SlideShare a Scribd company logo
1 of 35
APPLICATION OF LAST PLANNER SYSTEM TO IMPROVE
LABOUR PRODUCTIVITY AT CONSTRUCTION SITE
NAME – ANSHI V ERMA 1504
GUIDE – Dr. SHAILESH ANGALEKAR
CO- GUIDE – Prof. MANISH KHANDARE
CONTENTS
1. INTRODUCTION
2. AIM
3. OBJECTIVES
4. LITERATURE SURVEY
5. TOOL / PRINCIPLE OF LEAN CONSTRUCTION
6. BARRIERS IN LEAN CONSTRUCTION
7. BENEFITS OF LEAN CONSTRUCTION IN LABOUR PRODUCTIVITY
8. CASE STUDY OF LEAN CONSTRUCTION AND CALCULATION
9. RESULT AND CONCLUSION
10. REFERENCES
2
Lean construction: Is a way to design production system to minimize waste of
materials, time and efforts in order to generate the maximum possible amount of value.
Lean: The core idea is to maximize customer value while minimizing waste.
Simply lean means creating more value for customers within limited resources.
Last planner system: Is the collaborative, commitment based system that integrates pull
planning , make ready plan, look-ahead plan with constraint analysis, weekly work planning
based upon reliable promises, analysis of Percentage of plan completed and reasons for variance.
INTRODUCTION
AIM –
• To study about Application of Lean Construction tool ( L.P.S ) to improve labor productivity .
OBJECTIVE –
• By identify Importance of Lean Construction.
• By identify Tools of Lean Construction.
• By finding Barriers in implementing Lean Construction .
• By studying Case Study of Lean Construction.
• By identify Benefits of Lean Construction .
4
[3]
5
Phase Schedule
Look - Ahead plan
Master Schedule
Weekly work Plan
Feedback and Learning
Progress Tracking
SET MILDSTONE AND KEY DATES
SPECIFY HANDOFFS BETWEEN TRADES
MAKE READY AND INITIATE REPLAN
AS REQUIRED
MEASURE PROGRESS AND REMEDY ISSUES
Should do
Can do
Will do
Doing & Done
Improving
LAST PLANNER SYSTEM
(Fig. Ref. 1)
WHY SHOULD CONSTRUCTION PEOPLE CHOOSE TO USE L.P.S?
A non-technical person can also use L.P.S at site and users such as owners, client or
construction company can use L.P.S to achieve better performance in design and
construction through increased schedule predictability.
. To deliver projects more safely, fast as well as at
reduced cost.
. To build more predictable production program.
. To reduce burden on project management team.
. To help improve the overall production process.
Collaborative Programming
↓↓
Make – Ready Plan
↓↓
Construction Planning
↓↓
Construction Management
↓↓
Measurement, learning and Continual Improvement
(Fig. Ref. 1)
Step1. Collaborative Programming:
. The goal of this process is that all the main participants and specialist contractors are engaged right
from the start in developing and signing up to the master scheduling and the scheduling for each phase.
. Prepare each team member for action together from starting of project.
. Sorts out sequencing as well as issues or difficulty to make smooth work flow.
. Identifies unclear design details.
Step 2. Make – Ready
. Task or things are ready for construction when require.
. Less waste due to certainty of time, material and equipment.
Step 3. Production Evaluation & Planning:
Each last planner leader proposes a construction program for his team In P.E.P meeting and they
identifies if any inter-dependencies between their proposals like resources, equipment and reduce
the burden of over-committing by distributing each task to the team member.
Beneficial to monitoring current activity at site.
Step 4. Construction Management
. Collaboratively monitoring production to keep activities on track.
. Helps to adjust plans in the light of new information according to P.P.C
. Construction is a social process , coordination ,conferences on telephone between the contractors so
that manage/arrange the equipment/resources so that tomorrow’s work will be start on the time in-
spite of last minute adjustment and this is the responsibility of project manager for the set-up and
brief meeting or conversation and it takes not more than 15 minutes.
Step 5. Measurement, Learning & Continual improvement
. Learning together is all about improving project, planning and production process.
. At the end of the task executed at site by measurement we can get to know the reason for variance
and they try to reduce in next activity and this is called continual improvement.
. Last planner measure of predictability of work delivery – percentage of promises
completed on time and at the end of PPC meeting, team member encourages to do next
week activity for more satisfaction.
PROBLEM FACING CONSTRUCTION INDUSTRY
• PLANNING ERROR
• TECHNOLOGY UNAWARENESS
• WASTAGE
• PROJECT DELAY
• Quality
12
LITERATURE SURVEY
Sr. No Title and Publication Author Description
1 Applying lean construction to
Concrete construction project
UNIVERSITY OF HOUSTON
William Fitzgibbon college of Tech
December 2006
Aditi
Javkhedkar
• Introduction of lean in
construction
• Industry.
• Last planner system.
• Employee training
2 Application of lean construction
2012
Engineers
Australia
• Principles or lean construction.
• Eliminating Waste
• Building Information Modeling
• Pull Planning
• Continuous Improvement.
3 Implementing lean construction
Understanding and action
Elsevier, 2013
ghowelll@mmicron.net
Greg Howell
and Glenn
Ballard
• Comparing current practice with
lean.
• Lean Production.
13
Sr. No Title and Publication Author Description
4 Site implementation and assessment
of lean , construction techniques
lean Construction Journal 2005
www.leanconstructionjournal.org
ISSN : 1555 – 1369
O. Salem
J. Solomon
• Introduction of lean techniques.
• Last planner system.
• Case study of lean production system
, Honda U.K
5 Benefits of Building Information
Modeling
May 2011
Mehmet F.
Hergunsel
• Introduction of BIM.
• Tools of BIM.
• 3 D Visualization
• Case study
6 A3 Reports : Tools for Process
Improvement
2009
Durward K.
Sobek
Cindy
Jimmerson
• A3 Problem Solving Report
• Example of A3 Report
14
Tools / Principle of lean construction
1. Just – In – Time ( JIT)
2. Last Planner System ( LPS )
3. A3 Process Design
4 .Value Stream Mapping
5. 5s ( shine , sustain , standardize , sort , straighten )
6. Continues Improvement
7. Building Information Modeling (BIM)
15
Mr. Gregg Howell (Right) & Dr. Glenn Ballard (Left) (Fig. Ref. 1)
Last Planner System
On the basis of research, Glenn Ballard and Greg Howell invented the last planner system to improve
construction productivity in 1980s. It is “The Collaborative, commitment based planning system that integrates
should-can-will-did planning (Pull Planning, Make-Ready plan, Look-ahead plan)with constraint analysis,
weekly work planning based upon reliable promises and learning based upon analysis of PPC (Plan Percentage
Completed) and reasons for variance.”
(Fig. Ref. 1)
