SlideShare a Scribd company logo
1 of 47
Topics Covered

 Competitors to NPV
 The Payback Period

 The Book Rate of Return

 Internal Rate of Return

ALSO Consider
 Capital Rationing
Payback
   The payback period of a project is the number
    of years it takes before the cumulative
    forecasted cash flow equals the initial outlay.
   The payback rule says only accept projects
    that “payback” in the desired time frame.
   This method is very flawed, primarily because
    it ignores later year cash flows and the the
    present value of future cash flows.
Payback
Example
  Examine the three projects and note the mistake we
  would make if we insisted on only taking projects
  with a payback period of 2 years or less.
                                      Payback
 Project    C0      C1    C2    C3              NPV@ 10%
                                      Period
   A       - 2000   500    500 5000
   B       - 2000   500   1800   0
   C       - 2000 1800    500   0
Payback
Example
  Examine the three projects and note the mistake we
  would make if we insisted on only taking projects
  with a payback period of 2 years or less.
                                     Payback
 Project    C0      C1    C2    C3             NPV@ 10%
                                    Period
   A       - 2000   500    500 5000     3       + 2,624
   B       - 2000   500   1800   0      2         - 58
   C       - 2000 1800    500    0      2        + 50
Book Rate of Return
Book Rate of Return - Average income divided by
  average book value over project life. Also called
  accounting rate of return.

                            book income
      Book rate of return =
                             book assets
The book rate of return
   It does recognise that capital is required to
    earn income.
   However it has shortcomings as an
    investment appraisal method
       It does not have a hurdle rate
       It does not recognise the time value of money
       Ambiguity regarding its definition.
The Internal Rate of Return
   Like the NPV this is a discounted cash flow
    criterion. In the single period case where we
    are merely interested in accepting or rejecting
    a project it is exactly equivalent to the NPV
    rule. However in all other situations
    congruence of the IRR and NPV rules cannot
    be guaranteed. When a conflict does occur
    the NPV gives the correct answers.
Definition of IRR
   The IRR is the discount rate that when used to
    discount a projects cash flow gives an NPV of
    zero.
IRR in Single Period Case


    C1
       − 1 = IRR = ρ
    C0
Proof
                  C1
   NPV = - C 0 +
                 1+ i
        IF NPV = 0
              C1
      C0 =
             1+ ρ
    C 0 (1 + ρ) = C 1
              C1 - C0
   IRR = ρ=
                 C0
Example
   Cost of project 1000 at time 0
   Payoff in time 1 is 1400
   IRR = (1400/1000) – 1 = 40%


        1400
               − 1000 = 0
       1 + IRR
IRR Decision Rule
   Accept all projects with a rate of return that is
    greater than the cost of capital.
IRR versus NPV
For accept/reject decisions in a single period
  case the NPV and IRR decision rules give
  exactly the same answer.

For ranking decisions conflicts may occur
Structure of Analysis
   Single Period Case
       Accept / Reject Decisions
       Ranking Decisions
   Multi-period Case
       Accept / Reject Decisions
       Ranking Decisions
Single Period: Mutually Exclusive
Projects – Differing Scales

                                   Project B
                 Project A        Cash Flows
                Cash Flows


      t0           (10)              (100)
      t1            20                130
     IRR          100%               30%
  NPV @ 10%   (10) + 20/1.1 =   -100 + 130/1.1 =
                    8.2               18.2
Internal Rate of Return
    IRR ignores the magnitude of the project.
    The following two projects illustrate that problem.




    Project      C0           Ct        IRR     NPV @ 10%
      E       −10,000      + 20,000     100       + 8,182
      F       − 20,000     + 35,000      75       +11,818
IRR in Multi-period Case
   The IRR generally gives the same answer in
    accept/reject decisions.
   However, there may be some technical
    difficulties with the IRR.
   First we will examine how to compute the
    IRR in the multiperiod case.
Internal Rate of Return
Example
  You can purchase a turbo powered machine tool
  gadget for $4,000. The investment will generate
  $2,000 and $4,000 in cash flows for two years,
  respectively. What is the IRR on this investment?
Internal Rate of Return
Example
    You can purchase a turbo powered machine tool gadget for $4,000. The
   investment will generate $2,000 and $4,000 in cash flows for two years,
   respectively. What is the IRR on this investment?


                    2,000      4,000
  NPV = −4,000 +             +           =0
                 (1 + IRR ) (1 + IRR )
                           1           2
Internal Rate of Return
Example
    You can purchase a turbo powered machine tool gadget for $4,000. The
   investment will generate $2,000 and $4,000 in cash flows for two years,
   respectively. What is the IRR on this investment?


