic conditions of subcontract agreementFidic conditions of subcontract agreement
Fidic conditions of subcontract agreementabdmuhaiminyunus
 
Earned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project ControlEarned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project ControlM Maged Hegazy, LLM, MBA, CCP, P3O
 
Earned Value Analysis - Basic Concepts
Earned Value Analysis  - Basic ConceptsEarned Value Analysis  - Basic Concepts
Earned Value Analysis - Basic ConceptsRicardo Viana Vargas
 
Introduction to construction management
Introduction to construction managementIntroduction to construction management
Introduction to construction managementAditi Shah
 

Viewers also liked (15)

Methods of delay analysis
Methods of delay analysisMethods of delay analysis
Methods of delay analysis
 
Construction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedConstruction Delay Analysis, Simplified
Construction Delay Analysis, Simplified
 
Time Impact Analysis
Time Impact AnalysisTime Impact Analysis
Time Impact Analysis
 
Top10 planning fundamentals...
Top10 planning fundamentals...Top10 planning fundamentals...
Top10 planning fundamentals...
 
Delay, dispute (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
Delay, dispute  (1st annual conf. of planning in cairo 23-8-2014) engr. m magedDelay, dispute  (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
Delay, dispute (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
 
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanFIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
 
"Types and Causes of Construction Claims"
"Types and Causes of Construction Claims""Types and Causes of Construction Claims"
"Types and Causes of Construction Claims"
 
Fidic
FidicFidic
Fidic
 
Fidic flow charts final
Fidic flow charts finalFidic flow charts final
Fidic flow charts final
 
FIDIC & Dispute Boards
FIDIC & Dispute BoardsFIDIC & Dispute Boards
FIDIC & Dispute Boards
 
M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...
M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...
M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...
 
Fidic conditions of subcontract agreement
Fidic conditions of subcontract agreementFidic conditions of subcontract agreement
Fidic conditions of subcontract agreement
 
Earned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project ControlEarned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project Control
 
Earned Value Analysis - Basic Concepts
Earned Value Analysis  - Basic ConceptsEarned Value Analysis  - Basic Concepts
Earned Value Analysis - Basic Concepts
 
Introduction to construction management
Introduction to construction managementIntroduction to construction management
Introduction to construction management
 

Similar to EOT Related Cost Compensation Determination

FIDIC Lecture - EOT & Related Costs in Construction.pptx
FIDIC Lecture - EOT & Related Costs in Construction.pptxFIDIC Lecture - EOT & Related Costs in Construction.pptx
FIDIC Lecture - EOT & Related Costs in Construction.pptxJeff747294
 
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...Project Controls Expo
 
CFW NEC Management of change under the NEC3
CFW NEC  Management of change under the NEC3 CFW NEC  Management of change under the NEC3
CFW NEC Management of change under the NEC3 Rae Davies
 
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...Rae Davies
 
Professional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTProfessional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTYee Len Wan
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2ahmong4
 
IRJET- Delay in Construction its Causes and Mitigation: A Review
IRJET-  	  Delay in Construction its Causes and Mitigation: A ReviewIRJET-  	  Delay in Construction its Causes and Mitigation: A Review
IRJET- Delay in Construction its Causes and Mitigation: A ReviewIRJET Journal
 
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1Antonio Coladarce
 
C. Site managment chapter 5.pptx
C. Site managment chapter 5.pptxC. Site managment chapter 5.pptx
C. Site managment chapter 5.pptxEdenBekele5
 
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...Rae Davies
 
Seb Oram - The 2015 CDM Regulations - changes and impact on litigation
Seb Oram - The 2015 CDM Regulations - changes and impact on litigationSeb Oram - The 2015 CDM Regulations - changes and impact on litigation
Seb Oram - The 2015 CDM Regulations - changes and impact on litigationSeb Oram
 
Eot claims due to scope change under fidic contracts
Eot claims due to scope change under fidic contractsEot claims due to scope change under fidic contracts
Eot claims due to scope change under fidic contractsEssam Lotffy, PMP®, CCP®
 
PP Seminar Tutorial 7
PP Seminar Tutorial 7PP Seminar Tutorial 7
PP Seminar Tutorial 7Farah Sham
 
Cbb512 examination november_2011
Cbb512 examination november_2011Cbb512 examination november_2011
Cbb512 examination november_2011Maatla Moadi
 
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdfFIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdfBayuDarma4
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersIOSR Journals
 

Similar to EOT Related Cost Compensation Determination (20)

