Capitol Expressway Light Rail Project
         Pedestrian Improvements


               Project Update

                District 5 United
                January 25, 2012




1
Project Phasing


     • The Capitol Expressway Light Rail Project is
       phased with pedestrian and bus improvements
       prior to Light Rail

        o Pedestrian Improvements (Phase 1A)

        o Bus Improvements (Phase 1B)

        o Light Rail (Phase 2)




2                                 Capitol Expressway Light Rail Project
Project Phasing

    Pedestrian Improvements (prior to light rail)

     •   Continuous pathway on both sides of expressway
     •   Street lighting and pedestrian lighting along new sidewalk
     •   Landscape buffer between sidewalk and roadway
     •   HOV lanes to remain (will be removed with light rail)
     •   Construction is underway with completion in June 2012
     •   City to maintain street lights and landscape




3                                           Capitol Expressway Light Rail Project
Project Phasing

    Bus Improvements (prior to light rail)

    •    Bus stops at Story Road and Ocala Avenue
    •    Eastridge Transit Center: Expanded and reconfigured transit center
    •    Property acquisition began in May 2011
    •    Design underway and scheduled for completion in early 2012
    •    Construction anticipated for fall 2012 (pending approval of STIP
         allocation)


        Light Rail

    • Preparing Federal Environmental Document for public comment
      anticipated for early 2012




4                                           Capitol Expressway Light Rail Project
Overall Schedule


    • Construction for pedestrian               May 2011 to Summer 2012

    • Property acquisition for bus              May 2011 to early 2012

    • Federal EIS for public review             Early 2012

    • Design for bus improvements               current to early 2012

    • Federal EIS approved                      Late 2012

    • Construction of bus improvements          Fall 2012 to end 2014
      (pending CTC allocation approval)

    • Light rail final design and construction to be determined



5                                           Capitol Expressway Light Rail Project
Pedestrian Improvements




6                             Capitol Expressway LR Project Phase I A
Capitol Expressway Extension

     Pedestrian and Bus Improvements




                                   Capitol Avenue to Story Road
    Legend


             New Sidewalk: Pedestrian Improvements (Phase 1A)
             New Sidewalk: Bus Improvements (Phase 1B)

             Existing Sidewalk: to be reconstructed with Bus Improvements
             Existing Sidewalk to remain

             Eastridge Transit Center: Reconstructed with Bus Improvements
             New Landscape Area (Phase 1A)

             New Tree (Phase 1A)

7                                                               Capitol Expressway Light Rail Project
Capitol Expressway Extension

     Pedestrian and Bus Improvements




                                Between Story Road and Ocala Avenue
    Legend


             New Sidewalk: Pedestrian Improvements (Phase 1A)
             New Sidewalk: Bus Improvements (Phase 1B)

             Existing Sidewalk: to be reconstructed with Bus Improvements
             Existing Sidewalk to remain

             Eastridge Transit Center: Reconstructed with Bus Improvements
             New Landscape Area (Phase 1A)

             New Tree (Phase 1A)

8                                                               Capitol Expressway Light Rail Project
Capitol Expressway Extension

     Pedestrian and Bus Improvements




                                              Ocala Avenue
    Legend


             New Sidewalk: Pedestrian Improvements (Phase 1A)
             New Sidewalk: Bus Improvements (Phase 1B)

             Existing Sidewalk: to be reconstructed with Bus Improvements
             Existing Sidewalk to remain

             Eastridge Transit Center: Reconstructed with Bus Improvements
             New Landscape Area (Phase 1A)

             New Tree (Phase 1A)

9                                                               Capitol Expressway Light Rail Project
Capitol Expressway Extension

      Pedestrian and Bus Improvements




                                    Cunningham Avenue to Tully Road
     Legend


              New Sidewalk: Pedestrian Improvements (Phase 1A)
              New Sidewalk: Bus Improvements (Phase 1B)

              Existing Sidewalk: to be reconstructed with Bus Improvements
              Existing Sidewalk to remain

              Eastridge Transit Center: Reconstructed with Bus Improvements
              New Landscape Area (Phase 1A)

              New Tree (Phase 1A)

10                                                               Capitol Expressway Light Rail Project
Capitol Expressway Extension

      Pedestrian and Bus Improvements




                              Tully Road to Eastridge Transit Center
     Legend


              New Sidewalk: Pedestrian Improvements (Phase 1A)
              New Sidewalk: Bus Improvements (Phase 1B)

