SlideShare a Scribd company logo
1 of 24
Download to read offline
PROJECTS
PERFORMANCE ANALYSIS & FORECASTING
®
Prepared By:
WALEED ELBASYOUNI
Sr. Architect, PMP , SFC™, 6Sigma™
Using
Earned Value Management
Session Content :-
• Introduction
• Overview of Key Performance Indicators ( KPI )
• What Is The Earned Value Management ?
• Why Project Managers Use EVM ?
• Earned Value Management Terms and Formulas
• Planned value (PV)
• Earned value (EV)
• Actual cost (AC)
• Variance
• Schedule Variance ( SV )
• Cost Variance ( CV )
• Performance Index
• Schedule Performance Index (SPI)
• Cost Performance Index (CPI)
• Example ( Case Study )
• Project Forecasting
• Budget at Completion (BAC)
• Estimate at Completion (EAC)
• Estimate to Complete (ETC).
• Variance at Completion (VAC)
• To Complete Performance Index (TCPI)
1.1 Introduction
1.1 Introduction
Overview of Key Performance Indicators ( KPI )
• Key Performance Indicators ( KPI ) are a Set Of Quantifiable
Measures That a Company Uses To Gauge Its Performance
Over Time.
• These Metrics Are Used To Determine a Company's Progress In Achieving Its Strategic and Operational Goals,
And Also To Compare A Company's Performance Against Other Businesses Within Its Industry.
What Is The Earned Value Management ?
• Earned Value Management Is a Project Management Technique For Measuring Project Performance And
Progress.
• Earned Value Is An Approach Where You Monitor The Project Plan,
Actual Work, And Work-completed Value To See If a Project Is On
Track.
• Earned Value Shows How Much Of The Budget And Time Should
Have Been Spent, With Regard To The Amount Of Work Done So
Far.
Why Project Managers Use EVM ?
• Project Managers Use EVM To Assess The Schedule and Cost Performance Of a Project To Know Exactly
Whether The Project Is:
(Ahead Of / On / Behind Schedule) - ( Under / On / Over Budget )
1.1 Introduction
1.2 Earned Value Management
Terms and Formulas
Planned value
Earned value
Actual Cost
PV
EV
AC
1.2 Earned Value Management Terms and Formulas
 Any Project Manager Use Earned Value Management To Assess The Schedule and Cost
Performance Of a Project He Should Based On Three Terms.
EVMEVM
PVPV
EVEVACAC
Budgeted Cost For Work Scheduled (BCWS)
Planned valuePV
• The Approved Budget For The Work Scheduled To
Be Completed By a Specified Date.
• Also Referred To As The Budgeted Cost Of Work
Scheduled (BCWS).
1.2 Earned Value Management Terms and Formulas
Budgeted Cost For Work Performed (BCWP)
Earned valueEV
• The Approved Budget For The Work Actually
Completed By The Specified Date.
• Also Referred To As The Budgeted Cost Of
Work Performed (BCWP).
1.2 Earned Value Management Terms and Formulas
• The Costs Actually Incurred For The Work
Completed By The Specified Date.
• Also Referred To As The Actual Cost Of Work
Performed (ACWP).
Actual cost for work performed (ACWP)
Actual CostAC
1.2 Earned Value Management Terms and Formulas
1.3 Project Variance & Performance
Index
Project
Variance
Schedule
Variance
Cost
Variance
SV CV
EV – PV
EV – AC
Project Variance
According To Earned Value Management Three Terms We Can Define The Project
Variance :-
• Planned Value (PV)
• Earned Value (EV)
• Actual Cost (AC)
1.3 Project Variance & Performance Index
SV < 0
Behind Schedule SV = 0
On Schedule
SV > 0
Ahead of Schedule
Planned Value (PV) - Earned value (EV) - Actual Cost (AC)
Schedule Variance (SV) =
EV – PV
1.3 Project Variance & Performance Index
CV < 0
Over Budget CV = 0
On Budget
CV > 0
Under Budget
Planned Value (PV) - Earned value (EV) - Actual Cost (AC)
Cost Variance (CV) =
EV – AC
1.3 Project Variance & Performance Index
Project
Performance
Index
Schedule