FIDIC Lecture - EOT & Related Costs in Construction.pptx
FIDIC Lecture - EOT & Related Costs in Construction.pptxFIDIC Lecture - EOT & Related Costs in Construction.pptx
FIDIC Lecture - EOT & Related Costs in Construction.pptx
 
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
 
Essentials of EOT Claims
Essentials of EOT ClaimsEssentials of EOT Claims
Essentials of EOT Claims
 
CFW NEC Management of change under the NEC3
CFW NEC  Management of change under the NEC3 CFW NEC  Management of change under the NEC3
CFW NEC Management of change under the NEC3
 
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
 
Professional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTProfessional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOT
 
Cl presentation
Cl presentationCl presentation
Cl presentation
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2
 
Cl report final
Cl report finalCl report final
Cl report final
 
IRJET- Delay in Construction its Causes and Mitigation: A Review
IRJET-  	  Delay in Construction its Causes and Mitigation: A ReviewIRJET-  	  Delay in Construction its Causes and Mitigation: A Review
IRJET- Delay in Construction its Causes and Mitigation: A Review
 
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
 
Claims and insolvencies (1)
Claims and insolvencies (1)Claims and insolvencies (1)
Claims and insolvencies (1)
 
C. Site managment chapter 5.pptx
C. Site managment chapter 5.pptxC. Site managment chapter 5.pptx
C. Site managment chapter 5.pptx
 
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...
 
Seb Oram - The 2015 CDM Regulations - changes and impact on litigation
Seb Oram - The 2015 CDM Regulations - changes and impact on litigationSeb Oram - The 2015 CDM Regulations - changes and impact on litigation
Seb Oram - The 2015 CDM Regulations - changes and impact on litigation
 
Eot claims due to scope change under fidic contracts
Eot claims due to scope change under fidic contractsEot claims due to scope change under fidic contracts
Eot claims due to scope change under fidic contracts
 
PP Seminar Tutorial 7
PP Seminar Tutorial 7PP Seminar Tutorial 7
PP Seminar Tutorial 7
 
Cbb512 examination november_2011
Cbb512 examination november_2011Cbb512 examination november_2011
Cbb512 examination november_2011
 
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdfFIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
 

Recently uploaded

Instant Issue Debit Cards - School Designs
Instant Issue Debit Cards - School DesignsInstant Issue Debit Cards - School Designs
Instant Issue Debit Cards - School Designsegoetzinger
 
VVIP Pune Call Girls Katraj (7001035870) Pune Escorts Nearby with Complete Sa...
VVIP Pune Call Girls Katraj (7001035870) Pune Escorts Nearby with Complete Sa...VVIP Pune Call Girls Katraj (7001035870) Pune Escorts Nearby with Complete Sa...
VVIP Pune Call Girls Katraj (7001035870) Pune Escorts Nearby with Complete Sa...Call Girls in Nagpur High Profile
 
Solution Manual for Financial Accounting, 11th Edition by Robert Libby, Patri...
Solution Manual for Financial Accounting, 11th Edition by Robert Libby, Patri...Solution Manual for Financial Accounting, 11th Edition by Robert Libby, Patri...
Solution Manual for Financial Accounting, 11th Edition by Robert Libby, Patri...ssifa0344
 
06_Joeri Van Speybroek_Dell_MeetupDora&Cybersecurity.pdf
06_Joeri Van Speybroek_Dell_MeetupDora&Cybersecurity.pdf06_Joeri Van Speybroek_Dell_MeetupDora&Cybersecurity.pdf
06_Joeri Van Speybroek_Dell_MeetupDora&Cybersecurity.pdfFinTech Belgium
 
VIP Call Girls LB Nagar ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With Room...
VIP Call Girls LB Nagar ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With Room...VIP Call Girls LB Nagar ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With Room...
VIP Call Girls LB Nagar ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With Room...Suhani Kapoor
 
Call US 📞 9892124323 ✅ Kurla Call Girls In Kurla ( Mumbai ) secure service
Call US 📞 9892124323 ✅ Kurla Call Girls In Kurla ( Mumbai ) secure serviceCall US 📞 9892124323 ✅ Kurla Call Girls In Kurla ( Mumbai ) secure service
Call US 📞 9892124323 ✅ Kurla Call Girls In Kurla ( Mumbai ) secure servicePooja Nehwal
 
Call Girls Koregaon Park Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Koregaon Park Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Koregaon Park Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Koregaon Park Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
CALL ON ➥8923113531 🔝Call Girls Gomti Nagar Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Gomti Nagar Lucknow best sexual serviceCALL ON ➥8923113531 🔝Call Girls Gomti Nagar Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Gomti Nagar Lucknow best sexual serviceanilsa9823
 
