The document discusses establishing a Performance Measurement Baseline (PMB) which defines the schedule, budget, and organizational elements for all work to be performed. It notes that a PMB includes technical, schedule, and cost baselines needed for project success. The six steps to build a PMB are outlined: 1) decompose scope into a work breakdown structure (WBS) and work packages, 2) assign responsibility for work packages, 3) arrange work packages in a network, 4) develop a time-phased budget, 5) assign performance measures, and 6) establish the performance baseline. Critical success factors include ensuring deliverables represent required capabilities and value and that work package completion is represented by physical percent complete metrics.
1. Establishing the Performance
Measurement Baseline (PMB)
The Performance Measurement Baseline is a time–
phased schedule of all the work to be performed, the
budgeted cost for this work, and the organizational
elements that produce the deliverables from this work.
Glen B. Alleman
Vice President, Strategy and Performance Management
Lewis & Fowler
8310 South Valley Highway
Suite 300
Englewood, Colorado 80112
www.lewisandfowler.com
galleman@lewisandfowler.com
PMB for COS 2008.pptx
2. The Processes Surrounding the
Performance Measurement Baseline
PMI College of Scheduling
“PMI” is a registered trade and service markof the Project Management Institute, Inc.
2
Identify Needed
Business
Capabilities
Establish a
Performance
Measurement
Baseline
Execute the
Performance
Measurement
Baseline
Capabilities
Based Plan
Business Value
Stream
Earned Value
Performance
Technical
Performance
Measures
Business Value
Stream
Technical
Requirements
Establish a
Requirements
Baseline
Technical
Performance
Measures
PMB
3. There are 3 PMBs on Every Project
Technical, Schedule, and Cost Baselines are
needed for success
Building these requires an integrated effort
PMI College of Scheduling
“PMI” is a registered trade and service markof the Project Management Institute, Inc.
3
Establish Cost Baseline
Establish Schedule Baseline
Establish Technical Baseline
Perform
Functional
Analysis
Determine
Scope and
Approach
Develop
Technical Logic
Develop
Technical
Baseline
Develop WBS
Define
Activities
Estimate Time
Durations
Sequence
Activities
Finalize
Schedule
Identify
Apportioned
Milestones
Determine
Resource
Requirements
Prepare Cost
Estimate
Resource Load
Schedule
Finalize
Apportioned
Milestones
Determine
Funding
Constraints
Approve PMB
4. The Six Steps to Build the Performance
Measurement Baseline
PMI College of Scheduling
“PMI” is a registered trade and service markof the Project Management Institute, Inc.
4
Decompose the Project Scope into a product based Work
Breakdown Structure and then into Work Packages which
describe the production of all deliverables
Decompose
Scope
Assign Responsibility for Work Packages to named owners who
are accountable for the management of resource allocation and
cost baseline, and technical performance
Assign
Responsibility
Arrange the Work Packages in a well formed network with
explicitly defined deliverables, milestones and internal and
external dependencies
Arrange Work
Packages
Develop Time–Phased Budget (BCWS) from labor spreads in each
Work Package and balance these BCWS spreads across the
Project.
Develop
BCWS
Assign Objective Performance Measures for each Work Package
and summarize these for the Project as a whole. Use the
0%/100% measurement of complete whenever possible.
Assign
Performance
Measures
Establish a Performance Measurement Baseline to be used
forecasting Work Package and Project ongoing and completion
metrics.
Set
Performance
Baseline
5. These Definitions Will Help Clarify What
We’re Talking About
Deliverables Based Planning – focused on
tangible outcomes
Work Package – a unique collection of
deliverables with resources and deliverables
Performance Measurement Baseline – forecasts
of future performance come from past
performance
Performance Based Earned Value® – a means of
measuring progress using cost, schedule and
technical performance
PMI College of Scheduling
“PMI” is a registered trade and service markof the Project Management Institute, Inc.
5
6. Critical Success Factors For The
Performance Measurement Baseline
Deliverables represent the required business
capabilities and its value as defined by the business
and shared by the development team.
When all deliverables and their Work Packages are
completed, they are not revisited or reopened
– They are 100% done
The progression of Work Packages defines the
increasing maturity of the project
– The business value of the deliverables to the customer
increases as Work Packages are completed
Completion of Work Packages is represented by the
Physical Percent Completion of the project
– Either 0%/100% or Apportioned Milestones are used to
state the completion of each Work Package
PMI College of Scheduling
“PMI” is a registered trade and service markof the Project Management Institute, Inc.