                   2,000      4,000
 NPV = −4,000 +             +           =0
                (1 + IRR ) (1 + IRR )
                          1           2



 IRR = 28.08%
Internal Rate of Return
                2500
                2000
                                                  IRR=28%
                1500
                1000
  NPV (,000s)




                 500
                   0
                 -500
                             20




                                                 60
                        10



                                  30

                                       40

                                            50



                                                      70

                                                           80

                                                                90

                                                                        0
                                                                     10
                -1000
                -1500
                -2000
                                       Discount rate (%)
IRR computation with Excel ®
   See IRRDR.xls
Multi-period Computation of IRR
without a computer
   1. Calculate the NPV at a high discount rate so that it is < 0.
   2. Calculate the NPV at a low discount rate so that it is > 0.
    (e.g. use 0%)
   3. Divide the difference between the positive NPV and the
    negative NPV by the change in the discount rate to get the
    approximate change in NPV for a one- percent change in the
    discount rate.
   4. Using the information in 3 compute the required increase
    (decrease) in the rate to reduce (increase) the positive
    (negative) NPV to zero.
   5. Use the rate computed in 4 to discount the cash flows. If
    the NPV is not equal to zero then alter your estimate of the
    IRR accordingly.
Calculation of IRR in multi-period
case
TIME       0            1             2            3


CASH       -350         110           121          200
FLOW


  The NPV @ 0% = 81
  The NPV @ 20% = (59)

  Thus there is a spread of 140(7) in the NPV for a spread of
  20%(1%) in the discount rate.
IRR Calculation Continued
   On the basis of this information we should
    reduce the discount rate by (59/7)% = 8.43%
    from 20%.
   If we try a rate of 12% the NPV = (13).
    Therefore we have to reduce by a further 2%
    or so to get NPV = 0.
   Discounting at 10% gives an NPV of 0.
    Hence the IRR is 10%.
Internal Rate of Return
Accept / Reject Decisions: Technical Problem -
  Multiple Rates of Return
   Certain cash flows can generate NPV=0 at two different
    discount rates.
   The following cash flow generates NPV=0 at both (-50%)
    and 15.2%.

  C0     C1    C2    C3    C4    C5    C6
− 1,000 + 800 + 150 + 150 + 150 + 150 − 150
Internal Rate of Return
Pitfall 2 - Multiple Rates of Return
   Certain cash flows can generate NPV=0 at two different discount rates.
                NPV
    The following cash flow generates NPV=0 at both (-50%) and 15.2%.
              1000

                                    IRR=15.2%
               500


                 0                                      Discount
                                                        Rate

              -500       IRR=-50%

              -1000
Multiple IRRs
   A project has as many IRRs as it has
    changes in the sign of its cash flows.


      Number 0             1          2       3
      of IRRS
      1          (100)     200        300     400

      3          (100)     200        (100)   500
Internal Rate of Return
Mutually Exclusive Projects
Internal Rate of Return
Reinvestment rate assumption
 There is an implicit assumption that all intermediate cash
   inflows are reinvested at the IRR
 It makes far more sense to assume that the intermediate cash
   flows are reinvested at the opportunity cost of capital.
 We assume that discount rates are stable during the term of
   the project.
Profitability Index
   Profitability Index is PV/C0
   The rule is to accept all projects which have a
    PI > 1.
   One gets the same answers as the NPV for
    accept/reject decisions.
   For ranking decisions conflicts arise in a
    manner similar to the IRR case e.g.
    differences in the scale of the project.
The Profitability Index and Capital
Rationing
   There is one case where the Profitability
    Index is superior to the NPV. This is where
    the firm faces a limit on the amount it can
    invest in a single year and projects are
    divisible and there is no postponement. In
    this special case one should maximise the
    NPV per £1 invested.
Profitability Index
   When resources are limited, the profitability
    index (PI) provides a tool for selecting among
    various project combinations and alternatives
   A set of limited resources and projects can
    yield various combinations.
Project appraisal: capital rationing,

•Coping with investment appraisal in an environment of
  capital rationing, taxation and inflation
•More specifically:
 – Explain why capital rationing exists and be able to use
   the profitability ratio in one-period rationing situations
Capital rationing

