ANALYSIS OF RATES 
• To determine the rate of a particular item 
of work from a quantities of materials and 
labours required and their costs 
• The rates of materials and labour are 
changing from place to place, therefore the 
rates o different items of work also 
changes from place to place
ANALYSIS OF RATES 
• Every Estimate should be accompanied 
by the analysis of rates of the items 
provided in it . 
• Analysis of rates comprises of 
1. Cost of Material 
2. Cost of Labour 
3. T and P , and Sundries 
4. Carriage 
5. Contractor’s Profit
ANALYSIS OF RATES 
• Tools and Plants ( T & P ) = 2.5 to 3 % of 
the labour cost 
• Transportation cost more than 8 km is 
considered 
• Water charges = 1.5 to 2 % 0f total cost 
• Contractor ‘ s profit = 10 %
ANALYSIS OF RATES 
• Rates of Materials and Labours : 
• 1st class bricks = Rs 4500 per 1000 Nos. 
• 2nd class bricks = Rs 4000 per 1000 Nos. 
• Brick Ballast = Rs 800 per cum 
• Coarse sand = Rs 800 per cum 
• Cement 50 kg bag = Rs 270 per bag 
• Twisted bars = Rs 5000 per Quintel 
• Bitumen = Rs 10 per kg
ANALYSIS OF RATES 
• Mason = Rs 450 per day 
• Plaster = Rs 400 per day 
• Carpenter = Rs 400 per day 
• Bhishti = Rs 250 per day 
• Mazdoor = Rs 250 per day 
• Painter = Rs 300 per day
ANALYSIS OF RATES 
• Earth work in excavation: Mazdoor = 33 
(% cum) Mason = 1.5 
• Earth work in Filling : Mazdoor = 18 
(% cum) Mason = 0.5 
• Cement concrete : Mazdoor = 15 
in foundation Mason =1.5 
Bhishti = 2
ANALYSIS OF RATES 
• Cement concrete : Mazdoor = 15 
Mason = 1 
Bhishti = 2.5 
• R. Cement concrete : Mazdoor = 40 
(10 cum ) Mason = 2.5 
Bhishti = 5 
Blacksmith = 4 
Carpenter = 4
ANALYSIS OF RATES 
• DPC : Mazdoor = 2.5 
(10 cum ) Mason = 1.5 
Bhishti = 0.5 
• 1st class brick work : Mazdoor = 15 
Mason = 8 
Bhishti = 2
ANALYSIS OF RATES 
• Plastering work : Mazdoor = 10 
( 100 sqm) Mason = 10 
Bhishti = 2 
• Distempering/painting/white washing : 
Mazdoor = 5 
( 100 sqm) Painter = 4
ANALYSIS OF RATES 
Example 1. Find out dry materials required 
for 1 cu m. C. concrete 1:4:8 in foundation. 
Solution. 
Ratio = 1:4:8 (cement,sand and aggregate) 
Sum = 1+4+8=13 
cont..
Total dry mortar for 1 cu m cement concrete 
=1.54 cu m 
Therefore the following materials are 
required: 
Cement = (1*1.54*28.8)/13 
= 3.41 bags 
Sand = (4*1.54)/13 
= 0.47 cu m 
cont..
Aggregate (Brick ballast) = (8*1.57)/13 
= 0.94 cu m 
so materials for 1 cu m cement concrete 
1:4:8. 
Cement 3.41 bags 
Sand 0.47 cu m Ans. 
Brick ballast 0.94 cu m
Example 2. Find out dry materials for 1 
cu m lime concrete. 
Solution: 
Ratio = 1:2 (lime,surkhi) 
Sum = 1+2 
= 3 
Total dry mortar for 1 cu m lime concrete 
= 0.40 (lime, surkhi mortar)
Therefore the following materials are 
required. 
Lime = (1*0.40)/3 
= 0.13 cu m 
Surkhi = (2*0.40)/3 
= 0.27 cu m 
Aggregate (brick ballast) = 1.00 cu m
