Sudden three phase short circuit test
Table of Content:
1 Objective..........................................................................................................
2 Scope...............................................................................................................
3 Referenced documents....................................................................................
4 Terms and abbreviations..................................................................................
5 Sudden three-phase short-circuit test...............................................................
5.1 Preparations...................................................................................................
5.2 Conduction of test..........................................................................................
5.3 Evaluation of the test......................................................................................
6 Proceeding in case of deviations ......................................................................
7 Copyright............................................................................................................
1 Objective
The sudden three-phase short-circuit test is performed to determine the following
machine quantities:
- Direct-axis transient reactance Xd'
- Direct-axis subtransient reactance Xd"
- Direct-axis transient short-circuit time constant Td'
- Direct-axis subtransient short-circuit time constant Td"
- Armature short-circuit time constant Ta.
- Evidence of mechanical strength
2 Scope
This procedure applies to all types of synchronous machines during final inspections at
site or in the workshop.
3 Referenced documents
IEC 34-4, 40-41 Rotating electrical machines – Methods for determining
Synchronous machine quantities from tests
IEEE 115, 11.7 Test Procedures for synchronous machines
EN 60034-4 Rotating electrical machines - Methods for determining
Synchronous machine quantities from tests
4 Terms and abbreviations
none
5 Sudden three-phase short-circuit test
5.1 Preparations
Visual inspections:
- End winding supports
- Condition of foundation
- Are the foundation bolts tightened?
8/25/2005 9:02 a8/p8 © VA TECH HYDRO Page 1 of 4
- Correct assembly and fixation of all rotor components
- Disconnect the line terminals from the terminal buses (may not be necessary in all
cases).
- Connect the power cable between the line terminals and the circuit breaker, which is
used to make the short-circuit and install measuring devices for recording the short-
circuit currents in wye-connection.
Note: Normally the plant circuit breaker will be used for this purpose. To install a
separate
short-circuit breaker in the plant requires high efforts and good coordination between the
user of the plant and the generator manufacturer, as well as considerable extra costs.
In the workshop a special short-circuit breaker with synchronized phases is used. The
short circuit itself can be made with a special bar across the terminal buses or a
disconnector installed in the current leads (e.g. braking disconnector). This is placed
after the circuit breaker and is inserted before switching in the circuit breaker. Consider
that it is designed to support the current forces and can carry the substained short circuit
current during the recording time.
-
For current transformation the following equipment may be alternatively used:
- Linearized current transformers
- Low inductance precision shunts
- Unlock protection relays as required.
- Remove the grounding cable of the neutral terminals and directly connect the common
terminal of the three-phase short-circuit wye to ground.
- Attach a voltmeter and potential transformer to the generator line terminals (if required)
to measure the armature voltage prior to the sudden short-circuit.
- Connect and set the precision instruments for measuring the terminal voltage and field
current.
Note: The following analog- or digital instruments or equivalent (at least 4 channels) may
be used for recording purposes:
- Digital storage oscilloscope (Hioki 8855)
- Memory Recorder (YEW AR 1100 A)
- Memory Recorder (YEW DL 708)
- Connect the output signals of the current transformer (CT) or equivalent to the
recorder, whereby the current signal of the CT is converted into a voltage signal required
for the digital storage oscilloscope using precision shunts.
- Calibrate and set the trigger of the recording instruments to the expected levels.
5.2 Conduction of test
- Operate the unit at rated speed in no-load condition with the manual control of the
excitation system. In case of static excitation set the ignition anlge of the gate trigger
pulse to achieve the required generator voltage. Neither a current regulator (for the field
current) nor a voltage regulator (for the generator voltage) may be switched on.
Note: If a prime mover is not available, this test can also be performed by retardation
method, initiating the sudden short-circuit, when the decelerating machine passes
through nominal speed.
8/25/2005 9:02 a8/p8 © VA TECH HYDRO Page 2 of 4
- Supply small field current and then initiate a trial run of the sudden short-circuit test.
Verify that recorders are triggered and all signals are recorded properly.
- Adjust the excitation to the desired value of the terminal voltage.
Note: The usual test voltage is approx. 0.5 Un. The test may be repeated at various open
circuit voltages as required by the contract. For voltages exceeding this limit value,
explicit agreement of the turbine manufacturer should be reached. Through the machine
set must withstand the short-circuit forces, there is a high risk of damages to the
foundation (especially in case of bulb-type generators). Therefore it is not recommended
to perform a 100% Un sudden short-circuit directly at all stator terminals. Consider that
machine life endurance may be reduced.
- Read off the terminal voltage, frequency and field current immediately before
performing the sudden short circuit test. If still free channels are available on the digital
storage oscilloscope, at least the phase-to-phase voltage of the generator should be
recorded by oscilloscope.
- Close the circuit breaker in order to initiate the sudden short-circuits. Recording
instruments will be triggered and the three armature currents, the field current and the
voltage going to zero should be recorded continuously.
- After approx. 10 sec. record the armature currents manually, then switch off the
excitation and open the circuit breaker.
- Check the recordings in order to ensure that the data was registrated correctly.
Performed by: GP-QS1
5.3 Evaluation of the test
- Mathematical evaluation acc. to IEC-standard.
Note: Since the sudden short-circuit test is mainly performed with reduced voltages, in
general only unsaturated values for the reactance’s can be determined. Saturated
values should be estimated from the calculation values.
- The evaluation of analog short-circuit current characteristics can only be done by hand.
- Digital storage data may be computer evaluated, using a special program for
separating the envelope of the current waveform into 2 exponential functions.
- If a 100% Un sudden short-circuit is performed at the generator terminals (only after
agreement with the customer), despite of the prohibitive aspects mentioned, thorough
visual inspection for cracks, permanent deformations and any other damages shall be
made after the test.
e.g.:
- End winding support
- Condition of winding (ties, spacers …)
- Condition of foundation
- Foundation bolts
- Assembly and fixation of rotor components
- Acc. to international standards, a repetition of the voltage test, preferably 80% of test
voltage, are recommended.
8/25/2005 9:02 a8/p8 © VA TECH HYDRO Page 3 of 4
6 Proceeding in case of deviations
Any nominal value, minimum value, maximum value, tolerance etc. given in an
instruction is intended to serve for quality purposes only. In case of deviations, a non-
conformity report has to be written acc. to PNG Power Standard
7 Copyright
This Document is properly of PNG Power internal use only and must neither be copied.
Neither is it to be handed over nor in other way communicated to a third party.
Infringement will lead to prosecution.
8/25/2005 9:02 a8/p8 © VA TECH HYDRO Page 4 of 4

