ASSIGNMENT ON CASE STUDY OF

Supplier Evaluation &
Selection
SUBJECT: SOURCING MANAGEMENT

INTERNATIONAL SUPPLY CHAIN EDUCATION ALLIANCE (ISCEA)
DHAKA, BANGLADESH
JANUARY- 2014
Supplier Evaluation & Selection, Report By: Emdadul Huq, Roll # 007, Batch # 7, PGDSCM, ISCEA
Submitted To:
Mr. Mirza Muhammad Masud Rana,
Instructor, Sourcing Management
PGDSCM, ISCEA

Submitted by:

Emdadul Huq,
Roll – 007, BATCH - 7, PGDSCM, ISCEA

Supplier Evaluation & Selection, Report By: Emdadul Huq, Roll # 007, Batch # 7, PGDSCM, ISCEA
REPORT AT A GLANCE

1. IMPORTANT FACTS OF THE CASE
A. Strength of FTC
B. Product Expansion Plan
C. Pricing Plan
D. Quality Of Products

2. KEY ISSUES OF THE CASE
A. Outsourcing & Strategic Plan

3. ALTERNATIVE COURSES OF ACTION
A. Options to Outsourcing
B. Price Comparison of Four Supplier

4. EVALUATE EACH COURSES OF ACTION
A. Financial Risk Analysis
B. Total Cost Analysis
C. Supplier Evaluation & Selection Analysis

5. RECOMANDATION

Supplier Evaluation & Selection, Report By: Emdadul Huq, Roll # 007, Batch # 7, PGDSCM, ISCEA
1. IMPORTANT FACTS OF THE CASE
A. STRANGTH OF FTC
Fastraq Technology Corporation is a medium sized (growing) high
technology company
FTC produces component parts & subsystems for PC &
Engineering workstation.
The company recognized as well-established component &
subsystem manufacturer.
FTC has good reputation for high quality product & on time
delivery

Supplier Evaluation & Selection, Report By: Emdadul # 7, PGDSCM, ISCEA 7, PGDSCM, ISCEA
EMDADUL HUQ, ROLL # 007, BATCH Huq, Roll # 007, Batch #
1. IMPORTANT FACTS OF THE CASE
B. PRODUCT EXPANSION PLAN
FTC has decided to expend its product line to include fully
assembled personal computer (PC).
FTC has pursued an aggressive strategy of selling high quality
computer at affordable price.
The new line of computers, called 9000x series
FTC plan direct ship to customer as orders are received (maketo-order)
FTC will assembles the computers in its own facilities

Supplier Evaluation & Selection, Report By: Emdadul Huq, Roll # 007, Batch # 7, PGDSCM, ISCEA
1. IMPORTANT FACTS OF THE CASE
C. PRICING PLAN
FTC is targeting the price of its PC line from $1100-$1700 depending
on model & configuration.
Targeted DVD price within the range of $115-135.
Recent trends indicate that this level of pricing over extended
period would be difficult.
FTC call for redefining value in an economy where the cost of raw
technology is plummeting toward zero

Supplier Evaluation & Selection, Report By: Emdadul Huq, Roll # 007, Batch # 7, PGDSCM, ISCEA
1. IMPORTANT FACTS OF THE CASE
D. QUALITY OF PRODUCTS
Customers demand is defect free computers
Poor quality of products adversely affects market reputation &
future sales.
FTC committed to supply high quality product by offering to
take defects products/service back/redressing of complain etc.
FTC financial & quality analyst calculate on average
nonconforming cost is 375 per unit of pc (including lost goodwill)

Supplier Evaluation & Selection, Report By: Emdadul Huq, Roll # 007, Batch # 7, PGDSCM, ISCEA
2. KEY ISSUES OF THE CASE
A. OUTSOURCING & STRATEGIC PLAN
FTC intent to outsource some component and subassemblies, i.e.
DVD Drive
Because DVD production capacities beyond the FTC current
expertise.
FTC plans in early January to another new line of computers
directly to marketplace in August 2004
It must have inventory by June to begin providing & pilot
production.
FTC relies cross functional commodity team to develop sourcing
strategy for key purchase items
Executive management’s views DVD supplier selection decision is
critical part of 9000x series development.