(Fig. Ref. 1)
EMPLOYEE NAME WORK
ASSIGNED
MON
3/4/17
TUES
4/4/17
WED
5/4/17
THUR
6/4/17
FRI
7/4/17
SAT
8/4/17
SUN
9/4/17
HOURS
WEEK BEGINNING COMPANY DEPARTMENT
WORK SCHEDULE : WEEKLY
(Fig. Ref. 1)
WORK DONE
• Apply Last Planner System ( LPS ) at Site.
20
21
Site Name – Suvarana Rekha
Location – Prabhat Road
Type of Building – Commercial (7 Floor)
Project Duration – Feb 2012 to Dec 2016
Contractors / Consultancy – Project Management Consultancy.
Execution Consultancy.
Plumbing / Electrical / Water Proofing Consultancy.
Design ( Architecture / RCC / P.T Drawing )
22
23
Productivity of labour after applying L.P.S
Calculation
A. Labour productivity = Output / Labour cost
A. Labour productivity = Output / Work-hour
A. Labour productivity = Labour cost / Output
OR = Work hours / Output
A. Performance factor = Estimated unit rate / Actual unit rate
(Data. Ref. 3)
24
1. For plastering work
Per day work done by the labour = 10 m2 (quantity of material)
(8 hour)
Area covered = 100 ft2
No. of person = 1 skilled labour + 1 unskilled labour + 1 helper
Cost for 1 day = 500 + 350 + 300
= 1150
a. Labour productivity = 100 / 1150 = 0.086 ft2/Rs.
After applying L.P.S = 110 /1150 = 0.095 ft2 / Rs.
a. Labour productivity = 100/ 8 = 12.5 work/hr
After applying L.P.S = 110/8 = 13.75 work/hr
a. Labour productivity = 1150 / 100 = 11.5 Rs/ ft2
After applying L.P.S = 1150/ 110 = 10.45 Rs/ft2
a. Performance factor = 10.45/ 11.5 = 0.9
After applying L.P.S = 11.5/11.5 = 1
25
2. Brick work in foundation and Plinth level with cement mortar
Quantity = 1.25 m3 / day
Work done by mason
Payment for 1 day to mason = 1150 /-
After applying L.P.S work done = 50 m3
Quantity = 1.4 m3/day
a. Labour productivity = 45/1150 = 0.04 m3/Rs.
After L.P.S = 50/1150 = 0.043
a. Labour productivity 45/8 = 5.6 m3/hr
After L.P.S = 50/8 = 6.25 m3/hr
a. Labour productivity = 1150/45 = 25.6
After L.P.S = 1150/ 50 = 23
a. Performance factor = 20.5/25.6 = 0.9
After L.P.S 25.6 / 25.6 = 1
26
For
plasteri
ng
work
About Before
L.P.S
After
L.P.S
By
equatio
n A.
Labour
productivity
0.086
ft2/Rs.
0.095
ft2/Rs
By
equatio
n B.
Labour
productivity
12.5
ft2/hr.
13.75
ft2/hr
By
equatio
n C.
Labour
productivity
11.5
Rs./ft2
10.45
Rs./ft
2
By
equatio
n D.
Performanc
e factor
0.9 1
For
Brick
work
About Before
L.P.S
After
L.P.S
By
equati
on A.
Labour
product
ivity
0.04
m3/Rs.
0.043
m3/Rs
By
equati
on B.
Labour
product
ivity
5.62
m3/hr.
6.25
m3/hr
By
equati
on C.
Labour
product
ivity
25.6
Rs./m3
23
Rs./m3
By
equati
on D.
Perform
ance
factor
0.9 1
0
2
4
6
8
10
12
14
Labour Productivity for
Plastering Work
Performance Factor Labour Productivity for
Brick Work
Performance Factor
Chart Title
before LPS After LPS
LEAN CONSTRUCTION
+ LAST PLANNER
SYSTEM
REDUCE WASTE
TRANSPACENCY
AVOIDE DISPUTES
OPTIMUM USE
OF RESOURCES
BETTER
MONITRING
TIME SAVE
(Fig. Ref. 2)
Barriers in Lean Construction
• Managerial – Lack of management
• Technical – Lack of new technology
• Financial – insufficient finance
• Educational – Lack of knowledge
• Human Attitude – People do not want to accept new technology
• Theory of Toyota Production system do not fit to all firms.
• Medium and short construction sectors are not interested to perform L.P.S at their site.
• Last planner system do not feasible to apply each activity of construction site.
29
Traditional Construction Management Lean Construction Management
Customer is not involving in planning stage Customer, Client, Owner, Contractor, Project Manager everyone
involve from starting.
This is Push Techniques focus to increase productivity of
each activity even if this may be causes of rework,
reduce customer satisfaction.
This is Pull Techniques, main focus is on the proper flow of
activities with reduce error or rework and consideration of
customer’s requirement and satisfaction.
It does not consider adjustment because of the isolated
environment and only Project Manager Work as a boss,
so there are no suggestion or ideas come from the
participants.
This system’s capacity absorb the variation, because of feedback
loop, learning and continual improvement and rapid system
response.
Traditional construction management does not pay
attention to continuous improvement.
And this approach tries to make continuous improvements.
Construction management decision rights centered to
one person that is call project manager.
And in Lean construction, decision power making is distributed
in all those who are involved.
. It does not consider transparency in between the
customers, managers and labors.
It tries to increase transparency between the customers,
managers and labors.
(Fig. Ref. 2)
Project Objectives
Information Planning Work Should
Execute Plan DidResource
Normally a
Big Gap
(Fig. Ref. 1)
Project Objectives
Information Planning Work Should
Last Planner
Process
Will
People
Engagement &
Continuous
Improvement
Can
Production DidResource
(Fig. Ref. 1)
33
Result
By applying lean construction tool (L.P.S) at site, the labour productivity observed by 10 to 20% as
compared to previous. Exp. For plastering it improves 12.5 ft2/hr to 13.75 ft2/hr and performance factor
0.9 to 1. Same as for brick work and other construction work. So it is practically beneficial for the
optimizing resources.
Limitations
1. Participants: Large construction companies are ready to implement after giving training or small workshop, but the
small and medium companies are not much interested to use it.
1. No – one – size – fit – to – all: All firms are not fit in the guidelines or the way of Toyota production system, so all
firms operate their works differently that’s why all firms do not accept easily.
1. Takes time: it is not gives result in short term basis, implementation and then result takes time, overall it requires
time, efforts, engagement of employees to make planning and get together within a week or month.
References
1. Mossman Alan, 2013 paper “Last Planner 5+1 crucial and collaborative conversations for predictable design and
construction delivery.”
2. Amit Shankar Murje, 2014, why Iean construction techniques is better than the traditional project management
approach.
3. Thomas & Maloney has been published in ASCE journal paper “Modelling Construction Labor Productivity”
4. Howell, Gregory A. (1999). "What is Lean Construction" (pdf). Proceedings IGLC-7. Lean Construction Institute. pp.
1–10. Retrieved 31 March 2013.
5. Ballard, Glenn (2000). Last Planner™ System of Production Control (pdf) (Ph.D.). UK: University of Birmingham.
Retrieved 29 March 2013.
6. 2006 Aditi Javknedkar, Lean Construction in concrete construction project.
7. 2005 Mr. O.Salem and J. Salomom, implemented and assessed lean at construction site of Honda U.K
34
THANK You
35

