SlideShare une entreprise Scribd logo
1  sur  73
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014
V5
1/74
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 2/74
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 3/74
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 4/74
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 5/74
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 6/74
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014
So much for our strategy of
winning through technical
dominance
7/74
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014
WBS
SOW
IPTs
IMP
IMS
BOEs
CWBS
8/74
Each element of the PMB is supportive of the others
The integrated whole is the basis of a credible PMB
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014
Attribute Beneficial Outcome from this Attribute
Maturity Flows through
Program Events
 Performance measurement is in units of increasing
maturity of the Technical Performance Measures
 Each event is a mini authorization to proceed
Single outcome for each
work package (AC)
 Measure Physical Percent Complete at the WP level
 Use 0/100 for tasks for the vast majority of work
Technical Performance
Measures are explicitly
visible in the IMS
 Connect Cost, Schedule, and Technical Performance
 EV does not provide a means of adjust for “off TPM,” but
make your own adjustments to the risk numbers for now
Risk retirement explicitly
visible in the IMS
 Risk retirement is embedded in the IMS
 Risk mitigation means waiting until the risk happens
IMS flows vertically 1st
and horizontally 2nd
 All work supports the assessment of maturity
 Isolate tasks dependencies within a Work Package
No Event linkage except
for long lead items
 0/100 requires not partial completion
Decoupled dependences
improves risk
responsiveness
 1st round IMS defines a free flowing process
 Maintaining this decoupling is key to a “dynamic” IMS
that can respond to the natural changes in the program
9/74
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 10/74
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014
Risk Management
Requirements
Contractor Work
Breakdown Structure
(CWBS)
CWBS Dictionary / SOW
Integrated Master Plan
(IMP)
Integrated Master Schedule
(IMS)
Earned Value Management
System
Self Assessment / Award Fee
Determinations / CPAR’s
Technical Performance
Measures (TPM)
Process Metrics
 Specifications
 Work Statements
 Tailored to and outlines entire program and products
 Provides a single numbering system for the program
 States all deliverables and their components
 Follows IPT and CWBS structure
 Descriptions of work traceable to the IMS elements
 Event–driven Plan provides
roadmap of processes for program
 Event–driven Schedule expands IMP
into Work Packages
 Provides details and timing
 Builds in risk mitigation activities
 Connects measures of progress with
measures of increasing maturity
 Connects System
Performance with
Continuous
Technical
Improvements
 Connects Cost
Performance
with the IMS
Performance
 Determined by program execution
11/74
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014
Program
Events
Statement of
Work
CWBS
Significant
Accomplishments
Accomplishment
Criteria
CDRLs and
Deliverables
Tasks Contained
in Work Packages
Measures the progress to plan using Physical & Complete at the Accomplishment Criteria
(AC) and CWBS level
Defines
Aligned Aligned
AlignedAligned
Aligned
Completed SA’s are
entry criteria for
Program Events
Completed Work
Packages are exit
criteria for Tasks
Describes increasing
product maturity as 0/100 or
EVMS SD guidance
Documents the product
maturity that is aligned with
SOW and CWBS
Work necessary to
mature products
grouped by CWBS
Work structure
aligned to
SOW
12/74
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 13/74
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 14/74
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014
DoD Guide DAG SEMP CWBS
IMP
IMS ISE
Technical Reviews
Event Timing of Technical Reviews X X X X X
Success criteria Technical Reviews X X X X X
Include entry and exit criteria for Technical Reviews
in IMP/IMS X X
Assess Technical Maturity in Technical Reviews X X X X
Integrate SEP with: IMP/IMS, TPMs, and EVM X X X X
Integrate CWBS with: Requirements specification,
Statement of Work, and IMP/IMS/EVMS X X X
Link risk management and mitigation plans with
technical reviews, TPM, EVMS, and IMS X
Integrated Reviews
Include Technical Baseline Review (TBR) in IMS; X
Integrated Baseline Review: plans for event based
technical reviews, including entry and exit criteria
Correlation of TPM’s, IMP. IMS, and EVMS
X
15/74
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 16/74
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 17/74
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 18/74
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 19/74
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 20/74
Only put these on your bookshelf after you’ve read them
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 21/74
IMS
IMP
Describes the
strategy for
successful
program
delivery
Supplemental Schedules in CAM Notebook
Tasks Contained in Work Packages
Accomplishment
Criteria
Significant
Accomplishments
Program
Events
Integrated Master Plan (IMP)
 Identifies program events, significant accomplishments, and
accomplishment criteria. System level, controlled document.
Integrated Master Schedule (IMS)
 Logic network schedule of program planned activities
keyed to the imp’s accomplishment criteria
Supplemental Schedule
 Created (as needed) to provide lower
levels of detail data within CAM notebook
 Establishes the structure, parameters and basis for the
integrated master schedule (IMS) development
 Basis of performance measurement system; common
element integrating cost, schedule, & performance
 Constructed to provide integrated planning down to the
work package task level, provides horizontal & vertical
 Supports control account schedules and
the management of day–to–day
operations
traceability, summarization of info and critical path
identification and analysis
schedules and are summarized in the IMS
and part of the program’s PMB
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 22/74
Form IMP
Development
Team
Gather Inputs
Establish
Criteria For
Events
Define And Or
Derive
Deliverable
Products
Define Events
For Program
And Products
Define IPT
Structure To
Implement
Product
Structure
Expand WBS
To IPT
Structure
Produce The
Product IMP
Matrix With
CWBS
Data
Dictionary
IMS Inputs
OBS Update CWBS Update
Define Program
Demonstration
Capabilities
Define
Accomplishments
For Each
Capability
Set Order Of
Program Events
Select Topics For
IMP Narratives
Define Tasks And
Work Products
For Each
Accomplishment
IMS Inputs
Summary Of IMP
With E/A/C
Initial Approval Of
IMP
Demonstrate How
Subject Are
Managed
Release To Baseline
Control For Use By IMS
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014
… is an event–based plan depicting the overall structure of the
program and the key processes and activities. It defines
accomplishments and criteria for each event.
With the IMP, the increasing maturity of the program is stated
explicitly in the Significant Accomplishments (SA) and their
Accomplishment Criteria (AC).
It’s these key processes and activities that are the basis of the
credibility assessment.
Events are NOT milestones, they are mini–Authorizations to
Proceed. These mini-ATPs are the basis of maturity assessments
of the products and services of the program.
Work performed beyond the upcoming Program Event is
actually done “as risk.”
23/74
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 24/74
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 25/74
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 26/74
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 27/74
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 28/74
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 29/74
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 30/74
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014
Through PDR, the majority of the work is building the deliverables from the CDRLs.
Each CDRL should be assigned to a single AC and be connected to a single PE for the defined maturity level.
31/74
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 32/74
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 33/74
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 34/74
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 35/74
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014
 Without an IMP there
is no strategy
 Without an IMP the
us no place for the
work to reside
 Without an IMP there
is no way to answer to
the question: “Why
are we doing this?”
 Without an IMP there
is no way to measure
the increasing
maturity of the
deliverables
36/74
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 37/74
All work flows
vertically from
bottom up.
From Work Package
content to the Exit
Criteria of the WP
(AC), to the
Significant
Accomplishments
(SA) to the Program
Events (PE).
This flow is a
description of the
work that produces
increasing maturity.
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014
38/74
The activities of a
Work Package
“exit” through the
Accomplishment
Criteria (AC).
Interconnections
between Work
Packages at the
task level should
be avoided.
Only 100%
complete work
should start the
next Work
Package.
PE
SA
ACs
Tasks
Completing AC starts
task in next AC
Completed Task
lands on AC
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014
PE
SAs
ACs
Tasks
39/74
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 40/74
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014
Cost Performance Baseline
Schedule Performance Baseline
Technical Performance Baseline
Perform
Functional
Analysis
Determine
Scope and
Approach
Develop
Technical
Logic
Develop
Technical
Baseline
Develop WBS
Define
Activities
Estimate
Time
Durations
Sequence
Activities
Finalize
Schedule
Identify
Apportioned
Milestones
Determine
Resource
Requirements
Prepare Cost
Estimate
Resource
Load
Schedule
Finalize
Apportioned
Milestones
Determine
Funding
Constraints
Approve
