Interstate 5:NE 45th to NE 145th Full Depth HMA Reconstruction
Location Location Interstate 5 Northbound Lanes from North 45th Street to North 145th Street
Overview Location Interstate 5 Northbound Lanes from North 45th Street to North 145th Street Task Remove Current PCC Slabs Replace PCC with HMA Goals Reduce Cost Reduce Traffic Impacts Create a long lasting Sustainable Pavement
Existing Conditions Current Condition is Poor to Very Poor Built in the Early 1960s with a Design Life of 20 Years 9-inch thick PCC panels that are 15ft in length by 12 ft in width 11ft Lanes Extensive Panel Cracking and Faulting of Traverse Joints Extensive Wheel Path Wear and Pavement Surface Polishing Uncomfortable for Users Verge of not being able to Serve Traffic
Overall Scope I-5 Northbound  NE 45th St to NE 145th St Remove 9” PCC and Replace with 13” HMA and 9” base Two Phases 5.2 miles at 21.2 lane miles total
Scope:  Phase one Phase one NE 45th to Northgate Way overpass-express lanes Approximately 10.5 lane miles 3-4 lanes
Scope:  Phase two Phase two Northgate Way overpass to NE 145thSt- no express lanes Approximately 10.7 lane miles 5-6 lanes
Cost Construction (CA4PRS) Construction Costs:	$12,700,000 Roadway Costs:	$16,000,000 Supporting Costs:	$300,000 Total Cost:		$29,000,000 Agency (Real Cost) Life Cycle Agency Costs will be $25,000,000 LCCA (Real Cost) Life Cycle User Costs will be $16,000,000
Construction Time Phase 1 Begin on July 17th (After Independence Day) Continuous Closure Maximum Closure of 2 weeks Phase 2 Begin on August 7th Continuous Closure Maximum Closure of 2 weeks (Finish before Labor Day)
Construction Maintain three lanes of traffic at all times Allow one lane for equipment and trucks to passing at all times Excavate and replace with crushed aggregate quickly
Sequencing: Phase one Crossover to express lanes Extend third lane:  express lanes to main line Demolition & Excavation Grading & Paving
Sequencing: Phase two Remove crossover to express lanes Remove third lane:  express lanes to main line Left three lane then right lanes Demolition & Excavation Grading & Paving
Equipment
HMA Plant Location ICON Materials will be contracted to supply HMA and aggregate from their Auburn Aggregate Resource and Asphalt Plant located in Auburn WA Plant Produces 500 tons/hr when aggregate is wet and 600 tons/hr when the aggregate is dry Average trucking time from the plant to site is 40 minutes during normal conditions and 70 minutes during heavy traffic
Demolition Materials
Productivity Phase 1 Using 87% confidence interval productivity will be 6.55 lane miles per 7 day closure Requires two 7 day closures HMA trucks are greatest limit to productivity Phase 2 Using 87% confidence interval productivity will be 6.50 lane miles per 7 day  closure Requires two 7 day closures HMA trucks are greatest limit to productivity
Closures Phase 1 (45th St. to Northgate Way) Closes Friday July 17th 2015 at 11pm  Must reopen by Monday August 2nd 2015 at 4am Phase 2 (Northgate Way to 145th St.) Closes Friday August 7th 2015 at 11pm Must reopen by Monday August 24th 2015 at 4am
Alternative Routes SR-99  Aurora SR-522  Lake City/Bothell Way NE 15th Ave NE 11th/12th Ave NE 25th Ave NE Phinney/Greenwood Ave N
Traffic Impacts: Phase one Minimum impact southbound 20.3 mile maximum queue  $25 million user cost 25% no show 15% detour
Traffic Impacts: Phase two Less impact southbound than phase one  26.4 mile maximum queue  $25 million user cost 25% no show 15% detour
Critical Resources HMA Plant Plant is producing maximum capacity  to provide for this project HMA Hauling Trucks High Spearman Correlation Coefficient Dependent upon plant production Travel (coffee stops, traffic, etc.)
Backup Plans The Seattle Asphalt Plant owned by ICON Materials will be on standby incase the main plant faults Located in the South Park neighborhood of South Seattle Produces 250 tons/hr when aggregate is wet and 300 tons/hr when aggregate is dry Average trucking time from this plant to the site is estimated to be 18 minutes in normal conditions and 30 minutes in heavy traffic Extra equipment such as pavers, buggies, rollers and dump trucks will be stored at the temporary storage facilities
Public Awareness
Potential Cost Savings Warm Mix Asphalt (WMA) Recycled Concrete
WMA vs. HMA I-90 WSDOT study near George, WA Less fuel consumed Lower CO2 quantities produced
Near Site  Recycled Concrete Cost Savings Savings of $5 to $10 per ton $316,400 to $632,800 for the project Environmental Savings Less aggregate Less CO2 Blah
Questions http://www.youtube.com/watch?v=9QS0q3mGPGg