Supplier Evaluation & Selection, Report By: Emdadul Huq, Roll # 007, Batch # 7, PGDSCM, ISCEA
Material Requirement Planning based on Lead Time
3. ALTERNATIVE COURSES OF ACTION

A. OPTIONS TO OUTSOURCING
FTC ask to supplier “ Request for Proposal.
Six suppliers respond to the commodity team’s Request for
Proposal.
The commodity team spent the last several weeks visiting 4
DVD suppliers and evaluation various supply options
A review of these proposal revealed the four supplier out of
six where cost competitive given FTC initial target cost.
Among four suppliers two suppliers is United States & Two are
Asia region (Korea & Japan)
Name of the suppliers
Advance Technologies
Drivetech Company
D-Drive Systems
Parksoo Technologies

Supplier Evaluation & Selection, Report By: Emdadul Huq, Roll # 007, Batch # 7, PGDSCM, ISCEA
3. ALTERNATIVE COURSES OF ACTION
B. PRICE COMPARISON OF FOUR SUPPLIERS
Name of Suppliers
Parameters

Advance Tech

Drivetech

D-Drive

Parksoo

Quoted Price

128

141

137

130

8 Week

3 Week

2 Week

8-10 Week

95%

97%

99%

99%

9300 ppmd

9950 ppmd

7200 ppmd

3000 ppmd

17.50

6.10

14

20

98%

93%

95%

93%

9

0

0

9.5

2.5

1.5

3

3.5

Freq of Shipment

Monthly

Weekly

Every day

Monthly

Tooling Cost

2.25/mill

2.75/mill

2.25/mill

2.20/mill

Ordering Cost

4.75

4

3.25

2.25

Ramp-up Time

4 months

5 months

3 months

4 months

Yen

Dollar

Dollar

Dollar

Lead Time
On time delivery record
Quality
Transport Cost
Capacity
Duties & customs
Insurance

Currency

Supplier Evaluation & Selection, Report By: Emdadul Huq, Roll # 007, Batch # 7, PGDSCM, ISCEA
4. EVALUATE EACH COURSES OF ACTION
A. FINANCIAL RISK ANALYSIS
Current Ratio Analysis:
Suppliers

Current Assts

Current Liabilities

Current Ratio

Advanced

2165.10

1780.60

1.216

DriveTech

164.00

122.50

1.339

D-Drive

735.00

545.00

1.349

Parksoo

391.90

347.00

1.129

Quick (Acid Test) Ratio Analysis:
Suppliers

(Cash+ Marketable Securities+
Receivables)

Current Liabilities

Quick (Acid
Test)

Advanced

1107.40

1780.60

0.622

DriveTech

89.00

122.50

0.727

D-Drive

570.00

545.00

1.046

Parksoo

256.50

347.00

0.739

In ratio analysis D-Drive shows lowest financial risk

Supplier Evaluation & Selection, Report By: Emdadul # 7, PGDSCM, ISCEA 7, PGDSCM, ISCEA
EMDADUL HUQ, ROLL # 007, BATCH Huq, Roll # 007, Batch #
4. EVALUATE EACH COURSES OF ACTION
B. TOTAL COST ANALYSIS
Yearly Demand= 500000 Unit, Avg Weekly Demand: 500000/52 week= 10,000 Unit (Round up)
Lead
Time
(Week
)

Re-Order
Level
(LXD)

Unit
Price

Holding
Cost/Uni
t (25%)

Ordering
Cost/Uni
t (Fixed)

