SlideShare a Scribd company logo
1 of 45
By: Anand Bobade (nmbobade@gmail.com)
PMBOK Chap 12 – Project Procurement Management
The processes necessary to purchase or acquire product, services,
or results needed from outside the project team.
Initiating Planning Executing Monitoring &
Controlling
Closing
Plan Procurement
Management
Conduct
Procurement
Control
Procurement
Close Procurement
We cannot solve our problems with the same thinking we used when we created
them.
- Albert Einstein
Detailed
Part-2
By: Anand Bobade (nmbobade@gmail.com)
Introduction – Procurement Management Processes
12.1 Plan Procurement Management
• The process of documenting project procurement decisions,
specifying the approach, and identifying potential sellers.
12.2 Conduct Procurement
• The process of obtaining seller responses, selecting a seller, and
awarding a contract.
12.3 Control Procurement
• The process of managing procurement relationships, monitoring
contract performance, and making changes and corrections to
contracts as appropriate
12.4 Close Procurement
• The process of completing each procurement.
By: Anand Bobade (nmbobade@gmail.com)
Controlling Procurement
PM is
responsible
for
Manage
relationship
Document
Performance
Monitor and
communicate
variance
Manage
Changes
By: Anand Bobade (nmbobade@gmail.com)
The process of managing procurement relationships,
monitoring contract performance, and making changes
and corrections to contracts as appropriate.
It ensures both seller’s & buyer’s performance meets
procurement requirements according to agreement.
Managing
procurement
relationships
Monitoring
contract
performance
Making
changes and corrections
to contracts
12.3 Control Procurement
By: Anand Bobade (nmbobade@gmail.com)
12.3 Control Procurement
Buyer ensure that they follow through
on their own obligations.
Quality will suffer if obligations are
not met.
Schedule/cost will impact if obligation
are not meet.
Process will ensure adherence to
contract/agreements.
Buyers Obligation
By: Anand Bobade (nmbobade@gmail.com)
12.3 Control Procurement
Major processes where Buyer to focus:
• Monitor technical
performance
Technical:
Scope
Management:
• Ensure seller meets
agreed milestones
Schedule:
time
Management:
• Ensure project cost is
within the Budget
Budget:
Cost
Management:
• Continually Verify Seller
delivers agreed quality
Verification:
Quality
Management
• Contract risk has to be
mitigated.
Risk Mitigation:
Risk Management:
By: Anand Bobade (nmbobade@gmail.com)
12.3 Control Procurement
Multiple Sellers scenario
Buyer
Seller1
(Buyer for
Seller3)
Seller3
Seller2
Seller 1:
Setup IT infrastructure
Seller2 - Develops
application
Seller 3 –
Data Center setup
By: Anand Bobade (nmbobade@gmail.com)
Inputs (6)
• PMP
• Procurement
documents
• Agreements
• Approved change
requests
• Work performance
reports
• Work performance
data
Tools &
Techniques(7)
• Contract change
control system
• Procurement
performance reviews
• Inspections and audits
• Performance
reporting
• Payment systems
• Claims administration
• Records management
system
Outputs(5)
• Work performance
information
• Change requests
• Project management
plan updates
• Project documents
updates
• OPA updates
By: Anand Bobade (nmbobade@gmail.com)
12.3 Control Procurement -> ITTO
By: Anand Bobade (nmbobade@gmail.com)
12.3 Control Procurement ->Input
PMP
Procurement
documents
Agreements
Approved Change
Requests
Work
Performance
Reports
Work
Performance
Data
By: Anand Bobade (nmbobade@gmail.com)
12.3 Control Procurement ->Input->Procurement Doc’s
Procurement
documents
Contract
Contract
Amendments
Contract
Addendums
Technical
documentation
User Manual Invoices
Payment
records
Contract related documents:
By: Anand Bobade (nmbobade@gmail.com)
12.3 Control Procurement ->Input->WPD
Work
Performance
Data
The raw observations & measurements related to
contract & activities performed as per contract.
Deliverables
produced
Cost - committed Vs
incurred
Seller invoices
(submitted, paid)
Quality standards
Cost Invoices
Deliverables Quality
Direct and Manage Project work
By: Anand Bobade (nmbobade@gmail.com)
12.3 Control Procurement ->Input-> Work Performance Reports
Work
Performance
Reports
The physical or electronic representation of work performance
information compiled as reports, to generate decisions, actions,
or awareness.
Generated reports - IT system generated / Physical
Seller performance related documents
Technical documentation
Work Performance information
Monitor & Control Project work Control Procurement
By: Anand Bobade (nmbobade@gmail.com)
12.3 Control Procurement ->Input -> Approved Change Requests
Approved Change
Requests
A change request that has been processed through the
integrated change control process and approved.
Due to change in :
Business
requirement
Technical
specification
Schedule,
Milestone
Cost Contract
By: Anand Bobade (nmbobade@gmail.com)
12.3 Control Procurement-> T&T
Contract Change
Control System
Procurement
Performance
Reviews
Inspections and
audits
Performance
Reporting
Payment Systems Claims
Administration
Records
Management
System
By: Anand Bobade (nmbobade@gmail.com)
12.3 Control Procurement-> T&T
Inspections and
audits
Procurement
Performance Reviews
Performance
Reporting
Inspect
Control
Records
Management
System
Payment Systems
Contract Change
Control System
Claims
Administration
General Categorization (Not as per PMBOK):
By: Anand Bobade (nmbobade@gmail.com)
12.3 Control Procurement-> T&T->Record Management System
Records
Management
System
Processes & tools that are combined to record and
retain information about the project.
Maintain all Contract related
correspondence
Contract version control
(Amendments/Addendums)
Repository of all contract/dispute
resolution information
It acts as document archive
By: Anand Bobade (nmbobade@gmail.com)
12.3 Control Procurement-> T&T->Payment System
Payment Systems
Oracle financials Microsoft Dynamics
Payment is processed accordance with the terms of the contract.
Payment is done only after approval of satisfactory work by an
project team.
Ensure compliance with agreement
The system used to provide and track supplier's
invoices and payments for services and products.
By: Anand Bobade (nmbobade@gmail.com)
12.3 Control Procurement-> T&T->Inspection & Audits
Inspections and
audits
The system used to provide and track supplier's
invoices and payments for services and products.
Inspect seller deliverables.
Audit Seller processes.
Verify compliance with contract
Verify any weakness in process
By: Anand Bobade (nmbobade@gmail.com)
12.3 Control Procurement-> T&T-> Procurement Performance Reviews
Procurement
Performance
Reviews
Structured review of seller’s progress to deliver
project scope & quality, within cost & on schedule.
Performance review objective :
To identify seller’s
performance
• Successes or failures
• Progress with respect to
the Procurement SOW
• Contract noncompliance
Allow the buyer to quantify