More Related Content

What's hot

Construction scheduling & Cost control
Construction scheduling & Cost controlConstruction scheduling & Cost control
Construction scheduling & Cost controlGuhan M
 
Quality control in construction
Quality control in construction Quality control in construction
Quality control in construction Thanigaivel Asokan
 
Insepction and quality control
Insepction and quality controlInsepction and quality control
Insepction and quality controlSOURAV4798
 
Line of balance in civil engineering
Line of balance in civil engineeringLine of balance in civil engineering
Line of balance in civil engineeringrathodjaydeep2
 
Six Sigma and Construction Industry
Six Sigma and Construction IndustrySix Sigma and Construction Industry
Six Sigma and Construction IndustryMuhammad Ahmad
 
Construction project management
Construction project managementConstruction project management
Construction project managementSenthil Kannan
 
Resource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSPResource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSPSagar Kaptan
 
Construction Project Management
Construction Project Management Construction Project Management
Construction Project Management Rajat Nainwal
 
Lean Construction: From Theory to Implementation
Lean Construction: From Theory to ImplementationLean Construction: From Theory to Implementation
Lean Construction: From Theory to ImplementationAntonius Pompi Bramono
 
Productivity improvement in construction
Productivity  improvement in constructionProductivity  improvement in construction
Productivity improvement in constructionKabilanP1
 
Construction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project ManagementConstruction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project Managementsrinivas2036
 
Value engineering practical
Value engineering practicalValue engineering practical
Value engineering practicalAbada Saad
 
Construction Project management
Construction Project management Construction Project management
Construction Project management Anupama holla
 
THUMB RULE FOR CIVIL WORKS LABOUR PRODUCTIVITY
THUMB RULE FOR CIVIL WORKS LABOUR PRODUCTIVITYTHUMB RULE FOR CIVIL WORKS LABOUR PRODUCTIVITY
THUMB RULE FOR CIVIL WORKS LABOUR PRODUCTIVITYSSudhaVelan
 
Construction Planing & Schedule
Construction Planing & ScheduleConstruction Planing & Schedule
Construction Planing & ScheduleVîñõđ Kůmåř
 
Construction productivity
Construction productivityConstruction productivity
Construction productivitySunil Manjeri
 

What's hot (20)

Construction scheduling & Cost control
Construction scheduling & Cost controlConstruction scheduling & Cost control
Construction scheduling & Cost control
 
Quality control in construction
Quality control in construction Quality control in construction
Quality control in construction
 
Insepction and quality control
Insepction and quality controlInsepction and quality control
Insepction and quality control
 