Annual
Holding
Cost

Annual
Ordering
Cost

Total Annual
Cost

Advance
Te

8

80,000.00

128

32.0

34

1,280,000

211

65,280,211

Drivetec
h

3

30,000.00

141

35.3

12

528,750

193

71,028,943

D-Drive

2

20,000.00

137

34.3

20

342,500

506

68,843,006

Parksoo

9

90,000.00

130

32.5

35

1,462,500

196

66,462,696

Suppliers
Name

Supplier Evaluation & Selection, Report By: Emdadul Huq, Roll # 007, Batch # 7, PGDSCM, ISCEA
4. EVALUATE EACH COURSES OF ACTION
C. SUPPLIER EVALUATION & SELECTION ANALYSIS
Suppliers Name

Total Annual
Cost

Analysis & Findings

Advance Tech

65,280,211

Although Lowest Annual Cost but financial
condition is not so good and they are not
interested to sign less then 100 million

Drivetech

71,028,943

Annual Cost is High, Low Capacity; Ramp-up
time is high, although financial risk is
sustainable.

D-Drive

68,843,006

Annual cost is high but Convenient location
from FTC, lowest ramp-up time & Financial
condition is so good.

66,462,696

Although annual cost is 2nd lowest but Low
capacity, no experience to business with North
America

Parksoo

Supplier Evaluation & Selection, Report By: Emdadul # 7, PGDSCM, ISCEA 7, PGDSCM, ISCEA
EMDADUL HUQ, ROLL # 007, BATCH Huq, Roll # 007, Batch #
5. RECOMMANDATION

In the above total cost analysis The Advance Tech Company
annual cost is lowest but financial condition is not so good
and they are not interested to sign contract less then 100
million and FTC target is 75 million per year so best choice
would be D-Drive Systems.
Because of the following factors 1. Although annual cost is high but FTC can get corporatenegotiated rate discounts by supporting it inbound logistics.
2. Quality Concern: lowest defect parts per millions
3. Lead Time is lowest
4. On time delivery record is highest
5. Capacity is second highest
Continued…

Supplier Evaluation & Selection, Report By: Emdadul Huq, Roll # 007, Batch # 7, PGDSCM, ISCEA
5. RECOMMANDATION

6.Ram-up Time is lowest
7.Frequency of Shipment is every other day
8.Financial Risk is lowest.
9.D-Drive System 10 miles from FTC assembly facility
10.FTC not need to manage inventory and safety stock.
So Fastraq Technology Corporation can sign agreement with the
D-Drive Systems for outsource DVD Drive to catch the back to
school market without any risk .

Supplier Evaluation & Selection, Report By: Emdadul Huq, Roll # 007, Batch # 7, PGDSCM, ISCEA
THANK YOU

Supplier Evaluation & Selection, Report By: Emdadul Huq, Roll # 007, Batch # 7, PGDSCM, ISCEA

More Related Content

What's hot

Just In Time and Lean Management
Just In Time and Lean ManagementJust In Time and Lean Management
Just In Time and Lean Management
Ruhi Beri
 
Logistics outsourcing
Logistics outsourcingLogistics outsourcing
Logistics outsourcing
Marwan Bahgat
 
Logistics strategy & planning, Customer Service & Products
Logistics strategy & planning, Customer Service & ProductsLogistics strategy & planning, Customer Service & Products
Logistics strategy & planning, Customer Service & Products
Fahad Ali
 
Supplier selection
Supplier selectionSupplier selection
Supplier selection
joecobe
 

What's hot (20)

Total quality management and purchasing
Total quality management and purchasingTotal quality management and purchasing
Total quality management and purchasing
 
Components Of Logistics Management1
Components Of Logistics Management1Components Of Logistics Management1
Components Of Logistics Management1
 
SCM Outsourcing
SCM OutsourcingSCM Outsourcing
SCM Outsourcing
 
INTRODUCTION TO THE CONCEPT OF SOURCING
INTRODUCTION TO THE CONCEPT OF SOURCINGINTRODUCTION TO THE CONCEPT OF SOURCING
INTRODUCTION TO THE CONCEPT OF SOURCING
 
international sourcing
international sourcinginternational sourcing
international sourcing
 
MPC : Inventory control with case study of Dulux paints
MPC : Inventory control with case study of Dulux paintsMPC : Inventory control with case study of Dulux paints
MPC : Inventory control with case study of Dulux paints
 
