PROGRAM BACKGROUND
1. Following the completion of the National Water Supply and Sanitation program which was
started in May 2004 as a five years project with USD100 million (75 million USD credit and 25
million USD grant) from IDA and (later DFID joined as co financer with 70 million Great
Britain Pound in May 2007), IDA has made an agreement with Government of Ethiopia to
finance new program at a scope of US $ 205 Million for five years (2014 –2019) that has three
components of which Urban Water Supply and Sanitation is one of them.
KEY ELEMENTS OF POLICIES
2. The project implementation arrangements reflect the policy objectives of decentralization to the
lowest possible level, involvement of all stakeholders in the process, integration of sanitation
with improvements to water supply, and recognizing water as an economic as well as social
good. A demand responsive, performance-based approach will be followed so that communities
will receive assistance to put in place institutions and develop capacity for implementation and
will be able to access more resources for development of their water supply and sanitation
systems as they demonstrate capacity for implementation. A stepped approach will be
employed for both urban and rural water supply and sanitation to allow each community to
move at is own pace and receive further assistance when they are ready.
PROGRAM IMPLEMENTATION MECHANISMS
3. The One WASH National Program is the Government of Ethiopia’s (GoE) main instrument for
achieving the goals set out in the Growth and Transformation Plan (GTP). Alongside the this
national program, WB has simultaneously launched a WaSH II water supply and sanitation
program a continuation of the WaSH I. The program has started operation since July 2014 and
expected to stay three years of period.
PROGRAM COMPONENTS AND IMPLEMENTATION MODALITY
4. The OWNP has mainly 4 components: 1) Rural and Pastoralist WaSH, 2) Urban WaSH, 3)
Institutional WaSH and 4) Program Management and Capacity Building. The Urban
WASH(for water supply and sanitation improvements) finances study and design, capacity
building and management support, environmental and resettlement safeguards, immediate
service improvements and expansion and augmentation of Sanitation and urban environmental
improvements which will include desludging equipment and facilities, latrine sludge/septage
3
treatment plant and public toilets construction, and development of wastewater management
systems in selected category I cities and towns.
5. Cities under this ToR consideration are ones eligible for WRDF loan to do actives and services
indicated in sub component 2: sanitation services which include mainly, for im
a) Development of wastewater master plan
b) Tendering for sanitation services, works and goods
c) Procurement of works and goods/supplies
d) Carrying out building capacity activities, including technical O&M capacity
e) Development of appropriate service delivery models for urban sanitation
GENERAL CONSIDERATIONS
6. The Employer is responsible for preparing and implementing the project, and therefore for
selecting the consultant, and awarding and subsequently administering the contract. The Bank,
for its part, is required by its Articles of Agreement to “ensure that the proceeds of any
loan/grants are used only for the purposes for which the loan was granted, with due
attention to considerations of economy and efficiency and without regard to political or
other non-economic influences or considerations,” and it has established detailed
procedures for this purpose.
7. While the specific rules and procedures to be followed for employing consultants depend
on the circumstances of the particular case, five main considerations guide the Bank’s policy
on the selection process: (a) the need for high-quality services, (b) the need for economy
and efficiency, (c) the need to give all eligible consultants an opportunity to compete in
providing the services financed by the Bank, (d) the Bank’s interest in encouraging the
development and use of national consultants in its developing member countries, and (e)
the need for transparency in the selection process.
8. The Bank considers that, in the majority of cases, these considerations can best be addressed
through competition among qualified short-listed firms in which the selection is based on the
quality of the proposal and, where appropriate, on the cost of the services to be provided.
9. Water is consumed as an essential life-support substance by all living beings, including
humans. The essentials of a sustainable life-support system are not only the life-generating
and sustaining elements: air, water, light, heat, food, fluid and living space, but also the
removal of waste products:, effluent, trash and sanitary waste, also known as sewage.
Sewage is disposed of in several ways, mainly two: removal in a waterborne sewer systems
(sewerage) or disposed via an on-site sanitation system (pit latrines or septic tanks).
10. The management of liquid waste at national level has been very weak. About half of the
households handle household liquid waste by openly discharging into any accessible public
properties, such as streets, drainage lines and nearby open space. Sewer line application is
not that much familiar in the country except in Addis Ababa.
11. Disposal system has arrangements to distribute the used water either to aquatic bodies such
4
as oceans, rivers, lakes, ponds, or lagoons or to land by absorption systems, groundwater
recharge, and irrigation. Waste water must be mixed, diluted and absorbed before it is
discharged to the general body of water, so that the receiving environments do not lose its
beneficial usable characteristics.
12. The Ministry of water, Irrigation and energy has tried to indicate the concern of the issues in
its policy clearly. It is therefore essential to address these challenges in an integrated and
regional manner, the all complex and wide range of the problem with in the frame of its
National Plan UAP, MDG and GTP preparing strategic document is important with strong
and indicative action of the plan with the participation of key stakeholders including the
public and private sectors are actively engaged.
13. For the coming GTP II plan, 36 towns will have feasibility study and detail design for
sewerage and for those which have greater than 200,000 population construction sewerage
system will be started.
14. Currently, urbanization has been accelerated, fuelled by rapid economic growth in the
Country, life standards have gradually improved. Urbanization and rapid economic growth
have resulted in demand for better water supply and sanitation services in the Country.
Because of all those reason Waste management is one of the urban basic services being
addressed by the Government of Ethiopia.
15. This is a lump sum contract for consultancy services.
LOCATION THE PROJECT TOWN
16. Adama city is located in Oromia National Regional State, East Shewa Zone at a distance of
100 ከm from Addis Ababa. its astronomical location is 8º44’ North Latitude and 39º04’ East
Longitude.
FOUNDATION
17. Adama was founded in 1924. It is one of the reform cities in the region and has city
administration consisting of 14 urban and four rural kebeles. The city has structure plan which
was prepared in 2004.
18. Adama City Administration is an autonomous first grade urban local government established
following proclamation no.65/2003, for the establishment of local urban administrations issued
by the Regional State of Oromiya. It is, therefore, responsible to administer and develop the
city. For better management, the city administration is structured on a two-tier organizational
hierarchy.
OBJECTIVE
19. Objective of the study is to produce study and detailed design documents for Sewerage
5
/waste water management system in typical 4 large towns (Adama, Mekelle, Bahir Dar and