• Seller’s demonstrated
ability
• Inability to perform work.
Review of:
Seller‐prepared
documentation
Buyer inspections
Quality audits
conducted
By: Anand Bobade (nmbobade@gmail.com)
12.3 Control Procurement-> T&T->Performance Reporting
Performance
Reporting
It’s WPI, compiled as reports, to generate decisions,
actions, or awareness.
Similar to work performance reports, however focus
is on contractual performance.
Evaluate sellers work
performance
Verify sellers processes
& deliverable
compliance
By: Anand Bobade (nmbobade@gmail.com)
12.3 Control Procurement-> T&T->CCCS
Contract Change
Control System
Defines process to modify procurement.
Component of Integrated change control system:
Changes will be Documented Tracked Approved Arbitrate Communicated
The system used to collect, track, arbitrate, and
communicate changes to a contract.
Oracle’s Primavera Contract
Management
Microsoft SharePoint based Contract
Management
By: Anand Bobade (nmbobade@gmail.com)
12.3 Control Procurement-> T&T->Claim Administration
Claims
Administration
The process of processing, adjudicating, and
communicating contract claims.
Claim administrations helps PM to solves
disputes. Disputes in large projects with
multiple sellers can be very complex.
Manage according to the terms of contract.
Follow documented procedures.
If not resolved follow alternative dispute resolution
(ADR)
How to
resolve
disputes
By: Anand Bobade (nmbobade@gmail.com)
12.3 Control Procurement ->Output
Work Performance
Information
Change Requests PMP Updates
Project Documents
Updates
OPA Updates
By: Anand Bobade (nmbobade@gmail.com)
12.3 Control Procurement ->Output->WPI
Work
Performance
Information
Performance data collected from various controlling
processes and analyzed in contractual context.
Work
Performance
Data,
Work
Performance
Reports
Control Procurement T&T -
Inspections and audits,
Change Control system,
Performance Review
(Generates data)
Work
Performance
Information
By: Anand Bobade (nmbobade@gmail.com)
12.3 Control Procurement ->Output->change Request
Change Requests
Processed
through
Integrated
Change Control
Requested but
unresolved
changes which
are documented
leads to disputes.
Change requests
going through
disputes are not
implemented.
A formal proposal to modify any document,
deliverable, or baseline.
By: Anand Bobade (nmbobade@gmail.com)
12.3 Control Procurement ->Output-> PMP Updates
PMP Updates
Update Project
Management
plan related
documents.
Update
Procurement
Management
plan
Update
schedule
(Milestones &
Delivery dates )
By: Anand Bobade (nmbobade@gmail.com)
12.3 Control Procurement ->Output->OPA Updates
OPA Updates
Sellers Performance record, Preferred seller list.
Correspondence with seller.
Lesson Learned
By: Anand Bobade (nmbobade@gmail.com)
12.3 Control Procurement -> Process Flow
By: Anand Bobade (nmbobade@gmail.com)
Introduction – Procurement Management Processes
12.1 Plan Procurement Management
• The process of documenting project procurement decisions,
specifying the approach, and identifying potential sellers.
12.2 Conduct Procurement
• The process of obtaining seller responses, selecting a seller, and
awarding a contract.
12.3 Control Procurement
• The process of managing procurement relationships, monitoring
contract performance, and making changes and corrections to
contracts as appropriate
12.4 Close Procurement
• The process of completing each procurement.
By: Anand Bobade (nmbobade@gmail.com)
Procurement 1
Procurement 2
Individual
procurement
Closure
12.4 Close Procurement
The process of completing each procurement.
It documents agreements and related documentation
for future reference.
By: Anand Bobade (nmbobade@gmail.com)
12.4 Close Procurement
Early
Termination
Partial
Termination
Termination for
a Cause
Termination for
Convenience
When to end an Agreement:
Seller is delivering as planned/Agreed
Long Silence from both parties is not a termination
Notice is required to initiate termination
Awareness & abiding by terms and conditions is
required
Complete all administrative task before termination
By: Anand Bobade (nmbobade@gmail.com)
12.4 Close Procurement -> ITTO
Inputs (2)
• Project
Management Plan
• Procurement
Documents
Tools &
Techniques(3)
• Procurement
Audits
• Procurement
Negotiations
• Records
Management
System
Outputs(2)
• Closed
Procurements
• OPA Updates
By: Anand Bobade (nmbobade@gmail.com)
12.4 Close Procurement ->Inputs
PMP
Procurement
documents
By: Anand Bobade (nmbobade@gmail.com)
12.4 Close Procurement -> Inputs -> PMP
Procurement Management plan
Closure details & Guidelines
PMP
By: Anand Bobade (nmbobade@gmail.com)
12.4 Close Procurement -> Inputs -> Proc. Documents
Procurement
documents
Procurement documents, Lesson Learned
Contractual agreement documents
By: Anand Bobade (nmbobade@gmail.com)
12.4 Close Procurement -> T&T
Procurement
Audits
Procurement
Negotiations
Records
Management
System
By: Anand Bobade (nmbobade@gmail.com)
12.4 Close Procurement -> T&T->Procurement Audits
Procurement
Audits
Structured review of procurement process originating from
Plan Procurements through Administer Procurements.
Examine & evaluate
How was the execution
Procurement Audits
Was it a best contract?
List of success & failures
Is the changes implemented correctly?
By: Anand Bobade (nmbobade@gmail.com)
12.4 Close Procurement -> T&T->Procurement Negotiations
Procurement
Negotiations
Primary Goal is to final equitable
settlement of all outstanding issues,
claims, and disputes by negotiation.
Alternative dispute resolution ( ADR) )
including mediation or arbitration may
be explored if it cant be settled by direct
negotiations.
When all else fails, litigation in the courts
is the least desirable option.
By: Anand Bobade (nmbobade@gmail.com)
12.4 Close Procurement -> T&T->Records Management System
Records
Management
System
Processes & tools that are combined to record and
retain information about the project.
Maintain all Contract related
correspondence
Contract version control
(Amendments/Addendums)
Repository of all contract/dispute
resolution information
It acts as document archive
By: Anand Bobade (nmbobade@gmail.com)
12.4 Close Procurement ->Output
Closed
Procurements
OPA Updates
By: Anand Bobade (nmbobade@gmail.com)
12.4 Close Procurement ->Output->Close Procurement
Closed
Procurements
Closure has to be signed by person with appropriate
authority
Follows the process agreed in procurement
management plan
Formal notice is required
By: Anand Bobade (nmbobade@gmail.com)
12.4 Close Procurement ->Output->OPA Updates
OPA Updates
Update procurement documents with final notice &
contract closure
Update with Acceptance or non-compliance details
Update Lessons learned
By: Anand Bobade (nmbobade@gmail.com)
12.4 Close Procurement -> Process Flow
By: Anand Bobade (nmbobade@gmail.com)
By: Anand Bobade (nmbobade@gmail.com)
Visit Slide Share website & you will find other Knowledge area presentation… Please share!!
Thank You!

