Capital Planning and
Investment Management
and Control in Information
Technology


Alan McSweeney
Objectives

•   To provide information on a structured approach to
    Capital Planning and Investment Control in Information
    Technology




    February 3, 2010                                         2
Agenda

•   Capital Planning and Investment Control in Information
    Technology (CPIC-IT)
•   IT Investment Management (ITIM)
•   Cost Estimation
•   Cost Assessment Team
•   IT Investment Management Maturity




    February 3, 2010                                         3
Capital Planning and Investment Control (CPIC-IT)

•   CPIC-IT is a systematic process logical IT investments in new systems
    and maintaining and operating existing systems
•   CPIC-IT is a process for effective decision-making that ensures IT
    investments integrate strategic planning, budgeting, procurement,
    and the management of IT in support of organisation needs
      − Determines if a given investment in IT is justified
      − Ensures IT investment decisions support the needs of the organisation,
        minmise risks and maximise returns throughout the investment lifecycle
•   CPIC-IT is a structured process for managing the risks and returns
    associated with IT investments
•   CPIC-IT is designed to ensure that IT investments are implemented at
    acceptable costs, within reasonable and expected timeframes, and
    contribute to tangible, observable improvements in organisation
    performance

    February 3, 2010                                                             4
IT Investment Issues

•   IT is a key enabler of organisational strategy
•   Many organisations do not know exactly how much is spent on IT
•   Many organisations cannot accurately characterise IT assets
•   In many organisations, IT accounts for 50% or more of capital
    expenditure
•   IT architecture is perceived as not providing the adaptability that is
    needed
•   IT is seen as a friction point for change and not enough of an enabler
•   Organisations must implement processes for managing IT
    investment both for the value they deliver as well as their cost
•   There has been significant waste of IT investments and unused IT
    systems due to lack of investment validation
      − Over 80% of projects do not come close to their original goals of lifecycle costs
      − More expensive to implement and/or operate than initially stated

    February 3, 2010                                                                        5
Questions on IT Investments

•   Is your organisation’s IT portfolio a manifestation of your
    organisation’s mission and strategy?
•   Can you identify which IT projects are interdependent with adjacent
    people and process initiatives?
•   Do you have a rigorous IT investment selection process that is
    devoid of emotion and politics?
•   Do you account for multiple risk categories - technical, business,
    project, customer - when evaluating investment proposals?
•   Is IT operating expense in line with organisation growth?
•   Can you identify which IT investments contribute to true competitive
    advantage or mission achievement?
•   Do IT investment decision making methods mesh with the decision
    making framework of organisation?

    February 3, 2010                                                       6
What the Business Wants From IT

•   Business Requirement                       •   Corresponding IT Function
                                                            Maintain the
                       Deliver IT services                  momentum of the
                       consistently without                 business through
                       fuss                                 existing business
                                                            systems


                       Get involved in                      Contribute to
                       business                             improving business
                       improvement                          results


                       Provide the business                 Provide IT direction
                       with appropriate                     and management
                       information and                      that is aligned to the
                       technology leadership                needs of the business
    February 3, 2010                                                                 7
Disconnect Between What the Business Wants and
What IT Delivers

              What the Business Wants                              What the Business Gets

                              15%                                               5%

                    35%                                                25%



                                                                                           70%
                               50%

Maintain The Momentum Of The Business Through            Maintain The Momentum Of The Business Through
Existing Business Systems                                Existing Business Systems
Contribute To Improving Business Results                 Contribute To Improving Business Results

Provide It Direction And Management That Is Aligned To   Provide It Direction And Management That Is Aligned To
The Needs Of The Business                                The Needs Of The Business




 February 3, 2010                                                                                                 8
IT Value Management is a Key Topic for IT
                  Do Not Measure Business Value From IT
                                                                                         40%
                              Investments

         Metrics Do Not Adequately Capture Business
                                                                                             45%
                           Value


                        Executives Skeptical Of ROI From IT                                        52%



                           Find It Difficult To Calculate ROI                                             62%


                       CEO/CFO Demanding Better Ways To
                                                                                                                71%
                              Demonstrate Value

                                                                0%   10%   20%   30%   40%   50%    60%    70%   80%   90% 100%

•   Results of managing IT for business value
      − Budget flexibility coupled with strategic IT alignment leads to 50% greater IT
        payoffs
      − Improving management practices alongside IT investment drives 20% higher IT
        yields
    February 3, 2010                                                                                                              9
Core Elements of IT Value Management

                       Managing IT Like a      Managing
                          Business                 the
                                               IT Budget




                       Managing the IT      Managing IT for
                         Capability         Business Value



•   An effective approach to Capital Planning and Investment
    Control is an essential component of IT Value
    Management
    February 3, 2010                                           10
IT Investment Core Requirements

•   Determine the scale, scope, and sources of funding for IT
•   Assign financial resources to competing activities within
    the IT portfolio
•   Establish a balance between capital expenditure (new
    projects) and operating expenditure (running systems
    delivered by past projects)
•   Optimise the total cost of ownership
•   Manage IT portfolios for value and not just cost
•   IT needs to implement a process for justifying its costs and
    be seen to be taking these steps
    February 3, 2010                                               11
W5H

• Who - Who makes the decisions?

• Why - Why is the funding sought, how is it aligned to the
 needs of the business and what benefits are anticipated?
• What - Precisely what IT initiatives and business initiatives
 are to be funded?
• When - When is the funding required and when are
 benefits expected to flow?
• Where - From which source is the funding to be derived?

• How - How are funding decisions to be made?

 February 3, 2010                                                 12
IT Investment Management

•   Aligns IT Investments to organisation strategy (scoring)
•   Prioritises investments (ranking)
•   Provides strategic criteria for investment analysis
•   Conduct annual IT portfolio management reviews
•   Provides recommendation to stop, slow, maintain or
    accelerate program funding
•   Identifies redundant/inefficient systems
•   Integrates IT architectures within investments
•   Ensures compliance with funding standards
    February 3, 2010                                           13
Characteristics of Credible Cost Estimates

•   Clear identification of requirements of the ultimate deliverable
•   Broad participation in preparing estimates
•   Availability of valid data for performing estimates – historical,
    experience, benchmarks
•   Standardised and comprehensive estimate structure that includes all
    possible sources of cost
•   Provision for uncertainties – include known costs explicitly and allow
    for unknown costs
•   Recognition of inflation
•   Recognition of excluded costs
•   Independent review of estimates for completeness and realism
•   Revision of estimates for significant changes in requirements

    February 3, 2010                                                         14
Challenges of Developing Good Cost Estimates

•   Requires detailed, stable, agreed requirements
•   Agreed assumptions
•   Access to detailed documentation and historical data for
    comparison
•   Trained and experienced analysts
•   Risk and uncertainty analysis
•   Identification of a range of confidence levels
•   Adequate contingency and management reserves


    February 3, 2010                                           15
Reasons for Good and Bad Cost Estimates
                                                                                                              Ineffe
                                                                                                             and U ctive Risk
                                    Effect                                                                         ncer
                                           i ve
                                      Unce Risk and                                   Unfa                      Analy tainty
                                              r ta                                 Techn miliar                       s is
         Ident
               ificat                   Analy inty                                First- ology or
                                                 s is
              Rang ion of a                                                             Time
                                                                                             Use
                                                                                                         Probl
                                                                                                               em
        Confi      e of               De                                                                  Acces s Getting
              dence
                      Level     Docu tailed                                                                     s to D
                                       m                                                                              ata           Unre
                            s    and H entation                                Unre
                                                                                                                                  Proje asonable
           Adeq
                 ua                     istor             Train               Unre alistic or                                          ct Bas
       Conti
             ngen te                  Data ical                 e
                                                         Exper d and
                                                                                  liable
                                                                                         Data            Unre                                 elin e
        Mana      cy an                                        ien
              geme d          Detai
                                    led, S                Analy ced                                     Assumalistic
         Reser      nt                                           sts        No o                             ption
                ves               Agree table,                            Comp r Limited                           s            Overo
                              Requ       d                                     ariso                                                 ptimi
                                   ireme                 Agr                 Avail n Data                                                     sm
                                           n ts
                                                      Assum eed                   able              New
                                                            ption                                       Pr   ocess
                                                                   s                                              e   s        Untra
                                                                       Proje                                                  Inexp ined and
                                                                             ct Ins                                                er ie
                                                                                   t   abilit
                                                                                              y   Comp                          Analy nced
                                                                                                       le                              sts
                                                                                                  or Te x Project
                                                                                                       chnol              Unre
                                                                                                             ogy               alistic
                                                                                                                              Savin Project
                                                                                                                                     gs




•   Lost of reasons for and causes of inaccurate cost estimates

    February 3, 2010                                                                                                                                   16
Sources of Risk and Uncertainty in Estimating Costs

•   Lack of understanding of the project requirements
•   Shortcomings of human language and differing
    interpretations of meaning of project
•   Behaviour of parties involved in the cost estimation
    process
•   Haste
•   Deception
•   Poor cost estimating and pricing practices



    February 3, 2010                                       17
Specific Risks

•   Sizing and Technology                       •   Capability
      − Overly optimistic developers                 − Mixed skills of team
      − Poor assumptions on the use of reused        − Optimistic assumption on
        code                                           development tools
      − Vague or incomplete requirements             − Optimistic assumption on productivity
      − Not planning for additional effort           − Geographically dispersed team making
        associated with packages –                     communication and coordination more
        integration, testing                           difficult
•   Complexity                                  •   Management
      − Tools                                        − Management’s dictating an unrealistic
      − Applications: software purpose and             schedule
        reliability                                  − Incorporating a new method,
      − Hardware limitations                           language, tool or process for the first
      − Number of modules affecting                    time
        integration effort                           − Not handling creeping requirements
                                                       and change proactively
                                                     − Inadequate quality control, causing
                                                       delays in fixing unexpected defects
                                                     − Unanticipated risks associated with
                                                       package software upgrades and lack of
                                                       support

    February 3, 2010                                                                             18
Importance of System Requirements and Solution
Lifecycle Costs
•   System requirements drive costs, both implementation and operation
•   A factor present in every successful project and absent in every unsuccessful project is sufficient
    attention to requirements
•   Half of all bugs can be traced to requirement errors
•   Fixing these errors consumes 75% of project rework costs
•   25%- 40% percent of all spending on projects is wasted as a result of re-work
•   66% of software projects do not finish on time or on budget
•   56% of project defects originate in the requirements phase of the project
•   Completed projects have only 52% of proposed functionality
•   75-80% of IT project failures are the result of requirements problems
•   The average project exceeds its planned schedule by 120%
•   53% of projects will cost 189% of their original estimate
•   30% of projects are cancelled before completion
•   50% of projects are rolled back out of production
•   The typical project expends least effort on analysis where most errors originate and whose errors
    cost most to fix
•   Requirements errors cost the most and that poor requirements are the main cause of project
    failure

    February 3, 2010                                                                                      19
Requirements Drive Project Costs
                            100.0%                                                                                  •   While minimal
                             90.0%
                                                                                                                        costs have
                                                                                                                        actually been
                             80.0%                                                                                      spent at the
Costs Committed and Spent




                                                                                                                        requirements
                             70.0%                                                                                      phase of the
                                                                                                                        entire project
                             60.0%
                                                                                                                        process,
                             50.0%                                               Development and                        approximately
                                                                               Implementation Starts                    80% or more of
                             40.0%                                                                                      total life cycle
                                                                 Design Finalised                                       costs have
                             30.0%
                                         Requirements Defined
                                                                                                                        already been
                             20.0%            and Agreed                                                                determined at
                                                                                                                        this stage
                             10.0%
                                                                                                                    •   Need to get
                              0.0%                                                                                      requirements
                                                                                                                        right from the
                                                                 Project Timescale                                      outset to control
                                                                                                                        costs effectively
                              Costs Determined by Decisions on Requirements and Design         Actual Money Spent



                      February 3, 2010                                                                                                      20
Aligning the Solutions Being Delivered

