A Compelling Iron Ore Investment Opportunity 
Corporate Presentation 
December 2014 
TSX: BKI
TSX: BKI 
Disclaimer Forward Looking Statement 
This Presentation contains ‘‘forward-looking information’’ within the meaning of applicable Canadian securities legislation. Forward-looking information is based on what management believes to be reasonable assumptions, opinions and estimates of the date such statements are made based on information available to them at that time, including those factors discussed in the section entitled ‘‘Risk Factors’’ in the Company’s annual information form for the year ended December 31, 2013 (and dated March 14, 2013) or as may be identified in the Company’s public disclosure from time to time, as filed under the Company’s profile on SEDAR at www.sedar.com. Forward-looking information may include, but is not limited to, statements with respect to results of the Feasibility Study (as defined below) and the mineral reserve and resource estimate, the future financial or operating performance of the Company, its subsidiaries and its projects, the development of and the anticipated timing with respect to the Shymanivske project, the ability to obtain financing on commercially reasonable terms; and the impact of concerns relating to permitting, regulation, governmental and local community relations, including the results of upcoming Presidential elections and Western and Russian responses to the results of said elections. Generally, forward looking information can be identified by the use of forward-looking terminology such as "plans", "expects" or "does not expect", "is expected", "budget", "scheduled", "estimates", "forecasts", "intends", "anticipates" or "does not anticipate", or "believes", or “completion of the transaction with Metinvest” or variations of such words and phrases or state that certain actions, events or results "may", "could", "would", "might" or "will be taken", "occur" or "be achieved". Estimates underlying the results of the Feasibility Study arise from engineering, geological and costing work of Lycopodium Minerals Canada Ltd. (“Lycopodium”), Soutex Inc. (“Soutex”), Watts, Griffis and McOuat Limited (“WGM”), Consulting Geologists and Engineers of Toronto, P&E Mining Consultants Inc. (“P&E”) and the Company. See the technical report relating to the feasibility study for a description of all relevant estimates, assumptions and parameters. Forward-looking information is subject to known and unknown risks, uncertainties and other factors that may cause the actual results, level of activity, performance or achievements of the Company to be materially different from those expressed or implied by such forward-looking information, including but not limited to: general business, economic, competitive, geopolitical and social uncertainties; the actual results of current exploration activities; other risks of the mining industry and the risks described in the annual information form of the Company. Although the Company has attempted to identify important factors that could cause actual results to differ materially from those contained in forward-looking information, there may be other factors that cause results not to be as anticipated, estimated or intended. There can be no assurance that such information will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward looking information. The Company does not undertake to update any forward-looking information, except in accordance with applicable securities laws. This Presentation does not constitute an offer to sell, or solicitation of an offer to buy, any securities by any person in any jurisdiction in which it is unlawful for such person to make such an offering or solicitation. No representation or warranty, express or implied, is made as to the accuracy or completeness of the information set out herein, and nothing contained herein is, or shall be relied upon, as a promise or representation, whether as to the past or future. The technical information contained herein is derived from or a summary of the NI 43-101 Compliant Technical Report entitled “Feasibility Study of the Shymanivske Iron Ore Deposit for Black Iron Inc”, dated January 24, 2014 (Prepared by Lycopodium Minerals Canada Ltd. the “Feasibility Study”) – For additional information, please see the Feasibility Study filed on www.sedar.com dated January 24, 2014. *The mineral resource estimate for the Shymanivske Project is based on results from 185 historical drill holes totaling 37,316 meters and 60 Black Iron drill holes, which were drilled during the Company’s Twin Hole drill program and the Definition Drill program, totaling 16,518 meters and is effective as of September 2012. Watts, Griffis and McOuat Limted (“WGM”), Consulting Geologists and Engineers of Toronto, Canada, was retained to audit an in-house mineral resource estimate completed by Black Iron. Mr. Michael Kociumbas, P.Geo, Vice-President of WGM and Mr. Richard Risto, P.Geo, Senior Geological Associate of WGM, were retained by Black Iron as independent technical consultants and are Qualified Persons as defined by NI 43-101 and are responsible for reviewing and approving this mineral resource estimate. The Feasibility Study was prepared in accordance with the guidelines of National Instrument 43-101 by the independent firms of Lycopodium Minerals Canada Ltd.; Soutex Mineral & Metallurgical Consultants; Watts, Griffis and McOuat Limited; and P&E Mining Consultants Inc.. *Matt Simpson, President & CEO of Black Iron, a Qualified Person as defined by NI-43-101, has reviewed and approved the scientific and technical information in this presentation. 
2
TSX: BKI 
What Sets Black Iron Apart? 
Access to Skilled Labour & Existing Infrastructure – 
Two of the Most Challenging Iron Ore Project Development Risks 
Key Development Risks 
Taxes/Royalties 
Human Resources 
Access to Infrastructure 
Community Opposition 
Licensing/Permitting 
Access to Water 
Electricity Supply 
Canada 
Brazil 
Africa 
Australia 
Ukraine 
3
TSX: BKI 
* Please see note on Page 2 
Black Iron has ALL the Key Fundamentals for a Successful Low Cost Project in Place 
Exceptional Infrastructure 
• Significant infrastructure advantages (power, rail and port) with confirmed access and capacity 
• Skilled local workforce 
• Local partnerships 
Compelling Economics 
• Bankable Feasibility Study (Shymanivske Project): - 9.9Mtpa of 68% Fe Conc. - Post-tax NPV8 of US$2.6B - Post-tax IRR of 39% 
•Break even price of $54/t (after-tax) 
Sizeable Resource 
•Large NI 43-101 Compliant Resource* at Flagship Shymanivske - 646Mt (M+I) @ 32% Fe - 188Mt (Inf) @ 30% Fe - Significant resource potential upside 
Skilled Leadership 
•History of creating value for shareholders 
•Significant Ukrainian political and iron ore operations experience 
Close to Target Markets 
• Located in Kryvyi Rih, Ukraine a major iron ore district, close to Europe, Turkey, Russia, Asia and Middle East 
Metinvest Development Agreement 
•Ukraine’s largest company, 9th globally in iron ore, 16th in steel 
•Committed to half of project construction financing (est. $250-$500M) 
4
TSX: BKI 
Board of Directors 
Key Management 
Matt Simpson – President & CEO 
•Former General Manager, Mining for Rio Tinto’s Iron Ore Company of Canada 
•Worked for Hatch designing global metallurgical refineries Les Kwasik – COO 
•Over 40 years of hands-on experience building and operating mines globally with companies such as with INCO (VALE), Xstrata Columbia delivering disciplined operational successes in the mining industry Paul Bozoki – CFO Aaron Wolfe – VP Corp Development Nikolay Bayrak – VP Gov’t & Community Relations 
•Former department head, Ukrainian Ministry of Emergencies and Public Protection; Former MP George Mover – Special Advisor 
