SlideShare une entreprise Scribd logo
1  sur  29
Flask Loading Facility
(FLF) Project
“A new delivery
strategy”
association for project management Nuclear Technology and Innovation
FLF Project Overview
Irradiated Exotic Fuel is currently stored at Dounreay. As part of the
Dounreay decommissioning and restoration scheme, this fuel is to be
relocated to the Sellafield site in Cumbria.
To support this operation, the requirement was identified for a new
Flask Loading Facility (FLF) to enable the handling of transport flasks
to be loaded with Irradiated Fuel (IF) Containers for both road and rail
transfer.
Client: Dounreay Sites Restoration Limited
Location: Dounreay and Warrington
Contractor: Nuvia Limited
association for project management Nuclear Technology and Innovation
Project Outline
• The Project was to complete a concept and scheme
design for a new Flask Loading Facility at Dounreay.
• The function of the facility is to transfer fuel in Irradiated
Fuel Containers from site flasks to road/rail transport
flasks for onward transfer.
Contract stages
Phase 1 Concept
Phase 2 Preliminary Safety Case (PSR and Planning App support)
Phase 3 Scheme Design
association for project management Nuclear Technology and Innovation
Scope of Work
The Project scope included the following:
• Concept Design - a fully functional plant proposal was produced with fuel storage, fuel
preparation, and onsite flask unloading and offsite road/rail flask loading capability.
• Development of the Preliminary Safety Case (PSR) and Environmental documentation.
• Scheme Design – Developing the approved concept to enable a technical specification to
be produced for Detailed Design and Build Contract.
• Performance of the CDM 2015 roles of Designer and Principal Designer.
association for project management Nuclear Technology and Innovation
• The client outlined a preferred approach to roll back major elements of the FLF functionality into
the ‘Donor Plants’ resulting in a much reduced specification.
• Project timescales were vital as the Clients overall site decommissioning programme required, by
a specific date (Jan 2016), the ability to place a contract for detailed design and build. Therefore
delays at the front end of the project could not be allowed to impact the overall completion date.
• The resulting challenge for the FLF team was that a new Scheme Design including PSR was
required in six months instead of the planned 10 month schedule for the scheme design without
the benefit of a proven concept.
• This presented a challenge as key elements of the design specification were yet to be decided
The Challenge
association for project management
Options Developed
Main project driver - to decommission PFR at the earliest possible date
Baseline Option
FLF with 30 IF Container Storage
Option 1
FLF with 300 IF Container Storage
Option 2
PFR Re-Use of Pond - FLF with 300 IF Container Storage
Option 3
Phased Build FLF with 300 IF Container Storage
Building Information Modelling (BIM) with a Nuclear Project
association for project management Nuclear Technology and Innovation
• BIM - The project was delivered using a BIM
(Building Information Modelling) Level 2 process
whereby the majority of plant design definition
was incorporated into one 3D model. Supporting
drawings were reduced to a minimum.
• BIM Level 2 is all about Collaboration.
• Minimise “dumb” information, Maximise
centralised information.
Building Information Modelling (BIM) with a Nuclear
Project
association for project management Nuclear Technology and Innovation
• Planning is key.
• Getting the right systemisation in place
early makes proper collaboration
much easier.
• Each discipline has its own centralised
model which is incorporated into a
federated model for reviews and clash
detection.
Building Information Modelling (BIM) with a Nuclear
Project 212 Process Air (.IAM) EFD 105 External Temporary Supplies
214 Breathing Air (.IAM) EFD 105 External Temporary Supplies (.DWG) BCD
231 Fire Fighting Systems (.IAM) GA 110 External Supplies (.DWG) BCD
200 Mechanical Services Systems (.IAM) GA 232 Fire Water Storage & Pumps (.IAM) 130 Power Distribution (.DWG) SLD
235 Hot Water System (Heating) (.IAM) 140 UPS Systems
242 Portable Water (.IAM) 150 Diesel Input Board
244 Domestic/Foul Water Drainage (.IAM) 151 Standby Diesel Generators
160 Normal Lighting
710 General Area Supply Services - CS (.IAM) VFD 170 In Cell Lighting
720 Flask Loading Bay Vehicle Extract - CS (.IAM) VFD 180 Emergency Lighting
MEP (.IAM) 700 Ventilation (.IAM) GA 730 General Area Extract System (Main Building) -CL (.IAM) VFD 190 Small Power
740 Transfer Cell Area Extract/Stack Discharge System - CM (.IAM) 195 Earthing (.DWG) Earthing DIA
780 Change Room General Area Extract System -CL (.IAM) VFD 196 Lighting protection
930 Fire Protection Systems Layout
900 EC&I (.IAM) GA 940 CCTV-Systems-Process and Surveillance
945 Communications - BT Telephones
946 Communications - Internal Data
310 Flask Handing Crane (.IAM) GA 947 Communications -Intercom/PA
311 Z6022 Flask Handling Equipment (.IAM) 950 Main Plant Control System TOPOLOGY DWG
312 Transfer Flask Handling Equipment (.IAM) 955 Plant Data Management/SCADA TOPOLOGY DWG
330 Z6022 Flask Bogie (.IAM) 957 Management Information Systems
335 Transfer Flask Bogie (.IAM) GA 958 Main Control Room Layout
360 Flask Handling Area Roller Shutter Doors (.IAM) 960 Plant Security System - Access
Flask Handling Area 370 Z6022 Top Cover Equipment (.IAM) 970 Activity in Air Monitoring (Inc. Interlock Monitoring) Layout
and Transfer Halls (.IAM) 375 Z6022 Flask Docking Port (.IAM) 971 Criticality Incident Detection
380 Transfer Flask Outer Cover Equipment (.IAM) 972 Stack Monitoring
FLF Building and 385 Transfer Flask Docking Port (.IAM) 974 Air Quality Monitors
Navisworks (.NWF) 390 Transfer Flask Inner Lid Handling Machine (.IAM) DPD 975 Building Evacuation
Collaboration of weekly 391 Transfer Flask Interspace Test Equipment (.IAM) 978 Change Room/Portable Instruments
snapshots from each disciplines 395 Shielded PA Door (.IAM) 980 Special Radiometric Instruments
navisworks file. Weekly .
NWD snapshot produced for review.
Mech (.IAM) 800 Out Cell Operating Area (.IAM) GA 810 MSM Maintenance Area (.IAM)
820 Flask Maintenance (.IAM)
410 In cell Equipment Import/Export (.IAN)
430 MEB Equipment (.IAM)
440 Grab Station (.IAM)
400 Transfer Cell .(IAM) GA 460 In Cell Crane (Inc. Grabs) (.IAM) GA/DPD
470 In Cell Crane Maintenance Shield Door (.IAM) DPD
480 Shielded Personnel Door (.IAM)
490 Buffer Store Array (.IAM)
Reference shrink-wrap
model (.IPT). Model is
placed in all assemblies 001 External Works (CS&A) (.IAM) GA
where marked 010 Plant Layout & Space Management FLF Facility (.IAM)
011 Architectural Building Layouts (.IAM) GA
Civil Building 012 Steel Work Superstructure (.IAM)
Fabric (.IAM) 013 Reinforced Concrete Structures &Foundations (.IAM)
014 Secondary Steel Work(.IAM)
030 MSM Equipment (Runway Beams) (.IAM)
090 Out-Cell Runway Beams (.IAM)
External Plant
Works
GA300
association for project management Nuclear Technology and Innovation
Component Parts
• FLF Flask Loading Facility - 36 Flask Storage
• IF Container Irradiated Fuels Container – 2700mm x 195mm
• Inter site Flask (Existing)
• MEB Multi Element Bottle - IF Containers
• Flask Transport Flask - 50 Tonne and 4000mm high
What is a Flask?
association for project management
MEB lidding equipment
Platform & stairs
to in-cell Crane
Maintenance Area
IF container swab monitoring
glove box
MSM & shielded
viewing window
MSM extraction
hoist & beam
Stairwell to
-3m level
Shielded cell wall
1.350m thk
Original Concept Design
association for project management
Original Concept Design
Original Storage for 300 IF containers
association for project management
Flask Handling Area
association for project management
Z6022 Transfer Hall
association for project management
Plant Rooms
association for project management Nuclear Technology and Innovation
• BIM - The project was delivered using a BIM (Building
Information Modelling) Level 2 process whereby the