PMB
41/74
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 42/74
Program Events
Define the availability
of a Capability at a point in
time.
Accomplishments
Represent requirements
that enable Capabilities.
Criteria
Represent Work Packages that
fulfill Requirements.
Work
Package
Work
Package
Work
Package
Work
Package
Work
Package
Work
Package
Work
Package
Work
package
 The increasing maturing of a product or service is described through Events or Milestones,
Accomplishments, Criteria, and their Work Packages.
 Each Event or Milestone represents the availability of one or more capabilities.
 The presence of these capabilities is measured by the Accomplishments and their Criteria.
 Accomplishments are the pre–conditions for the maturity assessment of the product or service at
each Event or Milestone.
 This hierarchy decomposes the System Capabilities into Requirements, Work Packages, and the
activities which produce deliverables. This hierarchy also describes increasing program maturity
resulting from the activities contained in the Work Packages.
 Performance of the work activities, Work Packages, Criteria, Accomplishments, and Events or
Milestones is measured in units of “physical percent complete” by connecting Earned Value with
Technical Performance Measures.
The Structure of a
Performance Based
Plan
Work
Package
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014
Monthly Status Report:
 Validate schedule status
(start/complete/slip)
 Validate work package
% complete
 Take earned value from % Cmplt
 Identify/process cost ETCs
Weekly Status Report:
 Roll up of lower level schedule
status
 Roll up of lower level % complete
or
 Milestone start/complete
 Milestone slip (early/late,
start/complete)
 Physical % Complete of tasks
Weekly Status Report:
 Milestone start/complete
 Milestone slip (early/late,
start/complete)
 % complete of tasks
Near term Rolling Wave
Control account span
IMS Activities
(at Work Package level
WP’s < 45 work days)
20 to 40
Workday tasks
Or even
weekly tasks
IMS Tasks
(one and two levels
below WP level)
IMP
WBS
Levels
1, 2, and 3
WBS
Levels
4 and 5
WBS’s
Below
Work
Package
Planning Package
43/74
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 44/74
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 45/74
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014
Cost, Schedule, Technical Performance†
WBS
Task 100
Task 101
Task 102
Task 103
Task 104
Task 105
Task 106
†This is a Key concept. This is the part of the process
that integrates the cost and schedule risk impacts to
provide the basis of a credible schedule.
Without Technical Performance measures, Cost and
Schedule cannot show physical percent complete.
Probability
Density
Function
 Research the Project
 Find Analogies
 Ask Endless Questions
 Analyze the Results
 What can go wrong?
 How likely is it to go wrong?
 What is the cause?
 What is the consequence?
Monte Carlo Simulation
Tool is Mandatory
1.0
.8
.6
.4
.2
0 Days, Facilities, Parts, People
Cumulative Distribution Function
Days, Facilities,
Parts and People
46/74
DID–81650 calls out the
details of the IMS and it’s
statistical analysis
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014
A ship on the beach is a lighthouse
to the sea – Dutch Proverb
47/74
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 48/74
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 49/74
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 50/74
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 51/74
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014
 In the example above, the Work Package Managers collectively come to an agreement on how the sequence of
how the work will be performed within each AC.
 The result is a collective ownership of the outcome. This ownership comes from the collective development of
the project plan.
 This process is a Product Development Kaizen (PDK) and used in major aerospace, defense and product
development firms. 52/74
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 53/74
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 54/74
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 55/74
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 56/74
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 57/74
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 58/74
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 59/74
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 60/74
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 61/74
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014
AC: 005
Work Pkg
Work Pkg
Work Pkg
Work Pkg
AC
AC:023
Work Pkg
Work Pkg
Work Pkg
Work Pkg
AC
 The 100% completed work in AC:005 is needed to start the work in AC:023
 In the IMP/IMS paradigm, there is no Task-to-Task connection across
Accomplishment Criteria (AC) boundaries, only within an AC
 The AC-to-AC linking states “…all work in the predecessor AC must be complete
before starting the successor work, assuring the minimum of rework due to
partially defined requirements or partially completed products”
62/74
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014
PE: BPE: A
SA: 001
SA: 002
SA: 003
SA: 004
PE: A
Task
Task
Task
AC: 006
 The best arrangement has the completion of Event A start the first task in Event B.
 All work performed beyond the date of Event A is done at risk.
 At PDR (Event A), approval to proceed Event B (CDR) is given
 Only long lead items should cross Program Event boundaries
 All other work terminates on the Program Event where a formal review of the
planned maturity is conducted – SRR, SFR, PDR, CDR, …
 This topology assures a complete assessment of “progress to plan,” is available at
each Program Event
63/74
SA: 008
PE: B
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 64/74
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014
A Credible Performance Measurement Baseline
Assures Program Management has the needed performance information to deliver
on‒time, on‒budget, and on‒specification
Technical Performance Measures
Cost Schedule
Conventional Earned Value
+
=
 The Master Schedule
used to derive Basis of
Estimate (BOE) not the
other way around.
 Probabilistic cost
estimating uses past
performance and cost risk
modeling.
 Labor, Materiel, and other
direct costs accounted for
in Work Packages.
 Risk adjustments for all
elements of cost.
Cost Baseline
 Earned Value is diluted by
missing technical
performance.
 Earned Value is diluted by
postponed features.
 Earned Value is diluted by
non compliant quality.
 All these dilutions require
adjustments to the
Estimate at Complete
(EAC) and the To
Complete Performance
Index (TCPI).
Technical Performance
 Requirements are
decomposed into physical
deliverables.
 Deliverables are produced
through Work Packages.
 Work Packages are
assigned to accountable
manager.
 Work Packages are
sequenced to form the
highest value stream with
the lowest technical and
programmatic risk.
Schedule Baseline
65/74
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 66/74
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 67/74
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 68/74
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014
Update Contractor
System Spec
Update Program
Development
Allocate
Functional
Reqmts
Update Functional
System Design
Develop HWCI
Specifications
Develop SIL
Specifications
Build Astp1
F-18 IRR
SIL Baseline 1.0
Update SIL Test
Cases
Develop Prelim
SIL CSCI
Critical
Components
AstP 1,2
SSpS 1,2,3
1
2
3
4
6
7
5
8
10
9
11
13
14
15
Update AS Test
I&T on CVN
I&T on LHA
12
Contract Award + 15 days
Systems Requirements Review (SRR)
System Functional Review (SFR)
HW Preliminary Design Review (PDR)
System PDR
EDM 1.0
Baseline
EDM 2.0
Baseline
Mfg Docs
Available
TBD
TRR 1.0
EDM 7-8 TRR
69/74
 Each collection point provides
an assessment of incremental
mission value.
 Defining these points before
the project starts is the basis of
measuring progress to plan.
 Because then you know what
done looks like before it
arrives.
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014
Deliverables
WBS
Tasks and Schedule
Business Need
Process Invoices for
Top Tier Suppliers
1st Level
Electronic Invoice
Submittal
1st Level
Routing to Payables
Department
2nd Level
Payables Account
Verification
2nd Level
Payment Scheduling
2nd Level
Material receipt
verification
2nd Level
“On hand” balance
Updates
Work
Package
(WP)
1 2
3
4
6
5 A
B
Deliverables defined in WP
Terminal Node in the WBS
defines the products or
services that produce the
products of the project
Terminal node of the
WBS defined by a Work
Package.
Tasks within the Work
Package produce the
Deliverables
100% Completion of the
deliverables is the measure of
performance for the Work Package
Management of the
Work Package Tasks is
the responsibility of
the WP Manager.
A decomposition of the work
needed to fulfill the business
requirements
70/74
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 71/74
Maturity ActionProduct Product State
Adjective VerbNoun Verb
CompleteDesignModel/SimPreliminary
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014
Risk: CEV-037 - Loss of Critical Functions During Descent
Planned Risk Level Planned (Solid=Linked, Hollow =Unlinked, Filled=Complete)
RiskScore
24
22
20
18
16
14
12
10
8
6
4
2
0
Conduct Force and Moment Wind
Develop analytical model to de
Conduct focus splinter review
Conduct Block 1 w ind tunnel te
Correlate the analytical model
Conduct w ind tunnel testing of
Conduct w ind tunnel testing of
Flight Application of Spacecra
CEV block 5 w ind tunnel testin
In-Flight development tests of
Damaged TPS flight test
31.Mar.05
5.Oct.05
3.Apr.06
3.Jul.06
15.Sep.06
1.Jun.07
1.Apr.08
1.Aug.08
1.Apr.09
1.Jan.10
16.Dec.10
1.Jul.11
Risk Response
and Risk ID in
IMS
Milestone Date
traceable between
RM Tool and IMS
72/74
Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014
Glen B. Alleman
Niwot Ridge Consulting, LLC
4347 Pebble Beach Drive
Niwot, Colorado 80503
303.241.9633
glen.alleman@niwotridge.com
Performance-Based Project Management®
Integrated Master Plan
Integrated Master Schedule
Earned Value
Risk Management
Proposal Support Services