Line of balance in civil engineering
Line of balance in civil engineeringLine of balance in civil engineering
Line of balance in civil engineering
 
Six Sigma and Construction Industry
Six Sigma and Construction IndustrySix Sigma and Construction Industry
Six Sigma and Construction Industry
 
Construction project management
Construction project managementConstruction project management
Construction project management
 
Is 7272 1 (1)
Is 7272 1 (1)Is 7272 1 (1)
Is 7272 1 (1)
 
Resource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSPResource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSP
 
Construction Project Management
Construction Project Management Construction Project Management
Construction Project Management
 
Lean Construction: From Theory to Implementation
Lean Construction: From Theory to ImplementationLean Construction: From Theory to Implementation
Lean Construction: From Theory to Implementation
 
Productivity improvement in construction
Productivity  improvement in constructionProductivity  improvement in construction
Productivity improvement in construction
 
122 value engineering
122 value engineering122 value engineering
122 value engineering
 
Construction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project ManagementConstruction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project Management
 
Value engineering practical
Value engineering practicalValue engineering practical
Value engineering practical
 
Lean Construction
Lean ConstructionLean Construction
Lean Construction
 
Construction Project management
Construction Project management Construction Project management
Construction Project management
 
THUMB RULE FOR CIVIL WORKS LABOUR PRODUCTIVITY
THUMB RULE FOR CIVIL WORKS LABOUR PRODUCTIVITYTHUMB RULE FOR CIVIL WORKS LABOUR PRODUCTIVITY
THUMB RULE FOR CIVIL WORKS LABOUR PRODUCTIVITY
 
Construction Planing & Schedule
Construction Planing & ScheduleConstruction Planing & Schedule
Construction Planing & Schedule
 
Qaqc in civil construction
Qaqc in civil constructionQaqc in civil construction
Qaqc in civil construction
 
Construction productivity
Construction productivityConstruction productivity
Construction productivity
 

Viewers also liked

Process Improvement using Lean Six Sigma Methodology
Process Improvement using Lean Six Sigma MethodologyProcess Improvement using Lean Six Sigma Methodology
Process Improvement using Lean Six Sigma MethodologyAlvaro Plaza
 
Lean applied in Project Management
Lean applied in Project ManagementLean applied in Project Management
Lean applied in Project ManagementAlvaro Plaza
 
058 Lean Construction (PART 2) Construction productivity
058 Lean Construction  (PART 2) Construction productivity 058 Lean Construction  (PART 2) Construction productivity
058 Lean Construction (PART 2) Construction productivity Dr Fereidoun Dejahang
 
LCI Ireland COP March 2015 Event ( Sponsored by Project Management )
LCI Ireland COP   March 2015 Event ( Sponsored by Project Management )LCI Ireland COP   March 2015 Event ( Sponsored by Project Management )
LCI Ireland COP March 2015 Event ( Sponsored by Project Management )John French
 
Presentation green construction
Presentation   green constructionPresentation   green construction
Presentation green constructionMukhtar Malik
 
Ppt of green building
Ppt of green buildingPpt of green building
Ppt of green buildingpateljatin042
 
Green Building Final Presentation
Green Building Final PresentationGreen Building Final Presentation
Green Building Final PresentationQatar LEEDers
 

Viewers also liked (12)

Process Improvement using Lean Six Sigma Methodology
Process Improvement using Lean Six Sigma MethodologyProcess Improvement using Lean Six Sigma Methodology
Process Improvement using Lean Six Sigma Methodology
 
Lean applied in Project Management
Lean applied in Project ManagementLean applied in Project Management
Lean applied in Project Management
 
058 Lean Construction (PART 2) Construction productivity
058 Lean Construction  (PART 2) Construction productivity 058 Lean Construction  (PART 2) Construction productivity
058 Lean Construction (PART 2) Construction productivity
 
Green Construction
Green ConstructionGreen Construction
Green Construction
 
Last planner workshop
Last planner workshopLast planner workshop
Last planner workshop
 
LCI Ireland COP March 2015 Event ( Sponsored by Project Management )
LCI Ireland COP   March 2015 Event ( Sponsored by Project Management )LCI Ireland COP   March 2015 Event ( Sponsored by Project Management )
LCI Ireland COP March 2015 Event ( Sponsored by Project Management )
 
Presentation green construction
Presentation   green constructionPresentation   green construction
Presentation green construction
 
Ppt of green building
Ppt of green buildingPpt of green building
Ppt of green building
 
Green Building Final Presentation
Green Building Final PresentationGreen Building Final Presentation
Green Building Final Presentation
 
Concrete Mix Design
Concrete Mix DesignConcrete Mix Design
Concrete Mix Design
 
Ppt green
Ppt greenPpt green
Ppt green
 
Green buildings
Green buildingsGreen buildings
Green buildings
 

Similar to Last planner system

Project Management
Project ManagementProject Management
Project ManagementLean Teams
 
Implementation of Last Planner System and Challenges Encountered in an Indian...
Implementation of Last Planner System and Challenges Encountered in an Indian...Implementation of Last Planner System and Challenges Encountered in an Indian...
Implementation of Last Planner System and Challenges Encountered in an Indian...IRJET Journal
 
Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800PRIYANSHU KUMAR
 
Project Management Toolkit - Presentation
Project Management Toolkit - PresentationProject Management Toolkit - Presentation
Project Management Toolkit - PresentationHassan Rizwan
 
ACHAL_JOSHI_Academic_Profile
ACHAL_JOSHI_Academic_ProfileACHAL_JOSHI_Academic_Profile
ACHAL_JOSHI_Academic_ProfileACHAL JOSHI
 
