SlideShare a Scribd company logo
1 of 22
PMP – Cost Management
Chapter 7
Related Definitions
Life cycle costing
The costing over product life
Value analysis (engineering)
Analysis to minimize cost of a work
Cost risk
The risk of cost possessionThis document is a partial preview. Full document download can be found on Flevy:
http://flevy.com/browse/document/pmp-cost-management-project-management-professional-exam-1513
Plan Cost Management
How will you plan cost?
How will you manage and control costs and its variences?
How the costs will be paid?
Which cost accounts are existing and need to create?
Which cost will be assigned to which account?
How to finance, lease or buy? (also a procurement topic)
What is Net present value (NPV) and payback period and internal
rate of return of the project?
The key benefit of this process is that it provides guidance and
direction on how the project costs will be managed throughout the
project.
This document is a partial preview. Full document download can be found on Flevy:
http://flevy.com/browse/document/pmp-cost-management-project-management-professional-exam-1513
7. Cost Management Processes
•establishes the policies for planning, managing, expending, and
controlling project costs
7.1. Plan Cost management
•developing an approximation of the monetary resources needed to
complete project activities.
7.2. Estimate costs
•aggregating the estimated costs of individual activities or work packages
to establish an authorized cost baseline
7.3. Determine budget
•monitoring the status of the project to update the project costs
7.4. Control costs
This document is a partial preview. Full document download can be found on Flevy:
http://flevy.com/browse/document/pmp-cost-management-project-management-professional-exam-1513
7.2. Estimate Costs
Cost estimates are a prediction that is based on the
information known at a given point in time.
Cost estimates include the identification and consideration
of costing alternatives to initiate and complete the project.
Cost estimates are generally expressed in units of some
currency (i.e., dollars, euros, yen, etc.), although in some
instances other units of measure, such as staff hours or staff
days
Cost estimates should be reviewed and refined during the
course of the project
This document is a partial preview. Full document download can be found on Flevy:
http://flevy.com/browse/document/pmp-cost-management-project-management-professional-exam-1513
Estimation Methods – Time and Cost
Bottom-up
•Cost of individual
work packages
or activities is
estimated to the
greatest level of
specified detail
Three-Point
•Optimistic,
pessimistic and
most likely 3
points are
estimated
•Risk register is
used
•Simple or
weighted
average is used
Analogous
•Expert
judgement and
historical
information is
used
•Previous similar
project estimate
•Basicly a
prediction
•Less costly less
accurate
Parametric
•Calculates with
data
•Uses historical
data
•Regression and
learning curve
afffect it
•E.g. 1 operator
build 20 brick, 40
operators 800
brick.
This document is a partial preview. Full document download can be found on Flevy:
http://flevy.com/browse/document/pmp-cost-management-project-management-professional-exam-1513
Estimate Costs
# Have you included these in your project? Response
1 Project management activities cost
2 Assets cost
3 PM’s time cost
4 Labor cost
5 Quality costs
6 Risk management costs (Contingency Reserves cost)
7 Training and other HRM costs
8 Materials cost
9 Rental of PMO cost
10 Management salaries and overhead costs
This document is a partial preview. Full document download can be found on Flevy:
http://flevy.com/browse/document/pmp-cost-management-project-management-professional-exam-1513
Outputs of Estimate Cost
•quantitative assessments of the probable costs
•can be presented in summary form or in detail
Activity
Cost
estimate
•additional details supporting the cost estimate
•complete understanding of how the cost
estimate was derived
•Assumptions, constraints, ranges and confidence
levels
Basis of
estimates
This document is a partial preview. Full document download can be found on Flevy:
http://flevy.com/browse/document/pmp-cost-management-project-management-professional-exam-1513
Determine Budget
PM needs to find the total cost of the project and
contingency reserves and management reserves.
Inputs
Cost man.Plan
Scope baseline
Schedule
Activity Cost
estimates
Basis of estimate
HRM plan
Risk Register
Resource calendar
Org. Pro. Assets
Ent. Env. Factors
Determinebudget Cost aggregation
Reserve analysis
Expert judgment
Historical
relationships
Funding limit
reconcilation
Outputs
Cost baseline
Project funding
Requirements
Updates to project
docs
This document is a partial preview. Full document download can be found on Flevy:
http://flevy.com/browse/document/pmp-cost-management-project-management-professional-exam-1513
Outputs
Total funding requirements and periodic funding
requirements (e.g., quarterly, annually) are derived from
the cost baseline
Funding often occurs in incremental amounts that are
not continuous
This document is a partial preview. Full document download can be found on Flevy:
http://flevy.com/browse/document/pmp-cost-management-project-management-professional-exam-1513
Why do we use Reserve Analysis as a
Control costs Tool?
As project progresses the risks identified in planning will
happen or not. Therefore, we will have a bright idea if
contingency reserves will be needed still or may be
removed.
On the other hand, regarding Management reserves, as
project progresses the unknown risks will appear or not so
you can more accurately manage Management
Reserves which also influence budget.
Reserve analysis is basically update reserve amounts.
This document is a partial preview. Full document download can be found on Flevy:
http://flevy.com/browse/document/pmp-cost-management-project-management-professional-exam-1513
Earned Value Measurement