Contenu connexe

Tendances

Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan DevelopmentGlen Alleman
 
The integrated master plan and integrated master schedule
The integrated master plan and integrated master scheduleThe integrated master plan and integrated master schedule
The integrated master plan and integrated master scheduleGlen Alleman
 
Deliverables based planning handbook
Deliverables based planning handbookDeliverables based planning handbook
Deliverables based planning handbookGlen Alleman
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMGlen Alleman
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan DevelopmentGlen Alleman
 
Measurement News Webinar
Measurement News WebinarMeasurement News Webinar
Measurement News WebinarGlen Alleman
 
Improving Project Performance in the DOE
Improving Project Performance in the DOEImproving Project Performance in the DOE
Improving Project Performance in the DOEGlen Alleman
 
Integrated Agile Software Development with Earned Value Management
Integrated Agile Software Development with Earned Value ManagementIntegrated Agile Software Development with Earned Value Management
Integrated Agile Software Development with Earned Value ManagementGlen Alleman
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for AgileGlen Alleman
 
Build an integrated master plan and integrated master
Build an integrated master plan and integrated masterBuild an integrated master plan and integrated master
Build an integrated master plan and integrated masterGlen Alleman
 
Credible Plans, Integrated Reporting, and Control Systems
Credible Plans, Integrated Reporting, and Control SystemsCredible Plans, Integrated Reporting, and Control Systems
Credible Plans, Integrated Reporting, and Control SystemsGlen Alleman
 
Top habits of successful project managers brown bag (v3.2)
Top habits of successful project managers brown bag (v3.2)Top habits of successful project managers brown bag (v3.2)
Top habits of successful project managers brown bag (v3.2)Glen Alleman
 
Scrum lifecycle for Enterprise IT
Scrum lifecycle for Enterprise ITScrum lifecycle for Enterprise IT
Scrum lifecycle for Enterprise ITGlen Alleman
 
Deliverables Based Planning
Deliverables Based PlanningDeliverables Based Planning
Deliverables Based PlanningGlen Alleman
 
Increasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesIncreasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesGlen Alleman
 
Agile+EVM bibliography (v2)
Agile+EVM bibliography (v2)Agile+EVM bibliography (v2)
Agile+EVM bibliography (v2)Glen Alleman
 
Safe, Reliable, Available, High‒Integrity, and Fault Tolerant Embedded Softwa...
Safe, Reliable, Available, High‒Integrity, and Fault Tolerant Embedded Softwa...Safe, Reliable, Available, High‒Integrity, and Fault Tolerant Embedded Softwa...
Safe, Reliable, Available, High‒Integrity, and Fault Tolerant Embedded Softwa...Glen Alleman
 
SOLVING PROJECT ALLOCATION RESOURCE PROBLEMS WITH AEROSPACE ERP
SOLVING PROJECT ALLOCATION RESOURCE PROBLEMS WITH AEROSPACE ERPSOLVING PROJECT ALLOCATION RESOURCE PROBLEMS WITH AEROSPACE ERP
SOLVING PROJECT ALLOCATION RESOURCE PROBLEMS WITH AEROSPACE ERPKevin West
 
Event based scheduling brown bag
Event based scheduling brown bagEvent based scheduling brown bag
Event based scheduling brown bagGlen Alleman
 

Tendances (20)

Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan Development
 
The integrated master plan and integrated master schedule
The integrated master plan and integrated master scheduleThe integrated master plan and integrated master schedule
The integrated master plan and integrated master schedule
 
Deliverables based planning handbook
Deliverables based planning handbookDeliverables based planning handbook
Deliverables based planning handbook
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPM
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan Development
 
Measurement News Webinar
Measurement News WebinarMeasurement News Webinar
Measurement News Webinar
 
Improving Project Performance in the DOE
Improving Project Performance in the DOEImproving Project Performance in the DOE
Improving Project Performance in the DOE
 
Integrated Agile Software Development with Earned Value Management
Integrated Agile Software Development with Earned Value ManagementIntegrated Agile Software Development with Earned Value Management
Integrated Agile Software Development with Earned Value Management
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for Agile
 
Build an integrated master plan and integrated master
Build an integrated master plan and integrated masterBuild an integrated master plan and integrated master
Build an integrated master plan and integrated master
 
Credible Plans, Integrated Reporting, and Control Systems
Credible Plans, Integrated Reporting, and Control SystemsCredible Plans, Integrated Reporting, and Control Systems
Credible Plans, Integrated Reporting, and Control Systems
 
Top habits of successful project managers brown bag (v3.2)
Top habits of successful project managers brown bag (v3.2)Top habits of successful project managers brown bag (v3.2)
Top habits of successful project managers brown bag (v3.2)
 
Scrum lifecycle for Enterprise IT
Scrum lifecycle for Enterprise ITScrum lifecycle for Enterprise IT
Scrum lifecycle for Enterprise IT
 
Deliverables Based Planning
Deliverables Based PlanningDeliverables Based Planning
Deliverables Based Planning
 
Increasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesIncreasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and Practices
 
Agile+EVM bibliography (v2)
Agile+EVM bibliography (v2)Agile+EVM bibliography (v2)
Agile+EVM bibliography (v2)
 
Safe, Reliable, Available, High‒Integrity, and Fault Tolerant Embedded Softwa...
Safe, Reliable, Available, High‒Integrity, and Fault Tolerant Embedded Softwa...Safe, Reliable, Available, High‒Integrity, and Fault Tolerant Embedded Softwa...
Safe, Reliable, Available, High‒Integrity, and Fault Tolerant Embedded Softwa...
 