              Existing Sidewalk: to be reconstructed with Bus Improvements
              Existing Sidewalk to remain

              Eastridge Transit Center: Reconstructed with Bus Improvements
              New Landscape Area (Phase 1A)

              New Tree (Phase 1A)

11                                                               Capitol Expressway Light Rail Project
Capitol Expressway Extension

      Pedestrian and Bus Improvements




                           Eastridge Transit Center to Quimby Road
     Legend


              New Sidewalk: Pedestrian Improvements (Phase 1A)
              New Sidewalk: Bus Improvements (Phase 1B)

              Existing Sidewalk: to be reconstructed with Bus Improvements
              Existing Sidewalk to remain

              Eastridge Transit Center: Reconstructed with Bus Improvements
              New Landscape Area (Phase 1A)

              New Tree (Phase 1A)

12                                                               Capitol Expressway Light Rail Project
Construction Photos

      Excavation and grading
        along levee slope




13                             Capitol Expressway LR Project Phase I A
Construction Photos




                                    Grading for sidewalk near
                                       Cunningham Park




           Conduit for lighting
             and bus stop
14                                Capitol Expressway LR Project Phase I A
Construction Photos
     Pathway north of Tully Road




15                                 Capitol Expressway LR Project Phase I A
Construction Photos




         Storm Drain Relocation
          along Capitol Avenue



                                     Forming new curb and
                                   gutter south of Story Road

16                                Capitol Expressway LR Project Phase I A

Contenu connexe

Tendances

Eglinton Station Open House
Eglinton Station Open HouseEglinton Station Open House
Eglinton Station Open HouseCrosstown TO
 
NJ Redevelopment Forum 2020 - Cialone
NJ Redevelopment Forum 2020 - CialoneNJ Redevelopment Forum 2020 - Cialone
NJ Redevelopment Forum 2020 - CialoneNew Jersey Future
 
8th Street Bridge Community Information Session November 19th, 2015
8th Street Bridge Community Information Session November 19th, 20158th Street Bridge Community Information Session November 19th, 2015
8th Street Bridge Community Information Session November 19th, 2015City Brandon
 
Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016
Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016
Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016VDOT Northern Virginia
 
Project 5 cooper river bridge 092210
Project 5   cooper river bridge 092210Project 5   cooper river bridge 092210
Project 5 cooper river bridge 092210TTI-UTCM
 
2009 Presentaton For Web
2009  Presentaton For  Web2009  Presentaton For  Web
2009 Presentaton For WebACECSDES
 
Mountain View Double-Track Project May 22 Presentation
Mountain View Double-Track Project May 22 PresentationMountain View Double-Track Project May 22 Presentation
Mountain View Double-Track Project May 22 PresentationSCVTA
 
Virginia's Hampton Roads: Strategic position in the vision for High-Speed Ra...
Virginia's Hampton Roads:  Strategic position in the vision for High-Speed Ra...Virginia's Hampton Roads:  Strategic position in the vision for High-Speed Ra...
Virginia's Hampton Roads: Strategic position in the vision for High-Speed Ra...Hampton Roads: America's First Region
 
Stringfellow Park and Ride Expansion
Stringfellow Park and Ride ExpansionStringfellow Park and Ride Expansion
Stringfellow Park and Ride ExpansionFairfax County
 

Tendances (17)

Eglinton Station Open House
Eglinton Station Open HouseEglinton Station Open House
Eglinton Station Open House
 
Coordinated Transit Planning in Toronto
Coordinated Transit Planning in TorontoCoordinated Transit Planning in Toronto
Coordinated Transit Planning in Toronto
 
NJ Redevelopment Forum 2020 - Cialone
NJ Redevelopment Forum 2020 - CialoneNJ Redevelopment Forum 2020 - Cialone
NJ Redevelopment Forum 2020 - Cialone
 
8th Street Bridge Community Information Session November 19th, 2015
8th Street Bridge Community Information Session November 19th, 20158th Street Bridge Community Information Session November 19th, 2015
8th Street Bridge Community Information Session November 19th, 2015
 
Scarborough Transit Town Hall - April 23, 2016
Scarborough Transit Town Hall - April 23, 2016Scarborough Transit Town Hall - April 23, 2016
Scarborough Transit Town Hall - April 23, 2016
 
Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016
Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016
Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016
 