majority of plant design definition was incorporated
into one 3D model. Supporting drawings were
reduced to a minimum.
• The team developed new processes for
checking/approving designs and working with the 3D
model and managed the records electronically which
streamlined the process significantly reducing
timescales.
Making it Happen
“Nuvia demonstrated their ability to truly integrate with the client team to deliver the scheme design scope. To collaborate, be
flexible in meeting our moving requirements, and yet be robust in applying the processes and procedures that ensured the delivery
of a substantiated scope of work when it was required. Many a time I challenged Nuvia personnel to 'make it happen', and they
delivered.”
DSRL Engineering Manager, FLF Project
association for project management
Throughput video
association for project management Nuclear Technology and Innovation
Stage 3 Scheme Design
The Concept and PSR were completed on schedule
and within budget when a significant change in
approach was initiated by an emerging opportunity
which required the design to be reworked.
Project Change
Change entailed the de-scoping of many of the
original functional processes as they were ‘rolled
back’ into their own donor plants.
Typically the project completion date remained
fixed as it formed part of the site wide
decommissioning programme.
association for project management Nuclear Technology and Innovation
• In delivering the Project with a such a significant
change we formed an integrated team with the Client
and jointly developed a set of revised baseline design
parameters at the outset against which we delivered
the design.
• The scope of work was developed in stages as we
moved forward re-setting objectives around decision
points which acted as gateways. This approach
provided focus in short term whilst working toward an
agreed goal.
• Weekly internal technical reviews based around the
model were held agreeing approaches and resolving
issues as they were encountered.
Managing the Change
The approach undertaken mitigated potential conflict
situations arising.
association for project management
Delivery Team
The team demographic in which the
relationship between the discipline leads
and the 3D modellers meant that the
engineering seniors could be centred on
developing engineering solutions in an
emerging scope while the modellers were
able to focus on producing the designs and
integrating the requirements of the
engineering teams.
association for project management
Collaboration and Conflict Management
Logistics Separated by a distance of 550+ miles the integrated team
needed to work closely and efficiently as we effectively restarted
the team building process.
Management of potential conflict situations was vital during the
‘forming and storming’ process as we were redefining the project
scope whilst delivering on a fast track basis.
The new requirements brought many new stakeholders into the
project including donor plant Operations, safety and security
teams.
Rules of engagement were agreed at the outset to promote an open culture and trust.
association for project management
Logistics – Design Reviews, HAZOPs etc.
24 people at Thurso plus Client team 8 people at Risley
Stakeholder Management
Use of communications technology such as remote desktop and video conferencing enabling key team
members top work collaboratively even when separated by significant distances.
This proved a major advantage as it negated the impact of travelling logistics and reduced the time in
meetings to a minimum.
association for project management Nuclear Technology and Innovation
Stakeholder Management
• Stakeholder Engagement - Access to Information – The 3D model
data was presented through Navisworks, a freeware platform
available to all parties without licensing issues. This has the
added benefit of reducing demand on PC specification greatly
increasing the accessibility of the model data to all stakeholders.
• Design Reviews - We implemented a fast track review process in
which the MDDR and constructability reviews were held using on
screen 3D model walk through's. 2D documentation was reduced
to a minimum.
“Thanks for all that you and others are doing. I
understand that we are pushing hard with it
but be assured we appreciate all that you've
done and are doing to get us over the line.”
DSRL Project Manager, FLF Project
As the change introduced many stakeholders new to the
project, bringing them ‘up to speed’ as quickly as possible
was essential.
association for project management
Stakeholder Management
• Value engineering studies were undertaken to identify innovative or even novel solutions to
functional requirements, simplifying plant maintenance and identify cost saving initiatives.
• In-cell equipment was minimised to meet the requirements of the process and reduce the
decommissioning challenges at the end of plant life.
• Other stakeholders who were engaged from the outset included operations, RPA and SHE
representatives throughout the design process to ensure buy-in and produce a proposal capable
of meeting all operational and legislative requirements.
Along with the change of scope we needed to ensure that the Project Benefits were maintained and where
required re-defined.
association for project management
Benefit Realisation
• Focus on use of existing Plant Functionality - The use of existing DSRL equipment within the
donor plants was exploited where possible and newly specified equipment was aligned with the
existing site maintenance capability.
• Economic materials such as aluminium cladding were selected to maximise the opportunities
offered by a short plant life.
• Plant infrastructure was reduced to a minimum, full advantage being taken of opportunities such
as natural ventilation where plant operating conditions permitted.
• Space envelopes have been claimed to give the design the flexibility to incorporate
additional capabilities should the need arise as the unknowns in the baseline data reach
maturity.
Along with the change of scope we needed to ensure that the Project Benefits were maintained and where
required re-defined.
association for project management
Outcomes
Smaller Facility
Footprint
Final Facility
Design
Original Concept
Design
association for project management
Outcomes
11.47m
8.98m
8.85m
20.07m
3.00m
Simplification
of In-cell
Operation
Original Concept
Design
Final Cell Design
association for project management
Client Feedback
DSRL was able to meet the requirements of the overall decommissioning programme and
successfully navigate the ONR milestone for completion.
The project is considered by DSRL to be a major success.
“We are now in receipt of the scheme design for the flask loading
facility Can I take this opportunity in offering my congratulations
to all of you and your teams in achieving this. The journey to get
to this point has at moments been difficult but there is no doubt
when everyone pushes in the same direction with the same aim
that significant things are achieved.”
DSRL Project Manager, FLF Project
association for project management
Sharing LFE from the Project
8 2
5
7 3
6 4
1
COSTS
A 55% DD&B cost reduction was
achieved
DELIVERY
We delivered a PSR in an accelerated
timeframe – from Hazop to Safe
Working Party Review in 7 weeks
MILESTONES
Every project milestone was
successfully achieved
REVIEW
Designs were subject to
independent PBO review and
declared to be of a high standard.
1
2
3
4
COMMUNICATION
Effective communication is vital to
collaboration and ultimately
project success.
APPROACH
BIM Model approach is foundation for
Detailed Design and Construction
Information – (A process therefore
following straight through).
INNOVATION
BIM encourages innovation and
streamlining review processes
EFFICIENCY
Significant use of BIM, as trialled
on this project, has indicated
improvements in efficiencies,
potentially providing competitive
advantage.
5
6
7
8
£
This presentation was delivered at an
APM event
To find out more about upcoming
events please visit our website
www.apm.org.uk/events