Performance
Index
Cost
Performance
Index
SPI CPI
EV / PV
EV / AC
Performance Index
According To Earned Value Management Three Terms We Can Define The Project
Performance Index :-
• Planned Value (PV)
• Earned Value (EV)
• Actual Cost (AC)
1.3 Project Variance & Performance Index
SPI < 1
Behind Schedule
SPI = 1
On Schedule
SPI > 1
Ahead of Schedule
Schedule Performance Index (SPI) =
EV / PV
Planned Value (PV) - Earned value (EV) - Actual Cost (AC)
1.3 Project Variance & Performance Index
Cost Performance Index (CPI) =
EV / AC
Planned Value (PV) - Earned value (EV) - Actual Cost (AC)
CPI < 1
Over Budget
CPI = 1
On Budget
CPI > 1
Under Budget
1.3 Project Variance & Performance Index
 Planned Value (PV)
 Earned value (EV)
 Actual Cost (AC)
 Schedule Variance (SV)
 Cost Variance (CV)
 Schedule Performance Index (SPI)
 Cost Performance Index (CPI)
1.3 Project Variance & Performance Index
Quantity Cost | Unit
Budget 100 500 S.R
Actual 120 600 S.R
Example ( Case Study )
• This Schedule Shows Some Information About Budgeted
And Actual Cost To (XYZ) Construction Project ,
According To EVM Techniques Calculate The Following
Terms Then Define The Project Status (Schedule &
Budget) ?
• PV = 500 x 100 = 50.000 S.R
• EV = 500 x 120 = 60.000 S.R
• AC = 600 x 120 = 72.000 S.R
• SV = EV – PV = 60.000 – 50.000 = 10.000 S.R
• CV = EV – AC = 60.000 – 72.000 = -12.000 S.R
• SPI = EV / PV = 60.000 / 50.000 = 1.2
• CPI = EV / AC = 60.000 / 72.000 = 0.83
The Project (XYZ ) Status at this Time
• According SV & SPI The Project Ahead Of Schedule.
• According CV & CPI The Project Over Budget.
1.4 Project Forecasting
1.4 Project Forecasting
Project Forecasting
• Consists Of Taking The Project Status
Information And Extrapolating The Current
Project Performance To The End Of The
Project and How The Future Will Turn Out
Based On Evidence Or Assumptions.
• The Purpose Of Forecasting Is To Give
Managers Insight Into How Profitable
Projects Are Likely To Be In The Future.
1.4 Project Forecasting
Forecasting Terms :-
• Budget at Completion (BAC)
• Estimate at Completion (EAC)
• Estimate to Complete (ETC)
 Considering The Same Budgeted Rate
 Considering CPI
 Considering CPI and SPI
• Variance At Completion (VAC)
• To Complete Performance Index (TCPI)
1.4 Project Forecasting
• Estimate To Complete (ETC)
Is The Estimated Cost Required To Complete The Remainder Of
The Project There Are Various Methods To Calculate The (ETC):-
 Considering The Same Budgeted Rate
EAC = AC + (BAC – EV)
 Considering CPI
EAC = BAC / CPI
 Considering CPI and SPI
EAC = AC + [ (BAC – EV) / (CPI x SPI) ]
• Budget At Completion (BAC)
Is The Total Budget Allocated To The Project
• Estimate At Completion (EAC)
Is The Expected Total Cost Of A Schedule Activity Component, EAC Is Equal To The Actual Cost Of Work Performed
(ACWP) + The Estimate To Complete (ETC) For All Of The Remaining Work.
1.4 Project Forecasting
• Variance At Completion (VAC)
Is The Difference Between The Budget At Completion(BAC) And The Estimate
At Completion (EAC)
VAC = BAC – EAC
• To Complete Performance Index (TCPI)
It’s The Cost Performance That Must Be Achieved On The Remaining Work To Meet A Specified Goal Like
BAC Or EAC, It Represents The Ratio Between Remaining Works And Remaining Funds.
TCPI = (BAC- EV) / (BAC – AC) Or TCPI = (BAC-EV) / (EAC – AC)
From the Previous Example
• PV = 500 x 100 = 50.000 S.R
• EV = 500 x 120 = 60.000 S.R
• AC = 600 x 120 = 72.000 S.R
• Assumed BAC = 500.000 S.R
TCPI =
(BAC-EV)
---------------------
(BAC – AC)
TCPI =
500.000 - 60.000
-----------------------
500.000 – 72.000
TCPI =
1.028
TCPI =
440.000
--------------
428.000
Project Performance Analysis