•   Need more than project management
      − Not the complete picture
      − Cannot treat project management in isolation
•   Need to ensure that the solution being managed meets business
    requirements
•   Need to ensure business requirements are captured
•   Need to ensure that solutions are designed to deliver business
    requirements and comply with organisation’s enterprise architecture
•   Getting requirements right is essential for effective IT investment
    management
•   Fundamentally the project exists to manage the delivery of the
    solution that has been designed to meet business requirements
    that assist with delivery of the business plan

    February 3, 2010                                                      21
Complete Picture of Project Selection and Delivery

•   Need to consider all aspects of project selection and
    delivery:
      − What the business wants (requirements)
      − What the business gets (solution that delivers on requirements)
      − Delivered according to business priority (project portfolio
        management)
      − Implemented properly (project management)
•   Cannot take an individual view without risking problems
•   Need to emphasise the importance of the solution whole
    lifecycle and the interdependence of the roles


    February 3, 2010                                                      22
Lessons Learned From Large Systems
Implementation
 80 % More attention on process optimisation
 65 % Align systematically to company goals
 60 % Pay more attention to understanding the subject area spanned
 55 % Implementation of a management information system as part of scope
 50 % Outsource project management of the project to a third party
 45 % Increase investment in training
 35 % Greater employees involvement
 35 % Enforce changes more courageously
 30 % Identify and capture proof of benefits and saving as part of scope
 20 % Avoid big-bang implementations
 February 3, 2010                                                          23
Types of Cost Estimates

•   Life Cycle Cost Estimate (LCCE) - includes independent cost
    estimates, independent cost assessments and total ownership costs
      − Encompasses all past (or sunk), present and future costs for every aspect of the
        program, regardless of funding source
•   Business Case Analysis (BCA) - includes an analysis of alternatives
    and/or economic analyses
      − Cost benefit or comparative analysis that presents facts and supporting details
        among competing alternatives
      − Includes life-cycle costs from LCCE and also quantifiable and unquantifiable
        benefits
•   Rough Order of Magnitude (ROM ) - developed when a quick
    estimate is needed and few details are available
      − Usually based on historical ratio information
      − Typically developed to support what-if analyses
      − Helpful for examining differences in high-level alternative see which are the
        most feasible
      − A rough order of analysis should never be considered a budget-quality cost
        estimate

    February 3, 2010                                                                       24
Life Cycle Cost Estimate (LCCE) Composition
                                                                                           LIFE CYCLE COST

                                                                   SYSTEM ACQUISITION
                                                                              COST      •Operations
                                              PROCUREMENT COST                          •Internal Support
                                                                   •Planning, Research, •Disposal
                        TOTAL SYSTEM COST    •External Support and Analysis and Design
                                             Maintenance           •Ongoing Test
   BASIC SYSTEM COST   •Training             •Subscription         Facilities
                       •Documentation
 •Hardware             •Support Facilities
 •Software             •Parallel Running
 •Development and      •Warranty
 Implementation
 •Management
 •Installation
 •Transition and
 Cutover
 •Conversion




 February 3, 2010                                                                                            25
LCCE Cost Composition
                                                 Total Cost of Ownership


                       System Acquisition Cost                   Operating and Support Cost



              COST




                                                   YEARS



•   Depending on the life of the solution being implemented,
    the operating costs can be 1-3 times the cost of acquisition

    February 3, 2010                                                                          26
IT Investment Management and Project and
Solution Lifecycle
                                                                                Structured Capture
                                                                               and Management of
    Cost Effective                                                              Requirements and
    Operation of                                   Business Analysis           Cost Benefit Analysis
  Delivered Solution                                                             of Solution Costs
    and Effective              Solution
     Retirement/              Operation
    Replacement/
  Upgrade Decisions

                                                                                            Design/Selection of
                                                                                               Cost Effective
                                                                    Solution                 Solutions to Meet
                                                                Architecture and               Requirements
 Cost Effective                                                      Design                      Including
  Delivery of                                                                                 Evaluation of All
                       Programme and
 Projects and                                                                                     Options
                           Project
Management of           Management
     Costs



                                          Project Portfolio             Prioritisation of
                                           Management                    Projects and
                                                                          Investment
                                                                           Decisions
  February 3, 2010                                                                                          27
Benefits of Effective IT Investment Management
Framework
•   Aligns investments to business goals and objectives
•   Identifies and track spending on IT investments
•   Controls and monitor IT investment projects
•   Confirms that IT investments are meeting business
    objectives
•   Leverages IT investment opportunities that may generate
    internal capital
•   Make informed decisions on an IT investment portfolio by
    assessing value and risk
•   Demonstrates that IT can be trusted to invest wisely
    February 3, 2010                                           28
IT Investment Management Framework
                                 Business Plans
      Organisation               and Associated
                                                     What Proposed IT
                                  Technology
      Strategic Plan                 Needs        Investments Potentially
                                                    Solve the Identified
                                                     Business Needs?

                                                     Pre-Selection and
                                                       Identification
              Investment
                                                           Stage
                Results



         Did the Selected                                                                        Which IT
          IT Investments                                                                       Investments
            Deliver the     Evaluation Stage
                                                   Technology and           Selection Stage   Best Meet the
              Expected                            Systems Portfolio                              Business
         Business Value?                                                                         Needs?




                                                      Control Stage

                                                     Are the Selected IT
                                                  Investments Performing
                                                        as Planned?
 February 3, 2010                                                                                        29
IT Investment Management Stages
Pre-Selection and
  Identification                                                                                      Selection Stage
      Stage
Identify business needs and prioritise potential           Evaluate, score, and rank IT investments
investments                                                Prioritise IT projects
Develop investment business cases
Research possible enterprise/collaboration opportunities
Update the Strategic plan and technology Portfolio

Evaluation Stage                                                                                      Control Stage


Conduct post implementation reviews on major IT projects Translate business value into performance measures
using the asset performance measures established in the  Develop detailed project plans and execute projects in
Control Phase                                            accordance with project management standards
Use asset performance measures to measure the business Develop applications in accordance with technical and
value                                                    data standards for information technology
Document IT asset performance                              Submit project status reports, requests for baseline
Analyse gaps between current business needs and            adjustments greater than defined percentage (typically
performance of IT assets                                   10%) and verification and validation reports for each
Make a determination to maintain, migrate, improve, or     major IT project
retire each IT asset in the technology portfolio
   February 3, 2010                                                                                                     30
IT Investment Management Control Function
Responsibilities
                                                    Technical Scope
                                                     Management

                                                                                 Technical
                    Portfolio Management                                       Requirements
                                                                               Management



                                                 IT Investment
                                                 Management
                                                Control Function                       Progress
            Earned Value
                                                                                     Reporting and
            Management
                                                                                     Management



                                  Scope, Cost and
                                                                         Risk
                                     Schedule
                                                                      Management
                                   Management


 February 3, 2010                                                                                    31
Portfolio Management

•   Portfolio Management is an approach typically combined with a set
    of tools for identifying, diagnosing, controlling, and increasing the
    aggregate return on investments at a given level of risk tolerance
•   Based on the management principle that any set of investments
    requires proactive management to maximise value while minimising
    risk
•   IT portfolio management takes advantage of an integrated set of IT
    management processes, techniques, and tools that assist decision
    makers in analysing, selecting, evaluating, and controlling an optimal
    set of investments
•   Properly executed IT portfolio management delivers the benefits of
    balancing supply and demand of IT resources (financial and non-
    financial), eliminating redundancy, and enabling better alignment
    with strategic goals

    February 3, 2010                                                         32
Earned Value Management

•   Earned Value Management (EVM) is a project management metric
    that integrates the technical scope of work with schedule and cost
    elements for investment planning and control
•   Compares the value of work accomplished in a given period with the
    value of the work expected in that period
•   Differences in expectations are measured in both cost and schedule
    variances
•   Use EVM in performance-based management systems
•   Management of a cost estimate involves continually updating the
    estimate with actual data as they become available (EVM) revising
    the estimate to reflect changes and analysing differences between
    estimated and actual costs

    February 3, 2010                                                     33
Cost Estimation Best Practices Checklist

• The cost estimate type is clearly defined and is appropriate
  for its purpose
• All applicable program costs have been estimated,
  including all life-cycle costs
• The cost estimate is independent of funding source
• An affordability analysis has been performed at the agency
  level to see how the project fits within the overall portfolio
• The estimate is updated as actual costs become available
  from the EVM system or as requirements change
• Post mortems and lessons learned exercises are
  continually documented as information becomes available

    February 3, 2010                                               34
Cost Estimating Process
 Initiation and Research        Step 1:        Step 2:
                              Define the    Develop the
  The audience, what is       Purpose of     Estimating
being estimated and why      the Estimate       Plan
It is being estimated are
     very importance

      Assessment               Step 3:         Step 4:        Step 5:       Step 6:      Step 7:
                              Define the     Determine       Identify     Obtain Data   Develop
 Cost assessment steps         Project           the         Ground                       Point
are iterative and can be                     Estimating     Rules and                   Estimate
accomplished in varying                      Approach      Assumptions
 order or concurrently

         Analysis               Step 8:       Step 9:        Step 10:
                               Conduct      Conduct Risk    Document
 The confidence in the        Sensitivity       and        the Estimate
  point or range of the        Analysis     Uncertainty
estimate is crucial to the                    Analysis
     decision maker

      Presentation             Step 11:       Step 12:
                               Present        Update
   Documentation and         Estimate for   Estimate to
presentation can make or      Approval         Reflect
 break a cost estimating                    Actual Costs
    decision outcome                        and Changes
     February 3, 2010                                                                              35
Cost Estimating Process

•   Each of the 12 steps is important for ensuring that high-
    quality cost estimates are developed and delivered in time
    to support important decisions




    February 3, 2010                                             36
Cost Estimating Process

•   Step 1: Define the Purpose of the Estimate
      − Determine the estimate’s purpose
      − Determine the level of detail required
      − Determine who will receive the estimate
      − Determine the overall scope of the estimate
•   Step 2: Develop the Estimating Plan
      − Determine the cost estimating team
      − Outline the cost estimating approach
      − Develop the estimate timeline
      − Determine who will do the independent cost estimate
      − Develop the schedule

    February 3, 2010                                          37
Cost Estimating Process

•   Step 3: Define the Project
      −    Identify in a technical baseline description document
      −    The purpose of the project
      −    Its system and performance characteristics
      −    Any technology implications
      −    All system configurations
      −    project acquisition schedule
      −    Acquisition strategy;
      −    Relationship to other existing systems
      −    Support (manpower, training, etc.) and security needs
      −    Risks
      −    Assumptions
      −    System quantities for development, test, and production
      −    Deployment and maintenance plans;
      −    Predecessor or similar legacy systems
•   Step 4: Determine the Estimating Approach
      −    Define work breakdown structure (WBS) and describe each element
      −    Choose the estimating method best suited for each WBS element
      −    Identify potential cross-checks for likely cost and schedule drivers.
      −    Develop a cost estimating checklist



    February 3, 2010                                                               38
Cost Estimating Process

•   Step 5: Identify Ground Rules and Assumptions
      − Clearly define what is included and excluded from the estimate
      − Identify global and program specific assumptions such as:
             •    The estimate’s timescale, including time-phasing and life cycle
             •    Program schedule information by phase
             •    Program acquisition strategy
             •    Any schedule or budget constraints
             •    Inflation assumptions
             •    Costs such as travel and other expenses
             •    Equipment the organisation is to furnish
             •    Prime contractor and major subcontractors
             •    Use of existing facilities or new modifications or developments
             •    Technology refresh cycles
             •    Technology assumptions and new technology to be developed
             •    Commonality with legacy systems and assumed heritage savings
             •    Effects of new ways of doing business
•   Step 6: Obtain Data
      − Create a data collection plan with emphasis on collecting current and relevant technical, programmatic, cost, and
        risk data.
      − Investigate possible data sources
      − Collect data and normalise them for cost accounting, inflation, learning, and quantity adjustments
      − Analyse the data to look for cost drivers, trends, and outliers compare results against rules of thumb and
        standard factors derived from historical data
      − Interview data sources and document all relevant information including an assessment of data reliability and
        accuracy




    February 3, 2010                                                                                                        39
Cost Estimating Process