More Related Content

What's hot

PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
Anand Bobade
 

What's hot (20)

Pmp chap 11 - project risk management v0.1
Pmp   chap 11 - project risk management v0.1Pmp   chap 11 - project risk management v0.1
Pmp chap 11 - project risk management v0.1
 
PMP Chap 7 - Project Cost Management - Part 2
PMP Chap 7 - Project Cost Management - Part 2PMP Chap 7 - Project Cost Management - Part 2
PMP Chap 7 - Project Cost Management - Part 2
 
Chap 11.2 Identify Risks
Chap 11.2 Identify RisksChap 11.2 Identify Risks
Chap 11.2 Identify Risks
 
PMP Chap 5 - Project Scope Management - Part1
PMP Chap 5 - Project Scope Management - Part1PMP Chap 5 - Project Scope Management - Part1
PMP Chap 5 - Project Scope Management - Part1
 
PMP Chap 7 - Project Cost Management - Part 1
PMP Chap 7 - Project Cost Management - Part 1PMP Chap 7 - Project Cost Management - Part 1
PMP Chap 7 - Project Cost Management - Part 1
 
Chap 4.7 Project or Phase Close
Chap 4.7 Project or Phase CloseChap 4.7 Project or Phase Close
Chap 4.7 Project or Phase Close
 
Chap 8.2 Manage Quality
Chap 8.2 Manage QualityChap 8.2 Manage Quality
Chap 8.2 Manage Quality
 