More Related Content

What's hot

Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value ManagementMansoor Shoaib
 
Effective project management skills
Effective project management skillsEffective project management skills
Effective project management skillsCharles Cotter, PhD
 
Earned value management for Beginners
Earned value management for Beginners Earned value management for Beginners
Earned value management for Beginners Shenin Hassan
 
A simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value ManagementA simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value ManagementProPM Academy
 
Earned value analysis - presentation
Earned value analysis  -  presentationEarned value analysis  -  presentation
Earned value analysis - presentationProPM Academy
 
Project Management
Project ManagementProject Management
Project ManagementMark Roman
 
Earned Value Analysis - EVA
Earned Value Analysis - EVAEarned Value Analysis - EVA
Earned Value Analysis - EVAAhmed Bamasdoos
 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniquesShivangi Saini
 
Cost management plan
Cost management planCost management plan
Cost management planJody R Flower
 
Chapter 7 managing risk
Chapter 7   managing riskChapter 7   managing risk
Chapter 7 managing riskHammad Hashmi
 
Estimating Cost & Time.ppt
Estimating Cost & Time.pptEstimating Cost & Time.ppt
Estimating Cost & Time.ppt341741357
 
Work breakdown structures
Work breakdown structures Work breakdown structures
Work breakdown structures Ian Cammack
 
project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 waleed hamdy
 

What's hot (20)

Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Effective project management skills
Effective project management skillsEffective project management skills
Effective project management skills
 
Earned value management for Beginners
Earned value management for Beginners Earned value management for Beginners
Earned value management for Beginners
 
Project Control Process
Project Control ProcessProject Control Process
Project Control Process
 
A simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value ManagementA simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value Management
 
Earned value analysis - presentation
Earned value analysis  -  presentationEarned value analysis  -  presentation
Earned value analysis - presentation
 
Project Management
Project ManagementProject Management
Project Management
 
Project Management Tools and Techniques
Project Management Tools and TechniquesProject Management Tools and Techniques
Project Management Tools and Techniques
 
Project Planning Scheduling
Project Planning SchedulingProject Planning Scheduling
Project Planning Scheduling
 
Earned Value Analysis - EVA
Earned Value Analysis - EVAEarned Value Analysis - EVA
Earned Value Analysis - EVA
 
Project evaluation
Project evaluationProject evaluation
Project evaluation
 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniques
 
Project Management Concepts
Project Management ConceptsProject Management Concepts
Project Management Concepts
 
Cost management plan
Cost management planCost management plan
Cost management plan
 
Chapter 7 managing risk
Chapter 7   managing riskChapter 7   managing risk
Chapter 7 managing risk
 
Project Closing
Project ClosingProject Closing
Project Closing
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Estimating Cost & Time.ppt
Estimating Cost & Time.pptEstimating Cost & Time.ppt
Estimating Cost & Time.ppt
 
Work breakdown structures
Work breakdown structures Work breakdown structures
Work breakdown structures
 
project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 project control using earned value analysis - Part 01
project control using earned value analysis - Part 01
 

Viewers also liked

A simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in actionA simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in actionPlanisware
 
Earned value management with Examples | Control Cost | PMBOK | PMP
Earned value management with Examples | Control Cost | PMBOK | PMPEarned value management with Examples | Control Cost | PMBOK | PMP
Earned value management with Examples | Control Cost | PMBOK | PMPJustAcademy
 
A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)Glen Alleman
 
Earning Value from Earned Value Management
Earning Value from Earned Value ManagementEarning Value from Earned Value Management
Earning Value from Earned Value ManagementGlen Alleman
 