 •Capital rationing occurs when funds are not
available to finance all wealth-enhancing projects
 •Soft rationing
 •Hard rationing
 •One-period capital rationing
   – 1 Divisible projects
   – 2 Indivisible projects
One-period capital rationing
       with divisible projects
•Capital at time zero has been rationed to £4.5m
Bigtasks plc (continued)

   Ranking according to absolute NPV




                     Present value
                          Profitability index =
––––––––––––––––                                     Initial
outlay
                 Net present value
                              Benefit–cost ratio =
––––––––––––––                                       Initial
outlay
Bigtasks plc: Profitability indices
        and benefit–cost ratios
Bigtasks plc: Ranking according
   to the highest profitability index
Indivisible projects
NPV – the pros
   NPV is the theoretically correct criteria for
    making investment decisions when
    maximisation of shareholder wealth is the
    objective
   It recognises the time value of money
   It forces managers to consider their
    projections carefully when estimating future
    cash flows
NPV – the pros continued
   It is generally easy to use
   It has a clear decision rule
   It can deal with multiple discount rates –
    unlike IRR
   It is not affected by differences in scale –
    unlike IRR and Profitability Index
NPV – the cons
   It does not help find value creating projects
   It does not lend itself to ex-post evaluation of
    managers in a straightforward manner. But
    residual income can help here.
NPV vs. IRR
                   Single-      Multi-Period
                   Period       Case
                   Case
 Accept/Reject     Always       Can be
                   Consistent   technical
                                Problems with
                                IRR
 Non Independent   Conflicts    Conflicts
 Projects (e.g.
 Ranking)
IRR – the pros
   It is theoretically correct for accept/reject
    decsions
   It recognises the time value of money
IRR – the cons
   It cannot be relied upon to signal the correct decision
    for non-independent projects – e.g. mutually
    exclusive projects of differing scales.
   Can have multiple IRRs
   Some projects have no IRR
   The re-investment assumptions of the rule do not
    make economic sense
IRR – the cons continued
   It cannot cope with multiple discount rates
   In addition it has all the other the drawbacks
    of the NPV criterion.

More Related Content

What's hot

Time value of money
Time value of moneyTime value of money
Time value of moneymishra21
 
Payback period by harikrishnanan
Payback period by harikrishnananPayback period by harikrishnanan
Payback period by harikrishnananHari krishna
 
6. present worth analysis
6. present worth analysis6. present worth analysis
6. present worth analysisMohsin Siddique
 
Investment decisions / capital Budgeting
Investment decisions / capital BudgetingInvestment decisions / capital Budgeting
Investment decisions / capital BudgetingRaghav Jha
 
Net present Value, Internal Rate Of Return, Profitability Index, Payback, dis...
Net present Value, Internal Rate Of Return, Profitability Index, Payback, dis...Net present Value, Internal Rate Of Return, Profitability Index, Payback, dis...
Net present Value, Internal Rate Of Return, Profitability Index, Payback, dis...Akhil Sabu
 
Business Valuation PowerPoint Presentation Slides
Business Valuation PowerPoint Presentation SlidesBusiness Valuation PowerPoint Presentation Slides
Business Valuation PowerPoint Presentation SlidesSlideTeam
 
Chapter 9: CAPITAL BUDGETING
Chapter 9: CAPITAL BUDGETINGChapter 9: CAPITAL BUDGETING
Chapter 9: CAPITAL BUDGETINGAJ SEBUC
 
pay back period question.pdf
pay back period question.pdfpay back period question.pdf
pay back period question.pdfzohaibanwar20
 
Net operating income approach
Net operating income approachNet operating income approach
Net operating income approachDevTech Finance
 
The Time Value of Money
The Time Value of MoneyThe Time Value of Money
The Time Value of MoneyJyoti Yadav
 
Chapter 2.Time Value of Money ppt
Chapter 2.Time Value of Money pptChapter 2.Time Value of Money ppt
Chapter 2.Time Value of Money pptZahraMirzayeva
 

What's hot (20)

Internal rate of return
Internal rate of returnInternal rate of return
Internal rate of return
 
NPV v/s IRR
NPV v/s IRRNPV v/s IRR
NPV v/s IRR
 
Time value of money
Time value of moneyTime value of money
Time value of money
 
NET PRESENT VALUE (NPV)
NET PRESENT VALUE (NPV)NET PRESENT VALUE (NPV)
NET PRESENT VALUE (NPV)
 
Time value of money
Time value of  moneyTime value of  money
Time value of money
 
Payback period by harikrishnanan
Payback period by harikrishnananPayback period by harikrishnanan
Payback period by harikrishnanan
 
6. present worth analysis
6. present worth analysis6. present worth analysis
6. present worth analysis
 
Investment decisions / capital Budgeting
Investment decisions / capital BudgetingInvestment decisions / capital Budgeting
Investment decisions / capital Budgeting
 
Net present Value, Internal Rate Of Return, Profitability Index, Payback, dis...
Net present Value, Internal Rate Of Return, Profitability Index, Payback, dis...Net present Value, Internal Rate Of Return, Profitability Index, Payback, dis...
Net present Value, Internal Rate Of Return, Profitability Index, Payback, dis...
 