Definitions
Acro Terms Meaning
PV Planned Value Work planned till today
EV Earned Value Work accomplished till today
AC Actual Cost Cost till today
BAC Budget at completion Budget dedicated to the project
EAC Estimate at completion Expection cost at the end
ETC Estimate to complete How much more do you need?
VAC Variance at completion
How much more exceeded your
budget?
This document is a partial preview. Full document download can be found on Flevy:
http://flevy.com/browse/document/pmp-cost-management-project-management-professional-exam-1513
Definitions
Actual cost.
Actual cost (AC) is the realized cost incurred for the work
performed on an activity during a specific time period.
It is the total cost incurred in accomplishing the work that the
EV measured.
The AC needs to correspond in definition to what was
budgeted in the PV and measured in the EV (e.g., direct
hours only, direct costs only, or all costs including indirect
costs).
The AC will have no upper limit; whatever is spent to achieve
the EV will be measured.
This document is a partial preview. Full document download can be found on Flevy:
http://flevy.com/browse/document/pmp-cost-management-project-management-professional-exam-1513
Definitions
Cost variance. CV= EV − AC.
amount of budget deficit or surplus at a given point in time,
expressed as the difference between earned value and the
actual cost.
It is a measure of cost performance on a project. It is equal
to the earned value (EV) minus the actual cost (AC).
The cost variance at the end of the project will be the
difference between the budget at completion (BAC) and
the actual amount spent.
The CV is particularly critical because it indicates the
relationship of physical performance to the costs spent.
Negative CV is often difficult for the project to recover.
This document is a partial preview. Full document download can be found on Flevy:
http://flevy.com/browse/document/pmp-cost-management-project-management-professional-exam-1513
S-curve
First draw PV and BAC
Then, you can draw EV, AC and EAC according to
progression
This document is a partial preview. Full document download can be found on Flevy:
http://flevy.com/browse/document/pmp-cost-management-project-management-professional-exam-1513
Forecasting
Term Formula
Estimate at
completion EAC
BAC/CPI
AC+ BAC – EV
AC + ((BAC-EV)/
(CPI.SPI))
TCPI To complete
performance index
(BAC-EV)/(BAC-AC)
Estimate to
complete ETC
EAC- AC
Variance at
completion VAC
BAC – EAC
This document is a partial preview. Full document download can be found on Flevy:
http://flevy.com/browse/document/pmp-cost-management-project-management-professional-exam-1513
Method 2
EAC with same rate assumption
EAC forecast for ETC work performed at the present CPI.
This method assumes what the project has experienced to
date can be expected to continue in the future.
The ETC work is assumed to be performed at the same
cumulative cost performance index (CPI) as that incurred by
the project to date.
Equation: EAC = BAC / CPI
This document is a partial preview. Full document download can be found on Flevy:
http://flevy.com/browse/document/pmp-cost-management-project-management-professional-exam-1513
Exercise
You are managing a software project, heretofore you
spent $ 10 Million and controlling department reports tells
that your CPI is 1.2 and SPI 1.1, What is your EV?
Solution
CPI = EV/AC where your AC= 10 million
EV = $ 12 million
This document is a partial preview. Full document download can be found on Flevy:
http://flevy.com/browse/document/pmp-cost-management-project-management-professional-exam-1513
Exercise – Interpretation CPI
Your CPI is 0.84, what information you can understand from this
statement?
You are producing 84 cents (kurus) VALUE, out of each $1.
You are spending more than planned. You are overbudget. Your CV is
negative.
You need to be more productive in terms of cost to complete project,
on planned budget.
Your CPI is 1.2, what information you can understand from this
statement?
You are producing $1.2 VALUE for each$1.
You are spending less than planned. You are under-budget. CV is +.
You can achieve you planned budget, if you possess this track and
effectiveness.
This document is a partial preview. Full document download can be found on Flevy:
http://flevy.com/browse/document/pmp-cost-management-project-management-professional-exam-1513
Control Costs
• roject management
plan
• Project funding
• requirements
• Work performance
data
• .Organizational process
assets
Inputs
• Earned value
management
• .Forecasting
• To-complete
performance index
(TCPI)
• Performance reviews
• Project management
software
• Reserve analysis
Tools
• Work performance
information
• Cost forecasts
• Change requests
• Project management
plan update
• Project documents
updates
• Organizational process
assets updates
Outputs
This document is a partial preview. Full document download can be found on Flevy:
http://flevy.com/browse/document/pmp-cost-management-project-management-professional-exam-1513
EVM
This document is a partial preview. Full document download can be found on Flevy:
http://flevy.com/browse/document/pmp-cost-management-project-management-professional-exam-1513
1
Flevy (www.flevy.com) is the marketplace
for premium documents. These
documents can range from Business
Frameworks to Financial Models to
PowerPoint Templates.
Flevy was founded under the principle that
companies waste a lot of time and money
recreating the same foundational business
documents. Our vision is for Flevy to
become a comprehensive knowledge base
of business documents. All organizations,
from startups to large enterprises, can use
Flevy— whether it's to jumpstart projects, to
find reference or comparison materials, or
just to learn.
Contact Us
Please contact us with any questions you may have
about our company.
• General Inquiries
support@flevy.com
• Media/PR
press@flevy.com
• Billing
billing@flevy.com