The Economic History of the U.S. Lecture 17.pdf
The Economic History of the U.S. Lecture 17.pdfThe Economic History of the U.S. Lecture 17.pdf
The Economic History of the U.S. Lecture 17.pdfGale Pooley
 
20240429 Calibre April 2024 Investor Presentation.pdf
20240429 Calibre April 2024 Investor Presentation.pdf20240429 Calibre April 2024 Investor Presentation.pdf
20240429 Calibre April 2024 Investor Presentation.pdfAdnet Communications
 
Stock Market Brief Deck (Under Pressure).pdf
Stock Market Brief Deck (Under Pressure).pdfStock Market Brief Deck (Under Pressure).pdf
Stock Market Brief Deck (Under Pressure).pdfMichael Silva
 
The Economic History of the U.S. Lecture 30.pdf
The Economic History of the U.S. Lecture 30.pdfThe Economic History of the U.S. Lecture 30.pdf
The Economic History of the U.S. Lecture 30.pdfGale Pooley
 
Call Girls Service Nagpur Maya Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Maya Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Maya Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Maya Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
The Economic History of the U.S. Lecture 26.pdf
The Economic History of the U.S. Lecture 26.pdfThe Economic History of the U.S. Lecture 26.pdf
The Economic History of the U.S. Lecture 26.pdfGale Pooley
 
The Economic History of the U.S. Lecture 21.pdf
The Economic History of the U.S. Lecture 21.pdfThe Economic History of the U.S. Lecture 21.pdf
The Economic History of the U.S. Lecture 21.pdfGale Pooley
 
The Economic History of the U.S. Lecture 20.pdf
The Economic History of the U.S. Lecture 20.pdfThe Economic History of the U.S. Lecture 20.pdf
The Economic History of the U.S. Lecture 20.pdfGale Pooley
 
Instant Issue Debit Cards - High School Spirit
Instant Issue Debit Cards - High School SpiritInstant Issue Debit Cards - High School Spirit
Instant Issue Debit Cards - High School Spiritegoetzinger
 
Best VIP Call Girls Noida Sector 18 Call Me: 8448380779
Best VIP Call Girls Noida Sector 18 Call Me: 8448380779Best VIP Call Girls Noida Sector 18 Call Me: 8448380779
Best VIP Call Girls Noida Sector 18 Call Me: 8448380779Delhi Call girls
 
00_Main ppt_MeetupDORA&CyberSecurity.pptx
00_Main ppt_MeetupDORA&CyberSecurity.pptx00_Main ppt_MeetupDORA&CyberSecurity.pptx
00_Main ppt_MeetupDORA&CyberSecurity.pptxFinTech Belgium
 

Recently uploaded (20)

Instant Issue Debit Cards - School Designs
Instant Issue Debit Cards - School DesignsInstant Issue Debit Cards - School Designs
Instant Issue Debit Cards - School Designs
 
VVIP Pune Call Girls Katraj (7001035870) Pune Escorts Nearby with Complete Sa...
VVIP Pune Call Girls Katraj (7001035870) Pune Escorts Nearby with Complete Sa...VVIP Pune Call Girls Katraj (7001035870) Pune Escorts Nearby with Complete Sa...
VVIP Pune Call Girls Katraj (7001035870) Pune Escorts Nearby with Complete Sa...
 
Solution Manual for Financial Accounting, 11th Edition by Robert Libby, Patri...
Solution Manual for Financial Accounting, 11th Edition by Robert Libby, Patri...Solution Manual for Financial Accounting, 11th Edition by Robert Libby, Patri...
Solution Manual for Financial Accounting, 11th Edition by Robert Libby, Patri...
 
06_Joeri Van Speybroek_Dell_MeetupDora&Cybersecurity.pdf
06_Joeri Van Speybroek_Dell_MeetupDora&Cybersecurity.pdf06_Joeri Van Speybroek_Dell_MeetupDora&Cybersecurity.pdf
06_Joeri Van Speybroek_Dell_MeetupDora&Cybersecurity.pdf
 
VIP Call Girls LB Nagar ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With Room...
VIP Call Girls LB Nagar ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With Room...VIP Call Girls LB Nagar ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With Room...
VIP Call Girls LB Nagar ( Hyderabad ) Phone 8250192130 | ₹5k To 25k With Room...
 