•Former Project General Director of Ferrexpo Yeristovo Mining, Ukraine. Since 1994,worked on numerous mining projects in Former Soviet Union countries 
Bruce Humphrey – Chairman 
•Former Chief Operating Officer of Goldcorp Jaroslav Kinach 
•Former Advisor to Ukraine Prime Minister and former Ukraine Country Head of EBRD Chris Westdal 
•Canadian Ambassador to Ukraine (1996-98) and to Russia (2003-06) Pierre Pettigrew 
•Former Canadian Minister for Foreign Affairs and international Trade John Detmold 
•Chairman & Founder of Invecture Group, S.A. de C.V. which owns Frontera Copper Corporation Dave Porter 
•Former VP for Rio Tinto’s Iron Ore Company of Canada and COO of Algoma Steel Matt Simpson – President & CEO 
A Track Record of Iron Ore Success with Rio Tinto’s Iron Ore Company of Canada, and Ferrexpo 
5
TSX: BKI 
Major Local Development Partner: Metinvest Ukraine’s Largest Company and a Global Iron Ore & Steel Producer 
•Over 100,000 employees; Generated US$12.8 billion of revenues and a 18% EBITDA margin in 2013 
•Metinvest is owned by System Capital Management (SCM) and Smart Holding 
•SCM has over US$28.4B in assets and operations across 13 different areas including ownership of: 
•Global Commodity Ranking: 
•DTEK >18GW of electricity production (~26%) 
•Leman Trans, ~21% of railway cars 
•Portinvest, ~13% of Ukraine’s port capacity 
•9th in Iron Ore with 33.9 MT 
•16th in Steel with 18.4 MT 
•33rd in Coal with 2.6 MT 
6
TSX: BKI 
Sound Capital Structure Attractive Valuation with Substantial Upside & Funding Support 
Corporate Structure 
Capital Structure (TSX: BKI) 
Shares Outstanding 
161.1 million 
Stock Options(1) 
9.9 million 
Warrants(2) 
20.6 million 
Fully Diluted Shares 
191.7 million 
Market Cap(3) 
~US$8.4 million 
Current Cash Balance(4) 
~US$19.2 million 
Debt Balance 
nil 
1.9,913,750 options exercisable at a weighted average price of $0.32 per share. 
2.935,370 Warrants Expire Feb 20, 2016 (strike price: $0.25); 17.7M Warrants Expire Feb 20, 2017(strike price : $0.25); 2M Warrants Expire Aug 19, 2016(strike price: $0.20). 
3.As Dec 1, 2014, using a closing price of CAD $0.06 per share. 
4.Consolidated cash position as at Sept 30, 2014 as per Q3 Financial Statements 
Analyst Coverage 
Black Iron Inc. (TSX: BKI) 
Metinvest B.V. (Ukraine private) 
Black Iron (Cyprus) Ltd. (Cyprus private) 
Shymanivske Steel (Ukraine private) 
Zelenivske Steel (Ukraine private) 
51% 
49% 
100% 
100% 
7
TSX: BKI 
Deposits In Mining Friendly Region Adjacent to existing Iron Ore Producers 
•Two mining and exploration permits covering 5.92 km2 
−Mining permit at Shymanivske, which has been extensively explored, covering 2.56 km2 valid until 2024 
−Exploration permit at Zelenivske covering 3.36 km2 valid until 2014 
•Adjacent to ArcelorMittal’s Kryvyi Rih iron ore complex and Metinvest & Evraz’s YuGOK iron ore mine 
•Plan to acquire a plot of land from Ukraine Government adjacent to the Shymanivske deposit for project waste dumps, concentrator and tailings 
Black Iron’s Shymanivske Project* M&I: 646Mt @ 31.6% Inferred: 188Mt @ 30.1% 
Black Iron’s Zelenivske Project 
ArcelorMittal’s Kryvyi Rih Iron Ore Complex 
Metinvest & Evraz’s YuGOK Iron Ore Mine 
Railway lines 
**See Black Iron’s website at www.blackiron.com for a Corporate Video highlighting the project location and infrastructure ** 
*Please see notes on page 2 -Resources are not Reserves and do not have economic viability -Full details of the mineral reserve estimate can be found in the press release dated Jan 9, 2014 -Notes to the mineral reserves can be found on page 26 
8
TSX: BKI 
Large Ore Deposit with Growth Potential 
•Banded iron formation consisting primarily of magnetite with some hematite 
−Iron band thickness ranges from 40-80 m 
−Only 9.7-21.2 m of overburden with a strip ratio of 1.63:1, life of mine; 1.36:1 for first 8 years 
−Very clean ore body low in phosphorus, manganese and aluminum 
•Resource defined by ~54,000 metres of drilling 
―Black Iron completed a Twin Hole Drill Program consisting of 6,042 metres and a Phase II Drill Program consisting of 11,435 metres of infill drilling 
―Total iron grade and band width align very well with 37,000 metres of historical drilled data 
•Potential for resource expansion 
−Additional drilling of Shymanivske at North end of deposit and to depth 
−Exploration of the Zelenivske project 
Shymanivske 
Tonnage 
(Mt) 
Fe Tot 
(%) 
Fe Mag 
(%) 
Proven 
312.9 
31.1 
19.5 
Probable 
136.1 
31.1 
18.9 
Total Reserves* 
449.0 
31.1 
19.3 
Measured 
(incl. Proven) 
355.1 
32.0 
19.5 
Indicated 
(incl. Probable) 
290.7 
31.1 
17.9 
Total Resources* 
645.8 
31.6 
18.8 
Inferred 
188.3 
30.1 
18.4 
Tonnage and grade rounded to first decimals. Cut-off grade of 10% Fe Mag *Mineral Resources include Mineral Reserves. Please see notes on page 2 -Resources are not Reserves and do not have economic viability -Full details of the mineral reserve estimate can be found in the press release dated Jan 9, 2014 -Notes to the mineral reserves can be found on page 27 -The company has applied for an extension to the Zelenivske exploration permit that was to expire on Nov 1, 2014. The Company awaits a response from the Ministry of Ecology and Natural Resources 
9
TSX: BKI 
Potential Resource Extension at Shymanivske Ground Gravity Shows Iron Ore Mineralization at North End 
•Ground gravity and magnetic surveys show potential extension of iron ore mineralization at North end of property as circled in red 
•This area has not been included in the NI 43-101 resource as it has not yet been sufficiently drilled 
•The identified area will be a target of a future drill program to allow for a second phase process plant expansion to increase production and project value 
Potential resource upside to be drilled 
Drill hole 
Property boundary 
Very likely Iron in ground 
Likely just dirt in ground 
10
TSX: BKI 
Extensive Pit Shell Design and 3D Model Completed (Property Overview) 
11 
* Bankable Feasibility Study complete by Lycopodium Minerals Canada Ltd.
TSX: BKI 
Concentrator Footprint Compressed by Staggering HPGRs and Stacking LIMS 
12 
* Bankable Feasibility Study complete by Lycopodium Minerals Canada Ltd.
TSX: BKI 
13 
Conventional Flowsheet Producing High Quality Iron Ore Products 
Fe 
68.0% 
SiO2 
4.5% 
P 
0.02% 
S 
0.05% 
Al2O3 
0.43% 
Mn 
0.03% 
P80 
32 Îźm 
B.F. Concentrate 
Fe 
65.5% 
SiO2 
4.5% 
S 
<0.01% 
CaO/SiO2 
0.15% 
SiO2+Al2 O3 
5.1% 
CaO+MgO 
1.0% 
Compress. 
318kg/pel 
B.F. Pellets 
Fe 
69.5% 
SiO2 
1.3% 
P 
0.02% 
S 
0.05% 
Al2O3 
0.28% 
Mn 
0.03% 
P80 
32 Îźm 
D.R. Concentrate 
Fe 
67.4% 
SiO2 
2.0% 
S 
<0.01% 
CaO/SiO2 
0.34% 
SiO2+Al2 O3 
2.4% 
CaO+MgO 
1.2% 
Compress. 
283g/pel 
D.R. Pellets 
Core Product 
Value-Add Alternative Products
TSX: BKI 
Secured Infrastructure Access (Rail, Port Power) Key to a Successful Iron Ore Project 
•Letters of Intent in place for Electricity (140MW) and Natural Gas (900m3/hr @85kPa) 
•Paved roads to site, located 35km away from the major city of Kryvyi Rih which has a highly skilled work force 
•Letter of Intent in place for up to 20 million tonnes per year of rail capacity from site to Port Yuchniy 
•Black Iron’s Shymanivske Project is ~2 km from main state-owned rail line 
•Letter of Intent in place with a private operator at Port Yuzniy for 9.5 million tonnes per year +/- 15% 
•Port Yuzniy is located ~430 km away and provides access to the Black Sea and global seaborne iron ore markets 
** See Black Iron’s website at www.blackiron.com for a Corporate Video highlighting the project location and infrastructure ** 
14
TSX: BKI 
Strategic Global Location Close Proximity to Target Markets with Abundant Port and Rail Access 
•Project is surrounded by steel mills in Europe, Turkey and the Middle East 
•River barge & rail access to Western Europe. 