More Related Content

Viewers also liked

Total Cost Management - Synergy between Cost Estimating and Project Controls
Total Cost Management - Synergy between Cost Estimating and Project ControlsTotal Cost Management - Synergy between Cost Estimating and Project Controls
Total Cost Management - Synergy between Cost Estimating and Project ControlsMartin van Vliet
 
PMBoK, discussion #5: Project Cost Management
PMBoK, discussion #5: Project Cost ManagementPMBoK, discussion #5: Project Cost Management
PMBoK, discussion #5: Project Cost ManagementOleksandr Lutsaievskyi
 
project cost management
project cost managementproject cost management
project cost managementjay mitkari
 
Cost Estimation in Project Management - Case of Solar Assisted Water Pump
Cost Estimation in Project Management - Case of Solar Assisted Water PumpCost Estimation in Project Management - Case of Solar Assisted Water Pump
Cost Estimation in Project Management - Case of Solar Assisted Water PumpNitesh Bhatia
 
Project Cost Management
Project Cost Management Project Cost Management
Project Cost Management Muhammad Hanif
 
ادارة تكلفة المشروع
ادارة تكلفة المشروع ادارة تكلفة المشروع
ادارة تكلفة المشروع Mohamed Dahi
 
Case study 4 project cost management -- ppt slides
Case study 4   project cost management -- ppt slidesCase study 4   project cost management -- ppt slides
Case study 4 project cost management -- ppt slidesHarhar Caparida
 
Project Management C8 -cost_estimation_and_budgeting
Project Management C8  -cost_estimation_and_budgetingProject Management C8  -cost_estimation_and_budgeting
Project Management C8 -cost_estimation_and_budgetingIzah Asmadi
 
ادارة الوقت والتكلفة
ادارة الوقت والتكلفةادارة الوقت والتكلفة
ادارة الوقت والتكلفةmona-sh
 
PMP Chap 7 - Project Cost Management - Part 1
PMP Chap 7 - Project Cost Management - Part 1PMP Chap 7 - Project Cost Management - Part 1
PMP Chap 7 - Project Cost Management - Part 1Anand Bobade
 

Viewers also liked (11)

Total Cost Management - Synergy between Cost Estimating and Project Controls
Total Cost Management - Synergy between Cost Estimating and Project ControlsTotal Cost Management - Synergy between Cost Estimating and Project Controls
Total Cost Management - Synergy between Cost Estimating and Project Controls
 
Qs Approach To Project Cost
Qs Approach To Project CostQs Approach To Project Cost
Qs Approach To Project Cost
 
PMBoK, discussion #5: Project Cost Management
PMBoK, discussion #5: Project Cost ManagementPMBoK, discussion #5: Project Cost Management
PMBoK, discussion #5: Project Cost Management
 
project cost management
project cost managementproject cost management
project cost management
 
Cost Estimation in Project Management - Case of Solar Assisted Water Pump
Cost Estimation in Project Management - Case of Solar Assisted Water PumpCost Estimation in Project Management - Case of Solar Assisted Water Pump
Cost Estimation in Project Management - Case of Solar Assisted Water Pump
 
Project Cost Management
Project Cost Management Project Cost Management
Project Cost Management
 
ادارة تكلفة المشروع
ادارة تكلفة المشروع ادارة تكلفة المشروع
ادارة تكلفة المشروع
 
Case study 4 project cost management -- ppt slides
Case study 4   project cost management -- ppt slidesCase study 4   project cost management -- ppt slides
Case study 4 project cost management -- ppt slides
 
Project Management C8 -cost_estimation_and_budgeting
Project Management C8  -cost_estimation_and_budgetingProject Management C8  -cost_estimation_and_budgeting
Project Management C8 -cost_estimation_and_budgeting
 
ادارة الوقت والتكلفة
ادارة الوقت والتكلفةادارة الوقت والتكلفة
ادارة الوقت والتكلفة
 