Business Valuation PowerPoint Presentation Slides
Business Valuation PowerPoint Presentation SlidesBusiness Valuation PowerPoint Presentation Slides
Business Valuation PowerPoint Presentation Slides
 
Chapter 9: CAPITAL BUDGETING
Chapter 9: CAPITAL BUDGETINGChapter 9: CAPITAL BUDGETING
Chapter 9: CAPITAL BUDGETING
 
Internal rate of return
Internal rate of returnInternal rate of return
Internal rate of return
 
pay back period question.pdf
pay back period question.pdfpay back period question.pdf
pay back period question.pdf
 
Internal Rate of Return
Internal Rate of ReturnInternal Rate of Return
Internal Rate of Return
 
Net operating income approach
Net operating income approachNet operating income approach
Net operating income approach
 
The Time Value of Money
The Time Value of MoneyThe Time Value of Money
The Time Value of Money
 
TYPES OF BONDS
TYPES OF BONDSTYPES OF BONDS
TYPES OF BONDS
 
cash flow
cash flow cash flow
cash flow
 
Chapter 2.Time Value of Money ppt
Chapter 2.Time Value of Money pptChapter 2.Time Value of Money ppt
Chapter 2.Time Value of Money ppt
 
Investment appraisal techniques
Investment appraisal techniquesInvestment appraisal techniques
Investment appraisal techniques
 

Similar to Irr(1)

Lecture5 mba
Lecture5 mbaLecture5 mba
Lecture5 mbagldazo
 
Captial bugting
Captial bugtingCaptial bugting
Captial bugting3prem
 
ChapterTool KitChapter 10112018 The Basics of Capital Budgeting
ChapterTool KitChapter 10112018 The Basics of Capital BudgetingChapterTool KitChapter 10112018 The Basics of Capital Budgeting
ChapterTool KitChapter 10112018 The Basics of Capital BudgetingJinElias52
 
Profitability&npv
Profitability&npvProfitability&npv
Profitability&npvdannygriff1
 
Fm11 ch 10 show
Fm11 ch 10 showFm11 ch 10 show
Fm11 ch 10 showAdi Susilo
 
Fm11 ch 10 the basics of capital budgeting evaluating cash flows
Fm11 ch 10 the basics of capital budgeting evaluating cash flowsFm11 ch 10 the basics of capital budgeting evaluating cash flows
Fm11 ch 10 the basics of capital budgeting evaluating cash flowsNhu Tuyet Tran
 
Chapter 10 - Basics of Capital Budgeting.pptx
Chapter 10 - Basics of Capital Budgeting.pptxChapter 10 - Basics of Capital Budgeting.pptx
Chapter 10 - Basics of Capital Budgeting.pptxJaylouAguilar1
 
The_Basics_of_Capital_Budgeting.ppt
The_Basics_of_Capital_Budgeting.pptThe_Basics_of_Capital_Budgeting.ppt
The_Basics_of_Capital_Budgeting.pptFilyanFAnggriawan
 
THE BASICS OF CAPITAL BUDGETING
THE BASICS OF CAPITAL BUDGETINGTHE BASICS OF CAPITAL BUDGETING
THE BASICS OF CAPITAL BUDGETINGKhiemmy dela Torre
 
Capital budgeting kelompok 3 komplit email
Capital budgeting kelompok 3 komplit emailCapital budgeting kelompok 3 komplit email
Capital budgeting kelompok 3 komplit emailAndreas Hartoyo Yaputra
 
Chapter 4 CBT&D.pptx
Chapter 4 CBT&D.pptxChapter 4 CBT&D.pptx
Chapter 4 CBT&D.pptxSaif Uddin
 
Capital Budgeting Rules 04
Capital Budgeting Rules 04Capital Budgeting Rules 04
Capital Budgeting Rules 04rajeevgupta
 
Chapter8 investmentcriteria
Chapter8 investmentcriteriaChapter8 investmentcriteria
Chapter8 investmentcriteriaAKSHAYA0000
 

