Georgetown Pike Walkway Phase III

54 vues

Publié le

Phase III of the Georgetown Pike Trail was substantially completed on time and under budget on August 30, 2019. This project consisted of construction of asphalt sidewalk, curb and gutter, tree removal, improved stormwater management, ADA upgrades, and other related items

  • Soyez le premier à commenter

  • Soyez le premier à aimer ceci

Georgetown Pike Walkway Phase III

  1. 1. A Fairfax County, VA, publication Department of Public Works and Environmental Services Working for You! Georgetown Pike Trail Phase III Contract No. CN19102051 Project No. 1400130-2013 VDOT UPC No. 111913 Dranesville District September 23, 2019
  2. 2. Georgetown Pike Trail Phase III Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
  3. 3. Project Details Georgetown Pike Trail Phase III Description: The Georgetown Pike Trail Phase III Project was substantially completed on time and under budget on August 30, 2019. This project consisted of construction of asphalt sidewalk, curb & gutter, tree removal and other related items. Project Overview: • New Asphalt Walkway • New Handicap Ramp • Drainage Improvement Project Team: • Department of Transportation Project Manager – John Dresser • Department of Transportation Utility Coordinator – Richard Pugh • Land Acquisition Division – Daniel Rusu • Utilities Design and Construction Division (UDCD) – Ben Samiyi • Project Inspector, RK&K – Rick Richardson Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
  4. 4. Dranesville District, Tax Map No. 6-4 Project Location Georgetown Pike Trail Phase III Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
  5. 5. Georgetown Pike Trail Phase III Installation of Storm Drainage Pipe Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
  6. 6. Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch Georgetown Pike Trail Phase III Handicap Ramp
  7. 7. Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch Georgetown Pike Trail Phase III Asphalt Walkway
  8. 8. Before After Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
  9. 9. Additional Information For additional Information, please call www.fairfaxcounty.gov/publicworks Matthew Kaiser, Public Information Officer 703-324-8455, TTY 711 Matthew.Kaiser@fairfaxcounty.gov Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch

×