Project 5 cooper river bridge 092210
Project 5   cooper river bridge 092210Project 5   cooper river bridge 092210
Project 5 cooper river bridge 092210
 
The State of Rail in Illinois
The State of Rail in IllinoisThe State of Rail in Illinois
The State of Rail in Illinois
 
Briefing: Scarborough Transit Planning Update
Briefing: Scarborough Transit Planning UpdateBriefing: Scarborough Transit Planning Update
Briefing: Scarborough Transit Planning Update
 
Downtown Construction Projects
Downtown Construction Projects Downtown Construction Projects
Downtown Construction Projects
 
Four Mile Run Joint Task Force Presentation
Four Mile Run Joint Task Force PresentationFour Mile Run Joint Task Force Presentation
Four Mile Run Joint Task Force Presentation
 
2009 Presentaton For Web
2009  Presentaton For  Web2009  Presentaton For  Web
2009 Presentaton For Web
 
Mountain View Double-Track Project May 22 Presentation
Mountain View Double-Track Project May 22 PresentationMountain View Double-Track Project May 22 Presentation
Mountain View Double-Track Project May 22 Presentation
 
SMART Plan DTPW Corridor Estimates
SMART Plan DTPW Corridor EstimatesSMART Plan DTPW Corridor Estimates
SMART Plan DTPW Corridor Estimates
 
Virginia's Hampton Roads: Strategic position in the vision for High-Speed Ra...
Virginia's Hampton Roads:  Strategic position in the vision for High-Speed Ra...Virginia's Hampton Roads:  Strategic position in the vision for High-Speed Ra...
Virginia's Hampton Roads: Strategic position in the vision for High-Speed Ra...
 
Scarborough Subway Extension - Terms of Reference
Scarborough Subway Extension - Terms of ReferenceScarborough Subway Extension - Terms of Reference
Scarborough Subway Extension - Terms of Reference
 
Stringfellow Park and Ride Expansion
Stringfellow Park and Ride ExpansionStringfellow Park and Ride Expansion
Stringfellow Park and Ride Expansion
 

Similaire à Capitol Expressway Light Rail Project – Pedestrian Improvements

Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingCrosstown TO
 
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018Crosstown TO
 
Pharmacy to kennedy construction liaison committee meeting - June 2018
Pharmacy to kennedy construction liaison committee meeting - June 2018Pharmacy to kennedy construction liaison committee meeting - June 2018
Pharmacy to kennedy construction liaison committee meeting - June 2018Crosstown TO
 
Tysons Fire Station #29 and Bus Transit Facility - 111621 community meeting
Tysons Fire Station #29 and Bus Transit Facility - 111621 community meetingTysons Fire Station #29 and Bus Transit Facility - 111621 community meeting
Tysons Fire Station #29 and Bus Transit Facility - 111621 community meetingFairfax County
 
Exposition Light Rail Transit Project 1
Exposition Light Rail Transit Project 1Exposition Light Rail Transit Project 1
Exposition Light Rail Transit Project 1Daryl Kellner
 
LaSalle Overpass & May Street - Meeting of the Verdun / Sud-Ouest Good Neighb...
LaSalle Overpass & May Street - Meeting of the Verdun / Sud-Ouest Good Neighb...LaSalle Overpass & May Street - Meeting of the Verdun / Sud-Ouest Good Neighb...
LaSalle Overpass & May Street - Meeting of the Verdun / Sud-Ouest Good Neighb...Pont Samuel-De Champlain Bridge
 
Flatlick Sewer Rehabilitation Project Phase 1 and 2
Flatlick Sewer Rehabilitation Project Phase 1 and 2Flatlick Sewer Rehabilitation Project Phase 1 and 2
Flatlick Sewer Rehabilitation Project Phase 1 and 2Fairfax County
 
Islington council presentation on Wharfdale Road bridge
Islington council presentation on Wharfdale Road bridgeIslington council presentation on Wharfdale Road bridge
Islington council presentation on Wharfdale Road bridgewilliam perrin
 
Mount Dennis Station Open House
Mount Dennis Station Open HouseMount Dennis Station Open House
Mount Dennis Station Open HouseCrosstown TO
 
Sunset Hills Road Walkway
Sunset Hills Road WalkwaySunset Hills Road Walkway
Sunset Hills Road WalkwayFairfax County
 
Final public meeting presentation
Final public meeting presentationFinal public meeting presentation
Final public meeting presentationGunn Communications
 