Earned Value Analysis - Basic Concepts
Earned Value Analysis  - Basic ConceptsEarned Value Analysis  - Basic Concepts
Earned Value Analysis - Basic ConceptsRicardo Viana Vargas
 
iPLON presentation at Intersolar Mumbai 15 Dec 2011
iPLON presentation at Intersolar Mumbai 15 Dec 2011iPLON presentation at Intersolar Mumbai 15 Dec 2011
iPLON presentation at Intersolar Mumbai 15 Dec 2011iplon
 
Climates in places where I have lived
Climates in places where I have livedClimates in places where I have lived
Climates in places where I have livedMiguel Mariscal
 
Outdoor testing, analysis and performance predictions of PV technologies [PV ...
Outdoor testing, analysis and performance predictions of PV technologies [PV ...Outdoor testing, analysis and performance predictions of PV technologies [PV ...
Outdoor testing, analysis and performance predictions of PV technologies [PV ...Smithers Apex
 
PMP Application - Step by Step
PMP Application - Step by StepPMP Application - Step by Step
PMP Application - Step by StepWaleed Elnaggar
 
Thermal imagers-Thermography on Photovoltaic Modules
Thermal imagers-Thermography on Photovoltaic Modules Thermal imagers-Thermography on Photovoltaic Modules
Thermal imagers-Thermography on Photovoltaic Modules Testo Azerbaijan
 

Viewers also liked (20)

A simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in actionA simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in action
 
Earned Value fundamentals
Earned Value fundamentalsEarned Value fundamentals
Earned Value fundamentals
 
Back to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinarBack to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinar
 
Earned value management with Examples | Control Cost | PMBOK | PMP
Earned value management with Examples | Control Cost | PMBOK | PMPEarned value management with Examples | Control Cost | PMBOK | PMP
Earned value management with Examples | Control Cost | PMBOK | PMP
 
A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)
 
Earning Value from Earned Value Management
Earning Value from Earned Value ManagementEarning Value from Earned Value Management
Earning Value from Earned Value Management
 
Earned Value Analysis - Basic Concepts
Earned Value Analysis  - Basic ConceptsEarned Value Analysis  - Basic Concepts
Earned Value Analysis - Basic Concepts
 
iPLON presentation at Intersolar Mumbai 15 Dec 2011
iPLON presentation at Intersolar Mumbai 15 Dec 2011iPLON presentation at Intersolar Mumbai 15 Dec 2011
iPLON presentation at Intersolar Mumbai 15 Dec 2011
 
Climates in places where I have lived
Climates in places where I have livedClimates in places where I have lived
Climates in places where I have lived
 
Outdoor testing, analysis and performance predictions of PV technologies [PV ...
Outdoor testing, analysis and performance predictions of PV technologies [PV ...Outdoor testing, analysis and performance predictions of PV technologies [PV ...
Outdoor testing, analysis and performance predictions of PV technologies [PV ...
 
26 schweiger impact_of_spectral_irradiance_on_energy_yield
26 schweiger impact_of_spectral_irradiance_on_energy_yield26 schweiger impact_of_spectral_irradiance_on_energy_yield
26 schweiger impact_of_spectral_irradiance_on_energy_yield
 
Lecture 5 description of electro acoustic characteristics of hearing instrume...
Lecture 5 description of electro acoustic characteristics of hearing instrume...Lecture 5 description of electro acoustic characteristics of hearing instrume...
Lecture 5 description of electro acoustic characteristics of hearing instrume...
 
PMP Application - Step by Step
PMP Application - Step by StepPMP Application - Step by Step
PMP Application - Step by Step
 
Pmp in summary
Pmp in summaryPmp in summary
Pmp in summary
 
2014 PV Performance Modeling Workshop: Toward Reliable Module Temperature Mea...
2014 PV Performance Modeling Workshop: Toward Reliable Module Temperature Mea...2014 PV Performance Modeling Workshop: Toward Reliable Module Temperature Mea...
2014 PV Performance Modeling Workshop: Toward Reliable Module Temperature Mea...
 