SOLVING PROJECT ALLOCATION RESOURCE PROBLEMS WITH AEROSPACE ERP
SOLVING PROJECT ALLOCATION RESOURCE PROBLEMS WITH AEROSPACE ERPSOLVING PROJECT ALLOCATION RESOURCE PROBLEMS WITH AEROSPACE ERP
SOLVING PROJECT ALLOCATION RESOURCE PROBLEMS WITH AEROSPACE ERP
 
Control systems
Control systemsControl systems
Control systems
 
Event based scheduling brown bag
Event based scheduling brown bagEvent based scheduling brown bag
Event based scheduling brown bag
 

En vedette

4 PM Anti-Patterns
4 PM Anti-Patterns4 PM Anti-Patterns
4 PM Anti-PatternsBert Heymans
 
Executive Overview of Managing Agile Programs with Earned Value
Executive Overview of Managing Agile Programs with Earned ValueExecutive Overview of Managing Agile Programs with Earned Value
Executive Overview of Managing Agile Programs with Earned ValueGlen Alleman
 
Promotion flow (v5)
Promotion flow (v5)Promotion flow (v5)
Promotion flow (v5)Glen Alleman
 
Future technologies for business simulations
Future technologies for business simulationsFuture technologies for business simulations
Future technologies for business simulationsMichal Augustini
 
Business Intelligence: Google Enterprise B2B Strategy
Business Intelligence: Google Enterprise B2B StrategyBusiness Intelligence: Google Enterprise B2B Strategy
Business Intelligence: Google Enterprise B2B Strategyaudreyyzerd
 
Parametric project metrics
Parametric project metricsParametric project metrics
Parametric project metricsGlen Alleman
 
Identity Management with midPoint
Identity Management with midPointIdentity Management with midPoint
Identity Management with midPointRadovan Semancik
 
Product development kaizen (PDK)
Product  development kaizen (PDK)Product  development kaizen (PDK)
Product development kaizen (PDK)Glen Alleman
 
Risk Modeling and Analysis (Mitigating the Planning Fallacy)
Risk Modeling and Analysis (Mitigating the Planning Fallacy)Risk Modeling and Analysis (Mitigating the Planning Fallacy)
Risk Modeling and Analysis (Mitigating the Planning Fallacy)PMA Consultants
 
Identity As A Service Evaluation, Implementation, Realized Benefits
Identity As A Service Evaluation, Implementation, Realized BenefitsIdentity As A Service Evaluation, Implementation, Realized Benefits
Identity As A Service Evaluation, Implementation, Realized BenefitsCA Technologies
 
Basis of Estimate Processes
Basis of Estimate ProcessesBasis of Estimate Processes
Basis of Estimate ProcessesGlen Alleman
 
Flawless Execution
Flawless ExecutionFlawless Execution
Flawless ExecutionGlen Alleman
 
Agile in the government
Agile in the government Agile in the government
Agile in the government Glen Alleman
 
Oracle IDAM overview
Oracle IDAM overviewOracle IDAM overview
Oracle IDAM overviewEslam Hafez
 
12.0 risk management agile+evm (v10.2)
12.0 risk management agile+evm (v10.2)12.0 risk management agile+evm (v10.2)
12.0 risk management agile+evm (v10.2)Glen Alleman
 
Overview of Oracle Identity Management - Customer Presentation
Overview of Oracle Identity Management - Customer PresentationOverview of Oracle Identity Management - Customer Presentation
Overview of Oracle Identity Management - Customer PresentationDelivery Centric
 

En vedette (20)

4 PM Anti-Patterns
4 PM Anti-Patterns4 PM Anti-Patterns
4 PM Anti-Patterns
 
Nanorobotics
NanoroboticsNanorobotics
Nanorobotics
 
Executive Overview of Managing Agile Programs with Earned Value
Executive Overview of Managing Agile Programs with Earned ValueExecutive Overview of Managing Agile Programs with Earned Value
Executive Overview of Managing Agile Programs with Earned Value
 
Promotion flow (v5)
Promotion flow (v5)Promotion flow (v5)
Promotion flow (v5)
 
Future technologies for business simulations
Future technologies for business simulationsFuture technologies for business simulations
Future technologies for business simulations
 
Business Intelligence: Google Enterprise B2B Strategy
Business Intelligence: Google Enterprise B2B StrategyBusiness Intelligence: Google Enterprise B2B Strategy
Business Intelligence: Google Enterprise B2B Strategy
 
Parametric project metrics
Parametric project metricsParametric project metrics
Parametric project metrics
 
Identity Management with midPoint
Identity Management with midPointIdentity Management with midPoint
Identity Management with midPoint
 
Product development kaizen (PDK)
Product  development kaizen (PDK)Product  development kaizen (PDK)
Product development kaizen (PDK)
 
Risk management
Risk managementRisk management
Risk management
 
Risk Modeling and Analysis (Mitigating the Planning Fallacy)
Risk Modeling and Analysis (Mitigating the Planning Fallacy)Risk Modeling and Analysis (Mitigating the Planning Fallacy)
Risk Modeling and Analysis (Mitigating the Planning Fallacy)
 
Kantara May 2012
Kantara May 2012Kantara May 2012
Kantara May 2012
 
Identity As A Service Evaluation, Implementation, Realized Benefits
Identity As A Service Evaluation, Implementation, Realized BenefitsIdentity As A Service Evaluation, Implementation, Realized Benefits
Identity As A Service Evaluation, Implementation, Realized Benefits
 
Basis of Estimate Processes
Basis of Estimate ProcessesBasis of Estimate Processes
Basis of Estimate Processes
 
Flawless Execution
Flawless ExecutionFlawless Execution
Flawless Execution
 
Program management-agile
Program management-agileProgram management-agile
Program management-agile
 
Agile in the government
Agile in the government Agile in the government
Agile in the government
 
Oracle IDAM overview
Oracle IDAM overviewOracle IDAM overview
Oracle IDAM overview
 
12.0 risk management agile+evm (v10.2)
12.0 risk management agile+evm (v10.2)12.0 risk management agile+evm (v10.2)
12.0 risk management agile+evm (v10.2)
 
Overview of Oracle Identity Management - Customer Presentation
Overview of Oracle Identity Management - Customer PresentationOverview of Oracle Identity Management - Customer Presentation
Overview of Oracle Identity Management - Customer Presentation
 

Similaire à Building a Credible Performance Measurement Baseling

Chapter 0 of Performance Based Project Management (sm)
Chapter 0 of Performance Based Project Management (sm)Chapter 0 of Performance Based Project Management (sm)
Chapter 0 of Performance Based Project Management (sm)Glen Alleman
 
From WBS to Integrated Master Schedule
From WBS to Integrated Master ScheduleFrom WBS to Integrated Master Schedule
From WBS to Integrated Master ScheduleGlen Alleman
 
From Needed Capabilities to Project Deliverables - On Time, On Budget, On Spe...
From Needed Capabilities to Project Deliverables - On Time, On Budget, On Spe...From Needed Capabilities to Project Deliverables - On Time, On Budget, On Spe...
From Needed Capabilities to Project Deliverables - On Time, On Budget, On Spe...Glen Alleman
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement BaselineGlen Alleman
 
CRM 101: Session 7: Best Practices for Your CRM Implementation
CRM 101: Session 7: Best Practices for Your CRM ImplementationCRM 101: Session 7: Best Practices for Your CRM Implementation
CRM 101: Session 7: Best Practices for Your CRM ImplementationSugarCRM
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure RolloutGlen Alleman
 
Performance based planning in a nut shell (V5)
Performance based planning in a nut shell (V5)Performance based planning in a nut shell (V5)
Performance based planning in a nut shell (V5)Glen Alleman
 
Evm+agile (8.8).chapter 9
Evm+agile (8.8).chapter 9Evm+agile (8.8).chapter 9
Evm+agile (8.8).chapter 9Glen Alleman
 
Risk adjusted engineering management
Risk adjusted engineering managementRisk adjusted engineering management
Risk adjusted engineering managementGlen Alleman
 
Showing how to Increase the Probability of Project Success by applying the ...
Showing how to Increase the Probability of Project Success by applying the ...Showing how to Increase the Probability of Project Success by applying the ...
Showing how to Increase the Probability of Project Success by applying the ...Glen Alleman
 