6
7. Success Of The PMB Depends On
Identifying Measureable Results
PMI College of Scheduling
“PMI” is a registered trade and service markof the Project Management Institute, Inc.
7
What gets measured gets done1
If you don’t measure results, you can’t tell success from failure2
If you can’t see success, you can’t reward it3
If you can’t reward success, you’re probably rewarding failure4
If you can demonstrate results, you can remain credible7
If you can’t see success, you can’t learn from it5
If you can’t see failure, you can’t correct it6
8. Decompose The Scope Into A Proper “Tree”
PMI College of Scheduling
“PMI” is a registered trade and service markof the Project Management Institute, Inc.
8
Business Capability
Process Invoices for
Top Tier Suppliers
1st Level
Electronic Invoice
Submittal
1st Level
Routing to Payables
Department
2nd Level
Payables Account
Verification
2nd Level
Payment Scheduling
2nd Level
Material receipt
verification
2nd Level
“On hand” balance
Updates
9. Use This “Tree” To Decompose The
Project Scope Into Work Packages
The lowest level of the Work Breakdown
Structure defines the Work Packages which
contain named deliverables
The parents of these Work Packages collect the
business capabilities described in the baseline
requirements
The narrative of each Work Package is the WBS
Dictionary
PMI College of Scheduling
“PMI” is a registered trade and service markof the Project Management Institute, Inc.
9
10. What Does A Good Work Package
“NOT” Look Like?
PMI College of Scheduling
“PMI” is a registered trade and service markof the Project Management Institute, Inc.
10
What NOT to do Instead Think About
It’s NOT a laundry list of work to be
done
It’s a decomposition of the
products, services, and data
generated by those
It’s NOT a functional decomposition That’s the role of the Organizational
Breakdown Structure (OBS)
It’s NOT a direct map of the
requirements
Requirements produce products and
services, but are not one for one
with the WBS
It’s NOT a reflection of the
underlying product or service
partitioning
This is done later in the program
strategy
It’s NOT the first structure you might
think of…
Build the WBS several times, assess
its usefulness in describing the
products and services
11. What Is “NOT” In A Work Package?
Elements that are not products
Project phases
Rework, retesting, and refurbishing are not
separate elements in the WBS
Non–recurring and recurring are not classes of
work
Cost saving efforts like TQM and Lean are part of
the Level of Effort Workstream
Cost for meetings, travel, computer support are
part of the level of effort Workstream
PMI College of Scheduling
“PMI” is a registered trade and service markof the Project Management Institute, Inc.
11
12. Some Attributes Of A Good Work Package
All terminal nodes describe some end item in the
project – a product or a service
Each physical deliverable is testable in some
manner to demonstrate it is working
The WBS is an increasing fidelity description of
the deliverables produced by the project
The WBS articulates what the customer wants in
terms of deliverables – the products or services
produced by the project
PMI College of Scheduling
“PMI” is a registered trade and service markof the Project Management Institute, Inc.
12
13. A Deliverables Focused Work
Breakdown Structure (WBS)
From the requirements Tree construct a list of
Capabilities needed to satisfy the customer
needs
From this list of Capabilities construct a list of
Deliverables that will fulfill the customer needs
Arrange these deliverables into major systems
This has likely already been done…so let’s have a
hands on exercise to draw this out
PMI College of Scheduling
“PMI” is a registered trade and service markof the Project Management Institute, Inc.
13
14. The Work Breakdown Structure
Connections With The Work Packages
Product or services oriented
Includes all work in the project
Each element logically aggregates those
elements below it
Reflects the manner in which the work will be
done
PMI College of Scheduling
“PMI” is a registered trade and service markof the Project Management Institute, Inc.
14
The WBS becomes the framework for Cost,
Schedule, and Technical Performance Measurement.
The WBS is the organizational structure for the Work
Packages
15. Connect The WBS To Work Packages And Then
Define The Tasks To Produce The Deliverables
PMI College of Scheduling
“PMI” is a registered trade and service markof the Project Management Institute, Inc.