•Five dry bulk tonnage ports accessible using railway running beside properties 
•Approx 20% to 25% shorter transport distance to growth markets of India and China compared to North and South American producers 
•Excellent Ukrainian logistical advantages 
•Densely populated roadway infrastructure 
•468 million tonnes of cargo transported via rail 
•155 million tonnes of cargo transported via ship 
15
TSX: BKI 
Ukraine: A Mining Friendly Country in Transition 
•Member of World Trade Organization (WTO) 
•S&P Sovereign Risk rating of B 
−Commodity driven economy (agriculture, metals and energy) 
−Steel production is Ukraines largest industry 
−60% of total exports are commodity-related (majority is steel) 
−Recently held successful presidential election (5 year term); elected a new pro-democracy pro- Ukraine leader 
−Gross Domestic Product (GDP) in Ukraine averaged 0.55% from 2010 until 2014, reaching an all time high of 3.90% in the second quarter of 2010 and a record low of -2% in the first quarter of 2014 
•Signed the “Ukraine-European Union Association Agreement“ in two stages in 2014 (political portion March 21; economic portion June 27) 
−Demonstrates a strong desire by citizens and business for closer European integration 
−Expected to result in lower duties, but could drive Russian gas imports up 
•Large, highly skilled labour force (pop. 45.4 million) 
−GDP per capita only $7600/yr 
−Literacy rate >99% 
•Mining friendly jurisdiction with strong local and national support 
−ArcelorMittal and Ferrexpo plc have operated in- country for over 8 years 
•Competitive Corporate tax rate of 18% (Approximately half compared to other major iron ore producing countries) 
$5Bn Investment in Integrated Iron Mine/Steel Mill 
$3.2Bn Market Cap Iron Ore and Steel Production in Ukraine 
$1.8Bn Investment in Shale Gas Development 
Major Foreign Corporate Investors 
$10Bn Planned Investment in unconventional gas exploration and development 
$10Bn Planned Investment in exploration and development of shale gas 
16
TSX: BKI 
0% 
10% 
20% 
30% 
40% 
50% 
60% 
% of World Production and Reserves 
Production 
Reserves 
Source: Based on know production and reserves as listed in the USGS 2013 Iron Ore report 
Globally Significant Iron Ore District 4th largest iron ore producer & 2nd largest reserve base 
Global Distribution of Fe Reserves & Fe Production 
•Black Iron’s projects are located in the heart of Ukraine’s iron ore belt 
–35km from Kryvyi Rih, city of 750,000 people 
•Iron ore district trends 300 km with sedimentary rock hosted banded iron formations (Dnenpovskog complex) 
•Historically well explored resource base but substantially under-exploited due to historic Soviet policy 
•15 iron ore mines in Ukraine produced 88 million tonnes in 2012 
Kiev 
Yeristovskoye 
Poltavsky GOK 
Tsentralny 
Kryviy Rih Iron Ore Complex 
Ingulestky GOK 
Yuzhny GOK 
Kryviv Rih 
Ordzhonikize Gok 
Shymanivske 
Zelenivske 
C Gok 
YuGok 
Production 
Reserves 
7% 
20% 
17
TSX: BKI 
Permit Process for Shymanivske Deposit Black Iron Remains on Track 
Exploration Permit 
Extraction Permit 
Mining Allotment 
Construction Approval 
Operations Approval 
Deem deposit economical 
•Complete Ukraine version of scoping study including evaluation of various mining methods & high level environmental impact 
Pit shell reserves & environmental impact Gov approval 
•Complete field environmental (OVOS) & archeological studies for Gov approval 
•Submit pit shell design & mapped ground surface project for Gov. approval 
Obtain surface rights for mine, refinery & tailings 
•Land use analysis based on plot plan showing major buildings & agreed connections to utilities, rail and roads (Proekt) 
•Approval of the project location 
•Approval from all land owners & finalize lease 
Start mine overburden removal & plant construction 
•Detailed design approved (Expertisa) 
•Obtaining the construction permit 
•Commissioning of the facility 
•Registration of the ownership to the facility 
Explore resource potential 
•Conduct geophysical program 
•Drill ore body 
•State approval of explored deposit 
Operate mine & refinery 
•Ensure compliance with Ukraine Safety, Environment, Health and Employment laws as check by regular Gov inspections 
•Finalize environmental permits 
Completed 
Land Allotment 
18
TSX: BKI 
Annual Production: 
9.9 Mt 
Iron Content: 
68.0% 
Estimated Capital Investment: 
(capital intensity, includes 15% contingency) 
US$1,097 million 
US$111/t 
Estimated Operating Expenses: 
(average FOB) 
(average at Mine Gate) 
US$44.54/t 
US$29.64/t 
Long-Term CFR Benchmark Price(62%): 
US$95/t 
Net Present Value (8%): 
(pre-tax) 
(after-tax) 
US$3.3 billion 
US$2.6 billion 
Internal Rate of Return: 
(pre-tax) 
(after-tax) 
48% 
39% 
Annual Average Cash Flow: 
(pre-tax) 
(after-tax) 
US$630 million 
US$536 million 
Projected Payback (8%): 
(pre-tax) 
(after-tax) 
2.0 years 
2.5 years 
Estimated Mine Life: 
modelled reserve 
total defined resource 
14 years 
~19 years 
Projected Plant Start-Up 
Q4 2016 
Projected Revenue Commencement 
Q1 2017 
BFS Highlights – High Grade Concentrate High Value, Low Net Cost Iron Ore Development Project 
*** See Disclaimer on page 2 
* Bankable Feasibility Study completed by Lycopodium **Black Iron’s interest in Project is 51% 
19
TSX: BKI 
Black Iron’s Operating Cost Competitiveness Shymanivske: First Quartile to Local Markets; Second Quartile to China 
20 
** See Disclaimer on page 2 ** 
2013 Iron Ore Cost Curve 
World Cumulative Production (%) 
Source: Company data; Wood Mackenzie; BMO Capital Markets * Adjusted for iron content and shipping distance 
BKI delivered to Europe/Middle East Markets 
BKI delivered to China 
Spot: $70/t 
Total Cash Cost (US$/t CFR China)
TSX: BKI 
** See Disclaimer on page 2 ** 
Black Iron’s Capital Cost Advantage Shymanivske Relative to Other Iron Ore Projects 
21 
Source: Company data; Renaissance Capital estimates 
Vale (Shimandou 1) 
African Minerals (phase2) 
Xstrata (Askaf) 
African Minerals (DSO) 
ArcelorMittal (Western … 
Fortescue (Expansion) 
Black Iron 
Rio Tinto (IOC) 
Sundance 
Kumba 
Ferrexpo (Yeristovo) 
IRC (Kuranakh) 
London Mining 
IRC (K&S) 
Alderon 
Auila (Hardey) 
Xstrata (Zanaga) 
Atlas Iron (Ridley) 
Rio Tinto (Pilbara) 
Gindalbie (Karara) 
Anglo American (Minas Rio) 
BHP (RGP5&6) 
Aquila (West Pilbara) 
ArcelorMittal (Western … 
BHP (Samarco) 
Atlas Iron (Balla Balla) 
CITIC Pacific (Sino) 
Baffinland 
Xstrata (Geulb el Aouj) 
Grange Resources … 
84 
87 
90 
92 
109 
109 
111 
122 
134 
135 
141 
142 
157 
159 
159 
160 
167 
180 
186 
188 
189 
190 
192 
200 
211 
217 
221 
222 
236 
258 
CAPEX Forecast 
(US$/t of capacity) 
Average = 162 
0% 
25% 
50% 
75% 
100%
TSX: BKI 
Black Iron’s Target Capital Funding Strategy 49% of Equity Capital Solidified with Metinvest Transaction; 100% of Off-Take Still Available 
** See Disclaimer on page 2 ** 
Estimated Capital Investment US$1.1 billion 
Equity Investment 
Debt Investment 
Black Iron Inc. 
(TSX: BKI) 
Metinvest 
9.9Mtpa Off-take 
Export Credit Agencies 
Bank Debt / High-Yield Bonds 
Capital Markets 
60% 
40% 
49% 
51% 
(US$250-300 million) 
(US$0-50 million) 
(US$300-400 million) 
(US$250-350 million) 
Significant Off-take Opportunity with Equity Funding Support from Metinvest 
** % and $ amounts are indicative only and subject to negotiation ** 
(US$250-300 million) 
22
TSX: BKI 
Shymanivske Project Development Timeline* 
2011-2013 
2014 
Scoping Study/PEA 
Bankable Feasibility Study 
Off-take & Project Finance 
Construction 
Drill metallurgical holes 
Definition Drilling 
Land Acquisition 
Detailed Engineering 
Production 
Future 
* 2015 timeline contingent upon peace in Ukraine and recovered iron ore price 
** See Disclaimer on page 2 ** 
Pilot Plant Test Work 
2015 
Permitting 
Milestone Achieved 
23 
 