More Related Content

What's hot

Forest hill station open house
Forest hill station open house Forest hill station open house
Forest hill station open house
Crosstown TO
 
Avenue Station Open House - May 2017
Avenue Station Open House - May 2017Avenue Station Open House - May 2017
Avenue Station Open House - May 2017
Crosstown TO
 
Leaside - Laird Construction Liaison Committee Meeting - June 2017
Leaside - Laird Construction Liaison Committee Meeting - June 2017Leaside - Laird Construction Liaison Committee Meeting - June 2017
Leaside - Laird Construction Liaison Committee Meeting - June 2017
Crosstown TO
 
Laird Station Open House - April 2017
Laird Station Open House - April 2017Laird Station Open House - April 2017
Laird Station Open House - April 2017
Crosstown TO
 
Senior Design Presntation - Spring Term
Senior Design Presntation - Spring TermSenior Design Presntation - Spring Term
Senior Design Presntation - Spring Term
Steven E. Kreeley, EIT
 

What's hot (20)

Forest hill station open house
Forest hill station open house Forest hill station open house
Forest hill station open house
 
Okeechobee Road from Krome Avenue to NW 79 Avenue PD&E Study presentation, Ju...
Okeechobee Road from Krome Avenue to NW 79 Avenue PD&E Study presentation, Ju...Okeechobee Road from Krome Avenue to NW 79 Avenue PD&E Study presentation, Ju...
Okeechobee Road from Krome Avenue to NW 79 Avenue PD&E Study presentation, Ju...
 
Oct. 17, 2016 town hall meeting presentation
Oct. 17, 2016 town hall meeting presentation Oct. 17, 2016 town hall meeting presentation
Oct. 17, 2016 town hall meeting presentation
 
injo slip update
injo slip updateinjo slip update
injo slip update
 
Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016
Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016
Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016
 
River bore fact sheet_final
River bore fact sheet_finalRiver bore fact sheet_final
River bore fact sheet_final
 
14.30 tarek shuaib, pace
14.30 tarek shuaib, pace14.30 tarek shuaib, pace
14.30 tarek shuaib, pace
 
Avenue Station Open House - May 2017
Avenue Station Open House - May 2017Avenue Station Open House - May 2017
Avenue Station Open House - May 2017
 
Leaside - Laird Construction Liaison Committee Meeting - June 2017
Leaside - Laird Construction Liaison Committee Meeting - June 2017Leaside - Laird Construction Liaison Committee Meeting - June 2017
Leaside - Laird Construction Liaison Committee Meeting - June 2017
 
H3 New Conveyer Logistics
H3 New Conveyer LogisticsH3 New Conveyer Logistics
H3 New Conveyer Logistics
 
Laird Station Open House - April 2017
Laird Station Open House - April 2017Laird Station Open House - April 2017
Laird Station Open House - April 2017
 
Project portfolio mark rannel gamayo
Project portfolio mark rannel gamayoProject portfolio mark rannel gamayo
Project portfolio mark rannel gamayo
 
Nelson Perez Jacome - Utility Emergency Response
Nelson Perez Jacome - Utility Emergency ResponseNelson Perez Jacome - Utility Emergency Response
Nelson Perez Jacome - Utility Emergency Response
 
Pardon Our Dust meeting, March 9, 2016
Pardon Our Dust meeting, March 9, 2016Pardon Our Dust meeting, March 9, 2016
Pardon Our Dust meeting, March 9, 2016
 
Diverging Diamond Interchange: I-66 and Route 15
Diverging Diamond Interchange: I-66 and Route 15Diverging Diamond Interchange: I-66 and Route 15
Diverging Diamond Interchange: I-66 and Route 15
 