More Related Content

What's hot

Transient overvoltages and currents: mitigation and protection techniques
Transient overvoltages and currents: mitigation and protection techniquesTransient overvoltages and currents: mitigation and protection techniques
Transient overvoltages and currents: mitigation and protection techniquesBruno De Wachter
 
Control of dc drives
Control of dc drivesControl of dc drives
Control of dc drivesKeval Patel
 
Calibration & Testing of Electronic Meters
Calibration & Testing of Electronic MetersCalibration & Testing of Electronic Meters
Calibration & Testing of Electronic MetersSnehpal Singh
 
Introduction to power transformers
Introduction to power transformersIntroduction to power transformers
Introduction to power transformersLeonardo ENERGY
 
Electronics measurement and instrumentation ppt
Electronics measurement and instrumentation pptElectronics measurement and instrumentation ppt
Electronics measurement and instrumentation pptImranAhmad225
 
Pulse width modulated inverter
Pulse width modulated inverterPulse width modulated inverter
Pulse width modulated inverterVSRAGHU
 
Permanent Magnet Moving Coil
Permanent Magnet Moving Coil Permanent Magnet Moving Coil
Permanent Magnet Moving Coil Chandan Singh
 
An Overview Of Agbami Fpso Electrical Power System
An Overview Of Agbami Fpso Electrical Power SystemAn Overview Of Agbami Fpso Electrical Power System
An Overview Of Agbami Fpso Electrical Power Systemvkmalik
 
Harmonics in power system
Harmonics in power systemHarmonics in power system
Harmonics in power systemMinh Anh Nguyen
 
Power Quality and Monitoring
Power Quality and MonitoringPower Quality and Monitoring
Power Quality and Monitoringash08031996
 
transformer protection
transformer protection transformer protection
transformer protection jason adidela
 
Basics of Sensors & Transducers
Basics of Sensors & TransducersBasics of Sensors & Transducers
Basics of Sensors & TransducersBurdwan University
 
sub-station training report
sub-station training reportsub-station training report
sub-station training reportsitesh95074
 
harmonic distortion ppt
harmonic distortion pptharmonic distortion ppt
harmonic distortion pptAditi Tiwari
 
Vacuum Circuit Breakers Testing Methods
Vacuum Circuit Breakers Testing MethodsVacuum Circuit Breakers Testing Methods
Vacuum Circuit Breakers Testing MethodsAli Sepehri
 

What's hot (20)

Transient overvoltages and currents: mitigation and protection techniques
Transient overvoltages and currents: mitigation and protection techniquesTransient overvoltages and currents: mitigation and protection techniques
Transient overvoltages and currents: mitigation and protection techniques
 
Control of dc drives
Control of dc drivesControl of dc drives
Control of dc drives
 
Surge Protection
Surge ProtectionSurge Protection
Surge Protection
 
Calibration & Testing of Electronic Meters
Calibration & Testing of Electronic MetersCalibration & Testing of Electronic Meters
Calibration & Testing of Electronic Meters
 
Introduction to power transformers
Introduction to power transformersIntroduction to power transformers
Introduction to power transformers
 
Alternator
AlternatorAlternator
Alternator
 
Testing of transformer
Testing of transformerTesting of transformer
Testing of transformer
 
Electronics measurement and instrumentation ppt
Electronics measurement and instrumentation pptElectronics measurement and instrumentation ppt
Electronics measurement and instrumentation ppt
 
Pulse width modulated inverter
Pulse width modulated inverterPulse width modulated inverter
Pulse width modulated inverter
 
Permanent Magnet Moving Coil
Permanent Magnet Moving Coil Permanent Magnet Moving Coil
Permanent Magnet Moving Coil
 
An Overview Of Agbami Fpso Electrical Power System
An Overview Of Agbami Fpso Electrical Power SystemAn Overview Of Agbami Fpso Electrical Power System
An Overview Of Agbami Fpso Electrical Power System
 
Harmonics in power system
Harmonics in power systemHarmonics in power system
Harmonics in power system
 
CIRCUIT BREAKERS
CIRCUIT BREAKERSCIRCUIT BREAKERS
CIRCUIT BREAKERS
 
Power Quality and Monitoring
Power Quality and MonitoringPower Quality and Monitoring
Power Quality and Monitoring
 
Lightening Arrester.pptx
Lightening Arrester.pptxLightening Arrester.pptx
Lightening Arrester.pptx
 
transformer protection
transformer protection transformer protection
transformer protection
 
