EFFECT OF CONSTRUCTION DELAYS ON PROJECT TIME OVERRUN:
INDIAN SCENARIO
Ashwini Arun Salunkhe1
, Rahul S. Patil2
1
Post Graduate Student, 2
Assistant Professor, Department of Civil Engineering, Padmashree Dr. D. Y. Patil Institute of
Engineering & Technology. Pimpri, Pune (Maharashtra, India)
Abstract
The time and cost for performance of a project are usually important to the employer and contractor. About 57% of Indian
construction projects are experiencing time overrun. These time overruns always contributed as expensive to all parties. This paper
highlights the types of construction delays due to which project suffer time and cost overrun. Construction delay is considered to be
one of the recurring problems in the construction industry and it has an adverse effect on project success in terms of time, cost and
quality. The construction industry is the tool through which a society achieves its goal of urban and rural development. It is one of the
sectors that provides important ingredient for the development of an economy. This paper studies external and internal factors that
influence the construction process and outlines the effect of delay in large construction projects. Various media reports shows
incidents of extended delays and extensive cost overruns in infrastructure projects. These delayed projects are further can conclude
additional delays and this affects an ongoing projects and also new projects which could not be started due to pending projects whose
completion date already elongated. Realizing the density of matter this paper studies the performance of previous year 2012 ongoing
and also completed projects. These projects are from around 17 various central sectors costing Rs. 1000 crore and above (Mega
Projects).
Keywords: Delays, Time overrun, Cost overrun, Megaprojects etc
-----------------------------------------------------------------------***-----------------------------------------------------------------------
1. INTRODUCTION
The delay problem in the construction industry is a worldwide
phenomenon. Delays occur in most construction projects,
either simple or complex. In construction, delay can be
defined as the extension of time in the completion of project.
In short delay means failure to complete project in targeted
time & budgeted cost as agreed in contract. The occurrence of
delay is may concurrently with other delays and all of them
can impact the project completion date.
However, many projects experience extensive delays and
thereby exceed initial time and cost estimates. Construction
delay is considered to be one of the recurring problems in the
construction industry and it has an adverse effect on project
success in terms of time, cost and quality. It is shown from
previous studies (Abd Majid and Mccraffer (1998), Alwi and
Hampson (2003), Assaf and Al-Hejji (2006), Assaf, Al-khalif
and Al-Hajmi (1995)) that the failure of any project is mainly
related to the problems and failure in performance (contractor,
owner) of project which causes delay or time overrun and cost
overrun in project. Delays are always measured as expensive
to all parties concerned in projects and very often it will result
in clash, claims, total desertion and much difficult for
feasibility and also it slows the growth of construction
sector[5]. Construction is a risky industry with uncertainties
due to many external and internal factors that influence the
construction process.
All construction projects undergo several phases that are
shown in fig 1. The under development period is before the
projects put forward for approval. In development period the
projects are put forward and headed towards for approval of it.
During construction period project comes to execution of
work. Operating/performance period shows the time span of
operation and under maintenance period project is continued
through maintenance.
The project time overrun and cost overrun problem is faced by
numerous countries and the study on the causes of these
problems is also conducted such as India (Singh R., 2010),
Jordan ( Sweis G., Sweis R., Hammad A., and Schboul A.
2008), Nigeria (Aibinu A. and Odeyinka H. 2006), Saudi
Arabia ( Assaf S. and Al-Hejji S. 2006). In most construction
projects, best possible performance are unachievable with
poor productivity resulting in time overrun and consequently
cost escalation of the projects. The occurrence of delay is may
concurrently with other delays and all of them can impact the
project completion date. In delay project experiences delays in
construction period where different gaps occurred between the
actual progress on site work and scheduled work. Hence,
projects are failed to complete in construction period as per
contract and this failure to achieve targeted time, budgeted
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308
__________________________________________________________________________________________
Volume: 03 Issue: 01 | Jan-2014, Available @ http://www.ijret.org 544
cost and specified quality results in various negative effects.
Services provided by infrastructure projects serve as input for
other sectors, and cost overruns in these projects lead to an
increase in the capital-output ratio for the entire economy.
Delays and cost overruns reduce the efficiency of available
economic resources, limit the growth potential and reduce
competitiveness of the economy (Singh R., 2010).
A study conducted by Infrastructure and Project Monitoring
Division of Ministry of Statistics and Programme
Implementation (www.csgm.gov.in) reports on ongoing
projects. According to the reports published by programme
implementation division of the MOSPI December 2012, more
than 44% projects are experiencing time overrun. The Total
Original cost of implementation of 205 projects when
sanctioned, was of the order about Rs. 645643.20 crore but
this was subsequently revised to Rs. 7,62,450.96 crore
implying a cost overrun of 18.10% of original cost.
To measure the performance of projects, number of projects
who achieved their goal and number of projects who doesn’t
are analyzed. To improve the performance of project if we
could control the single most important factor of schedule
delay, the cost escalation can ultimately contained. This paper
studies the performance of previous year 2012 ongoing and
also completed mega projects and also studies the frequency
and magnitude of extended delays and extensive cost overruns
of infrastructure projects.
Fig 1: Project phases
2. LITERATURE REVIEW
Delays happen in most construction project; it could be
defined as time overrun either beyond completion date
specified in contract or beyond the date that parties agreed
upon for delivery of project (Assaf and Ai-Hejji 2006).
The project time overrun and cost overrun problem is faced by
numerous countries and the study on the causes of these
problems is also conducted such as India (Singh R., 2010),
Jordan ( Sweis G., Sweis R., Hammad A., and Schboul A.
2008), Nigeria (Aibinu A. and Odeyinka H. 2006), Saudi
Arabia ( Assaf S. and Al-Hejji S. 2006 ), Hong Kong (Tommy
Y., Ivan W. and Karen C. 2006), Egypt ( Mohamed M. and
Tarek I. 2013), Malaysia ( Hamzah N., Khoiry M., Arshad I.,
Tawil N. and Che A. 2011). In most construction projects, best
possible performance are unachievable with poor productivity
resulting in time overrun and consequently cost escalation of
the projects.
Singh R (2010) studied delays and cost overruns in 894
projects from 17 infrastructure sectors. According to this
study, delays are one of the crucial causes behind the cost
overrun. The bigger projects have experienced much high cost
overrun compare to smaller ones.
Wei K. S. (2010), identified major causes of delays, effects of
delays and methods of minimizing delays in construction
project in UTM construction project. The most significant
group that cause delay is contractor related, followed by
client-related and consultant related.
According to Saleh, Abdelnaser and Abdul (2009),
construction delay is a critical function in construction project
and also one of the biggest problems construction firms face in
Libya. In this study, the items of contractor’s factors that
cause delay and gave ranking based on the mean value criteria.
And in further analysis they identified the impact of delay in
construction projects i.e. loss of interest by stakeholder,
blacklist by authorities, waste of money and time and
declination of reputation.
Mohamad M. R. (2010) studies the factors and effects of delay
in government construction project. Research indicates that,
the most important causes of delay from 45 different causes
and 5 different effects of delays. They were cost overrun,
rescheduling and rearrangement, litigation, disputes and
arbitration.
3. TYPES OF DELAYS
According to Menesi (2007), delays are classified into two
different types according to liability: excusable and
inexcusable (Fig. 2).
Fig. 2: Types of Delays [8]
Delays that affect project completion date as agreed on
contract are considered as critical delays, while delays that do
not affect project completion date are known as non-critical