Call US 📞 9892124323 ✅ Kurla Call Girls In Kurla ( Mumbai ) secure service
Call US 📞 9892124323 ✅ Kurla Call Girls In Kurla ( Mumbai ) secure serviceCall US 📞 9892124323 ✅ Kurla Call Girls In Kurla ( Mumbai ) secure service
Call US 📞 9892124323 ✅ Kurla Call Girls In Kurla ( Mumbai ) secure service
 
Call Girls Koregaon Park Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Koregaon Park Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Koregaon Park Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Koregaon Park Call Me 7737669865 Budget Friendly No Advance Booking
 
CALL ON ➥8923113531 🔝Call Girls Gomti Nagar Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Gomti Nagar Lucknow best sexual serviceCALL ON ➥8923113531 🔝Call Girls Gomti Nagar Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Gomti Nagar Lucknow best sexual service
 
The Economic History of the U.S. Lecture 17.pdf
The Economic History of the U.S. Lecture 17.pdfThe Economic History of the U.S. Lecture 17.pdf
The Economic History of the U.S. Lecture 17.pdf
 
20240429 Calibre April 2024 Investor Presentation.pdf
20240429 Calibre April 2024 Investor Presentation.pdf20240429 Calibre April 2024 Investor Presentation.pdf
20240429 Calibre April 2024 Investor Presentation.pdf
 
Stock Market Brief Deck (Under Pressure).pdf
Stock Market Brief Deck (Under Pressure).pdfStock Market Brief Deck (Under Pressure).pdf
Stock Market Brief Deck (Under Pressure).pdf
 
The Economic History of the U.S. Lecture 30.pdf
The Economic History of the U.S. Lecture 30.pdfThe Economic History of the U.S. Lecture 30.pdf
The Economic History of the U.S. Lecture 30.pdf
 
Call Girls Service Nagpur Maya Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Maya Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Maya Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Maya Call 7001035870 Meet With Nagpur Escorts
 
The Economic History of the U.S. Lecture 26.pdf
The Economic History of the U.S. Lecture 26.pdfThe Economic History of the U.S. Lecture 26.pdf
The Economic History of the U.S. Lecture 26.pdf
 
The Economic History of the U.S. Lecture 21.pdf
The Economic History of the U.S. Lecture 21.pdfThe Economic History of the U.S. Lecture 21.pdf
The Economic History of the U.S. Lecture 21.pdf
 
The Economic History of the U.S. Lecture 20.pdf
The Economic History of the U.S. Lecture 20.pdfThe Economic History of the U.S. Lecture 20.pdf
The Economic History of the U.S. Lecture 20.pdf
 
Instant Issue Debit Cards - High School Spirit
Instant Issue Debit Cards - High School SpiritInstant Issue Debit Cards - High School Spirit
Instant Issue Debit Cards - High School Spirit
 
Best VIP Call Girls Noida Sector 18 Call Me: 8448380779
Best VIP Call Girls Noida Sector 18 Call Me: 8448380779Best VIP Call Girls Noida Sector 18 Call Me: 8448380779
Best VIP Call Girls Noida Sector 18 Call Me: 8448380779
 
00_Main ppt_MeetupDORA&CyberSecurity.pptx
00_Main ppt_MeetupDORA&CyberSecurity.pptx00_Main ppt_MeetupDORA&CyberSecurity.pptx
00_Main ppt_MeetupDORA&CyberSecurity.pptx
 
Veritas Interim Report 1 January–31 March 2024
Veritas Interim Report 1 January–31 March 2024Veritas Interim Report 1 January–31 March 2024
Veritas Interim Report 1 January–31 March 2024
 