My 5 Learnings of Waterfall Project Management
My 5 Learnings of Waterfall Project ManagementMy 5 Learnings of Waterfall Project Management
My 5 Learnings of Waterfall Project ManagementSHAZEBALIKHAN1
 
7. implementation (1) time management
7. implementation (1)   time management 7. implementation (1)   time management
7. implementation (1) time management Dania Abdel-aziz
 
Scheduling and Financial Analysis of a High Rise Building
Scheduling and Financial Analysis of a High Rise BuildingScheduling and Financial Analysis of a High Rise Building
Scheduling and Financial Analysis of a High Rise Buildingiosrjce
 
Brief introduction to project management and project management tools
Brief introduction to project management and project management toolsBrief introduction to project management and project management tools
Brief introduction to project management and project management toolsNathan Petralia
 
Introduction to Scrum.ppt
Introduction to Scrum.pptIntroduction to Scrum.ppt
Introduction to Scrum.pptMohan Late
 
Howe Street Basic Project Approach
Howe Street Basic Project ApproachHowe Street Basic Project Approach
Howe Street Basic Project ApproachJasonLhota1
 
Glen Ballard Last Planner Lean Construction Institute
Glen Ballard Last Planner Lean Construction InstituteGlen Ballard Last Planner Lean Construction Institute
Glen Ballard Last Planner Lean Construction InstituteYefersonCcoyllulle1
 
Resource-Allocation.ppt
Resource-Allocation.pptResource-Allocation.ppt
Resource-Allocation.pptTecnicoItca
 
STUDY AND IMPLEMENTATION OF LAST PLANNER SYSTEM (LPS) IN CONSTRUCTION PROJECTS
STUDY AND IMPLEMENTATION OF LAST PLANNER SYSTEM (LPS) IN CONSTRUCTION PROJECTSSTUDY AND IMPLEMENTATION OF LAST PLANNER SYSTEM (LPS) IN CONSTRUCTION PROJECTS
STUDY AND IMPLEMENTATION OF LAST PLANNER SYSTEM (LPS) IN CONSTRUCTION PROJECTSIRJET Journal
 
Lci la chapter lean intro 071410 no pics
Lci la chapter lean intro 071410 no picsLci la chapter lean intro 071410 no pics
Lci la chapter lean intro 071410 no picshaganone
 

Similar to Last planner system (20)

Project Management
Project ManagementProject Management
Project Management
 
Implementation of Last Planner System and Challenges Encountered in an Indian...
Implementation of Last Planner System and Challenges Encountered in an Indian...Implementation of Last Planner System and Challenges Encountered in an Indian...
Implementation of Last Planner System and Challenges Encountered in an Indian...
 
Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800
 
Project Management Toolkit - Presentation
Project Management Toolkit - PresentationProject Management Toolkit - Presentation
Project Management Toolkit - Presentation
 
ACHAL_JOSHI_Academic_Profile
ACHAL_JOSHI_Academic_ProfileACHAL_JOSHI_Academic_Profile
ACHAL_JOSHI_Academic_Profile
 
My 5 Learnings of Waterfall Project Management
My 5 Learnings of Waterfall Project ManagementMy 5 Learnings of Waterfall Project Management
My 5 Learnings of Waterfall Project Management
 
7. implementation (1) time management
7. implementation (1)   time management 7. implementation (1)   time management
7. implementation (1) time management
 
A012610106
A012610106A012610106
A012610106
 
Scheduling and Financial Analysis of a High Rise Building
Scheduling and Financial Analysis of a High Rise BuildingScheduling and Financial Analysis of a High Rise Building
Scheduling and Financial Analysis of a High Rise Building
 
Brief introduction to project management and project management tools
Brief introduction to project management and project management toolsBrief introduction to project management and project management tools
Brief introduction to project management and project management tools
 
Introduction to Scrum.ppt
Introduction to Scrum.pptIntroduction to Scrum.ppt
Introduction to Scrum.ppt
 
CSRA Havranek Hostetter Palisade 2012
CSRA Havranek Hostetter Palisade 2012CSRA Havranek Hostetter Palisade 2012
CSRA Havranek Hostetter Palisade 2012
 
Howe Street Basic Project Approach
Howe Street Basic Project ApproachHowe Street Basic Project Approach
Howe Street Basic Project Approach
 
Glen Ballard Last Planner Lean Construction Institute
Glen Ballard Last Planner Lean Construction InstituteGlen Ballard Last Planner Lean Construction Institute
Glen Ballard Last Planner Lean Construction Institute
 
Project Management Basics
Project Management BasicsProject Management Basics
Project Management Basics
 
Lean construction
Lean constructionLean construction
Lean construction
 
Resource-Allocation.ppt
Resource-Allocation.pptResource-Allocation.ppt
Resource-Allocation.ppt
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 
STUDY AND IMPLEMENTATION OF LAST PLANNER SYSTEM (LPS) IN CONSTRUCTION PROJECTS
STUDY AND IMPLEMENTATION OF LAST PLANNER SYSTEM (LPS) IN CONSTRUCTION PROJECTSSTUDY AND IMPLEMENTATION OF LAST PLANNER SYSTEM (LPS) IN CONSTRUCTION PROJECTS
STUDY AND IMPLEMENTATION OF LAST PLANNER SYSTEM (LPS) IN CONSTRUCTION PROJECTS
 
Lci la chapter lean intro 071410 no pics
Lci la chapter lean intro 071410 no picsLci la chapter lean intro 071410 no pics
Lci la chapter lean intro 071410 no pics
 

