Ce diaporama a bien été signalé.
Nous utilisons votre profil LinkedIn et vos données d’activité pour vous proposer des publicités personnalisées et pertinentes. Vous pouvez changer vos préférences de publicités à tout moment.
Dulles Corridor Metrorail Project
Board Transportation Committee Update
Mark Canale, Fairfax County Project Manager
Fairfa...
Phase 1
• Old Meadow Road Realignment – in design, construction completion
scheduled for the end of 2018
• VDOT punchlist ...
Phase 2 – Station Construction
• Reston Town Center Station – Precast erection and structural steel
• Herndon Station – St...
Phase 2 – Aerial Guideway
• Columns and Pier Caps – 100%
• Deck Spans Poured – 77%
• Trackway Spans
• Aerial track support...
Phase 2 – Rail Yard at Dulles Airport
• 100% Design Plans Submitted
• Installation of stormwater, sanitary, duct bank stru...
Phase 2 – Cost Summary
Budget
• Total Budget $2.778B
• Total Forecast $2.778B
• Total Expenditures $1.1B
Contingency Utili...
Herndon Metrorail Garage
Total Project Estimate: $44.5M
Schedule
Bid Opening: July 2016
Construction Award: October 2016
C...
Herndon Metrorail Garage
8
Innovation Metrorail Garage
Total Project Estimate: $52 million
Schedule
Bid Opening: December 2016 - February 2017
Constr...
Innovation Metrorail Garage
10
Reston Town Center Station
11
Herndon Station
12
Innovation Center Station
13
Dulles Airport Station
14
West Segment
15
QUESTIONS?
16
Prochain SlideShare
Chargement dans…5
×

Agenda Item 7: Silver Line Phase II Implementation

876 vues

Publié le

Agenda Item 7: Silver Line Phase II Implementation

Publié dans : Actualités & Politique
  • Soyez le premier à commenter

  • Soyez le premier à aimer ceci

Agenda Item 7: Silver Line Phase II Implementation

  1. 1. Dulles Corridor Metrorail Project Board Transportation Committee Update Mark Canale, Fairfax County Project Manager Fairfax County Department of Transportation May 9, 2017
  2. 2. Phase 1 • Old Meadow Road Realignment – in design, construction completion scheduled for the end of 2018 • VDOT punchlist ongoing • Phase 1 close out - $2.982B Phase 2 • Package A (Rail line, system, and stations)– 59% • Package B (Rail yard at Dulles) – 46% • Contractual Substantial Completion – August 2019 • WMATA to establish Revenue Operations Date 2
  3. 3. Phase 2 – Station Construction • Reston Town Center Station – Precast erection and structural steel • Herndon Station – Structural steel for roof, precast detailing, north and south pavilion construction • Innovation Station – Precast detailing, structural steel painting, electrical and plumbing, pedestrian bridge assembly for north and south pavilions • Dulles Airport Station – Precast and structural steel erection, station mechanical/electrical/plumbing rough in work, tunnel tie-in • Loudoun Gateway Station – Station precast erection • Ashburn Station - Station foundation and support walls 3
  4. 4. Phase 2 – Aerial Guideway • Columns and Pier Caps – 100% • Deck Spans Poured – 77% • Trackway Spans • Aerial track supports, and deck pours work ongoing 4
  5. 5. Phase 2 – Rail Yard at Dulles Airport • 100% Design Plans Submitted • Installation of stormwater, sanitary, duct bank structures, and retaining wall - ongoing • Final grading, utilities and yard layout continues • Structural steel erection for Service and Inspection and Maintenance buildings - ongoing • Foundation work for Transit Police and Train Wash Facility buildings - ongoing 5
  6. 6. Phase 2 – Cost Summary Budget • Total Budget $2.778B • Total Forecast $2.778B • Total Expenditures $1.1B Contingency Utilization • Total Contingency $561.3M • Total Contingency Utilized $131.3M • Remaining Contingency $430M 6
  7. 7. Herndon Metrorail Garage Total Project Estimate: $44.5M Schedule Bid Opening: July 2016 Construction Award: October 2016 Construction (new garage): November 2016 – January 2019 Construction (existing garage): February 2019 – March 2019 Ready for Occupancy: April 2019 7
  8. 8. Herndon Metrorail Garage 8
  9. 9. Innovation Metrorail Garage Total Project Estimate: $52 million Schedule Bid Opening: December 2016 - February 2017 Construction Award: March - April 2017 Construction: April 2017 Ready for Occupancy: April/May 2019 9
  10. 10. Innovation Metrorail Garage 10
  11. 11. Reston Town Center Station 11
  12. 12. Herndon Station 12
  13. 13. Innovation Center Station 13
  14. 14. Dulles Airport Station 14
  15. 15. West Segment 15
  16. 16. QUESTIONS? 16

×