PMP Chap 7 - Project Cost Management - Part 1
PMP Chap 7 - Project Cost Management - Part 1PMP Chap 7 - Project Cost Management - Part 1
PMP Chap 7 - Project Cost Management - Part 1
 

More from Flevy.com Best Practices

100 Case Studies on Strategy & Transformation.pdf
100 Case Studies on Strategy & Transformation.pdf100 Case Studies on Strategy & Transformation.pdf
100 Case Studies on Strategy & Transformation.pdfFlevy.com Best Practices
 
[Whitepaper] Business Transformation Success Factors
[Whitepaper] Business Transformation Success Factors[Whitepaper] Business Transformation Success Factors
[Whitepaper] Business Transformation Success FactorsFlevy.com Best Practices
 
[Whitepaper] 5 Dimensions of Employee Engagement Scorecard
[Whitepaper] 5 Dimensions of Employee Engagement Scorecard[Whitepaper] 5 Dimensions of Employee Engagement Scorecard
[Whitepaper] 5 Dimensions of Employee Engagement ScorecardFlevy.com Best Practices
 
[Whitepaper] Digital Transformation: Workforce Digitization
[Whitepaper] Digital Transformation: Workforce Digitization[Whitepaper] Digital Transformation: Workforce Digitization
[Whitepaper] Digital Transformation: Workforce DigitizationFlevy.com Best Practices
 
[Whitepaper] Strategic Human Resources: Evolution of Competition
[Whitepaper] Strategic Human Resources: Evolution of Competition[Whitepaper] Strategic Human Resources: Evolution of Competition
[Whitepaper] Strategic Human Resources: Evolution of CompetitionFlevy.com Best Practices
 
[Whitepaper] 8 Key Steps of Data Integration: Restructuring Redeployment Asse...
[Whitepaper] 8 Key Steps of Data Integration: Restructuring Redeployment Asse...[Whitepaper] 8 Key Steps of Data Integration: Restructuring Redeployment Asse...
[Whitepaper] 8 Key Steps of Data Integration: Restructuring Redeployment Asse...Flevy.com Best Practices
 
[Whitepaper] Strategy Classics: Value Disciplines Model
[Whitepaper] Strategy Classics: Value Disciplines Model[Whitepaper] Strategy Classics: Value Disciplines Model
[Whitepaper] Strategy Classics: Value Disciplines ModelFlevy.com Best Practices
 
[Whitepaper] The Definitive Guide to Strategic Planning: Here’s What You Need...
[Whitepaper] The Definitive Guide to Strategic Planning: Here’s What You Need...[Whitepaper] The Definitive Guide to Strategic Planning: Here’s What You Need...
[Whitepaper] The Definitive Guide to Strategic Planning: Here’s What You Need...Flevy.com Best Practices
 
[Whitepaper] The Definitive Introduction to Strategy Development and Strategy...
[Whitepaper] The Definitive Introduction to Strategy Development and Strategy...[Whitepaper] The Definitive Introduction to Strategy Development and Strategy...
[Whitepaper] The Definitive Introduction to Strategy Development and Strategy...Flevy.com Best Practices
 
[Whitepaper] The “Theory of Constraints:” What’s Limiting Your Organization?
[Whitepaper] The “Theory of Constraints:” What’s Limiting Your Organization?[Whitepaper] The “Theory of Constraints:” What’s Limiting Your Organization?
[Whitepaper] The “Theory of Constraints:” What’s Limiting Your Organization?Flevy.com Best Practices
 
[Whitepaper] Transportation Cost Reduction in Supply Chain Management
[Whitepaper] Transportation Cost Reduction in Supply Chain Management[Whitepaper] Transportation Cost Reduction in Supply Chain Management
[Whitepaper] Transportation Cost Reduction in Supply Chain ManagementFlevy.com Best Practices
 
[Whitepaper] A Great Leadership Experience: Dr. Rachid Yazami, Inventor of th...
[Whitepaper] A Great Leadership Experience: Dr. Rachid Yazami, Inventor of th...[Whitepaper] A Great Leadership Experience: Dr. Rachid Yazami, Inventor of th...
[Whitepaper] A Great Leadership Experience: Dr. Rachid Yazami, Inventor of th...Flevy.com Best Practices
 
[Whitepaper] Finding It Hard to Manage Conflict at the Workplace? Use the Tho...
[Whitepaper] Finding It Hard to Manage Conflict at the Workplace? Use the Tho...[Whitepaper] Finding It Hard to Manage Conflict at the Workplace? Use the Tho...
[Whitepaper] Finding It Hard to Manage Conflict at the Workplace? Use the Tho...Flevy.com Best Practices
 