Gonder) in the country.
Specific objectives
 Review previous and existing Study, Design and constructed sewerage systems of the
each town, evaluation of its functionality, and identification of basic issues / problems.
 Assess the feasibility of constructing decentralized and centralized wastewater treatment
and collection infrastructure at the current major discharge points. Review alternative
wastewater treatment plant(WWTP) scenarios including these decentralized WWTPs
and different arrangements of collection system and possibility of combined
sewerage.
 Selection of suitable route and design of force main of appropriate material to
carry out the sewerage due consideration of, Capable to conveyance the effluent through
gravity, accessible through existing infrastructure of roads / trails/tacks, least interference
with the social setup of the area, minimum social and environmental impacts, the
minimum damages to local Dug wells and other water resource, and Socially acceptable.
 Recommend the most appropriate and cost effective wastewater investment scenario. The
approach should be an optimal one for managing the Town’s wastewater treatment
requirements, reflecting locations and land requirements, treatment technologies, the
operations and maintenance characteristics of each technology studied, capital and
recurrent costs, sustainability, affordability, and other related factors
 Assess on-site sanitation facilities, septage collection and condition of septic tanks, fecal
sludge management strategies and effluent disposal fields.
 Preparation of detail design and engineering drawings for the up gradation of the waste
water management system based on the preferred alternative.
 Prepare a complete tender document for construction.
SCOPE OF SERVICES
20. The scope of consultancy services is divided in the following Tasks under Part I & II:
Task I: The details of the task will be not limited to
o Submission of inception report. The inception shall clearly indicate initial desk review,
field observations, existing situation, revised methodologies and approach to the
consulting services, revised schedule for activities, expert program, next deliverable
schedule and contacted individuals and references used. The inception report shall be
discussed and approved by the Client.
o Detail review report (1) the existing study and design reports including the sewerage
system functioning in the city. It shall include the assessement of on-site and off-site
complete sanitation chain facilities in the town to identify waste water management
6
characteristics.
o Detail report (2) on the design approach to Wastewater demand of the city, Where
does the wastewater come from?, Components of a Community’s Wastewater:
a)domestic (sanitary)- residential, institutional and commercial b) industrial),
c)Infiltration to Sanitary Sewer Systems d) Inflow to Sanitary Sewer Systems, also
identify quality of untreated wastewater for each categories; asses existing rivers
crossing the city and deep wells sources for level of contamination; propose the
computer software to be used;
o Prepare design criteria and concept plan for component of the town waste water
management project. Include also choice of technology and material to use. Concept
plan will be to provide a sound planning basis and finalize the criteria for detailed
engineering design under each subproject. Two or three scenarios to be delivered for the
client final choice. It shall indicate the economic analysis and sensitivity test for each
scenario (with centralized and decentralized treatment, separate or combined sewerage
systems). The size of the topography survey required and alternate choices shall be
presented.
o Appraisal workshop presentation before stepping to stage II.) (The panel shall have
specialists from MoWIE, MoH, Regional Bureau (Water and Health), Environmental
protection Office.
o Assess the technical, financial, social, and economic feasibility and sustainability and
priority of each subproject component, including the phasing of investments for
wastewater management including (a) sewage collection and treatment systems, (b)
septic tank sludge collection and treatment systems, and (c) other related investments.
o Assess in detail the operating utility’s: (a) financial management capacity; and (b)
financial state including income statements, balance sheet and cash flow statements, and
existing loan repayments. Analyze major constraints to the financial sustainability and
the degree of operational subsidies from the local government. Prepare financial
projections including revenues, operating and capital expenditures, and debt repayment.
o Assess the costs of wastewater collection and treatment and level of cost recovery
possible, and determine tariffs needed to ensure sustainable operations. Discuss with the
city utility/Municipality a phased politically acceptable way of introducing cost recovery
tariffs. Assess options and the feasibility of transferring responsibility for wastewater
services to a dedicated wastewater utility.
o Review the impact and affordability of introducing full and partial cost recovery in
wastewater management services. Assess demand on the basis of price, income, and
access to alternative supplies. Analyze the affordability of wastewater services and
assess willingness to pay for them.
o Assess in detail (a) financial management capacity, and (b) financial performance
including borrowing capacity and debt service coverage ratios relating to existing and
potential new loans. Prepare financial projections including revenues, operating and
7
capital expenditures, and debt repayment.
o Investigate alternative financing schemes for improving urban sanitation, including for
example municipal bonds, and public-private partnerships.
o Prepare detailed cost estimates and financing plans for each of the project components
and the Project as a whole. Prepare the financial arrangements specifying the foreign
exchange and local currency csts as applicable.
o Conduct comprehensive economic and financial analyses for each subproject and the
overall Project, using relevant WB guidelines, and handbooks. Based on past and
projected financial statements, compute relevant financial indicators, including, but not
limited to, debt service coverage ratios, and operating ratios. Compute for each
subproject and the overall project financial internal rates of return (FIRRs), weighted
average cost of capital (WACC), and economic internal rates of return (EIRRs). Analyse
the impact of the Project on poverty reduction. Review in detail the distribution of
project benefits, net economic benefits, and poverty impact.
o Prepare detailed project implementation and phasing schedules for each component, and
investigate implementation options including integrated design-procure construct
packages to improve implementation efficiency.
o Prepare an effective project performance monitoring system (PPMS) that includes
monitoring of the project's performance, benefits, and impact on poverty reduction.
Identify the training needs to strengthen performance monitoring capacity.
o Hold discussions with the city stakeholders to identify key issues and obtain their views
on capacity-building needs, and develop concepts for the design of the capacity-building
components. Develop a capacity-building program, and outline training programs and
recommended interventions that should be included in the Project, and estimated costs.
o Recommend subproject interventions to address gender imbalances, and interventions to
support other vulnerable groups, which will result in poverty reduction and social
inclusion strategy under the project.
o Develop and recommend mechanisms and procedures for public consultation and
community participation in project planning, operation and maintenance, project