•   Step 7: Develop Point Estimate
      − Develop the cost model by estimating each WBS element, using the best methodology
        from the data collected
      − Include all estimating assumptions in the cost model
      − Express costs in constant year currency
      − Time-phase the results by spreading costs in the years they are expected to occur,
        based on the pro gram schedule
      − Sum the WBS elements to develop the overall point estimate
      − Validate the estimate by looking for errors like double counting and omitting costs
      − Compare estimate against the independent cost estimate and examine w here and why
        there are differences
      − Perform cross-checks on cost drivers to see if results are similar
      − Update the model as more data become available or as changes occur and compare
        results against previous estimates
•   Step 8: Conduct Sensitivity Analysis
      − Test the sensitivity of cost elements to changes in estimating input values and key
        assumptions
      − Identify effects of changing the program schedule or quantities on the overall estimate
      − Determine which assumptions are key cost drivers and which cost elements are
        affected most by changes

    February 3, 2010                                                                              40
Cost Estimating Process

•   Step 9: Conduct Risk and Uncertainty Analysis
      − Determine the level of cost, schedule, and technical risk associated with each WBS element and discuss with
        technical experts
      − Analyse each risk for its severity and probability of occurrence
      − Develop minimum, most likely, and maximum ranges for each element of risk
      − Use an acceptable statistical analysis methodology to develop a confidence interval around the point estimate
      − Determine type of risk distributions and reason for their use
      − Identify the confidence level of the point estimate
      − Identify the amount of contingency funding and add this to the point estimate to determine the risk-adjusted
        cost estimate
      − Recommend that the project office develop a risk management plan to track and mitigate risks
•   Step 10: Document the Estimate
      − Document all steps used to develop the estimate so that it can be recreated quickly by a cost analyst unfamiliar
        with the program and produce the same result
      − Document the purpose of the estimate, the team that prepared it, and who approved the estimate and on what
        date
      − Describe the program, including the schedule and technical baseline used to create the estimate
      − Present the time-phased life-cycle cost of the program
      − Discuss all ground rules and assumptions
      − Include auditable and traceable data sources for each cost element
      − Document for all data sources how the data were normalised
      − Describe the results of the risk, uncertainty, and sensitivity analyses and whether any contingency funds were
        identified
      − Document how the estimate compares to the funding profile
      − Track how this estimate compares to previous estimates, if applicable


    February 3, 2010                                                                                                       41
Cost Estimating Process

•   Step 11: Present Estimate for Approval
      − Develop a briefing that presents the documented life-cycle cost estimate for management
        approval, including
             • An explanation of the technical and programmatic baseline and any uncertainties;
             • A comparison to an independent cost estimate (ICE) with explanations of any differences;
             • A comparison of the estimate (life-cycle cost estimate (LCCE) or independent cost estimate to the budget;
               and
             • Enough detail so the presenter can easily defend the estimate by showing how it is accurate, complete, and
               high in quality.
      − Focus the briefing, in a logical manner, on the largest cost elements and drivers of cost
      − Make the content concise and complete so that those who are unfamiliar with it can easily
        comprehend the competence that underlies the estimate results
      − Make backup slides available for more probing questions
      − Act on and document feedback from management
      − The cost estimating team should request acceptance of the estimate
•   Step 12: Update Estimate to Reflect Actual Costs and Changes
      − Update the estimate to
             • Reflect any changes in technical or program assumptions
             • Keep it current as the program passes through new phases
      − Replace estimates with EVM EAC and Independent estimate at completion (EAC) from EVM
      − Report progress on meeting cost and schedule estimates
      − Perform a post mortem and document lessons learned for elements whose actual costs or
        schedules differ from the estimate.
      − Document all changes to the program and how they affect the cost estimate

    February 3, 2010                                                                                                        42
Work Breakdown Structure

•   Cornerstone of every project because it defines in detail the work
    necessary to accomplish a project’s objectives
      − Essential part of developing a project’s cost estimate
      − WBS reflects the delivery of the agreed requirements to the agreed solution
        design
•   A typical WBS reflects the requirements, resources and tasks that
    must be accomplished to develop a program
•   WBS communicates to everyone what needs to be done and how
    the activities relate to one another
•   Provides a consistent framework for planning and assigning
    responsibility for the work
•   Define a project in terms of product-oriented elements, broken into
    a hierarchical structure
•   Product-oriented WBS ensures that all costs are captured
    February 3, 2010                                                                  43
Validating Cost Estimates

•   Cost estimates should be validated against best practice
    characteristics
      − Comprehensive
      − Well-documented
      − Accurate
      − Credible




    February 3, 2010                                           44
Validating Cost Estimates

•   Comprehensive
      −    Completely define the program and reflect the current schedule
      −    Include all possible costs using a logical WBS that accounts for all requirements
      −    Ensure that no costs are omitted nor double-counted
      −    Explain and document key assumptions that are technically reasonable
•   Well-documented
      − They can be easily repeated or updated and traced to original sources through
        auditing
      − Supporting documentation identifies the data sources, justifies all
        assumptions, and provides a description of each estimating methodology for
        every WBS cost element
      − Schedule milestones and deliverables are traceable and consistent with the
        cost estimate documentation



    February 3, 2010                                                                           45
Validating Cost Estimates

•   Accurate
      −    They are not overly conservative or too optimistic
      −    Based on an assessment of most likely costs and adjusted properly for inflation
      −    Contain few, if any, mistakes that are minor in nature
      −    Are updated when assumptions or requirements change to reflect current status
      −    Cost estimating relationships and parametric cost models are validated to ensure they are good
           predictors of costs
             • Data is current and applicable to the new program,
             • The relationships between technical parameters are logical and statistically significant
             • Results are tested with independent data
•   Credible
      − They clearly identify any limitations because of uncertainty or biases surrounding the data or assumptions
      − Results are similar to cross-checks and an independent cost estimate derived using different
        methodologies
             • Independent cost estimates performed by estimators farthest away from the acquiring program office represent a
               best practices because they
                       − Tend to produce higher and more accurate cost estimates than those performed by staff sharing a common supervisor
                         with the program office
                       − Produce more credible estimates than other types of independent estimate reviews which may not be as inclusive as an
                         ICE (e.g., IGCE, ICA, Sufficiency Review, etc.)
      − A sensitivity analysis has been performed to identify cost drivers and the impacts of varying assumptions
      − A risk / uncertainty analysis has been performed to determine the level of risk associated with the point
        estimate




    February 3, 2010                                                                                                                            46
Cost Assessment Team

•   Cost estimates are frequently developed with an
    incomplete knowledge of what the exact final technical
    solution will be
•   Cost assessment team must manage a great deal of risk,
    especially for programs that are complex or use leading
    edge of technology
•   Cost estimates define what a given solution will ultimately
    cost
•   Estimate will be affected by multiple assumptions and an
    interpretation of what the historical data represent

    February 3, 2010                                              47
Disciplines and Concepts in Cost Analysis
                               Economics                                Interpersonal
                           •Break-even Analysis                             Skills
                           •Personnel Cost                            •Approach
                           •Inflation                                 •Estimate
                           •Present Value                             •Knowledge
                           Analysis



      Budgeting                                                                                  Commercial
•Organisation                                                                                •Analysis of
Specific Skills                                                                              Commercial Models
•Program Specific                                  Cost Analysis                             •Analysis of
Skills                                              Team Skills                              Proposals
                                                                                             •Development of
                                                                                             Cost Estimating
                                                                                             Relationship


                       Information                     Statistics              Accounting
                       Technology                 •Forecasting             •Cost Data Analysis
                    •Analysis                     •Risk/Uncertainty        •Financial Analysis
                    •Design                       Analysis                 •Overhead Analysis
                    •Development                                           •Proposal Analysis
                    •Testing
                    •Scheduling
                    •System Integration
 February 3, 2010                                                                                                48
Centralised vs. Decentralised Costing Function

•   Centralised Costing Function              •   Decentralised Costing Function

      − Facilitates the use of standardised       − Often results in ad hoc and
        and consistent processes                    inconsistent processes
      − Better resource sharing                   − Decreased independence
      − Common tools and training                 − Greater access to local technical
      − Ability to resist pressure to lower         resources
        the cost estimate when it is higher
        than the allotted budget
      − Can be remote from technical
        experts




    February 3, 2010                                                                    49
Cost Assessment Team Best Practices Checklist

•   The estimating team’s composition has the skills needed
    for the program of work
      − The team has the proper number and mix of resources
      − The team has the proper number and mix of resources
      − The team includes experienced and trained cost analysts
      − The team includes, or has direct access to, analysts experienced in
        the program’s major areas
      − Team members’ experience, qualifications, certifications, and
        training are identified
• A master schedule with a written study plan has been
  developed
• The team has access to the necessary subject matter
  experts
    February 3, 2010                                                          50
IT Investment Management Maturity Stages

                                                                               Description
                                                 The organisation has mastered the selection, control, and evaluation
                          Leveraging IT for      processes and now seeks to shape its strategic outcomes by
5                        Strategic Outcomes      benchmarking its IT investment processes relative to other "best-in-class"
                                                 organizations.

                                                 The organisation is focused on evaluation techniques to improve its IT
                            Improving the
4                        Investment Process
                                                 investment processes and portfolio(s), while maintaining mature selection
                                                 and control techniques.

                                                 The organisation has developed a well-defined IT investment portfolio
                       Developing a Complete     using an investment process that has sound selection criteria and
3                       Investment Portfolio     maintains mature, evolving, and integrated selection, control, and
                                                 evaluation processes.
                                                 Basic selection capabilities are being driven by the development of project
                       Building the Investment   selection criteria, including benefit and risk criteria, and an awareness of
2                            Foundation          organizational priorities when identifying projects for funding. Executive
                                                 oversight is applied on a project-by-project basis.
                                                 Ad hoc, unstructured, and unpredictable investment processes
                        Creating Investment      characterise this stage. There is generally little relationship between the
1                           Awareness            success or failure of one project and the success or failure of another
                                                 project.
    February 3, 2010                                                                                                           51
Increasing IT Investment Management Maturity
  5 Leveraging IT for
  Strategic Outcomes

                     1.   The organisation learns from and adopts the tools,
                          techniques, or methods used by best-in-class external                   4 Improving the
                          organisations
                     2.   Changes to strategic business processes are driven by the             Investment Process
                          capabilities of identified information technologies

                                        1.   Evaluation techniques are being used to improve the
3 Developing a Complete                      investment processes and the portfolio
  Investment Portfolio                  2.   Succession management processes are developed for
                                             retaining or disposing of investments.

