Phase 2B          In this slide show:        Jackson PlazaGumby Lamp Fixtures Installation          May 5, 2012
Cast iron lamp posts were installed along the Jackson Plaza granite balustrade.
The 527 lbs lamp post was lifted by a crane to its location.
Each lamp post takes 4-5 hours to install.
When complete with the spherical bulb housing the lamp will reach a height of 6.5      feet. The electrician next to the l...
All electrical connection are moisture sealed with solid filled epoxy for longevity.
The lamp posts are nicknamed “gumbies”.
Efficient and long lasting LED modules are used in each glass spherical bulb.
Brick pavers havebeen installed onthe west sidewalkway.
Concrete foundation was cast for future planters .
Baggage room andticketing carouselsare being installed.
Demolition in theold electrical room
Prochain SlideShare
Chargement dans…5
×

5.9.12 King Street Station powerpoint update

10 361 vues

Publié le

Jackson Plaza
Gumby Lamp Fixtures Installation

  • Soyez le premier à commenter

  • Soyez le premier à aimer ceci

5.9.12 King Street Station powerpoint update

  1. 1. Phase 2B In this slide show: Jackson PlazaGumby Lamp Fixtures Installation May 5, 2012
  2. 2. Cast iron lamp posts were installed along the Jackson Plaza granite balustrade.
  3. 3. The 527 lbs lamp post was lifted by a crane to its location.
  4. 4. Each lamp post takes 4-5 hours to install.
  5. 5. When complete with the spherical bulb housing the lamp will reach a height of 6.5 feet. The electrician next to the lamp post in the photo is 5’11” tall.
  6. 6. All electrical connection are moisture sealed with solid filled epoxy for longevity.
  7. 7. The lamp posts are nicknamed “gumbies”.
  8. 8. Efficient and long lasting LED modules are used in each glass spherical bulb.
  9. 9. Brick pavers havebeen installed onthe west sidewalkway.
  10. 10. Concrete foundation was cast for future planters .
  11. 11. Baggage room andticketing carouselsare being installed.
  12. 12. Demolition in theold electrical room

×