EVM+Agile the darkside
EVM+Agile the darksideEVM+Agile the darkside
EVM+Agile the darksideGlen Alleman
 
Earned Value Management FAR 34.2 and DFARS 252.234-7001
Earned Value Management  FAR 34.2  and  DFARS 252.234-7001Earned Value Management  FAR 34.2  and  DFARS 252.234-7001
Earned Value Management FAR 34.2 and DFARS 252.234-7001Glen Alleman
 
Deliverables based planning
Deliverables based planning Deliverables based planning
Deliverables based planning Glen Alleman
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by StepGlen Alleman
 
Assure TotalView - Analytics for Application Delivery
Assure TotalView - Analytics for Application DeliveryAssure TotalView - Analytics for Application Delivery
Assure TotalView - Analytics for Application DeliveryAssure
 
Niwot Ridge LLC Capabilities
Niwot Ridge LLC CapabilitiesNiwot Ridge LLC Capabilities
Niwot Ridge LLC CapabilitiesGlen Alleman
 
How to build a credible performance measurement baseline (v5)
How to build a credible performance measurement baseline (v5)How to build a credible performance measurement baseline (v5)
How to build a credible performance measurement baseline (v5)Glen Alleman
 
Performance based management in a nut shell (v5)
Performance based management in a nut shell (v5)Performance based management in a nut shell (v5)
Performance based management in a nut shell (v5)Glen Alleman
 
The Intersection of Earned Value Management and Agile Software Development
The Intersection of Earned Value Management and Agile Software DevelopmentThe Intersection of Earned Value Management and Agile Software Development
The Intersection of Earned Value Management and Agile Software DevelopmentGlen Alleman
 
Implementing Technical Performance Measures
Implementing Technical Performance MeasuresImplementing Technical Performance Measures
Implementing Technical Performance MeasuresGlen Alleman
 

Similaire à Building a Credible Performance Measurement Baseling (20)

Chapter 0 of Performance Based Project Management (sm)
Chapter 0 of Performance Based Project Management (sm)Chapter 0 of Performance Based Project Management (sm)
Chapter 0 of Performance Based Project Management (sm)
 
From WBS to Integrated Master Schedule
From WBS to Integrated Master ScheduleFrom WBS to Integrated Master Schedule
From WBS to Integrated Master Schedule
 
From Needed Capabilities to Project Deliverables - On Time, On Budget, On Spe...
From Needed Capabilities to Project Deliverables - On Time, On Budget, On Spe...From Needed Capabilities to Project Deliverables - On Time, On Budget, On Spe...
From Needed Capabilities to Project Deliverables - On Time, On Budget, On Spe...
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement Baseline
 
CRM 101: Session 7: Best Practices for Your CRM Implementation
CRM 101: Session 7: Best Practices for Your CRM ImplementationCRM 101: Session 7: Best Practices for Your CRM Implementation
CRM 101: Session 7: Best Practices for Your CRM Implementation
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure Rollout
 
Performance based planning in a nut shell (V5)
Performance based planning in a nut shell (V5)Performance based planning in a nut shell (V5)
Performance based planning in a nut shell (V5)
 
Evm+agile (8.8).chapter 9
Evm+agile (8.8).chapter 9Evm+agile (8.8).chapter 9
Evm+agile (8.8).chapter 9
 
Risk adjusted engineering management
Risk adjusted engineering managementRisk adjusted engineering management
Risk adjusted engineering management
 
Showing how to Increase the Probability of Project Success by applying the ...
Showing how to Increase the Probability of Project Success by applying the ...Showing how to Increase the Probability of Project Success by applying the ...
Showing how to Increase the Probability of Project Success by applying the ...
 
EVM+Agile the darkside
EVM+Agile the darksideEVM+Agile the darkside
EVM+Agile the darkside
 
Earned Value Management FAR 34.2 and DFARS 252.234-7001
Earned Value Management  FAR 34.2  and  DFARS 252.234-7001Earned Value Management  FAR 34.2  and  DFARS 252.234-7001
Earned Value Management FAR 34.2 and DFARS 252.234-7001
 
Deliverables based planning
Deliverables based planning Deliverables based planning
Deliverables based planning
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by Step
 
Assure TotalView - Analytics for Application Delivery
Assure TotalView - Analytics for Application DeliveryAssure TotalView - Analytics for Application Delivery
Assure TotalView - Analytics for Application Delivery
 
Niwot Ridge LLC Capabilities
Niwot Ridge LLC CapabilitiesNiwot Ridge LLC Capabilities
Niwot Ridge LLC Capabilities
 
How to build a credible performance measurement baseline (v5)
How to build a credible performance measurement baseline (v5)How to build a credible performance measurement baseline (v5)
How to build a credible performance measurement baseline (v5)
 
Performance based management in a nut shell (v5)
Performance based management in a nut shell (v5)Performance based management in a nut shell (v5)
Performance based management in a nut shell (v5)
 
The Intersection of Earned Value Management and Agile Software Development
The Intersection of Earned Value Management and Agile Software DevelopmentThe Intersection of Earned Value Management and Agile Software Development
The Intersection of Earned Value Management and Agile Software Development
 
Implementing Technical Performance Measures
Implementing Technical Performance MeasuresImplementing Technical Performance Measures
Implementing Technical Performance Measures
 

Plus de Glen Alleman

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planningGlen Alleman
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSGlen Alleman
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project SuccessGlen Alleman
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk managementGlen Alleman
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk ManagementGlen Alleman
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Glen Alleman
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringGlen Alleman
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideGlen Alleman
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineGlen Alleman
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Glen Alleman
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)Glen Alleman
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possibleGlen Alleman
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic AbundanceGlen Alleman
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planningGlen Alleman
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaGlen Alleman
 
Project Management Theory
Project Management TheoryProject Management Theory
Project Management TheoryGlen Alleman
 
Seven Habits of a Highly Effective agile project manager
Seven Habits of a Highly Effective agile project managerSeven Habits of a Highly Effective agile project manager
Seven Habits of a Highly Effective agile project managerGlen Alleman
 
Paradigm of agile project management (update)
Paradigm of agile project management (update)Paradigm of agile project management (update)
Paradigm of agile project management (update)Glen Alleman
 
The 5 Immutable principles of project management
The 5 Immutable principles of project managementThe 5 Immutable principles of project management
The 5 Immutable principles of project managementGlen Alleman
 
Integrating cost, schedule, and technical performance
Integrating cost, schedule, and technical performanceIntegrating cost, schedule, and technical performance
Integrating cost, schedule, and technical performanceGlen Alleman
 

Plus de Glen Alleman (20)

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planning
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMS
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project Success
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk management
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk Management
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems Engineering
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guide
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement Baseline
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possible
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic Abundance
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planning
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six Sigma
 
Project Management Theory
Project Management TheoryProject Management Theory
Project Management Theory
 
Seven Habits of a Highly Effective agile project manager
Seven Habits of a Highly Effective agile project managerSeven Habits of a Highly Effective agile project manager
Seven Habits of a Highly Effective agile project manager
 
Paradigm of agile project management (update)
Paradigm of agile project management (update)Paradigm of agile project management (update)
Paradigm of agile project management (update)
 
The 5 Immutable principles of project management
The 5 Immutable principles of project managementThe 5 Immutable principles of project management
The 5 Immutable principles of project management
 
Integrating cost, schedule, and technical performance
Integrating cost, schedule, and technical performanceIntegrating cost, schedule, and technical performance
Integrating cost, schedule, and technical performance
 

Dernier

Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024BookNet Canada
 
Arizona Broadband Policy Past, Present, and Future Presentation 3/25/24
Arizona Broadband Policy Past, Present, and Future Presentation 3/25/24Arizona Broadband Policy Past, Present, and Future Presentation 3/25/24
Arizona Broadband Policy Past, Present, and Future Presentation 3/25/24Mark Goldstein
 