PMP Chap 10 - Project Communication Management Details
PMP  Chap 10 - Project Communication Management DetailsPMP  Chap 10 - Project Communication Management Details
PMP Chap 10 - Project Communication Management Details
 
PMP Chap4-Project Integration Management Details: Part-2
PMP Chap4-Project Integration Management Details: Part-2PMP Chap4-Project Integration Management Details: Part-2
PMP Chap4-Project Integration Management Details: Part-2
 
Chap 7.1 Plan Cost Management
Chap 7.1  Plan Cost ManagementChap 7.1  Plan Cost Management
Chap 7.1 Plan Cost Management
 
Chap 4.3 Direct and Manage Project work
Chap 4.3 Direct and Manage Project workChap 4.3 Direct and Manage Project work
Chap 4.3 Direct and Manage Project work
 
PMP Chap 5 - Project Scope Management - Part 2
PMP Chap 5 - Project Scope Management - Part 2PMP Chap 5 - Project Scope Management - Part 2
PMP Chap 5 - Project Scope Management - Part 2
 
Chap 6.2 Define Activity
Chap 6.2 Define ActivityChap 6.2 Define Activity
Chap 6.2 Define Activity
 
Chap 10.2 Manage Communication
Chap 10.2  Manage CommunicationChap 10.2  Manage Communication
Chap 10.2 Manage Communication
 
PMP Chap 4 - Project Integration Management - Part1
PMP Chap 4 - Project Integration Management - Part1PMP Chap 4 - Project Integration Management - Part1
PMP Chap 4 - Project Integration Management - Part1
 
Project Management-Project procurement Management
Project Management-Project procurement ManagementProject Management-Project procurement Management
Project Management-Project procurement Management
 
Procurement Contract Types | PMP | iZenBridge - Webinar
Procurement Contract Types | PMP | iZenBridge - Webinar Procurement Contract Types | PMP | iZenBridge - Webinar
Procurement Contract Types | PMP | iZenBridge - Webinar
 
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
 
PMP Chap 8 - Project Quality Management
PMP Chap 8 - Project Quality ManagementPMP Chap 8 - Project Quality Management
PMP Chap 8 - Project Quality Management
 
Chap 9.4 Develop Team
Chap 9.4  Develop TeamChap 9.4  Develop Team
Chap 9.4 Develop Team
 

Similar to PMP Chap 12 - Project Procurement Management Details - Part2

OGS Announces New Methods in
OGS Announces New Methods inOGS Announces New Methods in
OGS Announces New Methods in
Videoguy
 

Similar to PMP Chap 12 - Project Procurement Management Details - Part2 (20)

PMP Key Exam Concepts WPD, WPI & WPR
PMP Key Exam Concepts WPD, WPI & WPRPMP Key Exam Concepts WPD, WPI & WPR
PMP Key Exam Concepts WPD, WPI & WPR
 
Chap 4.6 Perform Integrated Change Control
Chap 4.6 Perform Integrated Change ControlChap 4.6 Perform Integrated Change Control
Chap 4.6 Perform Integrated Change Control
 
12.3 Control Procurements
12.3 Control Procurements12.3 Control Procurements
12.3 Control Procurements
 
Chap 5.5 validate scope
Chap 5.5 validate scopeChap 5.5 validate scope
Chap 5.5 validate scope
 
Growing your business with BPM
Growing your business with BPMGrowing your business with BPM
Growing your business with BPM
 
Edcil 28122017.pptx
Edcil 28122017.pptxEdcil 28122017.pptx
Edcil 28122017.pptx
 
ACH 216 Lecture 06 (Pre Construction Planning)
ACH 216 Lecture 06 (Pre Construction Planning)ACH 216 Lecture 06 (Pre Construction Planning)
ACH 216 Lecture 06 (Pre Construction Planning)
 
OGS Announces New Methods in
OGS Announces New Methods inOGS Announces New Methods in
OGS Announces New Methods in
 
The Six Business System Rules
The Six Business System RulesThe Six Business System Rules
The Six Business System Rules
 
Project Management (Practical Qustion Paper) [CBSGS - 75:25 Pattern] {Manual}
Project Management (Practical Qustion Paper) [CBSGS - 75:25 Pattern] {Manual}Project Management (Practical Qustion Paper) [CBSGS - 75:25 Pattern] {Manual}
Project Management (Practical Qustion Paper) [CBSGS - 75:25 Pattern] {Manual}
 
Procurement of Services using Oracle EBS
Procurement of Services using Oracle EBSProcurement of Services using Oracle EBS
Procurement of Services using Oracle EBS
 
Better than the Best
Better than the BestBetter than the Best
Better than the Best
 
Dmn Org Aligment Essentials
Dmn Org Aligment EssentialsDmn Org Aligment Essentials
Dmn Org Aligment Essentials
 
Part Three - The Role of Strategy in PPM - 2022.pptx
Part Three - The Role of Strategy in PPM - 2022.pptxPart Three - The Role of Strategy in PPM - 2022.pptx
Part Three - The Role of Strategy in PPM - 2022.pptx
 