                     1.   Criteria are developed for identifying investments that best
                          fit with the portfolio.
                     2.   The portfolio is developed through the use of                     2 Building the Investment
                          categorisation when comparing investments.                               Foundation
                     3.   Performance reviews are conducted both during and after
                          implementation
                                        1.   An investment board is established to drive the investment
                                             process
 1 Creating Investment                  2.   Business needs are identified for each project
      Awareness                         3.   An investment selection process is developed
                                        4.   Board oversees the progress of individual projects
                                        5.   Investment information is collected and disseminated
  February 3, 2010                                                                                                   52
More Information

          Alan McSweeney
          alan@alanmcsweeney.com




 February 3, 2010                  53

Contenu connexe

Tendances

IT Strategy & Planning
IT Strategy & PlanningIT Strategy & Planning
IT Strategy & Planningchakraj
 
Enterprise architecture framework business case
Enterprise architecture framework business caseEnterprise architecture framework business case
Enterprise architecture framework business caseAlex Antonatos
 
IT Strategy I Best Practices I NuggetHub
IT Strategy I Best Practices I NuggetHubIT Strategy I Best Practices I NuggetHub
IT Strategy I Best Practices I NuggetHubRichardNowack
 
Review of Information Technology Function Critical Capability Models
Review of Information Technology Function Critical Capability ModelsReview of Information Technology Function Critical Capability Models
Review of Information Technology Function Critical Capability ModelsAlan McSweeney
 
Enterprise Architecture Governance
Enterprise Architecture GovernanceEnterprise Architecture Governance
Enterprise Architecture GovernanceRakesh Sharan
 
Enterprise Architecture Frameworks
Enterprise Architecture FrameworksEnterprise Architecture Frameworks
Enterprise Architecture FrameworksStephen Lahanas
 
Design your Business, Model your Architecture (presentation by Marc Lankhorst...
Design your Business, Model your Architecture (presentation by Marc Lankhorst...Design your Business, Model your Architecture (presentation by Marc Lankhorst...
Design your Business, Model your Architecture (presentation by Marc Lankhorst...Patrick Van Renterghem
 
Bpm Implementation Success Criteria And Best Practice
Bpm Implementation   Success Criteria And Best PracticeBpm Implementation   Success Criteria And Best Practice
Bpm Implementation Success Criteria And Best PracticeAlan McSweeney
 
Data Profiling, Data Catalogs and Metadata Harmonisation
Data Profiling, Data Catalogs and Metadata HarmonisationData Profiling, Data Catalogs and Metadata Harmonisation
Data Profiling, Data Catalogs and Metadata HarmonisationAlan McSweeney
 
Becoming a Data-Driven Organization - Aligning Business & Data Strategy
Becoming a Data-Driven Organization - Aligning Business & Data StrategyBecoming a Data-Driven Organization - Aligning Business & Data Strategy
Becoming a Data-Driven Organization - Aligning Business & Data StrategyDATAVERSITY
 
Data Governance: Keystone of Information Management Initiatives
Data Governance: Keystone of Information Management InitiativesData Governance: Keystone of Information Management Initiatives
Data Governance: Keystone of Information Management InitiativesAlan McSweeney
 
Enterprise Business Analysis Capability - Strategic Asset for Business Alignm...
Enterprise Business Analysis Capability - Strategic Asset for Business Alignm...Enterprise Business Analysis Capability - Strategic Asset for Business Alignm...
Enterprise Business Analysis Capability - Strategic Asset for Business Alignm...Alan McSweeney
 
Data Governance for the Executive
Data Governance for the ExecutiveData Governance for the Executive
Data Governance for the ExecutiveDATAVERSITY
 
What is the Value of Mature Enterprise Architecture TOGAF
What is the Value of Mature Enterprise Architecture TOGAFWhat is the Value of Mature Enterprise Architecture TOGAF
What is the Value of Mature Enterprise Architecture TOGAFxavblai
 
IT Architecture’s Role In Solving Technical Debt.pdf
IT Architecture’s Role In Solving Technical Debt.pdfIT Architecture’s Role In Solving Technical Debt.pdf
IT Architecture’s Role In Solving Technical Debt.pdfAlan McSweeney
 
A TOGAF Case Study
A TOGAF Case StudyA TOGAF Case Study
A TOGAF Case StudySimplilearn
 

Tendances (20)

IT Strategy & Planning
IT Strategy & PlanningIT Strategy & Planning
IT Strategy & Planning
 
IT Strategy
IT StrategyIT Strategy
IT Strategy
 
Enterprise architecture framework business case
Enterprise architecture framework business caseEnterprise architecture framework business case
Enterprise architecture framework business case
 
IT Strategy I Best Practices I NuggetHub
IT Strategy I Best Practices I NuggetHubIT Strategy I Best Practices I NuggetHub
IT Strategy I Best Practices I NuggetHub
 
Review of Information Technology Function Critical Capability Models
Review of Information Technology Function Critical Capability ModelsReview of Information Technology Function Critical Capability Models
Review of Information Technology Function Critical Capability Models
 
Enterprise Architecture Governance
Enterprise Architecture GovernanceEnterprise Architecture Governance
Enterprise Architecture Governance
 
Define an EA Operating Model
Define an EA Operating ModelDefine an EA Operating Model
Define an EA Operating Model
 
Enterprise Architecture Frameworks
Enterprise Architecture FrameworksEnterprise Architecture Frameworks
Enterprise Architecture Frameworks
 
Design your Business, Model your Architecture (presentation by Marc Lankhorst...
Design your Business, Model your Architecture (presentation by Marc Lankhorst...Design your Business, Model your Architecture (presentation by Marc Lankhorst...
Design your Business, Model your Architecture (presentation by Marc Lankhorst...
 
Bpm Implementation Success Criteria And Best Practice
Bpm Implementation   Success Criteria And Best PracticeBpm Implementation   Success Criteria And Best Practice
Bpm Implementation Success Criteria And Best Practice
 
Data Profiling, Data Catalogs and Metadata Harmonisation
Data Profiling, Data Catalogs and Metadata HarmonisationData Profiling, Data Catalogs and Metadata Harmonisation
Data Profiling, Data Catalogs and Metadata Harmonisation
 
Becoming a Data-Driven Organization - Aligning Business & Data Strategy
Becoming a Data-Driven Organization - Aligning Business & Data StrategyBecoming a Data-Driven Organization - Aligning Business & Data Strategy
Becoming a Data-Driven Organization - Aligning Business & Data Strategy
 
Data Governance: Keystone of Information Management Initiatives
Data Governance: Keystone of Information Management InitiativesData Governance: Keystone of Information Management Initiatives
Data Governance: Keystone of Information Management Initiatives
 
Enterprise Business Analysis Capability - Strategic Asset for Business Alignm...
Enterprise Business Analysis Capability - Strategic Asset for Business Alignm...Enterprise Business Analysis Capability - Strategic Asset for Business Alignm...
Enterprise Business Analysis Capability - Strategic Asset for Business Alignm...
 
Data Governance for the Executive
Data Governance for the ExecutiveData Governance for the Executive
Data Governance for the Executive
 
Optimize the IT Operating Model
Optimize the IT Operating ModelOptimize the IT Operating Model
Optimize the IT Operating Model
 
What is the Value of Mature Enterprise Architecture TOGAF
What is the Value of Mature Enterprise Architecture TOGAFWhat is the Value of Mature Enterprise Architecture TOGAF
What is the Value of Mature Enterprise Architecture TOGAF
 
IT Architecture’s Role In Solving Technical Debt.pdf
IT Architecture’s Role In Solving Technical Debt.pdfIT Architecture’s Role In Solving Technical Debt.pdf
IT Architecture’s Role In Solving Technical Debt.pdf
 
EA Report.pdf
EA Report.pdfEA Report.pdf
EA Report.pdf
 
A TOGAF Case Study
A TOGAF Case StudyA TOGAF Case Study
A TOGAF Case Study
 

En vedette

Requirements Gathering And Management
Requirements Gathering And ManagementRequirements Gathering And Management
Requirements Gathering And ManagementAlan McSweeney
 
India Venture Capital Investments - April 2012
India Venture Capital Investments - April 2012India Venture Capital Investments - April 2012
India Venture Capital Investments - April 2012StartupCentral
 
Project Management with Mikola Andrejeu #2
Project Management with Mikola Andrejeu #2Project Management with Mikola Andrejeu #2
Project Management with Mikola Andrejeu #2Mikola Andrejeu
 
Robo Insurance Advisor from the EchoSage virtual agent platform
Robo Insurance Advisor from the EchoSage virtual agent platform Robo Insurance Advisor from the EchoSage virtual agent platform
Robo Insurance Advisor from the EchoSage virtual agent platform Duke Williams
 
Modelling an Enterprise Ecosystem for Digital Strategy - Craig Duncan, UNISDR...
Modelling an Enterprise Ecosystem for Digital Strategy - Craig Duncan, UNISDR...Modelling an Enterprise Ecosystem for Digital Strategy - Craig Duncan, UNISDR...
Modelling an Enterprise Ecosystem for Digital Strategy - Craig Duncan, UNISDR...Milan Guenther (eda.c)
 
Reasons For Global Recession Nayana
Reasons For Global Recession NayanaReasons For Global Recession Nayana
Reasons For Global Recession Nayananayanav
 
Time management Presentation at Insight Bible Church - Anua
Time management Presentation at Insight Bible Church - AnuaTime management Presentation at Insight Bible Church - Anua
Time management Presentation at Insight Bible Church - AnuaAkpanam Mkpa
 
COME AND HAVE A GO 2016
COME AND HAVE A GO 2016COME AND HAVE A GO 2016
COME AND HAVE A GO 2016Richard Smith
 
Creating Wealth In The Great Recession
Creating Wealth In The Great RecessionCreating Wealth In The Great Recession
Creating Wealth In The Great Recessionmoneyweb
 
The Nested Planning Cycle 160516
The Nested Planning Cycle 160516The Nested Planning Cycle 160516
The Nested Planning Cycle 160516Jeff Johnson
 
Bryson. chapter 1. why strategic planning is more important than ever
Bryson. chapter 1. why strategic planning is more important than everBryson. chapter 1. why strategic planning is more important than ever
Bryson. chapter 1. why strategic planning is more important than everBeulah Heights University
 
Marketing In A Recession
Marketing In A RecessionMarketing In A Recession
Marketing In A Recessiondavid hearn
 
Corporate Investment Structure for Governance Analysis by Elijah Ezendu
Corporate Investment Structure for Governance Analysis by Elijah EzenduCorporate Investment Structure for Governance Analysis by Elijah Ezendu
Corporate Investment Structure for Governance Analysis by Elijah EzenduElijah Ezendu
 

En vedette (17)

The estimating process
The estimating processThe estimating process
The estimating process
 
Requirements Gathering And Management
Requirements Gathering And ManagementRequirements Gathering And Management
Requirements Gathering And Management
 
India Venture Capital Investments - April 2012
India Venture Capital Investments - April 2012India Venture Capital Investments - April 2012
India Venture Capital Investments - April 2012
 
Capital Planning
Capital PlanningCapital Planning
Capital Planning
 
Investment planning
Investment planningInvestment planning
Investment planning
 
Project Management with Mikola Andrejeu #2
Project Management with Mikola Andrejeu #2Project Management with Mikola Andrejeu #2
Project Management with Mikola Andrejeu #2
 
Robo Insurance Advisor from the EchoSage virtual agent platform
Robo Insurance Advisor from the EchoSage virtual agent platform Robo Insurance Advisor from the EchoSage virtual agent platform
Robo Insurance Advisor from the EchoSage virtual agent platform
 
Modelling an Enterprise Ecosystem for Digital Strategy - Craig Duncan, UNISDR...
Modelling an Enterprise Ecosystem for Digital Strategy - Craig Duncan, UNISDR...Modelling an Enterprise Ecosystem for Digital Strategy - Craig Duncan, UNISDR...
Modelling an Enterprise Ecosystem for Digital Strategy - Craig Duncan, UNISDR...
 
Reasons For Global Recession Nayana
Reasons For Global Recession NayanaReasons For Global Recession Nayana
Reasons For Global Recession Nayana
 
Time management Presentation at Insight Bible Church - Anua
Time management Presentation at Insight Bible Church - AnuaTime management Presentation at Insight Bible Church - Anua
Time management Presentation at Insight Bible Church - Anua
 
COME AND HAVE A GO 2016
COME AND HAVE A GO 2016COME AND HAVE A GO 2016
COME AND HAVE A GO 2016
 
EchoSage
EchoSageEchoSage
EchoSage
 
Creating Wealth In The Great Recession
Creating Wealth In The Great RecessionCreating Wealth In The Great Recession
Creating Wealth In The Great Recession
 
The Nested Planning Cycle 160516
The Nested Planning Cycle 160516The Nested Planning Cycle 160516
The Nested Planning Cycle 160516
 
Bryson. chapter 1. why strategic planning is more important than ever
Bryson. chapter 1. why strategic planning is more important than everBryson. chapter 1. why strategic planning is more important than ever
Bryson. chapter 1. why strategic planning is more important than ever
 
Marketing In A Recession
Marketing In A RecessionMarketing In A Recession
Marketing In A Recession
 
Corporate Investment Structure for Governance Analysis by Elijah Ezendu
Corporate Investment Structure for Governance Analysis by Elijah EzenduCorporate Investment Structure for Governance Analysis by Elijah Ezendu
Corporate Investment Structure for Governance Analysis by Elijah Ezendu
 

Similaire à Capital Planning And Investment Management And Control In Information Technology

Whitepaper Practical Information Technology Governance
Whitepaper   Practical Information Technology GovernanceWhitepaper   Practical Information Technology Governance
Whitepaper Practical Information Technology GovernanceAlan McSweeney
 
Benefits Identification, Assessment, Validation and Realisation for Informati...
Benefits Identification, Assessment, Validation and Realisation for Informati...Benefits Identification, Assessment, Validation and Realisation for Informati...
Benefits Identification, Assessment, Validation and Realisation for Informati...Alan McSweeney
 