Assure Ecommerce and Retail Operations Uptime with ThousandEyes
Assure Ecommerce and Retail Operations Uptime with ThousandEyesAssure Ecommerce and Retail Operations Uptime with ThousandEyes
Assure Ecommerce and Retail Operations Uptime with ThousandEyesThousandEyes
 
Moving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdfMoving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdfLoriGlavin3
 
UiPath Community: Communication Mining from Zero to Hero
UiPath Community: Communication Mining from Zero to HeroUiPath Community: Communication Mining from Zero to Hero
UiPath Community: Communication Mining from Zero to HeroUiPathCommunity
 
From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .Alan Dix
 
Why device, WIFI, and ISP insights are crucial to supporting remote Microsoft...
Why device, WIFI, and ISP insights are crucial to supporting remote Microsoft...Why device, WIFI, and ISP insights are crucial to supporting remote Microsoft...
Why device, WIFI, and ISP insights are crucial to supporting remote Microsoft...panagenda
 
Sample pptx for embedding into website for demo
Sample pptx for embedding into website for demoSample pptx for embedding into website for demo
Sample pptx for embedding into website for demoHarshalMandlekar2
 
2024 April Patch Tuesday
2024 April Patch Tuesday2024 April Patch Tuesday
2024 April Patch TuesdayIvanti
 
Modern Roaming for Notes and Nomad – Cheaper Faster Better Stronger
Modern Roaming for Notes and Nomad – Cheaper Faster Better StrongerModern Roaming for Notes and Nomad – Cheaper Faster Better Stronger
Modern Roaming for Notes and Nomad – Cheaper Faster Better Strongerpanagenda
 
Rise of the Machines: Known As Drones...
Rise of the Machines: Known As Drones...Rise of the Machines: Known As Drones...
Rise of the Machines: Known As Drones...Rick Flair
 
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...Wes McKinney
 
Generative Artificial Intelligence: How generative AI works.pdf
Generative Artificial Intelligence: How generative AI works.pdfGenerative Artificial Intelligence: How generative AI works.pdf
Generative Artificial Intelligence: How generative AI works.pdfIngrid Airi González
 
Time Series Foundation Models - current state and future directions
Time Series Foundation Models - current state and future directionsTime Series Foundation Models - current state and future directions
Time Series Foundation Models - current state and future directionsNathaniel Shimoni
 
Potential of AI (Generative AI) in Business: Learnings and Insights
Potential of AI (Generative AI) in Business: Learnings and InsightsPotential of AI (Generative AI) in Business: Learnings and Insights
Potential of AI (Generative AI) in Business: Learnings and InsightsRavi Sanghani
 
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxMerck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxLoriGlavin3
 
(How to Program) Paul Deitel, Harvey Deitel-Java How to Program, Early Object...
(How to Program) Paul Deitel, Harvey Deitel-Java How to Program, Early Object...(How to Program) Paul Deitel, Harvey Deitel-Java How to Program, Early Object...
(How to Program) Paul Deitel, Harvey Deitel-Java How to Program, Early Object...AliaaTarek5
 
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptxUse of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptxLoriGlavin3
 
The Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsThe Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsPixlogix Infotech
 
How to write a Business Continuity Plan
How to write a Business Continuity PlanHow to write a Business Continuity Plan
How to write a Business Continuity PlanDatabarracks
 

Dernier (20)

Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
 
Arizona Broadband Policy Past, Present, and Future Presentation 3/25/24
Arizona Broadband Policy Past, Present, and Future Presentation 3/25/24Arizona Broadband Policy Past, Present, and Future Presentation 3/25/24
Arizona Broadband Policy Past, Present, and Future Presentation 3/25/24
 
Assure Ecommerce and Retail Operations Uptime with ThousandEyes
Assure Ecommerce and Retail Operations Uptime with ThousandEyesAssure Ecommerce and Retail Operations Uptime with ThousandEyes
Assure Ecommerce and Retail Operations Uptime with ThousandEyes
 
Moving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdfMoving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdf
 
UiPath Community: Communication Mining from Zero to Hero
UiPath Community: Communication Mining from Zero to HeroUiPath Community: Communication Mining from Zero to Hero
UiPath Community: Communication Mining from Zero to Hero
 
From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .
 
Why device, WIFI, and ISP insights are crucial to supporting remote Microsoft...
Why device, WIFI, and ISP insights are crucial to supporting remote Microsoft...Why device, WIFI, and ISP insights are crucial to supporting remote Microsoft...
Why device, WIFI, and ISP insights are crucial to supporting remote Microsoft...
 
Sample pptx for embedding into website for demo
Sample pptx for embedding into website for demoSample pptx for embedding into website for demo
Sample pptx for embedding into website for demo
 
2024 April Patch Tuesday
2024 April Patch Tuesday2024 April Patch Tuesday
2024 April Patch Tuesday
 
Modern Roaming for Notes and Nomad – Cheaper Faster Better Stronger
Modern Roaming for Notes and Nomad – Cheaper Faster Better StrongerModern Roaming for Notes and Nomad – Cheaper Faster Better Stronger
Modern Roaming for Notes and Nomad – Cheaper Faster Better Stronger
 
Rise of the Machines: Known As Drones...
Rise of the Machines: Known As Drones...Rise of the Machines: Known As Drones...
Rise of the Machines: Known As Drones...
 
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...
 
Generative Artificial Intelligence: How generative AI works.pdf
Generative Artificial Intelligence: How generative AI works.pdfGenerative Artificial Intelligence: How generative AI works.pdf
Generative Artificial Intelligence: How generative AI works.pdf
 
Time Series Foundation Models - current state and future directions
Time Series Foundation Models - current state and future directionsTime Series Foundation Models - current state and future directions
Time Series Foundation Models - current state and future directions
 
Potential of AI (Generative AI) in Business: Learnings and Insights
Potential of AI (Generative AI) in Business: Learnings and InsightsPotential of AI (Generative AI) in Business: Learnings and Insights
Potential of AI (Generative AI) in Business: Learnings and Insights
 
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxMerck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
 
(How to Program) Paul Deitel, Harvey Deitel-Java How to Program, Early Object...
(How to Program) Paul Deitel, Harvey Deitel-Java How to Program, Early Object...(How to Program) Paul Deitel, Harvey Deitel-Java How to Program, Early Object...
(How to Program) Paul Deitel, Harvey Deitel-Java How to Program, Early Object...
 
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptxUse of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
 
The Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsThe Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and Cons
 
How to write a Business Continuity Plan
How to write a Business Continuity PlanHow to write a Business Continuity Plan
How to write a Business Continuity Plan
 