Recently uploaded

Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Crystal Structure analysis and detailed information pptx
Crystal Structure analysis and detailed information pptxCrystal Structure analysis and detailed information pptx
Crystal Structure analysis and detailed information pptxachiever3003
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
home automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasadhome automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasadaditya806802
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...121011101441
 
Indian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptIndian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptMadan Karki
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substationstephanwindworld
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionMebane Rash
 
Crushers to screens in aggregate production
Crushers to screens in aggregate productionCrushers to screens in aggregate production
Crushers to screens in aggregate productionChinnuNinan
 
Autonomous emergency braking system (aeb) ppt.ppt
Autonomous emergency braking system (aeb) ppt.pptAutonomous emergency braking system (aeb) ppt.ppt
Autonomous emergency braking system (aeb) ppt.pptbibisarnayak0
 
BSNL Internship Training presentation.pptx
BSNL Internship Training presentation.pptxBSNL Internship Training presentation.pptx
BSNL Internship Training presentation.pptxNiranjanYadav41
 
Energy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxEnergy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxsiddharthjain2303
 
multiple access in wireless communication
multiple access in wireless communicationmultiple access in wireless communication
multiple access in wireless communicationpanditadesh123
 
"Exploring the Essential Functions and Design Considerations of Spillways in ...
"Exploring the Essential Functions and Design Considerations of Spillways in ..."Exploring the Essential Functions and Design Considerations of Spillways in ...
"Exploring the Essential Functions and Design Considerations of Spillways in ...Erbil Polytechnic University
 
Industrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.pptIndustrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.pptNarmatha D
 
Class 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm SystemClass 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm Systemirfanmechengr
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
Main Memory Management in Operating System
Main Memory Management in Operating SystemMain Memory Management in Operating System
Main Memory Management in Operating SystemRashmi Bhat
 

Recently uploaded (20)

Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Crystal Structure analysis and detailed information pptx
Crystal Structure analysis and detailed information pptxCrystal Structure analysis and detailed information pptx
Crystal Structure analysis and detailed information pptx
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
home automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasadhome automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasad
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...
 
Indian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptIndian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.ppt
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substation
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of Action
 
Crushers to screens in aggregate production
Crushers to screens in aggregate productionCrushers to screens in aggregate production
Crushers to screens in aggregate production
 
Autonomous emergency braking system (aeb) ppt.ppt
Autonomous emergency braking system (aeb) ppt.pptAutonomous emergency braking system (aeb) ppt.ppt
Autonomous emergency braking system (aeb) ppt.ppt
 
Designing pile caps according to ACI 318-19.pptx
Designing pile caps according to ACI 318-19.pptxDesigning pile caps according to ACI 318-19.pptx
Designing pile caps according to ACI 318-19.pptx
 
BSNL Internship Training presentation.pptx
BSNL Internship Training presentation.pptxBSNL Internship Training presentation.pptx
BSNL Internship Training presentation.pptx
 
Energy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxEnergy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptx
 
multiple access in wireless communication
multiple access in wireless communicationmultiple access in wireless communication
multiple access in wireless communication
 
"Exploring the Essential Functions and Design Considerations of Spillways in ...
"Exploring the Essential Functions and Design Considerations of Spillways in ..."Exploring the Essential Functions and Design Considerations of Spillways in ...
"Exploring the Essential Functions and Design Considerations of Spillways in ...
 
Industrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.pptIndustrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.ppt
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
Class 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm SystemClass 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm System
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
Main Memory Management in Operating System
Main Memory Management in Operating SystemMain Memory Management in Operating System
Main Memory Management in Operating System
 