Basics of Sensors & Transducers
Basics of Sensors & TransducersBasics of Sensors & Transducers
Basics of Sensors & Transducers
 
sub-station training report
sub-station training reportsub-station training report
sub-station training report
 
harmonic distortion ppt
harmonic distortion pptharmonic distortion ppt
harmonic distortion ppt
 
Vacuum Circuit Breakers Testing Methods
Vacuum Circuit Breakers Testing MethodsVacuum Circuit Breakers Testing Methods
Vacuum Circuit Breakers Testing Methods
 

Viewers also liked

Sustained three phase short-circuit test and overcurrent test
Sustained three phase short-circuit test and overcurrent testSustained three phase short-circuit test and overcurrent test
Sustained three phase short-circuit test and overcurrent testDonald Stephen
 
Deep bar n double cage rotors
Deep bar n double cage rotorsDeep bar n double cage rotors
Deep bar n double cage rotorsManish Sahu
 
Mobile Gaming: Corona SDK & Adobe AIR RIA Unleashed 2011
Mobile Gaming: Corona SDK & Adobe AIR RIA Unleashed 2011Mobile Gaming: Corona SDK & Adobe AIR RIA Unleashed 2011
Mobile Gaming: Corona SDK & Adobe AIR RIA Unleashed 2011Jesse Warden
 
Ee423 fault analysis_notes
Ee423  fault analysis_notesEe423  fault analysis_notes
Ee423 fault analysis_notesAcot Benard
 
Open circuit saturation test
Open circuit saturation testOpen circuit saturation test
Open circuit saturation testDonald Stephen
 
Corona presentation
Corona presentationCorona presentation
Corona presentationBriana Leigh
 
Electrical Heating 01 - 03
Electrical Heating 01 - 03Electrical Heating 01 - 03
Electrical Heating 01 - 03Vijay Raskar
 
Electrical power ecx3232 lab report
Electrical power ecx3232 lab reportElectrical power ecx3232 lab report
Electrical power ecx3232 lab reportSandun Perera
 
Unsymmetrical fault analysis 2003 final new 2007
Unsymmetrical fault analysis 2003 final new 2007Unsymmetrical fault analysis 2003 final new 2007
Unsymmetrical fault analysis 2003 final new 2007Viren Pandya
 
Corona effect, corona ring and any other topics
Corona effect, corona ring and any other topicsCorona effect, corona ring and any other topics
Corona effect, corona ring and any other topicsMithilesh Raj
 
Electrical Heating
Electrical HeatingElectrical Heating
Electrical Heatingpopet
 
Electrical Heating 01-03
Electrical Heating 01-03Electrical Heating 01-03
Electrical Heating 01-03Vijay Raskar
 
Series and parallel circuit
Series and parallel circuitSeries and parallel circuit
Series and parallel circuitNoman Rajput
 
Chapter 4 synchronous machine
Chapter 4 synchronous machineChapter 4 synchronous machine
Chapter 4 synchronous machinemkazree
 
Electrical machine lab
Electrical machine labElectrical machine lab
Electrical machine labDHEERAJ DHAKAR
 

Viewers also liked (20)

Sustained three phase short-circuit test and overcurrent test
Sustained three phase short-circuit test and overcurrent testSustained three phase short-circuit test and overcurrent test
Sustained three phase short-circuit test and overcurrent test
 
Deep bar n double cage rotors
Deep bar n double cage rotorsDeep bar n double cage rotors
Deep bar n double cage rotors
 
Mobile Gaming: Corona SDK & Adobe AIR RIA Unleashed 2011
Mobile Gaming: Corona SDK & Adobe AIR RIA Unleashed 2011Mobile Gaming: Corona SDK & Adobe AIR RIA Unleashed 2011
Mobile Gaming: Corona SDK & Adobe AIR RIA Unleashed 2011
 
Ee423 fault analysis_notes
Ee423  fault analysis_notesEe423  fault analysis_notes
Ee423 fault analysis_notes
 
Open circuit saturation test
Open circuit saturation testOpen circuit saturation test
Open circuit saturation test
 
Corona presentation
Corona presentationCorona presentation
Corona presentation
 
Corona1
Corona1Corona1
Corona1
 
Short circuit
Short circuit   Short circuit
Short circuit
 
Electrical Heating 01 - 03
Electrical Heating 01 - 03Electrical Heating 01 - 03
Electrical Heating 01 - 03
 
Seminar
SeminarSeminar
Seminar
 
Heating ppt
Heating pptHeating ppt
Heating ppt
 
Electrical power ecx3232 lab report
Electrical power ecx3232 lab reportElectrical power ecx3232 lab report
Electrical power ecx3232 lab report
 
Unsymmetrical fault analysis 2003 final new 2007
Unsymmetrical fault analysis 2003 final new 2007Unsymmetrical fault analysis 2003 final new 2007
Unsymmetrical fault analysis 2003 final new 2007
 
Corona effect, corona ring and any other topics
Corona effect, corona ring and any other topicsCorona effect, corona ring and any other topics
Corona effect, corona ring and any other topics
 
Protection of alternator
Protection of alternatorProtection of alternator
Protection of alternator
 
Electrical Heating
Electrical HeatingElectrical Heating
Electrical Heating
 
Electrical Heating 01-03
Electrical Heating 01-03Electrical Heating 01-03
Electrical Heating 01-03
 
Series and parallel circuit
Series and parallel circuitSeries and parallel circuit
Series and parallel circuit
 
Chapter 4 synchronous machine
Chapter 4 synchronous machineChapter 4 synchronous machine
Chapter 4 synchronous machine
 