Oracle Billing and Revenue Management(BRM)
Oracle Billing and Revenue Management(BRM)Oracle Billing and Revenue Management(BRM)
Oracle Billing and Revenue Management(BRM)
 
Sap sd bbp template
Sap sd bbp templateSap sd bbp template
Sap sd bbp template
 
Control procurement
Control procurement Control procurement
Control procurement
 
Pmp procurement rev
Pmp procurement revPmp procurement rev
Pmp procurement rev
 
Project Management Practical 01 - 04 (Mumbai University)
Project Management Practical 01 - 04 (Mumbai University)Project Management Practical 01 - 04 (Mumbai University)
Project Management Practical 01 - 04 (Mumbai University)
 
SeefinDM-DCS - Services To Financial Departments
SeefinDM-DCS - Services To Financial DepartmentsSeefinDM-DCS - Services To Financial Departments
SeefinDM-DCS - Services To Financial Departments
 

More from Anand Bobade

More from Anand Bobade (20)

Chap 11.7 Monitor Risks
Chap 11.7 Monitor RisksChap 11.7 Monitor Risks
Chap 11.7 Monitor Risks
 
Chap 10.3 Monitor Communication
Chap 10.3 Monitor CommunicationChap 10.3 Monitor Communication
Chap 10.3 Monitor Communication
 
Chap 10.1 Plan Communication Management
Chap 10.1  Plan Communication ManagementChap 10.1  Plan Communication Management
Chap 10.1 Plan Communication Management
 
Chap 9.6 Control Resources
Chap 9.6  Control ResourcesChap 9.6  Control Resources
Chap 9.6 Control Resources
 
Chap 9.5 Manage Team
Chap 9.5  Manage TeamChap 9.5  Manage Team
Chap 9.5 Manage Team
 
Chap 9.3 Acquire Resources
Chap 9.3   Acquire ResourcesChap 9.3   Acquire Resources
Chap 9.3 Acquire Resources
 
Chap 9.2 Estimate Activity Resource
Chap 9.2   Estimate Activity ResourceChap 9.2   Estimate Activity Resource
Chap 9.2 Estimate Activity Resource
 
Chap 9.1 Pan Resource Management
Chap 9.1   Pan Resource ManagementChap 9.1   Pan Resource Management
Chap 9.1 Pan Resource Management
 
Chap 9.0 Project Resource Management overview
Chap 9.0   Project Resource Management overviewChap 9.0   Project Resource Management overview
Chap 9.0 Project Resource Management overview
 
Chap 7.4 Control Cost
Chap 7.4   Control CostChap 7.4   Control Cost
Chap 7.4 Control Cost
 
Chap 7.2 Estimate Cost
Chap 7.2 Estimate CostChap 7.2 Estimate Cost
Chap 7.2 Estimate Cost
 
Chap 7.3 Determine budget
Chap 7.3   Determine budgetChap 7.3   Determine budget
Chap 7.3 Determine budget
 
Chap 7.0 Project Cost Management Overview
Chap 7.0 Project Cost Management OverviewChap 7.0 Project Cost Management Overview
Chap 7.0 Project Cost Management Overview
 
Chap 6.6 Control Schedule
Chap 6.6 Control ScheduleChap 6.6 Control Schedule
Chap 6.6 Control Schedule
 
Chap 6.5 Define Schedule
Chap 6.5 Define ScheduleChap 6.5 Define Schedule
Chap 6.5 Define Schedule
 
Chap 6.4 Estimate Activity Duration
Chap 6.4 Estimate Activity DurationChap 6.4 Estimate Activity Duration
Chap 6.4 Estimate Activity Duration
 
Chap 6.3 Sequence Activity
Chap 6.3 Sequence ActivityChap 6.3 Sequence Activity
Chap 6.3 Sequence Activity
 
Chap 6.1 Plan Schedule Management
Chap 6.1 Plan Schedule ManagementChap 6.1 Plan Schedule Management
Chap 6.1 Plan Schedule Management
 
Chap 6.0 Schedule Management Overview
Chap 6.0 Schedule Management OverviewChap 6.0 Schedule Management Overview
Chap 6.0 Schedule Management Overview
 
Chap 5.6 Control Scope
Chap 5.6 Control ScopeChap 5.6 Control Scope
Chap 5.6 Control Scope
 

Recently uploaded

Agile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxAgile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptx
alinstan901
 
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTECAbortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Riyadh +966572737505 get cytotec
 

Recently uploaded (20)

Peak Performance & Resilience - Dr Dorian Dugmore
Peak Performance & Resilience - Dr Dorian DugmorePeak Performance & Resilience - Dr Dorian Dugmore
Peak Performance & Resilience - Dr Dorian Dugmore
 
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
 
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
 
Continuous Improvement Posters for Learning
Continuous Improvement Posters for LearningContinuous Improvement Posters for Learning
Continuous Improvement Posters for Learning
 
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...
 