41 corbellini analysis_and_modelling_of_bifacial_pv_modules
41 corbellini analysis_and_modelling_of_bifacial_pv_modules41 corbellini analysis_and_modelling_of_bifacial_pv_modules
41 corbellini analysis_and_modelling_of_bifacial_pv_modules
 
Thermal imagers-Thermography on Photovoltaic Modules
Thermal imagers-Thermography on Photovoltaic Modules Thermal imagers-Thermography on Photovoltaic Modules
Thermal imagers-Thermography on Photovoltaic Modules
 
Session 3 gdas pmp study group presentation
Session 3   gdas pmp study group presentationSession 3   gdas pmp study group presentation
Session 3 gdas pmp study group presentation
 
Session 8 gdas pmp study group presentation
Session 8   gdas pmp study group presentationSession 8   gdas pmp study group presentation
Session 8 gdas pmp study group presentation
 
Session 10 gdas pmp study group presentation
Session 10   gdas pmp study group presentationSession 10   gdas pmp study group presentation
Session 10 gdas pmp study group presentation
 

Similar to Project Performance Analysis

Track Project Performance - Earned Value Management
Track Project Performance - Earned Value ManagementTrack Project Performance - Earned Value Management
Track Project Performance - Earned Value ManagementBaroness PM
 
PM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdfPM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdfNajm Naqvi
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisBECM, RUET, Bangladesh
 
Earned value analysis (1)
Earned value analysis (1)Earned value analysis (1)
Earned value analysis (1)Harshit Mahajan
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost ManagementSerdar Temiz
 
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxsagarlesley
 
Module 06 Adv Project Manager Budget Mgmt.ppt
Module 06 Adv Project Manager Budget Mgmt.pptModule 06 Adv Project Manager Budget Mgmt.ppt
Module 06 Adv Project Manager Budget Mgmt.pptAsBali1
 
07 projectcostmanagement
07 projectcostmanagement07 projectcostmanagement
07 projectcostmanagementDhamo daran
 
Earned value Project Management (evpm)
Earned value Project Management (evpm)Earned value Project Management (evpm)
Earned value Project Management (evpm)Ejaz Bhatti
 
day 3-2 PMP.pptx
day 3-2 PMP.pptxday 3-2 PMP.pptx
day 3-2 PMP.pptxAhmedKayed6
 
PMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - FormulasPMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - FormulasAnand Bobade
 
EVMmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmm.pdf
EVMmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmm.pdfEVMmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmm.pdf
EVMmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmm.pdfRedhaElhuni
 

Similar to Project Performance Analysis (20)

Track Project Performance - Earned Value Management
Track Project Performance - Earned Value ManagementTrack Project Performance - Earned Value Management
Track Project Performance - Earned Value Management
 
PM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdfPM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdf
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value Analysis
 
Earned value management
Earned value managementEarned value management
Earned value management
 
Project Management EVM & SCBA
Project Management EVM & SCBAProject Management EVM & SCBA
Project Management EVM & SCBA
 
Earned value analysis (1)
Earned value analysis (1)Earned value analysis (1)
Earned value analysis (1)
 
PMP COST FORMULAE
PMP COST FORMULAEPMP COST FORMULAE
PMP COST FORMULAE
 
Delivering nothing efficiently
Delivering nothing efficientlyDelivering nothing efficiently
Delivering nothing efficiently
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docx
 
Module 06 Adv PM Budget Mgmt.ppt
Module 06 Adv PM Budget Mgmt.pptModule 06 Adv PM Budget Mgmt.ppt
Module 06 Adv PM Budget Mgmt.ppt
 
Module 06 Adv Project Manager Budget Mgmt.ppt
Module 06 Adv Project Manager Budget Mgmt.pptModule 06 Adv Project Manager Budget Mgmt.ppt
Module 06 Adv Project Manager Budget Mgmt.ppt
 
07 projectcostmanagement
07 projectcostmanagement07 projectcostmanagement
07 projectcostmanagement
 
Project monitoring lecture 1
Project monitoring lecture 1Project monitoring lecture 1
Project monitoring lecture 1
 