Electrical machine lab
Electrical machine labElectrical machine lab
Electrical machine lab
 

Similar to Sudden three phase short-circuit test

Determination of the transient open circuit time constant
Determination of the transient open circuit time constantDetermination of the transient open circuit time constant
Determination of the transient open circuit time constantDonald Stephen
 
FOR AUTONICS IC.pdf
FOR AUTONICS IC.pdfFOR AUTONICS IC.pdf
FOR AUTONICS IC.pdfeShikhon
 
project presentation on "THMC"
project presentation on "THMC"project presentation on "THMC"
project presentation on "THMC"Teja venkat
 
Fed e-quick-start-up-guide-bientanfuji-dienhathe.com
Fed e-quick-start-up-guide-bientanfuji-dienhathe.comFed e-quick-start-up-guide-bientanfuji-dienhathe.com
Fed e-quick-start-up-guide-bientanfuji-dienhathe.comDien Ha The
 
10 - Ac Power Regulators & Control Power Transformers - Fuji Electric
10 - Ac Power Regulators & Control Power Transformers - Fuji Electric10 - Ac Power Regulators & Control Power Transformers - Fuji Electric
10 - Ac Power Regulators & Control Power Transformers - Fuji ElectricCTY TNHH HẠO PHƯƠNG
 
IRJET - Automated Monitoring Test Rig for Circuit Breaker Operation
IRJET -  	  Automated Monitoring Test Rig for Circuit Breaker OperationIRJET -  	  Automated Monitoring Test Rig for Circuit Breaker Operation
IRJET - Automated Monitoring Test Rig for Circuit Breaker OperationIRJET Journal
 
Power Quality Analyzer Kew 6315
Power Quality Analyzer Kew 6315Power Quality Analyzer Kew 6315
Power Quality Analyzer Kew 6315Kyoritsu India
 
Power Quality Analyzer Kew 6315
Power Quality Analyzer Kew 6315Power Quality Analyzer Kew 6315
Power Quality Analyzer Kew 6315Kyoritsu India
 
sharp_14mn10_ch_sn-000.pptx
sharp_14mn10_ch_sn-000.pptxsharp_14mn10_ch_sn-000.pptx
sharp_14mn10_ch_sn-000.pptxssuser27df19
 
The Intellectual Automated Substation
The Intellectual Automated SubstationThe Intellectual Automated Substation
The Intellectual Automated Substationijtsrd
 
Real time parameter estimation for power quality control and intelligent prot...
Real time parameter estimation for power quality control and intelligent prot...Real time parameter estimation for power quality control and intelligent prot...
Real time parameter estimation for power quality control and intelligent prot...EG TECHNOLOGIES
 
Hoja de datos lm 555 y configuraciones
Hoja de datos lm 555 y configuraciones Hoja de datos lm 555 y configuraciones
Hoja de datos lm 555 y configuraciones Marlon Torres
 
Resize bientanfuji-dienhathe.com
Resize bientanfuji-dienhathe.comResize bientanfuji-dienhathe.com
Resize bientanfuji-dienhathe.comDien Ha The
 
Ct2000 es manual_english_version_1[1].0
Ct2000 es manual_english_version_1[1].0Ct2000 es manual_english_version_1[1].0
Ct2000 es manual_english_version_1[1].0Toàn Huỳnh
 

Similar to Sudden three phase short-circuit test (20)

Determination of the transient open circuit time constant
Determination of the transient open circuit time constantDetermination of the transient open circuit time constant
Determination of the transient open circuit time constant
 
FOR AUTONICS IC.pdf
FOR AUTONICS IC.pdfFOR AUTONICS IC.pdf
FOR AUTONICS IC.pdf
 
project presentation on "THMC"
project presentation on "THMC"project presentation on "THMC"
project presentation on "THMC"
 
Abb lv breakers working with trip curves
Abb lv breakers working with trip curvesAbb lv breakers working with trip curves
Abb lv breakers working with trip curves
 
Hioki solution car_industry_ denkei
Hioki solution car_industry_ denkeiHioki solution car_industry_ denkei
Hioki solution car_industry_ denkei
 
Sharp 32 pulg 32c24
Sharp 32 pulg 32c24Sharp 32 pulg 32c24
Sharp 32 pulg 32c24
 
Fed e-quick-start-up-guide-bientanfuji-dienhathe.com
Fed e-quick-start-up-guide-bientanfuji-dienhathe.comFed e-quick-start-up-guide-bientanfuji-dienhathe.com
Fed e-quick-start-up-guide-bientanfuji-dienhathe.com
 
10 - Ac Power Regulators & Control Power Transformers - Fuji Electric
10 - Ac Power Regulators & Control Power Transformers - Fuji Electric10 - Ac Power Regulators & Control Power Transformers - Fuji Electric
10 - Ac Power Regulators & Control Power Transformers - Fuji Electric
 
IRJET - Automated Monitoring Test Rig for Circuit Breaker Operation
IRJET -  	  Automated Monitoring Test Rig for Circuit Breaker OperationIRJET -  	  Automated Monitoring Test Rig for Circuit Breaker Operation
IRJET - Automated Monitoring Test Rig for Circuit Breaker Operation
 
Unit 6 power quality
Unit 6 power qualityUnit 6 power quality
Unit 6 power quality
 
Power Quality Analyzer Kew 6315
Power Quality Analyzer Kew 6315Power Quality Analyzer Kew 6315
Power Quality Analyzer Kew 6315
 
