PROGRESS REPORT FOR RB PROJECT TILL 02/06/15
1. EQUALUZATION TANK:
The project started with septic tank cleaning. It is 60 m3
tank in which industrial waste/ effluent of entire plant
would accumulate. The tank has rectangular base area of
40 ft2 approximately. Submersible pumps were used to
remove water and subsequently, sweepers put out all
the sludge manually and disposed it into drain. All safety
measures were adopted during the entire cleaning
process. Compressed air line was provided so as to avoid
short of breath problem. The man holes were kept open throughout in order to avoid
accumulation of toxic gases inside the tank. Once the cleaning process was completed, floor
was leveled using concrete. It was strengthened using SBR binder. The floor was allowed to
cure and dry.
Then concrete blocks for the aeration header were plastered to the surface. They were installed
in such a way that the aeration header lies along the centre of the tank. As there are three
portions in the tank, core cutting was done to allow passage of header from one compartment
to another. The header (3’’) was then installed, 100 mm from the underground level, supported
by blocks. They were further clamped with u bolts and were then coated with concrete. All
remaining pebbles were removed from the tank after installation.
Diffusers serve the medium for the aeration. They are
coarse bubble diffusers, which provide efficient mixing
followed by growth of micro-organisms, which are actually
responsible to carry out the process, i.e. decreasing COD &
BOD. Diffusers are attached to the aeration header. Silicone
is used to provide water proofing.
PROGRESS REPORT FOR RB PROJECT TILL 02/06/15
Two submersible pumps are also placed, that will
transfer the water to the bio reactor, delivering pressure
of about 1.5 bar. 2’’ line is connected to the pump
outlet, evolving from a cut out provided for this purpose.
These lines connect to a header from which a common
emerges, connecting the septic tank and the reactor.
Double union ball valves are provided followed by NRV
to prevent back flow. Line (1/2’’) for pressure gauge is
also provided. A frame is fabricated for the cut out,
coated with red oxide to prevent corrosion. Checkered
plates have been fabricated. Ropes are provided to
facilitate easy removal of pumps when required. A drain
line is provided to with draw water outside the factory.
This is provided for safety measures, i.e. avoiding entry
of dead organisms into the reactor. Supports are
fabricated as required.
PROGRESS REPORT FOR RB PROJECT TILL 02/06/15
2. SUPPORTS FABRICATION AND INSTALLTION:
Three types of E supports were designed and fabricated
for the piping spool and cable trays. They were coated
with red oxide and painted royal blue color. The spool
and cable trays were then run on the supports.
3. CONSTRUCTION OF PIT:
It started with excavation of pit having approx.
dimensions of 5*5*5 ft. during excavation seepage water
starts accumulating. Therefore, padlo was used to cater this problem. After then pit was given
physical structure using wooden planks. Iron reinforced concrete was used for its construction.
It was then left for some days to cure and dry. The floor was later on plastered.
PROGRESS REPORT FOR RB PROJECT TILL 02/06/15
An enclosure of material SS 316, was fabricated
for the bar screen. Bar screen having dimensions
of about 1600*900 mm, will be placed at an
angle of 45ᴼ. This bar screen is responsible to
retain all the solid material present in the
effluent. Rawl bolts and concrete support the
enclosure. Later on ceiling for the pit is laid using
reinforced concrete.
PROGRESS REPORT FOR RB PROJECT TILL 02/06/15
A cavity is provided for manhole frame and
checkered plate. Finally bitumen diluted in
turpentine oil is coated on the outside wall to
prevent entry of seepage water into the pit.
4. BLOWER INSTALLATION:
Blower is palced on the foundation pad. The line (3’’) originating from the septic tank is
connected with the 1.5’’ line, attached to the blower, through a reducing bush.

