SlideShare une entreprise Scribd logo
1  sur  64
Télécharger pour lire hors ligne
Project Lessons from the Great Escape (Stalag Luft III)
New publication from the lessons-from-history series

Dedicated to Sagan’s
50 and others
Presentation at APM South
Wales and West of England
branch
November 13th, 2013
Mark Kozak-Holland BSc (Hons),
PMP, IPMA-D, Cert.APM
“Lessons From the Past that Assist the Projects of
Today to Shape the World of Tomorrow”
www.lessons-from-history.com
http://www.thegreatescapememorialproject.com/
Project Lessons from the Great Escape

www.lessons-from-history.com

© 2013 Mark Kozak-Holland
Incredible story of mass escape of Allied PoWs from Stalag Luft
III in March 1944. Today we can learn from this project.

 How it was originated and developed?
 How complex problems were solved?
 How it was managed and implemented?
 Its outcome based on events in March 1944?

 Please prepare questions for the end.

This presentation is the property of Mark Kozak-Holland

2

Project Lessons from the Great Escape

www.lessons-from-history.com

© 2013 Mark Kozak-Holland
Table of contents

1. Background
2. Problems
3. APM BOK
4. Solutions
5. Timeline to Escape
6. Post Mortem

3

Project Lessons from the Great Escape

www.lessons-from-history.com

© 2013 Mark Kozak-Holland
The defeated PM - what excuse is it today?

 Intimidating scope
 No resources
 Time constraints
 Uncoordinated team
 Too many problems
 Unclear objectives

 Hostile groups trying to close project
 No executive sponsor

4

Project Lessons from the Great Escape

www.lessons-from-history.com

© 2013 Mark Kozak-Holland
Imagine life as Allied Airman shot down during World War II, in
a Prisoner of War (PoW) camp.
 Bailing out
– Hostile population
 Captured by Luftwaffe
– Interrogation
– Monitored by Gestapo
 Behind barbed wire
– No outside news
 Scrutinized 24 hours a day
– Continuous surveillance
– No privacy
– Communications censored
 Length in captivity
– 1940-1944

5

Project Lessons from the Great Escape

www.lessons-from-history.com

© 2013 Mark Kozak-Holland
Consider the living conditions as a PoW
 Climate
– -25C to +25C
 Daily calorie intake
– Rec. 3,000, actual 1,500 - 1,900
• Breakfast – 2 slices of bread, jam,
ersatz coffee
• Lunch - Watery soup
• Dinner – 2 slices of bread

 Daily regime
– Roll call twice, morning and night
– Boredom
 Hygene
– Cold water only
– Fleas lice, scabies, and bed bugs
6

Project Lessons from the Great Escape

www.lessons-from-history.com

© 2013 Mark Kozak-Holland
Living conditions as a PoW were grueling to harsh
 No extra clothing
 Living space
– 600 PoWs, 60 acres.
– 1 heater/hut – 1 coal lump/person
 Cooler
– 5-15 days, harassment and beatings

 Diseases
– 40% - Upper Respiratory
– 20% - War wounds (fractures)
– 10% - Gastrointestinal
– 10% - Skin
– 10% - Diphtheria
– 10% - Other
7

Project Lessons from the Great Escape

www.lessons-from-history.com

© 2013 Mark Kozak-Holland
So what were the options for individual POWs, some
imprisoned for 4 years.
 Wait war out
– Atrocious conditions
– Hope right side wins
– Hope Gestapo don’t call
– Psychological stress

 Try and escape
– Wage war
– Give men hope

Lessons for
today – weigh
up the
options.

8

Project Lessons from the Great Escape

www.lessons-from-history.com

© 2013 Mark Kozak-Holland
There were short and long term benefits in organizing an
escape.
Lessons for today – clearly state short and long term organizational benefits


Camp population:
– 25% escapers (5% dedicated), 75% support



Short term:
– Occupy men, give goal, restore confidence in leaders



Long term:
– Psychological battle, tie down enemy resources
– Expand war, demoralize enemy

9

Project Lessons from the Great Escape

www.lessons-from-history.com

© 2013 Mark Kozak-Holland
Table of contents

1. Background
2. Problems
3. APM BOK
4. Solutions
5. Timeline to Escape
6. Post Mortem

10

Project Lessons from the Great Escape

www.lessons-from-history.com

© 2013 Mark Kozak-Holland
There were almost insurmountable problems and constraints
that needed to be prioritized and overcome.
Lessons for today – clearly state
organizational challenges
Snooping “ferrets”
No where to hide
Few raw materials
No equipment or tools
Erratic food/ fuel supply










No documents, passes



Project Lessons from the Great Escape

Foreign language



11

Civilian clothing strictly forbidden

Limited currency

www.lessons-from-history.com

© 2013 Mark Kozak-Holland
The first problem preventing escape was location and
unknown outside world.
Lessons for today – assess geographic constraints

 Distance to Sweden, Switzerland, Spain
 Hermetically sealed from communities
 Pine forest, sandy soil
12

Project Lessons from the Great Escape

www.lessons-from-history.com

© 2013 Mark Kozak-Holland
The second problem preventing escape were prowling enemy
guards.
Lessons for today – assess organizational constraints
 Guards or “Goons”
– Changed frequently, old or wounded
– 12 guards wandering the compound

 Ferrets
– Intelligence escape specialists
– Enter any time, search no warning

– English-speaking

Lessons for today – assess constraints
13

Project Lessons from the Great Escape

– Tunneling allowed to continue

www.lessons-from-history.com

© 2013 Mark Kozak-Holland
The third problem preventing escape were physical barriers
around camp.
Lessons for today – assess the physical constraints
 Search towers, flood lights
 Trip wire, shoot zone
 Double barbed-wire fences
 Huts stilts

 Seismographs - 33 feet

14

Project Lessons from the Great Escape

www.lessons-from-history.com

© 2013 Mark Kozak-Holland
The fourth problem preventing escape was going incognito in
the outside world.
 Language and culture
 Going unnoticed disguises

Lessons for today – assess the
cultural constraints

 No public sympathy, “terror flyers”
 No currency

 Kugel Erlass (bullet decree)
immediate execution
15

Project Lessons from the Great Escape

www.lessons-from-history.com

© 2013 Mark Kozak-Holland
The fifth problem preventing escape was survival in harsh
environment and climate, summer was escape season.
 November to March
snow

 Access to water,
food, and shelter
Lessons for today –
assess the survival
constraints

16

Project Lessons from the Great Escape

www.lessons-from-history.com

© 2013 Mark Kozak-Holland
The sixth problem preventing escape was access to
transportation to get to a neutral country and safety.
Lessons for today – assess implementation constraints
Transport

Security
checks

Move
ment

Problems

Risk

Foot

10-15

Only on roads

Night

Finding shelter

Low

Train

100s

Moderate

Day

Disguise scrutinized; currency

Med

Bike

20-60

Few, on roads

Day

Finding bike to steal

Med

Motor vehicle

17

Distance
/day miles

100s

Few, on roads

Day

Fuel; once reported stolen

High

Project Lessons from the Great Escape

www.lessons-from-history.com

© 2013 Mark Kozak-Holland
Table of contents

1. Background
2. Problems
3. APM BOK
4. Solutions
5. Timeline to Escape
6. Post Mortem

18

Project Lessons from the Great Escape

www.lessons-from-history.com

© 2013 Mark Kozak-Holland
Lessons for today “Planning the Strategy”
With tight security escape was thought impossible.


In April 1943 PoWs were moved to the
new North Compound.
An intact “Escape Committee” moved in
(Stakeholder Management)
Lessons from previous escapes






Escapes:
1. Well planned and organized
2. Well executed
3. Change managed
 Beat many complex problems

19

Project Lessons from the Great Escape

www.lessons-from-history.com

© 2013 Mark Kozak-Holland
When the escape committee started to plan their escape they
were instigating a project of a monumental scale.
 Equivalent to Project Management Plan
 Feasibility
– Idea, approach, proposal, ROI
– Checkpoint 1- assess risk, resources
 Planning and Design
– High level plan
– Preparation for escape
 Production
– Preparation of Tunnel
– Engineering
– Construction and testing
– Checkpoint 2 - Assess risk
 Implementation and Startup
– Implement escape
– Checkpoint 3 - Assess risk
– Collect metrics and determine success
– Consider rerun (reuse)
20

Project Lessons from the Great Escape

www.lessons-from-history.com

© 2013 Mark Kozak-Holland
At Checkpoint 1 the escape committee was faced with the
conundrum of Return on Investment and project scope.
Lessons for today “Value Management”
Approach to
escape