 
 
 
 
 
 

TSX: BKI 
Black Iron Value Proposition 
Close to Steel Mills in: W.Europe, Turkey, Russia, Asia and Middle East 
Close to Target Markets 
Large iron ore deposit with NI 43-101 compliant resource* 
•646 Mt Measured & Indicated mineral resource @ 31.6% iron; additional 188 Mt of Inferred mineral resource @ 30.1% iron, which will be concentrated to ~68% iron 
•Potential for resource expansion 
Sizable 
Resource 
Excellent access to skilled labour, power, rail & ports 
Exceptional 
Infrastructure 
Experienced management team and Board with history of creating value for shareholders of RioTinto and Ferrexpo 
Skilled Leadership 
High margins due to close proximity to multiple steel mills, skilled labour cost advantage and favourable corporate tax rate of 16% 
•Bankable Feasibility Study for 9.9Mt of high-grade 68% iron ore concentrate – NPV of US$3.3 billion and 48% IRR (US$2.6 billion and 39% after-tax) 
Compelling Economics 
*Please see notes on page 2 
-Resources are not Reserves and do not have economic viability 
-Full details of the mineral reserve estimate can be found in the press release dated Jan 9, 2014 -Notes to the mineral reserves can be found on page 26 
**The company has applied for an extension to the Zelenivske exploration permit that was to expire on Nov 1, 2014. The Company awaits a response from the Ministry of Ecology and Natural Resources 
Strategic 
Partners 
Metinvest: Largest company in Ukraine; committed to half of project equity financing 
24
TSX: BKI 
Shymanivske Project Site 
Paved Road 
High voltage power lines 
State-owned rail line 
25
Appendix
TSX: BKI 
Mineral Reserves & Resources Estimate 
1) Mineral Reserve Estimate for the Shymanivske iron ore open pit as of January 8, 2014 prepared by P&E Mining Consultants Inc. under the direction of Eugene Puritch, P.Eng. 
2) The Mineral Reserve is based on a cut-off grade of 13.0% Fe-Mag and incorporates an ore loss of 2% and dilution factor of 7.1%. 
3) The terms "mineral reserve", "probable mineral reserve" and "proven mineral reserve" have the meanings ascribed to those terms by the Canadian Institute of Mining, Metallurgy and Petroleum, as the CIM Definition Standards on Mineral Resources and Mineral Reserves adopted by CIM Council, as amended. 
4) P&E is not aware of mining, metallurgical, infrastructure, permitting, or other factors that could materially affect the mineral reserve estimates. 
27 
Tonnage and grade rounded to first decimals. Cut-off grade of 10% Fe Mag 
*Mineral Resources include Mineral Reserves. Please see notes on page 2 
-Resources are not Reserves and do not have economic viability 
-Full details of the mineral reserve estimate can be found in the press release dated Jan 9, 2014 
-The company has applied for an extension to the Zelenivske exploration permit that was to expire on Nov 1, 2014. The Company awaits a response from the Ministry of Ecology and Natural Resources 
Shymanivske 
Tonnage 
(Mt) 
Fe Tot 
(%) 
Fe Mag 
(%) 
Proven 
312.9 
31.1 
19.5 
Probable 
136.1 
31.1 
18.9 
Total Reserves* 
449.0 
31.1 
19.3 
Measured 
(incl. Proven) 
355.1 
32.0 
19.5 
Indicated 
(incl. Probable) 
290.7 
31.1 
17.9 
Total Resources* 
645.8 
31.6 
18.8 
Inferred 
188.3 
30.1 
18.4
Contact us: 
805-65 Queen Street West 
Toronto, ON, Canada, M5H 2M5 
Mike McAllister, Manager IR 
Toronto: +1(416) 309 2134 
Ukraine: +380 (56) 409 2536 
info@blackiron.com 
TSX: BKI 
Follow us: 
www.blackiron.com

More Related Content

What's hot

20140603 bki corp_pres
20140603 bki corp_pres20140603 bki corp_pres
20140603 bki corp_presblackiron
 
201505 bki corp_pres
201505 bki corp_pres201505 bki corp_pres
201505 bki corp_presblackiron
 
Corporate Presentation - June 5, 2013
Corporate Presentation - June 5, 2013Corporate Presentation - June 5, 2013
Corporate Presentation - June 5, 2013blackiron
 
Ur-Energy December 2016 Corporate Presentation
Ur-Energy December 2016 Corporate PresentationUr-Energy December 2016 Corporate Presentation
Ur-Energy December 2016 Corporate PresentationBrooke Rock
 
ATAC Resources Ltd. Corporate Presentation November 2021
ATAC Resources Ltd. Corporate Presentation November 2021ATAC Resources Ltd. Corporate Presentation November 2021
ATAC Resources Ltd. Corporate Presentation November 2021ATAC Resources Ltd
 
Belo Sun Mining - Corporate Presentation, October 2017
Belo Sun Mining - Corporate Presentation, October 2017Belo Sun Mining - Corporate Presentation, October 2017
Belo Sun Mining - Corporate Presentation, October 2017Belo Sun Mining Corp.
 
50.1 falco presentation feasibility - final - v2
50.1 falco presentation   feasibility - final - v250.1 falco presentation   feasibility - final - v2
50.1 falco presentation feasibility - final - v2FalcoCorporate
 
Lion One Metals Presentation Oct 2021
Lion One Metals Presentation Oct 2021Lion One Metals Presentation Oct 2021
Lion One Metals Presentation Oct 2021Joe Gray
 
White Gold Corp. Company Presentation
White Gold Corp. Company PresentationWhite Gold Corp. Company Presentation
White Gold Corp. Company PresentationJerryWang335042
 
Northisle Oct 2021 Overview Presentation Update
Northisle Oct 2021 Overview Presentation UpdateNorthisle Oct 2021 Overview Presentation Update
Northisle Oct 2021 Overview Presentation UpdateNicholas Van Dyk, CFA
 
12.6 2016 investor presentation
12.6 2016 investor presentation12.6 2016 investor presentation
12.6 2016 investor presentationFalcoCorporate
 
210426 silverton metals corp simplified_jun2021_v3
210426 silverton metals corp simplified_jun2021_v3210426 silverton metals corp simplified_jun2021_v3
210426 silverton metals corp simplified_jun2021_v3Adnet Communications
 
Lion One Metals Conference Exploration Presentation Sept 2021
Lion One Metals Conference Exploration Presentation Sept 2021Lion One Metals Conference Exploration Presentation Sept 2021
Lion One Metals Conference Exploration Presentation Sept 2021Joe Gray
 
202109 for corp_presentation
202109 for corp_presentation202109 for corp_presentation
202109 for corp_presentationZhalaRahim
 
January 2016 Corporate Presentation
January 2016 Corporate PresentationJanuary 2016 Corporate Presentation
January 2016 Corporate PresentationChris Donaldson
 
Corporate Presentation - May 2013
Corporate Presentation - May 2013Corporate Presentation - May 2013
Corporate Presentation - May 2013blackiron
 
Govi ex uranium corporate presentation sep2021
Govi ex uranium corporate presentation sep2021Govi ex uranium corporate presentation sep2021
Govi ex uranium corporate presentation sep2021Adnet Communications
 
Investor day presentation
Investor day presentation Investor day presentation
Investor day presentation newgold2011
 
Solaris Resources - Nov 2021
Solaris Resources - Nov 2021Solaris Resources - Nov 2021
Solaris Resources - Nov 2021JacquelineWagenaar1
 
GoviEx Corporate Presentation (October 2021)
GoviEx Corporate Presentation (October 2021)GoviEx Corporate Presentation (October 2021)
GoviEx Corporate Presentation (October 2021)Adnet Communications
 

What's hot (20)

20140603 bki corp_pres
20140603 bki corp_pres20140603 bki corp_pres
20140603 bki corp_pres
 
201505 bki corp_pres
201505 bki corp_pres201505 bki corp_pres
201505 bki corp_pres
 
Corporate Presentation - June 5, 2013
Corporate Presentation - June 5, 2013Corporate Presentation - June 5, 2013
Corporate Presentation - June 5, 2013
 
Ur-Energy December 2016 Corporate Presentation
Ur-Energy December 2016 Corporate PresentationUr-Energy December 2016 Corporate Presentation
Ur-Energy December 2016 Corporate Presentation
 
ATAC Resources Ltd. Corporate Presentation November 2021
ATAC Resources Ltd. Corporate Presentation November 2021ATAC Resources Ltd. Corporate Presentation November 2021
ATAC Resources Ltd. Corporate Presentation November 2021
 
Belo Sun Mining - Corporate Presentation, October 2017
Belo Sun Mining - Corporate Presentation, October 2017Belo Sun Mining - Corporate Presentation, October 2017
Belo Sun Mining - Corporate Presentation, October 2017
 
50.1 falco presentation feasibility - final - v2
50.1 falco presentation   feasibility - final - v250.1 falco presentation   feasibility - final - v2
50.1 falco presentation feasibility - final - v2
 
Lion One Metals Presentation Oct 2021
Lion One Metals Presentation Oct 2021Lion One Metals Presentation Oct 2021
Lion One Metals Presentation Oct 2021
 
White Gold Corp. Company Presentation
White Gold Corp. Company PresentationWhite Gold Corp. Company Presentation
White Gold Corp. Company Presentation
 
Northisle Oct 2021 Overview Presentation Update
Northisle Oct 2021 Overview Presentation UpdateNorthisle Oct 2021 Overview Presentation Update
Northisle Oct 2021 Overview Presentation Update
 
12.6 2016 investor presentation
12.6 2016 investor presentation12.6 2016 investor presentation
12.6 2016 investor presentation
 
210426 silverton metals corp simplified_jun2021_v3
210426 silverton metals corp simplified_jun2021_v3210426 silverton metals corp simplified_jun2021_v3
210426 silverton metals corp simplified_jun2021_v3
 
Lion One Metals Conference Exploration Presentation Sept 2021
Lion One Metals Conference Exploration Presentation Sept 2021Lion One Metals Conference Exploration Presentation Sept 2021
Lion One Metals Conference Exploration Presentation Sept 2021
 
202109 for corp_presentation
202109 for corp_presentation202109 for corp_presentation
202109 for corp_presentation
 
January 2016 Corporate Presentation
January 2016 Corporate PresentationJanuary 2016 Corporate Presentation
January 2016 Corporate Presentation
 