Similar to Irr(1) (20)

Lecture5 mba
Lecture5 mbaLecture5 mba
Lecture5 mba
 
Captial bugting
Captial bugtingCaptial bugting
Captial bugting
 
Cb
CbCb
Cb
 
Capital Budgeting
Capital BudgetingCapital Budgeting
Capital Budgeting
 
ch 11 Capital budgeting
ch 11 Capital budgetingch 11 Capital budgeting
ch 11 Capital budgeting
 
ChapterTool KitChapter 10112018 The Basics of Capital Budgeting
ChapterTool KitChapter 10112018 The Basics of Capital BudgetingChapterTool KitChapter 10112018 The Basics of Capital Budgeting
ChapterTool KitChapter 10112018 The Basics of Capital Budgeting
 
Profitability&npv
Profitability&npvProfitability&npv
Profitability&npv
 
Fm11 ch 10 show
Fm11 ch 10 showFm11 ch 10 show
Fm11 ch 10 show
 
Fm11 ch 10 the basics of capital budgeting evaluating cash flows
Fm11 ch 10 the basics of capital budgeting evaluating cash flowsFm11 ch 10 the basics of capital budgeting evaluating cash flows
Fm11 ch 10 the basics of capital budgeting evaluating cash flows
 
Chapter 10 - Basics of Capital Budgeting.pptx
Chapter 10 - Basics of Capital Budgeting.pptxChapter 10 - Basics of Capital Budgeting.pptx
Chapter 10 - Basics of Capital Budgeting.pptx
 
The_Basics_of_Capital_Budgeting.ppt
The_Basics_of_Capital_Budgeting.pptThe_Basics_of_Capital_Budgeting.ppt
The_Basics_of_Capital_Budgeting.ppt
 
THE BASICS OF CAPITAL BUDGETING
THE BASICS OF CAPITAL BUDGETINGTHE BASICS OF CAPITAL BUDGETING
THE BASICS OF CAPITAL BUDGETING
 
Capital budgeting
Capital budgetingCapital budgeting
Capital budgeting
 
Capital budgeting i
Capital budgeting iCapital budgeting i
Capital budgeting i
 
Capital budgeting
Capital budgeting Capital budgeting
Capital budgeting
 
Capital budgeting kelompok 3 komplit email
Capital budgeting kelompok 3 komplit emailCapital budgeting kelompok 3 komplit email
Capital budgeting kelompok 3 komplit email
 
Chapter 4 CBT&D.pptx
Chapter 4 CBT&D.pptxChapter 4 CBT&D.pptx
Chapter 4 CBT&D.pptx
 
Chap5
Chap5Chap5
Chap5
 
Capital Budgeting Rules 04
Capital Budgeting Rules 04Capital Budgeting Rules 04
Capital Budgeting Rules 04
 
Chapter8 investmentcriteria
Chapter8 investmentcriteriaChapter8 investmentcriteria
Chapter8 investmentcriteria
 

More from dannygriff1

Stocks&bonds2214 1
Stocks&bonds2214 1Stocks&bonds2214 1
Stocks&bonds2214 1dannygriff1
 
Ec2204 tutorial 8(2)
Ec2204 tutorial 8(2)Ec2204 tutorial 8(2)
Ec2204 tutorial 8(2)dannygriff1
 
Ec2204 tutorial 4(1)
Ec2204 tutorial 4(1)Ec2204 tutorial 4(1)
Ec2204 tutorial 4(1)dannygriff1
 
Ec2204 tutorial 3(1)
Ec2204 tutorial 3(1)Ec2204 tutorial 3(1)
Ec2204 tutorial 3(1)dannygriff1
 
Ec2204 tutorial 2(2)
Ec2204 tutorial 2(2)Ec2204 tutorial 2(2)
Ec2204 tutorial 2(2)dannygriff1
 
Ec2204 tutorial 1(2)
Ec2204 tutorial 1(2)Ec2204 tutorial 1(2)
Ec2204 tutorial 1(2)dannygriff1
 
6 price and output determination- monopoly
6 price and output determination- monopoly6 price and output determination- monopoly
6 price and output determination- monopolydannygriff1
 
5 industry structure and competition analysis
5  industry structure and competition analysis5  industry structure and competition analysis
5 industry structure and competition analysisdannygriff1
 
4 production and cost
4  production and cost4  production and cost
4 production and costdannygriff1
 
3 consumer choice
3 consumer choice3 consumer choice
3 consumer choicedannygriff1
 