# of

Description

Example

Resources
required

Risk of
Discovery

escapees

Unplanned
opportunistic

1-2

Take advantage of presented
situation

Hide in back of a
truck

Low

Low

Planned, used
once only

1-3

Escape route exposed

Cutting through
wire

Med

Low

Planned, reused
several

1 - 10

Escape route preserved, mass
escape over period

Tunnel

Med

High

Planned, used
once only

Up to 250

Escape route exposed

Tunnel

High

High

21

Project Lessons from the Great Escape

www.lessons-from-history.com

© 2013 Mark Kozak-Holland
The escape committee assessed project risks (qualitative and
quantitative) and modified project plans to accommodate it.
Lessons for today “Project Risk Management” and “Health and Safety”

 Hiding project
– From nosy ferrets on danger list
 Discovery of tunnel
– Multiple tunnels built in parallel
 Good enough POW disguise
– Plausible role
 Escape through tunnel
– Without detection
 Getting away from camp Geneva
Convention
– Not in uniform shot
 Traveling distances
– Forged passes & money.
 Survival in open
22

Project Lessons from the Great Escape

www.lessons-from-history.com

© 2013 Mark Kozak-Holland
The escape committee realized that mistakes were intolerable.
One slip up would give the game away.
 Concealing tunnel entrance
 Tunnel construction, secretly & safely

Lessons for today “Project Quality
Management”, determine where
quality is critical

 Forged documents scrutinized
 Clothing - meld wearer

23

Project Lessons from the Great Escape

www.lessons-from-history.com

© 2013 Mark Kozak-Holland
Once out the POWs depended with their lives on disguises
and documents.
 Forged documents scrutinized
 Clothing - meld wearer

24

Project Lessons from the Great Escape

Lessons for today “Project Quality
Management”, determine where
quality is critical in project

www.lessons-from-history.com

© 2013 Mark Kozak-Holland
Lessons for today “Executing the Strategy”
Utilize hard-won experience acquired by POWs
Lessons for today “Scope Management”- Philosophy reduce scope were
possible

 Scope carefully considered and its constraints
 Scope of tunnels
– Number was determined by the number of concrete
foundations available and the risk of discovery
– Depth and length determined by distance from camp to woods
and available tunnel shoring materials
 Scope of intelligence and security required
– Six guards were wandering around in the compound
– Number of escapers that could get through tunnel in given
night

25

Project Lessons from the Great Escape

www.lessons-from-history.com

© 2013 Mark Kozak-Holland
The escape committee evaluated the activities, their
sequencing, resources, duration and schedule.


Lessons for today “Scheduling”

Primary Activities
1. Tunnel (engineering & sand dispersal)

2. Preparing escapers


Time construct tunnel, constraints:
–

Manpower available

–

Impact of seasons, climate



26

Project Lessons from the Great Escape

Time to prepare escapers:
– Profiles – language, responses
– Identities, documents
– Disguises, clothes

www.lessons-from-history.com

© 2013 Mark Kozak-Holland
The escape committee created project teams to overcome the
various problems based on available skill sets.
Lessons for today – pick your project team with care, “Resource Management”

Escape
Committee
X Organisation

Big X

Intelligence
gathering

Equipment &
tool making

Tunnel
engineering

Document
production

Map
making

Clothing
production

Internal
security

Compass
factory

Dispersals

Dispersal
diversions

Cultural
training

Supplies

Professions, Trades and Skill Sets in the Camp
Miners, Forgers, Tailors, Carpenters, Physicists and Geologists,
Engineers, Surveillance Experts, Electricians, Tinsmiths
27

Project Lessons from the Great Escape

www.lessons-from-history.com

© 2013 Mark Kozak-Holland
The escape committee evaluated available resources (Cost
Estimating – Labor, Cost Budgeting, Cost Control)
 Food and parcels
Lessons for today “Budgeting and Cost Management”
– Not seen in Germany
– Relatives sent 1
parcel/man/week or month.
– International Red Cross:
• Clothes, shave/wash kits,
food.

– Captured officers paid

28

Project Lessons from the Great Escape

www.lessons-from-history.com

© 2013 Mark Kozak-Holland
The escape committee communicated the plan to other PoWs
to get buy-in and active participation in the project.
 Compliance, adoption, communication plans
 Adoption plan sell camp
– Contribute & support
 Incredible level of trust existed
– Impeccable security

Lessons for today
“Communication”

29

Project Lessons from the Great Escape

www.lessons-from-history.com

© 2013 Mark Kozak-Holland
The escape committee procured resources like tools and raw
materials essential to the project.
 Liberating wire for tunnel
lights

Lessons for today “Procurement”

 Visit of high ranking General
 Food and tobacco part of
procurement

30

Project Lessons from the Great Escape

www.lessons-from-history.com

© 2013 Mark Kozak-Holland
Table of contents

1. Background
2. Problems
3. APM BOK
4. Solutions
5. Timeline to Escape
6. Post Mortem

31

Project Lessons from the Great Escape

www.lessons-from-history.com

© 2013 Mark Kozak-Holland
Solution to the unknown (problem 1) required Intelligence
gathering
Lessons for today – assess all options
 Befriend guards German speakers
 Rope in first time
 Blackmail many times
– Some cooperative, railway
timetables, maps, & official papers
 Bushell monitors progress
 Kommendant provides camera &
film

32

Project Lessons from the Great Escape

www.lessons-from-history.com

© 2013 Mark Kozak-Holland
Solution to location (problem 1) required map making
capability based on intelligence gathered
 Team forged maps
– Rice paper, sewn into uniforms.
– Mimeograph

33

Project Lessons from the Great Escape

www.lessons-from-history.com

© 2013 Mark Kozak-Holland
Solution to prowling Guards, Goons and Ferrets (problem 2)
required sophisticated internal security
Lessons for today – leverage organizational intelligence where possible

 "Duty Pilot" system
 Security system "stooging"
 “Stool pigeons” 2 witness
 Inter-camp semaphore

34

Project Lessons from the Great Escape

www.lessons-from-history.com

© 2013 Mark Kozak-Holland
Solution to physical barriers (problem 3) required equipment
and tool making capability.
 Manufacturing
– Spades, blades, knives, hacksaws

35

Project Lessons from the Great Escape

www.lessons-from-history.com

© 2013 Mark Kozak-Holland
Solution to physical barriers (problem 3) required tunnel
preparation and engineering.
 Tunnel size width 2’
 Required huge number of physical
resources.
– 4,000 bedboards; 1,370 beading battens;
1,699 blankets; 161 pillow cases; 635
palliasses; 34 chairs; 52 20-man tables; 90
double tier bunks; 1,219 knives; 478 spoons;
30 shovels;
– 1,000 ft electric wire; 600 ft rope; 192 bed
covers; 3,424 towels; 1,212 bed bolsters; 10
single tables; 76 benches; 246 water cans;
582 forks; 69 lamps.

 Tunneling crude tools.
 Sand dispersal 'Penguins’.

36

Project Lessons from the Great Escape

www.lessons-from-history.com

© 2013 Mark Kozak-Holland
Solution to going incognito (problem 4) required a document
production unit known as "Dean and Dawson" (travel agents).
 Official stamps, papers changed often
 Forged papers (over 400) :
– Passports (studio), permission on
Wehrmacht property, military leave pass
– foreign workers returning home,
– general identity card, visa, currency,
– pass and temporary pass.

 Weeks to reproduce:
– Hand stenciled.
– Official stamps rubber heels.
37

Project Lessons from the Great Escape

www.lessons-from-history.com

© 2013 Mark Kozak-Holland
Solution to going incognito (problem 4) required the
production of clothing

 Civilian clothing forbidden
 Military uniforms cobbled together

 Escapees carried aircrew badges secretly
 Conversion of uniforms
38

Project Lessons from the Great Escape

www.lessons-from-history.com

© 2013 Mark Kozak-Holland
Solution to survival (problem 5) required survival rations
 "Foodacco" collective bargaining
and bartering
 Food hoarded for
escape

 Baked iron rations
 Canisters
39

Project Lessons from the Great Escape

www.lessons-from-history.com

© 2013 Mark Kozak-Holland
Solution to access to transportation (problem 6) required
profiling PoWS.


Train travel to
Suitcase brigade
1. Germanspeakers
2. Experienced
escapers
3. Greatest
contributors
 Foot travel for
“Hard-arsers" or
Blanket brigade
– Hide day “footslog by night”.
– Rudimentary
false papers &
identities.

Business travelers or foreign workers
40

Project Lessons from the Great Escape

www.lessons-from-history.com

© 2013 Mark Kozak-Holland
Table of contents

1. Background
2. Problems
3. APM BOK
4. Solutions
5. Timeline to Escape
6. Post Mortem

41

Project Lessons from the Great Escape

www.lessons-from-history.com

© 2013 Mark Kozak-Holland
July 1943 – construction on new camp starts
 Robs US airmen chance to escape.
 'Dick' abandoned.
– Ideal for clothing, contraband, workshop.
 Bushell put entire effort into "Tom."
 Skills transfer to US airmen.