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308
__________________________________________________________________________________________
Volume: 03 Issue: 01 | Jan-2014, Available @ http://www.ijret.org 545
delays. An excusable delay is beyond the contractor control i.e
delay due to unforeseeable activity beyond the contractors or
the sub-contractors control. Excusable delays without
compensation are delays caused by neither the client nor the
contractor. Non-excusable delays (NEDs) are within
contractor control. NEDs are the responsibility of contractor
and the client may be entitled to claim the damages [1].
Only excusable delay can be compensable delay. A
compensable delay is a delay where the contractor is entitled
to a time extension and to additional compensation. Under
non-compensable delay the contractor is not entitled to any
compensation resulting from the excusable delay [14].
When the same type of delay happens more than one time,
either alone or consequently, impact the projects critical
activity schedule, a concurrent delay occurs. The concurrent
delay can also be classified as:
Table -1: Classification of concurrent delay according grant to
the contractor (Wei, 2010)
Delays that occur
concurrently
Entitlement to the
contractor
Excusable and non-
excusable
Only time extension
granted
Excusable with
compensation and
excusable without
compensation
Entitled to time
extension but not to
damages
Two excusable with
compensation
Entitled to both time
extension and damages
4. FINDING AND SUMMARY STATISTICS
The programme implementation division of MOSPI (India)
publishes flash reports on mega projects having information of
central sector infrastructure project costing Rs. 1000 crore and
above. Each report contains information of all ongoing,
completed as well as delayed projects for respective month.
According to these reports during Jan 2011 – Dec 2012the
data of projects suffering time and cost overrun is plotted for
that year shown in chart 1 & 2.
Chart -1: Percentage Time Overrun
Chart -2: Percentage Cost Overrun
For meaningful summarization it is significant to consider
time overrun and cost overrun in percentage instead of definite
expression. Chart 1 describes the tendency of percentage time
overrun in months for the year 2011 and 2012. The
percentages of monthly time overrun for the projects are
plotted against the respective months of that year when that
delay has occurred. From the chart we can see as compare to
year 2011, in year 2012 the time overrun pattern is irregular &
it is in ascending order for the full year. In the same way Chart
2 shows the pattern of percentage cost overruns over the year
2011 and year 2012. The degree of cost overrun in 2011
seems to have come down over the months. Likewise the
degrees of cost overrun in 2012 is irregular, as we see in April
2012 the percentage cost overrun is suddenly large and in July
it come down , further it is increases uniformly. From both the
chart 1 and chart 2, it should be seen that in year 2012 the
percentage time overrun and percentage cost overrun is
comparatively more. According to MOSPI report of Dec 2012,
around 57 % projects are experiencing time overrun.
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308
__________________________________________________________________________________________
Volume: 03 Issue: 01 | Jan-2014, Available @ http://www.ijret.org 546
Collectively time overrun for these projects is huge, like out of
205 projects in 2012, around 28 projects are having time
overrun in range of 13 to 24 months, 23 projects have delay in
range of 25 – 60 months & 14 projects have delay of 61 &
above. In which 5 projects which are experiencing maximum
delay and their cost expenditure in percentage is shown in
following table 2.
Table -2: Projects Having Maximum Time and Cost Overrun (as on31-12-2012)
Sr.
No.
Name Sector Date of commissioning Time
overrun in
months
Cost of project (Rs crore) Cost
overrun
in %
Original Anticipated Original Anticipated
1
UDHAMPUR-
SRINAGAR-
BARAMULLA(NL),NR
Railways 03/2001 12/2017 201 2500.00
20000.00
700.00
2
BANKURA –
DAMODAR (GC)
(SER)
Railways 03/2005 06/2016 135 111.90 1028.05 1162.50
3
TAMLUK
DIGHA,LINE
DOUBLING
(SER)
Railways 06/2005 06/2016 132 293.97 1086.41 269.43
4
BELAPUR SEA WOOD
URAN ELECTRIFIED
DOUBLE LINE(MTP)
Railways 03/2004 03/2014 120 401.81 1512.86 276.51
5 IOR GELEKI (ONGCL)
Petroleum
03/2007 03/2017 120 - - -
Source Data: MOSPI 2012
CONCLUSIONS
Time and cost overrun have been a major recurring problem in
construction industry. Brief reasons for time overruns as
reported by various project implementing agencies are delay
in land acquisition, delay in equipment erection, inadequate
mobilization by the contractor, delay in forest clearance, fund
constraints, change in scope of work, cancellation of tender,
law & order problem, delay in supply of equipment, slow
progress of civil work, escalation in cost.
Realizing the importance of subject, construction delay not
only results in time overrun but also in cost overrun. There are
various causes due to which project suffers from these delays.
As the project is running on many number of factors &
participant, these all are having individual causes. But the
important participants like owner, contractor, and consultant
have more influence on project performance. Hence the causes
of these participants are discussed which will helpful to
improve the project delivery in terms of time as well as cost
efficient.
For owner the causes which affect the project are like, changes
in plan by owner during construction, less capability of
understanding technical terms. Also from the finance point of
view, if owner delays in payment of completed work it is
going to affect the further work of project.
Contractor’s improper planning & scheduling have more
influence on project duration, as well as lack of experience
will affect the ability of decision making which will result in
rework & financing problems. Consultant’s improper
drawings, late revising the specification, less coordination
with contractor also conclude in project time overrun.
REFERENCES
[1]. Abd. Majid, M. Z., and McCraffer, R. (1998). “Factors of
non-excusable delays that influence contractor’s
performance”. J. Mange. Eng., 14(3), 42-49.
[2]. Aibinu, A. A., and Odeyinka, H. A. (2006). “Construction
delays and their causative factors in Nigeria”. J. Constr. Eng.
and Mgmt., (ASCE), 132(7), 667-677.
[3]. Alwi, S., and Hampson, K. (2003). “Identifying the
important causes of delays in building construction projects”.
The 9th East Asia-Pacific conference on structural eng. and
constr., Bali, Indonesia.
[4]. Assaf, S. A., and Al-hejji S. (2006). “Causes of delay in
large construction projects”. International J. Project Mgmt.,
Science Direct, 24, 349-357. 4
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308
__________________________________________________________________________________________
Volume: 03 Issue: 01 | Jan-2014, Available @ http://www.ijret.org 547
[5]. Assaf, S. A., Al-Khalif, M., and Al-Hazmi, M. (1995).
“Causes of delay in large building construction projects”. J.
Mgmt. Eng., 11(2), 45-50. 5
[6]. Hamzah, N., Khoitry, M. A., Arshad, I., Tawil, N. M., and
Che Ani, A. I. (2011), “Causes of construction delay-
theoretical framework”. Procedia Eng., Science Direct, 20,
490-495.
[7]. Haseeb, M., Xinhai-Lu, Bibi, A., Dyian, M., and Rabbani,
W., (2011). “Problems of projects and effects of delays in the
construction industry of Pakistan”. Australian Journal of
Business and Mgmt. Research, 1(5), 41-50.
[8]. Menesi, W. (2007). “Construction delay analysis under
multiple baseline updates”. A Thesis Report.
[9]. Mohamad, M. R. (2010). “The factors and effect of delay
in government construction project (case study in Kuantan)”.
[10]. Saleh, H. T., Abdelnaser, O., and Abdul H. P. (2009).
“Causes of delay in construction industry in Libya”. The
International Conference on Administration and Business.
[11]. Singh, R. (2010). “Delays and cost overruns in
infrastructure project: Extent, causes and remedies”.
Economics and Political Weekly, XLV(21), 43-54.
[12]. Sweis, G., Sweis, R., Hammad, A. A., and Shboul, A.
(2008). “ Delays in construction projects: the case of Jordan”.
International J. Project Mgmt., Science Direct, 26, 665-674.
[13]. Tommy, Y., Fung, W. H., and Tung, C. F. (2006).
“Construction delays in Hong Kong civil engineering
projects”. J. Constr. Eng. and Mgmt., ASCE, 132(6), 636-649.
[14]. Wei, K. S. (2010). “Causes, effects and methods of
minimizing delays in construction projects”. A project report.
BIOGRAPHIES
Ashwini Arun Salunkhe is a P.G. Student &
Lecturer in Department of Civil Engineering,
Padmashree Dr. D. Y. Patil Institute of
Engineering & Technology Pimpri, Pune –
411018.
Rahul S. Patil is assistant Professor In
Department Of Civil Engineering, Padmashree
Dr. D.Y.Patil Institute of Engineering &
Technology Pimpri, Pune-411018. He is
having teaching experience of 12 years. He is
pursuing Ph.D. in Transportation Engineering from University
of Pune, Pune - 411018