15
Deliverables
WBS
Tasks and Schedule
Business Need
Process Invoices for Top Tier
Suppliers
1st Level
Electronic Invoice Submittal
1st Level
Routing to Payables Department
2nd Level
Payables Account Verification
2nd Level
Payment Scheduling
2nd Level
Material receipt verification
2nd Level
“On hand” balance Updates
Work
Package
1 2
3
4
6
5 A
B
Deliverables defined in WP
Terminal Node in the WBS
defines the products or
services of the project
Terminal node of the
WBS defined by a Work
Package
Tasks within the Work
Package produce the
Deliverables
100% Completion of deliverables is
the measure of performance for the
Work Package
Management of the
Work Package Tasks is
the responsibility of
the WP Manager.
These are not held in
the master plan
A decomposition of the work
needed to fulfill the business
requirements
16. Steps In Building The Work Packages
Step 1 – define what is going to be delivered to
produce business value
– One or more Deliverables produced within a Work
Package
Step 2 – define the effort and duration along with
the confidence levels
– Only effort and total duration
– Level of confidence for effort and duration
PMI College of Scheduling
“PMI” is a registered trade and service markof the Project Management Institute, Inc.
16
17. Decompose Business Capabilities Into
Deliverables, Then Work Packages, Then
Measurable Outcomes
PMI College of Scheduling
“PMI” is a registered trade and service markof the Project Management Institute, Inc.
17
Business
Capabilities
Capability
Number 1
Capability
Number 2
Deliverable
Number 1.1
Deliverable
Number 1.2
Deliverable
Number 1.3
Deliverable
Number 1.4
Work Package
Number 1
Work Package
Number 2
Work Package
Number 3
50% Milestone
50% Milestone
100% Milestone
100% Milestone
Deliverable
Number 2.1
Work Package
Number 4
100% Milestone
Deliverable
Number 2.1
Deliverable
Number 2.1
Work Package
Number 5
25% Milestone
75% Milestone
Increasing Detail of the Planning Outcomes
Increasing Value to the Customer
18. Step 1: Define The Deliverables And Their
Apportioned Value
PMI College of Scheduling
“PMI” is a registered trade and service markof the Project Management Institute, Inc.
18
Description Deliverable(s) Apportioned Milestones
Transaction processing
integration test
complete
Test plan compete and
approved
Author – 50%
Approval – 50%
Define integration
testing environment
Integration Test Plan complete
Test platform equipment
defined
Test environment defined
Test Plan – 25%
Equipment List – 50%
Environment – 25%
Business processes
defined and approved
Business process flow diagram 100%
User acceptance testing
defined
User Acceptance Plan
Developed
100%
User Acceptance Testing
Conducted
Test environment operational
User Acceptance Testing
performed with 90% success
UAT errors documented and
allocated for repair in next
release
Environment – 20%
UAT Conducted – 70%
Errors documented –
10%
19. Step 2: Define The Effort, Duration, And
Confidence Intervals
PMI College of Scheduling
“PMI” is a registered trade and service markof the Project Management Institute, Inc.
19
Description
Duration
Duration
Confidence
Effort
Effort
Confidence
Transaction processing integration test
complete
10w 1 2680h 2
Define integration testing environment 4w 1 480h 1
Business processes defined and
approved
6w 2 1200h 1
User acceptance testing defined 3w 2 800h 2
User acceptance testing conducted 4w 1 200h 1
20. Baseline Contents of a Work Package
Description
Assumptions
Earned Value Method
Basis of Estimate
Predecessors and
successors
Strategy for delivery
Completion criteria
Contents of the
deliverables
Responsibilities
Estimated duration
Estimated effort
Confidence intervals
Resources
PMI College of Scheduling
“PMI” is a registered trade and service markof the Project Management Institute, Inc.
20
In theory there is no
difference between
theory and practice. In
practice there is.
21. Use Word Or Excel, It Doesn’t Matter
Just Capture The Contents In One Place
PMI College of Scheduling
“PMI” is a registered trade and service markof the Project Management Institute, Inc.
21
No matter what form is used, the function of the Work Package must
communicate to the participants the baseline information described in
the Table of Contents of the previous page.
22. Naming Work Packages May Seem
Simple – But What’s In A Name?
The name should convey not only the work activities but
also the delivered result of these activities
The project plan and the list of Work Packages is the
concise statement of the work for the project – all held in a
single place – the Project Plan
PMI College of Scheduling
“PMI” is a registered trade and service markof the Project Management Institute, Inc.