Contenu connexe

Tendances (20)

Sewer joint
Sewer jointSewer joint
Sewer joint
 
Pipe materials and types of joints [autosaved]
Pipe materials and types of joints [autosaved]Pipe materials and types of joints [autosaved]
Pipe materials and types of joints [autosaved]
 
Selection of Pumps and Pipe drainage
Selection of Pumps and Pipe drainageSelection of Pumps and Pipe drainage
Selection of Pumps and Pipe drainage
 
precast manholes
precast manholesprecast manholes
precast manholes
 
Plumbing presentation by Jose Anacleto Soberano
Plumbing presentation by Jose Anacleto SoberanoPlumbing presentation by Jose Anacleto Soberano
Plumbing presentation by Jose Anacleto Soberano
 
Pipes in sanitation
Pipes in sanitationPipes in sanitation
Pipes in sanitation
 
Pillar and Bib taps
Pillar and Bib tapsPillar and Bib taps
Pillar and Bib taps
 
Plumbing fittings & fixtures
Plumbing fittings & fixturesPlumbing fittings & fixtures
Plumbing fittings & fixtures
 
Sewer pipes-and-fittings
Sewer pipes-and-fittingsSewer pipes-and-fittings
Sewer pipes-and-fittings
 
Various types of pressure pipes
Various types of pressure pipes Various types of pressure pipes
Various types of pressure pipes
 
Waterproofing
WaterproofingWaterproofing
Waterproofing
 
Silambarasan
SilambarasanSilambarasan
Silambarasan
 
WaterProofing Coatings
WaterProofing CoatingsWaterProofing Coatings
WaterProofing Coatings
 
Different Types of Water Pipes And Their Uses
Different Types of Water Pipes And Their UsesDifferent Types of Water Pipes And Their Uses
Different Types of Water Pipes And Their Uses
 
Plumbing presentation
Plumbing presentationPlumbing presentation
Plumbing presentation
 
Plumbing work in construction
Plumbing work in constructionPlumbing work in construction
Plumbing work in construction
 
Pool Circulation pdf document Aqua Middle East FZC
Pool Circulation pdf document Aqua Middle East FZCPool Circulation pdf document Aqua Middle East FZC
Pool Circulation pdf document Aqua Middle East FZC
 
Training presentation [cmci]
Training presentation [cmci]Training presentation [cmci]
Training presentation [cmci]
 
waterproofing
waterproofingwaterproofing
waterproofing
 
types of pipes
types of pipestypes of pipes
types of pipes
 

Similaire à DPR TILL 02-06-15

International Journal of Computational Engineering Research(IJCER)
International Journal of Computational Engineering Research(IJCER)International Journal of Computational Engineering Research(IJCER)
International Journal of Computational Engineering Research(IJCER)ijceronline
 
Traps and manhole aditya kumar barn1 ar14002
Traps and manhole aditya kumar barn1 ar14002Traps and manhole aditya kumar barn1 ar14002
Traps and manhole aditya kumar barn1 ar14002Aditya kumar
 
PROJECT ON Construction of a multistory building POWER POINT PRESENTATION
PROJECT ON Construction of a multistory building POWER POINT PRESENTATIONPROJECT ON Construction of a multistory building POWER POINT PRESENTATION
PROJECT ON Construction of a multistory building POWER POINT PRESENTATIONROHITASH ROJ
 
L14 - ONSITE SANITATION.pptx
L14 - ONSITE SANITATION.pptxL14 - ONSITE SANITATION.pptx
L14 - ONSITE SANITATION.pptxPRACHI DESSAI
 
Management & mitigation of groundwater infiltration within underground excava...
Management & mitigation of groundwater infiltration within underground excava...Management & mitigation of groundwater infiltration within underground excava...
Management & mitigation of groundwater infiltration within underground excava...Angelo Indelicato
 
WATER LEAKEGE REMEDIES AND PRECAUTIONS IN RCC STRUCTURE
WATER LEAKEGE REMEDIES AND PRECAUTIONS IN RCC STRUCTUREWATER LEAKEGE REMEDIES AND PRECAUTIONS IN RCC STRUCTURE
WATER LEAKEGE REMEDIES AND PRECAUTIONS IN RCC STRUCTUREchintandomadiya
 
Cut and cover_sections
Cut and cover_sectionsCut and cover_sections
Cut and cover_sectionsjuwes
 
REPAIR OF THE SPILLWAY AT PANDOH DAM
REPAIR OF THE  SPILLWAY AT PANDOH DAM REPAIR OF THE  SPILLWAY AT PANDOH DAM
REPAIR OF THE SPILLWAY AT PANDOH DAM Hemant Thakur
 
Contruction and services
Contruction and servicesContruction and services
Contruction and servicesCharu Garg
 
Interior services unit 2
Interior services unit 2Interior services unit 2
Interior services unit 2ctlachu
 