Building a Credible Performance Measurement Baseling

  • 1. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 V5 1/74
  • 2. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 2/74
  • 3. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 3/74
  • 4. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 4/74
  • 5. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 5/74
  • 6. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 6/74
  • 7. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 So much for our strategy of winning through technical dominance 7/74
  • 8. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 WBS SOW IPTs IMP IMS BOEs CWBS 8/74 Each element of the PMB is supportive of the others The integrated whole is the basis of a credible PMB
  • 9. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 Attribute Beneficial Outcome from this Attribute Maturity Flows through Program Events  Performance measurement is in units of increasing maturity of the Technical Performance Measures  Each event is a mini authorization to proceed Single outcome for each work package (AC)  Measure Physical Percent Complete at the WP level  Use 0/100 for tasks for the vast majority of work Technical Performance Measures are explicitly visible in the IMS  Connect Cost, Schedule, and Technical Performance  EV does not provide a means of adjust for “off TPM,” but make your own adjustments to the risk numbers for now Risk retirement explicitly visible in the IMS  Risk retirement is embedded in the IMS  Risk mitigation means waiting until the risk happens IMS flows vertically 1st and horizontally 2nd  All work supports the assessment of maturity  Isolate tasks dependencies within a Work Package No Event linkage except for long lead items  0/100 requires not partial completion Decoupled dependences improves risk responsiveness  1st round IMS defines a free flowing process  Maintaining this decoupling is key to a “dynamic” IMS that can respond to the natural changes in the program 9/74
  • 10. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 10/74
  • 11. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 Risk Management Requirements Contractor Work Breakdown Structure (CWBS) CWBS Dictionary / SOW Integrated Master Plan (IMP) Integrated Master Schedule (IMS) Earned Value Management System Self Assessment / Award Fee Determinations / CPAR’s Technical Performance Measures (TPM) Process Metrics  Specifications  Work Statements  Tailored to and outlines entire program and products  Provides a single numbering system for the program  States all deliverables and their components  Follows IPT and CWBS structure  Descriptions of work traceable to the IMS elements  Event–driven Plan provides roadmap of processes for program  Event–driven Schedule expands IMP into Work Packages  Provides details and timing  Builds in risk mitigation activities  Connects measures of progress with measures of increasing maturity  Connects System Performance with Continuous Technical Improvements  Connects Cost Performance with the IMS Performance  Determined by program execution 11/74
  • 12. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 Program Events Statement of Work CWBS Significant Accomplishments Accomplishment Criteria CDRLs and Deliverables Tasks Contained in Work Packages Measures the progress to plan using Physical & Complete at the Accomplishment Criteria (AC) and CWBS level Defines Aligned Aligned AlignedAligned Aligned Completed SA’s are entry criteria for Program Events Completed Work Packages are exit criteria for Tasks Describes increasing product maturity as 0/100 or EVMS SD guidance Documents the product maturity that is aligned with SOW and CWBS Work necessary to mature products grouped by CWBS Work structure aligned to SOW 12/74
  • 13. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 13/74
  • 14. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 14/74
  • 15. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 DoD Guide DAG SEMP CWBS IMP IMS ISE Technical Reviews Event Timing of Technical Reviews X X X X X Success criteria Technical Reviews X X X X X Include entry and exit criteria for Technical Reviews in IMP/IMS X X Assess Technical Maturity in Technical Reviews X X X X Integrate SEP with: IMP/IMS, TPMs, and EVM X X X X Integrate CWBS with: Requirements specification, Statement of Work, and IMP/IMS/EVMS X X X Link risk management and mitigation plans with technical reviews, TPM, EVMS, and IMS X Integrated Reviews Include Technical Baseline Review (TBR) in IMS; X Integrated Baseline Review: plans for event based technical reviews, including entry and exit criteria Correlation of TPM’s, IMP. IMS, and EVMS X 15/74
  • 16. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 16/74
  • 17. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 17/74
  • 18. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 18/74
  • 19. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 19/74
  • 20. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 20/74 Only put these on your bookshelf after you’ve read them
  • 21. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 21/74 IMS IMP Describes the strategy for successful program delivery Supplemental Schedules in CAM Notebook Tasks Contained in Work Packages Accomplishment Criteria Significant Accomplishments Program Events Integrated Master Plan (IMP)  Identifies program events, significant accomplishments, and accomplishment criteria. System level, controlled document. Integrated Master Schedule (IMS)  Logic network schedule of program planned activities keyed to the imp’s accomplishment criteria Supplemental Schedule  Created (as needed) to provide lower levels of detail data within CAM notebook  Establishes the structure, parameters and basis for the integrated master schedule (IMS) development  Basis of performance measurement system; common element integrating cost, schedule, & performance  Constructed to provide integrated planning down to the work package task level, provides horizontal & vertical  Supports control account schedules and the management of day–to–day operations traceability, summarization of info and critical path identification and analysis schedules and are summarized in the IMS and part of the program’s PMB
  • 22. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 22/74 Form IMP Development Team Gather Inputs Establish Criteria For Events Define And Or Derive Deliverable Products Define Events For Program And Products Define IPT Structure To Implement Product Structure Expand WBS To IPT Structure Produce The Product IMP Matrix With CWBS Data Dictionary IMS Inputs OBS Update CWBS Update Define Program Demonstration Capabilities Define Accomplishments For Each Capability Set Order Of Program Events Select Topics For IMP Narratives Define Tasks And Work Products For Each Accomplishment IMS Inputs Summary Of IMP With E/A/C Initial Approval Of IMP Demonstrate How Subject Are Managed Release To Baseline Control For Use By IMS
  • 23. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 … is an event–based plan depicting the overall structure of the program and the key processes and activities. It defines accomplishments and criteria for each event. With the IMP, the increasing maturity of the program is stated explicitly in the Significant Accomplishments (SA) and their Accomplishment Criteria (AC). It’s these key processes and activities that are the basis of the credibility assessment. Events are NOT milestones, they are mini–Authorizations to Proceed. These mini-ATPs are the basis of maturity assessments of the products and services of the program. Work performed beyond the upcoming Program Event is actually done “as risk.” 23/74
  • 24. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 24/74
  • 25. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 25/74
  • 26. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 26/74
  • 27. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 27/74
  • 28. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 28/74
  • 29. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 29/74
  • 30. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 30/74
  • 31. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 Through PDR, the majority of the work is building the deliverables from the CDRLs. Each CDRL should be assigned to a single AC and be connected to a single PE for the defined maturity level. 31/74
  • 32. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 32/74
  • 33. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 33/74
  • 34. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 34/74
  • 35. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 35/74
  • 36. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014  Without an IMP there is no strategy  Without an IMP the us no place for the work to reside  Without an IMP there is no way to answer to the question: “Why are we doing this?”  Without an IMP there is no way to measure the increasing maturity of the deliverables 36/74
  • 37. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 37/74 All work flows vertically from bottom up. From Work Package content to the Exit Criteria of the WP (AC), to the Significant Accomplishments (SA) to the Program Events (PE). This flow is a description of the work that produces increasing maturity.
  • 38. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 38/74 The activities of a Work Package “exit” through the Accomplishment Criteria (AC). Interconnections between Work Packages at the task level should be avoided. Only 100% complete work should start the next Work Package. PE SA ACs Tasks Completing AC starts task in next AC Completed Task lands on AC
  • 39. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 PE SAs ACs Tasks 39/74
  • 40. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 40/74
  • 41. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 Cost Performance Baseline Schedule Performance Baseline Technical Performance Baseline Perform Functional Analysis Determine Scope and Approach Develop Technical Logic Develop Technical Baseline Develop WBS Define Activities Estimate Time Durations Sequence Activities Finalize Schedule Identify Apportioned Milestones Determine Resource Requirements Prepare Cost Estimate Resource Load Schedule Finalize Apportioned Milestones Determine Funding Constraints Approve PMB 41/74