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018Crosstown TO
 
228 congressparkway overview_jan2010
228 congressparkway overview_jan2010228 congressparkway overview_jan2010
228 congressparkway overview_jan2010Daniel X. O'Neil
 
Congress Parkway Construction Overview, January 2010
Congress Parkway Construction Overview, January 2010Congress Parkway Construction Overview, January 2010
Congress Parkway Construction Overview, January 2010Daniel X. O'Neil
 
London Underground - Redesigning White-chapel Station
London Underground - Redesigning White-chapel Station London Underground - Redesigning White-chapel Station
London Underground - Redesigning White-chapel Station Ibrahim Al-Hudhaif
 
Substantial Completion: Lorton Road Project
Substantial Completion: Lorton Road ProjectSubstantial Completion: Lorton Road Project
Substantial Completion: Lorton Road ProjectFairfax County
 
Pharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingPharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingCrosstown TO
 

Similaire à Capitol Expressway Light Rail Project – Pedestrian Improvements (19)

Transport in london
 Transport in london  Transport in london
Transport in london
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
 
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018
 
Pharmacy to kennedy construction liaison committee meeting - June 2018
Pharmacy to kennedy construction liaison committee meeting - June 2018Pharmacy to kennedy construction liaison committee meeting - June 2018
Pharmacy to kennedy construction liaison committee meeting - June 2018
 
Tysons Fire Station #29 and Bus Transit Facility - 111621 community meeting
Tysons Fire Station #29 and Bus Transit Facility - 111621 community meetingTysons Fire Station #29 and Bus Transit Facility - 111621 community meeting
Tysons Fire Station #29 and Bus Transit Facility - 111621 community meeting
 
Exposition Light Rail Transit Project 1
Exposition Light Rail Transit Project 1Exposition Light Rail Transit Project 1
Exposition Light Rail Transit Project 1
 
LaSalle Overpass & May Street - Meeting of the Verdun / Sud-Ouest Good Neighb...
LaSalle Overpass & May Street - Meeting of the Verdun / Sud-Ouest Good Neighb...LaSalle Overpass & May Street - Meeting of the Verdun / Sud-Ouest Good Neighb...
LaSalle Overpass & May Street - Meeting of the Verdun / Sud-Ouest Good Neighb...
 
Flatlick Sewer Rehabilitation Project Phase 1 and 2
Flatlick Sewer Rehabilitation Project Phase 1 and 2Flatlick Sewer Rehabilitation Project Phase 1 and 2
Flatlick Sewer Rehabilitation Project Phase 1 and 2
 
Islington council presentation on Wharfdale Road bridge
Islington council presentation on Wharfdale Road bridgeIslington council presentation on Wharfdale Road bridge
Islington council presentation on Wharfdale Road bridge
 
Mount Dennis Station Open House
Mount Dennis Station Open HouseMount Dennis Station Open House
Mount Dennis Station Open House
 
Sunset Hills Road Walkway
Sunset Hills Road WalkwaySunset Hills Road Walkway
Sunset Hills Road Walkway
 
Final public meeting presentation
Final public meeting presentationFinal public meeting presentation
Final public meeting presentation
 
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
 
Toronto Relief Line Public Meeting Presentation
Toronto Relief Line Public Meeting PresentationToronto Relief Line Public Meeting Presentation
Toronto Relief Line Public Meeting Presentation
 
228 congressparkway overview_jan2010
228 congressparkway overview_jan2010228 congressparkway overview_jan2010
228 congressparkway overview_jan2010
 
Congress Parkway Construction Overview, January 2010
Congress Parkway Construction Overview, January 2010Congress Parkway Construction Overview, January 2010
Congress Parkway Construction Overview, January 2010
 
London Underground - Redesigning White-chapel Station
London Underground - Redesigning White-chapel Station London Underground - Redesigning White-chapel Station
London Underground - Redesigning White-chapel Station
 
Substantial Completion: Lorton Road Project
Substantial Completion: Lorton Road ProjectSubstantial Completion: Lorton Road Project
Substantial Completion: Lorton Road Project
 
Pharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingPharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee Meeting
 

Plus de district5united

SJ Council District 5 Accomplishments 2010-2014
SJ Council District 5 Accomplishments 2010-2014SJ Council District 5 Accomplishments 2010-2014
SJ Council District 5 Accomplishments 2010-2014district5united
 