IRJET- Roughness Coefficient of Alkali Activated Mineral based Concrete C...
IRJET-  	  Roughness Coefficient of Alkali Activated Mineral based Concrete C...IRJET-  	  Roughness Coefficient of Alkali Activated Mineral based Concrete C...
IRJET- Roughness Coefficient of Alkali Activated Mineral based Concrete C...IRJET Journal
 
Sustainable Storm-water Management Report
Sustainable Storm-water Management ReportSustainable Storm-water Management Report
Sustainable Storm-water Management ReportArissa Loh
 
Well_Completions.pdf
Well_Completions.pdfWell_Completions.pdf
Well_Completions.pdfAihamAltayeh1
 
7145044 rain-water-harvesting
7145044 rain-water-harvesting7145044 rain-water-harvesting
7145044 rain-water-harvestingGerrie Rousseau
 
STUDY ON WATER TANK REPAIRS AND BIO-TOILET MODIFICATION
STUDY ON WATER TANK REPAIRS AND BIO-TOILET MODIFICATIONSTUDY ON WATER TANK REPAIRS AND BIO-TOILET MODIFICATION
STUDY ON WATER TANK REPAIRS AND BIO-TOILET MODIFICATIONSujith Sonu
 
Rainwater harvesting
Rainwater harvesting Rainwater harvesting
Rainwater harvesting vidooshak
 

Similaire à DPR TILL 02-06-15 (20)

International Journal of Computational Engineering Research(IJCER)
International Journal of Computational Engineering Research(IJCER)International Journal of Computational Engineering Research(IJCER)
International Journal of Computational Engineering Research(IJCER)
 
Traps and manhole aditya kumar barn1 ar14002
Traps and manhole aditya kumar barn1 ar14002Traps and manhole aditya kumar barn1 ar14002
Traps and manhole aditya kumar barn1 ar14002
 
PROJECT ON Construction of a multistory building POWER POINT PRESENTATION
PROJECT ON Construction of a multistory building POWER POINT PRESENTATIONPROJECT ON Construction of a multistory building POWER POINT PRESENTATION
PROJECT ON Construction of a multistory building POWER POINT PRESENTATION
 
L14 - ONSITE SANITATION.pptx
L14 - ONSITE SANITATION.pptxL14 - ONSITE SANITATION.pptx
L14 - ONSITE SANITATION.pptx
 
Management & mitigation of groundwater infiltration within underground excava...
Management & mitigation of groundwater infiltration within underground excava...Management & mitigation of groundwater infiltration within underground excava...
Management & mitigation of groundwater infiltration within underground excava...
 
WATER LEAKEGE REMEDIES AND PRECAUTIONS IN RCC STRUCTURE
WATER LEAKEGE REMEDIES AND PRECAUTIONS IN RCC STRUCTUREWATER LEAKEGE REMEDIES AND PRECAUTIONS IN RCC STRUCTURE
WATER LEAKEGE REMEDIES AND PRECAUTIONS IN RCC STRUCTURE
 
Cut and cover_sections
Cut and cover_sectionsCut and cover_sections
Cut and cover_sections
 
REPAIR OF THE SPILLWAY AT PANDOH DAM
REPAIR OF THE  SPILLWAY AT PANDOH DAM REPAIR OF THE  SPILLWAY AT PANDOH DAM
REPAIR OF THE SPILLWAY AT PANDOH DAM
 
Contruction and services
Contruction and servicesContruction and services
Contruction and services
 
Interior services unit 2
Interior services unit 2Interior services unit 2
Interior services unit 2
 
vacation work report 2
vacation work report 2vacation work report 2
vacation work report 2
 
IRJET- Roughness Coefficient of Alkali Activated Mineral based Concrete C...
IRJET-  	  Roughness Coefficient of Alkali Activated Mineral based Concrete C...IRJET-  	  Roughness Coefficient of Alkali Activated Mineral based Concrete C...
IRJET- Roughness Coefficient of Alkali Activated Mineral based Concrete C...
 