EOT Related Cost Compensation Determination

  • 1. Extension of Time (EOT) and Related Costs in Construction
  • 2. •Time is of Essence •Delays are inevitable on construction projects •Time and Money go hand-in-hand. When projects get delayed, additional costs are incurred to all the parties . •This makes it imperative to take control of project delays; timely and effectively.
  • 3. FIDIC FIDIC FIDIC FIDIC FIDIC •Majority of construction projects worldwide are administered by the FIDIC forms of contract. •FIDIC recognises delay and related costs and has provisions related thereto. For example; Sub-Clauses 8.4 & 20.1 (FIDIC 1999 Edition) Clauses 44 & 53 (FIDIC 1987 Edition) http://www.ibclegal.com
  • 4. The FIDIC Provisions define the conditions where delay may be claimed as the basis for an Extension of Time (EOT). Some examples are; Late provision of design or drawings Unforeseeable Physical Conditions encountered on Site Inclement Weather Variations instructed by the Engineer (Additional Works etc.) http://www.ibclegal.com
  • 5. Meanwhile the principles of how delay and related costs should be calculated are not defined by FIDIC. This leads to issues; issues which are usually contentious due to various 'schools of thoughts' and varied interpretations existing worldwide. Disputes are the usual outcome. http://www.ibclegal.com
  • 6. Contentious Issues in Delay Analysis resulting in Disputes – Critical Path – Who owns the Float? – Concurrent (or Contractor) Delays and how these effect Entitlement – EOT and its relation with Compensation for Delay – Which is the best Method of Delay Analysis? » » » » » As-Planned Vs. As-Built Comparison Impacted As-Planned Collapsed As-Built / But-For Time Slice / Sub-Networks / Time-Impact Etc. http://www.ibclegal.com
  • 7. In order to eliminate disputes or facilitate settlement of disputes, there are now certain standards used worldwide. The leading standards are; Society of Construction Law’s Delay and Disruption Protocol (SCL Protocol) AACE 29R-03 (Forensic Schedule Analysis) http://www.ibclegal.com
  • 8. The SCL Protocol was finalized in October 2002 after several years of deliberations and considerable debate and agreement between experts from different backgrounds http://www.ibclegal.com
  • 9. The objective of the SCL Protocol was to bring reasonableness and fairness into the delay assessment process and to eliminate widespread manipulation of complex delay issues http://www.ibcl egal.com
  • 10. The SCL Protocol tried to standardize the issues such that disputes would be reduced or eliminated http://www.ibcl egal.com
  • 11. It is recommended that; should be adopted as a Standard and should be, where possible, incorporated in the Construction Contracts http://www.ibcl egal.com
  • 12. The SCL Protocol can be downloaded from: www.eotprotocol.com http://www.ibclegal.com
  • 13. The remaining slides of this lecture will review and discuss the basic Principles suggested and recommended by the SCL Protocol http://www.ibcl egal.com
  • 14. Basic Principles suggested and recommended by the SCL Protocol http://www.ibcl egal.com
  • 15. The Principles suggested by the SCL Protocol are simple. Some of the key principles suggested by the Protocol are; http://www.ibcl egal.com
  • 16. RULE NO. 1 If there is an Employer’s delay, which is beyond the Contractor’s control, and if this delay impacts the Completion Date of the Works, the Contractor should be entitled to receive an Extension of Time (EOT). [This will effectively result in an extended Time for Completion and will relieve the Contractor from having to pay penalties for delay (or Delay Damages under FIDIC)] http://www.ibcl egal.com
  • 17. RULE NO. 2 For the case of recovery of delay (or prolongation) costs incurred due to the Employer delays, the Contractor must be able to prove that there has been no other delay, which is in his own control, and which is equally (or partly) contributing for delaying the Time for Completion. This category of delay is called a ‘Concurrent’ (or Contractor’s) Delay [In order to win a Delay Costs Claim, the Contractor must be able to prove that he has not been responsible for Concurrent Delays to the Time for Completion] http://www.ibcl egal.com
  • 18. RULE NO. 3 Where Contractor’s Delay to Completion occurs concurrently with Employer’s Delay to Completion, the Contractor’s concurrent delay should NOT reduce any Extension of Time (EOT), which is due. [Result of Rule No. 1 will not change and is irrespective of the result of Rule No. 2] http://www.ibcl egal.com