42

Project Lessons from the Great Escape

www.lessons-from-history.com

© 2013 Mark Kozak-Holland
August 1943 - As tunnel reached perimeter fence trees were
cleared
 Microphones detecters pick up activity.
 Guards believed tunnel near
completion.
 Traces of tunnel sand spotted in
gardens.
 Five hour search of Hut 123 found
nothing.

43

Project Lessons from the Great Escape

www.lessons-from-history.com

© 2013 Mark Kozak-Holland
September 1943 - Tom discovered at 85 m, only 16m short of
completion. Guards surprised at its scale
 Intelligence alerted Bushell - 2,000 bed boards
plundered before count, and hidden down Dick.
 Dick - clothing, contraband, manufacturer
workshop.

44

Project Lessons from the Great Escape

www.lessons-from-history.com

© 2013 Mark Kozak-Holland
October – December 1943 - Tunnelling stopped.
activities switch away
 Equipment and tool making capability.
 Compass Factory.
 POWs moved around in job reshuffle.

45

Project Lessons from the Great Escape

www.lessons-from-history.com

© 2013 Mark Kozak-Holland
January 1944 - nervous about discovery of the project Bushell
restarted Harry. However, project showstopper was SAND
 Surplus sand into 'Dick'. Solution in theatre.
 Tunnel (336 foot) with miner’s rail, electric lights,
air ventilation

46

Project Lessons from the Great Escape

www.lessons-from-history.com

© 2013 Mark Kozak-Holland
Feb, 1944 – Ferret take 19 top suspects and 6 key men to
Stalag VIIIC at Belaria
• Bushell taken off list
• Deputies took over
• Project tracking and managing
change to accommodate risk

47

Project Lessons from the Great Escape

www.lessons-from-history.com

© 2013 Mark Kozak-Holland
March 1944 - Ideal conditions required for a night escape but
debate whether to go








48

Four conditions Bushell wanted:
– No moon
– A wind to disguise noises
– Good weather
– No ferrets around
Next moonless nights March 23/24/25.
25th Saturday - poor train tables,
No trains Sunday.
Arguments to postpone to April and
better weather.
Harry would not survive wet month of
April.

Project Lessons from the Great Escape

www.lessons-from-history.com

© 2013 Mark Kozak-Holland
March 23, 1944 - Day before, Bushell re-emphasizes objectives
with "Wings" Day and determines to go ahead with escape.
 “The weather’s going to be bloody awful, and will probably
get worse. 90% of the hardarsers will run into deep snow in
the mountains…[but it]…Doesn’t matter. It will give the Nazis
an almighty shock. 200 looney escape artists roaring around
the countryside.”

– Conversation between Roger Bushell, and Wings Day prior to
the escape.

49

Project Lessons from the Great Escape

www.lessons-from-history.com

© 2013 Mark Kozak-Holland
March 24, 1944 – Day of escape

 POW
congregate in
Hut 104
 9:45 Problems in
breakout
 Frozen trap
door

 Clever
improvisation
to continue

50

Project Lessons from the Great Escape

www.lessons-from-history.com

© 2013 Mark Kozak-Holland
In the Implementation and startup things started to go badly
wrong
 10:30 First out
from suitcase
brigade
 00:00 1 hour air
raid
 01:30 Tunnel cave
in

51

Project Lessons from the Great Escape

www.lessons-from-history.com

© 2013 Mark Kozak-Holland
The passage of escapers greatly slowed
 03:00 Blanket
brigade begins
 03:30 Word
sent back, 100
could escape
 Expected
throughput
60/hour, actual
12/hour.
 04:55 - 76
escapers were
out

52

Project Lessons from the Great Escape

www.lessons-from-history.com

© 2013 Mark Kozak-Holland
Breakout and escapers get away

 Escaper at exit
mixed up
signals
emerged under
guard

 Men in tunnel
returned to Hut
104
 Burned false
papers ate
rations

53

Project Lessons from the Great Escape

www.lessons-from-history.com

© 2013 Mark Kozak-Holland
Best chance was for suitcase brigade

 Station 1 mile from camp

 Many escapers could not find station,
missed trains.
 At dawn many POWs still on the platform,
ignoring each other.

 Bushell awaited the 3:30am service to
Breslau and arrived 5:00am.

54

Project Lessons from the Great Escape

www.lessons-from-history.com

© 2013 Mark Kozak-Holland
Who got where? 76 of 250 got out. Many escapers could not
find station, missed trains. 3 got to neutral country, "home run"
 Norwegians
(2) reach
Sweden
 Dutchman
reaches
Gibraltar via
France
/Spain (3.5
months).
 ~50 men
caught
within few
miles
 15 men
escape to
free
territory but
got caught

55

Project Lessons from the Great Escape

www.lessons-from-history.com

© 2013 Mark Kozak-Holland
Table of contents

1. Background
2. Problems
3. APM BOK
4. Solutions
5. Timeline to Escape
6. Post Mortem

56

Project Lessons from the Great Escape

www.lessons-from-history.com

© 2013 Mark Kozak-Holland
Was the project a success?

 Pros
– Massive disruption, million men looking
– Hitler outraged, diversion to war
 Cons
– Too few got out and away

– 50 captured and executed

57

Project Lessons from the Great Escape

www.lessons-from-history.com

© 2013 Mark Kozak-Holland
Lessons learned – the positives from the project
 Limited material resources
– Everything saved
 Decentralized organization
– 600 men were engaged
 High performance team
– Committed to cause

Lessons for today – nothing is
impossible

 Ad hoc group used diverse talents
 Extraordinarily difficult task
– Adverse circumstances
 Problems solved
– Continuous innovation
58

Project Lessons from the Great Escape

www.lessons-from-history.com

© 2013 Mark Kozak-Holland
Lessons learned downside - Airmen - Australia, Canada,
France, Greece, Holland, Norway, Poland, South Africa, &UK
 No rerun
– Poor ROI, massive
investment
 Attention to
implementation
– Priority to greatest
contributors
– March best month?
– Many escapers
drew attention?
 No withdrawal plan
– Tunnel too short
– No stopping
– Emotions
unchecked, desire
to get out
 Effective Project
Management?

59

Lessons for today – pay attention to all phases of project

Project Lessons from the Great Escape

www.lessons-from-history.com

© 2013 Mark Kozak-Holland
Lessons learned – Too much focus on the tunnel and its
construction
 Project Objectives
– Clear at outset, unclear in hindsight
– Game or sport
 WWII 30 of 10,000 RAF airmen reached safety.
 17% of PoWs died in German camps.

 Escapes more dangerous but continued.

60

Project Lessons from the Great Escape

www.lessons-from-history.com

© 2013 Mark Kozak-Holland
Questions

Presentation available on-line
Mark available to work with you and your organization (PMs and Executives),
speak or run workshops.
http://www.lessons-from-history.com/
Sign up for lessons-from-history newsletter (subscribe/unsubscribe).
Twitter @LessonsfromHist
You tube – ProjectLessons
http://ca.linked.com/in/markkozakholland
Skype name - mark.kozak.holland
Email: mark.kozak-holl@sympatico.ca
64

Project Lessons from the Great Escape

www.lessons-from-history.com

© 2013 Mark Kozak-Holland
Lessons-from-History is a series of publications for today’s
business world, established in 2001.
 Our authors are from the business world
but, with a deep passion for history.
 The authors are highly experienced and
working project managers, consultants,
business analysts.

 This combination of business and history
provides a deeper understanding of
challenges faced by today's business.

John J.

Byrne
65

Paul R.
Bruno

Michael
Dobson

Lessons From History Overview

Ian
Hughes

Mark
KozakHolland

Glen
LeClair

Bob
Lerner

www.lessons-from-history.com

Joe
Luttrell

Jerry
Manas

Ranjit
Sidhu

© 2013 Mark Kozak-Holland
Get signed copies, SPECIAL DISCOUNT of 30%
(business receipt, checks, credit cards).
 Value proposition - 100’s of best
practices, implemented save
1000’s of dollars
 “This book and others by Mark
Kozak-Holland are a
tremendous resource for
educators-the stark reality of
failed projects and Mark’s
detailed research, historical
accuracy, and the link to the
BOK, helps us to analyze and
understand we are not alone in
managing our complex projects
today. The incredible
resourcefulness and bravery of
these men gives us hope on our
own troubled projects.
 Linda F. Desmond, PMP, Project
Management Trainer/Consultant
President of Mass Bay Chapter,
PMI
66

Project Lessons from the Great Escape

£10

Also available at
http://www.mmpubs.com/books-LFH.html
Or call 1-866-721-1540
www.lessons-from-history.com
Please contact Mark:
mark.kozak-holl@sympatico.ca
www.lessons-from-history.com