Extended Local Control Funding Formula presentation by Public Advocates
Extended Local Control Funding Formula presentation by Public AdvocatesExtended Local Control Funding Formula presentation by Public Advocates
Extended Local Control Funding Formula presentation by Public Advocatesdistrict5united
 
Local Control Funding Formula 101 presentation by the Santa Clara County Offi...
Local Control Funding Formula 101 presentation by the Santa Clara County Offi...Local Control Funding Formula 101 presentation by the Santa Clara County Offi...
Local Control Funding Formula 101 presentation by the Santa Clara County Offi...district5united
 
Local Control Funding Formula presentation by The Education Trust - West
Local Control Funding Formula presentation by The Education Trust - WestLocal Control Funding Formula presentation by The Education Trust - West
Local Control Funding Formula presentation by The Education Trust - Westdistrict5united
 
Local Control Funding Formula presentation by Public Advocates
Local Control Funding Formula presentation by Public AdvocatesLocal Control Funding Formula presentation by Public Advocates
Local Control Funding Formula presentation by Public Advocatesdistrict5united
 
Restructuring K12 funding document
Restructuring K12 funding documentRestructuring K12 funding document
Restructuring K12 funding documentdistrict5united
 
Fairflyer revised spanish
Fairflyer revised spanishFairflyer revised spanish
Fairflyer revised spanishdistrict5united
 
NDTC 2012 Registration Packet
NDTC 2012 Registration PacketNDTC 2012 Registration Packet
NDTC 2012 Registration Packetdistrict5united
 
CAP Grant Cycle 26 Web Grants Info
CAP Grant Cycle 26 Web Grants InfoCAP Grant Cycle 26 Web Grants Info
CAP Grant Cycle 26 Web Grants Infodistrict5united
 
District 5 United Bylaws
District 5 United BylawsDistrict 5 United Bylaws
District 5 United Bylawsdistrict5united
 
2012-2013 Proposed Budget in Brief
2012-2013 Proposed Budget in Brief2012-2013 Proposed Budget in Brief
2012-2013 Proposed Budget in Briefdistrict5united
 
Council District 5 Add-Back Memo
Council District 5 Add-Back MemoCouncil District 5 Add-Back Memo
Council District 5 Add-Back Memodistrict5united
 
2012 District 5 Community Budget Meeting flyer
2012 District 5 Community Budget Meeting flyer2012 District 5 Community Budget Meeting flyer
2012 District 5 Community Budget Meeting flyerdistrict5united
 
SJ Neighborhoods Commission - Rancho del Pueblo letter
SJ Neighborhoods Commission - Rancho del Pueblo letterSJ Neighborhoods Commission - Rancho del Pueblo letter
SJ Neighborhoods Commission - Rancho del Pueblo letterdistrict5united
 

Plus de district5united (15)

SJ Council District 5 Accomplishments 2010-2014
SJ Council District 5 Accomplishments 2010-2014SJ Council District 5 Accomplishments 2010-2014
SJ Council District 5 Accomplishments 2010-2014
 
Extended Local Control Funding Formula presentation by Public Advocates
Extended Local Control Funding Formula presentation by Public AdvocatesExtended Local Control Funding Formula presentation by Public Advocates
Extended Local Control Funding Formula presentation by Public Advocates
 
Local Control Funding Formula 101 presentation by the Santa Clara County Offi...
Local Control Funding Formula 101 presentation by the Santa Clara County Offi...Local Control Funding Formula 101 presentation by the Santa Clara County Offi...
Local Control Funding Formula 101 presentation by the Santa Clara County Offi...
 
Local Control Funding Formula presentation by The Education Trust - West
Local Control Funding Formula presentation by The Education Trust - WestLocal Control Funding Formula presentation by The Education Trust - West
Local Control Funding Formula presentation by The Education Trust - West
 
Local Control Funding Formula presentation by Public Advocates
Local Control Funding Formula presentation by Public AdvocatesLocal Control Funding Formula presentation by Public Advocates
Local Control Funding Formula presentation by Public Advocates
 
SB 69 Education Funding
SB 69  Education FundingSB 69  Education Funding
SB 69 Education Funding
 
Restructuring K12 funding document
Restructuring K12 funding documentRestructuring K12 funding document
Restructuring K12 funding document
 
Fairflyer revised spanish
Fairflyer revised spanishFairflyer revised spanish
Fairflyer revised spanish
 