Earned value Project Management (evpm)
Earned value Project Management (evpm)Earned value Project Management (evpm)
Earned value Project Management (evpm)
 
day 3-2 PMP.pptx
day 3-2 PMP.pptxday 3-2 PMP.pptx
day 3-2 PMP.pptx
 
PMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - FormulasPMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - Formulas
 
EVMmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmm.pdf
EVMmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmm.pdfEVMmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmm.pdf
EVMmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmm.pdf
 
Basics of EVM.pdf
Basics of  EVM.pdfBasics of  EVM.pdf
Basics of EVM.pdf
 
Earned value 01
Earned value 01Earned value 01
Earned value 01
 

Recently uploaded

Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Pooja Nehwal
 
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, MumbaiPooja Nehwal
 
operational plan ppt.pptx nursing management
operational plan ppt.pptx nursing managementoperational plan ppt.pptx nursing management
operational plan ppt.pptx nursing managementTulsiDhidhi1
 
Day 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampDay 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampPLCLeadershipDevelop
 
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607dollysharma2066
 
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girladitipandeya
 
internal analysis on strategic management
internal analysis on strategic managementinternal analysis on strategic management
internal analysis on strategic managementharfimakarim
 
CEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biographyCEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biographyHafizMuhammadAbdulla5
 
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Nehwal
 

Recently uploaded (20)

Becoming an Inclusive Leader - Bernadette Thompson
Becoming an Inclusive Leader - Bernadette ThompsonBecoming an Inclusive Leader - Bernadette Thompson
Becoming an Inclusive Leader - Bernadette Thompson
 
Imagine - HR; are handling the 'bad banter' - Stella Chandler.pdf
Imagine - HR; are handling the 'bad banter' - Stella Chandler.pdfImagine - HR; are handling the 'bad banter' - Stella Chandler.pdf
Imagine - HR; are handling the 'bad banter' - Stella Chandler.pdf
 
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
 
Disrupt or be Disrupted - Kirk Vallis.pdf
Disrupt or be Disrupted - Kirk Vallis.pdfDisrupt or be Disrupted - Kirk Vallis.pdf
Disrupt or be Disrupted - Kirk Vallis.pdf
 
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
 
operational plan ppt.pptx nursing management
operational plan ppt.pptx nursing managementoperational plan ppt.pptx nursing management
operational plan ppt.pptx nursing management
 
Empowering Local Government Frontline Services - Mo Baines.pdf
Empowering Local Government Frontline Services - Mo Baines.pdfEmpowering Local Government Frontline Services - Mo Baines.pdf
Empowering Local Government Frontline Services - Mo Baines.pdf
 
Day 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampDay 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC Bootcamp
 
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
 
Rohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No AdvanceRohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
 
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg PartnershipUnlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
 
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote SpeakerLeadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
 
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
 
Discover -CQ Master Class - Rikita Wadhwa.pdf
Discover -CQ Master Class - Rikita Wadhwa.pdfDiscover -CQ Master Class - Rikita Wadhwa.pdf
Discover -CQ Master Class - Rikita Wadhwa.pdf
 
internal analysis on strategic management
internal analysis on strategic managementinternal analysis on strategic management
internal analysis on strategic management
 
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance VVIP 🍎 SERVICE
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SERVICECall Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SERVICE
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance VVIP 🍎 SERVICE
 
LoveLocalGov - Chris Twigg, Inner Circle
LoveLocalGov - Chris Twigg, Inner CircleLoveLocalGov - Chris Twigg, Inner Circle
LoveLocalGov - Chris Twigg, Inner Circle
 
CEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biographyCEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biography
 
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
 
Peak Performance & Resilience - Dr Dorian Dugmore
Peak Performance & Resilience - Dr Dorian DugmorePeak Performance & Resilience - Dr Dorian Dugmore
Peak Performance & Resilience - Dr Dorian Dugmore
 