Materials required for1 cu m lime cocrete 1:2 
Lime 0.13 cu m 
Surkhi 0.27 cu m Ans. 
Brick ballast 1.00 cu m
ANALYSIS OF RATES OF 
DIFFERENT ITEMS OF 
WORK. 
1. Excavation for foundation: payment 
% cu m 
(a)Materials at the site for % cu m nil 
No material is required Rs. P. 
(b)labour for % cu m 
Mazdoor 33 nos.@ 250.00/day = 8250.00
Mason 1 no. @ 450.00 = 450.00 
Sundries and Tand P 3% 
on labour = 261.00 
Total = 8961.00 
(c)Add 10% contractor’s profit = 896.10 
grand total =9857.10 
say Rs. = 9857.00 
Rate per % cu m = Rs. 9857.00
2.Earth filling under floors payment % cu m 
(a)Materials at site for %cu m Rs.P. 
No material is required nil 
(b) Labour for % cu m 
Majdoor18nos.@250.00/day =4500.00 
Bhishti 1/2no.@250.00/day = 125.00 
Sundries and Tand P3% on 
labour 465.00 = 123.75 
total = 4748.75 
Add 10% contractor’s profit = 474.87
G.Total= 5223.62 say Rs.=5224.00 
Rate per % cu m = Rs. 5224.00 
3. Cement concrete 1:4:8 in foundations 
(a) Materials at site for 1 cu m payment 
per cu m 
Cement 3.41 bags @270 bag = 929.70 
Sand 0.47 cu m @800.00 per cu m=376.00
Brick ballast 0.94 cu m @ 800.00 
= 752.00 
Cost of labour for 10 cu m = 7520.00 
(b)Labour for 10 cu m Rs. P 
Mason 1@ 400.00/ day = 400.00 
Mazdoors 15@ 250.00/ day = 3750.00 
Bhishti 2@ 250.oo/ day = 500.00 
Sundries and Tand P @ 3% 
on labour = 139.50
• Cost of for 10 cu m = 12309.50 
• Cost of for 1 cu m =12309.50/10 
• =1230.95 
• PROBLEM: Conglomerate floor 4 cm thick 
of cement concrete 1:2:4 over 10 cm thick 
cement concrete 1:6:18 over 10 cm sand 
filling.
calculation of material for 10 sq m 
(1) Wet mortar for cement concrete 
1:2:4= 10 sq m*4cm 
= 10*4/100 
=0.40cu m
Dry mortar = 0.40*1.54=0.616+0.62 cu m 
Ratio = 1:2:4 Sum =1+2+4=7 
Cement = 1*0.62*28.8/7 =2.55 bags 
Sand = 2*0.62/7 = 0.18 cu m
Crusher = 4*0.62/7=0.36 cu m 
(2)Wet mortar for cement concrete 1:6:18 
= 10 sq m*10 cm 
=10*10/100 
=1 cu m
Dry mortar 1*1.54 =1.54cu m 
Ratio =1:6:18=1+6+18 
= 25 
Cement = 1*1.54*28.8/25 
= 1.78 bags
Sand =6*1.54/25 
= 0.37 cu m 
Brick ballast = 18*1.54/2 
= 1.11 cu m 
(3) Sand for 10 sq m = 10 sq m* 10 cm 
= 10*10/10
= 1 cu m 
Total dry mortar for 10 sq m conglomerate 
flooring. 
Cement = 2.55+1.78 
Sand = 0.18+0.37+1.00 
Crusher = 0.46
(a) Materials at site for 10 sq m Rs.P 
Cement 4.33 bags @ 270.00/bag = 1170.00 
sand 1.55 cum@ 800.00 per cu m = 1240.00 
Crusher 0.36 cu m @1200 /cu m = 432.00 
Brick ballast 1.11 cu m@ 800 / cu m = 888.00
Cost of material for 10 sq m =3730.00 
(b) Labour for 10 sq m Rs. P 
Mason 2@ 400.00/ day = 900.00 
Mazdoor 3@ 250.00/day = 750.00 
Bhishti 1@ 250.00 / day = 250.00
Sundries T and P 3% on labour 
= 57.00 
Cost of labour for 10 sq m = 1957.00 
Cost of material and labour for 10 sq m 
=5687.00
Add 10% contractor’s profit = 
568.70 
and total = 6255.70 
Rate for 10 sq m = Rs.6256.00 
Rate per sq m = Rs.625.60