2 demand-supply and elasticity
2  demand-supply and elasticity2  demand-supply and elasticity
2 demand-supply and elasticitydannygriff1
 
1 goals of the firm
1  goals of the firm1  goals of the firm
1 goals of the firmdannygriff1
 
Ec2204 tutorial 6(1)
Ec2204 tutorial 6(1)Ec2204 tutorial 6(1)
Ec2204 tutorial 6(1)dannygriff1
 
Is2215 lecture7 lecturer_ado_intro
Is2215 lecture7 lecturer_ado_introIs2215 lecture7 lecturer_ado_intro
Is2215 lecture7 lecturer_ado_introdannygriff1
 
Is2215 lecture6 lecturer_file_access
Is2215 lecture6 lecturer_file_accessIs2215 lecture6 lecturer_file_access
Is2215 lecture6 lecturer_file_accessdannygriff1
 

More from dannygriff1 (20)

Stocks&bonds2214 1
Stocks&bonds2214 1Stocks&bonds2214 1
Stocks&bonds2214 1
 
Risk08a
Risk08aRisk08a
Risk08a
 
Npvrisk
NpvriskNpvrisk
Npvrisk
 
Npv2214(1)
Npv2214(1)Npv2214(1)
Npv2214(1)
 
Npv rule
Npv ruleNpv rule
Npv rule
 
Ec2204 tutorial 8(2)
Ec2204 tutorial 8(2)Ec2204 tutorial 8(2)
Ec2204 tutorial 8(2)
 
Ec2204 tutorial 4(1)
Ec2204 tutorial 4(1)Ec2204 tutorial 4(1)
Ec2204 tutorial 4(1)
 
Ec2204 tutorial 3(1)
Ec2204 tutorial 3(1)Ec2204 tutorial 3(1)
Ec2204 tutorial 3(1)
 
Ec2204 tutorial 2(2)
Ec2204 tutorial 2(2)Ec2204 tutorial 2(2)
Ec2204 tutorial 2(2)
 
Ec2204 tutorial 1(2)
Ec2204 tutorial 1(2)Ec2204 tutorial 1(2)
Ec2204 tutorial 1(2)
 
6 price and output determination- monopoly
6 price and output determination- monopoly6 price and output determination- monopoly
6 price and output determination- monopoly
 
5 industry structure and competition analysis
5  industry structure and competition analysis5  industry structure and competition analysis
5 industry structure and competition analysis
 
4 production and cost
4  production and cost4  production and cost
4 production and cost
 
3 consumer choice
3 consumer choice3 consumer choice
3 consumer choice
 
2 demand-supply and elasticity
2  demand-supply and elasticity2  demand-supply and elasticity
2 demand-supply and elasticity
 
1 goals of the firm
1  goals of the firm1  goals of the firm
1 goals of the firm
 
Ec2204 tutorial 6(1)
Ec2204 tutorial 6(1)Ec2204 tutorial 6(1)
Ec2204 tutorial 6(1)
 
Mcq sample
Mcq sampleMcq sample
Mcq sample
 
Is2215 lecture7 lecturer_ado_intro
Is2215 lecture7 lecturer_ado_introIs2215 lecture7 lecturer_ado_intro
Is2215 lecture7 lecturer_ado_intro
 
Is2215 lecture6 lecturer_file_access
Is2215 lecture6 lecturer_file_accessIs2215 lecture6 lecturer_file_access
Is2215 lecture6 lecturer_file_access
 

Irr(1)