implementation and management, particularly in relation to levels of service
performance, tariffs, and environmental protection.
o Assess the need for land acquisition in the Project. Where land acquisition is required, the
Consultant shall inform the Utility of the location, outline the likely resettlement
requirements and the work required to prepare an action plan to acquire the land
(including the preparation of cadastral plans) and resettle residents in accordance with
procedures regulated by the Federal and Regional ESFW Regulation covering the matter.
o Assess the need for preparing an indigenous peoples development framework,
development plan, or specific action in accordance with WBs policy on indigenous
peoples. If required, prepare the necessary framework, plan, and specific action in
accordance with WBs requirements. (xvi) Justify the Project from the point of view of
8
social dimensions (social impact, impact on poverty, marginalized and vulnerable
groups, and gender specific issues).
o Each intervention shall be screened for its environmental impact. For each intervention,
the initial objective shall be to determine if there will be a significant impact from the
proposed investment, based on criteria established under ESFW.
o The Consultant will concurrently prepare an initial environmental examination (IEE) or
environmental impact assessment (EIA), if warranted, for each individual subproject,
and a summary IEE or a summary EIA for the whole Project,
Task II: The details of the task work will be not limited to
o Detailed topographic surveys and drawings of plan & profile in A3 and Ao (general
layout) paper size. The topography coordinates shall be addendum UTM measurements.
The whole proposed route shall be surveyed. The soil investigation along selected
topographic survey routes and selected treatment sites;
o Zonal( where applicable) hydrological data analysis, Wastewater characterization,
and volume quantification based the sub catchment of the city drainage flow;
o detailed designing of sewerage Network, the route confirm to the master plan
layout recommendation and local development plan of the city; The specification shall
confirm to the latest material production standard, equipment output and method of for
all system components readable with bill of quantity pay items. The presentation shall
follow standard numbering method quantity surveying.
o Preparation of bid document based on the WB procurement requirements for works
and goods & related works; The Bill of quantities shall be detailed and specific to each
item of material uit od activity required and no lumped activities are allowed to be
submitted. Engineering Estimates derived from cost rate analysis prepared on Excel
spreadsheet correlated with outputs (manpower and equipment) and material. Production
3-D view of all treatment structures in appropriate CAD format. The ArcGIS report
whether soft or hard copy shall have complete presentation of the design pipe routes,
stations, major junction boxes, proposed treatment plants separated by implementation
phases;
o Appraisal workshop presentation before stepping to preparation of quantities.
o The Regional Bureau shall seek No Objection for the final document.
STUDY AND DESIGN TEAM STAFF
21. The Consulting firm shall be legally established firm and committed to put together a team
of highly qualified experts with direct experience and excellent understanding of technical,
economic, financial and environmental issues related to water supply and sewerage services
of major cities in the country.
22. The team will also need to have experience in conducting Feasibility Studies under the
conditions and regulations which exist in Major similar cities.
9
23. Resumes of the qualifications and experience of the key members of the team will be the key
criteria used to evaluate proposals.
Table 1: Activity Staff qualification requirement
S/No. Position
No of
person
Qualification/Experience
Person
Month
1 Team Leader
1
Wastewater/Sanitary Engineer/Civil :MSc or above
in Sanitary Engineering or related with 12 years or
above experience in the sanitation sub-sector with a
high credit to experiences in project manager for
study and designing of similar nature project
12
2 Wastewater/
sanitary
specialist 2
MSc or above in wastewater/ sanitary/ or related
fields with 8 years or above experience in the
Sanitation sub-sector with a high credit to
experiences of development of sanitary systems of
similar nature project .
12
3 Hydraulic
Engineer
1
MSc or above in /civil Engineering or related with
8 years or above experience in the water supply
and sanitation sub-sector with a high credit to
experiences in study and designing of of similar
nature project
12
4 Structural
Engineer
1
MSc or above in civil Engineering or related with 8
years or above experience in the water supply and
sanitation sub-sector with a high credit to
experiences in study and designing of of similar
nature project
4
5 Socio-Economist
1
BSc or above in economics with 8 yrs of
experience in similar nature projects
4
5 Mechanical
Engineer
/Electrical
Engineer
1
MSc or above in mechanical Engineering or
related with 8 years or above experience in the
wastewater with a high credit to experiences in
study and designing of similar nature project
4
7 Environmental
specialist
1
MSc or above in Environmental Engineering or
related with 8 years or above experience in the
water supply and sanitation sub-sector with a high
credit to experiences in study and designing of
different projects
4
8 Topographic
Surveyor 2
Minimum Technical diploma in surveying and 8
yrs relevant experience 4
9 Quantity
Surveyor
2
Diploma+10yrs relevant experience
5
10 Procurement
Specialist
1
BSc or above in civil Engineering or related with 8
years or above experience in the water supply and
sanitation sub-sector with a high credit to
experiences in study and designing of different
projects
2
11 AutoCAD
Draftsman
2
Diploma+10yrs relevant experience
12
10
CONSULTANT’S SERVICE ADMINISTRATION
24. The consultant firm is accountable to the Regional Water Supply and Sanitation Bureau at
the Regional Level. The sewerage system design and development Focal Person at MoWIE
in the Directorate will facilitate the execution of the assignment as project coordinator.
CLIENT’S INPUT FOR THE SERVICE
25. The client will:
 Avail to the consultant with all necessary data and document available.
 Facilitate to the consultant to have access to data and documents available in the WaSH
government sectors.
 Facilitate and organize stakeholders appraise the documents at each step.
ACTIVITY DELIVERABLES
Nr. Deliverables
Submission
Timing Day Pages
copies
Duration
Late
finish
1 Contract effectiveness 1
2 Inception Report 30 30 30 +Appendices 5 + CD
3 Part I draft report 90 120
Three reports( each
max 100 pages +
appendices)
5 + CD
4 Appraisal and part I Final report 20 140 5 + CD
5 Part II draft report 160 300
Four reports ( each max
100 pages + appendices)
5 + CD
6 Appraisal and Part I Final report 20 320
Four reports( each max
100 pages + appendices)
5 + CD
7 Bid Document including Dwgs 20 340
Specification, and BoQ,,
Bid document, Dwgs
5 + CD
8 No Objection 25 365
26. The Consulting firm shall recommend order of the activity deliverables in order of
presentation and respective timeline.
11
PAYMENT SCHEDULE
1) Signature of the contract. Down payment of 20% of the total budget
2) Delivery of the first interim report. Payment of 10% of the total budget.
3) Delivery of the second interim report (Task I). Payment of 10% of the total budget.
4) Delivery of the third interim report (Task II draft). Payment of 20% of the total budget.
5) Delivery and acceptance of the Final Payment (final report and bid document} of 40%
of the total budget following same procedure defined for former milestones.