22
Maturity Action Product Product State
Adjective Verb Noun Verb
Demonstrates
Maturity
A step in the
process
End Item Final Status
Preliminary Design Processes Complete
Preliminary design of transaction processes complete
23. Work Package Description
A clear and concise description of what the Work
Package produces in terms of deliverables
This is your elevator pitch when someone asks
“what does the Work Package you’re working on
do when its all done?”
Deliverables are meaning to the customer –
speak in deliverables terms
PMI College of Scheduling
“PMI” is a registered trade and service markof the Project Management Institute, Inc.
23
If you can’t tell the story
between the lobby and the
9th floor, then you haven't
got a clear picture of what
“done” looks like.
24. Assumptions
Make it clear (and concise) what you expect to be
in place before the Work Package starts
State these in terms of deliverables themselves
– What they are
– Who you’re getting them from
– A little bit of why you need them
Have a mitigation plan when the assumption
isn’t true
PMI College of Scheduling
“PMI” is a registered trade and service markof the Project Management Institute, Inc.
24
Assumptions
are repulsive,
especially to
gravity.
25. Earned Value Method
Think about how you would measure 100% done.
– Done, done
– Not, almost done
– Not, “I’ll be done soon”
If the Work Package is self contained and 100%
done occurs at the end of the WP then use that
If the Work Package has more than one
deliverable or the deliverable has incremental
functionality then Apportioned Milestones can be
used
PMI College of Scheduling
“PMI” is a registered trade and service markof the Project Management Institute, Inc.
25
Earned Value is how physical progress is measured
in the Performance Measurement Baseline.
Only delivered value to the customer is important.
26. Responsibilities
Each Work Package has one and only one person
Accountable for the successful delivery of the
Work Package
– Put that person’s name on the Work Package
PMI College of Scheduling
“PMI” is a registered trade and service markof the Project Management Institute, Inc.
26
WBS
OBS
The Work
Packages are
where the work
and the people
come together
27. Assign The Responsibilities And Make A
Single Person Accountable
PMI College of Scheduling
“PMI” is a registered trade and service markof the Project Management Institute, Inc.
27
28. Arrange The Work Packages Into A “Well
Formed” Network
PMI College of Scheduling
“PMI” is a registered trade and service markof the Project Management Institute, Inc.
28
2nd Level
Payables Account
Verification
2nd Level
Payment
Scheduling
2nd Level
Material receipt
verification
2nd Level
“On hand” balance
Updates
29. A “Well Formed” Network Has Specific
Attributes
Arrange Work Packages in a “Finish to Start”
network
No Leads or Lags
No Constraints – only “As Soon As Possible”
(ASAP)
This network of Work Packages is the flow on
increasing maturity of the deliverables from the
project
PMI College of Scheduling
“PMI” is a registered trade and service markof the Project Management Institute, Inc.
29
30. “Arranging” the Work Packages Is
Iterative And Incremental
PMI College of Scheduling
“PMI” is a registered trade and service markof the Project Management Institute, Inc.
30
In the example above, the Work Package Managers collectively come to an agreement on
how the sequence of how the work will be performed.
The result is a collective ownership of the outcome. This ownership comes from the
collective development of the project plan.
This process is a Product Development Kaizen (PDK)
31. Develop A Time–Phased Budget
PMI College of Scheduling
“PMI” is a registered trade and service markof the Project Management Institute, Inc.
31
2nd Level System
Payables Account
Verification
2nd Level System
Payment
Scheduling
2nd Level System
Material receipt
verification
2nd Level System
“On hand” balance
Updates Duration of the Work Package
BCWS
Duration of the Work Package
BCWS
Duration of the Work Package
BCWS
Duration of the Work Package
BCWS
33. Identify Objective Measures Of
Performance For Each Work Package
Define the Planned Value for each Work Package
completion or apportioned milestone within a
Work Package
Only Physical Percent Complete should be used
to measure progress – there can be no personal
“opinions” of progress
PMI College of Scheduling
“PMI” is a registered trade and service markof the Project Management Institute, Inc.
33
Physical Percent Complete CummBCWP BCWS
34. Set The Performance Baseline
Baselining the Performance Measurement
Baseline is the beginning of Executing the
project plan
Without the baseline and the change control over
this baseline, the performance predictions will
be difficult
PMI College of Scheduling
“PMI” is a registered trade and service markof the Project Management Institute, Inc.