  • 1. Topics Covered  Competitors to NPV  The Payback Period  The Book Rate of Return  Internal Rate of Return ALSO Consider  Capital Rationing
  • 2. Payback  The payback period of a project is the number of years it takes before the cumulative forecasted cash flow equals the initial outlay.  The payback rule says only accept projects that “payback” in the desired time frame.  This method is very flawed, primarily because it ignores later year cash flows and the the present value of future cash flows.
  • 3. Payback Example Examine the three projects and note the mistake we would make if we insisted on only taking projects with a payback period of 2 years or less. Payback Project C0 C1 C2 C3 NPV@ 10% Period A - 2000 500 500 5000 B - 2000 500 1800 0 C - 2000 1800 500 0
  • 4. Payback Example Examine the three projects and note the mistake we would make if we insisted on only taking projects with a payback period of 2 years or less. Payback Project C0 C1 C2 C3 NPV@ 10% Period A - 2000 500 500 5000 3 + 2,624 B - 2000 500 1800 0 2 - 58 C - 2000 1800 500 0 2 + 50
  • 5. Book Rate of Return Book Rate of Return - Average income divided by average book value over project life. Also called accounting rate of return. book income Book rate of return = book assets
  • 6. The book rate of return  It does recognise that capital is required to earn income.  However it has shortcomings as an investment appraisal method  It does not have a hurdle rate  It does not recognise the time value of money  Ambiguity regarding its definition.
  • 7. The Internal Rate of Return  Like the NPV this is a discounted cash flow criterion. In the single period case where we are merely interested in accepting or rejecting a project it is exactly equivalent to the NPV rule. However in all other situations congruence of the IRR and NPV rules cannot be guaranteed. When a conflict does occur the NPV gives the correct answers.
  • 8. Definition of IRR  The IRR is the discount rate that when used to discount a projects cash flow gives an NPV of zero.
  • 9. IRR in Single Period Case C1 − 1 = IRR = ρ C0
  • 10. Proof C1 NPV = - C 0 + 1+ i IF NPV = 0 C1 C0 = 1+ ρ C 0 (1 + ρ) = C 1 C1 - C0 IRR = ρ= C0
  • 11. Example  Cost of project 1000 at time 0  Payoff in time 1 is 1400  IRR = (1400/1000) – 1 = 40% 1400 − 1000 = 0 1 + IRR
  • 12. IRR Decision Rule  Accept all projects with a rate of return that is greater than the cost of capital.
  • 13. IRR versus NPV For accept/reject decisions in a single period case the NPV and IRR decision rules give exactly the same answer. For ranking decisions conflicts may occur
  • 14. Structure of Analysis  Single Period Case  Accept / Reject Decisions  Ranking Decisions  Multi-period Case  Accept / Reject Decisions  Ranking Decisions
  • 15. Single Period: Mutually Exclusive Projects – Differing Scales Project B Project A Cash Flows Cash Flows t0 (10) (100) t1 20 130 IRR 100% 30% NPV @ 10% (10) + 20/1.1 = -100 + 130/1.1 = 8.2 18.2
  • 16. Internal Rate of Return  IRR ignores the magnitude of the project.  The following two projects illustrate that problem. Project C0 Ct IRR NPV @ 10% E −10,000 + 20,000 100 + 8,182 F − 20,000 + 35,000 75 +11,818
  • 17. IRR in Multi-period Case  The IRR generally gives the same answer in accept/reject decisions.  However, there may be some technical difficulties with the IRR.  First we will examine how to compute the IRR in the multiperiod case.
  • 18. Internal Rate of Return Example You can purchase a turbo powered machine tool gadget for $4,000. The investment will generate $2,000 and $4,000 in cash flows for two years, respectively. What is the IRR on this investment?
  • 19. Internal Rate of Return Example You can purchase a turbo powered machine tool gadget for $4,000. The investment will generate $2,000 and $4,000 in cash flows for two years, respectively. What is the IRR on this investment? 2,000 4,000 NPV = −4,000 + + =0 (1 + IRR ) (1 + IRR ) 1 2
  • 20. Internal Rate of Return Example You can purchase a turbo powered machine tool gadget for $4,000. The investment will generate $2,000 and $4,000 in cash flows for two years, respectively. What is the IRR on this investment? 2,000 4,000 NPV = −4,000 + + =0 (1 + IRR ) (1 + IRR ) 1 2 IRR = 28.08%
  • 21. Internal Rate of Return 2500 2000 IRR=28% 1500 1000 NPV (,000s) 500 0 -500 20 60 10 30 40 50 70 80 90 0 10 -1000 -1500 -2000 Discount rate (%)
  • 22. IRR computation with Excel ®  See IRRDR.xls
  • 23. Multi-period Computation of IRR without a computer  1. Calculate the NPV at a high discount rate so that it is < 0.  2. Calculate the NPV at a low discount rate so that it is > 0. (e.g. use 0%)  3. Divide the difference between the positive NPV and the negative NPV by the change in the discount rate to get the approximate change in NPV for a one- percent change in the discount rate.  4. Using the information in 3 compute the required increase (decrease) in the rate to reduce (increase) the positive (negative) NPV to zero.  5. Use the rate computed in 4 to discount the cash flows. If the NPV is not equal to zero then alter your estimate of the IRR accordingly.