  • 42. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 42/74 Program Events Define the availability of a Capability at a point in time. Accomplishments Represent requirements that enable Capabilities. Criteria Represent Work Packages that fulfill Requirements. Work Package Work Package Work Package Work Package Work Package Work Package Work Package Work package  The increasing maturing of a product or service is described through Events or Milestones, Accomplishments, Criteria, and their Work Packages.  Each Event or Milestone represents the availability of one or more capabilities.  The presence of these capabilities is measured by the Accomplishments and their Criteria.  Accomplishments are the pre–conditions for the maturity assessment of the product or service at each Event or Milestone.  This hierarchy decomposes the System Capabilities into Requirements, Work Packages, and the activities which produce deliverables. This hierarchy also describes increasing program maturity resulting from the activities contained in the Work Packages.  Performance of the work activities, Work Packages, Criteria, Accomplishments, and Events or Milestones is measured in units of “physical percent complete” by connecting Earned Value with Technical Performance Measures. The Structure of a Performance Based Plan Work Package
  • 43. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 Monthly Status Report:  Validate schedule status (start/complete/slip)  Validate work package % complete  Take earned value from % Cmplt  Identify/process cost ETCs Weekly Status Report:  Roll up of lower level schedule status  Roll up of lower level % complete or  Milestone start/complete  Milestone slip (early/late, start/complete)  Physical % Complete of tasks Weekly Status Report:  Milestone start/complete  Milestone slip (early/late, start/complete)  % complete of tasks Near term Rolling Wave Control account span IMS Activities (at Work Package level WP’s < 45 work days) 20 to 40 Workday tasks Or even weekly tasks IMS Tasks (one and two levels below WP level) IMP WBS Levels 1, 2, and 3 WBS Levels 4 and 5 WBS’s Below Work Package Planning Package 43/74
  • 44. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 44/74
  • 45. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 45/74
  • 46. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 Cost, Schedule, Technical Performance† WBS Task 100 Task 101 Task 102 Task 103 Task 104 Task 105 Task 106 †This is a Key concept. This is the part of the process that integrates the cost and schedule risk impacts to provide the basis of a credible schedule. Without Technical Performance measures, Cost and Schedule cannot show physical percent complete. Probability Density Function  Research the Project  Find Analogies  Ask Endless Questions  Analyze the Results  What can go wrong?  How likely is it to go wrong?  What is the cause?  What is the consequence? Monte Carlo Simulation Tool is Mandatory 1.0 .8 .6 .4 .2 0 Days, Facilities, Parts, People Cumulative Distribution Function Days, Facilities, Parts and People 46/74 DID–81650 calls out the details of the IMS and it’s statistical analysis
  • 47. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 A ship on the beach is a lighthouse to the sea – Dutch Proverb 47/74
  • 48. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 48/74
  • 49. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 49/74
  • 50. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 50/74
  • 51. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 51/74
  • 52. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014  In the example above, the Work Package Managers collectively come to an agreement on how the sequence of how the work will be performed within each AC.  The result is a collective ownership of the outcome. This ownership comes from the collective development of the project plan.  This process is a Product Development Kaizen (PDK) and used in major aerospace, defense and product development firms. 52/74
  • 53. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 53/74
  • 54. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 54/74
  • 55. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 55/74
  • 56. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 56/74
  • 57. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 57/74
  • 58. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 58/74
  • 59. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 59/74
  • 60. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 60/74
  • 61. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 61/74
  • 62. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 AC: 005 Work Pkg Work Pkg Work Pkg Work Pkg AC AC:023 Work Pkg Work Pkg Work Pkg Work Pkg AC  The 100% completed work in AC:005 is needed to start the work in AC:023  In the IMP/IMS paradigm, there is no Task-to-Task connection across Accomplishment Criteria (AC) boundaries, only within an AC  The AC-to-AC linking states “…all work in the predecessor AC must be complete before starting the successor work, assuring the minimum of rework due to partially defined requirements or partially completed products” 62/74
  • 63. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 PE: BPE: A SA: 001 SA: 002 SA: 003 SA: 004 PE: A Task Task Task AC: 006  The best arrangement has the completion of Event A start the first task in Event B.  All work performed beyond the date of Event A is done at risk.  At PDR (Event A), approval to proceed Event B (CDR) is given  Only long lead items should cross Program Event boundaries  All other work terminates on the Program Event where a formal review of the planned maturity is conducted – SRR, SFR, PDR, CDR, …  This topology assures a complete assessment of “progress to plan,” is available at each Program Event 63/74 SA: 008 PE: B
  • 64. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 64/74
  • 65. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 A Credible Performance Measurement Baseline Assures Program Management has the needed performance information to deliver on‒time, on‒budget, and on‒specification Technical Performance Measures Cost Schedule Conventional Earned Value + =  The Master Schedule used to derive Basis of Estimate (BOE) not the other way around.  Probabilistic cost estimating uses past performance and cost risk modeling.  Labor, Materiel, and other direct costs accounted for in Work Packages.  Risk adjustments for all elements of cost. Cost Baseline  Earned Value is diluted by missing technical performance.  Earned Value is diluted by postponed features.  Earned Value is diluted by non compliant quality.  All these dilutions require adjustments to the Estimate at Complete (EAC) and the To Complete Performance Index (TCPI). Technical Performance  Requirements are decomposed into physical deliverables.  Deliverables are produced through Work Packages.  Work Packages are assigned to accountable manager.  Work Packages are sequenced to form the highest value stream with the lowest technical and programmatic risk. Schedule Baseline 65/74
  • 66. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 66/74
  • 67. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 67/74
  • 68. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 68/74
  • 69. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 Update Contractor System Spec Update Program Development Allocate Functional Reqmts Update Functional System Design Develop HWCI Specifications Develop SIL Specifications Build Astp1 F-18 IRR SIL Baseline 1.0 Update SIL Test Cases Develop Prelim SIL CSCI Critical Components AstP 1,2 SSpS 1,2,3 1 2 3 4 6 7 5 8 10 9 11 13 14 15 Update AS Test I&T on CVN I&T on LHA 12 Contract Award + 15 days Systems Requirements Review (SRR) System Functional Review (SFR) HW Preliminary Design Review (PDR) System PDR EDM 1.0 Baseline EDM 2.0 Baseline Mfg Docs Available TBD TRR 1.0 EDM 7-8 TRR 69/74  Each collection point provides an assessment of incremental mission value.  Defining these points before the project starts is the basis of measuring progress to plan.  Because then you know what done looks like before it arrives.
  • 70. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 Deliverables WBS Tasks and Schedule Business Need Process Invoices for Top Tier Suppliers 1st Level Electronic Invoice Submittal 1st Level Routing to Payables Department 2nd Level Payables Account Verification 2nd Level Payment Scheduling 2nd Level Material receipt verification 2nd Level “On hand” balance Updates Work Package (WP) 1 2 3 4 6 5 A B Deliverables defined in WP Terminal Node in the WBS defines the products or services that produce the products of the project Terminal node of the WBS defined by a Work Package. Tasks within the Work Package produce the Deliverables 100% Completion of the deliverables is the measure of performance for the Work Package Management of the Work Package Tasks is the responsibility of the WP Manager. A decomposition of the work needed to fulfill the business requirements 70/74
  • 71. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 71/74 Maturity ActionProduct Product State Adjective VerbNoun Verb CompleteDesignModel/SimPreliminary
  • 72. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 Risk: CEV-037 - Loss of Critical Functions During Descent Planned Risk Level Planned (Solid=Linked, Hollow =Unlinked, Filled=Complete) RiskScore 24 22 20 18 16 14 12 10 8 6 4 2 0 Conduct Force and Moment Wind Develop analytical model to de Conduct focus splinter review Conduct Block 1 w ind tunnel te Correlate the analytical model Conduct w ind tunnel testing of Conduct w ind tunnel testing of Flight Application of Spacecra CEV block 5 w ind tunnel testin In-Flight development tests of Damaged TPS flight test 31.Mar.05 5.Oct.05 3.Apr.06 3.Jul.06 15.Sep.06 1.Jun.07 1.Apr.08 1.Aug.08 1.Apr.09 1.Jan.10 16.Dec.10 1.Jul.11 Risk Response and Risk ID in IMS Milestone Date traceable between RM Tool and IMS 72/74
  • 73. Performance-Based Project Management ®, Copyright © Glen B. Alleman, 2012, 2013, 2014 Glen B. Alleman Niwot Ridge Consulting, LLC 4347 Pebble Beach Drive Niwot, Colorado 80503 303.241.9633 glen.alleman@niwotridge.com Performance-Based Project Management® Integrated Master Plan Integrated Master Schedule Earned Value Risk Management Proposal Support Services