More Related Content

What's hot

Delay analysis ... wise after the event.
Delay analysis ... wise after the event.Delay analysis ... wise after the event.
Delay analysis ... wise after the event.Tim Lloyd
 
causes and implication of delay in construction
causes and implication of delay in constructioncauses and implication of delay in construction
causes and implication of delay in constructionsudinak
 
Project Time Management ICTI.ppt
Project Time Management ICTI.pptProject Time Management ICTI.ppt
Project Time Management ICTI.pptMohammadReza60255
 
Lean Construction: From Theory to Implementation
Lean Construction: From Theory to ImplementationLean Construction: From Theory to Implementation
Lean Construction: From Theory to ImplementationAntonius Pompi Bramono
 
Nepal National Building Code: Need, Formulation and Implementation Strategy
Nepal National Building Code: Need, Formulation and Implementation StrategyNepal National Building Code: Need, Formulation and Implementation Strategy
Nepal National Building Code: Need, Formulation and Implementation StrategyAchyut Paudel
 
Project Costs, Budgeting and Appraisal
Project Costs, Budgeting and AppraisalProject Costs, Budgeting and Appraisal
Project Costs, Budgeting and AppraisalJude Iheanacho
 
Reconstruction and development
Reconstruction and developmentReconstruction and development
Reconstruction and developmentMahmoud Shaqria
 
Cost control monitoring and accounting
Cost control monitoring and accountingCost control monitoring and accounting
Cost control monitoring and accountingImran Amami
 
VERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule AnalysesVERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule AnalysesThe Vertex Companies, LLC
 
Critical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/SlacksCritical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/SlacksPrasad Thanthratey
 
Introduction to Artificial Intelligence Technique for Civil Engineering_ Unit...
Introduction to Artificial Intelligence Technique for Civil Engineering_ Unit...Introduction to Artificial Intelligence Technique for Civil Engineering_ Unit...
Introduction to Artificial Intelligence Technique for Civil Engineering_ Unit...Shrikant Kate
 
Overview of construction sector in India (construction management )
Overview of construction sector in India (construction management )Overview of construction sector in India (construction management )
Overview of construction sector in India (construction management )shindesuraj82
 
Planning and Scheduling Construction Projects using Primavera Software A Case...
Planning and Scheduling Construction Projects using Primavera Software A Case...Planning and Scheduling Construction Projects using Primavera Software A Case...
Planning and Scheduling Construction Projects using Primavera Software A Case...ijtsrd
 
Chapter 4 Construction Project Management. Lec 4.ppt
Chapter 4 Construction Project Management. Lec 4.pptChapter 4 Construction Project Management. Lec 4.ppt
Chapter 4 Construction Project Management. Lec 4.pptssuserb4074f
 
A Critical Review of the Causes of Cost Overrun in Construction Industries in...
A Critical Review of the Causes of Cost Overrun in Construction Industries in...A Critical Review of the Causes of Cost Overrun in Construction Industries in...
A Critical Review of the Causes of Cost Overrun in Construction Industries in...IRJET Journal
 
Chapter 3 Construction Planning and Scheduling lect. 3.ppt
Chapter 3 Construction Planning and Scheduling lect. 3.pptChapter 3 Construction Planning and Scheduling lect. 3.ppt
Chapter 3 Construction Planning and Scheduling lect. 3.pptssuserb4074f
 

What's hot (20)

Delay analysis ... wise after the event.
Delay analysis ... wise after the event.Delay analysis ... wise after the event.
Delay analysis ... wise after the event.
 
causes and implication of delay in construction
causes and implication of delay in constructioncauses and implication of delay in construction
causes and implication of delay in construction
 
Project Time Management ICTI.ppt
Project Time Management ICTI.pptProject Time Management ICTI.ppt
Project Time Management ICTI.ppt
 
Lean Construction: From Theory to Implementation
Lean Construction: From Theory to ImplementationLean Construction: From Theory to Implementation
Lean Construction: From Theory to Implementation
 
Nepal National Building Code: Need, Formulation and Implementation Strategy
Nepal National Building Code: Need, Formulation and Implementation StrategyNepal National Building Code: Need, Formulation and Implementation Strategy
Nepal National Building Code: Need, Formulation and Implementation Strategy
 
Project Costs, Budgeting and Appraisal
Project Costs, Budgeting and AppraisalProject Costs, Budgeting and Appraisal
Project Costs, Budgeting and Appraisal
 
Reconstruction and development
Reconstruction and developmentReconstruction and development
Reconstruction and development
 
Cost control monitoring and accounting
Cost control monitoring and accountingCost control monitoring and accounting
Cost control monitoring and accounting
 
Project Management Tools and Techniques
Project Management Tools and TechniquesProject Management Tools and Techniques
Project Management Tools and Techniques
 
VERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule AnalysesVERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule Analyses
 
Critical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/SlacksCritical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/Slacks
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Introduction to Artificial Intelligence Technique for Civil Engineering_ Unit...
Introduction to Artificial Intelligence Technique for Civil Engineering_ Unit...Introduction to Artificial Intelligence Technique for Civil Engineering_ Unit...
Introduction to Artificial Intelligence Technique for Civil Engineering_ Unit...
 
Overview of construction sector in India (construction management )
Overview of construction sector in India (construction management )Overview of construction sector in India (construction management )
Overview of construction sector in India (construction management )
 
Planning and Scheduling Construction Projects using Primavera Software A Case...
Planning and Scheduling Construction Projects using Primavera Software A Case...Planning and Scheduling Construction Projects using Primavera Software A Case...
Planning and Scheduling Construction Projects using Primavera Software A Case...
 
Chapter 4 Construction Project Management. Lec 4.ppt
Chapter 4 Construction Project Management. Lec 4.pptChapter 4 Construction Project Management. Lec 4.ppt
Chapter 4 Construction Project Management. Lec 4.ppt
 
A Critical Review of the Causes of Cost Overrun in Construction Industries in...
A Critical Review of the Causes of Cost Overrun in Construction Industries in...A Critical Review of the Causes of Cost Overrun in Construction Industries in...
A Critical Review of the Causes of Cost Overrun in Construction Industries in...
 
Introduction to schedule management
Introduction to schedule managementIntroduction to schedule management
Introduction to schedule management
 
Chapter 3 Construction Planning and Scheduling lect. 3.ppt
Chapter 3 Construction Planning and Scheduling lect. 3.pptChapter 3 Construction Planning and Scheduling lect. 3.ppt
Chapter 3 Construction Planning and Scheduling lect. 3.ppt
 
Changes in construction
Changes in constructionChanges in construction
Changes in construction
 

Viewers also liked

028 Fast-tracking Projects & Cost Overrun
028 Fast-tracking Projects & Cost Overrun028 Fast-tracking Projects & Cost Overrun
028 Fast-tracking Projects & Cost OverrunDr Fereidoun Dejahang
 
IDENTIFYING AND ASSESSING THE CAUSES OF COST OVERRUN AT THE DESIGN AND PRECON...
IDENTIFYING AND ASSESSING THE CAUSES OF COST OVERRUN AT THE DESIGN AND PRECON...IDENTIFYING AND ASSESSING THE CAUSES OF COST OVERRUN AT THE DESIGN AND PRECON...
IDENTIFYING AND ASSESSING THE CAUSES OF COST OVERRUN AT THE DESIGN AND PRECON...Ahmad Samy M.Sc.
 
On-line Heater & Boiler Chemical Cleaning Technology
On-line Heater & Boiler Chemical Cleaning TechnologyOn-line Heater & Boiler Chemical Cleaning Technology
On-line Heater & Boiler Chemical Cleaning TechnologyGTC Technology
 
Commissioning and Operations
Commissioning and OperationsCommissioning and Operations
Commissioning and OperationsAchal Gupta
 
Project delay and_cost_overrun-libre
Project delay and_cost_overrun-libreProject delay and_cost_overrun-libre
Project delay and_cost_overrun-libreUTHM
 
Commissioning of Industrial Projects - Cost Estimating Considerations
Commissioning of Industrial Projects - Cost Estimating ConsiderationsCommissioning of Industrial Projects - Cost Estimating Considerations
Commissioning of Industrial Projects - Cost Estimating ConsiderationsDoina Dobre, P.Eng, GSC
 
Hrsg Cleaning
Hrsg CleaningHrsg Cleaning
Hrsg Cleaningbfsinc
 
Pre commissioning checks & periodic inspection on power transformers
Pre commissioning checks & periodic inspection  on power transformersPre commissioning checks & periodic inspection  on power transformers
Pre commissioning checks & periodic inspection on power transformersayyadurai SHANMUGAM
 
Boiler chemical cleaning_
Boiler chemical cleaning_Boiler chemical cleaning_
Boiler chemical cleaning_rkpandey85
 
Mechanical Completions
Mechanical CompletionsMechanical Completions
Mechanical CompletionsAndy Lang
 
Commissioning & Interface With Engineering
Commissioning & Interface With EngineeringCommissioning & Interface With Engineering
Commissioning & Interface With Engineeringasim569
 
Chemical Cleaning of Boiler in a Thermal Power Plant
Chemical Cleaning of Boiler in a Thermal Power PlantChemical Cleaning of Boiler in a Thermal Power Plant
Chemical Cleaning of Boiler in a Thermal Power PlantSUDHEER KUMAR KALYANAM
 
Steam blowing stages before turbine rolling
Steam blowing stages before turbine rollingSteam blowing stages before turbine rolling
Steam blowing stages before turbine rollingabhinav kumar
 
Pre commissioning steam turbines load trial
Pre commissioning steam turbines load trialPre commissioning steam turbines load trial
Pre commissioning steam turbines load trialNagesh H
 
Boiler commissioning procedure
Boiler commissioning procedureBoiler commissioning procedure
Boiler commissioning procedureABVSAI
 
Precommissioning and Commissioning
Precommissioning and CommissioningPrecommissioning and Commissioning
Precommissioning and CommissioningWendy Soerachman
 
Piping and Vessels Flushing and Cleaning Procedure
Piping and Vessels Flushing and Cleaning ProcedurePiping and Vessels Flushing and Cleaning Procedure
Piping and Vessels Flushing and Cleaning ProcedureGerard B. Hawkins
 
Types of turbine & thier application
Types of turbine & thier applicationTypes of turbine & thier application
Types of turbine & thier applicationdaudsangeenkhan
 

Viewers also liked (20)

028 Fast-tracking Projects & Cost Overrun
028 Fast-tracking Projects & Cost Overrun028 Fast-tracking Projects & Cost Overrun
028 Fast-tracking Projects & Cost Overrun
 
IDENTIFYING AND ASSESSING THE CAUSES OF COST OVERRUN AT THE DESIGN AND PRECON...
IDENTIFYING AND ASSESSING THE CAUSES OF COST OVERRUN AT THE DESIGN AND PRECON...IDENTIFYING AND ASSESSING THE CAUSES OF COST OVERRUN AT THE DESIGN AND PRECON...
IDENTIFYING AND ASSESSING THE CAUSES OF COST OVERRUN AT THE DESIGN AND PRECON...
 