Corporate Presentation - May 2013
Corporate Presentation - May 2013Corporate Presentation - May 2013
Corporate Presentation - May 2013
 
Govi ex uranium corporate presentation sep2021
Govi ex uranium corporate presentation sep2021Govi ex uranium corporate presentation sep2021
Govi ex uranium corporate presentation sep2021
 
Investor day presentation
Investor day presentation Investor day presentation
Investor day presentation
 
Solaris Resources - Nov 2021
Solaris Resources - Nov 2021Solaris Resources - Nov 2021
Solaris Resources - Nov 2021
 
GoviEx Corporate Presentation (October 2021)
GoviEx Corporate Presentation (October 2021)GoviEx Corporate Presentation (October 2021)
GoviEx Corporate Presentation (October 2021)
 

Similar to Compelling Iron Ore Investment Opportunity

20140401 bki corp_pres
20140401 bki corp_pres20140401 bki corp_pres
20140401 bki corp_presblackiron
 
20140401 bki corp_pres
20140401 bki corp_pres20140401 bki corp_pres
20140401 bki corp_presblackiron
 
Corporate Presentation - May 8, 2013
Corporate Presentation - May 8, 2013Corporate Presentation - May 8, 2013
Corporate Presentation - May 8, 2013blackiron
 
Corporate Presentation - September 1, 2013
Corporate Presentation - September 1, 2013Corporate Presentation - September 1, 2013
Corporate Presentation - September 1, 2013blackiron
 
Corporate Presentation - September 1, 2013
Corporate Presentation - September 1, 2013Corporate Presentation - September 1, 2013
Corporate Presentation - September 1, 2013blackiron
 
Corporate Presentation - September 1, 2013
Corporate Presentation - September 1, 2013Corporate Presentation - September 1, 2013
Corporate Presentation - September 1, 2013blackiron
 
Corporate Presentation - August 7, 2013
Corporate Presentation - August 7, 2013Corporate Presentation - August 7, 2013
Corporate Presentation - August 7, 2013blackiron
 
Black Iron Corporate Presentation January 2014
Black Iron Corporate Presentation January 2014Black Iron Corporate Presentation January 2014
Black Iron Corporate Presentation January 2014blackiron
 
20140124 2 bki_corp_pres
20140124 2 bki_corp_pres20140124 2 bki_corp_pres
20140124 2 bki_corp_presblackiron
 
20140211 bki corp_pres
20140211 bki corp_pres20140211 bki corp_pres
20140211 bki corp_presblackiron
 
20140301 bki corp_pres
20140301 bki corp_pres20140301 bki corp_pres
20140301 bki corp_presblackiron
 
20140203 bki corp_pres
20140203 bki corp_pres20140203 bki corp_pres
20140203 bki corp_presblackiron
 
20140106 bki corp_pres
20140106 bki corp_pres20140106 bki corp_pres
20140106 bki corp_presblackiron
 
20140123 bki corp_pres
20140123 bki corp_pres20140123 bki corp_pres
20140123 bki corp_presblackiron
 
201705 bki corp_pres v2
201705 bki corp_pres v2201705 bki corp_pres v2
201705 bki corp_pres v2blackiron
 
Corporate Presentation - December 2013
Corporate Presentation - December 2013Corporate Presentation - December 2013
Corporate Presentation - December 2013blackiron
 
20110614 BKI Corp Presentation
20110614 BKI Corp Presentation20110614 BKI Corp Presentation
20110614 BKI Corp Presentationblackiron
 
Nan mines and money mining oct. corporate
Nan mines and money mining oct. corporateNan mines and money mining oct. corporate
Nan mines and money mining oct. corporateNorthAmericanNickel
 
Corporate Presentation
Corporate PresentationCorporate Presentation
Corporate Presentationblackiron
 
Corporate Presentation
Corporate PresentationCorporate Presentation
Corporate Presentationblackiron
 

Similar to Compelling Iron Ore Investment Opportunity (20)

20140401 bki corp_pres
20140401 bki corp_pres20140401 bki corp_pres
20140401 bki corp_pres
 
20140401 bki corp_pres
20140401 bki corp_pres20140401 bki corp_pres
20140401 bki corp_pres
 
Corporate Presentation - May 8, 2013
Corporate Presentation - May 8, 2013Corporate Presentation - May 8, 2013
Corporate Presentation - May 8, 2013
 
Corporate Presentation - September 1, 2013
Corporate Presentation - September 1, 2013Corporate Presentation - September 1, 2013
Corporate Presentation - September 1, 2013
 
Corporate Presentation - September 1, 2013
Corporate Presentation - September 1, 2013Corporate Presentation - September 1, 2013
Corporate Presentation - September 1, 2013
 
Corporate Presentation - September 1, 2013
Corporate Presentation - September 1, 2013Corporate Presentation - September 1, 2013
Corporate Presentation - September 1, 2013
 
Corporate Presentation - August 7, 2013
Corporate Presentation - August 7, 2013Corporate Presentation - August 7, 2013
Corporate Presentation - August 7, 2013
 
Black Iron Corporate Presentation January 2014
Black Iron Corporate Presentation January 2014Black Iron Corporate Presentation January 2014
Black Iron Corporate Presentation January 2014
 
20140124 2 bki_corp_pres
20140124 2 bki_corp_pres20140124 2 bki_corp_pres
20140124 2 bki_corp_pres
 
20140211 bki corp_pres
20140211 bki corp_pres20140211 bki corp_pres
20140211 bki corp_pres
 
20140301 bki corp_pres
20140301 bki corp_pres20140301 bki corp_pres
20140301 bki corp_pres
 
20140203 bki corp_pres
20140203 bki corp_pres20140203 bki corp_pres
20140203 bki corp_pres
 
20140106 bki corp_pres
20140106 bki corp_pres20140106 bki corp_pres
20140106 bki corp_pres
 
20140123 bki corp_pres
20140123 bki corp_pres20140123 bki corp_pres
20140123 bki corp_pres
 
201705 bki corp_pres v2
201705 bki corp_pres v2201705 bki corp_pres v2
201705 bki corp_pres v2
 
Corporate Presentation - December 2013
Corporate Presentation - December 2013Corporate Presentation - December 2013
Corporate Presentation - December 2013
 
20110614 BKI Corp Presentation
20110614 BKI Corp Presentation20110614 BKI Corp Presentation
20110614 BKI Corp Presentation
 
Nan mines and money mining oct. corporate
Nan mines and money mining oct. corporateNan mines and money mining oct. corporate
Nan mines and money mining oct. corporate
 
Corporate Presentation
Corporate PresentationCorporate Presentation
Corporate Presentation
 
Corporate Presentation
Corporate PresentationCorporate Presentation
Corporate Presentation
 

Recently uploaded

Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort ServiceCall US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Servicecallgirls2057
 
Innovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfInnovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfrichard876048
 
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...ictsugar
 
8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCR8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCRashishs7044
 
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptxContemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptxMarkAnthonyAurellano
 
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City GurgaonCall Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaoncallgirls2057
 
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / NcrCall Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncrdollysharma2066
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Seta Wicaksana
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCRashishs7044
 
International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...ssuserf63bd7
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCRashishs7044
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesKeppelCorporation
 
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCRashishs7044
 
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCRashishs7044
 
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607dollysharma2066
 
IoT Insurance Observatory: summary 2024
IoT Insurance Observatory:  summary 2024IoT Insurance Observatory:  summary 2024
IoT Insurance Observatory: summary 2024Matteo Carbone
 
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdfNewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdfKhaled Al Awadi
 
India Consumer 2024 Redacted Sample Report
India Consumer 2024 Redacted Sample ReportIndia Consumer 2024 Redacted Sample Report
India Consumer 2024 Redacted Sample ReportMintel Group
 
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607dollysharma2066
 
MemorĂĄndum de Entendimiento (MoU) entre Codelco y SQM
MemorĂĄndum de Entendimiento (MoU) entre Codelco y SQMMemorĂĄndum de Entendimiento (MoU) entre Codelco y SQM
MemorĂĄndum de Entendimiento (MoU) entre Codelco y SQMVoces Mineras
 

Recently uploaded (20)

Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort ServiceCall US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
 
Innovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfInnovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdf
 
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
 
8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCR8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCR
 
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptxContemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
 
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City GurgaonCall Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
 
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / NcrCall Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
 
International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation Slides
 
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
 
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
 
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
 
IoT Insurance Observatory: summary 2024
IoT Insurance Observatory:  summary 2024IoT Insurance Observatory:  summary 2024
IoT Insurance Observatory: summary 2024
 
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdfNewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
 
India Consumer 2024 Redacted Sample Report
India Consumer 2024 Redacted Sample ReportIndia Consumer 2024 Redacted Sample Report
India Consumer 2024 Redacted Sample Report
 