Power Quality Analyzer Kew 6315
Power Quality Analyzer Kew 6315Power Quality Analyzer Kew 6315
Power Quality Analyzer Kew 6315
 
Catalog biến tần Inovance MD310
Catalog biến tần Inovance MD310Catalog biến tần Inovance MD310
Catalog biến tần Inovance MD310
 
sharp_14mn10_ch_sn-000.pptx
sharp_14mn10_ch_sn-000.pptxsharp_14mn10_ch_sn-000.pptx
sharp_14mn10_ch_sn-000.pptx
 
The Intellectual Automated Substation
The Intellectual Automated SubstationThe Intellectual Automated Substation
The Intellectual Automated Substation
 
Real time parameter estimation for power quality control and intelligent prot...
Real time parameter estimation for power quality control and intelligent prot...Real time parameter estimation for power quality control and intelligent prot...
Real time parameter estimation for power quality control and intelligent prot...
 
Hoja de datos lm 555 y configuraciones
Hoja de datos lm 555 y configuraciones Hoja de datos lm 555 y configuraciones
Hoja de datos lm 555 y configuraciones
 
lm555.pdf
lm555.pdflm555.pdf
lm555.pdf
 
Resize bientanfuji-dienhathe.com
Resize bientanfuji-dienhathe.comResize bientanfuji-dienhathe.com
Resize bientanfuji-dienhathe.com
 
Ct2000 es manual_english_version_1[1].0
Ct2000 es manual_english_version_1[1].0Ct2000 es manual_english_version_1[1].0
Ct2000 es manual_english_version_1[1].0
 

More from Donald Stephen

Tangent delta test report form
Tangent delta test report formTangent delta test report form
Tangent delta test report formDonald Stephen
 
Stator insulation test setup
Stator insulation test setupStator insulation test setup
Stator insulation test setupDonald Stephen
 
Stator core induction test
Stator core induction testStator core induction test
Stator core induction testDonald Stephen
 
Stator core compr test
Stator core compr testStator core compr test
Stator core compr testDonald Stephen
 
Rotor insul test setup
Rotor insul test setupRotor insul test setup
Rotor insul test setupDonald Stephen
 
Measurement of winding resistances
Measurement of winding resistancesMeasurement of winding resistances
Measurement of winding resistancesDonald Stephen
 
Measurement of shaft voltage and shaft current on machines with sleeve bearings
Measurement of shaft voltage and shaft current on machines with sleeve bearingsMeasurement of shaft voltage and shaft current on machines with sleeve bearings
Measurement of shaft voltage and shaft current on machines with sleeve bearingsDonald Stephen
 
Measurement of partial discharges
Measurement of partial dischargesMeasurement of partial discharges
Measurement of partial dischargesDonald Stephen
 
Loss tangent delta test
Loss tangent delta testLoss tangent delta test
Loss tangent delta testDonald Stephen
 
Line to-line sustained short-circuit test
Line to-line sustained short-circuit testLine to-line sustained short-circuit test
Line to-line sustained short-circuit testDonald Stephen
 
Insulation resistance testing
Insulation resistance testingInsulation resistance testing
Insulation resistance testingDonald Stephen
 
Insulation resistance test
Insulation resistance testInsulation resistance test
Insulation resistance testDonald Stephen
 
Impedance measurement of field windings
Impedance measurement of field windingsImpedance measurement of field windings
Impedance measurement of field windingsDonald Stephen
 
Efficiency determination on hydrogenerators by calorimetric method
Efficiency determination on hydrogenerators by calorimetric methodEfficiency determination on hydrogenerators by calorimetric method
Efficiency determination on hydrogenerators by calorimetric methodDonald Stephen
 
Determination of inertia by load rejection
Determination of inertia by load rejectionDetermination of inertia by load rejection
Determination of inertia by load rejectionDonald Stephen
 

More from Donald Stephen (20)

Tangent delta test report form
Tangent delta test report formTangent delta test report form
Tangent delta test report form
 
Stator insulation test setup
Stator insulation test setupStator insulation test setup
Stator insulation test setup
 
Stator core induction test
Stator core induction testStator core induction test
Stator core induction test
 
Stator core compr test
Stator core compr testStator core compr test
Stator core compr test
 
Rotor insul test setup
Rotor insul test setupRotor insul test setup
Rotor insul test setup
 
Noise measurement
Noise measurementNoise measurement
Noise measurement
 
Measurement of winding resistances
Measurement of winding resistancesMeasurement of winding resistances
Measurement of winding resistances
 
Measurement of shaft voltage and shaft current on machines with sleeve bearings
Measurement of shaft voltage and shaft current on machines with sleeve bearingsMeasurement of shaft voltage and shaft current on machines with sleeve bearings
Measurement of shaft voltage and shaft current on machines with sleeve bearings
 
Measurement of partial discharges
Measurement of partial dischargesMeasurement of partial discharges
Measurement of partial discharges
 
Loss tangent delta test
Loss tangent delta testLoss tangent delta test
Loss tangent delta test
 
Load test
Load testLoad test
Load test
 
Line to-line sustained short-circuit test
Line to-line sustained short-circuit testLine to-line sustained short-circuit test
Line to-line sustained short-circuit test
 
Insulation resistance testing
Insulation resistance testingInsulation resistance testing
Insulation resistance testing
 
Insulation resistance test
Insulation resistance testInsulation resistance test
Insulation resistance test
 
Impedance measurement of field windings
Impedance measurement of field windingsImpedance measurement of field windings
Impedance measurement of field windings
 