Last planner system

  • 1. APPLICATION OF LAST PLANNER SYSTEM TO IMPROVE LABOUR PRODUCTIVITY AT CONSTRUCTION SITE NAME – ANSHI V ERMA 1504 GUIDE – Dr. SHAILESH ANGALEKAR CO- GUIDE – Prof. MANISH KHANDARE
  • 2. CONTENTS 1. INTRODUCTION 2. AIM 3. OBJECTIVES 4. LITERATURE SURVEY 5. TOOL / PRINCIPLE OF LEAN CONSTRUCTION 6. BARRIERS IN LEAN CONSTRUCTION 7. BENEFITS OF LEAN CONSTRUCTION IN LABOUR PRODUCTIVITY 8. CASE STUDY OF LEAN CONSTRUCTION AND CALCULATION 9. RESULT AND CONCLUSION 10. REFERENCES 2
  • 3. Lean construction: Is a way to design production system to minimize waste of materials, time and efforts in order to generate the maximum possible amount of value. Lean: The core idea is to maximize customer value while minimizing waste. Simply lean means creating more value for customers within limited resources. Last planner system: Is the collaborative, commitment based system that integrates pull planning , make ready plan, look-ahead plan with constraint analysis, weekly work planning based upon reliable promises, analysis of Percentage of plan completed and reasons for variance. INTRODUCTION
  • 4. AIM – • To study about Application of Lean Construction tool ( L.P.S ) to improve labor productivity . OBJECTIVE – • By identify Importance of Lean Construction. • By identify Tools of Lean Construction. • By finding Barriers in implementing Lean Construction . • By studying Case Study of Lean Construction. • By identify Benefits of Lean Construction . 4
  • 6. Phase Schedule Look - Ahead plan Master Schedule Weekly work Plan Feedback and Learning Progress Tracking SET MILDSTONE AND KEY DATES SPECIFY HANDOFFS BETWEEN TRADES MAKE READY AND INITIATE REPLAN AS REQUIRED MEASURE PROGRESS AND REMEDY ISSUES Should do Can do Will do Doing & Done Improving LAST PLANNER SYSTEM (Fig. Ref. 1)
  • 7. WHY SHOULD CONSTRUCTION PEOPLE CHOOSE TO USE L.P.S? A non-technical person can also use L.P.S at site and users such as owners, client or construction company can use L.P.S to achieve better performance in design and construction through increased schedule predictability. . To deliver projects more safely, fast as well as at reduced cost. . To build more predictable production program. . To reduce burden on project management team. . To help improve the overall production process.
  • 8. Collaborative Programming ↓↓ Make – Ready Plan ↓↓ Construction Planning ↓↓ Construction Management ↓↓ Measurement, learning and Continual Improvement (Fig. Ref. 1)
  • 9. Step1. Collaborative Programming: . The goal of this process is that all the main participants and specialist contractors are engaged right from the start in developing and signing up to the master scheduling and the scheduling for each phase. . Prepare each team member for action together from starting of project. . Sorts out sequencing as well as issues or difficulty to make smooth work flow. . Identifies unclear design details. Step 2. Make – Ready . Task or things are ready for construction when require. . Less waste due to certainty of time, material and equipment.
  • 10. Step 3. Production Evaluation & Planning: Each last planner leader proposes a construction program for his team In P.E.P meeting and they identifies if any inter-dependencies between their proposals like resources, equipment and reduce the burden of over-committing by distributing each task to the team member. Beneficial to monitoring current activity at site. Step 4. Construction Management . Collaboratively monitoring production to keep activities on track. . Helps to adjust plans in the light of new information according to P.P.C . Construction is a social process , coordination ,conferences on telephone between the contractors so that manage/arrange the equipment/resources so that tomorrow’s work will be start on the time in- spite of last minute adjustment and this is the responsibility of project manager for the set-up and brief meeting or conversation and it takes not more than 15 minutes.
  • 11. Step 5. Measurement, Learning & Continual improvement . Learning together is all about improving project, planning and production process. . At the end of the task executed at site by measurement we can get to know the reason for variance and they try to reduce in next activity and this is called continual improvement. . Last planner measure of predictability of work delivery – percentage of promises completed on time and at the end of PPC meeting, team member encourages to do next week activity for more satisfaction.
  • 12. PROBLEM FACING CONSTRUCTION INDUSTRY • PLANNING ERROR • TECHNOLOGY UNAWARENESS • WASTAGE • PROJECT DELAY • Quality 12
  • 13. LITERATURE SURVEY Sr. No Title and Publication Author Description 1 Applying lean construction to Concrete construction project UNIVERSITY OF HOUSTON William Fitzgibbon college of Tech December 2006 Aditi Javkhedkar • Introduction of lean in construction • Industry. • Last planner system. • Employee training 2 Application of lean construction 2012 Engineers Australia • Principles or lean construction. • Eliminating Waste • Building Information Modeling • Pull Planning • Continuous Improvement. 3 Implementing lean construction Understanding and action Elsevier, 2013 ghowelll@mmicron.net Greg Howell and Glenn Ballard • Comparing current practice with lean. • Lean Production. 13
  • 14. Sr. No Title and Publication Author Description 4 Site implementation and assessment of lean , construction techniques lean Construction Journal 2005 www.leanconstructionjournal.org ISSN : 1555 – 1369 O. Salem J. Solomon • Introduction of lean techniques. • Last planner system. • Case study of lean production system , Honda U.K 5 Benefits of Building Information Modeling May 2011 Mehmet F. Hergunsel • Introduction of BIM. • Tools of BIM. • 3 D Visualization • Case study 6 A3 Reports : Tools for Process Improvement 2009 Durward K. Sobek Cindy Jimmerson • A3 Problem Solving Report • Example of A3 Report 14
  • 15. Tools / Principle of lean construction 1. Just – In – Time ( JIT) 2. Last Planner System ( LPS ) 3. A3 Process Design 4 .Value Stream Mapping 5. 5s ( shine , sustain , standardize , sort , straighten ) 6. Continues Improvement 7. Building Information Modeling (BIM) 15
  • 16. Mr. Gregg Howell (Right) & Dr. Glenn Ballard (Left) (Fig. Ref. 1) Last Planner System On the basis of research, Glenn Ballard and Greg Howell invented the last planner system to improve construction productivity in 1980s. It is “The Collaborative, commitment based planning system that integrates should-can-will-did planning (Pull Planning, Make-Ready plan, Look-ahead plan)with constraint analysis, weekly work planning based upon reliable promises and learning based upon analysis of PPC (Plan Percentage Completed) and reasons for variance.”