Contenu connexe

Tendances

Item no
Item noItem no
Item norehant
 
Petrotech Presenttaion- Punj Lloyd
Petrotech Presenttaion- Punj LloydPetrotech Presenttaion- Punj Lloyd
Petrotech Presenttaion- Punj LloydNitin Sethi
 
Ashrae 90.1 2004 appendix g - performance rating method
Ashrae 90.1   2004 appendix g - performance rating methodAshrae 90.1   2004 appendix g - performance rating method
Ashrae 90.1 2004 appendix g - performance rating methodEduardo Miranda Cáceres
 
Primavera Activity ID Coding
Primavera Activity ID CodingPrimavera Activity ID Coding
Primavera Activity ID Codingignitetribes
 
R mayers_CV 2302
R mayers_CV 2302R mayers_CV 2302
R mayers_CV 2302Rhod Mayers
 
2013 Mission First Track, Navy GeoReadiness: Return on Location by Ed Riegelmann
2013 Mission First Track, Navy GeoReadiness: Return on Location by Ed Riegelmann2013 Mission First Track, Navy GeoReadiness: Return on Location by Ed Riegelmann
2013 Mission First Track, Navy GeoReadiness: Return on Location by Ed RiegelmannGIS in the Rockies
 
Leon Chacon Resume_Sept2016R
Leon Chacon Resume_Sept2016RLeon Chacon Resume_Sept2016R
Leon Chacon Resume_Sept2016RLeon Chacon
 
DAMMAM SECOND INDUSTRIAL CITY - IPS REHABILITATION WORKS
DAMMAM SECOND INDUSTRIAL CITY - IPS REHABILITATION WORKSDAMMAM SECOND INDUSTRIAL CITY - IPS REHABILITATION WORKS
DAMMAM SECOND INDUSTRIAL CITY - IPS REHABILITATION WORKSIslam Nassef
 
Performance Monitoring for Efficiency
Performance Monitoring for EfficiencyPerformance Monitoring for Efficiency
Performance Monitoring for EfficiencyCx Associates
 
Mary.zimmerman
Mary.zimmermanMary.zimmerman
Mary.zimmermanNASAPMC
 
Baijan Savalan _ Avans High School lecture 27.10.16
Baijan Savalan _ Avans High School lecture 27.10.16Baijan Savalan _ Avans High School lecture 27.10.16
Baijan Savalan _ Avans High School lecture 27.10.16Baijan Savalan
 
61T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 20141129
61T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 2014112961T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 20141129
61T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 20141129James Zhang (Chi, Zhang)
 
The Commissioning Process
The Commissioning ProcessThe Commissioning Process
The Commissioning Processd_mackay
 
Advanced Mechanical Systems – Finding the Right Solutions for the Client & Pr...
Advanced Mechanical Systems – Finding the Right Solutions for the Client & Pr...Advanced Mechanical Systems – Finding the Right Solutions for the Client & Pr...
Advanced Mechanical Systems – Finding the Right Solutions for the Client & Pr...Toronto 2030 District
 

Tendances (17)

Item no
Item noItem no
Item no
 
Petrotech Presenttaion- Punj Lloyd
Petrotech Presenttaion- Punj LloydPetrotech Presenttaion- Punj Lloyd
Petrotech Presenttaion- Punj Lloyd
 
Gopa 16 Aug 2016
Gopa 16 Aug 2016Gopa 16 Aug 2016
Gopa 16 Aug 2016
 
Ashrae 90.1 2004 appendix g - performance rating method
Ashrae 90.1   2004 appendix g - performance rating methodAshrae 90.1   2004 appendix g - performance rating method
Ashrae 90.1 2004 appendix g - performance rating method
 
Primavera Activity ID Coding
Primavera Activity ID CodingPrimavera Activity ID Coding
Primavera Activity ID Coding
 
R mayers_CV 2302
R mayers_CV 2302R mayers_CV 2302
R mayers_CV 2302
 
2013 Mission First Track, Navy GeoReadiness: Return on Location by Ed Riegelmann
2013 Mission First Track, Navy GeoReadiness: Return on Location by Ed Riegelmann2013 Mission First Track, Navy GeoReadiness: Return on Location by Ed Riegelmann
2013 Mission First Track, Navy GeoReadiness: Return on Location by Ed Riegelmann
 
Leon Chacon Resume_Sept2016R
Leon Chacon Resume_Sept2016RLeon Chacon Resume_Sept2016R
Leon Chacon Resume_Sept2016R
 
DAMMAM SECOND INDUSTRIAL CITY - IPS REHABILITATION WORKS
DAMMAM SECOND INDUSTRIAL CITY - IPS REHABILITATION WORKSDAMMAM SECOND INDUSTRIAL CITY - IPS REHABILITATION WORKS
DAMMAM SECOND INDUSTRIAL CITY - IPS REHABILITATION WORKS
 
DRAFT LHD-2 PEMT SKED V - Portfolio Example
DRAFT LHD-2 PEMT SKED V - Portfolio ExampleDRAFT LHD-2 PEMT SKED V - Portfolio Example
DRAFT LHD-2 PEMT SKED V - Portfolio Example
 
ptsresume[1]
ptsresume[1]ptsresume[1]
ptsresume[1]
 
Performance Monitoring for Efficiency
Performance Monitoring for EfficiencyPerformance Monitoring for Efficiency
Performance Monitoring for Efficiency
 
Mary.zimmerman
Mary.zimmermanMary.zimmerman
Mary.zimmerman
 
Baijan Savalan _ Avans High School lecture 27.10.16
Baijan Savalan _ Avans High School lecture 27.10.16Baijan Savalan _ Avans High School lecture 27.10.16
Baijan Savalan _ Avans High School lecture 27.10.16
 
61T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 20141129
61T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 2014112961T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 20141129
61T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 20141129
 
The Commissioning Process
The Commissioning ProcessThe Commissioning Process
The Commissioning Process
 
Advanced Mechanical Systems – Finding the Right Solutions for the Client & Pr...
Advanced Mechanical Systems – Finding the Right Solutions for the Client & Pr...Advanced Mechanical Systems – Finding the Right Solutions for the Client & Pr...
Advanced Mechanical Systems – Finding the Right Solutions for the Client & Pr...
 