[Whitepaper] Key Account Management: Handling Large Global Accounts the Right...
[Whitepaper] Key Account Management: Handling Large Global Accounts the Right...[Whitepaper] Key Account Management: Handling Large Global Accounts the Right...
[Whitepaper] Key Account Management: Handling Large Global Accounts the Right...Flevy.com Best Practices
 
[Whitepaper] Nudge Theory: An Effective Way to Transform Negative Behaviors
[Whitepaper] Nudge Theory: An Effective Way to Transform Negative Behaviors[Whitepaper] Nudge Theory: An Effective Way to Transform Negative Behaviors
[Whitepaper] Nudge Theory: An Effective Way to Transform Negative BehaviorsFlevy.com Best Practices
 
[Whitepaper] Business Model Innovation: Creation of Scalable Business Models ...
[Whitepaper] Business Model Innovation: Creation of Scalable Business Models ...[Whitepaper] Business Model Innovation: Creation of Scalable Business Models ...
[Whitepaper] Business Model Innovation: Creation of Scalable Business Models ...Flevy.com Best Practices
 
[Whitepaper] Shareholder Value Traps: How to Evade Them and Focus on Value Cr...
[Whitepaper] Shareholder Value Traps: How to Evade Them and Focus on Value Cr...[Whitepaper] Shareholder Value Traps: How to Evade Them and Focus on Value Cr...
[Whitepaper] Shareholder Value Traps: How to Evade Them and Focus on Value Cr...Flevy.com Best Practices
 

More from Flevy.com Best Practices (20)

100 Case Studies on Strategy & Transformation.pdf
100 Case Studies on Strategy & Transformation.pdf100 Case Studies on Strategy & Transformation.pdf
100 Case Studies on Strategy & Transformation.pdf
 
Project Management for MBA (in French)
Project Management for MBA (in French)Project Management for MBA (in French)
Project Management for MBA (in French)
 
4 Stages of Disruption
4 Stages of Disruption4 Stages of Disruption
4 Stages of Disruption
 
Customer-centric Culture
Customer-centric CultureCustomer-centric Culture
Customer-centric Culture
 
[Whitepaper] Business Transformation Success Factors
[Whitepaper] Business Transformation Success Factors[Whitepaper] Business Transformation Success Factors
[Whitepaper] Business Transformation Success Factors
 
[Whitepaper] 5 Dimensions of Employee Engagement Scorecard
[Whitepaper] 5 Dimensions of Employee Engagement Scorecard[Whitepaper] 5 Dimensions of Employee Engagement Scorecard
[Whitepaper] 5 Dimensions of Employee Engagement Scorecard
 
[Whitepaper] Digital Transformation: Workforce Digitization
[Whitepaper] Digital Transformation: Workforce Digitization[Whitepaper] Digital Transformation: Workforce Digitization
[Whitepaper] Digital Transformation: Workforce Digitization
 
[Whitepaper] Strategic Human Resources: Evolution of Competition
[Whitepaper] Strategic Human Resources: Evolution of Competition[Whitepaper] Strategic Human Resources: Evolution of Competition
[Whitepaper] Strategic Human Resources: Evolution of Competition
 
[Whitepaper] 8 Key Steps of Data Integration: Restructuring Redeployment Asse...
[Whitepaper] 8 Key Steps of Data Integration: Restructuring Redeployment Asse...[Whitepaper] 8 Key Steps of Data Integration: Restructuring Redeployment Asse...
[Whitepaper] 8 Key Steps of Data Integration: Restructuring Redeployment Asse...
 
[Whitepaper] Strategy Classics: Value Disciplines Model
[Whitepaper] Strategy Classics: Value Disciplines Model[Whitepaper] Strategy Classics: Value Disciplines Model
[Whitepaper] Strategy Classics: Value Disciplines Model
 
[Whitepaper] The Definitive Guide to Strategic Planning: Here’s What You Need...
[Whitepaper] The Definitive Guide to Strategic Planning: Here’s What You Need...[Whitepaper] The Definitive Guide to Strategic Planning: Here’s What You Need...
[Whitepaper] The Definitive Guide to Strategic Planning: Here’s What You Need...
 
[Whitepaper] The Definitive Introduction to Strategy Development and Strategy...
[Whitepaper] The Definitive Introduction to Strategy Development and Strategy...[Whitepaper] The Definitive Introduction to Strategy Development and Strategy...
[Whitepaper] The Definitive Introduction to Strategy Development and Strategy...
 
[Whitepaper] The “Theory of Constraints:” What’s Limiting Your Organization?
[Whitepaper] The “Theory of Constraints:” What’s Limiting Your Organization?[Whitepaper] The “Theory of Constraints:” What’s Limiting Your Organization?
[Whitepaper] The “Theory of Constraints:” What’s Limiting Your Organization?
 