NDTC 2012 Registration Packet
NDTC 2012 Registration PacketNDTC 2012 Registration Packet
NDTC 2012 Registration Packet
 
CAP Grant Cycle 26 Web Grants Info
CAP Grant Cycle 26 Web Grants InfoCAP Grant Cycle 26 Web Grants Info
CAP Grant Cycle 26 Web Grants Info
 
District 5 United Bylaws
District 5 United BylawsDistrict 5 United Bylaws
District 5 United Bylaws
 
2012-2013 Proposed Budget in Brief
2012-2013 Proposed Budget in Brief2012-2013 Proposed Budget in Brief
2012-2013 Proposed Budget in Brief
 
Council District 5 Add-Back Memo
Council District 5 Add-Back MemoCouncil District 5 Add-Back Memo
Council District 5 Add-Back Memo
 
2012 District 5 Community Budget Meeting flyer
2012 District 5 Community Budget Meeting flyer2012 District 5 Community Budget Meeting flyer
2012 District 5 Community Budget Meeting flyer
 
SJ Neighborhoods Commission - Rancho del Pueblo letter
SJ Neighborhoods Commission - Rancho del Pueblo letterSJ Neighborhoods Commission - Rancho del Pueblo letter
SJ Neighborhoods Commission - Rancho del Pueblo letter
 

Dernier

8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCRashishs7044
 
TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024Adnet Communications
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCRashishs7044
 
Investment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy CheruiyotInvestment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy Cheruiyotictsugar
 
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607dollysharma2066
 
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607dollysharma2066
 
Innovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfInnovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfrichard876048
 
Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy Verified Accounts
 
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdfNewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdfKhaled Al Awadi
 
Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Americas Got Grants
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Kirill Klimov
 
Cyber Security Training in Office Environment
Cyber Security Training in Office EnvironmentCyber Security Training in Office Environment
Cyber Security Training in Office Environmentelijahj01012
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Anamaria Contreras
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCRashishs7044
 
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...ictsugar
 
Chapter 9 PPT 4th edition.pdf internal audit
Chapter 9 PPT 4th edition.pdf internal auditChapter 9 PPT 4th edition.pdf internal audit
Chapter 9 PPT 4th edition.pdf internal auditNhtLNguyn9
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCRashishs7044
 
Kenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby AfricaKenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby Africaictsugar
 
Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Peter Ward
 

Dernier (20)

8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
 
TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
 
Investment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy CheruiyotInvestment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy Cheruiyot
 
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
 
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
 
Innovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfInnovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdf
 
Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail Accounts
 
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdfNewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
 
Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024
 
Cyber Security Training in Office Environment
Cyber Security Training in Office EnvironmentCyber Security Training in Office Environment
Cyber Security Training in Office Environment
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
 
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
 
Chapter 9 PPT 4th edition.pdf internal audit
Chapter 9 PPT 4th edition.pdf internal auditChapter 9 PPT 4th edition.pdf internal audit
Chapter 9 PPT 4th edition.pdf internal audit
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
 
Kenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby AfricaKenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby Africa
 
Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...
 
Call Us ➥9319373153▻Call Girls In North Goa
Call Us ➥9319373153▻Call Girls In North GoaCall Us ➥9319373153▻Call Girls In North Goa
Call Us ➥9319373153▻Call Girls In North Goa
 