On-line Heater & Boiler Chemical Cleaning Technology
On-line Heater & Boiler Chemical Cleaning TechnologyOn-line Heater & Boiler Chemical Cleaning Technology
On-line Heater & Boiler Chemical Cleaning Technology
 
Commissioning and Operations
Commissioning and OperationsCommissioning and Operations
Commissioning and Operations
 
Project delay and_cost_overrun-libre
Project delay and_cost_overrun-libreProject delay and_cost_overrun-libre
Project delay and_cost_overrun-libre
 
Commissioning of Industrial Projects - Cost Estimating Considerations
Commissioning of Industrial Projects - Cost Estimating ConsiderationsCommissioning of Industrial Projects - Cost Estimating Considerations
Commissioning of Industrial Projects - Cost Estimating Considerations
 
Hrsg Cleaning
Hrsg CleaningHrsg Cleaning
Hrsg Cleaning
 
Pre commissioning checks & periodic inspection on power transformers
Pre commissioning checks & periodic inspection  on power transformersPre commissioning checks & periodic inspection  on power transformers
Pre commissioning checks & periodic inspection on power transformers
 
Chemical cleaning
Chemical cleaningChemical cleaning
Chemical cleaning
 
Boiler chemical cleaning_
Boiler chemical cleaning_Boiler chemical cleaning_
Boiler chemical cleaning_
 
Mechanical Completions
Mechanical CompletionsMechanical Completions
Mechanical Completions
 
Commissioning & Interface With Engineering
Commissioning & Interface With EngineeringCommissioning & Interface With Engineering
Commissioning & Interface With Engineering
 
Steam turbine
Steam turbineSteam turbine
Steam turbine
 
Chemical Cleaning of Boiler in a Thermal Power Plant
Chemical Cleaning of Boiler in a Thermal Power PlantChemical Cleaning of Boiler in a Thermal Power Plant
Chemical Cleaning of Boiler in a Thermal Power Plant
 
Steam blowing stages before turbine rolling
Steam blowing stages before turbine rollingSteam blowing stages before turbine rolling
Steam blowing stages before turbine rolling
 
Pre commissioning steam turbines load trial
Pre commissioning steam turbines load trialPre commissioning steam turbines load trial
Pre commissioning steam turbines load trial
 
Boiler commissioning procedure
Boiler commissioning procedureBoiler commissioning procedure
Boiler commissioning procedure
 
Precommissioning and Commissioning
Precommissioning and CommissioningPrecommissioning and Commissioning
Precommissioning and Commissioning
 
Piping and Vessels Flushing and Cleaning Procedure
Piping and Vessels Flushing and Cleaning ProcedurePiping and Vessels Flushing and Cleaning Procedure
Piping and Vessels Flushing and Cleaning Procedure
 
Types of turbine & thier application
Types of turbine & thier applicationTypes of turbine & thier application
Types of turbine & thier application
 

Similar to Effect of construction delays on project time overrun

Delay Analysis in Industrial Projects by using Relative Importance Index Method
Delay Analysis in Industrial Projects by using Relative Importance Index MethodDelay Analysis in Industrial Projects by using Relative Importance Index Method
Delay Analysis in Industrial Projects by using Relative Importance Index MethodIRJET Journal
 
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECTINVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECTIRJET Journal
 
Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...IJERA Editor
 
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...IRJET Journal
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction ProjectIRJET Journal
 
Exploratory Study of Causes and Effects of Delay in Indian Residential Projects
Exploratory Study of Causes and Effects of Delay in Indian Residential ProjectsExploratory Study of Causes and Effects of Delay in Indian Residential Projects
Exploratory Study of Causes and Effects of Delay in Indian Residential ProjectsIRJET Journal
 
IRJET- Analysis of Cost Overrun in Construction Projects
IRJET- Analysis of Cost Overrun in Construction ProjectsIRJET- Analysis of Cost Overrun in Construction Projects
IRJET- Analysis of Cost Overrun in Construction ProjectsIRJET Journal
 
Element of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A ReviewElement of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A ReviewIRJET Journal
 
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET Journal
 
A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...
  A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...  A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...
A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...IAEME Publication
 
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET Journal
 
A Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction ProjectsA Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction ProjectsRick Vogel
 
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...IRJET Journal
 
IRJET - Causes, Effects and Minimizing Methods of Construction Projects D...
IRJET -  	  Causes, Effects and Minimizing Methods of Construction Projects D...IRJET -  	  Causes, Effects and Minimizing Methods of Construction Projects D...
IRJET - Causes, Effects and Minimizing Methods of Construction Projects D...IRJET Journal
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...IRJET Journal
 
Investigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsInvestigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsDr. Amarjeet Singh
 
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTSFACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTSIAEME Publication
 
Factor Affecting Construction Cost and Time in road project
Factor Affecting Construction Cost and Time in road projectFactor Affecting Construction Cost and Time in road project
Factor Affecting Construction Cost and Time in road projectIRJET Journal
 

Similar to Effect of construction delays on project time overrun (20)

Delay Analysis in Industrial Projects by using Relative Importance Index Method
Delay Analysis in Industrial Projects by using Relative Importance Index MethodDelay Analysis in Industrial Projects by using Relative Importance Index Method
Delay Analysis in Industrial Projects by using Relative Importance Index Method
 
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECTINVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
 
Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...
 
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction Project
 
Exploratory Study of Causes and Effects of Delay in Indian Residential Projects
Exploratory Study of Causes and Effects of Delay in Indian Residential ProjectsExploratory Study of Causes and Effects of Delay in Indian Residential Projects
Exploratory Study of Causes and Effects of Delay in Indian Residential Projects
 
IRJET- Analysis of Cost Overrun in Construction Projects
IRJET- Analysis of Cost Overrun in Construction ProjectsIRJET- Analysis of Cost Overrun in Construction Projects
IRJET- Analysis of Cost Overrun in Construction Projects
 
20320140503023
2032014050302320320140503023
20320140503023
 
Element of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A ReviewElement of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A Review
 
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
 
Ijciet 08 02_005
Ijciet 08 02_005Ijciet 08 02_005
Ijciet 08 02_005
 
A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...
  A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...  A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...
A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...
 
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
 
A Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction ProjectsA Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction Projects
 
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
 
IRJET - Causes, Effects and Minimizing Methods of Construction Projects D...
IRJET -  	  Causes, Effects and Minimizing Methods of Construction Projects D...IRJET -  	  Causes, Effects and Minimizing Methods of Construction Projects D...
IRJET - Causes, Effects and Minimizing Methods of Construction Projects D...
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...
 
Investigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsInvestigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure Projects
 
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTSFACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
 
Factor Affecting Construction Cost and Time in road project
Factor Affecting Construction Cost and Time in road projectFactor Affecting Construction Cost and Time in road project
Factor Affecting Construction Cost and Time in road project
 

More from eSAT Journals

Mechanical properties of hybrid fiber reinforced concrete for pavements
Mechanical properties of hybrid fiber reinforced concrete for pavementsMechanical properties of hybrid fiber reinforced concrete for pavements
Mechanical properties of hybrid fiber reinforced concrete for pavementseSAT Journals
 
Material management in construction – a case study
Material management in construction – a case studyMaterial management in construction – a case study
Material management in construction – a case studyeSAT Journals
 
Managing drought short term strategies in semi arid regions a case study
Managing drought    short term strategies in semi arid regions  a case studyManaging drought    short term strategies in semi arid regions  a case study
Managing drought short term strategies in semi arid regions a case studyeSAT Journals
 
Life cycle cost analysis of overlay for an urban road in bangalore
Life cycle cost analysis of overlay for an urban road in bangaloreLife cycle cost analysis of overlay for an urban road in bangalore
Life cycle cost analysis of overlay for an urban road in bangaloreeSAT Journals
 
Laboratory studies of dense bituminous mixes ii with reclaimed asphalt materials
Laboratory studies of dense bituminous mixes ii with reclaimed asphalt materialsLaboratory studies of dense bituminous mixes ii with reclaimed asphalt materials
Laboratory studies of dense bituminous mixes ii with reclaimed asphalt materialseSAT Journals
 
Laboratory investigation of expansive soil stabilized with natural inorganic ...
Laboratory investigation of expansive soil stabilized with natural inorganic ...Laboratory investigation of expansive soil stabilized with natural inorganic ...
Laboratory investigation of expansive soil stabilized with natural inorganic ...eSAT Journals
 
Influence of reinforcement on the behavior of hollow concrete block masonry p...
Influence of reinforcement on the behavior of hollow concrete block masonry p...Influence of reinforcement on the behavior of hollow concrete block masonry p...
Influence of reinforcement on the behavior of hollow concrete block masonry p...eSAT Journals
 
Influence of compaction energy on soil stabilized with chemical stabilizer
Influence of compaction energy on soil stabilized with chemical stabilizerInfluence of compaction energy on soil stabilized with chemical stabilizer
Influence of compaction energy on soil stabilized with chemical stabilizereSAT Journals
 
Geographical information system (gis) for water resources management
Geographical information system (gis) for water resources managementGeographical information system (gis) for water resources management
Geographical information system (gis) for water resources managementeSAT Journals
 
Forest type mapping of bidar forest division, karnataka using geoinformatics ...
Forest type mapping of bidar forest division, karnataka using geoinformatics ...Forest type mapping of bidar forest division, karnataka using geoinformatics ...
Forest type mapping of bidar forest division, karnataka using geoinformatics ...eSAT Journals
 
Factors influencing compressive strength of geopolymer concrete
Factors influencing compressive strength of geopolymer concreteFactors influencing compressive strength of geopolymer concrete
Factors influencing compressive strength of geopolymer concreteeSAT Journals
 
Experimental investigation on circular hollow steel columns in filled with li...
Experimental investigation on circular hollow steel columns in filled with li...Experimental investigation on circular hollow steel columns in filled with li...
Experimental investigation on circular hollow steel columns in filled with li...eSAT Journals
 
Experimental behavior of circular hsscfrc filled steel tubular columns under ...
Experimental behavior of circular hsscfrc filled steel tubular columns under ...Experimental behavior of circular hsscfrc filled steel tubular columns under ...
Experimental behavior of circular hsscfrc filled steel tubular columns under ...eSAT Journals
 
Evaluation of punching shear in flat slabs
Evaluation of punching shear in flat slabsEvaluation of punching shear in flat slabs
Evaluation of punching shear in flat slabseSAT Journals
 
Evaluation of performance of intake tower dam for recent earthquake in india
Evaluation of performance of intake tower dam for recent earthquake in indiaEvaluation of performance of intake tower dam for recent earthquake in india
Evaluation of performance of intake tower dam for recent earthquake in indiaeSAT Journals
 
Evaluation of operational efficiency of urban road network using travel time ...
Evaluation of operational efficiency of urban road network using travel time ...Evaluation of operational efficiency of urban road network using travel time ...
Evaluation of operational efficiency of urban road network using travel time ...eSAT Journals
 
Estimation of surface runoff in nallur amanikere watershed using scs cn method
Estimation of surface runoff in nallur amanikere watershed using scs cn methodEstimation of surface runoff in nallur amanikere watershed using scs cn method
Estimation of surface runoff in nallur amanikere watershed using scs cn methodeSAT Journals
 
Estimation of morphometric parameters and runoff using rs & gis techniques
Estimation of morphometric parameters and runoff using rs & gis techniquesEstimation of morphometric parameters and runoff using rs & gis techniques
Estimation of morphometric parameters and runoff using rs & gis techniqueseSAT Journals
 
Effect of variation of plastic hinge length on the results of non linear anal...
Effect of variation of plastic hinge length on the results of non linear anal...Effect of variation of plastic hinge length on the results of non linear anal...
Effect of variation of plastic hinge length on the results of non linear anal...eSAT Journals
 
Effect of use of recycled materials on indirect tensile strength of asphalt c...
Effect of use of recycled materials on indirect tensile strength of asphalt c...Effect of use of recycled materials on indirect tensile strength of asphalt c...
Effect of use of recycled materials on indirect tensile strength of asphalt c...eSAT Journals
 

More from eSAT Journals (20)

Mechanical properties of hybrid fiber reinforced concrete for pavements
Mechanical properties of hybrid fiber reinforced concrete for pavementsMechanical properties of hybrid fiber reinforced concrete for pavements
Mechanical properties of hybrid fiber reinforced concrete for pavements
 
Material management in construction – a case study
Material management in construction – a case studyMaterial management in construction – a case study
Material management in construction – a case study
 
Managing drought short term strategies in semi arid regions a case study
Managing drought    short term strategies in semi arid regions  a case studyManaging drought    short term strategies in semi arid regions  a case study
Managing drought short term strategies in semi arid regions a case study
 
Life cycle cost analysis of overlay for an urban road in bangalore
Life cycle cost analysis of overlay for an urban road in bangaloreLife cycle cost analysis of overlay for an urban road in bangalore
Life cycle cost analysis of overlay for an urban road in bangalore
 
Laboratory studies of dense bituminous mixes ii with reclaimed asphalt materials
Laboratory studies of dense bituminous mixes ii with reclaimed asphalt materialsLaboratory studies of dense bituminous mixes ii with reclaimed asphalt materials
Laboratory studies of dense bituminous mixes ii with reclaimed asphalt materials
 
Laboratory investigation of expansive soil stabilized with natural inorganic ...
Laboratory investigation of expansive soil stabilized with natural inorganic ...Laboratory investigation of expansive soil stabilized with natural inorganic ...
Laboratory investigation of expansive soil stabilized with natural inorganic ...
 
Influence of reinforcement on the behavior of hollow concrete block masonry p...
Influence of reinforcement on the behavior of hollow concrete block masonry p...Influence of reinforcement on the behavior of hollow concrete block masonry p...
Influence of reinforcement on the behavior of hollow concrete block masonry p...
 
Influence of compaction energy on soil stabilized with chemical stabilizer
Influence of compaction energy on soil stabilized with chemical stabilizerInfluence of compaction energy on soil stabilized with chemical stabilizer
Influence of compaction energy on soil stabilized with chemical stabilizer
 
Geographical information system (gis) for water resources management
Geographical information system (gis) for water resources managementGeographical information system (gis) for water resources management
Geographical information system (gis) for water resources management
 
Forest type mapping of bidar forest division, karnataka using geoinformatics ...
Forest type mapping of bidar forest division, karnataka using geoinformatics ...Forest type mapping of bidar forest division, karnataka using geoinformatics ...
Forest type mapping of bidar forest division, karnataka using geoinformatics ...
 
Factors influencing compressive strength of geopolymer concrete
Factors influencing compressive strength of geopolymer concreteFactors influencing compressive strength of geopolymer concrete
Factors influencing compressive strength of geopolymer concrete
 
Experimental investigation on circular hollow steel columns in filled with li...
Experimental investigation on circular hollow steel columns in filled with li...Experimental investigation on circular hollow steel columns in filled with li...
Experimental investigation on circular hollow steel columns in filled with li...
 
Experimental behavior of circular hsscfrc filled steel tubular columns under ...
Experimental behavior of circular hsscfrc filled steel tubular columns under ...Experimental behavior of circular hsscfrc filled steel tubular columns under ...
Experimental behavior of circular hsscfrc filled steel tubular columns under ...
 
Evaluation of punching shear in flat slabs
Evaluation of punching shear in flat slabsEvaluation of punching shear in flat slabs
Evaluation of punching shear in flat slabs
 
Evaluation of performance of intake tower dam for recent earthquake in india
Evaluation of performance of intake tower dam for recent earthquake in indiaEvaluation of performance of intake tower dam for recent earthquake in india
Evaluation of performance of intake tower dam for recent earthquake in india
 
Evaluation of operational efficiency of urban road network using travel time ...
Evaluation of operational efficiency of urban road network using travel time ...Evaluation of operational efficiency of urban road network using travel time ...
Evaluation of operational efficiency of urban road network using travel time ...
 