Inventory and inventory management
Inventory and inventory managementInventory and inventory management
Inventory and inventory management
 
Purchase management
Purchase managementPurchase management
Purchase management
 
Suppliers selection in construction supply chain management
Suppliers selection in construction supply chain managementSuppliers selection in construction supply chain management
Suppliers selection in construction supply chain management
 
Just In Time and Lean Management
Just In Time and Lean ManagementJust In Time and Lean Management
Just In Time and Lean Management
 
Principles Of Logistics Management
Principles Of Logistics ManagementPrinciples Of Logistics Management
Principles Of Logistics Management
 
Supply Chain Management_Presentation
Supply Chain Management_PresentationSupply Chain Management_Presentation
Supply Chain Management_Presentation
 
WAREHOUSING MANAGEMENT
WAREHOUSING MANAGEMENTWAREHOUSING MANAGEMENT
WAREHOUSING MANAGEMENT
 
Logistics
LogisticsLogistics
Logistics
 
Lean Value Stream Mapping (VSM) Training Module
Lean Value Stream Mapping (VSM) Training ModuleLean Value Stream Mapping (VSM) Training Module
Lean Value Stream Mapping (VSM) Training Module
 
Logistics outsourcing
Logistics outsourcingLogistics outsourcing
Logistics outsourcing
 
Logistics strategy & planning, Customer Service & Products
Logistics strategy & planning, Customer Service & ProductsLogistics strategy & planning, Customer Service & Products
Logistics strategy & planning, Customer Service & Products
 
Six sigma awareness
Six sigma awarenessSix sigma awareness
Six sigma awareness
 
Supplier evaluation and selection
Supplier evaluation and selectionSupplier evaluation and selection
Supplier evaluation and selection
 
Supplier selection
Supplier selectionSupplier selection
Supplier selection
 

Viewers also liked

Supplier evaluation & selection
Supplier evaluation & selectionSupplier evaluation & selection
Supplier evaluation & selection
Ankit
 
Supplier evaluation criteria
Supplier evaluation criteriaSupplier evaluation criteria
Supplier evaluation criteria
Art Acosta
 
Asbo Vendor Performance Eval Chicago 092509
Asbo Vendor Performance Eval   Chicago   092509Asbo Vendor Performance Eval   Chicago   092509
Asbo Vendor Performance Eval Chicago 092509
Richard Gay, CPPO, RSBO
 
Vendor Management Systems Best Practices
Vendor Management Systems Best PracticesVendor Management Systems Best Practices
Vendor Management Systems Best Practices
jeffmonaghan
 
Green Supply Chain Management
Green Supply Chain ManagementGreen Supply Chain Management
Green Supply Chain Management
Sandip Kadam
 

Viewers also liked (20)

SUPPLIER SELECTION AND EVALUATION
SUPPLIER SELECTION AND EVALUATIONSUPPLIER SELECTION AND EVALUATION
SUPPLIER SELECTION AND EVALUATION
 
Supplier evaluation & selection
Supplier evaluation & selectionSupplier evaluation & selection
Supplier evaluation & selection
 
Consumer Behaviour: Supplier Evaluation Selection
Consumer Behaviour:   Supplier Evaluation Selection Consumer Behaviour:   Supplier Evaluation Selection
Consumer Behaviour: Supplier Evaluation Selection
 
Supplier evaluation criteria
Supplier evaluation criteriaSupplier evaluation criteria
Supplier evaluation criteria
 
Vendor rating system
Vendor rating systemVendor rating system
Vendor rating system
 
A Supplier Selection Criteria Using Boolean Association Rule Mining
A Supplier Selection Criteria Using Boolean Association Rule MiningA Supplier Selection Criteria Using Boolean Association Rule Mining
A Supplier Selection Criteria Using Boolean Association Rule Mining
 
test
testtest
test
 
Supplier selection process of Merk
Supplier selection process of MerkSupplier selection process of Merk
Supplier selection process of Merk
 