  • 19. The foregoing Rules proposed by the SCL Protocol are meant to bring fairness and reasonableness into the delay assessment process. [The emphasis of the SCL Protocol is that no one Party should benefit from default of the other Party] http://www.ibcl egal.com
  • 20. The Illustrations demonstrating the principles of the SCL Protocol are contained in the following Figures A to G http://www.ibcl egal.com
  • 21. Figure A - Accepted Contract Programme 1 2 3 Path 1 4 5 6 7 8 Weeks 9 10 11 12 13 14 15 16 17 18 19 20 21 22 Path 1 Float = 3.5 Weeks Contract Start Date Contract Completion Date Path 2 Path 2 Float = 5.5 Weeks http://www.ibcl egal.com
  • 22. Figure B - Delay Impact 1 1 2 3 4 5 6 7 8 9 10 Weeks 11 12 13 14 15 16 17 18 19 20 21 22 PRIOR TO EXCUSABLE DELAY (UPDATE WITH ACTUAL PROGRESS) Path 1 <=Date of Excusable Delay Path 1 Float = 3.0 Weeks Contract Start Date Contract Completion Date Path 2 Path 2 Float = 5.5 Weeks AFTER EXCUSABLE DELAY Path 1 Impact on Path 1 = 2.0 Weeks Excusable Delay Contract Completion Date Path 1 Float = 1.0 Week Path 2 Path 2 Float = 5.5 Weeks (1) EOT Entitlement (a) 2.0 Weeks (b) 1.0 Weeks (c) 0 Weeks (d) 5.5 Weeks (2) Period of Prolongation Costs (a) 5.5 Weeks (b) 0 Weeks (c) 1.0 Weeks (d) 2.0 Weeks (3) Compensation for Delay to Progress (a) 2.0 Weeks (b) 1.0 Weeks (c) 0 Weeks (d) 5.5 Weeks (4) Other Compensation (a) 0.1% of Contract Price (b) Direct Costs of Excusable Delay (c) NIL (d) (a) plus (b) http://www.ibcl egal.com
  • 23. Principles & Provisions of the SCL Protocol relevant to Figure B Core Principle No. 7 - Float as it relates to time Unless there is express provision to the contrary in the contract, where there is remaining float in the programme at the time of an Employer Risk Event, an EOT should only be granted to the extent that the Employer Delay is predicted to reduce to below zero the total float on the activity paths affected by the Employer Delay. Guidance Section 1.12.1 If as a result of an Employer Delay, the Contractor is prevented from completing the works by the Contractor’s planned completion date (being a date earlier than the contract completion date), the Contractor should in principle be entitled to be paid the costs directly caused by the Employer Delay, notwithstanding that there is no delay to the contract completion date (and therefore no entitlement to an EOT), provided also that at the time they enter into the contract, the Employer is aware of the Contractor’s intention to complete the works prior to the contract completion date, and that intention is realistic and achievable. http://www.ibcl egal.com
  • 24. Figure C - Delay Impact 2 1 2 3 4 5 6 7 8 9 10 Weeks 11 12 13 14 15 16 17 18 19 20 21 22 PRIOR TO EXCUSABLE DELAY (UPDATE WITH ACTUAL PROGRESS) Path 1 <=Date of Excusable Delay Path 1 Float = 3.0 Weeks Contract Start Date Contract Completion Date Path 2 Path 2 Float = 5.5 Weeks AFTER EXCUSABLE DELAY Path 1 Impact on Path 1 = 3.5 Weeks Excusable Delay Contract Completion Date Float = -0.5 Week Path 2 (1) EOT Entitlement (a) 0.5 Weeks (b) 3.5 Weeks (c) 0 Weeks (d) 5.5 Weeks (2) Period of Prolongation Costs (a) 5.5 Weeks (b) 0.5 Weeks (c) 3.5 Weeks (d) 0 Weeks (3) Compensation for Delay to Progress (a) 3.5 Weeks (b) 0.5 Weeks (c) 0 Weeks (d) 3.0 Weeks (4) Other Compensation (a) 0.15% of Contract Price (b) Direct Costs of Excusable Delay (c) (a) plus (b) (d) NIL http://www.ibcl egal.com
  • 25. Principles & Provisions of the SCL Protocol relevant to Figure C Core Principle No. 4 - Procedure for granting extension of time The EOT should be granted to the extent that the Employer Risk Event is reasonably predicted to prevent the works being completed by the then prevailing contract completion date…..The goal of the EOT procedure is the ascertainment of the appropriate contractual entitlement to an EOT; the procedure is not to be based on whether or not the Contractor needs an EOT in order not to be liable for liquidated damages. Core Principle No. 5 – Effect of delay For an EOT to be granted, it is not necessary for the Employer Risk Event already to have begun to affect the Contractor’s progress with the works, or for the effect of the Employer Risk Event to have ended. http://www.ibcl egal.com
