1. Project Management –
Application (3)
8/8/2017 1Arch. Dania Abdel-Aziz/ Lecture 8
University of Jordan
Year 2016/2017
Second Summer Semester
Arch. Dania Abdel-Aziz
2. We are going to discus Project management under those main three
headlines:
1. Description.
2. Application.
3. Implementation Procedure.
8/8/2017 Arch. Dania Abdel-Aziz/ Lecture 8 2
5. TIME FRAME FOR IMPLEMENTATION
8/8/2017 Arch. Dania Abdel-Aziz/ Lecture 8 5
6. Time frame for implementation
• As mentioned before a project may
require less than 100 or more over
to 10,000,000 hours.
8/8/2017 Arch. Dania Abdel-Aziz/ Lecture 8 6
An example of a representative
construction project, implementation time
7. Time framework implementation processes
Time framework implementation include the follow processes:
1. Activity Definition.
2. Activity Sequencing.
3. Activity Duration Estimating.
4. Schedule Development.
5. Schedule Control
8/8/2017 Arch. Dania Abdel-Aziz/ Lecture 8 7
8. 1. Activity Definition
Identifying the specific activities that must be performed to
produce the various project deliverables.
8/8/2017 Arch. Dania Abdel-Aziz/ Lecture 8 8
Time framework implementation processes
2. Activity Sequencing
Identifying and documenting interactivity dependencies.
9. 3. Activity Duration Estimating
Estimating the number of work periods which will be needed to complete
individual activities.
8/8/2017 Arch. Dania Abdel-Aziz/ Lecture 8 9
Time framework implementation processes
4. Schedule Development
Analyzing activity sequences, activity durations, and Resource requirements
to create the project schedule.
5. Schedule Control
Controlling changes to the project schedule.
10. 1. Activity Definition
Identifying the specific activities that must be performed to
produce the various project deliverables.
8/8/2017 Arch. Dania Abdel-Aziz/ Lecture 8 10
Time framework implementation processes
12. Example
8/8/2017 Arch. Dania Abdel-Aziz/ Lecture 8 12
Suppose that we wish to develop a plan for a road construction project
including two culverts.
ScopeStatement
1. Activity Definition
Scope statement.
13. 8/8/2017 Arch. Dania Abdel-Aziz/ Lecture 8 13
Is this road construction project a development for existing road?
1. Activity Definition
Scope statement.
14. 8/8/2017 Arch. Dania Abdel-Aziz/ Lecture 8 14
1. Activity Definition
Is this road construction project a development for existing road?
Scope statement.
15. • Site view of Roads.
• Road length
• Destination
• Road width
• Road type
8/8/2017 Arch. Dania Abdel-Aziz/ Lecture 8 15
Scope statement.
1. Activity Definition
16. Conduct a study including :
1.1 TYPES OF ROADS
1.2 STATUS OF MAIN HIGHWAYS
1.3 NATIONAL HIGHWAY DEVELOPMENT PROJECT
1.4 ROAD CONSTRUCTION
1.5 CONSTRUCTION MATERIAL
1.6 ROAD CONSTRUCTION EQUIPMENT
1.7 MATERIAL FOR ROAD PAVEMENT
Example:
Types Of Roads:
1.1.1. Generally private roads: Driveway
1.1.2. Lower capacity highways
1.1.3. Higher capacity highways, sometimes with medians
1.1.4. Limited access grade-separated highways
8/8/2017 Arch. Dania Abdel-Aziz/ Lecture 8 16
Historical information.
1. Activity Definition
17. Develop WBS
Developing a WBS begins by:
Defining and developing lists of all activities needed to accomplish the
work of the project
Activities:
Work performed on the project that consumes project resources.
Including cost and time.
8/8/2017 Arch. Dania Abdel-Aziz/ Lecture 8 17
1. Activity Definition
Work breakdown structure.
18. Develop WBS
The first draft of the WBS includes activities at the
highest level of the hierarchy or the
management level and typically includes the
major activities or summary activities required
to accomplish the deliverables identified in the
project scope of work.
8/8/2017 Arch. Dania Abdel-Aziz/ Lecture 8 18
Top-Level Activities in Move Planning
1. Activity Definition
1. Structures
2. General
3. Roadway
Work breakdown structure.
19. Decomposition
8/8/2017 Arch. Dania Abdel-Aziz/ Lecture 8 19
The work breakdown structure is then decomposed—broken down into
smaller units. The 1.1, 1.2, and 1.3 numbers are the first subdivision of the
work.
1. Activity Definition
Decomposition
20. Decomposition
8/8/2017 Arch. Dania Abdel-Aziz/ Lecture 8 20
The work breakdown structure is then decomposed—broken down into
smaller units. The 1.1, 1.2, and 1.3 numbers are the first subdivision of the
work.