En vedette

West of England Rail Electrification Programme, 23 February 2017
West of England Rail Electrification Programme, 23 February 2017West of England Rail Electrification Programme, 23 February 2017
West of England Rail Electrification Programme, 23 February 2017Association for Project Management
 
APM Registered Project Professional: what you need to know by Peter Wakeling,...
APM Registered Project Professional: what you need to know by Peter Wakeling,...APM Registered Project Professional: what you need to know by Peter Wakeling,...
APM Registered Project Professional: what you need to know by Peter Wakeling,...Association for Project Management
 
Building the Dreadnought, APM Programme Management SIG Conference 2017, 02 Ma...
Building the Dreadnought, APM Programme Management SIG Conference 2017, 02 Ma...Building the Dreadnought, APM Programme Management SIG Conference 2017, 02 Ma...
Building the Dreadnought, APM Programme Management SIG Conference 2017, 02 Ma...Association for Project Management
 
Webinar - Introduction to Programme Management, 23 February 2017, Alan Macklin
Webinar - Introduction to Programme Management, 23 February 2017, Alan MacklinWebinar - Introduction to Programme Management, 23 February 2017, Alan Macklin
Webinar - Introduction to Programme Management, 23 February 2017, Alan MacklinAssociation for Project Management
 
Swapping the Remote for the Mouse
Swapping the Remote for the MouseSwapping the Remote for the Mouse
Swapping the Remote for the MouseTommy McCubbin
 
Tv remote controlled pc and devices with password protection
Tv remote controlled pc and devices with password protectionTv remote controlled pc and devices with password protection
Tv remote controlled pc and devices with password protectionJagadeesh Yadav
 
Armenian Project Management Association
Armenian Project Management AssociationArmenian Project Management Association
Armenian Project Management AssociationAlbert Poghosyan
 
La contaminación ambiental
La contaminación ambientalLa contaminación ambiental
La contaminación ambientalSharina Batista
 
Carol Bell APM Registered Project Professional presentation 25th June 2015 to...
Carol Bell APM Registered Project Professional presentation 25th June 2015 to...Carol Bell APM Registered Project Professional presentation 25th June 2015 to...
Carol Bell APM Registered Project Professional presentation 25th June 2015 to...Association for Project Management
 
Innovative Methods and Technologies in Project Management: Project Management...
Innovative Methods and Technologies in Project Management: Project Management...Innovative Methods and Technologies in Project Management: Project Management...
Innovative Methods and Technologies in Project Management: Project Management...Association for Project Management
 
Innovative Methods and Technologies in Project Management: Project Management...
Innovative Methods and Technologies in Project Management: Project Management...Innovative Methods and Technologies in Project Management: Project Management...
Innovative Methods and Technologies in Project Management: Project Management...Association for Project Management
 
Innovative Methods and Technologies in Project Management: Project Management...
Innovative Methods and Technologies in Project Management: Project Management...Innovative Methods and Technologies in Project Management: Project Management...
Innovative Methods and Technologies in Project Management: Project Management...Association for Project Management
 
PC control using TV remote
PC control using TV remotePC control using TV remote
PC control using TV remoteStupidsid.com
 

En vedette (20)

A Career in Project Management
A Career in Project ManagementA Career in Project Management
A Career in Project Management
 
West of England Rail Electrification Programme, 23 February 2017
West of England Rail Electrification Programme, 23 February 2017West of England Rail Electrification Programme, 23 February 2017
West of England Rail Electrification Programme, 23 February 2017
 
APM Registered Project Professional: what you need to know by Peter Wakeling,...
APM Registered Project Professional: what you need to know by Peter Wakeling,...APM Registered Project Professional: what you need to know by Peter Wakeling,...
APM Registered Project Professional: what you need to know by Peter Wakeling,...
 
Building the Dreadnought, APM Programme Management SIG Conference 2017, 02 Ma...
Building the Dreadnought, APM Programme Management SIG Conference 2017, 02 Ma...Building the Dreadnought, APM Programme Management SIG Conference 2017, 02 Ma...
Building the Dreadnought, APM Programme Management SIG Conference 2017, 02 Ma...
 
Webinar - Introduction to Programme Management, 23 February 2017, Alan Macklin
Webinar - Introduction to Programme Management, 23 February 2017, Alan MacklinWebinar - Introduction to Programme Management, 23 February 2017, Alan Macklin
Webinar - Introduction to Programme Management, 23 February 2017, Alan Macklin
 
Swapping the Remote for the Mouse
Swapping the Remote for the MouseSwapping the Remote for the Mouse
Swapping the Remote for the Mouse
 
Tv remote controlled pc and devices with password protection
Tv remote controlled pc and devices with password protectionTv remote controlled pc and devices with password protection
Tv remote controlled pc and devices with password protection
 
Armenian Project Management Association
Armenian Project Management AssociationArmenian Project Management Association
Armenian Project Management Association
 
Project management 101 for Community Associations
Project management 101 for Community AssociationsProject management 101 for Community Associations
Project management 101 for Community Associations
 
La contaminación ambiental
La contaminación ambientalLa contaminación ambiental
La contaminación ambiental
 
Carol Bell APM Registered Project Professional presentation 25th June 2015 to...
Carol Bell APM Registered Project Professional presentation 25th June 2015 to...Carol Bell APM Registered Project Professional presentation 25th June 2015 to...
Carol Bell APM Registered Project Professional presentation 25th June 2015 to...
 
APM chairman Steve Wake, PGCS Symposium, 11th and 12th May 2015
APM chairman Steve Wake, PGCS Symposium, 11th and 12th May 2015APM chairman Steve Wake, PGCS Symposium, 11th and 12th May 2015
APM chairman Steve Wake, PGCS Symposium, 11th and 12th May 2015
 
Innovative Methods and Technologies in Project Management: Project Management...
Innovative Methods and Technologies in Project Management: Project Management...Innovative Methods and Technologies in Project Management: Project Management...
Innovative Methods and Technologies in Project Management: Project Management...
 
Getting the risk basics right, 30th November 2016
Getting the risk basics right, 30th November 2016Getting the risk basics right, 30th November 2016
Getting the risk basics right, 30th November 2016
 
APM Registered Project Professional
APM Registered Project ProfessionalAPM Registered Project Professional
APM Registered Project Professional
 
Innovative Methods and Technologies in Project Management: Project Management...
Innovative Methods and Technologies in Project Management: Project Management...Innovative Methods and Technologies in Project Management: Project Management...
Innovative Methods and Technologies in Project Management: Project Management...
 
RPP presentation by Emma Carroll-Walsh on 20th October 2016
RPP presentation by Emma Carroll-Walsh on 20th October 2016RPP presentation by Emma Carroll-Walsh on 20th October 2016
RPP presentation by Emma Carroll-Walsh on 20th October 2016
 
Innovative Methods and Technologies in Project Management: Project Management...
Innovative Methods and Technologies in Project Management: Project Management...Innovative Methods and Technologies in Project Management: Project Management...
Innovative Methods and Technologies in Project Management: Project Management...
 