  • 26. Figure D - Delay Impact 3 1 2 3 4 5 6 7 8 9 10 Weeks 11 12 13 14 15 16 17 18 19 20 21 22 PRIOR TO EXCUSABLE DELAY (UPDATE WITH ACTUAL PROGRESS) Path 1 <=Date of Excusable Delay Path 1 Float = 3.0 Weeks Contract Start Date Contract Completion Date Path 2 Path 2 Float = 5.5 Weeks AFTER EXCUSABLE DELAY Path 1 Contract Completion Date Float = -0.5 Week Path 2 Excusable Delay Impact on Path 2 = 6.0 Weeks (1) EOT Entitlement (a) 0 Weeks (b) 6.0 Weeks (c) 0.5 Weeks (d) 5.5 Weeks (2) Period of Prolongation Costs (a) 5.5 Weeks (b) 0 Weeks (c) 6.0 Weeks (d) 0.5 Weeks (3) Compensation for Delay to Progress (a) 3.5 Weeks (b) 0.5 Weeks (c) 6.0 Weeks (d) 3.0 Weeks (4) Other Compensation (a) (d) minus (c) (b) Direct Costs of Excusable Delay NIL (c) Direct Costs of Excusable Delay (d) 0.2% of Contract Price http://www.ibcl egal.com
  • 27. Principles & Provisions of the SCL Protocol relevant to Figure D Core Principle No. 4 - Procedure for granting extension of time The EOT should be granted to the extent that the Employer Risk Event is reasonably predicted to prevent the works being completed by the then prevailing contract completion date…..The goal of the EOT procedure is the ascertainment of the appropriate contractual entitlement to an EOT; the procedure is not to be based on whether or not the Contractor needs an EOT in order not to be liable for liquidated damages. Core Principle No. 5 – Effect of delay For an EOT to be granted, it is not necessary for the Employer Risk Event already to have begun to affect the Contractor’s progress with the works, or for the effect of the Employer Risk Event to have ended. http://www.ibcl egal.com
  • 28. Figure E - Delay Impact 4 1 2 3 4 5 6 7 8 9 10 Weeks 11 12 13 14 15 16 17 18 19 20 21 22 PRIOR TO EXCUSABLE DELAY (UPDATE WITH ACTUAL PROGRESS) Path 1 <=Date of Excusable Delay Contract Completion Date Contract Start Date Float = -1.5 Weeks Path 2 AFTER EXCUSABLE DELAY Path 1 Contract Completion Date Excusable Delay Impact on Path 1 = 2.0 Weeks Float = -3.5 Weeks Path 2 (1) EOT Entitlement (a) 3.5 Weeks (b) 2.0 Weeks (c) 1.5 Weeks (d) 0 Weeks (2) Period of Prolongation Costs (a) 2.0 Weeks (b) 0 Weeks (c) 3.5 Weeks (d) 1.5 Weeks (3) Compensation for Delay to Progress (a) 3.5 Weeks (b) 2.0 Weeks (c) 3.0 Weeks (d) 0 Weeks (4) Other Compensation (a) (c) plus (d) (b) Direct Costs of Excusable Delay NIL (c) Direct Costs of Excusable Delay (d) 0.1% of Contract Price http://www.ibclegal.com
  • 29. Principles & Provisions of the SCL Protocol relevant to Figure E Guidance Section 1.2.11 …an EOT should be granted to the extent that the Employer Risk Event is predicted to prevent the works being completed by the then prevailing contract completion date. This process requires consideration of the available float… Guidance Section 1.4.12 …Where there has been Employer Delay, this may prevent the Employer charging the Contractor with LDs for failure to achieve a contract completion date… http://www.ibclegal.com
  • 30. Figure F - Delay Impact 5 1 2 3 4 5 6 7 8 9 10 Weeks 11 12 13 14 15 16 17 18 19 20 21 22 PRIOR TO EXCUSABLE DELAY (UPDATE WITH ACTUAL PROGRESS) Path 1 <=Date of Excusable Delay Contract Completion Date Contract Start Date Float = -1.5 Weeks Path 2 AFTER EXCUSABLE DELAY Path 1 Contract Completion Date Impact on Path 1 = 2.0 Weeks Excusable Delay Float = -3.5 Weeks Path 2 (1) EOT Entitlement (a) 2.0 Weeks (b) 3.5 Weeks (c) 1.5 Weeks (d) 0 Weeks (2) Period of Prolongation Costs (a) 0 Weeks (b) 2.0 Weeks (c) 3.5 Weeks (d) 1.5 Weeks (3) Compensation for Delay to Progress (a) 3.5 Weeks (b) 2.0 Weeks (c) 3.0 Weeks (d) 0 Weeks (4) Other Compensation (a) (c) plus (d) (b) Direct Costs of Excusable Delay NIL (c) Direct Costs of Excusable Delay (d) 0.1% of Contract Price http://www.ibclegal.com
  • 31. Principles & Provisions of the SCL Protocol relevant to Figure F Guidance Section 1.4.8 Where an Employer Risk Event occurs after the contract completion date, in a situation where failure to complete by the contract completion date has been caused by Contractor Delays, the principle set out in Section 1.4.7 above should apply, except where the Employer Risk Event is a non-compensable Employer Risk Event. In such an event, no EOT (or compensation) should be due. Where an EOT is due after the contract completion date, the Employer Risk Event does not exonerate the Contractor for all its delays prior to the Employer Risk Event occurring. The effect of the Employer Risk Event should be assessed as described above and any EOT found due should simply be added to the contract completion date. http://www.ibclegal.com