High potential test
High potential testHigh potential test
High potential test
 
Efficiency determination on hydrogenerators by calorimetric method
Efficiency determination on hydrogenerators by calorimetric methodEfficiency determination on hydrogenerators by calorimetric method
Efficiency determination on hydrogenerators by calorimetric method
 
Determination of inertia by load rejection
Determination of inertia by load rejectionDetermination of inertia by load rejection
Determination of inertia by load rejection
 
Crack monitor
Crack monitorCrack monitor
Crack monitor
 
Core deffect detector
Core deffect detectorCore deffect detector
Core deffect detector
 

Recently uploaded

Peek implant persentation - Copy (1).pdf
Peek implant persentation - Copy (1).pdfPeek implant persentation - Copy (1).pdf
Peek implant persentation - Copy (1).pdfAyahmorsy
 
Introduction to Machine Learning Unit-4 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-4 Notes for II-II Mechanical EngineeringIntroduction to Machine Learning Unit-4 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-4 Notes for II-II Mechanical EngineeringC Sai Kiran
 
一比一原版(UNK毕业证)内布拉斯加州立大学科尼分校毕业证成绩单
一比一原版(UNK毕业证)内布拉斯加州立大学科尼分校毕业证成绩单一比一原版(UNK毕业证)内布拉斯加州立大学科尼分校毕业证成绩单
一比一原版(UNK毕业证)内布拉斯加州立大学科尼分校毕业证成绩单tuuww
 
Research Methodolgy & Intellectual Property Rights Series 2
Research Methodolgy & Intellectual Property Rights Series 2Research Methodolgy & Intellectual Property Rights Series 2
Research Methodolgy & Intellectual Property Rights Series 2T.D. Shashikala
 
Paint shop management system project report.pdf
Paint shop management system project report.pdfPaint shop management system project report.pdf
Paint shop management system project report.pdfKamal Acharya
 
RM&IPR M4.pdfResearch Methodolgy & Intellectual Property Rights Series 4
RM&IPR M4.pdfResearch Methodolgy & Intellectual Property Rights Series 4RM&IPR M4.pdfResearch Methodolgy & Intellectual Property Rights Series 4
RM&IPR M4.pdfResearch Methodolgy & Intellectual Property Rights Series 4T.D. Shashikala
 
Natalia Rutkowska - BIM School Course in Kraków
Natalia Rutkowska - BIM School Course in KrakówNatalia Rutkowska - BIM School Course in Kraków
Natalia Rutkowska - BIM School Course in Krakówbim.edu.pl
 
Top 13 Famous Civil Engineering Scientist
Top 13 Famous Civil Engineering ScientistTop 13 Famous Civil Engineering Scientist
Top 13 Famous Civil Engineering Scientistgettygaming1
 
Online resume builder management system project report.pdf
Online resume builder management system project report.pdfOnline resume builder management system project report.pdf
Online resume builder management system project report.pdfKamal Acharya
 
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical EngineeringIntroduction to Machine Learning Unit-5 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical EngineeringC Sai Kiran
 
İTÜ CAD and Reverse Engineering Workshop
İTÜ CAD and Reverse Engineering WorkshopİTÜ CAD and Reverse Engineering Workshop
İTÜ CAD and Reverse Engineering WorkshopEmre Günaydın
 
Digital Signal Processing Lecture notes n.pdf
Digital Signal Processing Lecture notes n.pdfDigital Signal Processing Lecture notes n.pdf
Digital Signal Processing Lecture notes n.pdfAbrahamGadissa
 
Dairy management system project report..pdf
Dairy management system project report..pdfDairy management system project report..pdf
Dairy management system project report..pdfKamal Acharya
 
Software Engineering - Modelling Concepts + Class Modelling + Building the An...
Software Engineering - Modelling Concepts + Class Modelling + Building the An...Software Engineering - Modelling Concepts + Class Modelling + Building the An...
Software Engineering - Modelling Concepts + Class Modelling + Building the An...Prakhyath Rai
 
Laundry management system project report.pdf
Laundry management system project report.pdfLaundry management system project report.pdf
Laundry management system project report.pdfKamal Acharya
 
Electrical shop management system project report.pdf
Electrical shop management system project report.pdfElectrical shop management system project report.pdf
Electrical shop management system project report.pdfKamal Acharya
 
Activity Planning: Objectives, Project Schedule, Network Planning Model. Time...
Activity Planning: Objectives, Project Schedule, Network Planning Model. Time...Activity Planning: Objectives, Project Schedule, Network Planning Model. Time...
Activity Planning: Objectives, Project Schedule, Network Planning Model. Time...Lovely Professional University
 
KIT-601 Lecture Notes-UNIT-4.pdf Frequent Itemsets and Clustering
KIT-601 Lecture Notes-UNIT-4.pdf Frequent Itemsets and ClusteringKIT-601 Lecture Notes-UNIT-4.pdf Frequent Itemsets and Clustering
KIT-601 Lecture Notes-UNIT-4.pdf Frequent Itemsets and ClusteringDr. Radhey Shyam
 
ONLINE CAR SERVICING SYSTEM PROJECT REPORT.pdf
ONLINE CAR SERVICING SYSTEM PROJECT REPORT.pdfONLINE CAR SERVICING SYSTEM PROJECT REPORT.pdf
ONLINE CAR SERVICING SYSTEM PROJECT REPORT.pdfKamal Acharya
 
Lect 2 - Design of slender column-2.pptx
Lect 2 - Design of slender column-2.pptxLect 2 - Design of slender column-2.pptx
Lect 2 - Design of slender column-2.pptxHamzaKhawar4
 