More Related Content

What's hot

Neuse River Basic OWLS '14 Presentation
Neuse River Basic OWLS '14 PresentationNeuse River Basic OWLS '14 Presentation
Neuse River Basic OWLS '14 PresentationU.S. Water Alliance
 
Mega Cebu - World Water Day 2016
Mega Cebu - World Water Day 2016Mega Cebu - World Water Day 2016
Mega Cebu - World Water Day 2016Rehne Gibb Larena
 
Learning From the States to Mainstream Best Practices
Learning From the States to Mainstream Best PracticesLearning From the States to Mainstream Best Practices
Learning From the States to Mainstream Best PracticesNITI Aayog
 
02 sectoral planning 02_
02 sectoral planning 02_02 sectoral planning 02_
02 sectoral planning 02_Primum Nocere
 
Mr. Anju Gaur IEWP @ Workshop on River Basin Management Planning and Governan...
Mr. Anju Gaur IEWP @ Workshop on River Basin Management Planning and Governan...Mr. Anju Gaur IEWP @ Workshop on River Basin Management Planning and Governan...
Mr. Anju Gaur IEWP @ Workshop on River Basin Management Planning and Governan...India-EU Water Partnership
 
Work Session X: Water Quality - What Is Integrated Water Quality Planning And...
Work Session X: Water Quality - What Is Integrated Water Quality Planning And...Work Session X: Water Quality - What Is Integrated Water Quality Planning And...
Work Session X: Water Quality - What Is Integrated Water Quality Planning And...Best Best and Krieger LLP
 
DEBANJALI SAHA- VAMBAY POLICY
DEBANJALI SAHA- VAMBAY POLICYDEBANJALI SAHA- VAMBAY POLICY
DEBANJALI SAHA- VAMBAY POLICYNIT Rourkela
 
2013 Florida Legislative Summary - Environmental and Water Bills
2013 Florida Legislative Summary - Environmental and Water Bills2013 Florida Legislative Summary - Environmental and Water Bills
2013 Florida Legislative Summary - Environmental and Water BillsThomas F. Mullin
 
Only the Pipes Should be Hidden
Only the Pipes Should be HiddenOnly the Pipes Should be Hidden
Only the Pipes Should be HiddenAnnette Dubreuil
 
Sector planning presentation by Jim Sellen, Mike McDaniel, David Powell & Dav...
Sector planning presentation by Jim Sellen, Mike McDaniel, David Powell & Dav...Sector planning presentation by Jim Sellen, Mike McDaniel, David Powell & Dav...
Sector planning presentation by Jim Sellen, Mike McDaniel, David Powell & Dav...APA Florida
 
Follow-up to COP21 & COP22 Outcomes, INBO
Follow-up to COP21 & COP22 Outcomes, INBOFollow-up to COP21 & COP22 Outcomes, INBO
Follow-up to COP21 & COP22 Outcomes, INBOOECD Governance
 
Goals on Safety & Health, and Social Inclusivity of Wastewater in Makati City
Goals on Safety & Health, and Social Inclusivity of Wastewater in Makati City Goals on Safety & Health, and Social Inclusivity of Wastewater in Makati City
Goals on Safety & Health, and Social Inclusivity of Wastewater in Makati City Rodelon Ramos
 
TOD City Zoning, Permits, and Related Approval Processes
TOD City Zoning, Permits, and Related Approval ProcessesTOD City Zoning, Permits, and Related Approval Processes
TOD City Zoning, Permits, and Related Approval ProcessesJesse Souki
 
Chitral development vision
Chitral development visionChitral development vision
Chitral development visionTariqullah Khan
 
20161216 angolan national plan for rural water & sanitation (nrwssp) af...
20161216 angolan national plan for rural water & sanitation (nrwssp)   af...20161216 angolan national plan for rural water & sanitation (nrwssp)   af...
20161216 angolan national plan for rural water & sanitation (nrwssp) af...Development Workshop Angola
 
Water governance in France - ASTEE
Water governance in France - ASTEEWater governance in France - ASTEE
Water governance in France - ASTEEOECD Governance
 
2016-21 State of the Environment report for Moree Plains and Narrabri Councils
2016-21 State of the Environment report for Moree Plains and Narrabri Councils2016-21 State of the Environment report for Moree Plains and Narrabri Councils
2016-21 State of the Environment report for Moree Plains and Narrabri CouncilsNeil Dufty
 

What's hot (20)

Neuse River Basic OWLS '14 Presentation
Neuse River Basic OWLS '14 PresentationNeuse River Basic OWLS '14 Presentation
Neuse River Basic OWLS '14 Presentation
 
Mega Cebu - World Water Day 2016
Mega Cebu - World Water Day 2016Mega Cebu - World Water Day 2016
Mega Cebu - World Water Day 2016
 
Learning From the States to Mainstream Best Practices
Learning From the States to Mainstream Best PracticesLearning From the States to Mainstream Best Practices
Learning From the States to Mainstream Best Practices
 
02 sectoral planning 02_
02 sectoral planning 02_02 sectoral planning 02_
02 sectoral planning 02_
 
PWP & Water Sector Reforms
PWP & Water Sector ReformsPWP & Water Sector Reforms
PWP & Water Sector Reforms
 
Mr. Anju Gaur IEWP @ Workshop on River Basin Management Planning and Governan...
Mr. Anju Gaur IEWP @ Workshop on River Basin Management Planning and Governan...Mr. Anju Gaur IEWP @ Workshop on River Basin Management Planning and Governan...
Mr. Anju Gaur IEWP @ Workshop on River Basin Management Planning and Governan...
 
Work Session X: Water Quality - What Is Integrated Water Quality Planning And...
Work Session X: Water Quality - What Is Integrated Water Quality Planning And...Work Session X: Water Quality - What Is Integrated Water Quality Planning And...
Work Session X: Water Quality - What Is Integrated Water Quality Planning And...
 
DEBANJALI SAHA- VAMBAY POLICY
DEBANJALI SAHA- VAMBAY POLICYDEBANJALI SAHA- VAMBAY POLICY
DEBANJALI SAHA- VAMBAY POLICY
 
Jnnurm
JnnurmJnnurm
Jnnurm
 
Reformers
ReformersReformers
Reformers
 
2013 Florida Legislative Summary - Environmental and Water Bills
2013 Florida Legislative Summary - Environmental and Water Bills2013 Florida Legislative Summary - Environmental and Water Bills
2013 Florida Legislative Summary - Environmental and Water Bills
 
Only the Pipes Should be Hidden
Only the Pipes Should be HiddenOnly the Pipes Should be Hidden
Only the Pipes Should be Hidden
 
Sector planning presentation by Jim Sellen, Mike McDaniel, David Powell & Dav...
Sector planning presentation by Jim Sellen, Mike McDaniel, David Powell & Dav...Sector planning presentation by Jim Sellen, Mike McDaniel, David Powell & Dav...
Sector planning presentation by Jim Sellen, Mike McDaniel, David Powell & Dav...
 
Follow-up to COP21 & COP22 Outcomes, INBO
Follow-up to COP21 & COP22 Outcomes, INBOFollow-up to COP21 & COP22 Outcomes, INBO
Follow-up to COP21 & COP22 Outcomes, INBO
 
Goals on Safety & Health, and Social Inclusivity of Wastewater in Makati City
Goals on Safety & Health, and Social Inclusivity of Wastewater in Makati City Goals on Safety & Health, and Social Inclusivity of Wastewater in Makati City
Goals on Safety & Health, and Social Inclusivity of Wastewater in Makati City
 
TOD City Zoning, Permits, and Related Approval Processes
TOD City Zoning, Permits, and Related Approval ProcessesTOD City Zoning, Permits, and Related Approval Processes
TOD City Zoning, Permits, and Related Approval Processes
 
Chitral development vision
Chitral development visionChitral development vision
Chitral development vision
 
20161216 angolan national plan for rural water & sanitation (nrwssp) af...
20161216 angolan national plan for rural water & sanitation (nrwssp)   af...20161216 angolan national plan for rural water & sanitation (nrwssp)   af...
20161216 angolan national plan for rural water & sanitation (nrwssp) af...
 
