Chain Bridge Road Walkway from Niblick Drive to Horse Shoe Drive

50 vues

Publié le

This project is part of commercial and industrial revenue projects and consists of the construction of approximately 3,300 feet of 5-foot-wide sidewalk with associated stormwater drainage, curb and gutter works, and signal modifications along the east side of Chain Bridge Road between Niblick Drive and Horse Shoe Drive.

  • Soyez le premier à commenter

  • Soyez le premier à aimer ceci

Chain Bridge Road Walkway from Niblick Drive to Horse Shoe Drive

  1. 1. A Fairfax County, VA, publication Department of Public Works and Environmental Services Working for You! Task Order No. 10 Contract No. CN19124125 Project No. 2G40-088-014 Providence District Tax Map No. 38-2, 39-1 November 13, 2019 CHAIN BRIDGE ROAD WALKWAY FROM NIBLICK DRIVE TO HORSE SHOE DRIVE
  2. 2. Chain Bridge Road Walkway Improvements (from Niblick Drive to Horse Shoe Drive) Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
  3. 3. Project Details Chain Bridge Road Walkway Improvements Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch Description: The Chain Bridge Road Walkway Improvements Project was substantially completed on September 24, 2019. This project is part of commercial and industrial (C&I) revenue projects and consists of the construction of approximately 3,300 ft long, 5 ft. wide, sidewalk with associated stormwater drainage, curb and gutter works, and signal modifications along the east side of Chain Bridge Road between Niblick Drive and Horse Shoe Drive. Project Team: Department of Transportation - James Beall (PM); Eldar Yusufoglu (Utility Coordinator) Utilities Design and Construction Division (UDCD) - Abul M. Syed (CM) UDCD Inspections - Kenneth Giles and Jim Cooper Capital Facilities Survey- Gregory Harper Engineer - Whitman, Requardt & Associates, LLP Contractor - Finley Asphalt & Sealing, Inc.
  4. 4. Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch Providence, Tax Map 38-2, 39-1 Limits of Improvements, Project No. 2G40-088-014 PROJECT SITE Chain Bridge Road Walkway Improvements
  5. 5. Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch Pre-Existing Conditions Chain Bridge Road Walkway Improvements
  6. 6. Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch Pre-Existing Conditions Chain Bridge Road Walkway Improvements
  7. 7. Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch Chain Bridge Road Walkway Improvements Installation of Storm Drainage Pipe
  8. 8. Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch Chain Bridge Road Walkway Improvements Installation of Concrete Sidewalk
  9. 9. Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch Installation of Soil Stabilization Mats Chain Bridge Road Walkway Improvements
  10. 10. Chain Bridge Road Walkway Improvements (from Niblick Drive to Horse Shoe Drive) Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
  11. 11. Chain Bridge Road Walkway Improvements (from Niblick Drive to Horse Shoe Drive) Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
  12. 12. Chain Bridge Road Walkway Improvements (from Niblick Drive to Horse Shoe Drive) Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
  13. 13. Before After Chain Bridge Road Walkway Improvements (from Niblick Drive to Horse Shoe Drive) Capital Facilities/Utilities Design and Construction Division, Transportation Construction Branch
  14. 14. Before After Capital Facilities/Utilities Design and Construction Division, Transportation Construction Branch Chain Bridge Road Walkway Improvements (from Niblick Drive to Horse Shoe Drive)
  15. 15. Before After Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch Chain Bridge Road Walkway Improvements (from Niblick Drive to Horse Shoe Drive)
  16. 16. Before After Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch Chain Bridge Road Walkway Improvements (from Niblick Drive to Horse Shoe Drive)
  17. 17. Additional Information For additional Information, please call www.fairfaxcounty.gov/publicworks Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch Matthew Kaiser, Public Information Officer 703-324-8455, TTY 711 Matthew.Kaiser@fairfaxcounty.gov Chain Bridge Road Walkway Improvements

×