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
 
MemorĂĄndum de Entendimiento (MoU) entre Codelco y SQM
MemorĂĄndum de Entendimiento (MoU) entre Codelco y SQMMemorĂĄndum de Entendimiento (MoU) entre Codelco y SQM
MemorĂĄndum de Entendimiento (MoU) entre Codelco y SQM
 

Compelling Iron Ore Investment Opportunity

  • 1. A Compelling Iron Ore Investment Opportunity Corporate Presentation December 2014 TSX: BKI
  • 2. TSX: BKI Disclaimer Forward Looking Statement This Presentation contains ‘‘forward-looking information’’ within the meaning of applicable Canadian securities legislation. Forward-looking information is based on what management believes to be reasonable assumptions, opinions and estimates of the date such statements are made based on information available to them at that time, including those factors discussed in the section entitled ‘‘Risk Factors’’ in the Company’s annual information form for the year ended December 31, 2013 (and dated March 14, 2013) or as may be identified in the Company’s public disclosure from time to time, as filed under the Company’s profile on SEDAR at www.sedar.com. Forward-looking information may include, but is not limited to, statements with respect to results of the Feasibility Study (as defined below) and the mineral reserve and resource estimate, the future financial or operating performance of the Company, its subsidiaries and its projects, the development of and the anticipated timing with respect to the Shymanivske project, the ability to obtain financing on commercially reasonable terms; and the impact of concerns relating to permitting, regulation, governmental and local community relations, including the results of upcoming Presidential elections and Western and Russian responses to the results of said elections. Generally, forward looking information can be identified by the use of forward-looking terminology such as "plans", "expects" or "does not expect", "is expected", "budget", "scheduled", "estimates", "forecasts", "intends", "anticipates" or "does not anticipate", or "believes", or “completion of the transaction with Metinvest” or variations of such words and phrases or state that certain actions, events or results "may", "could", "would", "might" or "will be taken", "occur" or "be achieved". Estimates underlying the results of the Feasibility Study arise from engineering, geological and costing work of Lycopodium Minerals Canada Ltd. (“Lycopodium”), Soutex Inc. (“Soutex”), Watts, Griffis and McOuat Limited (“WGM”), Consulting Geologists and Engineers of Toronto, P&E Mining Consultants Inc. (“P&E”) and the Company. See the technical report relating to the feasibility study for a description of all relevant estimates, assumptions and parameters. Forward-looking information is subject to known and unknown risks, uncertainties and other factors that may cause the actual results, level of activity, performance or achievements of the Company to be materially different from those expressed or implied by such forward-looking information, including but not limited to: general business, economic, competitive, geopolitical and social uncertainties; the actual results of current exploration activities; other risks of the mining industry and the risks described in the annual information form of the Company. Although the Company has attempted to identify important factors that could cause actual results to differ materially from those contained in forward-looking information, there may be other factors that cause results not to be as anticipated, estimated or intended. There can be no assurance that such information will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward looking information. The Company does not undertake to update any forward-looking information, except in accordance with applicable securities laws. This Presentation does not constitute an offer to sell, or solicitation of an offer to buy, any securities by any person in any jurisdiction in which it is unlawful for such person to make such an offering or solicitation. No representation or warranty, express or implied, is made as to the accuracy or completeness of the information set out herein, and nothing contained herein is, or shall be relied upon, as a promise or representation, whether as to the past or future. The technical information contained herein is derived from or a summary of the NI 43-101 Compliant Technical Report entitled “Feasibility Study of the Shymanivske Iron Ore Deposit for Black Iron Inc”, dated January 24, 2014 (Prepared by Lycopodium Minerals Canada Ltd. the “Feasibility Study”) – For additional information, please see the Feasibility Study filed on www.sedar.com dated January 24, 2014. *The mineral resource estimate for the Shymanivske Project is based on results from 185 historical drill holes totaling 37,316 meters and 60 Black Iron drill holes, which were drilled during the Company’s Twin Hole drill program and the Definition Drill program, totaling 16,518 meters and is effective as of September 2012. Watts, Griffis and McOuat Limted (“WGM”), Consulting Geologists and Engineers of Toronto, Canada, was retained to audit an in-house mineral resource estimate completed by Black Iron. Mr. Michael Kociumbas, P.Geo, Vice-President of WGM and Mr. Richard Risto, P.Geo, Senior Geological Associate of WGM, were retained by Black Iron as independent technical consultants and are Qualified Persons as defined by NI 43-101 and are responsible for reviewing and approving this mineral resource estimate. The Feasibility Study was prepared in accordance with the guidelines of National Instrument 43-101 by the independent firms of Lycopodium Minerals Canada Ltd.; Soutex Mineral & Metallurgical Consultants; Watts, Griffis and McOuat Limited; and P&E Mining Consultants Inc.. *Matt Simpson, President & CEO of Black Iron, a Qualified Person as defined by NI-43-101, has reviewed and approved the scientific and technical information in this presentation. 2
  • 3. TSX: BKI What Sets Black Iron Apart? Access to Skilled Labour & Existing Infrastructure – Two of the Most Challenging Iron Ore Project Development Risks Key Development Risks Taxes/Royalties Human Resources Access to Infrastructure Community Opposition Licensing/Permitting Access to Water Electricity Supply Canada Brazil Africa Australia Ukraine 3
  • 4. TSX: BKI * Please see note on Page 2 Black Iron has ALL the Key Fundamentals for a Successful Low Cost Project in Place Exceptional Infrastructure • Significant infrastructure advantages (power, rail and port) with confirmed access and capacity • Skilled local workforce • Local partnerships Compelling Economics • Bankable Feasibility Study (Shymanivske Project): - 9.9Mtpa of 68% Fe Conc. - Post-tax NPV8 of US$2.6B - Post-tax IRR of 39% •Break even price of $54/t (after-tax) Sizeable Resource •Large NI 43-101 Compliant Resource* at Flagship Shymanivske - 646Mt (M+I) @ 32% Fe - 188Mt (Inf) @ 30% Fe - Significant resource potential upside Skilled Leadership •History of creating value for shareholders •Significant Ukrainian political and iron ore operations experience Close to Target Markets • Located in Kryvyi Rih, Ukraine a major iron ore district, close to Europe, Turkey, Russia, Asia and Middle East Metinvest Development Agreement •Ukraine’s largest company, 9th globally in iron ore, 16th in steel •Committed to half of project construction financing (est. $250-$500M) 4
  • 5. TSX: BKI Board of Directors Key Management Matt Simpson – President & CEO •Former General Manager, Mining for Rio Tinto’s Iron Ore Company of Canada •Worked for Hatch designing global metallurgical refineries Les Kwasik – COO •Over 40 years of hands-on experience building and operating mines globally with companies such as with INCO (VALE), Xstrata Columbia delivering disciplined operational successes in the mining industry Paul Bozoki – CFO Aaron Wolfe – VP Corp Development Nikolay Bayrak – VP Gov’t & Community Relations •Former department head, Ukrainian Ministry of Emergencies and Public Protection; Former MP George Mover – Special Advisor •Former Project General Director of Ferrexpo Yeristovo Mining, Ukraine. Since 1994,worked on numerous mining projects in Former Soviet Union countries Bruce Humphrey – Chairman •Former Chief Operating Officer of Goldcorp Jaroslav Kinach •Former Advisor to Ukraine Prime Minister and former Ukraine Country Head of EBRD Chris Westdal •Canadian Ambassador to Ukraine (1996-98) and to Russia (2003-06) Pierre Pettigrew •Former Canadian Minister for Foreign Affairs and international Trade John Detmold •Chairman & Founder of Invecture Group, S.A. de C.V. which owns Frontera Copper Corporation Dave Porter •Former VP for Rio Tinto’s Iron Ore Company of Canada and COO of Algoma Steel Matt Simpson – President & CEO A Track Record of Iron Ore Success with Rio Tinto’s Iron Ore Company of Canada, and Ferrexpo 5