Water governance in France - ASTEE
Water governance in France - ASTEEWater governance in France - ASTEE
Water governance in France - ASTEE
 
2016-21 State of the Environment report for Moree Plains and Narrabri Councils
2016-21 State of the Environment report for Moree Plains and Narrabri Councils2016-21 State of the Environment report for Moree Plains and Narrabri Councils
2016-21 State of the Environment report for Moree Plains and Narrabri Councils
 

Similar to 2cmc to r for sewarage system design

Public private partnership_(sanitation)[1]
Public private partnership_(sanitation)[1]Public private partnership_(sanitation)[1]
Public private partnership_(sanitation)[1]Shraddha Kulkarni
 
Ravi Riverfront Urban Development Project - Excerpts from the Announcement
Ravi Riverfront Urban Development Project - Excerpts from the AnnouncementRavi Riverfront Urban Development Project - Excerpts from the Announcement
Ravi Riverfront Urban Development Project - Excerpts from the AnnouncementKKM Architects
 
The African Development Bank in Action Activities in the water and sanitation...
The African Development Bank in Action Activities in the water and sanitation...The African Development Bank in Action Activities in the water and sanitation...
The African Development Bank in Action Activities in the water and sanitation...George Appiah
 
2015-Canadian-Municipal-Water-Consortium-Report-web
2015-Canadian-Municipal-Water-Consortium-Report-web2015-Canadian-Municipal-Water-Consortium-Report-web
2015-Canadian-Municipal-Water-Consortium-Report-webJennifer Dingman, PhD
 
10 page Summary of TrackFin's results in Morocco
10 page Summary of TrackFin's results in Morocco10 page Summary of TrackFin's results in Morocco
10 page Summary of TrackFin's results in MoroccoTrackFin
 
PPT presentation ESIAF1.pptx
PPT presentation ESIAF1.pptxPPT presentation ESIAF1.pptx
PPT presentation ESIAF1.pptxyonas513377
 
Strengthening M& E Systems in Africa Dakar presentation
Strengthening M& E Systems in Africa  Dakar presentationStrengthening M& E Systems in Africa  Dakar presentation
Strengthening M& E Systems in Africa Dakar presentationHawa Seydou DIOP
 
Overview of enabling environment and implementation of climate resilient WASH
Overview of enabling environment and implementation of climate resilient WASH Overview of enabling environment and implementation of climate resilient WASH
Overview of enabling environment and implementation of climate resilient WASH IRC
 
Dumaguete City Septage Management System
Dumaguete City Septage Management SystemDumaguete City Septage Management System
Dumaguete City Septage Management SystemOswar Mungkasa
 
Pollution controlboard
Pollution controlboardPollution controlboard
Pollution controlboardOnkar Chauhan
 
JAR review presentation
JAR review presentationJAR review presentation
JAR review presentationict4devwg
 
Assignment On: Government of the People’s Republic of Bangladesh National Po...
Assignment On:  Government of the People’s Republic of Bangladesh National Po...Assignment On:  Government of the People’s Republic of Bangladesh National Po...
Assignment On: Government of the People’s Republic of Bangladesh National Po...Asian Paint Bangladesh Ltd
 
Detailed understanding of the master plan ar. m. senthil
Detailed understanding of the master plan  ar. m. senthilDetailed understanding of the master plan  ar. m. senthil
Detailed understanding of the master plan ar. m. senthilAr. M. Senthil [ senthilmani ]
 
Session 3B Finance - Getenet community development funds ethiopia (pp tminimi...
Session 3B Finance - Getenet community development funds ethiopia (pp tminimi...Session 3B Finance - Getenet community development funds ethiopia (pp tminimi...
Session 3B Finance - Getenet community development funds ethiopia (pp tminimi...IRC
 
Waste water management
Waste water managementWaste water management
Waste water managementIman Ghosh
 
Integrated municipal stormwater and wastewater planning approach framework
Integrated municipal stormwater and wastewater planning approach frameworkIntegrated municipal stormwater and wastewater planning approach framework
Integrated municipal stormwater and wastewater planning approach frameworkThe Texas Network, LLC
 

Similar to 2cmc to r for sewarage system design (20)

003 NCWRM 2011 Fakih_Lebanon
003 NCWRM 2011 Fakih_Lebanon003 NCWRM 2011 Fakih_Lebanon
003 NCWRM 2011 Fakih_Lebanon
 
Public private partnership_(sanitation)[1]
Public private partnership_(sanitation)[1]Public private partnership_(sanitation)[1]
Public private partnership_(sanitation)[1]
 
Ravi Riverfront Urban Development Project - Excerpts from the Announcement
Ravi Riverfront Urban Development Project - Excerpts from the AnnouncementRavi Riverfront Urban Development Project - Excerpts from the Announcement
Ravi Riverfront Urban Development Project - Excerpts from the Announcement
 
The African Development Bank in Action Activities in the water and sanitation...
The African Development Bank in Action Activities in the water and sanitation...The African Development Bank in Action Activities in the water and sanitation...
The African Development Bank in Action Activities in the water and sanitation...
 
A M R U T.pptx
A M R U T.pptxA M R U T.pptx
A M R U T.pptx
 
2015-Canadian-Municipal-Water-Consortium-Report-web
2015-Canadian-Municipal-Water-Consortium-Report-web2015-Canadian-Municipal-Water-Consortium-Report-web
2015-Canadian-Municipal-Water-Consortium-Report-web
 
10 page Summary of TrackFin's results in Morocco
10 page Summary of TrackFin's results in Morocco10 page Summary of TrackFin's results in Morocco
10 page Summary of TrackFin's results in Morocco
 
PPT presentation ESIAF1.pptx
PPT presentation ESIAF1.pptxPPT presentation ESIAF1.pptx
PPT presentation ESIAF1.pptx
 
Strengthening M& E Systems in Africa Dakar presentation
Strengthening M& E Systems in Africa  Dakar presentationStrengthening M& E Systems in Africa  Dakar presentation
Strengthening M& E Systems in Africa Dakar presentation
 
Overview of enabling environment and implementation of climate resilient WASH
Overview of enabling environment and implementation of climate resilient WASH Overview of enabling environment and implementation of climate resilient WASH
Overview of enabling environment and implementation of climate resilient WASH
 
National water law policy
National water law policy  National water law policy
National water law policy
 
Dumaguete City Septage Management System
Dumaguete City Septage Management SystemDumaguete City Septage Management System
Dumaguete City Septage Management System
 
Pollution controlboard
Pollution controlboardPollution controlboard
Pollution controlboard
 
JAR review presentation
JAR review presentationJAR review presentation
JAR review presentation
 
Assignment On: Government of the People’s Republic of Bangladesh National Po...
Assignment On:  Government of the People’s Republic of Bangladesh National Po...Assignment On:  Government of the People’s Republic of Bangladesh National Po...
Assignment On: Government of the People’s Republic of Bangladesh National Po...
 