IT Governance for (smaller) Nonprofits
IT Governance for (smaller) NonprofitsIT Governance for (smaller) Nonprofits
IT Governance for (smaller) NonprofitsNTEN
 
IT Governance for Nonprofits
IT Governance for NonprofitsIT Governance for Nonprofits
IT Governance for NonprofitsDonny Shimamoto
 
Service management time to fly, time to die it sm-fbe 2012
Service management   time to fly, time to die it sm-fbe 2012Service management   time to fly, time to die it sm-fbe 2012
Service management time to fly, time to die it sm-fbe 2012John M Walsh
 
20061102 CIO Magazine Round Table Top 5 Agenda 2006 by Joseph Toh
20061102 CIO Magazine Round Table Top 5 Agenda 2006 by Joseph Toh20061102 CIO Magazine Round Table Top 5 Agenda 2006 by Joseph Toh
20061102 CIO Magazine Round Table Top 5 Agenda 2006 by Joseph TohJoseph Toh
 
MAKING SENSE OF IT GOVERNANCE
MAKING SENSE OF IT GOVERNANCEMAKING SENSE OF IT GOVERNANCE
MAKING SENSE OF IT GOVERNANCERudy Shoushany
 
IT Governance.ppt
IT Governance.pptIT Governance.ppt
IT Governance.pptInsta13
 
Aligning Business & IT Strategy Workshop BumbleBee
Aligning Business & IT Strategy Workshop BumbleBeeAligning Business & IT Strategy Workshop BumbleBee
Aligning Business & IT Strategy Workshop BumbleBeeAdrian Hall
 
4. it governance a compass without a map v.2.6 pink elephant
4. it governance a compass without a map v.2.6   pink elephant4. it governance a compass without a map v.2.6   pink elephant
4. it governance a compass without a map v.2.6 pink elephantaventia
 
Itvr val approach
Itvr val approachItvr val approach
Itvr val approachsunnyaisha
 
Convergence Of Technology And Core Business Strategy
Convergence Of Technology And Core Business StrategyConvergence Of Technology And Core Business Strategy
Convergence Of Technology And Core Business StrategyLee Stott
 
Modern IT Service Management Transformation - ITIL Indonesia
Modern IT Service Management Transformation - ITIL IndonesiaModern IT Service Management Transformation - ITIL Indonesia
Modern IT Service Management Transformation - ITIL IndonesiaEryk Budi Pratama
 
Cinco consejos de los expertos Cutter (Cuitláhuac Osorio)
Cinco consejos de los expertos Cutter (Cuitláhuac Osorio)Cinco consejos de los expertos Cutter (Cuitláhuac Osorio)
Cinco consejos de los expertos Cutter (Cuitláhuac Osorio)Software Guru
 
The Case for Continual Realignment of the IT Function
The Case for Continual Realignment of the IT FunctionThe Case for Continual Realignment of the IT Function
The Case for Continual Realignment of the IT FunctionFormicio
 
Governance and Management of Enterprise IT with COBIT 5 Framework
Governance and Management of Enterprise IT with COBIT 5 FrameworkGovernance and Management of Enterprise IT with COBIT 5 Framework
Governance and Management of Enterprise IT with COBIT 5 FrameworkGoutama Bachtiar
 

Similaire à Capital Planning And Investment Management And Control In Information Technology (20)

Whitepaper Practical Information Technology Governance
Whitepaper   Practical Information Technology GovernanceWhitepaper   Practical Information Technology Governance
Whitepaper Practical Information Technology Governance
 
Sharpening the Lens
Sharpening the LensSharpening the Lens
Sharpening the Lens
 
Benefits Identification, Assessment, Validation and Realisation for Informati...
Benefits Identification, Assessment, Validation and Realisation for Informati...Benefits Identification, Assessment, Validation and Realisation for Informati...
Benefits Identification, Assessment, Validation and Realisation for Informati...
 
IT Governance for (smaller) Nonprofits
IT Governance for (smaller) NonprofitsIT Governance for (smaller) Nonprofits
IT Governance for (smaller) Nonprofits
 
IT Governance for Nonprofits
IT Governance for NonprofitsIT Governance for Nonprofits
IT Governance for Nonprofits
 
Service management time to fly, time to die it sm-fbe 2012
Service management   time to fly, time to die it sm-fbe 2012Service management   time to fly, time to die it sm-fbe 2012
Service management time to fly, time to die it sm-fbe 2012
 
20061102 CIO Magazine Round Table Top 5 Agenda 2006 by Joseph Toh
20061102 CIO Magazine Round Table Top 5 Agenda 2006 by Joseph Toh20061102 CIO Magazine Round Table Top 5 Agenda 2006 by Joseph Toh
20061102 CIO Magazine Round Table Top 5 Agenda 2006 by Joseph Toh
 
MAKING SENSE OF IT GOVERNANCE
MAKING SENSE OF IT GOVERNANCEMAKING SENSE OF IT GOVERNANCE
MAKING SENSE OF IT GOVERNANCE
 
IT Governance.ppt
IT Governance.pptIT Governance.ppt
IT Governance.ppt
 
Hawaii OIMT presentation
Hawaii OIMT presentationHawaii OIMT presentation
Hawaii OIMT presentation
 
IT Governance - COBIT Perspective
IT Governance - COBIT PerspectiveIT Governance - COBIT Perspective
IT Governance - COBIT Perspective
 
Aligning Business & IT Strategy Workshop BumbleBee
Aligning Business & IT Strategy Workshop BumbleBeeAligning Business & IT Strategy Workshop BumbleBee
Aligning Business & IT Strategy Workshop BumbleBee
 
4. it governance a compass without a map v.2.6 pink elephant
4. it governance a compass without a map v.2.6   pink elephant4. it governance a compass without a map v.2.6   pink elephant
4. it governance a compass without a map v.2.6 pink elephant
 
IT Governance
IT GovernanceIT Governance
IT Governance
 
Itvr val approach
Itvr val approachItvr val approach
Itvr val approach
 
Convergence Of Technology And Core Business Strategy
Convergence Of Technology And Core Business StrategyConvergence Of Technology And Core Business Strategy
Convergence Of Technology And Core Business Strategy
 
Modern IT Service Management Transformation - ITIL Indonesia
Modern IT Service Management Transformation - ITIL IndonesiaModern IT Service Management Transformation - ITIL Indonesia
Modern IT Service Management Transformation - ITIL Indonesia
 
Cinco consejos de los expertos Cutter (Cuitláhuac Osorio)
Cinco consejos de los expertos Cutter (Cuitláhuac Osorio)Cinco consejos de los expertos Cutter (Cuitláhuac Osorio)
Cinco consejos de los expertos Cutter (Cuitláhuac Osorio)
 
The Case for Continual Realignment of the IT Function
The Case for Continual Realignment of the IT FunctionThe Case for Continual Realignment of the IT Function
The Case for Continual Realignment of the IT Function
 
Governance and Management of Enterprise IT with COBIT 5 Framework
Governance and Management of Enterprise IT with COBIT 5 FrameworkGovernance and Management of Enterprise IT with COBIT 5 Framework
Governance and Management of Enterprise IT with COBIT 5 Framework
 

Plus de Alan McSweeney

Data Architecture for Solutions.pdf
Data Architecture for Solutions.pdfData Architecture for Solutions.pdf
Data Architecture for Solutions.pdfAlan McSweeney
 
Solution Architecture and Solution Estimation.pdf
Solution Architecture and Solution Estimation.pdfSolution Architecture and Solution Estimation.pdf
Solution Architecture and Solution Estimation.pdfAlan McSweeney
 
Validating COVID-19 Mortality Data and Deaths for Ireland March 2020 – March ...
Validating COVID-19 Mortality Data and Deaths for Ireland March 2020 – March ...Validating COVID-19 Mortality Data and Deaths for Ireland March 2020 – March ...
Validating COVID-19 Mortality Data and Deaths for Ireland March 2020 – March ...Alan McSweeney
 
Analysis of the Numbers of Catholic Clergy and Members of Religious in Irelan...
Analysis of the Numbers of Catholic Clergy and Members of Religious in Irelan...Analysis of the Numbers of Catholic Clergy and Members of Religious in Irelan...
Analysis of the Numbers of Catholic Clergy and Members of Religious in Irelan...Alan McSweeney
 
Solution Architecture And Solution Security
Solution Architecture And Solution SecuritySolution Architecture And Solution Security
Solution Architecture And Solution SecurityAlan McSweeney
 
Data Privatisation, Data Anonymisation, Data Pseudonymisation and Differentia...
Data Privatisation, Data Anonymisation, Data Pseudonymisation and Differentia...Data Privatisation, Data Anonymisation, Data Pseudonymisation and Differentia...
Data Privatisation, Data Anonymisation, Data Pseudonymisation and Differentia...Alan McSweeney
 
Data Privatisation, Data Anonymisation, Data Pseudonymisation and Differentia...
Data Privatisation, Data Anonymisation, Data Pseudonymisation and Differentia...Data Privatisation, Data Anonymisation, Data Pseudonymisation and Differentia...
Data Privatisation, Data Anonymisation, Data Pseudonymisation and Differentia...Alan McSweeney
 
Solution Security Architecture
Solution Security ArchitectureSolution Security Architecture
Solution Security ArchitectureAlan McSweeney
 
Solution Architecture And (Robotic) Process Automation Solutions
Solution Architecture And (Robotic) Process Automation SolutionsSolution Architecture And (Robotic) Process Automation Solutions
Solution Architecture And (Robotic) Process Automation SolutionsAlan McSweeney
 
Comparison of COVID-19 Mortality Data and Deaths for Ireland March 2020 – Mar...
Comparison of COVID-19 Mortality Data and Deaths for Ireland March 2020 – Mar...Comparison of COVID-19 Mortality Data and Deaths for Ireland March 2020 – Mar...
Comparison of COVID-19 Mortality Data and Deaths for Ireland March 2020 – Mar...Alan McSweeney
 
Analysis of Decentralised, Distributed Decision-Making For Optimising Domesti...
Analysis of Decentralised, Distributed Decision-Making For Optimising Domesti...Analysis of Decentralised, Distributed Decision-Making For Optimising Domesti...
Analysis of Decentralised, Distributed Decision-Making For Optimising Domesti...Alan McSweeney
 
Operational Risk Management Data Validation Architecture
Operational Risk Management Data Validation ArchitectureOperational Risk Management Data Validation Architecture
Operational Risk Management Data Validation ArchitectureAlan McSweeney
 
Data Integration, Access, Flow, Exchange, Transfer, Load And Extract Architec...
Data Integration, Access, Flow, Exchange, Transfer, Load And Extract Architec...Data Integration, Access, Flow, Exchange, Transfer, Load And Extract Architec...
Data Integration, Access, Flow, Exchange, Transfer, Load And Extract Architec...Alan McSweeney
 
Ireland 2019 and 2020 Compared - Individual Charts
Ireland   2019 and 2020 Compared - Individual ChartsIreland   2019 and 2020 Compared - Individual Charts
Ireland 2019 and 2020 Compared - Individual ChartsAlan McSweeney
 
Analysis of Irish Mortality Using Public Data Sources 2014-2020
Analysis of Irish Mortality Using Public Data Sources 2014-2020Analysis of Irish Mortality Using Public Data Sources 2014-2020
Analysis of Irish Mortality Using Public Data Sources 2014-2020Alan McSweeney
 
Ireland – 2019 And 2020 Compared In Data
Ireland – 2019 And 2020 Compared In DataIreland – 2019 And 2020 Compared In Data
Ireland – 2019 And 2020 Compared In DataAlan McSweeney
 
Critical Review of Open Group IT4IT Reference Architecture
Critical Review of Open Group IT4IT Reference ArchitectureCritical Review of Open Group IT4IT Reference Architecture
Critical Review of Open Group IT4IT Reference ArchitectureAlan McSweeney
 
Analysis of Possible Excess COVID-19 Deaths in Ireland From Jan 2020 to Jun 2020
Analysis of Possible Excess COVID-19 Deaths in Ireland From Jan 2020 to Jun 2020Analysis of Possible Excess COVID-19 Deaths in Ireland From Jan 2020 to Jun 2020
Analysis of Possible Excess COVID-19 Deaths in Ireland From Jan 2020 to Jun 2020Alan McSweeney
 
Agile Solution Architecture and Design
Agile Solution Architecture and DesignAgile Solution Architecture and Design
Agile Solution Architecture and DesignAlan McSweeney
 
Solution Architecture and Solution Acquisition
Solution Architecture and Solution AcquisitionSolution Architecture and Solution Acquisition
Solution Architecture and Solution AcquisitionAlan McSweeney
 

Plus de Alan McSweeney (20)

Data Architecture for Solutions.pdf
Data Architecture for Solutions.pdfData Architecture for Solutions.pdf
Data Architecture for Solutions.pdf
 
Solution Architecture and Solution Estimation.pdf
Solution Architecture and Solution Estimation.pdfSolution Architecture and Solution Estimation.pdf
Solution Architecture and Solution Estimation.pdf
 
Validating COVID-19 Mortality Data and Deaths for Ireland March 2020 – March ...
Validating COVID-19 Mortality Data and Deaths for Ireland March 2020 – March ...Validating COVID-19 Mortality Data and Deaths for Ireland March 2020 – March ...
Validating COVID-19 Mortality Data and Deaths for Ireland March 2020 – March ...
 