  • 20. WORK DONE • Apply Last Planner System ( LPS ) at Site. 20
  • 21. 21 Site Name – Suvarana Rekha Location – Prabhat Road Type of Building – Commercial (7 Floor) Project Duration – Feb 2012 to Dec 2016 Contractors / Consultancy – Project Management Consultancy. Execution Consultancy. Plumbing / Electrical / Water Proofing Consultancy. Design ( Architecture / RCC / P.T Drawing )
  • 22. 22
  • 23. 23 Productivity of labour after applying L.P.S Calculation A. Labour productivity = Output / Labour cost A. Labour productivity = Output / Work-hour A. Labour productivity = Labour cost / Output OR = Work hours / Output A. Performance factor = Estimated unit rate / Actual unit rate (Data. Ref. 3)
  • 24. 24 1. For plastering work Per day work done by the labour = 10 m2 (quantity of material) (8 hour) Area covered = 100 ft2 No. of person = 1 skilled labour + 1 unskilled labour + 1 helper Cost for 1 day = 500 + 350 + 300 = 1150 a. Labour productivity = 100 / 1150 = 0.086 ft2/Rs. After applying L.P.S = 110 /1150 = 0.095 ft2 / Rs. a. Labour productivity = 100/ 8 = 12.5 work/hr After applying L.P.S = 110/8 = 13.75 work/hr a. Labour productivity = 1150 / 100 = 11.5 Rs/ ft2 After applying L.P.S = 1150/ 110 = 10.45 Rs/ft2 a. Performance factor = 10.45/ 11.5 = 0.9 After applying L.P.S = 11.5/11.5 = 1
  • 25. 25 2. Brick work in foundation and Plinth level with cement mortar Quantity = 1.25 m3 / day Work done by mason Payment for 1 day to mason = 1150 /- After applying L.P.S work done = 50 m3 Quantity = 1.4 m3/day a. Labour productivity = 45/1150 = 0.04 m3/Rs. After L.P.S = 50/1150 = 0.043 a. Labour productivity 45/8 = 5.6 m3/hr After L.P.S = 50/8 = 6.25 m3/hr a. Labour productivity = 1150/45 = 25.6 After L.P.S = 1150/ 50 = 23 a. Performance factor = 20.5/25.6 = 0.9 After L.P.S 25.6 / 25.6 = 1
  • 26. 26 For plasteri ng work About Before L.P.S After L.P.S By equatio n A. Labour productivity 0.086 ft2/Rs. 0.095 ft2/Rs By equatio n B. Labour productivity 12.5 ft2/hr. 13.75 ft2/hr By equatio n C. Labour productivity 11.5 Rs./ft2 10.45 Rs./ft 2 By equatio n D. Performanc e factor 0.9 1 For Brick work About Before L.P.S After L.P.S By equati on A. Labour product ivity 0.04 m3/Rs. 0.043 m3/Rs By equati on B. Labour product ivity 5.62 m3/hr. 6.25 m3/hr By equati on C. Labour product ivity 25.6 Rs./m3 23 Rs./m3 By equati on D. Perform ance factor 0.9 1
  • 27. 0 2 4 6 8 10 12 14 Labour Productivity for Plastering Work Performance Factor Labour Productivity for Brick Work Performance Factor Chart Title before LPS After LPS
  • 28. LEAN CONSTRUCTION + LAST PLANNER SYSTEM REDUCE WASTE TRANSPACENCY AVOIDE DISPUTES OPTIMUM USE OF RESOURCES BETTER MONITRING TIME SAVE (Fig. Ref. 2)
  • 29. Barriers in Lean Construction • Managerial – Lack of management • Technical – Lack of new technology • Financial – insufficient finance • Educational – Lack of knowledge • Human Attitude – People do not want to accept new technology • Theory of Toyota Production system do not fit to all firms. • Medium and short construction sectors are not interested to perform L.P.S at their site. • Last planner system do not feasible to apply each activity of construction site. 29
  • 30. Traditional Construction Management Lean Construction Management Customer is not involving in planning stage Customer, Client, Owner, Contractor, Project Manager everyone involve from starting. This is Push Techniques focus to increase productivity of each activity even if this may be causes of rework, reduce customer satisfaction. This is Pull Techniques, main focus is on the proper flow of activities with reduce error or rework and consideration of customer’s requirement and satisfaction. It does not consider adjustment because of the isolated environment and only Project Manager Work as a boss, so there are no suggestion or ideas come from the participants. This system’s capacity absorb the variation, because of feedback loop, learning and continual improvement and rapid system response. Traditional construction management does not pay attention to continuous improvement. And this approach tries to make continuous improvements. Construction management decision rights centered to one person that is call project manager. And in Lean construction, decision power making is distributed in all those who are involved. . It does not consider transparency in between the customers, managers and labors. It tries to increase transparency between the customers, managers and labors. (Fig. Ref. 2)
  • 31. Project Objectives Information Planning Work Should Execute Plan DidResource Normally a Big Gap (Fig. Ref. 1)
  • 32. Project Objectives Information Planning Work Should Last Planner Process Will People Engagement & Continuous Improvement Can Production DidResource (Fig. Ref. 1)
  • 33. 33 Result By applying lean construction tool (L.P.S) at site, the labour productivity observed by 10 to 20% as compared to previous. Exp. For plastering it improves 12.5 ft2/hr to 13.75 ft2/hr and performance factor 0.9 to 1. Same as for brick work and other construction work. So it is practically beneficial for the optimizing resources. Limitations 1. Participants: Large construction companies are ready to implement after giving training or small workshop, but the small and medium companies are not much interested to use it. 1. No – one – size – fit – to – all: All firms are not fit in the guidelines or the way of Toyota production system, so all firms operate their works differently that’s why all firms do not accept easily. 1. Takes time: it is not gives result in short term basis, implementation and then result takes time, overall it requires time, efforts, engagement of employees to make planning and get together within a week or month.
  • 34. References 1. Mossman Alan, 2013 paper “Last Planner 5+1 crucial and collaborative conversations for predictable design and construction delivery.” 2. Amit Shankar Murje, 2014, why Iean construction techniques is better than the traditional project management approach. 3. Thomas & Maloney has been published in ASCE journal paper “Modelling Construction Labor Productivity” 4. Howell, Gregory A. (1999). "What is Lean Construction" (pdf). Proceedings IGLC-7. Lean Construction Institute. pp. 1–10. Retrieved 31 March 2013. 5. Ballard, Glenn (2000). Last Planner™ System of Production Control (pdf) (Ph.D.). UK: University of Birmingham. Retrieved 29 March 2013. 6. 2006 Aditi Javknedkar, Lean Construction in concrete construction project. 7. 2005 Mr. O.Salem and J. Salomom, implemented and assessed lean at construction site of Honda U.K 34