Estimation of surface runoff in nallur amanikere watershed using scs cn method
Estimation of surface runoff in nallur amanikere watershed using scs cn methodEstimation of surface runoff in nallur amanikere watershed using scs cn method
Estimation of surface runoff in nallur amanikere watershed using scs cn method
 
Estimation of morphometric parameters and runoff using rs & gis techniques
Estimation of morphometric parameters and runoff using rs & gis techniquesEstimation of morphometric parameters and runoff using rs & gis techniques
Estimation of morphometric parameters and runoff using rs & gis techniques
 
Effect of variation of plastic hinge length on the results of non linear anal...
Effect of variation of plastic hinge length on the results of non linear anal...Effect of variation of plastic hinge length on the results of non linear anal...
Effect of variation of plastic hinge length on the results of non linear anal...
 
Effect of use of recycled materials on indirect tensile strength of asphalt c...
Effect of use of recycled materials on indirect tensile strength of asphalt c...Effect of use of recycled materials on indirect tensile strength of asphalt c...
Effect of use of recycled materials on indirect tensile strength of asphalt c...
 

Recently uploaded

High Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMS
High Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMSHigh Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMS
High Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMSsandhya757531
 
Module-1-(Building Acoustics) Noise Control (Unit-3). pdf
Module-1-(Building Acoustics) Noise Control (Unit-3). pdfModule-1-(Building Acoustics) Noise Control (Unit-3). pdf
Module-1-(Building Acoustics) Noise Control (Unit-3). pdfManish Kumar
 
System Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingSystem Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingBootNeck1
 
Virtual memory management in Operating System
Virtual memory management in Operating SystemVirtual memory management in Operating System
Virtual memory management in Operating SystemRashmi Bhat
 
Novel 3D-Printed Soft Linear and Bending Actuators
Novel 3D-Printed Soft Linear and Bending ActuatorsNovel 3D-Printed Soft Linear and Bending Actuators
Novel 3D-Printed Soft Linear and Bending ActuatorsResearcher Researcher
 
Stork Webinar | APM Transformational planning, Tool Selection & Performance T...
Stork Webinar | APM Transformational planning, Tool Selection & Performance T...Stork Webinar | APM Transformational planning, Tool Selection & Performance T...
Stork Webinar | APM Transformational planning, Tool Selection & Performance T...Stork
 
『澳洲文凭』买麦考瑞大学毕业证书成绩单办理澳洲Macquarie文凭学位证书
『澳洲文凭』买麦考瑞大学毕业证书成绩单办理澳洲Macquarie文凭学位证书『澳洲文凭』买麦考瑞大学毕业证书成绩单办理澳洲Macquarie文凭学位证书
『澳洲文凭』买麦考瑞大学毕业证书成绩单办理澳洲Macquarie文凭学位证书rnrncn29
 
Paper Tube : Shigeru Ban projects and Case Study of Cardboard Cathedral .pdf
Paper Tube : Shigeru Ban projects and Case Study of Cardboard Cathedral .pdfPaper Tube : Shigeru Ban projects and Case Study of Cardboard Cathedral .pdf
Paper Tube : Shigeru Ban projects and Case Study of Cardboard Cathedral .pdfNainaShrivastava14
 
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONjhunlian
 
CME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTES
CME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTESCME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTES
CME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTESkarthi keyan
 
Turn leadership mistakes into a better future.pptx
Turn leadership mistakes into a better future.pptxTurn leadership mistakes into a better future.pptx
Turn leadership mistakes into a better future.pptxStephen Sitton
 
SOFTWARE ESTIMATION COCOMO AND FP CALCULATION
SOFTWARE ESTIMATION COCOMO AND FP CALCULATIONSOFTWARE ESTIMATION COCOMO AND FP CALCULATION
SOFTWARE ESTIMATION COCOMO AND FP CALCULATIONSneha Padhiar
 
FUNCTIONAL AND NON FUNCTIONAL REQUIREMENT
FUNCTIONAL AND NON FUNCTIONAL REQUIREMENTFUNCTIONAL AND NON FUNCTIONAL REQUIREMENT
FUNCTIONAL AND NON FUNCTIONAL REQUIREMENTSneha Padhiar
 
TEST CASE GENERATION GENERATION BLOCK BOX APPROACH
TEST CASE GENERATION GENERATION BLOCK BOX APPROACHTEST CASE GENERATION GENERATION BLOCK BOX APPROACH
TEST CASE GENERATION GENERATION BLOCK BOX APPROACHSneha Padhiar
 
Artificial Intelligence in Power System overview
Artificial Intelligence in Power System overviewArtificial Intelligence in Power System overview
Artificial Intelligence in Power System overviewsandhya757531
 
Gravity concentration_MI20612MI_________
Gravity concentration_MI20612MI_________Gravity concentration_MI20612MI_________
Gravity concentration_MI20612MI_________Romil Mishra
 
"Exploring the Essential Functions and Design Considerations of Spillways in ...
"Exploring the Essential Functions and Design Considerations of Spillways in ..."Exploring the Essential Functions and Design Considerations of Spillways in ...
"Exploring the Essential Functions and Design Considerations of Spillways in ...Erbil Polytechnic University
 
DEVICE DRIVERS AND INTERRUPTS SERVICE MECHANISM.pdf
DEVICE DRIVERS AND INTERRUPTS  SERVICE MECHANISM.pdfDEVICE DRIVERS AND INTERRUPTS  SERVICE MECHANISM.pdf
DEVICE DRIVERS AND INTERRUPTS SERVICE MECHANISM.pdfAkritiPradhan2
 
ROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.ppt
ROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.pptROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.ppt
ROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.pptJohnWilliam111370
 
Robotics Group 10 (Control Schemes) cse.pdf
Robotics Group 10  (Control Schemes) cse.pdfRobotics Group 10  (Control Schemes) cse.pdf
Robotics Group 10 (Control Schemes) cse.pdfsahilsajad201
 

Recently uploaded (20)

High Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMS
High Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMSHigh Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMS
High Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMS
 
Module-1-(Building Acoustics) Noise Control (Unit-3). pdf
Module-1-(Building Acoustics) Noise Control (Unit-3). pdfModule-1-(Building Acoustics) Noise Control (Unit-3). pdf
Module-1-(Building Acoustics) Noise Control (Unit-3). pdf
 
System Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingSystem Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event Scheduling
 
Virtual memory management in Operating System
Virtual memory management in Operating SystemVirtual memory management in Operating System
Virtual memory management in Operating System
 
Novel 3D-Printed Soft Linear and Bending Actuators
Novel 3D-Printed Soft Linear and Bending ActuatorsNovel 3D-Printed Soft Linear and Bending Actuators
Novel 3D-Printed Soft Linear and Bending Actuators
 
Stork Webinar | APM Transformational planning, Tool Selection & Performance T...
Stork Webinar | APM Transformational planning, Tool Selection & Performance T...Stork Webinar | APM Transformational planning, Tool Selection & Performance T...
Stork Webinar | APM Transformational planning, Tool Selection & Performance T...
 
『澳洲文凭』买麦考瑞大学毕业证书成绩单办理澳洲Macquarie文凭学位证书
『澳洲文凭』买麦考瑞大学毕业证书成绩单办理澳洲Macquarie文凭学位证书『澳洲文凭』买麦考瑞大学毕业证书成绩单办理澳洲Macquarie文凭学位证书
『澳洲文凭』买麦考瑞大学毕业证书成绩单办理澳洲Macquarie文凭学位证书
 
Paper Tube : Shigeru Ban projects and Case Study of Cardboard Cathedral .pdf
Paper Tube : Shigeru Ban projects and Case Study of Cardboard Cathedral .pdfPaper Tube : Shigeru Ban projects and Case Study of Cardboard Cathedral .pdf
Paper Tube : Shigeru Ban projects and Case Study of Cardboard Cathedral .pdf
 
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
 
CME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTES
CME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTESCME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTES
CME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTES
 
Turn leadership mistakes into a better future.pptx
Turn leadership mistakes into a better future.pptxTurn leadership mistakes into a better future.pptx
Turn leadership mistakes into a better future.pptx
 
SOFTWARE ESTIMATION COCOMO AND FP CALCULATION
SOFTWARE ESTIMATION COCOMO AND FP CALCULATIONSOFTWARE ESTIMATION COCOMO AND FP CALCULATION
SOFTWARE ESTIMATION COCOMO AND FP CALCULATION
 
FUNCTIONAL AND NON FUNCTIONAL REQUIREMENT
FUNCTIONAL AND NON FUNCTIONAL REQUIREMENTFUNCTIONAL AND NON FUNCTIONAL REQUIREMENT
FUNCTIONAL AND NON FUNCTIONAL REQUIREMENT
 
TEST CASE GENERATION GENERATION BLOCK BOX APPROACH
TEST CASE GENERATION GENERATION BLOCK BOX APPROACHTEST CASE GENERATION GENERATION BLOCK BOX APPROACH
TEST CASE GENERATION GENERATION BLOCK BOX APPROACH
 
Artificial Intelligence in Power System overview
Artificial Intelligence in Power System overviewArtificial Intelligence in Power System overview
Artificial Intelligence in Power System overview
 
Gravity concentration_MI20612MI_________
Gravity concentration_MI20612MI_________Gravity concentration_MI20612MI_________
Gravity concentration_MI20612MI_________
 
"Exploring the Essential Functions and Design Considerations of Spillways in ...
"Exploring the Essential Functions and Design Considerations of Spillways in ..."Exploring the Essential Functions and Design Considerations of Spillways in ...
"Exploring the Essential Functions and Design Considerations of Spillways in ...
 