Ch18
Ch18Ch18
Ch18
 
Asbo Vendor Performance Eval Chicago 092509
Asbo Vendor Performance Eval   Chicago   092509Asbo Vendor Performance Eval   Chicago   092509
Asbo Vendor Performance Eval Chicago 092509
 
LEED & Green Materials
LEED & Green MaterialsLEED & Green Materials
LEED & Green Materials
 
Supplier Selection
Supplier SelectionSupplier Selection
Supplier Selection
 
Vendor/Supplier rating
Vendor/Supplier ratingVendor/Supplier rating
Vendor/Supplier rating
 
Green supply chain management
Green supply chain management Green supply chain management
Green supply chain management
 
Vendor Management Systems Best Practices
Vendor Management Systems Best PracticesVendor Management Systems Best Practices
Vendor Management Systems Best Practices
 
Vendor rating
Vendor ratingVendor rating
Vendor rating
 
Value analysis
Value analysisValue analysis
Value analysis
 
Purchase management
Purchase managementPurchase management
Purchase management
 
Vendor Management
Vendor ManagementVendor Management
Vendor Management
 
Green Supply Chain Management
Green Supply Chain ManagementGreen Supply Chain Management
Green Supply Chain Management
 

Similar to Supplier Evaluation & Selection

Supply Chain Presentation BIPL.
Supply Chain Presentation BIPL.Supply Chain Presentation BIPL.
Supply Chain Presentation BIPL.
Farrukh Hasnain
 
Tendering process CVC guidelines-converted.pptx
Tendering process CVC guidelines-converted.pptxTendering process CVC guidelines-converted.pptx
Tendering process CVC guidelines-converted.pptx
AshishMishra416872
 
CV_Maricel Molina rev 1
CV_Maricel Molina rev 1CV_Maricel Molina rev 1
CV_Maricel Molina rev 1
Maricel Molina
 

Similar to Supplier Evaluation & Selection (20)

China Case Study MRO Electrical Spare Parts
China Case Study MRO Electrical Spare PartsChina Case Study MRO Electrical Spare Parts
China Case Study MRO Electrical Spare Parts
 
Door Hardware Sourcing Case Study by Dragon Sourcing
Door Hardware Sourcing Case Study by Dragon SourcingDoor Hardware Sourcing Case Study by Dragon Sourcing
Door Hardware Sourcing Case Study by Dragon Sourcing
 
Basics of quality and seven qc tools
Basics of quality and seven qc toolsBasics of quality and seven qc tools
Basics of quality and seven qc tools
 
Management Repot
Management RepotManagement Repot
Management Repot
 
Multi Category Sourcing in China, India, Vietnam and Turkey
Multi Category Sourcing in China, India, Vietnam and TurkeyMulti Category Sourcing in China, India, Vietnam and Turkey
Multi Category Sourcing in China, India, Vietnam and Turkey
 
Construction categories case study
Construction categories case studyConstruction categories case study
Construction categories case study
 
Design of a Prevention, Appraisal and Failure Cost Model
Design of a Prevention, Appraisal and Failure Cost ModelDesign of a Prevention, Appraisal and Failure Cost Model
Design of a Prevention, Appraisal and Failure Cost Model
 
Case Study: Multi Category Sourcing in China, India, Vietnam and Turkey
Case Study: Multi Category Sourcing in China, India, Vietnam and TurkeyCase Study: Multi Category Sourcing in China, India, Vietnam and Turkey
Case Study: Multi Category Sourcing in China, India, Vietnam and Turkey
 
Supply Chain Presentation BIPL.
Supply Chain Presentation BIPL.Supply Chain Presentation BIPL.
Supply Chain Presentation BIPL.
 