Backlick Run Gravity Sewer Abandonment Project June 2020
Backlick Run Gravity Sewer Abandonment Project June 2020Backlick Run Gravity Sewer Abandonment Project June 2020
Backlick Run Gravity Sewer Abandonment Project June 2020
 
Senior Design Presntation - Spring Term
Senior Design Presntation - Spring TermSenior Design Presntation - Spring Term
Senior Design Presntation - Spring Term
 
Dcl hdd presentation 9 2-2014
Dcl hdd presentation 9 2-2014Dcl hdd presentation 9 2-2014
Dcl hdd presentation 9 2-2014
 
Project report
Project reportProject report
Project report
 
Gulpur Hydropower Plant Project Full Report 2019
Gulpur Hydropower Plant Project Full Report 2019Gulpur Hydropower Plant Project Full Report 2019
Gulpur Hydropower Plant Project Full Report 2019
 

Viewers also liked (6)

Amigo es
Amigo esAmigo es
Amigo es
 
Connecting to the LIS Online Community: Developing a PLN
Connecting to the LIS Online Community: Developing a PLNConnecting to the LIS Online Community: Developing a PLN
Connecting to the LIS Online Community: Developing a PLN
 
Analysis of Online Information Management
Analysis of Online Information Management Analysis of Online Information Management
Analysis of Online Information Management
 
Algo especial -avrenim2003
Algo especial -avrenim2003Algo especial -avrenim2003
Algo especial -avrenim2003
 
2013 uk digital future in focus
2013 uk digital future in focus 2013 uk digital future in focus
2013 uk digital future in focus
 
BRAND conversation
BRAND conversationBRAND conversation
BRAND conversation
 

Similar to 404 presentation

Pharmacy to kennedy construction liaison committee meeting - June 2018
Pharmacy to kennedy construction liaison committee meeting - June 2018Pharmacy to kennedy construction liaison committee meeting - June 2018
Pharmacy to kennedy construction liaison committee meeting - June 2018
Crosstown TO
 
BT_TatuanuiCaseStudy_F
BT_TatuanuiCaseStudy_FBT_TatuanuiCaseStudy_F
BT_TatuanuiCaseStudy_F
philip dobson
 
Eglinton Crosstown Update
Eglinton Crosstown UpdateEglinton Crosstown Update
Eglinton Crosstown Update
Crosstown TO
 
Chaplin - Avenue Construction Liaison Committee - July 2018
Chaplin - Avenue Construction Liaison Committee - July 2018Chaplin - Avenue Construction Liaison Committee - July 2018
Chaplin - Avenue Construction Liaison Committee - July 2018
Crosstown TO
 
2009-11_UTA-SL Chamber Airport TRAX et al
2009-11_UTA-SL Chamber Airport TRAX et al2009-11_UTA-SL Chamber Airport TRAX et al
2009-11_UTA-SL Chamber Airport TRAX et al
Salt Lake Chamber
 
Cold In-Place Recycling (Foamed Asphalt) PowerPoint
Cold In-Place Recycling (Foamed Asphalt) PowerPointCold In-Place Recycling (Foamed Asphalt) PowerPoint
Cold In-Place Recycling (Foamed Asphalt) PowerPoint
Dennis McElroy
 

Similar to 404 presentation (20)

Canalside board update dec 2015
Canalside board update dec 2015Canalside board update dec 2015
Canalside board update dec 2015
 
VDOT: Fairfax County Board of Supervisors Transportation Committee: Dec. 13, ...
VDOT: Fairfax County Board of Supervisors Transportation Committee: Dec. 13, ...VDOT: Fairfax County Board of Supervisors Transportation Committee: Dec. 13, ...
VDOT: Fairfax County Board of Supervisors Transportation Committee: Dec. 13, ...
 