Sustainable Storm-water Management Report
Sustainable Storm-water Management ReportSustainable Storm-water Management Report
Sustainable Storm-water Management Report
 
Well_Completions.pdf
Well_Completions.pdfWell_Completions.pdf
Well_Completions.pdf
 
7145044 rain-water-harvesting
7145044 rain-water-harvesting7145044 rain-water-harvesting
7145044 rain-water-harvesting
 
Sewer Appurtances
Sewer AppurtancesSewer Appurtances
Sewer Appurtances
 
05_WP-3M_1011_LR
05_WP-3M_1011_LR05_WP-3M_1011_LR
05_WP-3M_1011_LR
 
STUDY ON WATER TANK REPAIRS AND BIO-TOILET MODIFICATION
STUDY ON WATER TANK REPAIRS AND BIO-TOILET MODIFICATIONSTUDY ON WATER TANK REPAIRS AND BIO-TOILET MODIFICATION
STUDY ON WATER TANK REPAIRS AND BIO-TOILET MODIFICATION
 
Rainwater harvesting
Rainwater harvesting Rainwater harvesting
Rainwater harvesting
 
Tema basics of construction 07.10
Tema basics of construction   07.10Tema basics of construction   07.10
Tema basics of construction 07.10
 

DPR TILL 02-06-15

  • 1. PROGRESS REPORT FOR RB PROJECT TILL 02/06/15 1. EQUALUZATION TANK: The project started with septic tank cleaning. It is 60 m3 tank in which industrial waste/ effluent of entire plant would accumulate. The tank has rectangular base area of 40 ft2 approximately. Submersible pumps were used to remove water and subsequently, sweepers put out all the sludge manually and disposed it into drain. All safety measures were adopted during the entire cleaning process. Compressed air line was provided so as to avoid short of breath problem. The man holes were kept open throughout in order to avoid accumulation of toxic gases inside the tank. Once the cleaning process was completed, floor was leveled using concrete. It was strengthened using SBR binder. The floor was allowed to cure and dry. Then concrete blocks for the aeration header were plastered to the surface. They were installed in such a way that the aeration header lies along the centre of the tank. As there are three portions in the tank, core cutting was done to allow passage of header from one compartment to another. The header (3’’) was then installed, 100 mm from the underground level, supported by blocks. They were further clamped with u bolts and were then coated with concrete. All remaining pebbles were removed from the tank after installation. Diffusers serve the medium for the aeration. They are coarse bubble diffusers, which provide efficient mixing followed by growth of micro-organisms, which are actually responsible to carry out the process, i.e. decreasing COD & BOD. Diffusers are attached to the aeration header. Silicone is used to provide water proofing.
  • 2. PROGRESS REPORT FOR RB PROJECT TILL 02/06/15 Two submersible pumps are also placed, that will transfer the water to the bio reactor, delivering pressure of about 1.5 bar. 2’’ line is connected to the pump outlet, evolving from a cut out provided for this purpose. These lines connect to a header from which a common emerges, connecting the septic tank and the reactor. Double union ball valves are provided followed by NRV to prevent back flow. Line (1/2’’) for pressure gauge is also provided. A frame is fabricated for the cut out, coated with red oxide to prevent corrosion. Checkered plates have been fabricated. Ropes are provided to facilitate easy removal of pumps when required. A drain line is provided to with draw water outside the factory. This is provided for safety measures, i.e. avoiding entry of dead organisms into the reactor. Supports are fabricated as required.
  • 3. PROGRESS REPORT FOR RB PROJECT TILL 02/06/15 2. SUPPORTS FABRICATION AND INSTALLTION: Three types of E supports were designed and fabricated for the piping spool and cable trays. They were coated with red oxide and painted royal blue color. The spool and cable trays were then run on the supports. 3. CONSTRUCTION OF PIT: It started with excavation of pit having approx. dimensions of 5*5*5 ft. during excavation seepage water starts accumulating. Therefore, padlo was used to cater this problem. After then pit was given physical structure using wooden planks. Iron reinforced concrete was used for its construction. It was then left for some days to cure and dry. The floor was later on plastered.
  • 4. PROGRESS REPORT FOR RB PROJECT TILL 02/06/15 An enclosure of material SS 316, was fabricated for the bar screen. Bar screen having dimensions of about 1600*900 mm, will be placed at an angle of 45ᴼ. This bar screen is responsible to retain all the solid material present in the effluent. Rawl bolts and concrete support the enclosure. Later on ceiling for the pit is laid using reinforced concrete.
  • 5. PROGRESS REPORT FOR RB PROJECT TILL 02/06/15 A cavity is provided for manhole frame and checkered plate. Finally bitumen diluted in turpentine oil is coated on the outside wall to prevent entry of seepage water into the pit. 4. BLOWER INSTALLATION: Blower is palced on the foundation pad. The line (3’’) originating from the septic tank is connected with the 1.5’’ line, attached to the blower, through a reducing bush.