Keeping your stakeholders happy, 9 March 2017
Keeping your stakeholders happy, 9 March 2017Keeping your stakeholders happy, 9 March 2017
Keeping your stakeholders happy, 9 March 2017
 
PC control using TV remote
PC control using TV remotePC control using TV remote
PC control using TV remote
 

Similaire à Dounreay’s Nuclear Flask Loading Facility Project – A New Delivery Strategy, Liverpool John Moores University - 30 Jan 17

German perez lifes50+ design summary - deep wind 2018
German perez   lifes50+ design summary - deep wind 2018German perez   lifes50+ design summary - deep wind 2018
German perez lifes50+ design summary - deep wind 2018TECNALIA Marine Energy
 
RESUME - NAJMUL SAQIB MANIAR
RESUME - NAJMUL SAQIB MANIARRESUME - NAJMUL SAQIB MANIAR
RESUME - NAJMUL SAQIB MANIARSAQIB MANIAR
 
CD 2016 March - Advisian Showcase
CD 2016 March - Advisian ShowcaseCD 2016 March - Advisian Showcase
CD 2016 March - Advisian ShowcaseComit Projects Ltd
 
Vattenfall: Challenges for next generation offshore WTGs from a developer’s p...
Vattenfall: Challenges for next generation offshore WTGs from a developer’s p...Vattenfall: Challenges for next generation offshore WTGs from a developer’s p...
Vattenfall: Challenges for next generation offshore WTGs from a developer’s p...Torben Haagh
 
RESUME - NAJMUL SAQIB MANIAR
RESUME - NAJMUL SAQIB MANIARRESUME - NAJMUL SAQIB MANIAR
RESUME - NAJMUL SAQIB MANIARSAQIB MANIAR
 
General_ENTRION_Presentation_December2015
General_ENTRION_Presentation_December2015General_ENTRION_Presentation_December2015
General_ENTRION_Presentation_December2015Arun Jothilingam
 
Richard Turnbull CV Supplement 2012
Richard Turnbull CV Supplement 2012Richard Turnbull CV Supplement 2012
Richard Turnbull CV Supplement 2012Richard Turnbull
 
Relocation Pres.General Rev.9
Relocation Pres.General Rev.9Relocation Pres.General Rev.9
Relocation Pres.General Rev.9bas.pauwels
 
I tron automation's experience
I tron automation's experienceI tron automation's experience
I tron automation's experiencehugo_mx
 
AES_Capabilities_09012016
AES_Capabilities_09012016AES_Capabilities_09012016
AES_Capabilities_09012016Svetlana Vasey
 
dokumen.tips_installation-of-api-610-centrifugal-pumps-to-achieve-a-8-api-686...
dokumen.tips_installation-of-api-610-centrifugal-pumps-to-achieve-a-8-api-686...dokumen.tips_installation-of-api-610-centrifugal-pumps-to-achieve-a-8-api-686...
dokumen.tips_installation-of-api-610-centrifugal-pumps-to-achieve-a-8-api-686...yusuf699644
 
Attachement 3 61T01411 - Construction Execution Plan
Attachement 3 61T01411 - Construction Execution PlanAttachement 3 61T01411 - Construction Execution Plan
Attachement 3 61T01411 - Construction Execution PlanJames Zhang (Chi, Zhang)
 
Cce Long Brief
Cce Long BriefCce Long Brief
Cce Long BriefPetePhelan
 

Similaire à Dounreay’s Nuclear Flask Loading Facility Project – A New Delivery Strategy, Liverpool John Moores University - 30 Jan 17 (20)

German perez lifes50+ design summary - deep wind 2018
German perez   lifes50+ design summary - deep wind 2018German perez   lifes50+ design summary - deep wind 2018
German perez lifes50+ design summary - deep wind 2018
 
RESUME - NAJMUL SAQIB MANIAR
RESUME - NAJMUL SAQIB MANIARRESUME - NAJMUL SAQIB MANIAR
RESUME - NAJMUL SAQIB MANIAR
 
CD 2016 March - Advisian Showcase
CD 2016 March - Advisian ShowcaseCD 2016 March - Advisian Showcase
CD 2016 March - Advisian Showcase
 
Vattenfall: Challenges for next generation offshore WTGs from a developer’s p...
Vattenfall: Challenges for next generation offshore WTGs from a developer’s p...Vattenfall: Challenges for next generation offshore WTGs from a developer’s p...
Vattenfall: Challenges for next generation offshore WTGs from a developer’s p...
 
Rihan Height Project Execution Plan-Rev00
Rihan Height Project Execution Plan-Rev00Rihan Height Project Execution Plan-Rev00
Rihan Height Project Execution Plan-Rev00
 
RESUME - NAJMUL SAQIB MANIAR
RESUME - NAJMUL SAQIB MANIARRESUME - NAJMUL SAQIB MANIAR
RESUME - NAJMUL SAQIB MANIAR
 
API 610 pumps .pdf
API 610 pumps .pdfAPI 610 pumps .pdf
API 610 pumps .pdf
 
General_ENTRION_Presentation_December2015
General_ENTRION_Presentation_December2015General_ENTRION_Presentation_December2015
General_ENTRION_Presentation_December2015
 
vinoth-projects
vinoth-projectsvinoth-projects
vinoth-projects
 
James Bullen CV
James Bullen CVJames Bullen CV
James Bullen CV
 
Richard Turnbull CV Supplement 2012
Richard Turnbull CV Supplement 2012Richard Turnbull CV Supplement 2012
Richard Turnbull CV Supplement 2012
 
Anindam_Resume
Anindam_ResumeAnindam_Resume
Anindam_Resume
 
Relocation Pres.General Rev.9
Relocation Pres.General Rev.9Relocation Pres.General Rev.9
Relocation Pres.General Rev.9
 
4 YEARS EXP RESUME
4 YEARS EXP RESUME4 YEARS EXP RESUME
4 YEARS EXP RESUME
 
I tron automation's experience
I tron automation's experienceI tron automation's experience
I tron automation's experience
 
AES_Capabilities_09012016
AES_Capabilities_09012016AES_Capabilities_09012016
AES_Capabilities_09012016
 
ind brochure
ind brochureind brochure
ind brochure
 
dokumen.tips_installation-of-api-610-centrifugal-pumps-to-achieve-a-8-api-686...
dokumen.tips_installation-of-api-610-centrifugal-pumps-to-achieve-a-8-api-686...dokumen.tips_installation-of-api-610-centrifugal-pumps-to-achieve-a-8-api-686...
dokumen.tips_installation-of-api-610-centrifugal-pumps-to-achieve-a-8-api-686...
 
Attachement 3 61T01411 - Construction Execution Plan
Attachement 3 61T01411 - Construction Execution PlanAttachement 3 61T01411 - Construction Execution Plan
Attachement 3 61T01411 - Construction Execution Plan
 
Cce Long Brief
Cce Long BriefCce Long Brief
Cce Long Brief
 

Plus de Association for Project Management

APM Project Management Awards - Hints and tips for a winning award entry webi...
APM Project Management Awards - Hints and tips for a winning award entry webi...APM Project Management Awards - Hints and tips for a winning award entry webi...
APM Project Management Awards - Hints and tips for a winning award entry webi...Association for Project Management
 
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024Association for Project Management
 
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...Association for Project Management
 
AI in the project profession: examples of current use and roadmaps to adoptio...
AI in the project profession: examples of current use and roadmaps to adoptio...AI in the project profession: examples of current use and roadmaps to adoptio...
AI in the project profession: examples of current use and roadmaps to adoptio...Association for Project Management
 
Scaling New Heights: Project Management on the world’s 3rd highest peak
Scaling New Heights: Project Management on the world’s 3rd highest peakScaling New Heights: Project Management on the world’s 3rd highest peak
Scaling New Heights: Project Management on the world’s 3rd highest peakAssociation for Project Management
 
Inspire inclusion within the project profession to attract and retain a diver...
Inspire inclusion within the project profession to attract and retain a diver...Inspire inclusion within the project profession to attract and retain a diver...
Inspire inclusion within the project profession to attract and retain a diver...Association for Project Management
 
Discussing the new Competence Framework for project managers in the built env...
Discussing the new Competence Framework for project managers in the built env...Discussing the new Competence Framework for project managers in the built env...
Discussing the new Competence Framework for project managers in the built env...Association for Project Management
 
Successful projects and failed programmes – the cost of not designing the who...
Successful projects and failed programmes – the cost of not designing the who...Successful projects and failed programmes – the cost of not designing the who...
Successful projects and failed programmes – the cost of not designing the who...Association for Project Management
 
APM Volunteer opportunities - Insights in how you can get involved, 7 Februar...
APM Volunteer opportunities - Insights in how you can get involved, 7 Februar...APM Volunteer opportunities - Insights in how you can get involved, 7 Februar...
APM Volunteer opportunities - Insights in how you can get involved, 7 Februar...Association for Project Management
 

Plus de Association for Project Management (20)

APM Project Management Awards - Hints and tips for a winning award entry webi...
APM Project Management Awards - Hints and tips for a winning award entry webi...APM Project Management Awards - Hints and tips for a winning award entry webi...
APM Project Management Awards - Hints and tips for a winning award entry webi...
 