  • 6. TSX: BKI Major Local Development Partner: Metinvest Ukraine’s Largest Company and a Global Iron Ore & Steel Producer •Over 100,000 employees; Generated US$12.8 billion of revenues and a 18% EBITDA margin in 2013 •Metinvest is owned by System Capital Management (SCM) and Smart Holding •SCM has over US$28.4B in assets and operations across 13 different areas including ownership of: •Global Commodity Ranking: •DTEK >18GW of electricity production (~26%) •Leman Trans, ~21% of railway cars •Portinvest, ~13% of Ukraine’s port capacity •9th in Iron Ore with 33.9 MT •16th in Steel with 18.4 MT •33rd in Coal with 2.6 MT 6
  • 7. TSX: BKI Sound Capital Structure Attractive Valuation with Substantial Upside & Funding Support Corporate Structure Capital Structure (TSX: BKI) Shares Outstanding 161.1 million Stock Options(1) 9.9 million Warrants(2) 20.6 million Fully Diluted Shares 191.7 million Market Cap(3) ~US$8.4 million Current Cash Balance(4) ~US$19.2 million Debt Balance nil 1.9,913,750 options exercisable at a weighted average price of $0.32 per share. 2.935,370 Warrants Expire Feb 20, 2016 (strike price: $0.25); 17.7M Warrants Expire Feb 20, 2017(strike price : $0.25); 2M Warrants Expire Aug 19, 2016(strike price: $0.20). 3.As Dec 1, 2014, using a closing price of CAD $0.06 per share. 4.Consolidated cash position as at Sept 30, 2014 as per Q3 Financial Statements Analyst Coverage Black Iron Inc. (TSX: BKI) Metinvest B.V. (Ukraine private) Black Iron (Cyprus) Ltd. (Cyprus private) Shymanivske Steel (Ukraine private) Zelenivske Steel (Ukraine private) 51% 49% 100% 100% 7
  • 8. TSX: BKI Deposits In Mining Friendly Region Adjacent to existing Iron Ore Producers •Two mining and exploration permits covering 5.92 km2 −Mining permit at Shymanivske, which has been extensively explored, covering 2.56 km2 valid until 2024 −Exploration permit at Zelenivske covering 3.36 km2 valid until 2014 •Adjacent to ArcelorMittal’s Kryvyi Rih iron ore complex and Metinvest & Evraz’s YuGOK iron ore mine •Plan to acquire a plot of land from Ukraine Government adjacent to the Shymanivske deposit for project waste dumps, concentrator and tailings Black Iron’s Shymanivske Project* M&I: 646Mt @ 31.6% Inferred: 188Mt @ 30.1% Black Iron’s Zelenivske Project ArcelorMittal’s Kryvyi Rih Iron Ore Complex Metinvest & Evraz’s YuGOK Iron Ore Mine Railway lines **See Black Iron’s website at www.blackiron.com for a Corporate Video highlighting the project location and infrastructure ** *Please see notes on page 2 -Resources are not Reserves and do not have economic viability -Full details of the mineral reserve estimate can be found in the press release dated Jan 9, 2014 -Notes to the mineral reserves can be found on page 26 8
  • 9. TSX: BKI Large Ore Deposit with Growth Potential •Banded iron formation consisting primarily of magnetite with some hematite −Iron band thickness ranges from 40-80 m −Only 9.7-21.2 m of overburden with a strip ratio of 1.63:1, life of mine; 1.36:1 for first 8 years −Very clean ore body low in phosphorus, manganese and aluminum •Resource defined by ~54,000 metres of drilling ―Black Iron completed a Twin Hole Drill Program consisting of 6,042 metres and a Phase II Drill Program consisting of 11,435 metres of infill drilling ―Total iron grade and band width align very well with 37,000 metres of historical drilled data •Potential for resource expansion −Additional drilling of Shymanivske at North end of deposit and to depth −Exploration of the Zelenivske project Shymanivske Tonnage (Mt) Fe Tot (%) Fe Mag (%) Proven 312.9 31.1 19.5 Probable 136.1 31.1 18.9 Total Reserves* 449.0 31.1 19.3 Measured (incl. Proven) 355.1 32.0 19.5 Indicated (incl. Probable) 290.7 31.1 17.9 Total Resources* 645.8 31.6 18.8 Inferred 188.3 30.1 18.4 Tonnage and grade rounded to first decimals. Cut-off grade of 10% Fe Mag *Mineral Resources include Mineral Reserves. Please see notes on page 2 -Resources are not Reserves and do not have economic viability -Full details of the mineral reserve estimate can be found in the press release dated Jan 9, 2014 -Notes to the mineral reserves can be found on page 27 -The company has applied for an extension to the Zelenivske exploration permit that was to expire on Nov 1, 2014. The Company awaits a response from the Ministry of Ecology and Natural Resources 9
  • 10. TSX: BKI Potential Resource Extension at Shymanivske Ground Gravity Shows Iron Ore Mineralization at North End •Ground gravity and magnetic surveys show potential extension of iron ore mineralization at North end of property as circled in red •This area has not been included in the NI 43-101 resource as it has not yet been sufficiently drilled •The identified area will be a target of a future drill program to allow for a second phase process plant expansion to increase production and project value Potential resource upside to be drilled Drill hole Property boundary Very likely Iron in ground Likely just dirt in ground 10
  • 11. TSX: BKI Extensive Pit Shell Design and 3D Model Completed (Property Overview) 11 * Bankable Feasibility Study complete by Lycopodium Minerals Canada Ltd.
  • 12. TSX: BKI Concentrator Footprint Compressed by Staggering HPGRs and Stacking LIMS 12 * Bankable Feasibility Study complete by Lycopodium Minerals Canada Ltd.
  • 13. TSX: BKI 13 Conventional Flowsheet Producing High Quality Iron Ore Products Fe 68.0% SiO2 4.5% P 0.02% S 0.05% Al2O3 0.43% Mn 0.03% P80 32 Îźm B.F. Concentrate Fe 65.5% SiO2 4.5% S <0.01% CaO/SiO2 0.15% SiO2+Al2 O3 5.1% CaO+MgO 1.0% Compress. 318kg/pel B.F. Pellets Fe 69.5% SiO2 1.3% P 0.02% S 0.05% Al2O3 0.28% Mn 0.03% P80 32 Îźm D.R. Concentrate Fe 67.4% SiO2 2.0% S <0.01% CaO/SiO2 0.34% SiO2+Al2 O3 2.4% CaO+MgO 1.2% Compress. 283g/pel D.R. Pellets Core Product Value-Add Alternative Products
  • 14. TSX: BKI Secured Infrastructure Access (Rail, Port Power) Key to a Successful Iron Ore Project •Letters of Intent in place for Electricity (140MW) and Natural Gas (900m3/hr @85kPa) •Paved roads to site, located 35km away from the major city of Kryvyi Rih which has a highly skilled work force •Letter of Intent in place for up to 20 million tonnes per year of rail capacity from site to Port Yuchniy •Black Iron’s Shymanivske Project is ~2 km from main state-owned rail line •Letter of Intent in place with a private operator at Port Yuzniy for 9.5 million tonnes per year +/- 15% •Port Yuzniy is located ~430 km away and provides access to the Black Sea and global seaborne iron ore markets ** See Black Iron’s website at www.blackiron.com for a Corporate Video highlighting the project location and infrastructure ** 14
  • 15. TSX: BKI Strategic Global Location Close Proximity to Target Markets with Abundant Port and Rail Access •Project is surrounded by steel mills in Europe, Turkey and the Middle East •River barge & rail access to Western Europe. •Five dry bulk tonnage ports accessible using railway running beside properties •Approx 20% to 25% shorter transport distance to growth markets of India and China compared to North and South American producers •Excellent Ukrainian logistical advantages •Densely populated roadway infrastructure •468 million tonnes of cargo transported via rail •155 million tonnes of cargo transported via ship 15
  • 16. TSX: BKI Ukraine: A Mining Friendly Country in Transition •Member of World Trade Organization (WTO) •S&P Sovereign Risk rating of B −Commodity driven economy (agriculture, metals and energy) −Steel production is Ukraines largest industry −60% of total exports are commodity-related (majority is steel) −Recently held successful presidential election (5 year term); elected a new pro-democracy pro- Ukraine leader −Gross Domestic Product (GDP) in Ukraine averaged 0.55% from 2010 until 2014, reaching an all time high of 3.90% in the second quarter of 2010 and a record low of -2% in the first quarter of 2014 •Signed the “Ukraine-European Union Association Agreement“ in two stages in 2014 (political portion March 21; economic portion June 27) −Demonstrates a strong desire by citizens and business for closer European integration −Expected to result in lower duties, but could drive Russian gas imports up •Large, highly skilled labour force (pop. 45.4 million) −GDP per capita only $7600/yr −Literacy rate >99% •Mining friendly jurisdiction with strong local and national support −ArcelorMittal and Ferrexpo plc have operated in- country for over 8 years •Competitive Corporate tax rate of 18% (Approximately half compared to other major iron ore producing countries) $5Bn Investment in Integrated Iron Mine/Steel Mill $3.2Bn Market Cap Iron Ore and Steel Production in Ukraine $1.8Bn Investment in Shale Gas Development Major Foreign Corporate Investors $10Bn Planned Investment in unconventional gas exploration and development $10Bn Planned Investment in exploration and development of shale gas 16