  • 24. Calculation of IRR in multi-period case TIME 0 1 2 3 CASH -350 110 121 200 FLOW The NPV @ 0% = 81 The NPV @ 20% = (59) Thus there is a spread of 140(7) in the NPV for a spread of 20%(1%) in the discount rate.
  • 25. IRR Calculation Continued  On the basis of this information we should reduce the discount rate by (59/7)% = 8.43% from 20%.  If we try a rate of 12% the NPV = (13). Therefore we have to reduce by a further 2% or so to get NPV = 0.  Discounting at 10% gives an NPV of 0. Hence the IRR is 10%.
  • 26. Internal Rate of Return Accept / Reject Decisions: Technical Problem - Multiple Rates of Return  Certain cash flows can generate NPV=0 at two different discount rates.  The following cash flow generates NPV=0 at both (-50%) and 15.2%. C0 C1 C2 C3 C4 C5 C6 − 1,000 + 800 + 150 + 150 + 150 + 150 − 150
  • 27. Internal Rate of Return Pitfall 2 - Multiple Rates of Return  Certain cash flows can generate NPV=0 at two different discount rates.  NPV The following cash flow generates NPV=0 at both (-50%) and 15.2%. 1000 IRR=15.2% 500 0 Discount Rate -500 IRR=-50% -1000
  • 28. Multiple IRRs  A project has as many IRRs as it has changes in the sign of its cash flows. Number 0 1 2 3 of IRRS 1 (100) 200 300 400 3 (100) 200 (100) 500
  • 29. Internal Rate of Return Mutually Exclusive Projects
  • 30. Internal Rate of Return Reinvestment rate assumption  There is an implicit assumption that all intermediate cash inflows are reinvested at the IRR  It makes far more sense to assume that the intermediate cash flows are reinvested at the opportunity cost of capital.  We assume that discount rates are stable during the term of the project.
  • 31. Profitability Index  Profitability Index is PV/C0  The rule is to accept all projects which have a PI > 1.  One gets the same answers as the NPV for accept/reject decisions.  For ranking decisions conflicts arise in a manner similar to the IRR case e.g. differences in the scale of the project.
  • 32. The Profitability Index and Capital Rationing  There is one case where the Profitability Index is superior to the NPV. This is where the firm faces a limit on the amount it can invest in a single year and projects are divisible and there is no postponement. In this special case one should maximise the NPV per £1 invested.
  • 33. Profitability Index  When resources are limited, the profitability index (PI) provides a tool for selecting among various project combinations and alternatives  A set of limited resources and projects can yield various combinations.
  • 34. Project appraisal: capital rationing, •Coping with investment appraisal in an environment of capital rationing, taxation and inflation •More specifically: – Explain why capital rationing exists and be able to use the profitability ratio in one-period rationing situations
  • 35. Capital rationing •Capital rationing occurs when funds are not available to finance all wealth-enhancing projects •Soft rationing •Hard rationing •One-period capital rationing – 1 Divisible projects – 2 Indivisible projects
  • 36. One-period capital rationing with divisible projects •Capital at time zero has been rationed to £4.5m
  • 37. Bigtasks plc (continued) Ranking according to absolute NPV Present value Profitability index = –––––––––––––––– Initial outlay Net present value Benefit–cost ratio = –––––––––––––– Initial outlay
  • 38. Bigtasks plc: Profitability indices and benefit–cost ratios
  • 39. Bigtasks plc: Ranking according to the highest profitability index
  • 41. NPV – the pros  NPV is the theoretically correct criteria for making investment decisions when maximisation of shareholder wealth is the objective  It recognises the time value of money  It forces managers to consider their projections carefully when estimating future cash flows
  • 42. NPV – the pros continued  It is generally easy to use  It has a clear decision rule  It can deal with multiple discount rates – unlike IRR  It is not affected by differences in scale – unlike IRR and Profitability Index
  • 43. NPV – the cons  It does not help find value creating projects  It does not lend itself to ex-post evaluation of managers in a straightforward manner. But residual income can help here.
  • 44. NPV vs. IRR Single- Multi-Period Period Case Case Accept/Reject Always Can be Consistent technical Problems with IRR Non Independent Conflicts Conflicts Projects (e.g. Ranking)
  • 45. IRR – the pros  It is theoretically correct for accept/reject decsions  It recognises the time value of money
  • 46. IRR – the cons  It cannot be relied upon to signal the correct decision for non-independent projects – e.g. mutually exclusive projects of differing scales.  Can have multiple IRRs  Some projects have no IRR  The re-investment assumptions of the rule do not make economic sense
  • 47. IRR – the cons continued  It cannot cope with multiple discount rates  In addition it has all the other the drawbacks of the NPV criterion.