Detailed understanding of the master plan ar. m. senthil
Detailed understanding of the master plan  ar. m. senthilDetailed understanding of the master plan  ar. m. senthil
Detailed understanding of the master plan ar. m. senthil
 
Session 3B Finance - Getenet community development funds ethiopia (pp tminimi...
Session 3B Finance - Getenet community development funds ethiopia (pp tminimi...Session 3B Finance - Getenet community development funds ethiopia (pp tminimi...
Session 3B Finance - Getenet community development funds ethiopia (pp tminimi...
 
AMRUT MoUD
AMRUT MoUDAMRUT MoUD
AMRUT MoUD
 
Waste water management
Waste water managementWaste water management
Waste water management
 
Integrated municipal stormwater and wastewater planning approach framework
Integrated municipal stormwater and wastewater planning approach frameworkIntegrated municipal stormwater and wastewater planning approach framework
Integrated municipal stormwater and wastewater planning approach framework
 

Recently uploaded

VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...ranjana rawat
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfKamal Acharya
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 

Recently uploaded (20)

VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 

2cmc to r for sewarage system design

  • 1. 1 THE FEDERAL DEMOCRTAICE REPUBLIC OF ETHIOPIA MINISTRY OF WATER IRRIATION AND ENERGY TERMS OF REFERENCES (ToR) FOR ADAMA CITY SEWERAGE SYSTEM STUDY AND DETAIL DESIGN REPORT March 2015 ETHIOPIA
  • 2. 2 Terms of Reference (ToR) Adama City Wastewater Management System Feasibility of Study and detail design PROGRAM BACKGROUND 1. Following the completion of the National Water Supply and Sanitation program which was started in May 2004 as a five years project with USD100 million (75 million USD credit and 25 million USD grant) from IDA and (later DFID joined as co financer with 70 million Great Britain Pound in May 2007), IDA has made an agreement with Government of Ethiopia to finance new program at a scope of US $ 205 Million for five years (2014 –2019) that has three components of which Urban Water Supply and Sanitation is one of them. KEY ELEMENTS OF POLICIES 2. The project implementation arrangements reflect the policy objectives of decentralization to the lowest possible level, involvement of all stakeholders in the process, integration of sanitation with improvements to water supply, and recognizing water as an economic as well as social good. A demand responsive, performance-based approach will be followed so that communities will receive assistance to put in place institutions and develop capacity for implementation and will be able to access more resources for development of their water supply and sanitation systems as they demonstrate capacity for implementation. A stepped approach will be employed for both urban and rural water supply and sanitation to allow each community to move at is own pace and receive further assistance when they are ready. PROGRAM IMPLEMENTATION MECHANISMS 3. The One WASH National Program is the Government of Ethiopia’s (GoE) main instrument for achieving the goals set out in the Growth and Transformation Plan (GTP). Alongside the this national program, WB has simultaneously launched a WaSH II water supply and sanitation program a continuation of the WaSH I. The program has started operation since July 2014 and expected to stay three years of period. PROGRAM COMPONENTS AND IMPLEMENTATION MODALITY 4. The OWNP has mainly 4 components: 1) Rural and Pastoralist WaSH, 2) Urban WaSH, 3) Institutional WaSH and 4) Program Management and Capacity Building. The Urban WASH(for water supply and sanitation improvements) finances study and design, capacity building and management support, environmental and resettlement safeguards, immediate service improvements and expansion and augmentation of Sanitation and urban environmental improvements which will include desludging equipment and facilities, latrine sludge/septage
  • 3. 3 treatment plant and public toilets construction, and development of wastewater management systems in selected category I cities and towns. 5. Cities under this ToR consideration are ones eligible for WRDF loan to do actives and services indicated in sub component 2: sanitation services which include mainly, for im a) Development of wastewater master plan b) Tendering for sanitation services, works and goods c) Procurement of works and goods/supplies d) Carrying out building capacity activities, including technical O&M capacity e) Development of appropriate service delivery models for urban sanitation GENERAL CONSIDERATIONS 6. The Employer is responsible for preparing and implementing the project, and therefore for selecting the consultant, and awarding and subsequently administering the contract. The Bank, for its part, is required by its Articles of Agreement to “ensure that the proceeds of any loan/grants are used only for the purposes for which the loan was granted, with due attention to considerations of economy and efficiency and without regard to political or other non-economic influences or considerations,” and it has established detailed procedures for this purpose. 7. While the specific rules and procedures to be followed for employing consultants depend on the circumstances of the particular case, five main considerations guide the Bank’s policy on the selection process: (a) the need for high-quality services, (b) the need for economy and efficiency, (c) the need to give all eligible consultants an opportunity to compete in providing the services financed by the Bank, (d) the Bank’s interest in encouraging the development and use of national consultants in its developing member countries, and (e) the need for transparency in the selection process. 8. The Bank considers that, in the majority of cases, these considerations can best be addressed through competition among qualified short-listed firms in which the selection is based on the quality of the proposal and, where appropriate, on the cost of the services to be provided. 9. Water is consumed as an essential life-support substance by all living beings, including humans. The essentials of a sustainable life-support system are not only the life-generating and sustaining elements: air, water, light, heat, food, fluid and living space, but also the removal of waste products:, effluent, trash and sanitary waste, also known as sewage. Sewage is disposed of in several ways, mainly two: removal in a waterborne sewer systems (sewerage) or disposed via an on-site sanitation system (pit latrines or septic tanks). 10. The management of liquid waste at national level has been very weak. About half of the households handle household liquid waste by openly discharging into any accessible public properties, such as streets, drainage lines and nearby open space. Sewer line application is not that much familiar in the country except in Addis Ababa. 11. Disposal system has arrangements to distribute the used water either to aquatic bodies such
  • 4. 4 as oceans, rivers, lakes, ponds, or lagoons or to land by absorption systems, groundwater recharge, and irrigation. Waste water must be mixed, diluted and absorbed before it is discharged to the general body of water, so that the receiving environments do not lose its beneficial usable characteristics. 12. The Ministry of water, Irrigation and energy has tried to indicate the concern of the issues in its policy clearly. It is therefore essential to address these challenges in an integrated and regional manner, the all complex and wide range of the problem with in the frame of its National Plan UAP, MDG and GTP preparing strategic document is important with strong and indicative action of the plan with the participation of key stakeholders including the public and private sectors are actively engaged. 13. For the coming GTP II plan, 36 towns will have feasibility study and detail design for sewerage and for those which have greater than 200,000 population construction sewerage system will be started. 14. Currently, urbanization has been accelerated, fuelled by rapid economic growth in the Country, life standards have gradually improved. Urbanization and rapid economic growth have resulted in demand for better water supply and sanitation services in the Country. Because of all those reason Waste management is one of the urban basic services being addressed by the Government of Ethiopia. 15. This is a lump sum contract for consultancy services. LOCATION THE PROJECT TOWN 16. Adama city is located in Oromia National Regional State, East Shewa Zone at a distance of 100 ከm from Addis Ababa. its astronomical location is 8º44’ North Latitude and 39º04’ East Longitude. FOUNDATION 17. Adama was founded in 1924. It is one of the reform cities in the region and has city administration consisting of 14 urban and four rural kebeles. The city has structure plan which was prepared in 2004. 18. Adama City Administration is an autonomous first grade urban local government established following proclamation no.65/2003, for the establishment of local urban administrations issued by the Regional State of Oromiya. It is, therefore, responsible to administer and develop the city. For better management, the city administration is structured on a two-tier organizational hierarchy. OBJECTIVE 19. Objective of the study is to produce study and detailed design documents for Sewerage