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote SpeakerLeadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
 
Imagine - HR; are handling the 'bad banter' - Stella Chandler.pdf
Imagine - HR; are handling the 'bad banter' - Stella Chandler.pdfImagine - HR; are handling the 'bad banter' - Stella Chandler.pdf
Imagine - HR; are handling the 'bad banter' - Stella Chandler.pdf
 
Imagine - Creating Healthy Workplaces - Anthony Montgomery.pdf
Imagine - Creating Healthy Workplaces - Anthony Montgomery.pdfImagine - Creating Healthy Workplaces - Anthony Montgomery.pdf
Imagine - Creating Healthy Workplaces - Anthony Montgomery.pdf
 
situational leadership theory by Misba Fathima S
situational leadership theory by Misba Fathima Ssituational leadership theory by Misba Fathima S
situational leadership theory by Misba Fathima S
 
Reviewing and summarization of university ranking system to.pptx
Reviewing and summarization of university ranking system  to.pptxReviewing and summarization of university ranking system  to.pptx
Reviewing and summarization of university ranking system to.pptx
 
Empowering Local Government Frontline Services - Mo Baines.pdf
Empowering Local Government Frontline Services - Mo Baines.pdfEmpowering Local Government Frontline Services - Mo Baines.pdf
Empowering Local Government Frontline Services - Mo Baines.pdf
 
internal analysis on strategic management
internal analysis on strategic managementinternal analysis on strategic management
internal analysis on strategic management
 
Continuous Improvement Infographics for Learning
Continuous Improvement Infographics for LearningContinuous Improvement Infographics for Learning
Continuous Improvement Infographics for Learning
 
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
 
LoveLocalGov - Chris Twigg, Inner Circle
LoveLocalGov - Chris Twigg, Inner CircleLoveLocalGov - Chris Twigg, Inner Circle
LoveLocalGov - Chris Twigg, Inner Circle
 
Agile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxAgile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptx
 
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
 
Becoming an Inclusive Leader - Bernadette Thompson
Becoming an Inclusive Leader - Bernadette ThompsonBecoming an Inclusive Leader - Bernadette Thompson
Becoming an Inclusive Leader - Bernadette Thompson
 
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg PartnershipUnlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
 
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTECAbortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
 