© 2013 Mark Kozak-Holland
Credits and Sources

 http://www.historyinfilm.com/escape/real1.htm
 http://www.pbs.org/wgbh/nova/greatescape/
 http://www.u-s-history.com/pages/h1778.html
 http://www.b24.net/pow/stalag3.htm
 http://www.afhi.org/museum/stalag/escape.html
 http://www.elsham.pwp.blueyonder.co.uk/gt_esc/
 http://www.au.af.mil/au/goe/eaglebios/84bios/stok84.htm

 http://www.inyourpocket.com/poland/poznan/en/feature?id=4326
 http://www.pegasus-one.org/pow/pSL_3
 http://www.simonsays.com/content/book.cfm?sid=33&pid=508729
 The Great Escape, by Paul Brickhill

 The Longest Tunnel, by Alan Burgess

67

Project Lessons from the Great Escape

www.lessons-from-history.com

© 2013 Mark Kozak-Holland

Contenu connexe

Tendances

Rapport projet fin d'études SALAH EDDINE GHANDRI
Rapport projet fin d'études SALAH EDDINE GHANDRI Rapport projet fin d'études SALAH EDDINE GHANDRI
Rapport projet fin d'études SALAH EDDINE GHANDRI Salah Eddine Ghandri
 
Supply Chain Management of DHL Express Operations
Supply Chain Management of DHL Express Operations Supply Chain Management of DHL Express Operations
Supply Chain Management of DHL Express Operations Talha Bin Irfan Usmani
 
Project Planning and Management of Millau Viaduct Bridge, France
Project Planning and Management of Millau Viaduct Bridge, FranceProject Planning and Management of Millau Viaduct Bridge, France
Project Planning and Management of Millau Viaduct Bridge, FranceRakibul Hasan,MEng,EIT
 
Rapport PFE | Eolane | Amélioration de la productivité de l'atelier CMS
Rapport PFE | Eolane | Amélioration de la productivité de l'atelier CMSRapport PFE | Eolane | Amélioration de la productivité de l'atelier CMS
Rapport PFE | Eolane | Amélioration de la productivité de l'atelier CMSZouhair Boufakri
 
Delhi metro rail corporation project
Delhi metro rail corporation projectDelhi metro rail corporation project
Delhi metro rail corporation projectVimal Maurya
 
Case Study: DHL Shifts Left With CA Application Performance Management to Bo...
Case Study: DHL Shifts Left With CA Application Performance Management to Bo...Case Study: DHL Shifts Left With CA Application Performance Management to Bo...
Case Study: DHL Shifts Left With CA Application Performance Management to Bo...CA Technologies
 
Evaluation and Reduction of Truck Turnaround Time
Evaluation and Reduction of Truck Turnaround Time Evaluation and Reduction of Truck Turnaround Time
Evaluation and Reduction of Truck Turnaround Time Rutulshah15
 
IIT BHU B-Club Casebook 3 (2022).pdf
IIT BHU B-Club Casebook 3 (2022).pdfIIT BHU B-Club Casebook 3 (2022).pdf
IIT BHU B-Club Casebook 3 (2022).pdfEtoosEdu
 
Hindustan Construction Company (HCC)
Hindustan Construction Company (HCC)Hindustan Construction Company (HCC)
Hindustan Construction Company (HCC)Sk Md Nayar
 
Portfolio, Project and Programme Management
Portfolio, Project and Programme ManagementPortfolio, Project and Programme Management
Portfolio, Project and Programme ManagementBruce Levitan
 
Edita.Logistics Management
Edita.Logistics ManagementEdita.Logistics Management
Edita.Logistics Managementsally sanhory
 
The Eurotunnel Project - Cam Ready.pdf
The Eurotunnel Project - Cam Ready.pdfThe Eurotunnel Project - Cam Ready.pdf
The Eurotunnel Project - Cam Ready.pdfAnkur829275
 
DHL Express Public Sector team
DHL Express Public Sector teamDHL Express Public Sector team
DHL Express Public Sector teamKen Nielsen
 

Tendances (20)

DHL
DHLDHL
DHL
 
Rapport projet fin d'études SALAH EDDINE GHANDRI
Rapport projet fin d'études SALAH EDDINE GHANDRI Rapport projet fin d'études SALAH EDDINE GHANDRI
Rapport projet fin d'études SALAH EDDINE GHANDRI
 
Supply Chain Management of DHL Express Operations
Supply Chain Management of DHL Express Operations Supply Chain Management of DHL Express Operations
Supply Chain Management of DHL Express Operations
 
Casestudy on DHL
Casestudy on DHLCasestudy on DHL
Casestudy on DHL
 
Project Planning and Management of Millau Viaduct Bridge, France
Project Planning and Management of Millau Viaduct Bridge, FranceProject Planning and Management of Millau Viaduct Bridge, France
Project Planning and Management of Millau Viaduct Bridge, France
 
Rapport PFE | Eolane | Amélioration de la productivité de l'atelier CMS
Rapport PFE | Eolane | Amélioration de la productivité de l'atelier CMSRapport PFE | Eolane | Amélioration de la productivité de l'atelier CMS
Rapport PFE | Eolane | Amélioration de la productivité de l'atelier CMS
 
Supply chain of dhl
Supply chain of  dhlSupply chain of  dhl
Supply chain of dhl
 
Delhi metro rail corporation project
Delhi metro rail corporation projectDelhi metro rail corporation project
Delhi metro rail corporation project
 
Maersk Company
Maersk CompanyMaersk Company
Maersk Company
 
Case Study: DHL Shifts Left With CA Application Performance Management to Bo...
Case Study: DHL Shifts Left With CA Application Performance Management to Bo...Case Study: DHL Shifts Left With CA Application Performance Management to Bo...
Case Study: DHL Shifts Left With CA Application Performance Management to Bo...
 
Dhl final
Dhl finalDhl final
Dhl final
 
Evaluation and Reduction of Truck Turnaround Time
Evaluation and Reduction of Truck Turnaround Time Evaluation and Reduction of Truck Turnaround Time
Evaluation and Reduction of Truck Turnaround Time
 
IIT BHU B-Club Casebook 3 (2022).pdf
IIT BHU B-Club Casebook 3 (2022).pdfIIT BHU B-Club Casebook 3 (2022).pdf
IIT BHU B-Club Casebook 3 (2022).pdf
 
Hindustan Construction Company (HCC)
Hindustan Construction Company (HCC)Hindustan Construction Company (HCC)
Hindustan Construction Company (HCC)
 
Portfolio, Project and Programme Management
Portfolio, Project and Programme ManagementPortfolio, Project and Programme Management
Portfolio, Project and Programme Management
 
Edita.Logistics Management
Edita.Logistics ManagementEdita.Logistics Management
Edita.Logistics Management
 
The Eurotunnel Project - Cam Ready.pdf
The Eurotunnel Project - Cam Ready.pdfThe Eurotunnel Project - Cam Ready.pdf
The Eurotunnel Project - Cam Ready.pdf
 
DHL Express Public Sector team
DHL Express Public Sector teamDHL Express Public Sector team
DHL Express Public Sector team
 
Crossrail: lessons in governance
Crossrail: lessons in governanceCrossrail: lessons in governance
Crossrail: lessons in governance
 
Sripadasagar project
Sripadasagar projectSripadasagar project
Sripadasagar project
 

En vedette

Case Study - The Great Escape
Case Study -  The Great EscapeCase Study -  The Great Escape
Case Study - The Great EscapeKim Goldspink
 
Teamwork.Lessons from the Great Escape
Teamwork.Lessons from the Great EscapeTeamwork.Lessons from the Great Escape
Teamwork.Lessons from the Great Escaperoshansuhail
 
Looking at mise en-scène in the apartment
Looking at mise en-scène in the apartmentLooking at mise en-scène in the apartment
Looking at mise en-scène in the apartmentMatthew Hartman
 
The Great Escape
The Great EscapeThe Great Escape
The Great Escapekbrenchley
 
Great Escape
Great EscapeGreat Escape
Great Escapekktv
 
The Great Escape
The Great EscapeThe Great Escape
The Great EscapeRavi Reddy
 
Cpd ch 9 engage deeply
Cpd ch 9 engage deeplyCpd ch 9 engage deeply
Cpd ch 9 engage deeplyKamlesh Joshi
 
CPD Chapter 9 Engage Deeply
CPD Chapter 9 Engage DeeplyCPD Chapter 9 Engage Deeply
CPD Chapter 9 Engage DeeplyKazim Marfatiya
 
Plan de Exportacion del TEQUILA
Plan de Exportacion del TEQUILAPlan de Exportacion del TEQUILA
Plan de Exportacion del TEQUILAKaTh JRedding
 

En vedette (9)

Case Study - The Great Escape
Case Study -  The Great EscapeCase Study -  The Great Escape
Case Study - The Great Escape
 
Teamwork.Lessons from the Great Escape
Teamwork.Lessons from the Great EscapeTeamwork.Lessons from the Great Escape
Teamwork.Lessons from the Great Escape
 
Looking at mise en-scène in the apartment
Looking at mise en-scène in the apartmentLooking at mise en-scène in the apartment
Looking at mise en-scène in the apartment
 