  • 5. 5 /waste water management system in typical 4 large towns (Adama, Mekelle, Bahir Dar and Gonder) in the country. Specific objectives  Review previous and existing Study, Design and constructed sewerage systems of the each town, evaluation of its functionality, and identification of basic issues / problems.  Assess the feasibility of constructing decentralized and centralized wastewater treatment and collection infrastructure at the current major discharge points. Review alternative wastewater treatment plant(WWTP) scenarios including these decentralized WWTPs and different arrangements of collection system and possibility of combined sewerage.  Selection of suitable route and design of force main of appropriate material to carry out the sewerage due consideration of, Capable to conveyance the effluent through gravity, accessible through existing infrastructure of roads / trails/tacks, least interference with the social setup of the area, minimum social and environmental impacts, the minimum damages to local Dug wells and other water resource, and Socially acceptable.  Recommend the most appropriate and cost effective wastewater investment scenario. The approach should be an optimal one for managing the Town’s wastewater treatment requirements, reflecting locations and land requirements, treatment technologies, the operations and maintenance characteristics of each technology studied, capital and recurrent costs, sustainability, affordability, and other related factors  Assess on-site sanitation facilities, septage collection and condition of septic tanks, fecal sludge management strategies and effluent disposal fields.  Preparation of detail design and engineering drawings for the up gradation of the waste water management system based on the preferred alternative.  Prepare a complete tender document for construction. SCOPE OF SERVICES 20. The scope of consultancy services is divided in the following Tasks under Part I & II: Task I: The details of the task will be not limited to o Submission of inception report. The inception shall clearly indicate initial desk review, field observations, existing situation, revised methodologies and approach to the consulting services, revised schedule for activities, expert program, next deliverable schedule and contacted individuals and references used. The inception report shall be discussed and approved by the Client. o Detail review report (1) the existing study and design reports including the sewerage system functioning in the city. It shall include the assessement of on-site and off-site complete sanitation chain facilities in the town to identify waste water management
  • 6. 6 characteristics. o Detail report (2) on the design approach to Wastewater demand of the city, Where does the wastewater come from?, Components of a Community’s Wastewater: a)domestic (sanitary)- residential, institutional and commercial b) industrial), c)Infiltration to Sanitary Sewer Systems d) Inflow to Sanitary Sewer Systems, also identify quality of untreated wastewater for each categories; asses existing rivers crossing the city and deep wells sources for level of contamination; propose the computer software to be used; o Prepare design criteria and concept plan for component of the town waste water management project. Include also choice of technology and material to use. Concept plan will be to provide a sound planning basis and finalize the criteria for detailed engineering design under each subproject. Two or three scenarios to be delivered for the client final choice. It shall indicate the economic analysis and sensitivity test for each scenario (with centralized and decentralized treatment, separate or combined sewerage systems). The size of the topography survey required and alternate choices shall be presented. o Appraisal workshop presentation before stepping to stage II.) (The panel shall have specialists from MoWIE, MoH, Regional Bureau (Water and Health), Environmental protection Office. o Assess the technical, financial, social, and economic feasibility and sustainability and priority of each subproject component, including the phasing of investments for wastewater management including (a) sewage collection and treatment systems, (b) septic tank sludge collection and treatment systems, and (c) other related investments. o Assess in detail the operating utility’s: (a) financial management capacity; and (b) financial state including income statements, balance sheet and cash flow statements, and existing loan repayments. Analyze major constraints to the financial sustainability and the degree of operational subsidies from the local government. Prepare financial projections including revenues, operating and capital expenditures, and debt repayment. o Assess the costs of wastewater collection and treatment and level of cost recovery possible, and determine tariffs needed to ensure sustainable operations. Discuss with the city utility/Municipality a phased politically acceptable way of introducing cost recovery tariffs. Assess options and the feasibility of transferring responsibility for wastewater services to a dedicated wastewater utility. o Review the impact and affordability of introducing full and partial cost recovery in wastewater management services. Assess demand on the basis of price, income, and access to alternative supplies. Analyze the affordability of wastewater services and assess willingness to pay for them. o Assess in detail (a) financial management capacity, and (b) financial performance including borrowing capacity and debt service coverage ratios relating to existing and potential new loans. Prepare financial projections including revenues, operating and
  • 7. 7 capital expenditures, and debt repayment. o Investigate alternative financing schemes for improving urban sanitation, including for example municipal bonds, and public-private partnerships. o Prepare detailed cost estimates and financing plans for each of the project components and the Project as a whole. Prepare the financial arrangements specifying the foreign exchange and local currency csts as applicable. o Conduct comprehensive economic and financial analyses for each subproject and the overall Project, using relevant WB guidelines, and handbooks. Based on past and projected financial statements, compute relevant financial indicators, including, but not limited to, debt service coverage ratios, and operating ratios. Compute for each subproject and the overall project financial internal rates of return (FIRRs), weighted average cost of capital (WACC), and economic internal rates of return (EIRRs). Analyse the impact of the Project on poverty reduction. Review in detail the distribution of project benefits, net economic benefits, and poverty impact. o Prepare detailed project implementation and phasing schedules for each component, and investigate implementation options including integrated design-procure construct packages to improve implementation efficiency. o Prepare an effective project performance monitoring system (PPMS) that includes monitoring of the project's performance, benefits, and impact on poverty reduction. Identify the training needs to strengthen performance monitoring capacity. o Hold discussions with the city stakeholders to identify key issues and obtain their views on capacity-building needs, and develop concepts for the design