[Whitepaper] Transportation Cost Reduction in Supply Chain Management
[Whitepaper] Transportation Cost Reduction in Supply Chain Management[Whitepaper] Transportation Cost Reduction in Supply Chain Management
[Whitepaper] Transportation Cost Reduction in Supply Chain Management
 
[Whitepaper] A Great Leadership Experience: Dr. Rachid Yazami, Inventor of th...
[Whitepaper] A Great Leadership Experience: Dr. Rachid Yazami, Inventor of th...[Whitepaper] A Great Leadership Experience: Dr. Rachid Yazami, Inventor of th...
[Whitepaper] A Great Leadership Experience: Dr. Rachid Yazami, Inventor of th...
 
[Whitepaper] Finding It Hard to Manage Conflict at the Workplace? Use the Tho...
[Whitepaper] Finding It Hard to Manage Conflict at the Workplace? Use the Tho...[Whitepaper] Finding It Hard to Manage Conflict at the Workplace? Use the Tho...
[Whitepaper] Finding It Hard to Manage Conflict at the Workplace? Use the Tho...
 
[Whitepaper] Key Account Management: Handling Large Global Accounts the Right...
[Whitepaper] Key Account Management: Handling Large Global Accounts the Right...[Whitepaper] Key Account Management: Handling Large Global Accounts the Right...
[Whitepaper] Key Account Management: Handling Large Global Accounts the Right...
 
[Whitepaper] Nudge Theory: An Effective Way to Transform Negative Behaviors
[Whitepaper] Nudge Theory: An Effective Way to Transform Negative Behaviors[Whitepaper] Nudge Theory: An Effective Way to Transform Negative Behaviors
[Whitepaper] Nudge Theory: An Effective Way to Transform Negative Behaviors
 
[Whitepaper] Business Model Innovation: Creation of Scalable Business Models ...
[Whitepaper] Business Model Innovation: Creation of Scalable Business Models ...[Whitepaper] Business Model Innovation: Creation of Scalable Business Models ...
[Whitepaper] Business Model Innovation: Creation of Scalable Business Models ...
 
[Whitepaper] Shareholder Value Traps: How to Evade Them and Focus on Value Cr...
[Whitepaper] Shareholder Value Traps: How to Evade Them and Focus on Value Cr...[Whitepaper] Shareholder Value Traps: How to Evade Them and Focus on Value Cr...
[Whitepaper] Shareholder Value Traps: How to Evade Them and Focus on Value Cr...
 

Recently uploaded

Appkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptxAppkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptxappkodes
 
Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Peter Ward
 
Entrepreneurship lessons in Philippines
Entrepreneurship lessons in  PhilippinesEntrepreneurship lessons in  Philippines
Entrepreneurship lessons in PhilippinesDavidSamuel525586
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesKeppelCorporation
 
1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdf1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdfShaun Heinrichs
 
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdfNewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdfKhaled Al Awadi
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Seta Wicaksana
 
Innovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfInnovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfrichard876048
 
Darshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfDarshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfShashank Mehta
 
Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMintel Group
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03DallasHaselhorst
 
Kenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith PereraKenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith Pereraictsugar
 
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckHajeJanKamps
 
TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024Adnet Communications
 
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxmbikashkanyari
 
Call Girls Contact Number Andheri 9920874524
Call Girls Contact Number Andheri 9920874524Call Girls Contact Number Andheri 9920874524
Call Girls Contact Number Andheri 9920874524najka9823
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCRashishs7044
 

Recently uploaded (20)

Appkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptxAppkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptx
 
Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...
 
Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)
 
Entrepreneurship lessons in Philippines
Entrepreneurship lessons in  PhilippinesEntrepreneurship lessons in  Philippines
Entrepreneurship lessons in Philippines
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation Slides
 
1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdf1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdf
 
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdfNewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...
 
Innovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfInnovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdf
 
Darshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfDarshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdf
 
Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 Edition
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03
 
Kenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith PereraKenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith Perera
 
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
 
No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...
No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...
No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...
 
TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024
 
Corporate Profile 47Billion Information Technology
Corporate Profile 47Billion Information TechnologyCorporate Profile 47Billion Information Technology
Corporate Profile 47Billion Information Technology
 
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
 
Call Girls Contact Number Andheri 9920874524
Call Girls Contact Number Andheri 9920874524Call Girls Contact Number Andheri 9920874524
Call Girls Contact Number Andheri 9920874524
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
 

PMP Cost Management (Project Management Professional Exam)