The Great Escape
The Great EscapeThe Great Escape
The Great Escape
 
Great Escape
Great EscapeGreat Escape
Great Escape
 
The Great Escape
The Great EscapeThe Great Escape
The Great Escape
 
Cpd ch 9 engage deeply
Cpd ch 9 engage deeplyCpd ch 9 engage deeply
Cpd ch 9 engage deeply
 
CPD Chapter 9 Engage Deeply
CPD Chapter 9 Engage DeeplyCPD Chapter 9 Engage Deeply
CPD Chapter 9 Engage Deeply
 
Plan de Exportacion del TEQUILA
Plan de Exportacion del TEQUILAPlan de Exportacion del TEQUILA
Plan de Exportacion del TEQUILA
 

Plus de Association for Project Management

APM Project Management Awards - Hints and tips for a winning award entry webi...
APM Project Management Awards - Hints and tips for a winning award entry webi...APM Project Management Awards - Hints and tips for a winning award entry webi...
APM Project Management Awards - Hints and tips for a winning award entry webi...Association for Project Management
 
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024Association for Project Management
 
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...Association for Project Management
 
AI in the project profession: examples of current use and roadmaps to adoptio...
AI in the project profession: examples of current use and roadmaps to adoptio...AI in the project profession: examples of current use and roadmaps to adoptio...
AI in the project profession: examples of current use and roadmaps to adoptio...Association for Project Management
 
Scaling New Heights: Project Management on the world’s 3rd highest peak
Scaling New Heights: Project Management on the world’s 3rd highest peakScaling New Heights: Project Management on the world’s 3rd highest peak
Scaling New Heights: Project Management on the world’s 3rd highest peakAssociation for Project Management
 
Inspire inclusion within the project profession to attract and retain a diver...
Inspire inclusion within the project profession to attract and retain a diver...Inspire inclusion within the project profession to attract and retain a diver...
Inspire inclusion within the project profession to attract and retain a diver...Association for Project Management
 
Discussing the new Competence Framework for project managers in the built env...
Discussing the new Competence Framework for project managers in the built env...Discussing the new Competence Framework for project managers in the built env...
Discussing the new Competence Framework for project managers in the built env...Association for Project Management
 
Successful projects and failed programmes – the cost of not designing the who...
Successful projects and failed programmes – the cost of not designing the who...Successful projects and failed programmes – the cost of not designing the who...
Successful projects and failed programmes – the cost of not designing the who...Association for Project Management
 
APM Volunteer opportunities - Insights in how you can get involved, 7 Februar...
APM Volunteer opportunities - Insights in how you can get involved, 7 Februar...APM Volunteer opportunities - Insights in how you can get involved, 7 Februar...
APM Volunteer opportunities - Insights in how you can get involved, 7 Februar...Association for Project Management
 

Plus de Association for Project Management (20)

APM Project Management Awards - Hints and tips for a winning award entry webi...
APM Project Management Awards - Hints and tips for a winning award entry webi...APM Project Management Awards - Hints and tips for a winning award entry webi...
APM Project Management Awards - Hints and tips for a winning award entry webi...
 
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
 
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
 
Staurt Earl - ARCC Programme for APM Awards.pptx
Staurt Earl - ARCC Programme for APM Awards.pptxStaurt Earl - ARCC Programme for APM Awards.pptx
Staurt Earl - ARCC Programme for APM Awards.pptx
 
If AI changes everything – do feelings still matter?
If AI changes everything – do feelings still matter?If AI changes everything – do feelings still matter?
If AI changes everything – do feelings still matter?
 
AI in the project profession: examples of current use and roadmaps to adoptio...
AI in the project profession: examples of current use and roadmaps to adoptio...AI in the project profession: examples of current use and roadmaps to adoptio...
AI in the project profession: examples of current use and roadmaps to adoptio...
 
Katharine Fox, WRAP - Valuing sustainability
Katharine Fox, WRAP - Valuing sustainabilityKatharine Fox, WRAP - Valuing sustainability
Katharine Fox, WRAP - Valuing sustainability
 
The silent project disruptor: Building AI solutions
The silent project disruptor: Building AI solutionsThe silent project disruptor: Building AI solutions
The silent project disruptor: Building AI solutions
 
Personal Resilience in Project Management 2 - TV Edit 1a.pdf
Personal Resilience in Project Management 2 - TV Edit 1a.pdfPersonal Resilience in Project Management 2 - TV Edit 1a.pdf
Personal Resilience in Project Management 2 - TV Edit 1a.pdf
 
Scaling New Heights: Project Management on the world’s 3rd highest peak
Scaling New Heights: Project Management on the world’s 3rd highest peakScaling New Heights: Project Management on the world’s 3rd highest peak
Scaling New Heights: Project Management on the world’s 3rd highest peak
 
Demystifying digital accessibility webinar
Demystifying digital accessibility webinarDemystifying digital accessibility webinar
Demystifying digital accessibility webinar
 
Inspire inclusion within the project profession to attract and retain a diver...
Inspire inclusion within the project profession to attract and retain a diver...Inspire inclusion within the project profession to attract and retain a diver...
Inspire inclusion within the project profession to attract and retain a diver...
 
Burnout_ Prevention Intervention Recovery.pdf
Burnout_ Prevention Intervention  Recovery.pdfBurnout_ Prevention Intervention  Recovery.pdf
Burnout_ Prevention Intervention Recovery.pdf
 
Discussing the new Competence Framework for project managers in the built env...
Discussing the new Competence Framework for project managers in the built env...Discussing the new Competence Framework for project managers in the built env...
Discussing the new Competence Framework for project managers in the built env...
 
Successful projects and failed programmes – the cost of not designing the who...
Successful projects and failed programmes – the cost of not designing the who...Successful projects and failed programmes – the cost of not designing the who...
Successful projects and failed programmes – the cost of not designing the who...
 
Risk in the changing world – Opportunity or threat
Risk in the changing world – Opportunity or threatRisk in the changing world – Opportunity or threat
Risk in the changing world – Opportunity or threat
 
Time-Honored Wisdom: African Teachings for VUCA Leaders
Time-Honored Wisdom: African Teachings for VUCA LeadersTime-Honored Wisdom: African Teachings for VUCA Leaders
Time-Honored Wisdom: African Teachings for VUCA Leaders
 
APM Volunteer opportunities - Insights in how you can get involved, 7 Februar...
APM Volunteer opportunities - Insights in how you can get involved, 7 Februar...APM Volunteer opportunities - Insights in how you can get involved, 7 Februar...
APM Volunteer opportunities - Insights in how you can get involved, 7 Februar...
 
Including mental health support in project delivery
Including mental health support in project deliveryIncluding mental health support in project delivery
Including mental health support in project delivery
 
Sustainability in Project Management – what you need to know
Sustainability in Project Management – what you need to knowSustainability in Project Management – what you need to know
Sustainability in Project Management – what you need to know
 

Dernier

Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Peter Ward
 
Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMintel Group
 
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City GurgaonCall Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaoncallgirls2057
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessSeta Wicaksana
 
TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024Adnet Communications
 
Cyber Security Training in Office Environment
Cyber Security Training in Office EnvironmentCyber Security Training in Office Environment
Cyber Security Training in Office Environmentelijahj01012
 
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCRashishs7044
 
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCRashishs7044
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCRashishs7044
 
Financial-Statement-Analysis-of-Coca-cola-Company.pptx
Financial-Statement-Analysis-of-Coca-cola-Company.pptxFinancial-Statement-Analysis-of-Coca-cola-Company.pptx
Financial-Statement-Analysis-of-Coca-cola-Company.pptxsaniyaimamuddin
 
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckHajeJanKamps
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCRashishs7044
 
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxmbikashkanyari
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCRashishs7044
 
1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdf1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdfShaun Heinrichs
 
Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy Verified Accounts
 
8447779800, Low rate Call girls in Dwarka mor Delhi NCR
8447779800, Low rate Call girls in Dwarka mor Delhi NCR8447779800, Low rate Call girls in Dwarka mor Delhi NCR
8447779800, Low rate Call girls in Dwarka mor Delhi NCRashishs7044
 

Dernier (20)

Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...
 
Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 Edition
 
Call Us ➥9319373153▻Call Girls In North Goa
Call Us ➥9319373153▻Call Girls In North GoaCall Us ➥9319373153▻Call Girls In North Goa
Call Us ➥9319373153▻Call Girls In North Goa
 
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City GurgaonCall Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful Business
 
TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024
 
Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)
 
Cyber Security Training in Office Environment
Cyber Security Training in Office EnvironmentCyber Security Training in Office Environment
Cyber Security Training in Office Environment
 
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
 
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
 
Financial-Statement-Analysis-of-Coca-cola-Company.pptx
Financial-Statement-Analysis-of-Coca-cola-Company.pptxFinancial-Statement-Analysis-of-Coca-cola-Company.pptx
Financial-Statement-Analysis-of-Coca-cola-Company.pptx
 
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
 
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
 
Corporate Profile 47Billion Information Technology
Corporate Profile 47Billion Information TechnologyCorporate Profile 47Billion Information Technology
Corporate Profile 47Billion Information Technology
 
1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdf1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdf
 
Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail Accounts
 
8447779800, Low rate Call girls in Dwarka mor Delhi NCR
8447779800, Low rate Call girls in Dwarka mor Delhi NCR8447779800, Low rate Call girls in Dwarka mor Delhi NCR
8447779800, Low rate Call girls in Dwarka mor Delhi NCR
 