Contenu connexe

Tendances

Estimating and-costing book
Estimating and-costing bookEstimating and-costing book
Estimating and-costing bookThomas Britto
 
Specifications of buildings
Specifications of buildingsSpecifications of buildings
Specifications of buildingsSimarpreet Singh
 
Reinforced cement concrete
Reinforced cement concreteReinforced cement concrete
Reinforced cement concreteShourya Puri
 
Design of residential building
Design of residential buildingDesign of residential building
Design of residential buildingK.MAHESH KUMAR
 
5#rate analysis problems
5#rate analysis   problems5#rate analysis   problems
5#rate analysis problemsLIJI A
 
Self compacting concrete (scc)
Self compacting concrete (scc)Self compacting concrete (scc)
Self compacting concrete (scc)y Sahaja
 
Residential building construction ppt
Residential building construction pptResidential building construction ppt
Residential building construction pptBeing Deepak
 
Visit to a construction site
Visit to a construction siteVisit to a construction site
Visit to a construction siteUmair Ali
 
Admixture of concrete
Admixture of concreteAdmixture of concrete
Admixture of concreteLavanya Singh
 
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contractssrinivas2036
 
Building Construction 1: project 1
Building Construction 1: project 1Building Construction 1: project 1
Building Construction 1: project 1Nabeel Joomun
 
Concrete- types, testing & properties
Concrete- types, testing & propertiesConcrete- types, testing & properties
Concrete- types, testing & propertieslalitha moorthy
 
Construction equipments
Construction equipmentsConstruction equipments
Construction equipmentsAshish Parihar
 
Quality control of concrete
Quality control of concreteQuality control of concrete
Quality control of concreteGaurang Kakadiya
 
grouting and guniting
grouting and gunitinggrouting and guniting
grouting and gunitingVipul Kerni
 

Tendances (20)

Estimating and-costing book
Estimating and-costing bookEstimating and-costing book
Estimating and-costing book
 
Analysis of rates
Analysis of ratesAnalysis of rates
Analysis of rates
 
Specifications of buildings
Specifications of buildingsSpecifications of buildings
Specifications of buildings
 
Reinforced cement concrete
Reinforced cement concreteReinforced cement concrete
Reinforced cement concrete
 
Design of residential building
Design of residential buildingDesign of residential building
Design of residential building
 
5#rate analysis problems
5#rate analysis   problems5#rate analysis   problems
5#rate analysis problems
 
Types of formwork
Types of formworkTypes of formwork
Types of formwork
 
Self compacting concrete (scc)
Self compacting concrete (scc)Self compacting concrete (scc)
Self compacting concrete (scc)
 
Residential building construction ppt
Residential building construction pptResidential building construction ppt
Residential building construction ppt
 
Cracks in Buildings
Cracks in BuildingsCracks in Buildings
Cracks in Buildings
 
specification of Rcc
specification of Rccspecification of Rcc
specification of Rcc
 
Visit to a construction site
Visit to a construction siteVisit to a construction site
Visit to a construction site
 
Pile foundations
Pile foundationsPile foundations
Pile foundations
 
Admixture of concrete
Admixture of concreteAdmixture of concrete
Admixture of concrete
 
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contracts
 
Building Construction 1: project 1
Building Construction 1: project 1Building Construction 1: project 1
Building Construction 1: project 1
 
Concrete- types, testing & properties
Concrete- types, testing & propertiesConcrete- types, testing & properties
Concrete- types, testing & properties
 
Construction equipments
Construction equipmentsConstruction equipments
Construction equipments
 
Quality control of concrete
Quality control of concreteQuality control of concrete
Quality control of concrete
 
grouting and guniting
grouting and gunitinggrouting and guniting
grouting and guniting
 

En vedette

Estimation and costing
Estimation and costingEstimation and costing
Estimation and costingGanesh Murugan
 
estimation and quantity surveying
estimation and quantity surveyingestimation and quantity surveying
estimation and quantity surveyingsooricivil
 
Estimation and quantity surveying
Estimation and quantity surveyingEstimation and quantity surveying
Estimation and quantity surveyingAwanish Shukla
 
QUANTITY SURVEYING
QUANTITY SURVEYINGQUANTITY SURVEYING
QUANTITY SURVEYINGlizwi nyandu
 
Estimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction WorkEstimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction WorkDaniel Ross
 
General notes to BSR BUILDING SCHEDULE OF RATES
General notes to BSR BUILDING SCHEDULE OF RATESGeneral notes to BSR BUILDING SCHEDULE OF RATES
General notes to BSR BUILDING SCHEDULE OF RATESR.R.G.S Bandara
 
Industrial training @ sierra amjedh
Industrial training @ sierra amjedhIndustrial training @ sierra amjedh
Industrial training @ sierra amjedhAmjedh Haleel
 
Top 10 project quantity surveyor interview questions and answers
Top 10 project quantity surveyor interview questions and answersTop 10 project quantity surveyor interview questions and answers
Top 10 project quantity surveyor interview questions and answersmitchellparker911
 
ANALYSS OF RATES-VOLUME-I
ANALYSS OF RATES-VOLUME-IANALYSS OF RATES-VOLUME-I
ANALYSS OF RATES-VOLUME-IAlok Kumar
 
Estimation and costing of a commercial building
Estimation and costing of a commercial buildingEstimation and costing of a commercial building
Estimation and costing of a commercial buildinglckr117
 
Estimation of a residential building
Estimation of a residential buildingEstimation of a residential building
Estimation of a residential buildingVardhaman Sethia
 