Tendering process CVC guidelines-converted.pptx
Tendering process CVC guidelines-converted.pptxTendering process CVC guidelines-converted.pptx
Tendering process CVC guidelines-converted.pptx
 
Case Study-Calcium Carbide Sourcing Project
Case Study-Calcium Carbide Sourcing ProjectCase Study-Calcium Carbide Sourcing Project
Case Study-Calcium Carbide Sourcing Project
 
Battery Sourcing Case Study by Dragon Sourcing
Battery Sourcing Case Study by Dragon SourcingBattery Sourcing Case Study by Dragon Sourcing
Battery Sourcing Case Study by Dragon Sourcing
 
Pacific case
Pacific casePacific case
Pacific case
 
Case Study - Desalination Unit Project
Case Study - Desalination Unit ProjectCase Study - Desalination Unit Project
Case Study - Desalination Unit Project
 
Proposal for Salt Iodization
Proposal for Salt IodizationProposal for Salt Iodization
Proposal for Salt Iodization
 
Cotton Bags for Luxury Retail Brand Case Study
Cotton Bags for Luxury Retail Brand Case StudyCotton Bags for Luxury Retail Brand Case Study
Cotton Bags for Luxury Retail Brand Case Study
 
FOCUS XP_Team 08.pptx
FOCUS XP_Team 08.pptxFOCUS XP_Team 08.pptx
FOCUS XP_Team 08.pptx
 
ISMA 9 - van Heeringen - Using IFPUG and ISBSG to improve organization success
ISMA 9 - van Heeringen - Using IFPUG and ISBSG to improve organization successISMA 9 - van Heeringen - Using IFPUG and ISBSG to improve organization success
ISMA 9 - van Heeringen - Using IFPUG and ISBSG to improve organization success
 
CV_Maricel Molina rev 1
CV_Maricel Molina rev 1CV_Maricel Molina rev 1
CV_Maricel Molina rev 1
 
Steel structural parts case study
Steel structural parts case studySteel structural parts case study
Steel structural parts case study
 