Project lessons from The Great Escape

  • 1. Project Lessons from the Great Escape (Stalag Luft III) New publication from the lessons-from-history series Dedicated to Sagan’s 50 and others Presentation at APM South Wales and West of England branch November 13th, 2013 Mark Kozak-Holland BSc (Hons), PMP, IPMA-D, Cert.APM “Lessons From the Past that Assist the Projects of Today to Shape the World of Tomorrow” www.lessons-from-history.com http://www.thegreatescapememorialproject.com/ Project Lessons from the Great Escape www.lessons-from-history.com © 2013 Mark Kozak-Holland
  • 2. Incredible story of mass escape of Allied PoWs from Stalag Luft III in March 1944. Today we can learn from this project.  How it was originated and developed?  How complex problems were solved?  How it was managed and implemented?  Its outcome based on events in March 1944?  Please prepare questions for the end. This presentation is the property of Mark Kozak-Holland 2 Project Lessons from the Great Escape www.lessons-from-history.com © 2013 Mark Kozak-Holland
  • 3. Table of contents 1. Background 2. Problems 3. APM BOK 4. Solutions 5. Timeline to Escape 6. Post Mortem 3 Project Lessons from the Great Escape www.lessons-from-history.com © 2013 Mark Kozak-Holland
  • 4. The defeated PM - what excuse is it today?  Intimidating scope  No resources  Time constraints  Uncoordinated team  Too many problems  Unclear objectives  Hostile groups trying to close project  No executive sponsor 4 Project Lessons from the Great Escape www.lessons-from-history.com © 2013 Mark Kozak-Holland
  • 5. Imagine life as Allied Airman shot down during World War II, in a Prisoner of War (PoW) camp.  Bailing out – Hostile population  Captured by Luftwaffe – Interrogation – Monitored by Gestapo  Behind barbed wire – No outside news  Scrutinized 24 hours a day – Continuous surveillance – No privacy – Communications censored  Length in captivity – 1940-1944 5 Project Lessons from the Great Escape www.lessons-from-history.com © 2013 Mark Kozak-Holland
  • 6. Consider the living conditions as a PoW  Climate – -25C to +25C  Daily calorie intake – Rec. 3,000, actual 1,500 - 1,900 • Breakfast – 2 slices of bread, jam, ersatz coffee • Lunch - Watery soup • Dinner – 2 slices of bread  Daily regime – Roll call twice, morning and night – Boredom  Hygene – Cold water only – Fleas lice, scabies, and bed bugs 6 Project Lessons from the Great Escape www.lessons-from-history.com © 2013 Mark Kozak-Holland
  • 7. Living conditions as a PoW were grueling to harsh  No extra clothing  Living space – 600 PoWs, 60 acres. – 1 heater/hut – 1 coal lump/person  Cooler – 5-15 days, harassment and beatings  Diseases – 40% - Upper Respiratory – 20% - War wounds (fractures) – 10% - Gastrointestinal – 10% - Skin – 10% - Diphtheria – 10% - Other 7 Project Lessons from the Great Escape www.lessons-from-history.com © 2013 Mark Kozak-Holland
  • 8. So what were the options for individual POWs, some imprisoned for 4 years.  Wait war out – Atrocious conditions – Hope right side wins – Hope Gestapo don’t call – Psychological stress  Try and escape – Wage war – Give men hope Lessons for today – weigh up the options. 8 Project Lessons from the Great Escape www.lessons-from-history.com © 2013 Mark Kozak-Holland
  • 9. There were short and long term benefits in organizing an escape. Lessons for today – clearly state short and long term organizational benefits  Camp population: – 25% escapers (5% dedicated), 75% support  Short term: – Occupy men, give goal, restore confidence in leaders  Long term: – Psychological battle, tie down enemy resources – Expand war, demoralize enemy 9 Project Lessons from the Great Escape www.lessons-from-history.com © 2013 Mark Kozak-Holland
  • 10. Table of contents 1. Background 2. Problems 3. APM BOK 4. Solutions 5. Timeline to Escape 6. Post Mortem 10 Project Lessons from the Great Escape www.lessons-from-history.com © 2013 Mark Kozak-Holland
  • 11. There were almost insurmountable problems and constraints that needed to be prioritized and overcome. Lessons for today – clearly state organizational challenges Snooping “ferrets” No where to hide Few raw materials No equipment or tools Erratic food/ fuel supply        No documents, passes  Project Lessons from the Great Escape Foreign language  11 Civilian clothing strictly forbidden Limited currency www.lessons-from-history.com © 2013 Mark Kozak-Holland
  • 12. The first problem preventing escape was location and unknown outside world. Lessons for today – assess geographic constraints  Distance to Sweden, Switzerland, Spain  Hermetically sealed from communities  Pine forest, sandy soil 12 Project Lessons from the Great Escape www.lessons-from-history.com © 2013 Mark Kozak-Holland
  • 13. The second problem preventing escape were prowling enemy guards. Lessons for today – assess organizational constraints  Guards or “Goons” – Changed frequently, old or wounded – 12 guards wandering the compound  Ferrets – Intelligence escape specialists – Enter any time, search no warning – English-speaking Lessons for today – assess constraints 13 Project Lessons from the Great Escape – Tunneling allowed to continue www.lessons-from-history.com © 2013 Mark Kozak-Holland
  • 14. The third problem preventing escape were physical barriers around camp. Lessons for today – assess the physical constraints  Search towers, flood lights  Trip wire, shoot zone  Double barbed-wire fences  Huts stilts  Seismographs - 33 feet 14 Project Lessons from the Great Escape www.lessons-from-history.com © 2013 Mark Kozak-Holland
  • 15. The fourth problem preventing escape was going incognito in the outside world.  Language and culture  Going unnoticed disguises Lessons for today – assess the cultural constraints  No public sympathy, “terror flyers”  No currency  Kugel Erlass (bullet decree) immediate execution 15 Project Lessons from the Great Escape www.lessons-from-history.com © 2013 Mark Kozak-Holland
  • 16. The fifth problem preventing escape was survival in harsh environment and climate, summer was escape season.  November to March snow  Access to water, food, and shelter Lessons for today – assess the survival constraints 16 Project Lessons from the Great Escape www.lessons-from-history.com © 2013 Mark Kozak-Holland
  • 17. The sixth problem preventing escape was access to transportation to get to a neutral country and safety. Lessons for today – assess implementation constraints Transport Security checks Move ment Problems Risk Foot 10-15 Only on roads Night Finding shelter Low Train 100s Moderate Day Disguise scrutinized; currency Med Bike 20-60 Few, on roads Day Finding bike to steal Med Motor vehicle 17 Distance /day miles 100s Few, on roads Day Fuel; once reported stolen High Project Lessons from the Great Escape www.lessons-from-history.com © 2013 Mark Kozak-Holland
  • 18. Table of contents 1. Background 2. Problems 3. APM BOK 4. Solutions 5. Timeline to Escape 6. Post Mortem 18 Project Lessons from the Great Escape www.lessons-from-history.com © 2013 Mark Kozak-Holland
  • 19. Lessons for today “Planning the Strategy” With tight security escape was thought impossible.  In April 1943 PoWs were moved to the new North Compound. An intact “Escape Committee” moved in (Stakeholder Management) Lessons from previous escapes    Escapes: 1. Well planned and organized 2. Well executed 3. Change managed  Beat many complex problems 19 Project Lessons from the Great Escape www.lessons-from-history.com © 2013 Mark Kozak-Holland
  • 20. When the escape committee started to plan their escape they were instigating a project of a monumental scale.  Equivalent to Project Management Plan  Feasibility – Idea, approach, proposal, ROI – Checkpoint 1- assess risk, resources  Planning and Design – High level plan – Preparation for escape  Production – Preparation of Tunnel – Engineering – Construction and testing – Checkpoint 2 - Assess risk  Implementation and Startup – Implement escape – Checkpoint 3 - Assess risk – Collect metrics and determine success – Consider rerun (reuse) 20 Project Lessons from the Great Escape www.lessons-from-history.com © 2013 Mark Kozak-Holland
  • 21. At Checkpoint 1 the escape committee was faced with the conundrum of Return on Investment and project scope. Lessons for today “Value Management” Approach to escape # of Description Example Resources required Risk of Discovery escapees Unplanned opportunistic 1-2 Take advantage of presented situation Hide in back of a truck Low Low Planned, used once only 1-3 Escape route exposed Cutting through wire Med Low Planned, reused several 1 - 10 Escape route preserved, mass escape over period Tunnel Med High Planned, used once only Up to 250 Escape route exposed Tunnel High High 21 Project Lessons from the Great Escape www.lessons-from-history.com © 2013 Mark Kozak-Holland
  • 22. The escape committee assessed project risks (qualitative and quantitative) and modified project plans to accommodate it. Lessons for today “Project Risk Management” and “Health and Safety”  Hiding project – From nosy ferrets on danger list  Discovery of tunnel – Multiple tunnels built in parallel  Good enough POW disguise – Plausible role  Escape through tunnel – Without detection  Getting away from camp Geneva Convention – Not in uniform shot  Traveling distances – Forged passes & money.  Survival in open 22 Project Lessons from the Great Escape www.lessons-from-history.com © 2013 Mark Kozak-Holland
  • 23. The escape committee realized that mistakes were intolerable. One slip up would give the game away.  Concealing tunnel entrance  Tunnel construction, secretly & safely Lessons for today “Project Quality Management”, determine where quality is critical  Forged documents scrutinized  Clothing - meld wearer 23 Project Lessons from the Great Escape www.lessons-from-history.com © 2013 Mark Kozak-Holland
  • 24. Once out the POWs depended with their lives on disguises and documents.  Forged documents scrutinized  Clothing - meld wearer 24 Project Lessons from the Great Escape Lessons for today “Project Quality Management”, determine where quality is critical in project www.lessons-from-history.com © 2013 Mark Kozak-Holland
  • 25. Lessons for today “Executing the Strategy” Utilize hard-won experience acquired by POWs Lessons for today “Scope Management”- Philosophy reduce scope were possible  Scope carefully considered and its constraints  Scope of tunnels – Number was determined by the number of concrete foundations available and the risk of discovery – Depth and length determined by distance from camp to woods and available tunnel shoring materials  Scope of intelligence and security required – Six guards were wandering around in the compound – Number of escapers that could get through tunnel in given night 25 Project Lessons from the Great Escape www.lessons-from-history.com © 2013 Mark Kozak-Holland
  • 26. The escape committee evaluated the activities, their sequencing, resources, duration and schedule.  Lessons for today “Scheduling” Primary Activities 1. Tunnel (engineering & sand dispersal) 2. Preparing escapers  Time construct tunnel, constraints: – Manpower available – Impact of seasons, climate  26 Project Lessons from the Great Escape Time to prepare escapers: – Profiles – language, responses – Identities, documents – Disguises, clothes www.lessons-from-history.com © 2013 Mark Kozak-Holland
  • 27. The escape committee created project teams to overcome the various problems based on available skill sets. Lessons for today – pick your project team with care, “Resource Management” Escape Committee X Organisation Big X Intelligence gathering Equipment & tool making Tunnel engineering Document production Map making Clothing production Internal security Compass factory Dispersals Dispersal diversions Cultural training Supplies Professions, Trades and Skill Sets in the Camp Miners, Forgers, Tailors, Carpenters, Physicists and Geologists, Engineers, Surveillance Experts, Electricians, Tinsmiths 27 Project Lessons from the Great Escape www.lessons-from-history.com © 2013 Mark Kozak-Holland
  • 28. The escape committee evaluated available resources (Cost Estimating – Labor, Cost Budgeting, Cost Control)  Food and parcels Lessons for today “Budgeting and Cost Management” – Not seen in Germany – Relatives sent 1 parcel/man/week or month. – International Red Cross: • Clothes, shave/wash kits, food. – Captured officers paid 28 Project Lessons from the Great Escape www.lessons-from-history.com © 2013 Mark Kozak-Holland
  • 29. The escape committee communicated the plan to other PoWs to get buy-in and active participation in the project.  Compliance, adoption, communication plans  Adoption plan sell camp – Contribute & support  Incredible level of trust existed – Impeccable security Lessons for today “Communication” 29 Project Lessons from the Great Escape www.lessons-from-history.com © 2013 Mark Kozak-Holland
  • 30. The escape committee procured resources like tools and raw materials essential to the project.  Liberating wire for tunnel lights Lessons for today “Procurement”  Visit of high ranking General  Food and tobacco part of procurement 30 Project Lessons from the Great Escape www.lessons-from-history.com © 2013 Mark Kozak-Holland