Tender processing
Tender processingTender processing
Tender processingdnyandev_d
 
Tendering process, Bid Evaluation & Award Process
Tendering process, Bid Evaluation & Award ProcessTendering process, Bid Evaluation & Award Process
Tendering process, Bid Evaluation & Award ProcessPrateek Kashyap
 
Tendering in construction introduction
Tendering in construction introductionTendering in construction introduction
Tendering in construction introductionDaniel Ross
 
Building estimation methods
Building estimation methodsBuilding estimation methods
Building estimation methodsSimarpreet Singh
 
Tender evaluation procedure
Tender evaluation procedureTender evaluation procedure
Tender evaluation procedureayushida
 
Tender Process | A Complete Procurement Guide
Tender Process | A Complete Procurement GuideTender Process | A Complete Procurement Guide
Tender Process | A Complete Procurement GuideTender Process
 

En vedette (20)

Estimation and costing
Estimation and costingEstimation and costing
Estimation and costing
 
estimation and quantity surveying
estimation and quantity surveyingestimation and quantity surveying
estimation and quantity surveying
 
Estimation and quantity surveying
Estimation and quantity surveyingEstimation and quantity surveying
Estimation and quantity surveying
 
QUANTITY SURVEYING
QUANTITY SURVEYINGQUANTITY SURVEYING
QUANTITY SURVEYING
 
Estimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction WorkEstimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction Work
 
General notes to BSR BUILDING SCHEDULE OF RATES
General notes to BSR BUILDING SCHEDULE OF RATESGeneral notes to BSR BUILDING SCHEDULE OF RATES
General notes to BSR BUILDING SCHEDULE OF RATES
 
Industrial training @ sierra amjedh
Industrial training @ sierra amjedhIndustrial training @ sierra amjedh
Industrial training @ sierra amjedh
 
Top 10 project quantity surveyor interview questions and answers
Top 10 project quantity surveyor interview questions and answersTop 10 project quantity surveyor interview questions and answers
Top 10 project quantity surveyor interview questions and answers
 
ANALYSS OF RATES-VOLUME-I
ANALYSS OF RATES-VOLUME-IANALYSS OF RATES-VOLUME-I
ANALYSS OF RATES-VOLUME-I
 
Estimation and costing of a commercial building
Estimation and costing of a commercial buildingEstimation and costing of a commercial building
Estimation and costing of a commercial building
 
Tendering process cvc_guidelines
Tendering process cvc_guidelinesTendering process cvc_guidelines
Tendering process cvc_guidelines
 
Estimation of a residential building
Estimation of a residential buildingEstimation of a residential building
Estimation of a residential building
 
Tender processing
Tender processingTender processing
Tender processing
 
Tendering process, Bid Evaluation & Award Process
Tendering process, Bid Evaluation & Award ProcessTendering process, Bid Evaluation & Award Process
Tendering process, Bid Evaluation & Award Process
 
Tendering in construction introduction
Tendering in construction introductionTendering in construction introduction
Tendering in construction introduction
 
Building estimation methods
Building estimation methodsBuilding estimation methods
Building estimation methods
 
Tender evaluation procedure
Tender evaluation procedureTender evaluation procedure
Tender evaluation procedure
 
Tender procedure slide
Tender procedure slideTender procedure slide
Tender procedure slide
 
Tender
TenderTender
Tender
 
Tender Process | A Complete Procurement Guide
Tender Process | A Complete Procurement GuideTender Process | A Complete Procurement Guide
Tender Process | A Complete Procurement Guide
 

Similaire à Analyzing Rates of Construction Items

Ratesanalysis for Material and Labor
Ratesanalysis for Material and LaborRatesanalysis for Material and Labor
Ratesanalysis for Material and LaborNagoorkani Majeed
 
ANALYSIS_OF_RATES.ppt
ANALYSIS_OF_RATES.pptANALYSIS_OF_RATES.ppt
ANALYSIS_OF_RATES.pptRijuDasgupta
 
Estimation and costing pdf
Estimation and costing pdfEstimation and costing pdf
Estimation and costing pdfSaqib Imran
 
Quantity notes by engineer saqib imran
Quantity notes by engineer saqib imranQuantity notes by engineer saqib imran
Quantity notes by engineer saqib imranSaqib Imran
 
Quantity notes by engineer saqb imran
Quantity notes by engineer saqb imranQuantity notes by engineer saqb imran
Quantity notes by engineer saqb imranSaqib Imran
 
QUANTITY SURVEYING PORTFOLIO.pptx
QUANTITY SURVEYING PORTFOLIO.pptxQUANTITY SURVEYING PORTFOLIO.pptx
QUANTITY SURVEYING PORTFOLIO.pptxRajnishKumar916873
 
Bill of Quantity Tabulation
Bill of Quantity TabulationBill of Quantity Tabulation
Bill of Quantity TabulationLamaJassim1
 