Recently uploaded (20)

Peek implant persentation - Copy (1).pdf
Peek implant persentation - Copy (1).pdfPeek implant persentation - Copy (1).pdf
Peek implant persentation - Copy (1).pdf
 
Introduction to Machine Learning Unit-4 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-4 Notes for II-II Mechanical EngineeringIntroduction to Machine Learning Unit-4 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-4 Notes for II-II Mechanical Engineering
 
一比一原版(UNK毕业证)内布拉斯加州立大学科尼分校毕业证成绩单
一比一原版(UNK毕业证)内布拉斯加州立大学科尼分校毕业证成绩单一比一原版(UNK毕业证)内布拉斯加州立大学科尼分校毕业证成绩单
一比一原版(UNK毕业证)内布拉斯加州立大学科尼分校毕业证成绩单
 
Research Methodolgy & Intellectual Property Rights Series 2
Research Methodolgy & Intellectual Property Rights Series 2Research Methodolgy & Intellectual Property Rights Series 2
Research Methodolgy & Intellectual Property Rights Series 2
 
Paint shop management system project report.pdf
Paint shop management system project report.pdfPaint shop management system project report.pdf
Paint shop management system project report.pdf
 
RM&IPR M4.pdfResearch Methodolgy & Intellectual Property Rights Series 4
RM&IPR M4.pdfResearch Methodolgy & Intellectual Property Rights Series 4RM&IPR M4.pdfResearch Methodolgy & Intellectual Property Rights Series 4
RM&IPR M4.pdfResearch Methodolgy & Intellectual Property Rights Series 4
 
Natalia Rutkowska - BIM School Course in Kraków
Natalia Rutkowska - BIM School Course in KrakówNatalia Rutkowska - BIM School Course in Kraków
Natalia Rutkowska - BIM School Course in Kraków
 
Top 13 Famous Civil Engineering Scientist
Top 13 Famous Civil Engineering ScientistTop 13 Famous Civil Engineering Scientist
Top 13 Famous Civil Engineering Scientist
 
Online resume builder management system project report.pdf
Online resume builder management system project report.pdfOnline resume builder management system project report.pdf
Online resume builder management system project report.pdf
 
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical EngineeringIntroduction to Machine Learning Unit-5 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical Engineering
 
İTÜ CAD and Reverse Engineering Workshop
İTÜ CAD and Reverse Engineering WorkshopİTÜ CAD and Reverse Engineering Workshop
İTÜ CAD and Reverse Engineering Workshop
 
Digital Signal Processing Lecture notes n.pdf
Digital Signal Processing Lecture notes n.pdfDigital Signal Processing Lecture notes n.pdf
Digital Signal Processing Lecture notes n.pdf
 
Dairy management system project report..pdf
Dairy management system project report..pdfDairy management system project report..pdf
Dairy management system project report..pdf
 
Software Engineering - Modelling Concepts + Class Modelling + Building the An...
Software Engineering - Modelling Concepts + Class Modelling + Building the An...Software Engineering - Modelling Concepts + Class Modelling + Building the An...
Software Engineering - Modelling Concepts + Class Modelling + Building the An...
 
Laundry management system project report.pdf
Laundry management system project report.pdfLaundry management system project report.pdf
Laundry management system project report.pdf
 
Electrical shop management system project report.pdf
Electrical shop management system project report.pdfElectrical shop management system project report.pdf
Electrical shop management system project report.pdf
 
Activity Planning: Objectives, Project Schedule, Network Planning Model. Time...
Activity Planning: Objectives, Project Schedule, Network Planning Model. Time...Activity Planning: Objectives, Project Schedule, Network Planning Model. Time...
Activity Planning: Objectives, Project Schedule, Network Planning Model. Time...
 
KIT-601 Lecture Notes-UNIT-4.pdf Frequent Itemsets and Clustering
KIT-601 Lecture Notes-UNIT-4.pdf Frequent Itemsets and ClusteringKIT-601 Lecture Notes-UNIT-4.pdf Frequent Itemsets and Clustering
KIT-601 Lecture Notes-UNIT-4.pdf Frequent Itemsets and Clustering
 
ONLINE CAR SERVICING SYSTEM PROJECT REPORT.pdf
ONLINE CAR SERVICING SYSTEM PROJECT REPORT.pdfONLINE CAR SERVICING SYSTEM PROJECT REPORT.pdf
ONLINE CAR SERVICING SYSTEM PROJECT REPORT.pdf
 
Lect 2 - Design of slender column-2.pptx
Lect 2 - Design of slender column-2.pptxLect 2 - Design of slender column-2.pptx
Lect 2 - Design of slender column-2.pptx
 