DEVICE DRIVERS AND INTERRUPTS SERVICE MECHANISM.pdf
DEVICE DRIVERS AND INTERRUPTS  SERVICE MECHANISM.pdfDEVICE DRIVERS AND INTERRUPTS  SERVICE MECHANISM.pdf
DEVICE DRIVERS AND INTERRUPTS SERVICE MECHANISM.pdf
 
ROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.ppt
ROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.pptROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.ppt
ROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.ppt
 
Robotics Group 10 (Control Schemes) cse.pdf
Robotics Group 10  (Control Schemes) cse.pdfRobotics Group 10  (Control Schemes) cse.pdf
Robotics Group 10 (Control Schemes) cse.pdf
 

Effect of construction delays on project time overrun

  • 1. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 __________________________________________________________________________________________ Volume: 03 Issue: 01 | Jan-2014, Available @ http://www.ijret.org 543 EFFECT OF CONSTRUCTION DELAYS ON PROJECT TIME OVERRUN: INDIAN SCENARIO Ashwini Arun Salunkhe1 , Rahul S. Patil2 1 Post Graduate Student, 2 Assistant Professor, Department of Civil Engineering, Padmashree Dr. D. Y. Patil Institute of Engineering & Technology. Pimpri, Pune (Maharashtra, India) Abstract The time and cost for performance of a project are usually important to the employer and contractor. About 57% of Indian construction projects are experiencing time overrun. These time overruns always contributed as expensive to all parties. This paper highlights the types of construction delays due to which project suffer time and cost overrun. Construction delay is considered to be one of the recurring problems in the construction industry and it has an adverse effect on project success in terms of time, cost and quality. The construction industry is the tool through which a society achieves its goal of urban and rural development. It is one of the sectors that provides important ingredient for the development of an economy. This paper studies external and internal factors that influence the construction process and outlines the effect of delay in large construction projects. Various media reports shows incidents of extended delays and extensive cost overruns in infrastructure projects. These delayed projects are further can conclude additional delays and this affects an ongoing projects and also new projects which could not be started due to pending projects whose completion date already elongated. Realizing the density of matter this paper studies the performance of previous year 2012 ongoing and also completed projects. These projects are from around 17 various central sectors costing Rs. 1000 crore and above (Mega Projects). Keywords: Delays, Time overrun, Cost overrun, Megaprojects etc -----------------------------------------------------------------------***----------------------------------------------------------------------- 1. INTRODUCTION The delay problem in the construction industry is a worldwide phenomenon. Delays occur in most construction projects, either simple or complex. In construction, delay can be defined as the extension of time in the completion of project. In short delay means failure to complete project in targeted time & budgeted cost as agreed in contract. The occurrence of delay is may concurrently with other delays and all of them can impact the project completion date. However, many projects experience extensive delays and thereby exceed initial time and cost estimates. Construction delay is considered to be one of the recurring problems in the construction industry and it has an adverse effect on project success in terms of time, cost and quality. It is shown from previous studies (Abd Majid and Mccraffer (1998), Alwi and Hampson (2003), Assaf and Al-Hejji (2006), Assaf, Al-khalif and Al-Hajmi (1995)) that the failure of any project is mainly related to the problems and failure in performance (contractor, owner) of project which causes delay or time overrun and cost overrun in project. Delays are always measured as expensive to all parties concerned in projects and very often it will result in clash, claims, total desertion and much difficult for feasibility and also it slows the growth of construction sector[5]. Construction is a risky industry with uncertainties due to many external and internal factors that influence the construction process. All construction projects undergo several phases that are shown in fig 1. The under development period is before the projects put forward for approval. In development period the projects are put forward and headed towards for approval of it. During construction period project comes to execution of work. Operating/performance period shows the time span of operation and under maintenance period project is continued through maintenance. The project time overrun and cost overrun problem is faced by numerous countries and the study on the causes of these problems is also conducted such as India (Singh R., 2010), Jordan ( Sweis G., Sweis R., Hammad A., and Schboul A. 2008), Nigeria (Aibinu A. and Odeyinka H. 2006), Saudi Arabia ( Assaf S. and Al-Hejji S. 2006). In most construction projects, best possible performance are unachievable with poor productivity resulting in time overrun and consequently cost escalation of the projects. The occurrence of delay is may concurrently with other delays and all of them can impact the project completion date. In delay project experiences delays in construction period where different gaps occurred between the actual progress on site work and scheduled work. Hence, projects are failed to complete in construction period as per contract and this failure to achieve targeted time, budgeted
  • 2. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 __________________________________________________________________________________________ Volume: 03 Issue: 01 | Jan-2014, Available @ http://www.ijret.org 544 cost and specified quality results in various negative effects. Services provided by infrastructure projects serve as input for other sectors, and cost overruns in these projects lead to an increase in the capital-output ratio for the entire economy. Delays and cost overruns reduce the efficiency of available economic resources, limit the growth potential and reduce competitiveness of the economy (Singh R., 2010). A study conducted by Infrastructure and Project Monitoring Division of Ministry of Statistics and Programme Implementation (www.csgm.gov.in) reports on ongoing projects. According to the reports published by programme implementation division of the MOSPI December 2012, more than 44% projects are experiencing time overrun. The Total Original cost of implementation of 205 projects when sanctioned, was of the order about Rs. 645643.20 crore but this was subsequently revised to Rs. 7,62,450.96 crore implying a cost overrun of 18.10% of original cost. To measure the performance of projects, number of projects who achieved their goal and number of projects who doesn’t are analyzed. To improve the performance of project if we could control the single most important factor of schedule delay, the cost escalation can ultimately contained. This paper studies the performance of previous year 2012 ongoing and also completed mega projects and also studies the frequency and magnitude of extended delays and extensive cost overruns of infrastructure projects. Fig 1: Project phases 2. LITERATURE REVIEW Delays happen in most construction project; it could be defined as time overrun either beyond completion date specified in contract or beyond the date that parties agreed upon for delivery of project (Assaf and Ai-Hejji 2006). The project time overrun and cost overrun problem is faced by numerous countries and the study on the causes of these problems is also conducted such as India (Singh R., 2010), Jordan ( Sweis G., Sweis R., Hammad A., and Schboul A. 2008), Nigeria (Aibinu A. and Odeyinka H. 2006), Saudi Arabia ( Assaf S. and Al-Hejji S. 2006 ), Hong Kong (Tommy Y., Ivan W. and Karen C. 2006), Egypt ( Mohamed M. and Tarek I. 2013), Malaysia ( Hamzah N., Khoiry M., Arshad I., Tawil N. and Che A. 2011). In most construction projects, best possible performance are unachievable with poor productivity resulting in time overrun and consequently cost escalation of the projects. Singh R (2010) studied delays and cost overruns in 894 projects from 17 infrastructure sectors. According to this study, delays are one of the crucial causes behind the cost overrun. The bigger projects have experienced much high cost overrun compare to smaller ones. Wei K. S. (2010), identified major causes of delays, effects of delays and methods of minimizing delays in construction project in UTM construction project. The most significant group that cause delay is contractor related, followed by client-related and consultant related. According to Saleh, Abdelnaser and Abdul (2009), construction delay is a critical function in construction project and also one of the biggest problems construction firms face in Libya. In this study, the items of contractor’s factors that cause delay and gave ranking based on the mean value criteria. And in further analysis they identified the impact of delay in construction projects i.e. loss of interest by stakeholder, blacklist by authorities, waste of money and time and declination of reputation. Mohamad M. R. (2010) studies the factors and effects of delay in government construction project. Research indicates that, the most important causes of delay from 45 different causes and 5 different effects of delays. They were cost overrun, rescheduling and rearrangement, litigation, disputes and arbitration. 3. TYPES OF DELAYS According to Menesi (2007), delays are classified into two different types according to liability: excusable and inexcusable (Fig. 2). Fig. 2: Types of Delays [8] Delays that affect project completion date as agreed on contract are considered as critical delays, while delays that do not affect project completion date are known as non-critical