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
 
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
 
Staurt Earl - ARCC Programme for APM Awards.pptx
Staurt Earl - ARCC Programme for APM Awards.pptxStaurt Earl - ARCC Programme for APM Awards.pptx
Staurt Earl - ARCC Programme for APM Awards.pptx
 
If AI changes everything – do feelings still matter?
If AI changes everything – do feelings still matter?If AI changes everything – do feelings still matter?
If AI changes everything – do feelings still matter?
 
AI in the project profession: examples of current use and roadmaps to adoptio...
AI in the project profession: examples of current use and roadmaps to adoptio...AI in the project profession: examples of current use and roadmaps to adoptio...
AI in the project profession: examples of current use and roadmaps to adoptio...
 
Katharine Fox, WRAP - Valuing sustainability
Katharine Fox, WRAP - Valuing sustainabilityKatharine Fox, WRAP - Valuing sustainability
Katharine Fox, WRAP - Valuing sustainability
 
The silent project disruptor: Building AI solutions
The silent project disruptor: Building AI solutionsThe silent project disruptor: Building AI solutions
The silent project disruptor: Building AI solutions
 
Personal Resilience in Project Management 2 - TV Edit 1a.pdf
Personal Resilience in Project Management 2 - TV Edit 1a.pdfPersonal Resilience in Project Management 2 - TV Edit 1a.pdf
Personal Resilience in Project Management 2 - TV Edit 1a.pdf
 
Scaling New Heights: Project Management on the world’s 3rd highest peak
Scaling New Heights: Project Management on the world’s 3rd highest peakScaling New Heights: Project Management on the world’s 3rd highest peak
Scaling New Heights: Project Management on the world’s 3rd highest peak
 
Demystifying digital accessibility webinar
Demystifying digital accessibility webinarDemystifying digital accessibility webinar
Demystifying digital accessibility webinar
 
Inspire inclusion within the project profession to attract and retain a diver...
Inspire inclusion within the project profession to attract and retain a diver...Inspire inclusion within the project profession to attract and retain a diver...
Inspire inclusion within the project profession to attract and retain a diver...
 
Burnout_ Prevention Intervention Recovery.pdf
Burnout_ Prevention Intervention  Recovery.pdfBurnout_ Prevention Intervention  Recovery.pdf
Burnout_ Prevention Intervention Recovery.pdf
 
Discussing the new Competence Framework for project managers in the built env...
Discussing the new Competence Framework for project managers in the built env...Discussing the new Competence Framework for project managers in the built env...
Discussing the new Competence Framework for project managers in the built env...
 
Successful projects and failed programmes – the cost of not designing the who...
Successful projects and failed programmes – the cost of not designing the who...Successful projects and failed programmes – the cost of not designing the who...
Successful projects and failed programmes – the cost of not designing the who...
 
Risk in the changing world – Opportunity or threat
Risk in the changing world – Opportunity or threatRisk in the changing world – Opportunity or threat
Risk in the changing world – Opportunity or threat
 
Time-Honored Wisdom: African Teachings for VUCA Leaders
Time-Honored Wisdom: African Teachings for VUCA LeadersTime-Honored Wisdom: African Teachings for VUCA Leaders
Time-Honored Wisdom: African Teachings for VUCA Leaders
 
APM Volunteer opportunities - Insights in how you can get involved, 7 Februar...
APM Volunteer opportunities - Insights in how you can get involved, 7 Februar...APM Volunteer opportunities - Insights in how you can get involved, 7 Februar...
APM Volunteer opportunities - Insights in how you can get involved, 7 Februar...
 
Including mental health support in project delivery
Including mental health support in project deliveryIncluding mental health support in project delivery
Including mental health support in project delivery
 
Sustainability in Project Management – what you need to know
Sustainability in Project Management – what you need to knowSustainability in Project Management – what you need to know
Sustainability in Project Management – what you need to know
 

Dernier

TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024Adnet Communications
 
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607dollysharma2066
 
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort ServiceCall US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Servicecallgirls2057
 
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!Doge Mining Website
 
MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?Olivia Kresic
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCRashishs7044
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessSeta Wicaksana
 
Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMintel Group
 
8447779800, Low rate Call girls in Dwarka mor Delhi NCR
8447779800, Low rate Call girls in Dwarka mor Delhi NCR8447779800, Low rate Call girls in Dwarka mor Delhi NCR
8447779800, Low rate Call girls in Dwarka mor Delhi NCRashishs7044
 
International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...ssuserf63bd7
 
8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCRashishs7044
 
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607dollysharma2066
 
Darshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfDarshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfShashank Mehta
 
PSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationPSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationAnamaria Contreras
 
APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfRbc Rbcua
 
Entrepreneurship lessons in Philippines
Entrepreneurship lessons in  PhilippinesEntrepreneurship lessons in  Philippines
Entrepreneurship lessons in PhilippinesDavidSamuel525586
 
Investment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy CheruiyotInvestment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy Cheruiyotictsugar
 
Appkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptxAppkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptxappkodes
 
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCREnjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCRalexsharmaa01
 

Dernier (20)

TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024
 
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
 
Call Us ➥9319373153▻Call Girls In North Goa
Call Us ➥9319373153▻Call Girls In North GoaCall Us ➥9319373153▻Call Girls In North Goa
Call Us ➥9319373153▻Call Girls In North Goa
 
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort ServiceCall US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
 
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
 
MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful Business
 
Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 Edition
 
8447779800, Low rate Call girls in Dwarka mor Delhi NCR
8447779800, Low rate Call girls in Dwarka mor Delhi NCR8447779800, Low rate Call girls in Dwarka mor Delhi NCR
8447779800, Low rate Call girls in Dwarka mor Delhi NCR
 
International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...
 