Sudden three phase short-circuit test

  • 1. Sudden three phase short circuit test Table of Content: 1 Objective.......................................................................................................... 2 Scope............................................................................................................... 3 Referenced documents.................................................................................... 4 Terms and abbreviations.................................................................................. 5 Sudden three-phase short-circuit test............................................................... 5.1 Preparations................................................................................................... 5.2 Conduction of test.......................................................................................... 5.3 Evaluation of the test...................................................................................... 6 Proceeding in case of deviations ...................................................................... 7 Copyright............................................................................................................ 1 Objective The sudden three-phase short-circuit test is performed to determine the following machine quantities: - Direct-axis transient reactance Xd' - Direct-axis subtransient reactance Xd" - Direct-axis transient short-circuit time constant Td' - Direct-axis subtransient short-circuit time constant Td" - Armature short-circuit time constant Ta. - Evidence of mechanical strength 2 Scope This procedure applies to all types of synchronous machines during final inspections at site or in the workshop. 3 Referenced documents IEC 34-4, 40-41 Rotating electrical machines – Methods for determining Synchronous machine quantities from tests IEEE 115, 11.7 Test Procedures for synchronous machines EN 60034-4 Rotating electrical machines - Methods for determining Synchronous machine quantities from tests 4 Terms and abbreviations none 5 Sudden three-phase short-circuit test 5.1 Preparations Visual inspections: - End winding supports - Condition of foundation - Are the foundation bolts tightened? 8/25/2005 9:02 a8/p8 © VA TECH HYDRO Page 1 of 4
  • 2. - Correct assembly and fixation of all rotor components - Disconnect the line terminals from the terminal buses (may not be necessary in all cases). - Connect the power cable between the line terminals and the circuit breaker, which is used to make the short-circuit and install measuring devices for recording the short- circuit currents in wye-connection. Note: Normally the plant circuit breaker will be used for this purpose. To install a separate short-circuit breaker in the plant requires high efforts and good coordination between the user of the plant and the generator manufacturer, as well as considerable extra costs. In the workshop a special short-circuit breaker with synchronized phases is used. The short circuit itself can be made with a special bar across the terminal buses or a disconnector installed in the current leads (e.g. braking disconnector). This is placed after the circuit breaker and is inserted before switching in the circuit breaker. Consider that it is designed to support the current forces and can carry the substained short circuit current during the recording time. - For current transformation the following equipment may be alternatively used: - Linearized current transformers - Low inductance precision shunts - Unlock protection relays as required. - Remove the grounding cable of the neutral terminals and directly connect the common terminal of the three-phase short-circuit wye to ground. - Attach a voltmeter and potential transformer to the generator line terminals (if required) to measure the armature voltage prior to the sudden short-circuit. - Connect and set the precision instruments for measuring the terminal voltage and field current. Note: The following analog- or digital instruments or equivalent (at least 4 channels) may be used for recording purposes: - Digital storage oscilloscope (Hioki 8855) - Memory Recorder (YEW AR 1100 A) - Memory Recorder (YEW DL 708) - Connect the output signals of the current transformer (CT) or equivalent to the recorder, whereby the current signal of the CT is converted into a voltage signal required for the digital storage oscilloscope using precision shunts. - Calibrate and set the trigger of the recording instruments to the expected levels. 5.2 Conduction of test - Operate the unit at rated speed in no-load condition with the manual control of the excitation system. In case of static excitation set the ignition anlge of the gate trigger pulse to achieve the required generator voltage. Neither a current regulator (for the field current) nor a voltage regulator (for the generator voltage) may be switched on. Note: If a prime mover is not available, this test can also be performed by retardation method, initiating the sudden short-circuit, when the decelerating machine passes through nominal speed. 8/25/2005 9:02 a8/p8 © VA TECH HYDRO Page 2 of 4
  • 3. - Supply small field current and then initiate a trial run of the sudden short-circuit test. Verify that recorders are triggered and all signals are recorded properly. - Adjust the excitation to the desired value of the terminal voltage. Note: The usual test voltage is approx. 0.5 Un. The test may be repeated at various open circuit voltages as required by the contract. For voltages exceeding this limit value, explicit agreement of the turbine manufacturer should be reached. Through the machine set must withstand the short-circuit forces, there is a high risk of damages to the foundation (especially in case of bulb-type generators). Therefore it is not recommended to perform a 100% Un sudden short-circuit directly at all stator terminals. Consider that machine life endurance may be reduced. - Read off the terminal voltage, frequency and field current immediately before performing the sudden short circuit test. If still free channels are available on the digital storage oscilloscope, at least the phase-to-phase voltage of the generator should be recorded by oscilloscope. - Close the circuit breaker in order to initiate the sudden short-circuits. Recording instruments will be triggered and the three armature currents, the field current and the voltage going to zero should be recorded continuously. - After approx. 10 sec. record the armature currents manually, then switch off the excitation and open the circuit breaker. - Check the recordings in order to ensure that the data was registrated correctly. Performed by: GP-QS1 5.3 Evaluation of the test - Mathematical evaluation acc. to IEC-standard. Note: Since the sudden short-circuit test is mainly performed with reduced voltages, in general only unsaturated values for the reactance’s can be determined. Saturated values should be estimated from the calculation values. - The evaluation of analog short-circuit current characteristics can only be done by hand. - Digital storage data may be computer evaluated, using a special program for separating the envelope of the current waveform into 2 exponential functions. - If a 100% Un sudden short-circuit is performed at the generator terminals (only after agreement with the customer), despite of the prohibitive aspects mentioned, thorough visual inspection for cracks, permanent deformations and any other damages shall be made after the test. e.g.: - End winding support - Condition of winding (ties, spacers …) - Condition of foundation - Foundation bolts - Assembly and fixation of rotor components - Acc. to international standards, a repetition of the voltage test, preferably 80% of test voltage, are recommended. 8/25/2005 9:02 a8/p8 © VA TECH HYDRO Page 3 of 4
  • 4. 6 Proceeding in case of deviations Any nominal value, minimum value, maximum value, tolerance etc. given in an instruction is intended to serve for quality purposes only. In case of deviations, a non- conformity report has to be written acc. to PNG Power Standard 7 Copyright This Document is properly of PNG Power internal use only and must neither be copied. Neither is it to be handed over nor in other way communicated to a third party. Infringement will lead to prosecution. 8/25/2005 9:02 a8/p8 © VA TECH HYDRO Page 4 of 4