  • 1. PMP – Cost Management Chapter 7
  • 2. Related Definitions Life cycle costing The costing over product life Value analysis (engineering) Analysis to minimize cost of a work Cost risk The risk of cost possessionThis document is a partial preview. Full document download can be found on Flevy: http://flevy.com/browse/document/pmp-cost-management-project-management-professional-exam-1513
  • 3. Plan Cost Management How will you plan cost? How will you manage and control costs and its variences? How the costs will be paid? Which cost accounts are existing and need to create? Which cost will be assigned to which account? How to finance, lease or buy? (also a procurement topic) What is Net present value (NPV) and payback period and internal rate of return of the project? The key benefit of this process is that it provides guidance and direction on how the project costs will be managed throughout the project. This document is a partial preview. Full document download can be found on Flevy: http://flevy.com/browse/document/pmp-cost-management-project-management-professional-exam-1513
  • 4. 7. Cost Management Processes •establishes the policies for planning, managing, expending, and controlling project costs 7.1. Plan Cost management •developing an approximation of the monetary resources needed to complete project activities. 7.2. Estimate costs •aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline 7.3. Determine budget •monitoring the status of the project to update the project costs 7.4. Control costs This document is a partial preview. Full document download can be found on Flevy: http://flevy.com/browse/document/pmp-cost-management-project-management-professional-exam-1513
  • 5. 7.2. Estimate Costs Cost estimates are a prediction that is based on the information known at a given point in time. Cost estimates include the identification and consideration of costing alternatives to initiate and complete the project. Cost estimates are generally expressed in units of some currency (i.e., dollars, euros, yen, etc.), although in some instances other units of measure, such as staff hours or staff days Cost estimates should be reviewed and refined during the course of the project This document is a partial preview. Full document download can be found on Flevy: http://flevy.com/browse/document/pmp-cost-management-project-management-professional-exam-1513
  • 6. Estimation Methods – Time and Cost Bottom-up •Cost of individual work packages or activities is estimated to the greatest level of specified detail Three-Point •Optimistic, pessimistic and most likely 3 points are estimated •Risk register is used •Simple or weighted average is used Analogous •Expert judgement and historical information is used •Previous similar project estimate •Basicly a prediction •Less costly less accurate Parametric •Calculates with data •Uses historical data •Regression and learning curve afffect it •E.g. 1 operator build 20 brick, 40 operators 800 brick. This document is a partial preview. Full document download can be found on Flevy: http://flevy.com/browse/document/pmp-cost-management-project-management-professional-exam-1513
  • 7. Estimate Costs # Have you included these in your project? Response 1 Project management activities cost 2 Assets cost 3 PM’s time cost 4 Labor cost 5 Quality costs 6 Risk management costs (Contingency Reserves cost) 7 Training and other HRM costs 8 Materials cost 9 Rental of PMO cost 10 Management salaries and overhead costs This document is a partial preview. Full document download can be found on Flevy: http://flevy.com/browse/document/pmp-cost-management-project-management-professional-exam-1513
  • 8. Outputs of Estimate Cost •quantitative assessments of the probable costs •can be presented in summary form or in detail Activity Cost estimate •additional details supporting the cost estimate •complete understanding of how the cost estimate was derived •Assumptions, constraints, ranges and confidence levels Basis of estimates This document is a partial preview. Full document download can be found on Flevy: http://flevy.com/browse/document/pmp-cost-management-project-management-professional-exam-1513
  • 9. Determine Budget PM needs to find the total cost of the project and contingency reserves and management reserves. Inputs Cost man.Plan Scope baseline Schedule Activity Cost estimates Basis of estimate HRM plan Risk Register Resource calendar Org. Pro. Assets Ent. Env. Factors Determinebudget Cost aggregation Reserve analysis Expert judgment Historical relationships Funding limit reconcilation Outputs Cost baseline Project funding Requirements Updates to project docs This document is a partial preview. Full document download can be found on Flevy: http://flevy.com/browse/document/pmp-cost-management-project-management-professional-exam-1513
  • 10. Outputs Total funding requirements and periodic funding requirements (e.g., quarterly, annually) are derived from the cost baseline Funding often occurs in incremental amounts that are not continuous This document is a partial preview. Full document download can be found on Flevy: http://flevy.com/browse/document/pmp-cost-management-project-management-professional-exam-1513
  • 11. Why do we use Reserve Analysis as a Control costs Tool? As project progresses the risks identified in planning will happen or not. Therefore, we will have a bright idea if contingency reserves will be needed still or may be removed. On the other hand, regarding Management reserves, as project progresses the unknown risks will appear or not so you can more accurately manage Management Reserves which also influence budget. Reserve analysis is basically update reserve amounts. This document is a partial preview. Full document download can be found on Flevy: http://flevy.com/browse/document/pmp-cost-management-project-management-professional-exam-1513