  • 32. Figure G - Delay Impact 6 1 2 3 4 5 6 7 8 9 10 Weeks 11 12 13 14 15 16 17 18 19 20 21 22 PRIOR TO EXCUSABLE DELAY (UPDATE WITH ACTUAL PROGRESS) Path 1 <=Date of Excusable Delay Contract Completion Date Contract Start Date Float = -1.5 Weeks Path 2 Path 2 Float = 2.5 Weeks AFTER EXCUSABLE DELAY Path 1 Contract Completion Date Float = -1.5 Weeks Path 2 Excusable Delay = 3.5 Weeks (1) EOT Entitlement (a) 2.5 Weeks (b) 3.5 Weeks (c) 1.0 Weeks (d) 1.5 Weeks (2) Period of Prolongation Costs (a) 0 Weeks (b) 2.5 Weeks (c) 3.5 Weeks (d) 1.5 Weeks (3) Compensation for Delay to Progress (a) 0 Weeks (b) 2.0 Weeks (c) 3.0 Weeks (d) 3.5 Weeks (4) Other Compensation (a) (b) plus (d) (b) Direct Costs of Excusable Delay (c) NIL (d) 0.2% of Contract Price http://www.ibclegal.com
  • 33. Principles & Provisions of the SCL Protocol relevant to Figure G – Slide 1/2 Guidance Section 1.4.1 Where Contractor Delay to Completion occurs concurrently with Employer Delay to Completion, the Contractor’s concurrent delay should not reduce any EOT due. Guidance Section 1.4.7 Where Employer Risk Events and Contractor Risk Events occur sequentially but have concurrent effects, here again any Contractor Delay should not reduce the amount of EOT due to the Contractor as a result of the Employer Delay. Concurrency (Appendix A – Definations and Glossary) True concurrent delay is the occurrence of two or more delay events at the same time, one an Employer Risk Event, the other a Contractor Risk Event and the effects of which are felt at the same time. The term ‘concurrent delay’ is often used to describe the situation where two or more delay events arise at different times, but the effects of them are felt (in whole or in part) at the same time. To avoid confusion, this is more correctly termed the ‘concurrent effect’ of sequential delay events. http://www.ibclegal.com
  • 34. Principles & Provisions of the SCL Protocol relevant to Figure G – Slide 2/2 Core Principle No. 9 - Concurrent delay – its effect on entitlement to extension of time Where Contractor Delay to Completion occurs or has effect concurrently with Employer Delay to Completion, the Contractor’s concurrent delay should not reduce any EOT due. Core Principle No. 14 - Link between extension of time and compensation Entitlement to an EOT does not automatically lead to entitlement to compensation (and vice versa). Core Principle No. 10 - Concurrent delay – its effect on entitlement to compensation for prolongation If the Contractor incurs additional costs that are caused both by Employer Delay and concurrent Contractor Delay, then the Contractor should only recover compensation to the extent it is able to separately identify the additional costs caused by the Employer Delay from those caused by the Contractor Delay. If it would have incurred the additional costs in any event as a result of Contractor Delays, the Contractor will not be entitled to recover those additional costs. http://www.ibclegal.com
  • 35. Key Guideline, Suggestion and Advice of the SCL Protocol Guidance Section 3.2.13 Although the programme should be the primary tool for guiding the CA in his determination of EOT, it should be used in conjunction with the contemporary evidence to ensure that the resulting EOT is fair and reasonable. It will also be necessary for the parties to apply common sense and experience to the process to ensure that all relevant factors are taken into account, and that any anomalous results generated by the programme analysis are managed properly. http://www.ibclegal.com
  • 36. Correct Responses for Figures B to G Figure No. Question 1 Question 2 Question 3 Question 4 B (c) (b) (a) (b) C (a) (b) (d) (b) D (c) (d) (d) (c) E (b) (a) (d) (c) F (a) (b) (d) (c) G (c) (a) (a) (b) http://www.ibclegal.com
  • 37. Congratulations we have come to the end of the Lecture. You are now a Qualified and Certified Delay Claims Analyst and Expert. http://www.ibclegal.com
  • 38. FIDIC and Construction Solutions thank you for your attendance and contribution. We wish you all Good Luck. http://www.ibclegal.com
  • 39. We urge all participants to review the SCL Protocol on their own. Construction Solutions’ Claims Management Division (http://www.ibclegal.com) will remain available for further discussions on the foregoing and any other relevant issue. http://www.ibcl egal.com