Supplier Evaluation & Selection

  • 1. ASSIGNMENT ON CASE STUDY OF Supplier Evaluation & Selection SUBJECT: SOURCING MANAGEMENT INTERNATIONAL SUPPLY CHAIN EDUCATION ALLIANCE (ISCEA) DHAKA, BANGLADESH JANUARY- 2014 Supplier Evaluation & Selection, Report By: Emdadul Huq, Roll # 007, Batch # 7, PGDSCM, ISCEA
  • 2. Submitted To: Mr. Mirza Muhammad Masud Rana, Instructor, Sourcing Management PGDSCM, ISCEA Submitted by: Emdadul Huq, Roll – 007, BATCH - 7, PGDSCM, ISCEA Supplier Evaluation & Selection, Report By: Emdadul Huq, Roll # 007, Batch # 7, PGDSCM, ISCEA
  • 3. REPORT AT A GLANCE 1. IMPORTANT FACTS OF THE CASE A. Strength of FTC B. Product Expansion Plan C. Pricing Plan D. Quality Of Products 2. KEY ISSUES OF THE CASE A. Outsourcing & Strategic Plan 3. ALTERNATIVE COURSES OF ACTION A. Options to Outsourcing B. Price Comparison of Four Supplier 4. EVALUATE EACH COURSES OF ACTION A. Financial Risk Analysis B. Total Cost Analysis C. Supplier Evaluation & Selection Analysis 5. RECOMANDATION Supplier Evaluation & Selection, Report By: Emdadul Huq, Roll # 007, Batch # 7, PGDSCM, ISCEA
  • 4. 1. IMPORTANT FACTS OF THE CASE A. STRANGTH OF FTC Fastraq Technology Corporation is a medium sized (growing) high technology company FTC produces component parts & subsystems for PC & Engineering workstation. The company recognized as well-established component & subsystem manufacturer. FTC has good reputation for high quality product & on time delivery Supplier Evaluation & Selection, Report By: Emdadul # 7, PGDSCM, ISCEA 7, PGDSCM, ISCEA EMDADUL HUQ, ROLL # 007, BATCH Huq, Roll # 007, Batch #
  • 5. 1. IMPORTANT FACTS OF THE CASE B. PRODUCT EXPANSION PLAN FTC has decided to expend its product line to include fully assembled personal computer (PC). FTC has pursued an aggressive strategy of selling high quality computer at affordable price. The new line of computers, called 9000x series FTC plan direct ship to customer as orders are received (maketo-order) FTC will assembles the computers in its own facilities Supplier Evaluation & Selection, Report By: Emdadul Huq, Roll # 007, Batch # 7, PGDSCM, ISCEA
  • 6. 1. IMPORTANT FACTS OF THE CASE C. PRICING PLAN FTC is targeting the price of its PC line from $1100-$1700 depending on model & configuration. Targeted DVD price within the range of $115-135. Recent trends indicate that this level of pricing over extended period would be difficult. FTC call for redefining value in an economy where the cost of raw technology is plummeting toward zero Supplier Evaluation & Selection, Report By: Emdadul Huq, Roll # 007, Batch # 7, PGDSCM, ISCEA
  • 7. 1. IMPORTANT FACTS OF THE CASE D. QUALITY OF PRODUCTS Customers demand is defect free computers Poor quality of products adversely affects market reputation & future sales. FTC committed to supply high quality product by offering to take defects products/service back/redressing of complain etc. FTC financial & quality analyst calculate on average nonconforming cost is 375 per unit of pc (including lost goodwill) Supplier Evaluation & Selection, Report By: Emdadul Huq, Roll # 007, Batch # 7, PGDSCM, ISCEA
  • 8. 2. KEY ISSUES OF THE CASE A. OUTSOURCING & STRATEGIC PLAN FTC intent to outsource some component and subassemblies, i.e. DVD Drive Because DVD production capacities beyond the FTC current expertise. FTC plans in early January to another new line of computers directly to marketplace in August 2004 It must have inventory by June to begin providing & pilot production. FTC relies cross functional commodity team to develop sourcing strategy for key purchase items Executive management’s views DVD supplier selection decision is critical part of 9000x series development. Supplier Evaluation & Selection, Report By: Emdadul Huq, Roll # 007, Batch # 7, PGDSCM, ISCEA
  • 9. Material Requirement Planning based on Lead Time 3. ALTERNATIVE COURSES OF ACTION A. OPTIONS TO OUTSOURCING FTC ask to supplier “ Request for Proposal. Six suppliers respond to the commodity team’s Request for Proposal. The commodity team spent the last several weeks visiting 4 DVD suppliers and evaluation various supply options A review of these proposal revealed the four supplier out of six where cost competitive given FTC initial target cost. Among four suppliers two suppliers is United States & Two are Asia region (Korea & Japan) Name of the suppliers Advance Technologies Drivetech Company D-Drive Systems Parksoo Technologies Supplier Evaluation & Selection, Report By: Emdadul Huq, Roll # 007, Batch # 7, PGDSCM, ISCEA