PMP Chap 12 - Project Procurement Management Details - Part2

  • 1. By: Anand Bobade (nmbobade@gmail.com) PMBOK Chap 12 – Project Procurement Management The processes necessary to purchase or acquire product, services, or results needed from outside the project team. Initiating Planning Executing Monitoring & Controlling Closing Plan Procurement Management Conduct Procurement Control Procurement Close Procurement We cannot solve our problems with the same thinking we used when we created them. - Albert Einstein Detailed Part-2
  • 2. By: Anand Bobade (nmbobade@gmail.com) Introduction – Procurement Management Processes 12.1 Plan Procurement Management • The process of documenting project procurement decisions, specifying the approach, and identifying potential sellers. 12.2 Conduct Procurement • The process of obtaining seller responses, selecting a seller, and awarding a contract. 12.3 Control Procurement • The process of managing procurement relationships, monitoring contract performance, and making changes and corrections to contracts as appropriate 12.4 Close Procurement • The process of completing each procurement.
  • 3. By: Anand Bobade (nmbobade@gmail.com) Controlling Procurement PM is responsible for Manage relationship Document Performance Monitor and communicate variance Manage Changes
  • 4. By: Anand Bobade (nmbobade@gmail.com) The process of managing procurement relationships, monitoring contract performance, and making changes and corrections to contracts as appropriate. It ensures both seller’s & buyer’s performance meets procurement requirements according to agreement. Managing procurement relationships Monitoring contract performance Making changes and corrections to contracts 12.3 Control Procurement
  • 5. By: Anand Bobade (nmbobade@gmail.com) 12.3 Control Procurement Buyer ensure that they follow through on their own obligations. Quality will suffer if obligations are not met. Schedule/cost will impact if obligation are not meet. Process will ensure adherence to contract/agreements. Buyers Obligation
  • 6. By: Anand Bobade (nmbobade@gmail.com) 12.3 Control Procurement Major processes where Buyer to focus: • Monitor technical performance Technical: Scope Management: • Ensure seller meets agreed milestones Schedule: time Management: • Ensure project cost is within the Budget Budget: Cost Management: • Continually Verify Seller delivers agreed quality Verification: Quality Management • Contract risk has to be mitigated. Risk Mitigation: Risk Management:
  • 7. By: Anand Bobade (nmbobade@gmail.com) 12.3 Control Procurement Multiple Sellers scenario Buyer Seller1 (Buyer for Seller3) Seller3 Seller2 Seller 1: Setup IT infrastructure Seller2 - Develops application Seller 3 – Data Center setup
  • 8. By: Anand Bobade (nmbobade@gmail.com) Inputs (6) • PMP • Procurement documents • Agreements • Approved change requests • Work performance reports • Work performance data Tools & Techniques(7) • Contract change control system • Procurement performance reviews • Inspections and audits • Performance reporting • Payment systems • Claims administration • Records management system Outputs(5) • Work performance information • Change requests • Project management plan updates • Project documents updates • OPA updates By: Anand Bobade (nmbobade@gmail.com) 12.3 Control Procurement -> ITTO
  • 9. By: Anand Bobade (nmbobade@gmail.com) 12.3 Control Procurement ->Input PMP Procurement documents Agreements Approved Change Requests Work Performance Reports Work Performance Data
  • 10. By: Anand Bobade (nmbobade@gmail.com) 12.3 Control Procurement ->Input->Procurement Doc’s Procurement documents Contract Contract Amendments Contract Addendums Technical documentation User Manual Invoices Payment records Contract related documents:
  • 11. By: Anand Bobade (nmbobade@gmail.com) 12.3 Control Procurement ->Input->WPD Work Performance Data The raw observations & measurements related to contract & activities performed as per contract. Deliverables produced Cost - committed Vs incurred Seller invoices (submitted, paid) Quality standards Cost Invoices Deliverables Quality Direct and Manage Project work
  • 12. By: Anand Bobade (nmbobade@gmail.com) 12.3 Control Procurement ->Input-> Work Performance Reports Work Performance Reports The physical or electronic representation of work performance information compiled as reports, to generate decisions, actions, or awareness. Generated reports - IT system generated / Physical Seller performance related documents Technical documentation Work Performance information Monitor & Control Project work Control Procurement
  • 13. By: Anand Bobade (nmbobade@gmail.com) 12.3 Control Procurement ->Input -> Approved Change Requests Approved Change Requests A change request that has been processed through the integrated change control process and approved. Due to change in : Business requirement Technical specification Schedule, Milestone Cost Contract
  • 14. By: Anand Bobade (nmbobade@gmail.com) 12.3 Control Procurement-> T&T Contract Change Control System Procurement Performance Reviews Inspections and audits Performance Reporting Payment Systems Claims Administration Records Management System
  • 15. By: Anand Bobade (nmbobade@gmail.com) 12.3 Control Procurement-> T&T Inspections and audits Procurement Performance Reviews Performance Reporting Inspect Control Records Management System Payment Systems Contract Change Control System Claims Administration General Categorization (Not as per PMBOK):
  • 16. By: Anand Bobade (nmbobade@gmail.com) 12.3 Control Procurement-> T&T->Record Management System Records Management System Processes & tools that are combined to record and retain information about the project. Maintain all Contract related correspondence Contract version control (Amendments/Addendums) Repository of all contract/dispute resolution information It acts as document archive
  • 17. By: Anand Bobade (nmbobade@gmail.com) 12.3 Control Procurement-> T&T->Payment System Payment Systems Oracle financials Microsoft Dynamics Payment is processed accordance with the terms of the contract. Payment is done only after approval of satisfactory work by an project team. Ensure compliance with agreement The system used to provide and track supplier's invoices and payments for services and products.
  • 18. By: Anand Bobade (nmbobade@gmail.com) 12.3 Control Procurement-> T&T->Inspection & Audits Inspections and audits The system used to provide and track supplier's invoices and payments for services and products. Inspect seller deliverables. Audit Seller processes. Verify compliance with contract Verify any weakness in process
  • 19. By: Anand Bobade (nmbobade@gmail.com) 12.3 Control Procurement-> T&T-> Procurement Performance Reviews Procurement Performance Reviews Structured review of seller’s progress to deliver project scope & quality, within cost & on schedule. Performance review objective : To identify seller’s performance • Successes or failures • Progress with respect to the Procurement SOW • Contract noncompliance Allow the buyer to quantify • Seller’s demonstrated ability • Inability to perform work. Review of: Seller‐prepared documentation Buyer inspections Quality audits conducted