2170610_PPV_GTU_Study_Material_Presentations_Unit-4_31072020050116AM.ppt
2170610_PPV_GTU_Study_Material_Presentations_Unit-4_31072020050116AM.ppt2170610_PPV_GTU_Study_Material_Presentations_Unit-4_31072020050116AM.ppt
2170610_PPV_GTU_Study_Material_Presentations_Unit-4_31072020050116AM.pptHimani762003
 
Estimating calculation
Estimating calculationEstimating calculation
Estimating calculationZIyeeTan
 
Estimating calculation
Estimating calculationEstimating calculation
Estimating calculationZIyeeTan
 
Estimating calculation
Estimating calculationEstimating calculation
Estimating calculationZIyeeTan
 
Farm Survey Assignment, Avin Kharel (16, IAAS Lamjung Campus)..pdf
Farm Survey Assignment, Avin Kharel (16, IAAS Lamjung Campus)..pdfFarm Survey Assignment, Avin Kharel (16, IAAS Lamjung Campus)..pdf
Farm Survey Assignment, Avin Kharel (16, IAAS Lamjung Campus)..pdfAvin Kharel
 
estimating and costing (1).pdf
estimating and costing (1).pdfestimating and costing (1).pdf
estimating and costing (1).pdfRoshani Shahi
 
Eqs unit 3 final
Eqs unit 3 finalEqs unit 3 final
Eqs unit 3 finaldhanapal143
 
Notes on Estimation.ppt
Notes on Estimation.pptNotes on Estimation.ppt
Notes on Estimation.pptashoklalwani6
 

Similaire à Analyzing Rates of Construction Items (20)

Analysis of rates
Analysis of ratesAnalysis of rates
Analysis of rates
 
Ratesanalysis for Material and Labor
Ratesanalysis for Material and LaborRatesanalysis for Material and Labor
Ratesanalysis for Material and Labor
 
ANALYSIS_OF_RATES.ppt
ANALYSIS_OF_RATES.pptANALYSIS_OF_RATES.ppt
ANALYSIS_OF_RATES.ppt
 
Estimation and costing pdf
Estimation and costing pdfEstimation and costing pdf
Estimation and costing pdf
 
EQS - RATE ANALYSIS.pdf
EQS -  RATE ANALYSIS.pdfEQS -  RATE ANALYSIS.pdf
EQS - RATE ANALYSIS.pdf
 
Rate analysis
Rate analysisRate analysis
Rate analysis
 
Quantity notes by engineer saqib imran
Quantity notes by engineer saqib imranQuantity notes by engineer saqib imran
Quantity notes by engineer saqib imran
 
Quantity notes by engineer saqb imran
Quantity notes by engineer saqb imranQuantity notes by engineer saqb imran
Quantity notes by engineer saqb imran
 
QUANTITY SURVEYING PORTFOLIO.pptx
QUANTITY SURVEYING PORTFOLIO.pptxQUANTITY SURVEYING PORTFOLIO.pptx
QUANTITY SURVEYING PORTFOLIO.pptx
 
Bill of Quantity Tabulation
Bill of Quantity TabulationBill of Quantity Tabulation
Bill of Quantity Tabulation
 
2170610_PPV_GTU_Study_Material_Presentations_Unit-4_31072020050116AM.ppt
2170610_PPV_GTU_Study_Material_Presentations_Unit-4_31072020050116AM.ppt2170610_PPV_GTU_Study_Material_Presentations_Unit-4_31072020050116AM.ppt
2170610_PPV_GTU_Study_Material_Presentations_Unit-4_31072020050116AM.ppt
 
Case Study of Foundry
Case Study of FoundryCase Study of Foundry
Case Study of Foundry
 
Estimating calculation
Estimating calculationEstimating calculation
Estimating calculation
 
Estimating calculation
Estimating calculationEstimating calculation
Estimating calculation
 
Estimating calculation
Estimating calculationEstimating calculation
Estimating calculation
 
Farm Survey Assignment, Avin Kharel (16, IAAS Lamjung Campus)..pdf
Farm Survey Assignment, Avin Kharel (16, IAAS Lamjung Campus)..pdfFarm Survey Assignment, Avin Kharel (16, IAAS Lamjung Campus)..pdf
Farm Survey Assignment, Avin Kharel (16, IAAS Lamjung Campus)..pdf
 
Section 6
Section 6Section 6
Section 6
 
estimating and costing (1).pdf
estimating and costing (1).pdfestimating and costing (1).pdf
estimating and costing (1).pdf
 