8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR
 
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
 
Darshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfDarshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdf
 
PSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationPSCC - Capability Statement Presentation
PSCC - Capability Statement Presentation
 
APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdf
 
Entrepreneurship lessons in Philippines
Entrepreneurship lessons in  PhilippinesEntrepreneurship lessons in  Philippines
Entrepreneurship lessons in Philippines
 
Investment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy CheruiyotInvestment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy Cheruiyot
 
Appkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptxAppkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptx
 
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCREnjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
 

Dounreay’s Nuclear Flask Loading Facility Project – A New Delivery Strategy, Liverpool John Moores University - 30 Jan 17

  • 1. Flask Loading Facility (FLF) Project “A new delivery strategy”
  • 2. association for project management Nuclear Technology and Innovation FLF Project Overview Irradiated Exotic Fuel is currently stored at Dounreay. As part of the Dounreay decommissioning and restoration scheme, this fuel is to be relocated to the Sellafield site in Cumbria. To support this operation, the requirement was identified for a new Flask Loading Facility (FLF) to enable the handling of transport flasks to be loaded with Irradiated Fuel (IF) Containers for both road and rail transfer. Client: Dounreay Sites Restoration Limited Location: Dounreay and Warrington Contractor: Nuvia Limited
  • 3. association for project management Nuclear Technology and Innovation Project Outline • The Project was to complete a concept and scheme design for a new Flask Loading Facility at Dounreay. • The function of the facility is to transfer fuel in Irradiated Fuel Containers from site flasks to road/rail transport flasks for onward transfer. Contract stages Phase 1 Concept Phase 2 Preliminary Safety Case (PSR and Planning App support) Phase 3 Scheme Design
  • 4. association for project management Nuclear Technology and Innovation Scope of Work The Project scope included the following: • Concept Design - a fully functional plant proposal was produced with fuel storage, fuel preparation, and onsite flask unloading and offsite road/rail flask loading capability. • Development of the Preliminary Safety Case (PSR) and Environmental documentation. • Scheme Design – Developing the approved concept to enable a technical specification to be produced for Detailed Design and Build Contract. • Performance of the CDM 2015 roles of Designer and Principal Designer.
  • 5. association for project management Nuclear Technology and Innovation • The client outlined a preferred approach to roll back major elements of the FLF functionality into the ‘Donor Plants’ resulting in a much reduced specification. • Project timescales were vital as the Clients overall site decommissioning programme required, by a specific date (Jan 2016), the ability to place a contract for detailed design and build. Therefore delays at the front end of the project could not be allowed to impact the overall completion date. • The resulting challenge for the FLF team was that a new Scheme Design including PSR was required in six months instead of the planned 10 month schedule for the scheme design without the benefit of a proven concept. • This presented a challenge as key elements of the design specification were yet to be decided The Challenge
  • 6. association for project management Options Developed Main project driver - to decommission PFR at the earliest possible date Baseline Option FLF with 30 IF Container Storage Option 1 FLF with 300 IF Container Storage Option 2 PFR Re-Use of Pond - FLF with 300 IF Container Storage Option 3 Phased Build FLF with 300 IF Container Storage Building Information Modelling (BIM) with a Nuclear Project
  • 7. association for project management Nuclear Technology and Innovation • BIM - The project was delivered using a BIM (Building Information Modelling) Level 2 process whereby the majority of plant design definition was incorporated into one 3D model. Supporting drawings were reduced to a minimum. • BIM Level 2 is all about Collaboration. • Minimise “dumb” information, Maximise centralised information. Building Information Modelling (BIM) with a Nuclear Project
  • 8. association for project management Nuclear Technology and Innovation • Planning is key. • Getting the right systemisation in place early makes proper collaboration much easier. • Each discipline has its own centralised model which is incorporated into a federated model for reviews and clash detection. Building Information Modelling (BIM) with a Nuclear Project 212 Process Air (.IAM) EFD 105 External Temporary Supplies 214 Breathing Air (.IAM) EFD 105 External Temporary Supplies (.DWG) BCD 231 Fire Fighting Systems (.IAM) GA 110 External Supplies (.DWG) BCD 200 Mechanical Services Systems (.IAM) GA 232 Fire Water Storage & Pumps (.IAM) 130 Power Distribution (.DWG) SLD 235 Hot Water System (Heating) (.IAM) 140 UPS Systems 242 Portable Water (.IAM) 150 Diesel Input Board 244 Domestic/Foul Water Drainage (.IAM) 151 Standby Diesel Generators 160 Normal Lighting 710 General Area Supply Services - CS (.IAM) VFD 170 In Cell Lighting 720 Flask Loading Bay Vehicle Extract - CS (.IAM) VFD 180 Emergency Lighting MEP (.IAM) 700 Ventilation (.IAM) GA 730 General Area Extract System (Main Building) -CL (.IAM) VFD 190 Small Power 740 Transfer Cell Area Extract/Stack Discharge System - CM (.IAM) 195 Earthing (.DWG) Earthing DIA 780 Change Room General Area Extract System -CL (.IAM) VFD 196 Lighting protection 930 Fire Protection Systems Layout 900 EC&I (.IAM) GA 940 CCTV-Systems-Process and Surveillance 945 Communications - BT Telephones 946 Communications - Internal Data 310 Flask Handing Crane (.IAM) GA 947 Communications -Intercom/PA 311 Z6022 Flask Handling Equipment (.IAM) 950 Main Plant Control System TOPOLOGY DWG 312 Transfer Flask Handling Equipment (.IAM) 955 Plant Data Management/SCADA TOPOLOGY DWG 330 Z6022 Flask Bogie (.IAM) 957 Management Information Systems 335 Transfer Flask Bogie (.IAM) GA 958 Main Control Room Layout 360 Flask Handling Area Roller Shutter Doors (.IAM) 960 Plant Security System - Access Flask Handling Area 370 Z6022 Top Cover Equipment (.IAM) 970 Activity in Air Monitoring (Inc. Interlock Monitoring) Layout and Transfer Halls (.IAM) 375 Z6022 Flask Docking Port (.IAM) 971 Criticality Incident Detection 380 Transfer Flask Outer Cover Equipment (.IAM) 972 Stack Monitoring FLF Building and 385 Transfer Flask Docking Port (.IAM) 974 Air Quality Monitors Navisworks (.NWF) 390 Transfer Flask Inner Lid Handling Machine (.IAM) DPD 975 Building Evacuation Collaboration of weekly 391 Transfer Flask Interspace Test Equipment (.IAM) 978 Change Room/Portable Instruments snapshots from each disciplines 395 Shielded PA Door (.IAM) 980 Special Radiometric Instruments navisworks file. Weekly . NWD snapshot produced for review. Mech (.IAM) 800 Out Cell Operating Area (.IAM) GA 810 MSM Maintenance Area (.IAM) 820 Flask Maintenance (.IAM) 410 In cell Equipment Import/Export (.IAN) 430 MEB Equipment (.IAM) 440 Grab Station (.IAM) 400 Transfer Cell .(IAM) GA 460 In Cell Crane (Inc. Grabs) (.IAM) GA/DPD 470 In Cell Crane Maintenance Shield Door (.IAM) DPD 480 Shielded Personnel Door (.IAM) 490 Buffer Store Array (.IAM) Reference shrink-wrap model (.IPT). Model is placed in all assemblies 001 External Works (CS&A) (.IAM) GA where marked 010 Plant Layout & Space Management FLF Facility (.IAM) 011 Architectural Building Layouts (.IAM) GA Civil Building 012 Steel Work Superstructure (.IAM) Fabric (.IAM) 013 Reinforced Concrete Structures &Foundations (.IAM) 014 Secondary Steel Work(.IAM) 030 MSM Equipment (Runway Beams) (.IAM) 090 Out-Cell Runway Beams (.IAM) External Plant Works GA300
  • 9. association for project management Nuclear Technology and Innovation Component Parts • FLF Flask Loading Facility - 36 Flask Storage • IF Container Irradiated Fuels Container – 2700mm x 195mm • Inter site Flask (Existing) • MEB Multi Element Bottle - IF Containers • Flask Transport Flask - 50 Tonne and 4000mm high What is a Flask?
  • 10. association for project management MEB lidding equipment Platform & stairs to in-cell Crane Maintenance Area IF container swab monitoring glove box MSM & shielded viewing window MSM extraction hoist & beam Stairwell to -3m level Shielded cell wall 1.350m thk Original Concept Design