Project Performance Analysis

  • 1. PROJECTS PERFORMANCE ANALYSIS & FORECASTING ® Prepared By: WALEED ELBASYOUNI Sr. Architect, PMP , SFC™, 6Sigma™ Using Earned Value Management
  • 2. Session Content :- • Introduction • Overview of Key Performance Indicators ( KPI ) • What Is The Earned Value Management ? • Why Project Managers Use EVM ? • Earned Value Management Terms and Formulas • Planned value (PV) • Earned value (EV) • Actual cost (AC) • Variance • Schedule Variance ( SV ) • Cost Variance ( CV ) • Performance Index • Schedule Performance Index (SPI) • Cost Performance Index (CPI) • Example ( Case Study ) • Project Forecasting • Budget at Completion (BAC) • Estimate at Completion (EAC) • Estimate to Complete (ETC). • Variance at Completion (VAC) • To Complete Performance Index (TCPI)
  • 4. 1.1 Introduction Overview of Key Performance Indicators ( KPI ) • Key Performance Indicators ( KPI ) are a Set Of Quantifiable Measures That a Company Uses To Gauge Its Performance Over Time. • These Metrics Are Used To Determine a Company's Progress In Achieving Its Strategic and Operational Goals, And Also To Compare A Company's Performance Against Other Businesses Within Its Industry.
  • 5. What Is The Earned Value Management ? • Earned Value Management Is a Project Management Technique For Measuring Project Performance And Progress. • Earned Value Is An Approach Where You Monitor The Project Plan, Actual Work, And Work-completed Value To See If a Project Is On Track. • Earned Value Shows How Much Of The Budget And Time Should Have Been Spent, With Regard To The Amount Of Work Done So Far. Why Project Managers Use EVM ? • Project Managers Use EVM To Assess The Schedule and Cost Performance Of a Project To Know Exactly Whether The Project Is: (Ahead Of / On / Behind Schedule) - ( Under / On / Over Budget ) 1.1 Introduction
  • 6. 1.2 Earned Value Management Terms and Formulas
  • 7. Planned value Earned value Actual Cost PV EV AC 1.2 Earned Value Management Terms and Formulas  Any Project Manager Use Earned Value Management To Assess The Schedule and Cost Performance Of a Project He Should Based On Three Terms. EVMEVM PVPV EVEVACAC
  • 8. Budgeted Cost For Work Scheduled (BCWS) Planned valuePV • The Approved Budget For The Work Scheduled To Be Completed By a Specified Date. • Also Referred To As The Budgeted Cost Of Work Scheduled (BCWS). 1.2 Earned Value Management Terms and Formulas
  • 9. Budgeted Cost For Work Performed (BCWP) Earned valueEV • The Approved Budget For The Work Actually Completed By The Specified Date. • Also Referred To As The Budgeted Cost Of Work Performed (BCWP). 1.2 Earned Value Management Terms and Formulas
  • 10. • The Costs Actually Incurred For The Work Completed By The Specified Date. • Also Referred To As The Actual Cost Of Work Performed (ACWP). Actual cost for work performed (ACWP) Actual CostAC 1.2 Earned Value Management Terms and Formulas
  • 11. 1.3 Project Variance & Performance Index
  • 12. Project Variance Schedule Variance Cost Variance SV CV EV – PV EV – AC Project Variance According To Earned Value Management Three Terms We Can Define The Project Variance :- • Planned Value (PV) • Earned Value (EV) • Actual Cost (AC) 1.3 Project Variance & Performance Index
  • 13. SV < 0 Behind Schedule SV = 0 On Schedule SV > 0 Ahead of Schedule Planned Value (PV) - Earned value (EV) - Actual Cost (AC) Schedule Variance (SV) = EV – PV 1.3 Project Variance & Performance Index
  • 14. CV < 0 Over Budget CV = 0 On Budget CV > 0 Under Budget Planned Value (PV) - Earned value (EV) - Actual Cost (AC) Cost Variance (CV) = EV – AC 1.3 Project Variance & Performance Index