  • 20. By: Anand Bobade (nmbobade@gmail.com) 12.3 Control Procurement-> T&T->Performance Reporting Performance Reporting It’s WPI, compiled as reports, to generate decisions, actions, or awareness. Similar to work performance reports, however focus is on contractual performance. Evaluate sellers work performance Verify sellers processes & deliverable compliance
  • 21. By: Anand Bobade (nmbobade@gmail.com) 12.3 Control Procurement-> T&T->CCCS Contract Change Control System Defines process to modify procurement. Component of Integrated change control system: Changes will be Documented Tracked Approved Arbitrate Communicated The system used to collect, track, arbitrate, and communicate changes to a contract. Oracle’s Primavera Contract Management Microsoft SharePoint based Contract Management
  • 22. By: Anand Bobade (nmbobade@gmail.com) 12.3 Control Procurement-> T&T->Claim Administration Claims Administration The process of processing, adjudicating, and communicating contract claims. Claim administrations helps PM to solves disputes. Disputes in large projects with multiple sellers can be very complex. Manage according to the terms of contract. Follow documented procedures. If not resolved follow alternative dispute resolution (ADR) How to resolve disputes
  • 23. By: Anand Bobade (nmbobade@gmail.com) 12.3 Control Procurement ->Output Work Performance Information Change Requests PMP Updates Project Documents Updates OPA Updates
  • 24. By: Anand Bobade (nmbobade@gmail.com) 12.3 Control Procurement ->Output->WPI Work Performance Information Performance data collected from various controlling processes and analyzed in contractual context. Work Performance Data, Work Performance Reports Control Procurement T&T - Inspections and audits, Change Control system, Performance Review (Generates data) Work Performance Information
  • 25. By: Anand Bobade (nmbobade@gmail.com) 12.3 Control Procurement ->Output->change Request Change Requests Processed through Integrated Change Control Requested but unresolved changes which are documented leads to disputes. Change requests going through disputes are not implemented. A formal proposal to modify any document, deliverable, or baseline.
  • 26. By: Anand Bobade (nmbobade@gmail.com) 12.3 Control Procurement ->Output-> PMP Updates PMP Updates Update Project Management plan related documents. Update Procurement Management plan Update schedule (Milestones & Delivery dates )
  • 27. By: Anand Bobade (nmbobade@gmail.com) 12.3 Control Procurement ->Output->OPA Updates OPA Updates Sellers Performance record, Preferred seller list. Correspondence with seller. Lesson Learned
  • 28. By: Anand Bobade (nmbobade@gmail.com) 12.3 Control Procurement -> Process Flow
  • 29. By: Anand Bobade (nmbobade@gmail.com) Introduction – Procurement Management Processes 12.1 Plan Procurement Management • The process of documenting project procurement decisions, specifying the approach, and identifying potential sellers. 12.2 Conduct Procurement • The process of obtaining seller responses, selecting a seller, and awarding a contract. 12.3 Control Procurement • The process of managing procurement relationships, monitoring contract performance, and making changes and corrections to contracts as appropriate 12.4 Close Procurement • The process of completing each procurement.
  • 30. By: Anand Bobade (nmbobade@gmail.com) Procurement 1 Procurement 2 Individual procurement Closure 12.4 Close Procurement The process of completing each procurement. It documents agreements and related documentation for future reference.
  • 31. By: Anand Bobade (nmbobade@gmail.com) 12.4 Close Procurement Early Termination Partial Termination Termination for a Cause Termination for Convenience When to end an Agreement: Seller is delivering as planned/Agreed Long Silence from both parties is not a termination Notice is required to initiate termination Awareness & abiding by terms and conditions is required Complete all administrative task before termination
  • 32. By: Anand Bobade (nmbobade@gmail.com) 12.4 Close Procurement -> ITTO Inputs (2) • Project Management Plan • Procurement Documents Tools & Techniques(3) • Procurement Audits • Procurement Negotiations • Records Management System Outputs(2) • Closed Procurements • OPA Updates
  • 33. By: Anand Bobade (nmbobade@gmail.com) 12.4 Close Procurement ->Inputs PMP Procurement documents
  • 34. By: Anand Bobade (nmbobade@gmail.com) 12.4 Close Procurement -> Inputs -> PMP Procurement Management plan Closure details & Guidelines PMP
  • 35. By: Anand Bobade (nmbobade@gmail.com) 12.4 Close Procurement -> Inputs -> Proc. Documents Procurement documents Procurement documents, Lesson Learned Contractual agreement documents
  • 36. By: Anand Bobade (nmbobade@gmail.com) 12.4 Close Procurement -> T&T Procurement Audits Procurement Negotiations Records Management System
  • 37. By: Anand Bobade (nmbobade@gmail.com) 12.4 Close Procurement -> T&T->Procurement Audits Procurement Audits Structured review of procurement process originating from Plan Procurements through Administer Procurements. Examine & evaluate How was the execution Procurement Audits Was it a best contract? List of success & failures Is the changes implemented correctly?
  • 38. By: Anand Bobade (nmbobade@gmail.com) 12.4 Close Procurement -> T&T->Procurement Negotiations Procurement Negotiations Primary Goal is to final equitable settlement of all outstanding issues, claims, and disputes by negotiation. Alternative dispute resolution ( ADR) ) including mediation or arbitration may be explored if it cant be settled by direct negotiations. When all else fails, litigation in the courts is the least desirable option.
  • 39. By: Anand Bobade (nmbobade@gmail.com) 12.4 Close Procurement -> T&T->Records Management System Records Management System Processes & tools that are combined to record and retain information about the project. Maintain all Contract related correspondence Contract version control (Amendments/Addendums) Repository of all contract/dispute resolution information It acts as document archive
  • 40. By: Anand Bobade (nmbobade@gmail.com) 12.4 Close Procurement ->Output Closed Procurements OPA Updates
  • 41. By: Anand Bobade (nmbobade@gmail.com) 12.4 Close Procurement ->Output->Close Procurement Closed Procurements Closure has to be signed by person with appropriate authority Follows the process agreed in procurement management plan Formal notice is required
  • 42. By: Anand Bobade (nmbobade@gmail.com) 12.4 Close Procurement ->Output->OPA Updates OPA Updates Update procurement documents with final notice & contract closure Update with Acceptance or non-compliance details Update Lessons learned
  • 43. By: Anand Bobade (nmbobade@gmail.com) 12.4 Close Procurement -> Process Flow
  • 44. By: Anand Bobade (nmbobade@gmail.com)
  • 45. By: Anand Bobade (nmbobade@gmail.com) Visit Slide Share website & you will find other Knowledge area presentation… Please share!! Thank You!