  • 31. Table of contents 1. Background 2. Problems 3. APM BOK 4. Solutions 5. Timeline to Escape 6. Post Mortem 31 Project Lessons from the Great Escape www.lessons-from-history.com © 2013 Mark Kozak-Holland
  • 32. Solution to the unknown (problem 1) required Intelligence gathering Lessons for today – assess all options  Befriend guards German speakers  Rope in first time  Blackmail many times – Some cooperative, railway timetables, maps, & official papers  Bushell monitors progress  Kommendant provides camera & film 32 Project Lessons from the Great Escape www.lessons-from-history.com © 2013 Mark Kozak-Holland
  • 33. Solution to location (problem 1) required map making capability based on intelligence gathered  Team forged maps – Rice paper, sewn into uniforms. – Mimeograph 33 Project Lessons from the Great Escape www.lessons-from-history.com © 2013 Mark Kozak-Holland
  • 34. Solution to prowling Guards, Goons and Ferrets (problem 2) required sophisticated internal security Lessons for today – leverage organizational intelligence where possible  "Duty Pilot" system  Security system "stooging"  “Stool pigeons” 2 witness  Inter-camp semaphore 34 Project Lessons from the Great Escape www.lessons-from-history.com © 2013 Mark Kozak-Holland
  • 35. Solution to physical barriers (problem 3) required equipment and tool making capability.  Manufacturing – Spades, blades, knives, hacksaws 35 Project Lessons from the Great Escape www.lessons-from-history.com © 2013 Mark Kozak-Holland
  • 36. Solution to physical barriers (problem 3) required tunnel preparation and engineering.  Tunnel size width 2’  Required huge number of physical resources. – 4,000 bedboards; 1,370 beading battens; 1,699 blankets; 161 pillow cases; 635 palliasses; 34 chairs; 52 20-man tables; 90 double tier bunks; 1,219 knives; 478 spoons; 30 shovels; – 1,000 ft electric wire; 600 ft rope; 192 bed covers; 3,424 towels; 1,212 bed bolsters; 10 single tables; 76 benches; 246 water cans; 582 forks; 69 lamps.  Tunneling crude tools.  Sand dispersal 'Penguins’. 36 Project Lessons from the Great Escape www.lessons-from-history.com © 2013 Mark Kozak-Holland
  • 37. Solution to going incognito (problem 4) required a document production unit known as "Dean and Dawson" (travel agents).  Official stamps, papers changed often  Forged papers (over 400) : – Passports (studio), permission on Wehrmacht property, military leave pass – foreign workers returning home, – general identity card, visa, currency, – pass and temporary pass.  Weeks to reproduce: – Hand stenciled. – Official stamps rubber heels. 37 Project Lessons from the Great Escape www.lessons-from-history.com © 2013 Mark Kozak-Holland
  • 38. Solution to going incognito (problem 4) required the production of clothing  Civilian clothing forbidden  Military uniforms cobbled together  Escapees carried aircrew badges secretly  Conversion of uniforms 38 Project Lessons from the Great Escape www.lessons-from-history.com © 2013 Mark Kozak-Holland
  • 39. Solution to survival (problem 5) required survival rations  "Foodacco" collective bargaining and bartering  Food hoarded for escape  Baked iron rations  Canisters 39 Project Lessons from the Great Escape www.lessons-from-history.com © 2013 Mark Kozak-Holland
  • 40. Solution to access to transportation (problem 6) required profiling PoWS.  Train travel to Suitcase brigade 1. Germanspeakers 2. Experienced escapers 3. Greatest contributors  Foot travel for “Hard-arsers" or Blanket brigade – Hide day “footslog by night”. – Rudimentary false papers & identities. Business travelers or foreign workers 40 Project Lessons from the Great Escape www.lessons-from-history.com © 2013 Mark Kozak-Holland
  • 41. Table of contents 1. Background 2. Problems 3. APM BOK 4. Solutions 5. Timeline to Escape 6. Post Mortem 41 Project Lessons from the Great Escape www.lessons-from-history.com © 2013 Mark Kozak-Holland
  • 42. July 1943 – construction on new camp starts  Robs US airmen chance to escape.  'Dick' abandoned. – Ideal for clothing, contraband, workshop.  Bushell put entire effort into "Tom."  Skills transfer to US airmen. 42 Project Lessons from the Great Escape www.lessons-from-history.com © 2013 Mark Kozak-Holland
  • 43. August 1943 - As tunnel reached perimeter fence trees were cleared  Microphones detecters pick up activity.  Guards believed tunnel near completion.  Traces of tunnel sand spotted in gardens.  Five hour search of Hut 123 found nothing. 43 Project Lessons from the Great Escape www.lessons-from-history.com © 2013 Mark Kozak-Holland
  • 44. September 1943 - Tom discovered at 85 m, only 16m short of completion. Guards surprised at its scale  Intelligence alerted Bushell - 2,000 bed boards plundered before count, and hidden down Dick.  Dick - clothing, contraband, manufacturer workshop. 44 Project Lessons from the Great Escape www.lessons-from-history.com © 2013 Mark Kozak-Holland
  • 45. October – December 1943 - Tunnelling stopped. activities switch away  Equipment and tool making capability.  Compass Factory.  POWs moved around in job reshuffle. 45 Project Lessons from the Great Escape www.lessons-from-history.com © 2013 Mark Kozak-Holland
  • 46. January 1944 - nervous about discovery of the project Bushell restarted Harry. However, project showstopper was SAND  Surplus sand into 'Dick'. Solution in theatre.  Tunnel (336 foot) with miner’s rail, electric lights, air ventilation 46 Project Lessons from the Great Escape www.lessons-from-history.com © 2013 Mark Kozak-Holland
  • 47. Feb, 1944 – Ferret take 19 top suspects and 6 key men to Stalag VIIIC at Belaria • Bushell taken off list • Deputies took over • Project tracking and managing change to accommodate risk 47 Project Lessons from the Great Escape www.lessons-from-history.com © 2013 Mark Kozak-Holland
  • 48. March 1944 - Ideal conditions required for a night escape but debate whether to go       48 Four conditions Bushell wanted: – No moon – A wind to disguise noises – Good weather – No ferrets around Next moonless nights March 23/24/25. 25th Saturday - poor train tables, No trains Sunday. Arguments to postpone to April and better weather. Harry would not survive wet month of April. Project Lessons from the Great Escape www.lessons-from-history.com © 2013 Mark Kozak-Holland
  • 49. March 23, 1944 - Day before, Bushell re-emphasizes objectives with "Wings" Day and determines to go ahead with escape.  “The weather’s going to be bloody awful, and will probably get worse. 90% of the hardarsers will run into deep snow in the mountains…[but it]…Doesn’t matter. It will give the Nazis an almighty shock. 200 looney escape artists roaring around the countryside.” – Conversation between Roger Bushell, and Wings Day prior to the escape. 49 Project Lessons from the Great Escape www.lessons-from-history.com © 2013 Mark Kozak-Holland
  • 50. March 24, 1944 – Day of escape  POW congregate in Hut 104  9:45 Problems in breakout  Frozen trap door  Clever improvisation to continue 50 Project Lessons from the Great Escape www.lessons-from-history.com © 2013 Mark Kozak-Holland
  • 51. In the Implementation and startup things started to go badly wrong  10:30 First out from suitcase brigade  00:00 1 hour air raid  01:30 Tunnel cave in 51 Project Lessons from the Great Escape www.lessons-from-history.com © 2013 Mark Kozak-Holland
  • 52. The passage of escapers greatly slowed  03:00 Blanket brigade begins  03:30 Word sent back, 100 could escape  Expected throughput 60/hour, actual 12/hour.  04:55 - 76 escapers were out 52 Project Lessons from the Great Escape www.lessons-from-history.com © 2013 Mark Kozak-Holland
  • 53. Breakout and escapers get away  Escaper at exit mixed up signals emerged under guard  Men in tunnel returned to Hut 104  Burned false papers ate rations 53 Project Lessons from the Great Escape www.lessons-from-history.com © 2013 Mark Kozak-Holland
  • 54. Best chance was for suitcase brigade  Station 1 mile from camp  Many escapers could not find station, missed trains.  At dawn many POWs still on the platform, ignoring each other.  Bushell awaited the 3:30am service to Breslau and arrived 5:00am. 54 Project Lessons from the Great Escape www.lessons-from-history.com © 2013 Mark Kozak-Holland
  • 55. Who got where? 76 of 250 got out. Many escapers could not find station, missed trains. 3 got to neutral country, "home run"  Norwegians (2) reach Sweden  Dutchman reaches Gibraltar via France /Spain (3.5 months).  ~50 men caught within few miles  15 men escape to free territory but got caught 55 Project Lessons from the Great Escape www.lessons-from-history.com © 2013 Mark Kozak-Holland
  • 56. Table of contents 1. Background 2. Problems 3. APM BOK 4. Solutions 5. Timeline to Escape 6. Post Mortem 56 Project Lessons from the Great Escape www.lessons-from-history.com © 2013 Mark Kozak-Holland
  • 57. Was the project a success?  Pros – Massive disruption, million men looking – Hitler outraged, diversion to war  Cons – Too few got out and away – 50 captured and executed 57 Project Lessons from the Great Escape www.lessons-from-history.com © 2013 Mark Kozak-Holland
  • 58. Lessons learned – the positives from the project  Limited material resources – Everything saved  Decentralized organization – 600 men were engaged  High performance team – Committed to cause Lessons for today – nothing is impossible  Ad hoc group used diverse talents  Extraordinarily difficult task – Adverse circumstances  Problems solved – Continuous innovation 58 Project Lessons from the Great Escape www.lessons-from-history.com © 2013 Mark Kozak-Holland
  • 59. Lessons learned downside - Airmen - Australia, Canada, France, Greece, Holland, Norway, Poland, South Africa, &UK  No rerun – Poor ROI, massive investment  Attention to implementation – Priority to greatest contributors – March best month? – Many escapers drew attention?  No withdrawal plan – Tunnel too short – No stopping – Emotions unchecked, desire to get out  Effective Project Management? 59 Lessons for today – pay attention to all phases of project Project Lessons from the Great Escape www.lessons-from-history.com © 2013 Mark Kozak-Holland
  • 60. Lessons learned – Too much focus on the tunnel and its construction  Project Objectives – Clear at outset, unclear in hindsight – Game or sport  WWII 30 of 10,000 RAF airmen reached safety.  17% of PoWs died in German camps.  Escapes more dangerous but continued. 60 Project Lessons from the Great Escape www.lessons-from-history.com © 2013 Mark Kozak-Holland
  • 61. Questions Presentation available on-line Mark available to work with you and your organization (PMs and Executives), speak or run workshops. http://www.lessons-from-history.com/ Sign up for lessons-from-history newsletter (subscribe/unsubscribe). Twitter @LessonsfromHist You tube – ProjectLessons http://ca.linked.com/in/markkozakholland Skype name - mark.kozak.holland Email: mark.kozak-holl@sympatico.ca 64 Project Lessons from the Great Escape www.lessons-from-history.com © 2013 Mark Kozak-Holland
  • 62. Lessons-from-History is a series of publications for today’s business world, established in 2001.  Our authors are from the business world but, with a deep passion for history.  The authors are highly experienced and working project managers, consultants, business analysts.  This combination of business and history provides a deeper understanding of challenges faced by today's business. John J. Byrne 65 Paul R. Bruno Michael Dobson Lessons From History Overview Ian Hughes Mark KozakHolland Glen LeClair Bob Lerner www.lessons-from-history.com Joe Luttrell Jerry Manas Ranjit Sidhu © 2013 Mark Kozak-Holland
  • 63. Get signed copies, SPECIAL DISCOUNT of 30% (business receipt, checks, credit cards).  Value proposition - 100’s of best practices, implemented save 1000’s of dollars  “This book and others by Mark Kozak-Holland are a tremendous resource for educators-the stark reality of failed projects and Mark’s detailed research, historical accuracy, and the link to the BOK, helps us to analyze and understand we are not alone in managing our complex projects today. The incredible resourcefulness and bravery of these men gives us hope on our own troubled projects.  Linda F. Desmond, PMP, Project Management Trainer/Consultant President of Mass Bay Chapter, PMI 66 Project Lessons from the Great Escape £10 Also available at http://www.mmpubs.com/books-LFH.html Or call 1-866-721-1540 www.lessons-from-history.com Please contact Mark: mark.kozak-holl@sympatico.ca www.lessons-from-history.com © 2013 Mark Kozak-Holland
  • 64. Credits and Sources  http://www.historyinfilm.com/escape/real1.htm  http://www.pbs.org/wgbh/nova/greatescape/  http://www.u-s-history.com/pages/h1778.html  http://www.b24.net/pow/stalag3.htm  http://www.afhi.org/museum/stalag/escape.html  http://www.elsham.pwp.blueyonder.co.uk/gt_esc/  http://www.au.af.mil/au/goe/eaglebios/84bios/stok84.htm  http://www.inyourpocket.com/poland/poznan/en/feature?id=4326  http://www.pegasus-one.org/pow/pSL_3  http://www.simonsays.com/content/book.cfm?sid=33&pid=508729  The Great Escape, by Paul Brickhill  The Longest Tunnel, by Alan Burgess 67 Project Lessons from the Great Escape www.lessons-from-history.com © 2013 Mark Kozak-Holland