  • 15. Project Performance Index Schedule Performance Index Cost Performance Index SPI CPI EV / PV EV / AC Performance Index According To Earned Value Management Three Terms We Can Define The Project Performance Index :- • Planned Value (PV) • Earned Value (EV) • Actual Cost (AC) 1.3 Project Variance & Performance Index
  • 16. SPI < 1 Behind Schedule SPI = 1 On Schedule SPI > 1 Ahead of Schedule Schedule Performance Index (SPI) = EV / PV Planned Value (PV) - Earned value (EV) - Actual Cost (AC) 1.3 Project Variance & Performance Index
  • 17. Cost Performance Index (CPI) = EV / AC Planned Value (PV) - Earned value (EV) - Actual Cost (AC) CPI < 1 Over Budget CPI = 1 On Budget CPI > 1 Under Budget 1.3 Project Variance & Performance Index
  • 18.  Planned Value (PV)  Earned value (EV)  Actual Cost (AC)  Schedule Variance (SV)  Cost Variance (CV)  Schedule Performance Index (SPI)  Cost Performance Index (CPI) 1.3 Project Variance & Performance Index Quantity Cost | Unit Budget 100 500 S.R Actual 120 600 S.R Example ( Case Study ) • This Schedule Shows Some Information About Budgeted And Actual Cost To (XYZ) Construction Project , According To EVM Techniques Calculate The Following Terms Then Define The Project Status (Schedule & Budget) ? • PV = 500 x 100 = 50.000 S.R • EV = 500 x 120 = 60.000 S.R • AC = 600 x 120 = 72.000 S.R • SV = EV – PV = 60.000 – 50.000 = 10.000 S.R • CV = EV – AC = 60.000 – 72.000 = -12.000 S.R • SPI = EV / PV = 60.000 / 50.000 = 1.2 • CPI = EV / AC = 60.000 / 72.000 = 0.83 The Project (XYZ ) Status at this Time • According SV & SPI The Project Ahead Of Schedule. • According CV & CPI The Project Over Budget.
  • 20. 1.4 Project Forecasting Project Forecasting • Consists Of Taking The Project Status Information And Extrapolating The Current Project Performance To The End Of The Project and How The Future Will Turn Out Based On Evidence Or Assumptions. • The Purpose Of Forecasting Is To Give Managers Insight Into How Profitable Projects Are Likely To Be In The Future.
  • 21. 1.4 Project Forecasting Forecasting Terms :- • Budget at Completion (BAC) • Estimate at Completion (EAC) • Estimate to Complete (ETC)  Considering The Same Budgeted Rate  Considering CPI  Considering CPI and SPI • Variance At Completion (VAC) • To Complete Performance Index (TCPI)
  • 22. 1.4 Project Forecasting • Estimate To Complete (ETC) Is The Estimated Cost Required To Complete The Remainder Of The Project There Are Various Methods To Calculate The (ETC):-  Considering The Same Budgeted Rate EAC = AC + (BAC – EV)  Considering CPI EAC = BAC / CPI  Considering CPI and SPI EAC = AC + [ (BAC – EV) / (CPI x SPI) ] • Budget At Completion (BAC) Is The Total Budget Allocated To The Project • Estimate At Completion (EAC) Is The Expected Total Cost Of A Schedule Activity Component, EAC Is Equal To The Actual Cost Of Work Performed (ACWP) + The Estimate To Complete (ETC) For All Of The Remaining Work.
  • 23. 1.4 Project Forecasting • Variance At Completion (VAC) Is The Difference Between The Budget At Completion(BAC) And The Estimate At Completion (EAC) VAC = BAC – EAC • To Complete Performance Index (TCPI) It’s The Cost Performance That Must Be Achieved On The Remaining Work To Meet A Specified Goal Like BAC Or EAC, It Represents The Ratio Between Remaining Works And Remaining Funds. TCPI = (BAC- EV) / (BAC – AC) Or TCPI = (BAC-EV) / (EAC – AC) From the Previous Example • PV = 500 x 100 = 50.000 S.R • EV = 500 x 120 = 60.000 S.R • AC = 600 x 120 = 72.000 S.R • Assumed BAC = 500.000 S.R TCPI = (BAC-EV) --------------------- (BAC – AC) TCPI = 500.000 - 60.000 ----------------------- 500.000 – 72.000 TCPI = 1.028 TCPI = 440.000 -------------- 428.000