Eqs unit 3 final
Eqs unit 3 finalEqs unit 3 final
Eqs unit 3 final
 
Notes on Estimation.ppt
Notes on Estimation.pptNotes on Estimation.ppt
Notes on Estimation.ppt
 

Plus de ALI HYDER GADHI

Material required for different items of civil building works
Material required for different items of civil  building worksMaterial required for different items of civil  building works
Material required for different items of civil building worksALI HYDER GADHI
 
National Fund for Mohenjodaro , its status, functions and detail of deposits
National Fund for Mohenjodaro , its status,    functions and detail of deposits National Fund for Mohenjodaro , its status,    functions and detail of deposits
National Fund for Mohenjodaro , its status, functions and detail of deposits ALI HYDER GADHI
 
Conservation methods 13 2-2013
Conservation methods 13 2-2013Conservation methods 13 2-2013
Conservation methods 13 2-2013ALI HYDER GADHI
 
General Contract Conditions as incorporated by SPPRA /PPPRA
General Contract Conditions as incorporated by SPPRA /PPPRA General Contract Conditions as incorporated by SPPRA /PPPRA
General Contract Conditions as incorporated by SPPRA /PPPRA ALI HYDER GADHI
 
Monsoon Preparations Survey for Archaeological Ruins Mohenjodaro
 Monsoon Preparations Survey for  Archaeological Ruins Mohenjodaro  Monsoon Preparations Survey for  Archaeological Ruins Mohenjodaro
Monsoon Preparations Survey for Archaeological Ruins Mohenjodaro ALI HYDER GADHI
 
Urban renewal, conservation & regeneration of arabic cities
Urban renewal, conservation & regeneration of arabic citiesUrban renewal, conservation & regeneration of arabic cities
Urban renewal, conservation & regeneration of arabic citiesALI HYDER GADHI
 
Conservation and revitalization of historic buildings
Conservation and revitalization of historic buildingsConservation and revitalization of historic buildings
Conservation and revitalization of historic buildingsALI HYDER GADHI
 
Mohen jo Daro Indus valley by ALI HYDER GADHI BALOCH
Mohen jo Daro  Indus valley by ALI HYDER GADHI BALOCH Mohen jo Daro  Indus valley by ALI HYDER GADHI BALOCH
Mohen jo Daro Indus valley by ALI HYDER GADHI BALOCH ALI HYDER GADHI
 
Emergency Measures adopted before monsoon, during and after rainfall at World...
Emergency Measures adopted before monsoon, during and after rainfall at World...Emergency Measures adopted before monsoon, during and after rainfall at World...
Emergency Measures adopted before monsoon, during and after rainfall at World...ALI HYDER GADHI
 
History of Conservation and Preservation of Cultural Property
 History of Conservation and Preservation of Cultural Property  History of Conservation and Preservation of Cultural Property
History of Conservation and Preservation of Cultural Property ALI HYDER GADHI
 
2nd day presentation mohanlal
2nd day presentation   mohanlal2nd day presentation   mohanlal
2nd day presentation mohanlalALI HYDER GADHI
 
Conservation terminologies for site and monuments
Conservation terminologies for site and monumentsConservation terminologies for site and monuments
Conservation terminologies for site and monumentsALI HYDER GADHI
 

Plus de ALI HYDER GADHI (14)

Material required for different items of civil building works
Material required for different items of civil  building worksMaterial required for different items of civil  building works
Material required for different items of civil building works
 
National Fund for Mohenjodaro , its status, functions and detail of deposits
National Fund for Mohenjodaro , its status,    functions and detail of deposits National Fund for Mohenjodaro , its status,    functions and detail of deposits
National Fund for Mohenjodaro , its status, functions and detail of deposits
 
Conservation methods 13 2-2013
Conservation methods 13 2-2013Conservation methods 13 2-2013
Conservation methods 13 2-2013
 
General Contract Conditions as incorporated by SPPRA /PPPRA
General Contract Conditions as incorporated by SPPRA /PPPRA General Contract Conditions as incorporated by SPPRA /PPPRA
General Contract Conditions as incorporated by SPPRA /PPPRA
 
Monsoon Preparations Survey for Archaeological Ruins Mohenjodaro
 Monsoon Preparations Survey for  Archaeological Ruins Mohenjodaro  Monsoon Preparations Survey for  Archaeological Ruins Mohenjodaro
Monsoon Preparations Survey for Archaeological Ruins Mohenjodaro
 
Urban renewal, conservation & regeneration of arabic cities
Urban renewal, conservation & regeneration of arabic citiesUrban renewal, conservation & regeneration of arabic cities
Urban renewal, conservation & regeneration of arabic cities
 
Conservation and revitalization of historic buildings
Conservation and revitalization of historic buildingsConservation and revitalization of historic buildings
Conservation and revitalization of historic buildings
 
Mohen jo Daro Indus valley by ALI HYDER GADHI BALOCH
Mohen jo Daro  Indus valley by ALI HYDER GADHI BALOCH Mohen jo Daro  Indus valley by ALI HYDER GADHI BALOCH
Mohen jo Daro Indus valley by ALI HYDER GADHI BALOCH
 
Emergency Measures adopted before monsoon, during and after rainfall at World...
Emergency Measures adopted before monsoon, during and after rainfall at World...Emergency Measures adopted before monsoon, during and after rainfall at World...
Emergency Measures adopted before monsoon, during and after rainfall at World...
 