Analysis of the Numbers of Catholic Clergy and Members of Religious in Irelan...
Analysis of the Numbers of Catholic Clergy and Members of Religious in Irelan...Analysis of the Numbers of Catholic Clergy and Members of Religious in Irelan...
Analysis of the Numbers of Catholic Clergy and Members of Religious in Irelan...
 
Solution Architecture And Solution Security
Solution Architecture And Solution SecuritySolution Architecture And Solution Security
Solution Architecture And Solution Security
 
Data Privatisation, Data Anonymisation, Data Pseudonymisation and Differentia...
Data Privatisation, Data Anonymisation, Data Pseudonymisation and Differentia...Data Privatisation, Data Anonymisation, Data Pseudonymisation and Differentia...
Data Privatisation, Data Anonymisation, Data Pseudonymisation and Differentia...
 
Data Privatisation, Data Anonymisation, Data Pseudonymisation and Differentia...
Data Privatisation, Data Anonymisation, Data Pseudonymisation and Differentia...Data Privatisation, Data Anonymisation, Data Pseudonymisation and Differentia...
Data Privatisation, Data Anonymisation, Data Pseudonymisation and Differentia...
 
Solution Security Architecture
Solution Security ArchitectureSolution Security Architecture
Solution Security Architecture
 
Solution Architecture And (Robotic) Process Automation Solutions
Solution Architecture And (Robotic) Process Automation SolutionsSolution Architecture And (Robotic) Process Automation Solutions
Solution Architecture And (Robotic) Process Automation Solutions
 
Comparison of COVID-19 Mortality Data and Deaths for Ireland March 2020 – Mar...
Comparison of COVID-19 Mortality Data and Deaths for Ireland March 2020 – Mar...Comparison of COVID-19 Mortality Data and Deaths for Ireland March 2020 – Mar...
Comparison of COVID-19 Mortality Data and Deaths for Ireland March 2020 – Mar...
 
Analysis of Decentralised, Distributed Decision-Making For Optimising Domesti...
Analysis of Decentralised, Distributed Decision-Making For Optimising Domesti...Analysis of Decentralised, Distributed Decision-Making For Optimising Domesti...
Analysis of Decentralised, Distributed Decision-Making For Optimising Domesti...
 
Operational Risk Management Data Validation Architecture
Operational Risk Management Data Validation ArchitectureOperational Risk Management Data Validation Architecture
Operational Risk Management Data Validation Architecture
 
Data Integration, Access, Flow, Exchange, Transfer, Load And Extract Architec...
Data Integration, Access, Flow, Exchange, Transfer, Load And Extract Architec...Data Integration, Access, Flow, Exchange, Transfer, Load And Extract Architec...
Data Integration, Access, Flow, Exchange, Transfer, Load And Extract Architec...
 
Ireland 2019 and 2020 Compared - Individual Charts
Ireland   2019 and 2020 Compared - Individual ChartsIreland   2019 and 2020 Compared - Individual Charts
Ireland 2019 and 2020 Compared - Individual Charts
 
Analysis of Irish Mortality Using Public Data Sources 2014-2020
Analysis of Irish Mortality Using Public Data Sources 2014-2020Analysis of Irish Mortality Using Public Data Sources 2014-2020
Analysis of Irish Mortality Using Public Data Sources 2014-2020
 
Ireland – 2019 And 2020 Compared In Data
Ireland – 2019 And 2020 Compared In DataIreland – 2019 And 2020 Compared In Data
Ireland – 2019 And 2020 Compared In Data
 
Critical Review of Open Group IT4IT Reference Architecture
Critical Review of Open Group IT4IT Reference ArchitectureCritical Review of Open Group IT4IT Reference Architecture
Critical Review of Open Group IT4IT Reference Architecture
 
Analysis of Possible Excess COVID-19 Deaths in Ireland From Jan 2020 to Jun 2020
Analysis of Possible Excess COVID-19 Deaths in Ireland From Jan 2020 to Jun 2020Analysis of Possible Excess COVID-19 Deaths in Ireland From Jan 2020 to Jun 2020
Analysis of Possible Excess COVID-19 Deaths in Ireland From Jan 2020 to Jun 2020
 
Agile Solution Architecture and Design
Agile Solution Architecture and DesignAgile Solution Architecture and Design
Agile Solution Architecture and Design
 
Solution Architecture and Solution Acquisition
Solution Architecture and Solution AcquisitionSolution Architecture and Solution Acquisition
Solution Architecture and Solution Acquisition
 

Dernier

Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckHajeJanKamps
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Kirill Klimov
 
Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMVoces Mineras
 
APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfRbc Rbcua
 
International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...ssuserf63bd7
 
PB Project 1: Exploring Your Personal Brand
PB Project 1: Exploring Your Personal BrandPB Project 1: Exploring Your Personal Brand
PB Project 1: Exploring Your Personal BrandSharisaBethune
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03DallasHaselhorst
 
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdfNewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdfKhaled Al Awadi
 
Financial-Statement-Analysis-of-Coca-cola-Company.pptx
Financial-Statement-Analysis-of-Coca-cola-Company.pptxFinancial-Statement-Analysis-of-Coca-cola-Company.pptx
Financial-Statement-Analysis-of-Coca-cola-Company.pptxsaniyaimamuddin
 
Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Americas Got Grants
 
MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?Olivia Kresic
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Anamaria Contreras
 
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxmbikashkanyari
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Seta Wicaksana
 
Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Riya Pathan
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCRashishs7044
 

Dernier (20)

Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024
 
Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQM
 
APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdf
 
Call Us ➥9319373153▻Call Girls In North Goa
Call Us ➥9319373153▻Call Girls In North GoaCall Us ➥9319373153▻Call Girls In North Goa
Call Us ➥9319373153▻Call Girls In North Goa
 
International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...
 
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCREnjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
 
No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...
No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...
No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...
 
PB Project 1: Exploring Your Personal Brand
PB Project 1: Exploring Your Personal BrandPB Project 1: Exploring Your Personal Brand
PB Project 1: Exploring Your Personal Brand
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03
 
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdfNewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
 
Financial-Statement-Analysis-of-Coca-cola-Company.pptx
Financial-Statement-Analysis-of-Coca-cola-Company.pptxFinancial-Statement-Analysis-of-Coca-cola-Company.pptx
Financial-Statement-Analysis-of-Coca-cola-Company.pptx
 
Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...
 
MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.
 
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
 
Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...
 
Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
 

Capital Planning And Investment Management And Control In Information Technology

  • 1. Capital Planning and Investment Management and Control in Information Technology Alan McSweeney
  • 2. Objectives • To provide information on a structured approach to Capital Planning and Investment Control in Information Technology February 3, 2010 2
  • 3. Agenda • Capital Planning and Investment Control in Information Technology (CPIC-IT) • IT Investment Management (ITIM) • Cost Estimation • Cost Assessment Team • IT Investment Management Maturity February 3, 2010 3
  • 4. Capital Planning and Investment Control (CPIC-IT) • CPIC-IT is a systematic process logical IT investments in new systems and maintaining and operating existing systems • CPIC-IT is a process for effective decision-making that ensures IT investments integrate strategic planning, budgeting, procurement, and the management of IT in support of organisation needs − Determines if a given investment in IT is justified − Ensures IT investment decisions support the needs of the organisation, minmise risks and maximise returns throughout the investment lifecycle • CPIC-IT is a structured process for managing the risks and returns associated with IT investments • CPIC-IT is designed to ensure that IT investments are implemented at acceptable costs, within reasonable and expected timeframes, and contribute to tangible, observable improvements in organisation performance February 3, 2010 4
  • 5. IT Investment Issues • IT is a key enabler of organisational strategy • Many organisations do not know exactly how much is spent on IT • Many organisations cannot accurately characterise IT assets • In many organisations, IT accounts for 50% or more of capital expenditure • IT architecture is perceived as not providing the adaptability that is needed • IT is seen as a friction point for change and not enough of an enabler • Organisations must implement processes for managing IT investment both for the value they deliver as well as their cost • There has been significant waste of IT investments and unused IT systems due to lack of investment validation − Over 80% of projects do not come close to their original goals of lifecycle costs − More expensive to implement and/or operate than initially stated February 3, 2010 5
  • 6. Questions on IT Investments • Is your organisation’s IT portfolio a manifestation of your organisation’s mission and strategy? • Can you identify which IT projects are interdependent with adjacent people and process initiatives? • Do you have a rigorous IT investment selection process that is devoid of emotion and politics? • Do you account for multiple risk categories - technical, business, project, customer - when evaluating investment proposals? • Is IT operating expense in line with organisation growth? • Can you identify which IT investments contribute to true competitive advantage or mission achievement? • Do IT investment decision making methods mesh with the decision making framework of organisation? February 3, 2010 6
  • 7. What the Business Wants From IT • Business Requirement • Corresponding IT Function Maintain the Deliver IT services momentum of the consistently without business through fuss existing business systems Get involved in Contribute to business improving business improvement results Provide the business Provide IT direction with appropriate and management information and that is aligned to the technology leadership needs of the business February 3, 2010 7
  • 8. Disconnect Between What the Business Wants and What IT Delivers What the Business Wants What the Business Gets 15% 5% 35% 25% 70% 50% Maintain The Momentum Of The Business Through Maintain The Momentum Of The Business Through Existing Business Systems Existing Business Systems Contribute To Improving Business Results Contribute To Improving Business Results Provide It Direction And Management That Is Aligned To Provide It Direction And Management That Is Aligned To The Needs Of The Business The Needs Of The Business February 3, 2010 8
  • 9. IT Value Management is a Key Topic for IT Do Not Measure Business Value From IT 40% Investments Metrics Do Not Adequately Capture Business 45% Value Executives Skeptical Of ROI From IT 52% Find It Difficult To Calculate ROI 62% CEO/CFO Demanding Better Ways To 71% Demonstrate Value 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% • Results of managing IT for business value − Budget flexibility coupled with strategic IT alignment leads to 50% greater IT payoffs − Improving management practices alongside IT investment drives 20% higher IT yields February 3, 2010 9
  • 10. Core Elements of IT Value Management Managing IT Like a Managing Business the IT Budget Managing the IT Managing IT for Capability Business Value • An effective approach to Capital Planning and Investment Control is an essential component of IT Value Management February 3, 2010 10
  • 11. IT Investment Core Requirements • Determine the scale, scope, and sources of funding for IT • Assign financial resources to competing activities within the IT portfolio • Establish a balance between capital expenditure (new projects) and operating expenditure (running systems delivered by past projects) • Optimise the total cost of ownership • Manage IT portfolios for value and not just cost • IT needs to implement a process for justifying its costs and be seen to be taking these steps February 3, 2010 11
  • 12. W5H • Who - Who makes the decisions? • Why - Why is the funding sought, how is it aligned to the needs of the business and what benefits are anticipated? • What - Precisely what IT initiatives and business initiatives are to be funded? • When - When is the funding required and when are benefits expected to flow? • Where - From which source is the funding to be derived? • How - How are funding decisions to be made? February 3, 2010 12
  • 13. IT Investment Management • Aligns IT Investments to organisation strategy (scoring) • Prioritises investments (ranking) • Provides strategic criteria for investment analysis • Conduct annual IT portfolio management reviews • Provides recommendation to stop, slow, maintain or accelerate program funding • Identifies redundant/inefficient systems • Integrates IT architectures within investments • Ensures compliance with funding standards February 3, 2010 13
  • 14. Characteristics of Credible Cost Estimates • Clear identification of requirements of the ultimate deliverable • Broad participation in preparing estimates • Availability of valid data for performing estimates – historical, experience, benchmarks • Standardised and comprehensive estimate structure that includes all possible sources of cost • Provision for uncertainties – include known costs explicitly and allow for unknown costs • Recognition of inflation • Recognition of excluded costs • Independent review of estimates for completeness and realism • Revision of estimates for significant changes in requirements February 3, 2010 14
  • 15. Challenges of Developing Good Cost Estimates • Requires detailed, stable, agreed requirements • Agreed assumptions • Access to detailed documentation and historical data for comparison • Trained and experienced analysts • Risk and uncertainty analysis • Identification of a range of confidence levels • Adequate contingency and management reserves February 3, 2010 15
  • 16. Reasons for Good and Bad Cost Estimates Ineffe and U ctive Risk Effect ncer i ve Unce Risk and Unfa Analy tainty r ta Techn miliar s is Ident ificat Analy inty First- ology or s is Rang ion of a Time Use Probl em Confi e of De Acces s Getting dence Level Docu tailed s to D m ata Unre s and H entation Unre Proje asonable Adeq ua istor Train Unre alistic or ct Bas Conti ngen te Data ical e Exper d and liable Data Unre elin e Mana cy an ien geme d Detai led, S Analy ced Assumalistic Reser nt sts No o ption ves Agree table, Comp r Limited s Overo Requ d ariso ptimi ireme Agr Avail n Data sm n ts Assum eed able New ption Pr ocess s e s Untra Proje Inexp ined and ct Ins er ie t abilit y Comp Analy nced le sts or Te x Project chnol Unre ogy alistic Savin Project gs • Lost of reasons for and causes of inaccurate cost estimates February 3, 2010 16
  • 17. Sources of Risk and Uncertainty in Estimating Costs • Lack of understanding of the project requirements • Shortcomings of human language and differing interpretations of meaning of project • Behaviour of parties involved in the cost estimation process • Haste • Deception • Poor cost estimating and pricing practices February 3, 2010 17
  • 18. Specific Risks • Sizing and Technology • Capability − Overly optimistic developers − Mixed skills of team − Poor assumptions on the use of reused − Optimistic assumption on code development tools − Vague or incomplete requirements − Optimistic assumption on productivity − Not planning for additional effort − Geographically dispersed team making associated with packages – communication and coordination more integration, testing difficult • Complexity • Management − Tools − Management’s dictating an unrealistic − Applications: software purpose and schedule reliability − Incorporating a new method, − Hardware limitations language, tool or process for the first − Number of modules affecting time integration effort − Not handling creeping requirements and change proactively − Inadequate quality control, causing delays in fixing unexpected defects − Unanticipated risks associated with package software upgrades and lack of support February 3, 2010 18
  • 19. Importance of System Requirements and Solution Lifecycle Costs • System requirements drive costs, both implementation and operation • A factor present in every successful project and absent in every unsuccessful project is sufficient attention to requirements • Half of all bugs can be traced to requirement errors • Fixing these errors consumes 75% of project rework costs • 25%- 40% percent of all spending on projects is wasted as a result of re-work • 66% of software projects do not finish on time or on budget • 56% of project defects originate in the requirements phase of the project • Completed projects have only 52% of proposed functionality • 75-80% of IT project failures are the result of requirements problems • The average project exceeds its planned schedule by 120% • 53% of projects will cost 189% of their original estimate • 30% of projects are cancelled before completion • 50% of projects are rolled back out of production • The typical project expends least effort on analysis where most errors originate and whose errors cost most to fix • Requirements errors cost the most and that poor requirements are the main cause of project failure February 3, 2010 19
  • 20. Requirements Drive Project Costs 100.0% • While minimal 90.0% costs have actually been 80.0% spent at the Costs Committed and Spent requirements 70.0% phase of the entire project 60.0% process, 50.0% Development and approximately Implementation Starts 80% or more of 40.0% total life cycle Design Finalised costs have 30.0% Requirements Defined already been 20.0% and Agreed determined at this stage 10.0% • Need to get 0.0% requirements right from the Project Timescale outset to control costs effectively Costs Determined by Decisions on Requirements and Design Actual Money Spent February 3, 2010 20
  • 21. Aligning the Solutions Being Delivered • Need more than project management − Not the complete picture − Cannot treat project management in isolation • Need to ensure that the solution being managed meets business requirements • Need to ensure business requirements are captured • Need to ensure that solutions are designed to deliver business requirements and comply with organisation’s enterprise architecture • Getting requirements right is essential for effective IT investment management • Fundamentally the project exists to manage the delivery of the solution that has been designed to meet business requirements that assist with delivery of the business plan February 3, 2010 21
  • 22. Complete Picture of Project Selection and Delivery • Need to consider all aspects of project selection and delivery: − What the business wants (requirements) − What the business gets (solution that delivers on requirements) − Delivered according to business priority (project portfolio management) − Implemented properly (project management) • Cannot take an individual view without risking problems • Need to emphasise the importance of the solution whole lifecycle and the interdependence of the roles February 3, 2010 22
  • 23. Lessons Learned From Large Systems Implementation 80 % More attention on process optimisation 65 % Align systematically to company goals 60 % Pay more attention to understanding the subject area spanned 55 % Implementation of a management information system as part of scope 50 % Outsource project management of the project to a third party 45 % Increase investment in training 35 % Greater employees involvement 35 % Enforce changes more courageously 30 % Identify and capture proof of benefits and saving as part of scope 20 % Avoid big-bang implementations February 3, 2010 23
  • 24. Types of Cost Estimates • Life Cycle Cost Estimate (LCCE) - includes independent cost estimates, independent cost assessments and total ownership costs − Encompasses all past (or sunk), present and future costs for every aspect of the program, regardless of funding source • Business Case Analysis (BCA) - includes an analysis of alternatives and/or economic analyses − Cost benefit or comparative analysis that presents facts and supporting details among competing alternatives − Includes life-cycle costs from LCCE and also quantifiable and unquantifiable benefits • Rough Order of Magnitude (ROM ) - developed when a quick estimate is needed and few details are available − Usually based on historical ratio information − Typically developed to support what-if analyses − Helpful for examining differences in high-level alternative see which are the most feasible − A rough order of analysis should never be considered a budget-quality cost estimate February 3, 2010 24
  • 25. Life Cycle Cost Estimate (LCCE) Composition LIFE CYCLE COST SYSTEM ACQUISITION COST •Operations PROCUREMENT COST •Internal Support •Planning, Research, •Disposal TOTAL SYSTEM COST •External Support and Analysis and Design Maintenance •Ongoing Test BASIC SYSTEM COST •Training •Subscription Facilities •Documentation •Hardware •Support Facilities •Software •Parallel Running •Development and •Warranty Implementation •Management •Installation •Transition and Cutover •Conversion February 3, 2010 25
  • 26. LCCE Cost Composition Total Cost of Ownership System Acquisition Cost Operating and Support Cost COST YEARS • Depending on the life of the solution being implemented, the operating costs can be 1-3 times the cost of acquisition February 3, 2010 26
  • 27. IT Investment Management and Project and Solution Lifecycle Structured Capture and Management of Cost Effective Requirements and Operation of Business Analysis Cost Benefit Analysis Delivered Solution of Solution Costs and Effective Solution Retirement/ Operation Replacement/ Upgrade Decisions Design/Selection of Cost Effective Solution Solutions to Meet Architecture and Requirements Cost Effective Design Including Delivery of Evaluation of All Programme and Projects and Options Project Management of Management Costs Project Portfolio Prioritisation of Management Projects and Investment Decisions February 3, 2010 27
  • 28. Benefits of Effective IT Investment Management Framework • Aligns investments to business goals and objectives • Identifies and track spending on IT investments • Controls and monitor IT investment projects • Confirms that IT investments are meeting business objectives • Leverages IT investment opportunities that may generate internal capital • Make informed decisions on an IT investment portfolio by assessing value and risk • Demonstrates that IT can be trusted to invest wisely February 3, 2010 28
  • 29. IT Investment Management Framework Business Plans Organisation and Associated What Proposed IT Technology Strategic Plan Needs Investments Potentially Solve the Identified Business Needs? Pre-Selection and Identification Investment Stage Results Did the Selected Which IT IT Investments Investments Deliver the Evaluation Stage Technology and Selection Stage Best Meet the Expected Systems Portfolio Business Business Value? Needs? Control Stage Are the Selected IT Investments Performing as Planned? February 3, 2010 29
  • 30. IT Investment Management Stages Pre-Selection and Identification Selection Stage Stage Identify business needs and prioritise potential Evaluate, score, and rank IT investments investments Prioritise IT projects Develop investment business cases Research possible enterprise/collaboration opportunities Update the Strategic plan and technology Portfolio Evaluation Stage Control Stage Conduct post implementation reviews on major IT projects Translate business value into performance measures using the asset performance measures established in the Develop detailed project plans and execute projects in Control Phase accordance with project management standards Use asset performance measures to measure the business Develop applications in accordance with technical and value data standards for information technology Document IT asset performance Submit project status reports, requests for baseline Analyse gaps between current business needs and adjustments greater than defined percentage (typically performance of IT assets 10%) and verification and validation reports for each Make a determination to maintain, migrate, improve, or major IT project retire each IT asset in the technology portfolio February 3, 2010 30
  • 31. IT Investment Management Control Function Responsibilities Technical Scope Management Technical Portfolio Management Requirements Management IT Investment Management Control Function Progress Earned Value Reporting and Management Management Scope, Cost and Risk Schedule Management Management February 3, 2010 31