of the capacity-building components. Develop a capacity-building program, and outline training programs and recommended interventions that should be included in the Project, and estimated costs. o Recommend subproject interventions to address gender imbalances, and interventions to support other vulnerable groups, which will result in poverty reduction and social inclusion strategy under the project. o Develop and recommend mechanisms and procedures for public consultation and community participation in project planning, operation and maintenance, project implementation and management, particularly in relation to levels of service performance, tariffs, and environmental protection. o Assess the need for land acquisition in the Project. Where land acquisition is required, the Consultant shall inform the Utility of the location, outline the likely resettlement requirements and the work required to prepare an action plan to acquire the land (including the preparation of cadastral plans) and resettle residents in accordance with procedures regulated by the Federal and Regional ESFW Regulation covering the matter. o Assess the need for preparing an indigenous peoples development framework, development plan, or specific action in accordance with WBs policy on indigenous peoples. If required, prepare the necessary framework, plan, and specific action in accordance with WBs requirements. (xvi) Justify the Project from the point of view of
  • 8. 8 social dimensions (social impact, impact on poverty, marginalized and vulnerable groups, and gender specific issues). o Each intervention shall be screened for its environmental impact. For each intervention, the initial objective shall be to determine if there will be a significant impact from the proposed investment, based on criteria established under ESFW. o The Consultant will concurrently prepare an initial environmental examination (IEE) or environmental impact assessment (EIA), if warranted, for each individual subproject, and a summary IEE or a summary EIA for the whole Project, Task II: The details of the task work will be not limited to o Detailed topographic surveys and drawings of plan & profile in A3 and Ao (general layout) paper size. The topography coordinates shall be addendum UTM measurements. The whole proposed route shall be surveyed. The soil investigation along selected topographic survey routes and selected treatment sites; o Zonal( where applicable) hydrological data analysis, Wastewater characterization, and volume quantification based the sub catchment of the city drainage flow; o detailed designing of sewerage Network, the route confirm to the master plan layout recommendation and local development plan of the city; The specification shall confirm to the latest material production standard, equipment output and method of for all system components readable with bill of quantity pay items. The presentation shall follow standard numbering method quantity surveying. o Preparation of bid document based on the WB procurement requirements for works and goods & related works; The Bill of quantities shall be detailed and specific to each item of material uit od activity required and no lumped activities are allowed to be submitted. Engineering Estimates derived from cost rate analysis prepared on Excel spreadsheet correlated with outputs (manpower and equipment) and material. Production 3-D view of all treatment structures in appropriate CAD format. The ArcGIS report whether soft or hard copy shall have complete presentation of the design pipe routes, stations, major junction boxes, proposed treatment plants separated by implementation phases; o Appraisal workshop presentation before stepping to preparation of quantities. o The Regional Bureau shall seek No Objection for the final document. STUDY AND DESIGN TEAM STAFF 21. The Consulting firm shall be legally established firm and committed to put together a team of highly qualified experts with direct experience and excellent understanding of technical, economic, financial and environmental issues related to water supply and sewerage services of major cities in the country. 22. The team will also need to have experience in conducting Feasibility Studies under the conditions and regulations which exist in Major similar cities.
  • 9. 9 23. Resumes of the qualifications and experience of the key members of the team will be the key criteria used to evaluate proposals. Table 1: Activity Staff qualification requirement S/No. Position No of person Qualification/Experience Person Month 1 Team Leader 1 Wastewater/Sanitary Engineer/Civil :MSc or above in Sanitary Engineering or related with 12 years or above experience in the sanitation sub-sector with a high credit to experiences in project manager for study and designing of similar nature project 12 2 Wastewater/ sanitary specialist 2 MSc or above in wastewater/ sanitary/ or related fields with 8 years or above experience in the Sanitation sub-sector with a high credit to experiences of development of sanitary systems of similar nature project . 12 3 Hydraulic Engineer 1 MSc or above in /civil Engineering or related with 8 years or above experience in the water supply and sanitation sub-sector with a high credit to experiences in study and designing of of similar nature project 12 4 Structural Engineer 1 MSc or above in civil Engineering or related with 8 years or above experience in the water supply and sanitation sub-sector with a high credit to experiences in study and designing of of similar nature project 4 5 Socio-Economist 1 BSc or above in economics with 8 yrs of experience in similar nature projects 4 5 Mechanical Engineer /Electrical Engineer 1 MSc or above in mechanical Engineering or related with 8 years or above experience in the wastewater with a high credit to experiences in study and designing of similar nature project 4 7 Environmental specialist 1 MSc or above in Environmental Engineering or related with 8 years or above experience in the water supply and sanitation sub-sector with a high credit to experiences in study and designing of different projects 4 8 Topographic Surveyor 2 Minimum Technical diploma in surveying and 8 yrs relevant experience 4 9 Quantity Surveyor 2 Diploma+10yrs relevant experience 5 10 Procurement Specialist 1 BSc or above in civil Engineering or related with 8 years or above experience in the water supply and sanitation sub-sector with a high credit to experiences in study and designing of different projects 2 11 AutoCAD Draftsman 2 Diploma+10yrs relevant experience 12
  • 10. 10 CONSULTANT’S SERVICE ADMINISTRATION 24. The consultant firm is accountable to the Regional Water Supply and Sanitation Bureau at the Regional Level. The sewerage system design and development Focal Person at MoWIE in the Directorate will facilitate the execution of the assignment as project coordinator. CLIENT’S INPUT FOR THE SERVICE 25. The client will:  Avail to the consultant with all necessary data and document available.  Facilitate to the consultant to have access to data and documents available in the WaSH government sectors.  Facilitate and organize stakeholders appraise the documents at each step. ACTIVITY DELIVERABLES Nr. Deliverables Submission Timing Day Pages copies Duration Late finish 1 Contract effectiveness 1 2 Inception Report 30 30 30 +Appendices 5 + CD 3 Part I draft report 90 120 Three reports( each max 100 pages + appendices) 5 + CD 4 Appraisal and part I Final report 20 140 5 + CD 5 Part II draft report 160 300 Four reports ( each max 100 pages + appendices) 5 + CD 6 Appraisal and Part I Final report 20 320 Four reports( each max 100 pages + appendices) 5 + CD 7 Bid Document including Dwgs 20 340 Specification, and BoQ,, Bid document, Dwgs 5 + CD 8 No Objection 25 365 26. The Consulting firm shall recommend order of the activity deliverables in order of presentation and respective timeline.
  • 11. 11 PAYMENT SCHEDULE 1) Signature of the contract. Down payment of 20% of the total budget 2) Delivery of the first interim report. Payment of 10% of the total budget. 3) Delivery of the second interim report (Task I). Payment of 10% of the total budget. 4) Delivery of the third interim report (Task II draft). Payment of 20% of the total budget. 5) Delivery and acceptance of the Final Payment (final report and bid document} of 40% of the total budget following same procedure defined for former milestones.