History of Conservation and Preservation of Cultural Property
 History of Conservation and Preservation of Cultural Property  History of Conservation and Preservation of Cultural Property
History of Conservation and Preservation of Cultural Property
 
Estimation
Estimation    Estimation
Estimation
 
2nd day presentation mohanlal
2nd day presentation   mohanlal2nd day presentation   mohanlal
2nd day presentation mohanlal
 
Group a workshop on c h
Group a workshop on c hGroup a workshop on c h
Group a workshop on c h
 
Conservation terminologies for site and monuments
Conservation terminologies for site and monumentsConservation terminologies for site and monuments
Conservation terminologies for site and monuments
 

Analyzing Rates of Construction Items

  • 2. ANALYSIS OF RATES • To determine the rate of a particular item of work from a quantities of materials and labours required and their costs • The rates of materials and labour are changing from place to place, therefore the rates o different items of work also changes from place to place
  • 3. ANALYSIS OF RATES • Every Estimate should be accompanied by the analysis of rates of the items provided in it . • Analysis of rates comprises of 1. Cost of Material 2. Cost of Labour 3. T and P , and Sundries 4. Carriage 5. Contractor’s Profit
  • 4. ANALYSIS OF RATES • Tools and Plants ( T & P ) = 2.5 to 3 % of the labour cost • Transportation cost more than 8 km is considered • Water charges = 1.5 to 2 % 0f total cost • Contractor ‘ s profit = 10 %
  • 5. ANALYSIS OF RATES • Rates of Materials and Labours : • 1st class bricks = Rs 4500 per 1000 Nos. • 2nd class bricks = Rs 4000 per 1000 Nos. • Brick Ballast = Rs 800 per cum • Coarse sand = Rs 800 per cum • Cement 50 kg bag = Rs 270 per bag • Twisted bars = Rs 5000 per Quintel • Bitumen = Rs 10 per kg
  • 6. ANALYSIS OF RATES • Mason = Rs 450 per day • Plaster = Rs 400 per day • Carpenter = Rs 400 per day • Bhishti = Rs 250 per day • Mazdoor = Rs 250 per day • Painter = Rs 300 per day
  • 7. ANALYSIS OF RATES • Earth work in excavation: Mazdoor = 33 (% cum) Mason = 1.5 • Earth work in Filling : Mazdoor = 18 (% cum) Mason = 0.5 • Cement concrete : Mazdoor = 15 in foundation Mason =1.5 Bhishti = 2
  • 8. ANALYSIS OF RATES • Cement concrete : Mazdoor = 15 Mason = 1 Bhishti = 2.5 • R. Cement concrete : Mazdoor = 40 (10 cum ) Mason = 2.5 Bhishti = 5 Blacksmith = 4 Carpenter = 4
  • 9. ANALYSIS OF RATES • DPC : Mazdoor = 2.5 (10 cum ) Mason = 1.5 Bhishti = 0.5 • 1st class brick work : Mazdoor = 15 Mason = 8 Bhishti = 2
  • 10. ANALYSIS OF RATES • Plastering work : Mazdoor = 10 ( 100 sqm) Mason = 10 Bhishti = 2 • Distempering/painting/white washing : Mazdoor = 5 ( 100 sqm) Painter = 4
  • 11. ANALYSIS OF RATES Example 1. Find out dry materials required for 1 cu m. C. concrete 1:4:8 in foundation. Solution. Ratio = 1:4:8 (cement,sand and aggregate) Sum = 1+4+8=13 cont..
  • 12. Total dry mortar for 1 cu m cement concrete =1.54 cu m Therefore the following materials are required: Cement = (1*1.54*28.8)/13 = 3.41 bags Sand = (4*1.54)/13 = 0.47 cu m cont..
  • 13. Aggregate (Brick ballast) = (8*1.57)/13 = 0.94 cu m so materials for 1 cu m cement concrete 1:4:8. Cement 3.41 bags Sand 0.47 cu m Ans. Brick ballast 0.94 cu m