  • 32. Portfolio Management • Portfolio Management is an approach typically combined with a set of tools for identifying, diagnosing, controlling, and increasing the aggregate return on investments at a given level of risk tolerance • Based on the management principle that any set of investments requires proactive management to maximise value while minimising risk • IT portfolio management takes advantage of an integrated set of IT management processes, techniques, and tools that assist decision makers in analysing, selecting, evaluating, and controlling an optimal set of investments • Properly executed IT portfolio management delivers the benefits of balancing supply and demand of IT resources (financial and non- financial), eliminating redundancy, and enabling better alignment with strategic goals February 3, 2010 32
  • 33. Earned Value Management • Earned Value Management (EVM) is a project management metric that integrates the technical scope of work with schedule and cost elements for investment planning and control • Compares the value of work accomplished in a given period with the value of the work expected in that period • Differences in expectations are measured in both cost and schedule variances • Use EVM in performance-based management systems • Management of a cost estimate involves continually updating the estimate with actual data as they become available (EVM) revising the estimate to reflect changes and analysing differences between estimated and actual costs February 3, 2010 33
  • 34. Cost Estimation Best Practices Checklist • The cost estimate type is clearly defined and is appropriate for its purpose • All applicable program costs have been estimated, including all life-cycle costs • The cost estimate is independent of funding source • An affordability analysis has been performed at the agency level to see how the project fits within the overall portfolio • The estimate is updated as actual costs become available from the EVM system or as requirements change • Post mortems and lessons learned exercises are continually documented as information becomes available February 3, 2010 34
  • 35. Cost Estimating Process Initiation and Research Step 1: Step 2: Define the Develop the The audience, what is Purpose of Estimating being estimated and why the Estimate Plan It is being estimated are very importance Assessment Step 3: Step 4: Step 5: Step 6: Step 7: Define the Determine Identify Obtain Data Develop Cost assessment steps Project the Ground Point are iterative and can be Estimating Rules and Estimate accomplished in varying Approach Assumptions order or concurrently Analysis Step 8: Step 9: Step 10: Conduct Conduct Risk Document The confidence in the Sensitivity and the Estimate point or range of the Analysis Uncertainty estimate is crucial to the Analysis decision maker Presentation Step 11: Step 12: Present Update Documentation and Estimate for Estimate to presentation can make or Approval Reflect break a cost estimating Actual Costs decision outcome and Changes February 3, 2010 35
  • 36. Cost Estimating Process • Each of the 12 steps is important for ensuring that high- quality cost estimates are developed and delivered in time to support important decisions February 3, 2010 36
  • 37. Cost Estimating Process • Step 1: Define the Purpose of the Estimate − Determine the estimate’s purpose − Determine the level of detail required − Determine who will receive the estimate − Determine the overall scope of the estimate • Step 2: Develop the Estimating Plan − Determine the cost estimating team − Outline the cost estimating approach − Develop the estimate timeline − Determine who will do the independent cost estimate − Develop the schedule February 3, 2010 37
  • 38. Cost Estimating Process • Step 3: Define the Project − Identify in a technical baseline description document − The purpose of the project − Its system and performance characteristics − Any technology implications − All system configurations − project acquisition schedule − Acquisition strategy; − Relationship to other existing systems − Support (manpower, training, etc.) and security needs − Risks − Assumptions − System quantities for development, test, and production − Deployment and maintenance plans; − Predecessor or similar legacy systems • Step 4: Determine the Estimating Approach − Define work breakdown structure (WBS) and describe each element − Choose the estimating method best suited for each WBS element − Identify potential cross-checks for likely cost and schedule drivers. − Develop a cost estimating checklist February 3, 2010 38
  • 39. Cost Estimating Process • Step 5: Identify Ground Rules and Assumptions − Clearly define what is included and excluded from the estimate − Identify global and program specific assumptions such as: • The estimate’s timescale, including time-phasing and life cycle • Program schedule information by phase • Program acquisition strategy • Any schedule or budget constraints • Inflation assumptions • Costs such as travel and other expenses • Equipment the organisation is to furnish • Prime contractor and major subcontractors • Use of existing facilities or new modifications or developments • Technology refresh cycles • Technology assumptions and new technology to be developed • Commonality with legacy systems and assumed heritage savings • Effects of new ways of doing business • Step 6: Obtain Data − Create a data collection plan with emphasis on collecting current and relevant technical, programmatic, cost, and risk data. − Investigate possible data sources − Collect data and normalise them for cost accounting, inflation, learning, and quantity adjustments − Analyse the data to look for cost drivers, trends, and outliers compare results against rules of thumb and standard factors derived from historical data − Interview data sources and document all relevant information including an assessment of data reliability and accuracy February 3, 2010 39
  • 40. Cost Estimating Process • Step 7: Develop Point Estimate − Develop the cost model by estimating each WBS element, using the best methodology from the data collected − Include all estimating assumptions in the cost model − Express costs in constant year currency − Time-phase the results by spreading costs in the years they are expected to occur, based on the pro gram schedule − Sum the WBS elements to develop the overall point estimate − Validate the estimate by looking for errors like double counting and omitting costs − Compare estimate against the independent cost estimate and examine w here and why there are differences − Perform cross-checks on cost drivers to see if results are similar − Update the model as more data become available or as changes occur and compare results against previous estimates • Step 8: Conduct Sensitivity Analysis − Test the sensitivity of cost elements to changes in estimating input values and key assumptions − Identify effects of changing the program schedule or quantities on the overall estimate − Determine which assumptions are key cost drivers and which cost elements are affected most by changes February 3, 2010 40
  • 41. Cost Estimating Process • Step 9: Conduct Risk and Uncertainty Analysis − Determine the level of cost, schedule, and technical risk associated with each WBS element and discuss with technical experts − Analyse each risk for its severity and probability of occurrence − Develop minimum, most likely, and maximum ranges for each element of risk − Use an acceptable statistical analysis methodology to develop a confidence interval around the point estimate − Determine type of risk distributions and reason for their use − Identify the confidence level of the point estimate − Identify the amount of contingency funding and add this to the point estimate to determine the risk-adjusted cost estimate − Recommend that the project office develop a risk management plan to track and mitigate risks • Step 10: Document the Estimate − Document all steps used to develop the estimate so that it can be recreated quickly by a cost analyst unfamiliar with the program and produce the same result − Document the purpose of the estimate, the team that prepared it, and who approved the estimate and on what date − Describe the program, including the schedule and technical baseline used to create the estimate − Present the time-phased life-cycle cost of the program − Discuss all ground rules and assumptions − Include auditable and traceable data sources for each cost element − Document for all data sources how the data were normalised − Describe the results of the risk, uncertainty, and sensitivity analyses and whether any contingency funds were identified − Document how the estimate compares to the funding profile − Track how this estimate compares to previous estimates, if applicable February 3, 2010 41
  • 42. Cost Estimating Process • Step 11: Present Estimate for Approval − Develop a briefing that presents the documented life-cycle cost estimate for management approval, including • An explanation of the technical and programmatic baseline and any uncertainties; • A comparison to an independent cost estimate (ICE) with explanations of any differences; • A comparison of the estimate (life-cycle cost estimate (LCCE) or independent cost estimate to the budget; and • Enough detail so the presenter can easily defend the estimate by showing how it is accurate, complete, and high in quality. − Focus the briefing, in a logical manner, on the largest cost elements and drivers of cost − Make the content concise and complete so that those who are unfamiliar with it can easily comprehend the competence that underlies the estimate results − Make backup slides available for more probing questions − Act on and document feedback from management − The cost estimating team should request acceptance of the estimate • Step 12: Update Estimate to Reflect Actual Costs and Changes − Update the estimate to • Reflect any changes in technical or program assumptions • Keep it current as the program passes through new phases − Replace estimates with EVM EAC and Independent estimate at completion (EAC) from EVM − Report progress on meeting cost and schedule estimates − Perform a post mortem and document lessons learned for elements whose actual costs or schedules differ from the estimate. − Document all changes to the program and how they affect the cost estimate February 3, 2010 42
  • 43. Work Breakdown Structure • Cornerstone of every project because it defines in detail the work necessary to accomplish a project’s objectives − Essential part of developing a project’s cost estimate − WBS reflects the delivery of the agreed requirements to the agreed solution design • A typical WBS reflects the requirements, resources and tasks that must be accomplished to develop a program • WBS communicates to everyone what needs to be done and how the activities relate to one another • Provides a consistent framework for planning and assigning responsibility for the work • Define a project in terms of product-oriented elements, broken into a hierarchical structure • Product-oriented WBS ensures that all costs are captured February 3, 2010 43
  • 44. Validating Cost Estimates • Cost estimates should be validated against best practice characteristics − Comprehensive − Well-documented − Accurate − Credible February 3, 2010 44
  • 45. Validating Cost Estimates • Comprehensive − Completely define the program and reflect the current schedule − Include all possible costs using a logical WBS that accounts for all requirements − Ensure that no costs are omitted nor double-counted − Explain and document key assumptions that are technically reasonable • Well-documented − They can be easily repeated or updated and traced to original sources through auditing − Supporting documentation identifies the data sources, justifies all assumptions, and provides a description of each estimating methodology for every WBS cost element − Schedule milestones and deliverables are traceable and consistent with the cost estimate documentation February 3, 2010 45
  • 46. Validating Cost Estimates • Accurate − They are not overly conservative or too optimistic − Based on an assessment of most likely costs and adjusted properly for inflation − Contain few, if any, mistakes that are minor in nature − Are updated when assumptions or requirements change to reflect current status − Cost estimating relationships and parametric cost models are validated to ensure they are good predictors of costs • Data is current and applicable to the new program, • The relationships between technical parameters are logical and statistically significant • Results are tested with independent data • Credible − They clearly identify any limitations because of uncertainty or biases surrounding the data or assumptions − Results are similar to cross-checks and an independent cost estimate derived using different methodologies • Independent cost estimates performed by estimators farthest away from the acquiring program office represent a best practices because they − Tend to produce higher and more accurate cost estimates than those performed by staff sharing a common supervisor with the program office − Produce more credible estimates than other types of independent estimate reviews which may not be as inclusive as an ICE (e.g., IGCE, ICA, Sufficiency Review, etc.) − A sensitivity analysis has been performed to identify cost drivers and the impacts of varying assumptions − A risk / uncertainty analysis has been performed to determine the level of risk associated with the point estimate February 3, 2010 46
  • 47. Cost Assessment Team • Cost estimates are frequently developed with an incomplete knowledge of what the exact final technical solution will be • Cost assessment team must manage a great deal of risk, especially for programs that are complex or use leading edge of technology • Cost estimates define what a given solution will ultimately cost • Estimate will be affected by multiple assumptions and an interpretation of what the historical data represent February 3, 2010 47
  • 48. Disciplines and Concepts in Cost Analysis Economics Interpersonal •Break-even Analysis Skills •Personnel Cost •Approach •Inflation •Estimate •Present Value •Knowledge Analysis Budgeting Commercial •Organisation •Analysis of Specific Skills Commercial Models •Program Specific Cost Analysis •Analysis of Skills Team Skills Proposals •Development of Cost Estimating Relationship Information Statistics Accounting Technology •Forecasting •Cost Data Analysis •Analysis •Risk/Uncertainty •Financial Analysis •Design Analysis •Overhead Analysis •Development •Proposal Analysis •Testing •Scheduling •System Integration February 3, 2010 48
  • 49. Centralised vs. Decentralised Costing Function • Centralised Costing Function • Decentralised Costing Function − Facilitates the use of standardised − Often results in ad hoc and and consistent processes inconsistent processes − Better resource sharing − Decreased independence − Common tools and training − Greater access to local technical − Ability to resist pressure to lower resources the cost estimate when it is higher than the allotted budget − Can be remote from technical experts February 3, 2010 49
  • 50. Cost Assessment Team Best Practices Checklist • The estimating team’s composition has the skills needed for the program of work − The team has the proper number and mix of resources − The team has the proper number and mix of resources − The team includes experienced and trained cost analysts − The team includes, or has direct access to, analysts experienced in the program’s major areas − Team members’ experience, qualifications, certifications, and training are identified • A master schedule with a written study plan has been developed • The team has access to the necessary subject matter experts February 3, 2010 50
  • 51. IT Investment Management Maturity Stages Description The organisation has mastered the selection, control, and evaluation Leveraging IT for processes and now seeks to shape its strategic outcomes by 5 Strategic Outcomes benchmarking its IT investment processes relative to other "best-in-class" organizations. The organisation is focused on evaluation techniques to improve its IT Improving the 4 Investment Process investment processes and portfolio(s), while maintaining mature selection and control techniques. The organisation has developed a well-defined IT investment portfolio Developing a Complete using an investment process that has sound selection criteria and 3 Investment Portfolio maintains mature, evolving, and integrated selection, control, and evaluation processes. Basic selection capabilities are being driven by the development of project Building the Investment selection criteria, including benefit and risk criteria, and an awareness of 2 Foundation organizational priorities when identifying projects for funding. Executive oversight is applied on a project-by-project basis. Ad hoc, unstructured, and unpredictable investment processes Creating Investment characterise this stage. There is generally little relationship between the 1 Awareness success or failure of one project and the success or failure of another project. February 3, 2010 51
  • 52. Increasing IT Investment Management Maturity 5 Leveraging IT for Strategic Outcomes 1. The organisation learns from and adopts the tools, techniques, or methods used by best-in-class external 4 Improving the organisations 2. Changes to strategic business processes are driven by the Investment Process capabilities of identified information technologies 1. Evaluation techniques are being used to improve the 3 Developing a Complete investment processes and the portfolio Investment Portfolio 2. Succession management processes are developed for retaining or disposing of investments. 1. Criteria are developed for identifying investments that best fit with the portfolio. 2. The portfolio is developed through the use of 2 Building the Investment categorisation when comparing investments. Foundation 3. Performance reviews are conducted both during and after implementation 1. An investment board is established to drive the investment process 1 Creating Investment 2. Business needs are identified for each project Awareness 3. An investment selection process is developed 4. Board oversees the progress of individual projects 5. Investment information is collected and disseminated February 3, 2010 52
  • 53. More Information Alan McSweeney alan@alanmcsweeney.com February 3, 2010 53