  • 10. 3. ALTERNATIVE COURSES OF ACTION B. PRICE COMPARISON OF FOUR SUPPLIERS Name of Suppliers Parameters Advance Tech Drivetech D-Drive Parksoo Quoted Price 128 141 137 130 8 Week 3 Week 2 Week 8-10 Week 95% 97% 99% 99% 9300 ppmd 9950 ppmd 7200 ppmd 3000 ppmd 17.50 6.10 14 20 98% 93% 95% 93% 9 0 0 9.5 2.5 1.5 3 3.5 Freq of Shipment Monthly Weekly Every day Monthly Tooling Cost 2.25/mill 2.75/mill 2.25/mill 2.20/mill Ordering Cost 4.75 4 3.25 2.25 Ramp-up Time 4 months 5 months 3 months 4 months Yen Dollar Dollar Dollar Lead Time On time delivery record Quality Transport Cost Capacity Duties & customs Insurance Currency Supplier Evaluation & Selection, Report By: Emdadul Huq, Roll # 007, Batch # 7, PGDSCM, ISCEA
  • 11. 4. EVALUATE EACH COURSES OF ACTION A. FINANCIAL RISK ANALYSIS Current Ratio Analysis: Suppliers Current Assts Current Liabilities Current Ratio Advanced 2165.10 1780.60 1.216 DriveTech 164.00 122.50 1.339 D-Drive 735.00 545.00 1.349 Parksoo 391.90 347.00 1.129 Quick (Acid Test) Ratio Analysis: Suppliers (Cash+ Marketable Securities+ Receivables) Current Liabilities Quick (Acid Test) Advanced 1107.40 1780.60 0.622 DriveTech 89.00 122.50 0.727 D-Drive 570.00 545.00 1.046 Parksoo 256.50 347.00 0.739 In ratio analysis D-Drive shows lowest financial risk Supplier Evaluation & Selection, Report By: Emdadul # 7, PGDSCM, ISCEA 7, PGDSCM, ISCEA EMDADUL HUQ, ROLL # 007, BATCH Huq, Roll # 007, Batch #
  • 12. 4. EVALUATE EACH COURSES OF ACTION B. TOTAL COST ANALYSIS Yearly Demand= 500000 Unit, Avg Weekly Demand: 500000/52 week= 10,000 Unit (Round up) Lead Time (Week ) Re-Order Level (LXD) Unit Price Holding Cost/Uni t (25%) Ordering Cost/Uni t (Fixed) Annual Holding Cost Annual Ordering Cost Total Annual Cost Advance Te 8 80,000.00 128 32.0 34 1,280,000 211 65,280,211 Drivetec h 3 30,000.00 141 35.3 12 528,750 193 71,028,943 D-Drive 2 20,000.00 137 34.3 20 342,500 506 68,843,006 Parksoo 9 90,000.00 130 32.5 35 1,462,500 196 66,462,696 Suppliers Name Supplier Evaluation & Selection, Report By: Emdadul Huq, Roll # 007, Batch # 7, PGDSCM, ISCEA
  • 13. 4. EVALUATE EACH COURSES OF ACTION C. SUPPLIER EVALUATION & SELECTION ANALYSIS Suppliers Name Total Annual Cost Analysis & Findings Advance Tech 65,280,211 Although Lowest Annual Cost but financial condition is not so good and they are not interested to sign less then 100 million Drivetech 71,028,943 Annual Cost is High, Low Capacity; Ramp-up time is high, although financial risk is sustainable. D-Drive 68,843,006 Annual cost is high but Convenient location from FTC, lowest ramp-up time & Financial condition is so good. 66,462,696 Although annual cost is 2nd lowest but Low capacity, no experience to business with North America Parksoo Supplier Evaluation & Selection, Report By: Emdadul # 7, PGDSCM, ISCEA 7, PGDSCM, ISCEA EMDADUL HUQ, ROLL # 007, BATCH Huq, Roll # 007, Batch #
  • 14. 5. RECOMMANDATION In the above total cost analysis The Advance Tech Company annual cost is lowest but financial condition is not so good and they are not interested to sign contract less then 100 million and FTC target is 75 million per year so best choice would be D-Drive Systems. Because of the following factors 1. Although annual cost is high but FTC can get corporatenegotiated rate discounts by supporting it inbound logistics. 2. Quality Concern: lowest defect parts per millions 3. Lead Time is lowest 4. On time delivery record is highest 5. Capacity is second highest Continued… Supplier Evaluation & Selection, Report By: Emdadul Huq, Roll # 007, Batch # 7, PGDSCM, ISCEA
  • 15. 5. RECOMMANDATION 6.Ram-up Time is lowest 7.Frequency of Shipment is every other day 8.Financial Risk is lowest. 9.D-Drive System 10 miles from FTC assembly facility 10.FTC not need to manage inventory and safety stock. So Fastraq Technology Corporation can sign agreement with the D-Drive Systems for outsource DVD Drive to catch the back to school market without any risk . Supplier Evaluation & Selection, Report By: Emdadul Huq, Roll # 007, Batch # 7, PGDSCM, ISCEA
  • 16. THANK YOU Supplier Evaluation & Selection, Report By: Emdadul Huq, Roll # 007, Batch # 7, PGDSCM, ISCEA