  • 14. Example 2. Find out dry materials for 1 cu m lime concrete. Solution: Ratio = 1:2 (lime,surkhi) Sum = 1+2 = 3 Total dry mortar for 1 cu m lime concrete = 0.40 (lime, surkhi mortar)
  • 15. Therefore the following materials are required. Lime = (1*0.40)/3 = 0.13 cu m Surkhi = (2*0.40)/3 = 0.27 cu m Aggregate (brick ballast) = 1.00 cu m
  • 16. Materials required for1 cu m lime cocrete 1:2 Lime 0.13 cu m Surkhi 0.27 cu m Ans. Brick ballast 1.00 cu m
  • 17. ANALYSIS OF RATES OF DIFFERENT ITEMS OF WORK. 1. Excavation for foundation: payment % cu m (a)Materials at the site for % cu m nil No material is required Rs. P. (b)labour for % cu m Mazdoor 33 nos.@ 250.00/day = 8250.00
  • 18. Mason 1 no. @ 450.00 = 450.00 Sundries and Tand P 3% on labour = 261.00 Total = 8961.00 (c)Add 10% contractor’s profit = 896.10 grand total =9857.10 say Rs. = 9857.00 Rate per % cu m = Rs. 9857.00
  • 19. 2.Earth filling under floors payment % cu m (a)Materials at site for %cu m Rs.P. No material is required nil (b) Labour for % cu m Majdoor18nos.@250.00/day =4500.00 Bhishti 1/2no.@250.00/day = 125.00 Sundries and Tand P3% on labour 465.00 = 123.75 total = 4748.75 Add 10% contractor’s profit = 474.87
  • 20. G.Total= 5223.62 say Rs.=5224.00 Rate per % cu m = Rs. 5224.00 3. Cement concrete 1:4:8 in foundations (a) Materials at site for 1 cu m payment per cu m Cement 3.41 bags @270 bag = 929.70 Sand 0.47 cu m @800.00 per cu m=376.00
  • 21. Brick ballast 0.94 cu m @ 800.00 = 752.00 Cost of labour for 10 cu m = 7520.00 (b)Labour for 10 cu m Rs. P Mason 1@ 400.00/ day = 400.00 Mazdoors 15@ 250.00/ day = 3750.00 Bhishti 2@ 250.oo/ day = 500.00 Sundries and Tand P @ 3% on labour = 139.50
  • 22. • Cost of for 10 cu m = 12309.50 • Cost of for 1 cu m =12309.50/10 • =1230.95 • PROBLEM: Conglomerate floor 4 cm thick of cement concrete 1:2:4 over 10 cm thick cement concrete 1:6:18 over 10 cm sand filling.
  • 23. calculation of material for 10 sq m (1) Wet mortar for cement concrete 1:2:4= 10 sq m*4cm = 10*4/100 =0.40cu m
  • 24. Dry mortar = 0.40*1.54=0.616+0.62 cu m Ratio = 1:2:4 Sum =1+2+4=7 Cement = 1*0.62*28.8/7 =2.55 bags Sand = 2*0.62/7 = 0.18 cu m
  • 25. Crusher = 4*0.62/7=0.36 cu m (2)Wet mortar for cement concrete 1:6:18 = 10 sq m*10 cm =10*10/100 =1 cu m
  • 26. Dry mortar 1*1.54 =1.54cu m Ratio =1:6:18=1+6+18 = 25 Cement = 1*1.54*28.8/25 = 1.78 bags
  • 27. Sand =6*1.54/25 = 0.37 cu m Brick ballast = 18*1.54/2 = 1.11 cu m (3) Sand for 10 sq m = 10 sq m* 10 cm = 10*10/10
  • 28. = 1 cu m Total dry mortar for 10 sq m conglomerate flooring. Cement = 2.55+1.78 Sand = 0.18+0.37+1.00 Crusher = 0.46
  • 29. (a) Materials at site for 10 sq m Rs.P Cement 4.33 bags @ 270.00/bag = 1170.00 sand 1.55 cum@ 800.00 per cu m = 1240.00 Crusher 0.36 cu m @1200 /cu m = 432.00 Brick ballast 1.11 cu m@ 800 / cu m = 888.00
  • 30. Cost of material for 10 sq m =3730.00 (b) Labour for 10 sq m Rs. P Mason 2@ 400.00/ day = 900.00 Mazdoor 3@ 250.00/day = 750.00 Bhishti 1@ 250.00 / day = 250.00
  • 31. Sundries T and P 3% on labour = 57.00 Cost of labour for 10 sq m = 1957.00 Cost of material and labour for 10 sq m =5687.00
  • 32. Add 10% contractor’s profit = 568.70 and total = 6255.70 Rate for 10 sq m = Rs.6256.00 Rate per sq m = Rs.625.60