1. Activity Definition
1. Structures
1.1. Structural Excavations
1.2. Concrete
1.3. Reinforcing
2. General
2.1. Move in
2.2. Supervise
2.3. Clean up
3. Roadway
3.1. Earthwork
3.2. Paving
Decomposition
21. Decomposition
8/8/2017 Arch. Dania Abdel-Aziz/ Lecture 8 21
Major Activity Decomposed into Smaller Activities
1. Activity Definition
Decomposition
22. Estimation of Duration
8/8/2017 Arch. Dania Abdel-Aziz/ Lecture 8 22
After the project team has created the WBS, each activity is reviewed and
evaluated to determine:
1. The duration:(how long it will take to accomplish from beginning to
end).
2. What resources (time, materials, facilities, and equipment) are needed.
An estimate is an educated guess based on knowledge,
experience, and inference—the process of deriving
conclusions based on assumptions
1. Activity Definition
Assumptions.
23. Good to know
The unit of time used to develop the activity duration is a function of the
level of detail needed by the user of the schedule. The larger and more
complex the project, the greater the need for detail, which usually
translates into shorter durations for activities.
8/8/2017 Arch. Dania Abdel-Aziz/ Lecture 8 23
Need for Greater
Detail
1. Activity Definition
Days
Hours
Months
Weeks
24. Milestone
A milestone has no duration
or resources. It is simply
an indicator of an
important point in the
project.
8/8/2017 Arch. Dania Abdel-Aziz/ Lecture 8 24
1. Activity Definition
Work Breakdown Structure (WBS) Milestones
Activity ID Activity Description
Advertise Date (Start Milestone)
Bid Date (Start Milestone)
Award Date (Start Milestone)
Start Design Work (Design/Build only) (Start Milestone)
Complete Design Work (Design/Build only) (Finish
Milestone)
Construction Start Date (Start Milestone)
Stage_ Complete (Finish Milestone)
Substantial Completion (Finish Milestone)
Completion (Finish Milestone)
25. Resource Allocation and Calendars
A common resource constraint is availability. To consider the availability of:
• Team members.
• Consultants.
• key pieces of equipment.
You can create a resource calendar for each that indicates which days are
available and which are days off for a group, an individual, or a project
asset such as a piece of important equipment.
8/8/2017 Arch. Dania Abdel-Aziz/ Lecture 8 25
1. Activity Definition
26. A calendar for team members:
1. From the same company could be the company calendar that shows
working days, weekend days, and holidays.
2. Individual team members can have individual calendars that show their
vacation days or other days off, such as parental leave days.
8/8/2017 Arch. Dania Abdel-Aziz/ Lecture 8 26
1. Activity Definition
Calendar
27. 8/8/2017 Arch. Dania Abdel-Aziz/ Lecture 8 27
Nonworking days can be designated in a calendar.
1. Activity Definition
28. 8/8/2017 Arch. Dania Abdel-Aziz/ Lecture 8 28
1. Activity Definition
If major pieces of equipment are only available for certain periods of time, they can
be given a resource calendar.
Resource calendars become important tools
when changes must be made to the schedule.
29. You can create your own team calendar through this link:
• Go to www.teamup.com
8/8/2017 Arch. Dania Abdel-Aziz/ Lecture 8 29
1. Activity Definition
37. Project Logic
• The project logic is the development of the activity sequence or
determining the order in which the activities will be completed.
• The process for developing the project logic involves identifying the:
1. Predecessors—activities that come before.
2. Successors—the activities that come after.
8/8/2017 Arch. Dania Abdel-Aziz/ Lecture 8 37
Dependencies
2. Activity Sequencing
Dependencies
38. Example : Precedence Definition for Site Preparation and
Foundation Work
Suppose that a site preparation and concrete slab foundation construction
project consists of nine different activities:
A. Site clearing (of brush and minor debris).
B. Removal of trees.
C. General excavation.
D. Grading general area.
E. Excavation for utility trenches.
F. Placing formwork and reinforcement for concrete.
G. Installing sewer lines.
H. Installing other utilities.
I. Pouring concrete.
8/8/2017 Arch. Dania Abdel-Aziz/ Lecture 8 38
2. Activity Sequencing
39. Bare in Mind!
Lag and Lead Times
• Most activities in a network diagram have a finish-start relationship. If a
certain amount of time must go by before a successor activity can begin,
the required delay is called lag time.
• For example, concrete does not reach its full strength for several days
after it is poured. Lag time is required between the end of the pouring
process and the beginning of construction that puts stress on the
concrete.