  • 11. association for project management Original Concept Design Original Storage for 300 IF containers
  • 12. association for project management Flask Handling Area
  • 13. association for project management Z6022 Transfer Hall
  • 14. association for project management Plant Rooms
  • 15. association for project management Nuclear Technology and Innovation • BIM - The project was delivered using a BIM (Building Information Modelling) Level 2 process whereby the majority of plant design definition was incorporated into one 3D model. Supporting drawings were reduced to a minimum. • The team developed new processes for checking/approving designs and working with the 3D model and managed the records electronically which streamlined the process significantly reducing timescales. Making it Happen “Nuvia demonstrated their ability to truly integrate with the client team to deliver the scheme design scope. To collaborate, be flexible in meeting our moving requirements, and yet be robust in applying the processes and procedures that ensured the delivery of a substantiated scope of work when it was required. Many a time I challenged Nuvia personnel to 'make it happen', and they delivered.” DSRL Engineering Manager, FLF Project
  • 16. association for project management Throughput video
  • 17. association for project management Nuclear Technology and Innovation Stage 3 Scheme Design The Concept and PSR were completed on schedule and within budget when a significant change in approach was initiated by an emerging opportunity which required the design to be reworked. Project Change Change entailed the de-scoping of many of the original functional processes as they were ‘rolled back’ into their own donor plants. Typically the project completion date remained fixed as it formed part of the site wide decommissioning programme.
  • 18. association for project management Nuclear Technology and Innovation • In delivering the Project with a such a significant change we formed an integrated team with the Client and jointly developed a set of revised baseline design parameters at the outset against which we delivered the design. • The scope of work was developed in stages as we moved forward re-setting objectives around decision points which acted as gateways. This approach provided focus in short term whilst working toward an agreed goal. • Weekly internal technical reviews based around the model were held agreeing approaches and resolving issues as they were encountered. Managing the Change The approach undertaken mitigated potential conflict situations arising.
  • 19. association for project management Delivery Team The team demographic in which the relationship between the discipline leads and the 3D modellers meant that the engineering seniors could be centred on developing engineering solutions in an emerging scope while the modellers were able to focus on producing the designs and integrating the requirements of the engineering teams.
  • 20. association for project management Collaboration and Conflict Management Logistics Separated by a distance of 550+ miles the integrated team needed to work closely and efficiently as we effectively restarted the team building process. Management of potential conflict situations was vital during the ‘forming and storming’ process as we were redefining the project scope whilst delivering on a fast track basis. The new requirements brought many new stakeholders into the project including donor plant Operations, safety and security teams. Rules of engagement were agreed at the outset to promote an open culture and trust.
  • 21. association for project management Logistics – Design Reviews, HAZOPs etc. 24 people at Thurso plus Client team 8 people at Risley Stakeholder Management Use of communications technology such as remote desktop and video conferencing enabling key team members top work collaboratively even when separated by significant distances. This proved a major advantage as it negated the impact of travelling logistics and reduced the time in meetings to a minimum.
  • 22. association for project management Nuclear Technology and Innovation Stakeholder Management • Stakeholder Engagement - Access to Information – The 3D model data was presented through Navisworks, a freeware platform available to all parties without licensing issues. This has the added benefit of reducing demand on PC specification greatly increasing the accessibility of the model data to all stakeholders. • Design Reviews - We implemented a fast track review process in which the MDDR and constructability reviews were held using on screen 3D model walk through's. 2D documentation was reduced to a minimum. “Thanks for all that you and others are doing. I understand that we are pushing hard with it but be assured we appreciate all that you've done and are doing to get us over the line.” DSRL Project Manager, FLF Project As the change introduced many stakeholders new to the project, bringing them ‘up to speed’ as quickly as possible was essential.
  • 23. association for project management Stakeholder Management • Value engineering studies were undertaken to identify innovative or even novel solutions to functional requirements, simplifying plant maintenance and identify cost saving initiatives. • In-cell equipment was minimised to meet the requirements of the process and reduce the decommissioning challenges at the end of plant life. • Other stakeholders who were engaged from the outset included operations, RPA and SHE representatives throughout the design process to ensure buy-in and produce a proposal capable of meeting all operational and legislative requirements. Along with the change of scope we needed to ensure that the Project Benefits were maintained and where required re-defined.
  • 24. association for project management Benefit Realisation • Focus on use of existing Plant Functionality - The use of existing DSRL equipment within the donor plants was exploited where possible and newly specified equipment was aligned with the existing site maintenance capability. • Economic materials such as aluminium cladding were selected to maximise the opportunities offered by a short plant life. • Plant infrastructure was reduced to a minimum, full advantage being taken of opportunities such as natural ventilation where plant operating conditions permitted. • Space envelopes have been claimed to give the design the flexibility to incorporate additional capabilities should the need arise as the unknowns in the baseline data reach maturity. Along with the change of scope we needed to ensure that the Project Benefits were maintained and where required re-defined.
  • 25. association for project management Outcomes Smaller Facility Footprint Final Facility Design Original Concept Design
  • 26. association for project management Outcomes 11.47m 8.98m 8.85m 20.07m 3.00m Simplification of In-cell Operation Original Concept Design Final Cell Design
  • 27. association for project management Client Feedback DSRL was able to meet the requirements of the overall decommissioning programme and successfully navigate the ONR milestone for completion. The project is considered by DSRL to be a major success. “We are now in receipt of the scheme design for the flask loading facility Can I take this opportunity in offering my congratulations to all of you and your teams in achieving this. The journey to get to this point has at moments been difficult but there is no doubt when everyone pushes in the same direction with the same aim that significant things are achieved.” DSRL Project Manager, FLF Project
  • 28. association for project management Sharing LFE from the Project 8 2 5 7 3 6 4 1 COSTS A 55% DD&B cost reduction was achieved DELIVERY We delivered a PSR in an accelerated timeframe – from Hazop to Safe Working Party Review in 7 weeks MILESTONES Every project milestone was successfully achieved REVIEW Designs were subject to independent PBO review and declared to be of a high standard. 1 2 3 4 COMMUNICATION Effective communication is vital to collaboration and ultimately project success. APPROACH BIM Model approach is foundation for Detailed Design and Construction Information – (A process therefore following straight through). INNOVATION BIM encourages innovation and streamlining review processes EFFICIENCY Significant use of BIM, as trialled on this project, has indicated improvements in efficiencies, potentially providing competitive advantage. 5 6 7 8 £
  • 29. This presentation was delivered at an APM event To find out more about upcoming events please visit our website www.apm.org.uk/events