  • 17. TSX: BKI 0% 10% 20% 30% 40% 50% 60% % of World Production and Reserves Production Reserves Source: Based on know production and reserves as listed in the USGS 2013 Iron Ore report Globally Significant Iron Ore District 4th largest iron ore producer & 2nd largest reserve base Global Distribution of Fe Reserves & Fe Production •Black Iron’s projects are located in the heart of Ukraine’s iron ore belt –35km from Kryvyi Rih, city of 750,000 people •Iron ore district trends 300 km with sedimentary rock hosted banded iron formations (Dnenpovskog complex) •Historically well explored resource base but substantially under-exploited due to historic Soviet policy •15 iron ore mines in Ukraine produced 88 million tonnes in 2012 Kiev Yeristovskoye Poltavsky GOK Tsentralny Kryviy Rih Iron Ore Complex Ingulestky GOK Yuzhny GOK Kryviv Rih Ordzhonikize Gok Shymanivske Zelenivske C Gok YuGok Production Reserves 7% 20% 17
  • 18. TSX: BKI Permit Process for Shymanivske Deposit Black Iron Remains on Track Exploration Permit Extraction Permit Mining Allotment Construction Approval Operations Approval Deem deposit economical •Complete Ukraine version of scoping study including evaluation of various mining methods & high level environmental impact Pit shell reserves & environmental impact Gov approval •Complete field environmental (OVOS) & archeological studies for Gov approval •Submit pit shell design & mapped ground surface project for Gov. approval Obtain surface rights for mine, refinery & tailings •Land use analysis based on plot plan showing major buildings & agreed connections to utilities, rail and roads (Proekt) •Approval of the project location •Approval from all land owners & finalize lease Start mine overburden removal & plant construction •Detailed design approved (Expertisa) •Obtaining the construction permit •Commissioning of the facility •Registration of the ownership to the facility Explore resource potential •Conduct geophysical program •Drill ore body •State approval of explored deposit Operate mine & refinery •Ensure compliance with Ukraine Safety, Environment, Health and Employment laws as check by regular Gov inspections •Finalize environmental permits Completed Land Allotment 18
  • 19. TSX: BKI Annual Production: 9.9 Mt Iron Content: 68.0% Estimated Capital Investment: (capital intensity, includes 15% contingency) US$1,097 million US$111/t Estimated Operating Expenses: (average FOB) (average at Mine Gate) US$44.54/t US$29.64/t Long-Term CFR Benchmark Price(62%): US$95/t Net Present Value (8%): (pre-tax) (after-tax) US$3.3 billion US$2.6 billion Internal Rate of Return: (pre-tax) (after-tax) 48% 39% Annual Average Cash Flow: (pre-tax) (after-tax) US$630 million US$536 million Projected Payback (8%): (pre-tax) (after-tax) 2.0 years 2.5 years Estimated Mine Life: modelled reserve total defined resource 14 years ~19 years Projected Plant Start-Up Q4 2016 Projected Revenue Commencement Q1 2017 BFS Highlights – High Grade Concentrate High Value, Low Net Cost Iron Ore Development Project *** See Disclaimer on page 2 * Bankable Feasibility Study completed by Lycopodium **Black Iron’s interest in Project is 51% 19
  • 20. TSX: BKI Black Iron’s Operating Cost Competitiveness Shymanivske: First Quartile to Local Markets; Second Quartile to China 20 ** See Disclaimer on page 2 ** 2013 Iron Ore Cost Curve World Cumulative Production (%) Source: Company data; Wood Mackenzie; BMO Capital Markets * Adjusted for iron content and shipping distance BKI delivered to Europe/Middle East Markets BKI delivered to China Spot: $70/t Total Cash Cost (US$/t CFR China)
  • 21. TSX: BKI ** See Disclaimer on page 2 ** Black Iron’s Capital Cost Advantage Shymanivske Relative to Other Iron Ore Projects 21 Source: Company data; Renaissance Capital estimates Vale (Shimandou 1) African Minerals (phase2) Xstrata (Askaf) African Minerals (DSO) ArcelorMittal (Western … Fortescue (Expansion) Black Iron Rio Tinto (IOC) Sundance Kumba Ferrexpo (Yeristovo) IRC (Kuranakh) London Mining IRC (K&S) Alderon Auila (Hardey) Xstrata (Zanaga) Atlas Iron (Ridley) Rio Tinto (Pilbara) Gindalbie (Karara) Anglo American (Minas Rio) BHP (RGP5&6) Aquila (West Pilbara) ArcelorMittal (Western … BHP (Samarco) Atlas Iron (Balla Balla) CITIC Pacific (Sino) Baffinland Xstrata (Geulb el Aouj) Grange Resources … 84 87 90 92 109 109 111 122 134 135 141 142 157 159 159 160 167 180 186 188 189 190 192 200 211 217 221 222 236 258 CAPEX Forecast (US$/t of capacity) Average = 162 0% 25% 50% 75% 100%
  • 22. TSX: BKI Black Iron’s Target Capital Funding Strategy 49% of Equity Capital Solidified with Metinvest Transaction; 100% of Off-Take Still Available ** See Disclaimer on page 2 ** Estimated Capital Investment US$1.1 billion Equity Investment Debt Investment Black Iron Inc. (TSX: BKI) Metinvest 9.9Mtpa Off-take Export Credit Agencies Bank Debt / High-Yield Bonds Capital Markets 60% 40% 49% 51% (US$250-300 million) (US$0-50 million) (US$300-400 million) (US$250-350 million) Significant Off-take Opportunity with Equity Funding Support from Metinvest ** % and $ amounts are indicative only and subject to negotiation ** (US$250-300 million) 22
  • 23. TSX: BKI Shymanivske Project Development Timeline* 2011-2013 2014 Scoping Study/PEA Bankable Feasibility Study Off-take & Project Finance Construction Drill metallurgical holes Definition Drilling Land Acquisition Detailed Engineering Production Future * 2015 timeline contingent upon peace in Ukraine and recovered iron ore price ** See Disclaimer on page 2 ** Pilot Plant Test Work 2015 Permitting Milestone Achieved 23        
  • 24. TSX: BKI Black Iron Value Proposition Close to Steel Mills in: W.Europe, Turkey, Russia, Asia and Middle East Close to Target Markets Large iron ore deposit with NI 43-101 compliant resource* •646 Mt Measured & Indicated mineral resource @ 31.6% iron; additional 188 Mt of Inferred mineral resource @ 30.1% iron, which will be concentrated to ~68% iron •Potential for resource expansion Sizable Resource Excellent access to skilled labour, power, rail & ports Exceptional Infrastructure Experienced management team and Board with history of creating value for shareholders of RioTinto and Ferrexpo Skilled Leadership High margins due to close proximity to multiple steel mills, skilled labour cost advantage and favourable corporate tax rate of 16% •Bankable Feasibility Study for 9.9Mt of high-grade 68% iron ore concentrate – NPV of US$3.3 billion and 48% IRR (US$2.6 billion and 39% after-tax) Compelling Economics *Please see notes on page 2 -Resources are not Reserves and do not have economic viability -Full details of the mineral reserve estimate can be found in the press release dated Jan 9, 2014 -Notes to the mineral reserves can be found on page 26 **The company has applied for an extension to the Zelenivske exploration permit that was to expire on Nov 1, 2014. The Company awaits a response from the Ministry of Ecology and Natural Resources Strategic Partners Metinvest: Largest company in Ukraine; committed to half of project equity financing 24
  • 25. TSX: BKI Shymanivske Project Site Paved Road High voltage power lines State-owned rail line 25
  • 27. TSX: BKI Mineral Reserves & Resources Estimate 1) Mineral Reserve Estimate for the Shymanivske iron ore open pit as of January 8, 2014 prepared by P&E Mining Consultants Inc. under the direction of Eugene Puritch, P.Eng. 2) The Mineral Reserve is based on a cut-off grade of 13.0% Fe-Mag and incorporates an ore loss of 2% and dilution factor of 7.1%. 3) The terms "mineral reserve", "probable mineral reserve" and "proven mineral reserve" have the meanings ascribed to those terms by the Canadian Institute of Mining, Metallurgy and Petroleum, as the CIM Definition Standards on Mineral Resources and Mineral Reserves adopted by CIM Council, as amended. 4) P&E is not aware of mining, metallurgical, infrastructure, permitting, or other factors that could materially affect the mineral reserve estimates. 27 Tonnage and grade rounded to first decimals. Cut-off grade of 10% Fe Mag *Mineral Resources include Mineral Reserves. Please see notes on page 2 -Resources are not Reserves and do not have economic viability -Full details of the mineral reserve estimate can be found in the press release dated Jan 9, 2014 -The company has applied for an extension to the Zelenivske exploration permit that was to expire on Nov 1, 2014. The Company awaits a response from the Ministry of Ecology and Natural Resources Shymanivske Tonnage (Mt) Fe Tot (%) Fe Mag (%) Proven 312.9 31.1 19.5 Probable 136.1 31.1 18.9 Total Reserves* 449.0 31.1 19.3 Measured (incl. Proven) 355.1 32.0 19.5 Indicated (incl. Probable) 290.7 31.1 17.9 Total Resources* 645.8 31.6 18.8 Inferred 188.3 30.1 18.4