8/8/2017 Arch. Dania Abdel-Aziz/ Lecture 8 39
2. Activity Sequencing
40. • In some cases, the successor activity can overlap the end of its
predecessor activity and begin before the predecessor is finished. This is
called lead time.
8/8/2017 Arch. Dania Abdel-Aziz/ Lecture 8 40
2. Activity Sequencing
41. The characteristics and identifiers of an activity are its attributes.
Each activity has an identifying code, a short description, predecessors,
and lead or lag times, as shown in a partial table of activities in "Table
of Attributes".
8/8/2017 Arch. Dania Abdel-Aziz/ Lecture 8 41
"Table of Attributes
2. Activity Sequencing
44. Graphic Representations
Bar Charts
• The type of bar chart used to illustrate activity relationships in a project is
the Gantt chart.
8/8/2017 Arch. Dania Abdel-Aziz/ Lecture 8 44
2. Activity Sequencing
47. A straightforward approach to the estimation of activity durations is to keep
historical records of particular activities and rely on the average durations
from this experience in making new duration estimates.
• Since the scope of activities are unlikely to be identical between different
projects, unit productivity rates are typically employed for this purpose.
For example, the duration of an activity Dij such as concrete formwork
assembly might be estimated as:
8/8/2017 Arch. Dania Abdel-Aziz/ Lecture 8 47
where Aij is the required formwork area to assemble (in square meters), Pij is
the average productivity of a standard crew in this task (measured in square
meters per hour), and Nij is the number of crews assigned to the task.
3. Activity Duration Estimating
48. 8/8/2017 Arch. Dania Abdel-Aziz/ Lecture 8 48
Maximum Productivity Estimates for Masonry Work
Some possible maximum productivity values that might be employed in this
estimation
3. Activity Duration Estimating
Masonry unit size Condition(s) Maximum productivity achievable
12 inch Labor is nonunion 300 units/day/mason
4 inch Weather is "warm and dry"
or high-strength mortar is used
480 units/day/mason
4 inch Weather is "warm and dry"
or high-strength mortar is used
430 units/day/mason
4 inch Weather is not "warm and dry"
or high-strength mortar is not used
370 units/day/mason
4 inch Weather is not "warm and dry"
or high-strength mortar is not used
320 units/day/mason
49. • At the next higher level, adjustments to these maximum productivities are
made to account for special site conditions and crew compositions.
8/8/2017 Arch. Dania Abdel-Aziz/ Lecture 8 49
Impact Condition(s)
Adjustment magnitude
(% of maximum)
Elevation Solid masonry building with
work on exterior uses
nonunion labor
12%
Temperature Temperature is below 45o F 15%
Temperature Temperature is above 45o F 10%
Brick texture bricks are baked high
Weather is cold or moist
10%
3. Activity Duration Estimating
50. In making adjustments for the resources required by a particular activity.
• In particular, resources such as labor requirements will vary in proportion
to the work productivity, Pij, used to estimate activity durations in
Equation.
• Mathematically, a typical estimating equation would be:
8/8/2017 Arch. Dania Abdel-Aziz/ Lecture 8 50
where Rk
ij are the resources of type k required by activity ij, Dij is the duration of
activity ij, Nij is the number of standard crews allocated to activity ij, and Uk
ij is the
amount of resource type k used per standard crew
3. Activity Duration Estimating
52. Production Rates For Roadway Items
8/8/2017 Arch. Dania Abdel-Aziz/ Lecture 8 52
Note:
Production Rates are based on 8-hour working day
per crew
LF = Linear foot, CY= Cubic Yard, SY= square yard
4. Schedule Development
55. 8/8/2017 Arch. Dania Abdel-Aziz/ Lecture 8 55
Number of Days Lost per Month for Weather Sensitive Activities (Contract Time
Determination only)
5. Schedule Control
56. Group Hard Copy Electronic Group Hard Copy
Electronic
Group Hard Copy
Electronic
Project Manager X X
Construction Management X X
Quality Management Services X
Traffic Engineering X
Structural Design & Geotechnical Engineering
Copies are available upon
request
from the PM
Geometric Design – Pavements
Landscape
Utilities
Right of Way
8/8/2017 Arch. Dania Abdel-Aziz/ Lecture 8 56
5. Schedule Control
Final Submission
Construction progress schedules are prepared and submitted by the Designer with the
final design submission. Distribution of the construction progress schedules is as
follows:
57. Conditions for implementation
In order to implement project management technique in any organization,
the companies have, first, to adopt the project management philosophy
and understand its tremendous benefits and profits that can be obtained.
The main conditions can be focused in:
• Sufficient cost allocation (cash flow).
• Sufficient infrastructure (existing or new required).
• Project manager appointment.
• Staff acquisition and team development.
8/8/2017 Arch. Dania Abdel-Aziz/ Lecture 8 57