Pharmacy to kennedy construction liaison committee meeting - June 2018
Pharmacy to kennedy construction liaison committee meeting - June 2018Pharmacy to kennedy construction liaison committee meeting - June 2018
Pharmacy to kennedy construction liaison committee meeting - June 2018
 
Chaplin Grout Plant and Headwall Construction
Chaplin Grout Plant and Headwall ConstructionChaplin Grout Plant and Headwall Construction
Chaplin Grout Plant and Headwall Construction
 
BT_TatuanuiCaseStudy_F
BT_TatuanuiCaseStudy_FBT_TatuanuiCaseStudy_F
BT_TatuanuiCaseStudy_F
 
Chaplin slide deck final
Chaplin slide deck finalChaplin slide deck final
Chaplin slide deck final
 
Eglinton Crosstown Update
Eglinton Crosstown UpdateEglinton Crosstown Update
Eglinton Crosstown Update
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
 
Noise Analysis | Gaurav Singh Rajput
Noise Analysis | Gaurav Singh Rajput Noise Analysis | Gaurav Singh Rajput
Noise Analysis | Gaurav Singh Rajput
 
WMATA Blue and Yellow Lines Station Shutdown Bus Service Plans
WMATA Blue and Yellow Lines Station Shutdown Bus Service PlansWMATA Blue and Yellow Lines Station Shutdown Bus Service Plans
WMATA Blue and Yellow Lines Station Shutdown Bus Service Plans
 
Chaplin - Avenue Construction Liaison Committee - July 2018
Chaplin - Avenue Construction Liaison Committee - July 2018Chaplin - Avenue Construction Liaison Committee - July 2018
Chaplin - Avenue Construction Liaison Committee - July 2018
 
2009-11_UTA-SL Chamber Airport TRAX et al
2009-11_UTA-SL Chamber Airport TRAX et al2009-11_UTA-SL Chamber Airport TRAX et al
2009-11_UTA-SL Chamber Airport TRAX et al
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 
Level of Service F for Grade A Streets--Cesar Chavez Street
Level of Service F for Grade A Streets--Cesar Chavez Street  Level of Service F for Grade A Streets--Cesar Chavez Street
Level of Service F for Grade A Streets--Cesar Chavez Street
 
Cold In-Place Recycling (Foamed Asphalt) PowerPoint
Cold In-Place Recycling (Foamed Asphalt) PowerPointCold In-Place Recycling (Foamed Asphalt) PowerPoint
Cold In-Place Recycling (Foamed Asphalt) PowerPoint
 
Nebraska Precast Concrete Pavement
Nebraska Precast Concrete PavementNebraska Precast Concrete Pavement
Nebraska Precast Concrete Pavement
 
MTC San Mateo County 101 corridor strategies 062515
MTC San Mateo County 101 corridor strategies 062515 MTC San Mateo County 101 corridor strategies 062515
MTC San Mateo County 101 corridor strategies 062515
 
Construction Presentations 2019
Construction Presentations 2019Construction Presentations 2019
Construction Presentations 2019
 
Armoured Ford construction calculator v15
Armoured Ford construction calculator v15Armoured Ford construction calculator v15
Armoured Ford construction calculator v15
 
Stormwater and Wastewater Consolidation
Stormwater and Wastewater Consolidation Stormwater and Wastewater Consolidation
Stormwater and Wastewater Consolidation
 

Recently uploaded

Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
amitlee9823
 
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service NoidaCall Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
dlhescort
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
daisycvs
 
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
lizamodels9
 
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabiunwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
Abortion pills in Kuwait Cytotec pills in Kuwait
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
Renandantas16
 
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
dollysharma2066
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
amitlee9823
 

Recently uploaded (20)

Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023
 
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMAN
 
Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1
 
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service NoidaCall Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with Culture
 
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
 
Forklift Operations: Safety through Cartoons
Forklift Operations: Safety through CartoonsForklift Operations: Safety through Cartoons
Forklift Operations: Safety through Cartoons
 
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabiunwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
 
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service AvailableCall Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
 
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League City
 
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
 
Phases of negotiation .pptx
 Phases of negotiation .pptx Phases of negotiation .pptx
Phases of negotiation .pptx
 