  • 3. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 __________________________________________________________________________________________ Volume: 03 Issue: 01 | Jan-2014, Available @ http://www.ijret.org 545 delays. An excusable delay is beyond the contractor control i.e delay due to unforeseeable activity beyond the contractors or the sub-contractors control. Excusable delays without compensation are delays caused by neither the client nor the contractor. Non-excusable delays (NEDs) are within contractor control. NEDs are the responsibility of contractor and the client may be entitled to claim the damages [1]. Only excusable delay can be compensable delay. A compensable delay is a delay where the contractor is entitled to a time extension and to additional compensation. Under non-compensable delay the contractor is not entitled to any compensation resulting from the excusable delay [14]. When the same type of delay happens more than one time, either alone or consequently, impact the projects critical activity schedule, a concurrent delay occurs. The concurrent delay can also be classified as: Table -1: Classification of concurrent delay according grant to the contractor (Wei, 2010) Delays that occur concurrently Entitlement to the contractor Excusable and non- excusable Only time extension granted Excusable with compensation and excusable without compensation Entitled to time extension but not to damages Two excusable with compensation Entitled to both time extension and damages 4. FINDING AND SUMMARY STATISTICS The programme implementation division of MOSPI (India) publishes flash reports on mega projects having information of central sector infrastructure project costing Rs. 1000 crore and above. Each report contains information of all ongoing, completed as well as delayed projects for respective month. According to these reports during Jan 2011 – Dec 2012the data of projects suffering time and cost overrun is plotted for that year shown in chart 1 & 2. Chart -1: Percentage Time Overrun Chart -2: Percentage Cost Overrun For meaningful summarization it is significant to consider time overrun and cost overrun in percentage instead of definite expression. Chart 1 describes the tendency of percentage time overrun in months for the year 2011 and 2012. The percentages of monthly time overrun for the projects are plotted against the respective months of that year when that delay has occurred. From the chart we can see as compare to year 2011, in year 2012 the time overrun pattern is irregular & it is in ascending order for the full year. In the same way Chart 2 shows the pattern of percentage cost overruns over the year 2011 and year 2012. The degree of cost overrun in 2011 seems to have come down over the months. Likewise the degrees of cost overrun in 2012 is irregular, as we see in April 2012 the percentage cost overrun is suddenly large and in July it come down , further it is increases uniformly. From both the chart 1 and chart 2, it should be seen that in year 2012 the percentage time overrun and percentage cost overrun is comparatively more. According to MOSPI report of Dec 2012, around 57 % projects are experiencing time overrun.
  • 4. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 __________________________________________________________________________________________ Volume: 03 Issue: 01 | Jan-2014, Available @ http://www.ijret.org 546 Collectively time overrun for these projects is huge, like out of 205 projects in 2012, around 28 projects are having time overrun in range of 13 to 24 months, 23 projects have delay in range of 25 – 60 months & 14 projects have delay of 61 & above. In which 5 projects which are experiencing maximum delay and their cost expenditure in percentage is shown in following table 2. Table -2: Projects Having Maximum Time and Cost Overrun (as on31-12-2012) Sr. No. Name Sector Date of commissioning Time overrun in months Cost of project (Rs crore) Cost overrun in % Original Anticipated Original Anticipated 1 UDHAMPUR- SRINAGAR- BARAMULLA(NL),NR Railways 03/2001 12/2017 201 2500.00 20000.00 700.00 2 BANKURA – DAMODAR (GC) (SER) Railways 03/2005 06/2016 135 111.90 1028.05 1162.50 3 TAMLUK DIGHA,LINE DOUBLING (SER) Railways 06/2005 06/2016 132 293.97 1086.41 269.43 4 BELAPUR SEA WOOD URAN ELECTRIFIED DOUBLE LINE(MTP) Railways 03/2004 03/2014 120 401.81 1512.86 276.51 5 IOR GELEKI (ONGCL) Petroleum 03/2007 03/2017 120 - - - Source Data: MOSPI 2012 CONCLUSIONS Time and cost overrun have been a major recurring problem in construction industry. Brief reasons for time overruns as reported by various project implementing agencies are delay in land acquisition, delay in equipment erection, inadequate mobilization by the contractor, delay in forest clearance, fund constraints, change in scope of work, cancellation of tender, law & order problem, delay in supply of equipment, slow progress of civil work, escalation in cost. Realizing the importance of subject, construction delay not only results in time overrun but also in cost overrun. There are various causes due to which project suffers from these delays. As the project is running on many number of factors & participant, these all are having individual causes. But the important participants like owner, contractor, and consultant have more influence on project performance. Hence the causes of these participants are discussed which will helpful to improve the project delivery in terms of time as well as cost efficient. For owner the causes which affect the project are like, changes in plan by owner during construction, less capability of understanding technical terms. Also from the finance point of view, if owner delays in payment of completed work it is going to affect the further work of project. Contractor’s improper planning & scheduling have more influence on project duration, as well as lack of experience will affect the ability of decision making which will result in rework & financing problems. Consultant’s improper drawings, late revising the specification, less coordination with contractor also conclude in project time overrun. REFERENCES [1]. Abd. Majid, M. Z., and McCraffer, R. (1998). “Factors of non-excusable delays that influence contractor’s performance”. J. Mange. Eng., 14(3), 42-49. [2]. Aibinu, A. A., and Odeyinka, H. A. (2006). “Construction delays and their causative factors in Nigeria”. J. Constr. Eng. and Mgmt., (ASCE), 132(7), 667-677. [3]. Alwi, S., and Hampson, K. (2003). “Identifying the important causes of delays in building construction projects”. The 9th East Asia-Pacific conference on structural eng. and constr., Bali, Indonesia. [4]. Assaf, S. A., and Al-hejji S. (2006). “Causes of delay in large construction projects”. International J. Project Mgmt., Science Direct, 24, 349-357. 4
  • 5. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 __________________________________________________________________________________________ Volume: 03 Issue: 01 | Jan-2014, Available @ http://www.ijret.org 547 [5]. Assaf, S. A., Al-Khalif, M., and Al-Hazmi, M. (1995). “Causes of delay in large building construction projects”. J. Mgmt. Eng., 11(2), 45-50. 5 [6]. Hamzah, N., Khoitry, M. A., Arshad, I., Tawil, N. M., and Che Ani, A. I. (2011), “Causes of construction delay- theoretical framework”. Procedia Eng., Science Direct, 20, 490-495. [7]. Haseeb, M., Xinhai-Lu, Bibi, A., Dyian, M., and Rabbani, W., (2011). “Problems of projects and effects of delays in the construction industry of Pakistan”. Australian Journal of Business and Mgmt. Research, 1(5), 41-50. [8]. Menesi, W. (2007). “Construction delay analysis under multiple baseline updates”. A Thesis Report. [9]. Mohamad, M. R. (2010). “The factors and effect of delay in government construction project (case study in Kuantan)”. [10]. Saleh, H. T., Abdelnaser, O., and Abdul H. P. (2009). “Causes of delay in construction industry in Libya”. The International Conference on Administration and Business. [11]. Singh, R. (2010). “Delays and cost overruns in infrastructure project: Extent, causes and remedies”. Economics and Political Weekly, XLV(21), 43-54. [12]. Sweis, G., Sweis, R., Hammad, A. A., and Shboul, A. (2008). “ Delays in construction projects: the case of Jordan”. International J. Project Mgmt., Science Direct, 26, 665-674. [13]. Tommy, Y., Fung, W. H., and Tung, C. F. (2006). “Construction delays in Hong Kong civil engineering projects”. J. Constr. Eng. and Mgmt., ASCE, 132(6), 636-649. [14]. Wei, K. S. (2010). “Causes, effects and methods of minimizing delays in construction projects”. A project report. BIOGRAPHIES Ashwini Arun Salunkhe is a P.G. Student & Lecturer in Department of Civil Engineering, Padmashree Dr. D. Y. Patil Institute of Engineering & Technology Pimpri, Pune – 411018. Rahul S. Patil is assistant Professor In Department Of Civil Engineering, Padmashree Dr. D.Y.Patil Institute of Engineering & Technology Pimpri, Pune-411018. He is having teaching experience of 12 years. He is pursuing Ph.D. in Transportation Engineering from University of Pune, Pune - 411018