  • 12. Earned Value Measurement Definitions Acro Terms Meaning PV Planned Value Work planned till today EV Earned Value Work accomplished till today AC Actual Cost Cost till today BAC Budget at completion Budget dedicated to the project EAC Estimate at completion Expection cost at the end ETC Estimate to complete How much more do you need? VAC Variance at completion How much more exceeded your budget? This document is a partial preview. Full document download can be found on Flevy: http://flevy.com/browse/document/pmp-cost-management-project-management-professional-exam-1513
  • 13. Definitions Actual cost. Actual cost (AC) is the realized cost incurred for the work performed on an activity during a specific time period. It is the total cost incurred in accomplishing the work that the EV measured. The AC needs to correspond in definition to what was budgeted in the PV and measured in the EV (e.g., direct hours only, direct costs only, or all costs including indirect costs). The AC will have no upper limit; whatever is spent to achieve the EV will be measured. This document is a partial preview. Full document download can be found on Flevy: http://flevy.com/browse/document/pmp-cost-management-project-management-professional-exam-1513
  • 14. Definitions Cost variance. CV= EV − AC. amount of budget deficit or surplus at a given point in time, expressed as the difference between earned value and the actual cost. It is a measure of cost performance on a project. It is equal to the earned value (EV) minus the actual cost (AC). The cost variance at the end of the project will be the difference between the budget at completion (BAC) and the actual amount spent. The CV is particularly critical because it indicates the relationship of physical performance to the costs spent. Negative CV is often difficult for the project to recover. This document is a partial preview. Full document download can be found on Flevy: http://flevy.com/browse/document/pmp-cost-management-project-management-professional-exam-1513
  • 15. S-curve First draw PV and BAC Then, you can draw EV, AC and EAC according to progression This document is a partial preview. Full document download can be found on Flevy: http://flevy.com/browse/document/pmp-cost-management-project-management-professional-exam-1513
  • 16. Forecasting Term Formula Estimate at completion EAC BAC/CPI AC+ BAC – EV AC + ((BAC-EV)/ (CPI.SPI)) TCPI To complete performance index (BAC-EV)/(BAC-AC) Estimate to complete ETC EAC- AC Variance at completion VAC BAC – EAC This document is a partial preview. Full document download can be found on Flevy: http://flevy.com/browse/document/pmp-cost-management-project-management-professional-exam-1513
  • 17. Method 2 EAC with same rate assumption EAC forecast for ETC work performed at the present CPI. This method assumes what the project has experienced to date can be expected to continue in the future. The ETC work is assumed to be performed at the same cumulative cost performance index (CPI) as that incurred by the project to date. Equation: EAC = BAC / CPI This document is a partial preview. Full document download can be found on Flevy: http://flevy.com/browse/document/pmp-cost-management-project-management-professional-exam-1513
  • 18. Exercise You are managing a software project, heretofore you spent $ 10 Million and controlling department reports tells that your CPI is 1.2 and SPI 1.1, What is your EV? Solution CPI = EV/AC where your AC= 10 million EV = $ 12 million This document is a partial preview. Full document download can be found on Flevy: http://flevy.com/browse/document/pmp-cost-management-project-management-professional-exam-1513
  • 19. Exercise – Interpretation CPI Your CPI is 0.84, what information you can understand from this statement? You are producing 84 cents (kurus) VALUE, out of each $1. You are spending more than planned. You are overbudget. Your CV is negative. You need to be more productive in terms of cost to complete project, on planned budget. Your CPI is 1.2, what information you can understand from this statement? You are producing $1.2 VALUE for each$1. You are spending less than planned. You are under-budget. CV is +. You can achieve you planned budget, if you possess this track and effectiveness. This document is a partial preview. Full document download can be found on Flevy: http://flevy.com/browse/document/pmp-cost-management-project-management-professional-exam-1513
  • 20. Control Costs • roject management plan • Project funding • requirements • Work performance data • .Organizational process assets Inputs • Earned value management • .Forecasting • To-complete performance index (TCPI) • Performance reviews • Project management software • Reserve analysis Tools • Work performance information • Cost forecasts • Change requests • Project management plan update • Project documents updates • Organizational process assets updates Outputs This document is a partial preview. Full document download can be found on Flevy: http://flevy.com/browse/document/pmp-cost-management-project-management-professional-exam-1513
  • 21. EVM This document is a partial preview. Full document download can be found on Flevy: http://flevy.com/browse/document/pmp-cost-management-project-management-professional-exam-1513
  • 22. 1 Flevy (www.flevy.com) is the marketplace for premium documents. These documents can range from Business Frameworks to Financial Models to PowerPoint Templates. Flevy was founded under the principle that companies waste a lot of time and money recreating the same foundational business documents. Our vision is for Flevy to become a comprehensive knowledge base of business documents. All organizations, from startups to large enterprises, can use Flevy— whether it's to jumpstart projects, to find reference or comparison materials, or just to learn. Contact Us Please contact us with any questions you may have about our company. • General Inquiries support@flevy.com • Media/PR press@flevy.com • Billing billing@flevy.com