404 presentation

  • 1. Interstate 5:NE 45th to NE 145th Full Depth HMA Reconstruction
  • 2. Location Location Interstate 5 Northbound Lanes from North 45th Street to North 145th Street
  • 3. Overview Location Interstate 5 Northbound Lanes from North 45th Street to North 145th Street Task Remove Current PCC Slabs Replace PCC with HMA Goals Reduce Cost Reduce Traffic Impacts Create a long lasting Sustainable Pavement
  • 4. Existing Conditions Current Condition is Poor to Very Poor Built in the Early 1960s with a Design Life of 20 Years 9-inch thick PCC panels that are 15ft in length by 12 ft in width 11ft Lanes Extensive Panel Cracking and Faulting of Traverse Joints Extensive Wheel Path Wear and Pavement Surface Polishing Uncomfortable for Users Verge of not being able to Serve Traffic
  • 5. Overall Scope I-5 Northbound NE 45th St to NE 145th St Remove 9” PCC and Replace with 13” HMA and 9” base Two Phases 5.2 miles at 21.2 lane miles total
  • 6. Scope: Phase one Phase one NE 45th to Northgate Way overpass-express lanes Approximately 10.5 lane miles 3-4 lanes
  • 7. Scope: Phase two Phase two Northgate Way overpass to NE 145thSt- no express lanes Approximately 10.7 lane miles 5-6 lanes
  • 8. Cost Construction (CA4PRS) Construction Costs: $12,700,000 Roadway Costs: $16,000,000 Supporting Costs: $300,000 Total Cost: $29,000,000 Agency (Real Cost) Life Cycle Agency Costs will be $25,000,000 LCCA (Real Cost) Life Cycle User Costs will be $16,000,000
  • 9. Construction Time Phase 1 Begin on July 17th (After Independence Day) Continuous Closure Maximum Closure of 2 weeks Phase 2 Begin on August 7th Continuous Closure Maximum Closure of 2 weeks (Finish before Labor Day)
  • 10. Construction Maintain three lanes of traffic at all times Allow one lane for equipment and trucks to passing at all times Excavate and replace with crushed aggregate quickly
  • 11. Sequencing: Phase one Crossover to express lanes Extend third lane: express lanes to main line Demolition & Excavation Grading & Paving
  • 12. Sequencing: Phase two Remove crossover to express lanes Remove third lane: express lanes to main line Left three lane then right lanes Demolition & Excavation Grading & Paving
  • 14. HMA Plant Location ICON Materials will be contracted to supply HMA and aggregate from their Auburn Aggregate Resource and Asphalt Plant located in Auburn WA Plant Produces 500 tons/hr when aggregate is wet and 600 tons/hr when the aggregate is dry Average trucking time from the plant to site is 40 minutes during normal conditions and 70 minutes during heavy traffic
  • 16. Productivity Phase 1 Using 87% confidence interval productivity will be 6.55 lane miles per 7 day closure Requires two 7 day closures HMA trucks are greatest limit to productivity Phase 2 Using 87% confidence interval productivity will be 6.50 lane miles per 7 day closure Requires two 7 day closures HMA trucks are greatest limit to productivity
  • 17. Closures Phase 1 (45th St. to Northgate Way) Closes Friday July 17th 2015 at 11pm Must reopen by Monday August 2nd 2015 at 4am Phase 2 (Northgate Way to 145th St.) Closes Friday August 7th 2015 at 11pm Must reopen by Monday August 24th 2015 at 4am
  • 18. Alternative Routes SR-99 Aurora SR-522 Lake City/Bothell Way NE 15th Ave NE 11th/12th Ave NE 25th Ave NE Phinney/Greenwood Ave N
  • 19. Traffic Impacts: Phase one Minimum impact southbound 20.3 mile maximum queue $25 million user cost 25% no show 15% detour
  • 20. Traffic Impacts: Phase two Less impact southbound than phase one 26.4 mile maximum queue $25 million user cost 25% no show 15% detour
  • 21. Critical Resources HMA Plant Plant is producing maximum capacity to provide for this project HMA Hauling Trucks High Spearman Correlation Coefficient Dependent upon plant production Travel (coffee stops, traffic, etc.)
  • 22. Backup Plans The Seattle Asphalt Plant owned by ICON Materials will be on standby incase the main plant faults Located in the South Park neighborhood of South Seattle Produces 250 tons/hr when aggregate is wet and 300 tons/hr when aggregate is dry Average trucking time from this plant to the site is estimated to be 18 minutes in normal conditions and 30 minutes in heavy traffic Extra equipment such as pavers, buggies, rollers and dump trucks will be stored at the temporary storage facilities
  • 24. Potential Cost Savings Warm Mix Asphalt (WMA) Recycled Concrete
  • 25. WMA vs. HMA I-90 WSDOT study near George, WA Less fuel consumed Lower CO2 quantities produced
  • 26. Near Site Recycled Concrete Cost Savings Savings of $5 to $10 per ton $316,400 to $632,800 for the project Environmental Savings Less aggregate Less CO2 Blah