Capitol Expressway Light Rail Project – Pedestrian Improvements

  • 1. Capitol Expressway Light Rail Project Pedestrian Improvements Project Update District 5 United January 25, 2012 1
  • 2. Project Phasing • The Capitol Expressway Light Rail Project is phased with pedestrian and bus improvements prior to Light Rail o Pedestrian Improvements (Phase 1A) o Bus Improvements (Phase 1B) o Light Rail (Phase 2) 2 Capitol Expressway Light Rail Project
  • 3. Project Phasing Pedestrian Improvements (prior to light rail) • Continuous pathway on both sides of expressway • Street lighting and pedestrian lighting along new sidewalk • Landscape buffer between sidewalk and roadway • HOV lanes to remain (will be removed with light rail) • Construction is underway with completion in June 2012 • City to maintain street lights and landscape 3 Capitol Expressway Light Rail Project
  • 4. Project Phasing Bus Improvements (prior to light rail) • Bus stops at Story Road and Ocala Avenue • Eastridge Transit Center: Expanded and reconfigured transit center • Property acquisition began in May 2011 • Design underway and scheduled for completion in early 2012 • Construction anticipated for fall 2012 (pending approval of STIP allocation) Light Rail • Preparing Federal Environmental Document for public comment anticipated for early 2012 4 Capitol Expressway Light Rail Project
  • 5. Overall Schedule • Construction for pedestrian May 2011 to Summer 2012 • Property acquisition for bus May 2011 to early 2012 • Federal EIS for public review Early 2012 • Design for bus improvements current to early 2012 • Federal EIS approved Late 2012 • Construction of bus improvements Fall 2012 to end 2014 (pending CTC allocation approval) • Light rail final design and construction to be determined 5 Capitol Expressway Light Rail Project
  • 6. Pedestrian Improvements 6 Capitol Expressway LR Project Phase I A
  • 7. Capitol Expressway Extension Pedestrian and Bus Improvements Capitol Avenue to Story Road Legend New Sidewalk: Pedestrian Improvements (Phase 1A) New Sidewalk: Bus Improvements (Phase 1B) Existing Sidewalk: to be reconstructed with Bus Improvements Existing Sidewalk to remain Eastridge Transit Center: Reconstructed with Bus Improvements New Landscape Area (Phase 1A) New Tree (Phase 1A) 7 Capitol Expressway Light Rail Project
  • 8. Capitol Expressway Extension Pedestrian and Bus Improvements Between Story Road and Ocala Avenue Legend New Sidewalk: Pedestrian Improvements (Phase 1A) New Sidewalk: Bus Improvements (Phase 1B) Existing Sidewalk: to be reconstructed with Bus Improvements Existing Sidewalk to remain Eastridge Transit Center: Reconstructed with Bus Improvements New Landscape Area (Phase 1A) New Tree (Phase 1A) 8 Capitol Expressway Light Rail Project
  • 9. Capitol Expressway Extension Pedestrian and Bus Improvements Ocala Avenue Legend New Sidewalk: Pedestrian Improvements (Phase 1A) New Sidewalk: Bus Improvements (Phase 1B) Existing Sidewalk: to be reconstructed with Bus Improvements Existing Sidewalk to remain Eastridge Transit Center: Reconstructed with Bus Improvements New Landscape Area (Phase 1A) New Tree (Phase 1A) 9 Capitol Expressway Light Rail Project
  • 10. Capitol Expressway Extension Pedestrian and Bus Improvements Cunningham Avenue to Tully Road Legend New Sidewalk: Pedestrian Improvements (Phase 1A) New Sidewalk: Bus Improvements (Phase 1B) Existing Sidewalk: to be reconstructed with Bus Improvements Existing Sidewalk to remain Eastridge Transit Center: Reconstructed with Bus Improvements New Landscape Area (Phase 1A) New Tree (Phase 1A) 10 Capitol Expressway Light Rail Project
  • 11. Capitol Expressway Extension Pedestrian and Bus Improvements Tully Road to Eastridge Transit Center Legend New Sidewalk: Pedestrian Improvements (Phase 1A) New Sidewalk: Bus Improvements (Phase 1B) Existing Sidewalk: to be reconstructed with Bus Improvements Existing Sidewalk to remain Eastridge Transit Center: Reconstructed with Bus Improvements New Landscape Area (Phase 1A) New Tree (Phase 1A) 11 Capitol Expressway Light Rail Project
  • 12. Capitol Expressway Extension Pedestrian and Bus Improvements Eastridge Transit Center to Quimby Road Legend New Sidewalk: Pedestrian Improvements (Phase 1A) New Sidewalk: Bus Improvements (Phase 1B) Existing Sidewalk: to be reconstructed with Bus Improvements Existing Sidewalk to remain Eastridge Transit Center: Reconstructed with Bus Improvements New Landscape Area (Phase 1A) New Tree (Phase 1A) 12 Capitol Expressway Light Rail Project
  • 13. Construction Photos Excavation and grading along levee slope 13 Capitol Expressway LR Project Phase I A
  • 14. Construction Photos Grading for sidewalk near Cunningham Park Conduit for lighting and bus stop 14 Capitol Expressway LR Project Phase I A
  • 15. Construction Photos Pathway north of Tully Road 15 Capitol Expressway LR Project Phase I A
  • 16. Construction Photos Storm Drain Relocation along Capitol Avenue Forming new curb and gutter south of Story Road 16 Capitol Expressway LR Project Phase I A