34
There are two phases of any complex project …
Too early to tell and too late to stop
35. Build The Apportioned Milestones And
Assign Physical Percent Complete
Identify each incremental deliverable in the
Work Package
Assign an apportioned value to that deliverable
Document the evidentiary materials for the
incremental deliverable and its assigned
percentage value
Identify the delivery date for the apportioned
milestone in the schedule
PMI College of Scheduling
“PMI” is a registered trade and service markof the Project Management Institute, Inc.
35
1 mile = 1,000 (mille) paces
= 1,640 yards .
Introduced to Britain by the Romans
The passage of a milestone meant progress to the destination.
But it is critical to pre-assign value to each milestone and record
this value as the milestone is passed
36. Assemble The Work Packages Into A
Credible Schedule
Start with Work Packages and their total BCWS
spreads
– Total WP duration – in the Duration field
– Total WP work effort – in the Work field
– Start dates aligned with the project start date defined
in the Project menu
– The result is a Gantt–style picture of the flow of WP
value
PMI College of Scheduling
“PMI” is a registered trade and service markof the Project Management Institute, Inc.
36
Henry Laurence Gantt, A.B., M.E
1861–1919
37. Project Maturity Flow Is The Incremental
Delivery Of Business Capabilities
PMI College of Scheduling
“PMI” is a registered trade and service markof the Project Management Institute, Inc.
37
Pilot
Data
Enrollment
Integrators
Quality Monitor
Internal
Router
External Interfaces
Finance Loss
Data Store Lookup
Data Warehouse
Data Marts
Data Marts
Portals and others
Billing
Resale's
Emulations
Demo conversion process, member reconciliation
Shared group matrix reports and interfaces
Shared member crosswalk and members to ERP
Integrators in ERP converted to inventory
Status and trigger conversions
Data in Marts for ERP
Material Master
Converted from legacy
External Vendors
converted to ERP
TBD
Vendors from legacy
Material converted end–
to–end
38. Analyzing And Assessing The Network Of
Work Packages Requires Understanding
Critical path
Accuracy
Integration
Realism
Performance
Variances
Forecasting
What–If Analysis
Risk
Resources
PMI College of Scheduling
“PMI” is a registered trade and service markof the Project Management Institute, Inc.
38
A credible schedule cannot
be just a list of activities. It
must be an accurate model
of the project strategy and
execution that can be
analyzed, assessed, and
used to answer risk based
questions.
39. A “Very” Simple Risk Management Process Is
Needed To Establish Credibility
PMI College of Scheduling
“PMI” is a registered trade and service markof the Project Management Institute, Inc.
39
Planning Identification Analysis Handling
Communication
and
Tracking
Build the process for managing risk
Allocate responsibilities at the project level
Determine What is to be Risk–Managed
Do a comparative analysis of the risks
Assign risk attributes
Assign risk ownership
Evaluate the impact of each risk
“A” Risk
“All” Risks
Prepare risk decision–packages
Define the Decision–Making Process
Iterate the analysis to select mitigation
Keep everyone aware of decisions made
Track progress
Evaluate effectiveness of the risk management processes
“Risk Analysis Techniques, Schedule, Cost and Other Aspects, INCOSE Heartland
Chapter October 24, 2001, Futon Corporation
40. Integrating Cost, Schedule, And
Technical Performance
PMI College of Scheduling
“PMI” is a registered trade and service markof the Project Management Institute, Inc.
40
Cost, Schedule, Technical Model†
WBS
Task 100
Task 101
Task 102
Task 103
Task 104
Task 105
Task 106 † This is a Key concept. This is the part of the process that
integrates the cost and schedule risk impacts to provide the
basis of a credible schedule.
Probability
Density
Function
Research the Project
Find Analogies
Ask Endless Questions
Analyze the Results
What can go wrong?
How likely is it to go wrong?
What is the cause?
What is the consequence?
Monte Carlo Simulation
Tool is Mandatory
1.0
.8
.6
.4
.2
0 Days, Facilities, Parts, People
Cumulative Distribution Function
Days, Facilities,
Parts and People
41. There Is Technical And Programmatic
Risk – Both Must Be Addressed
• There are two types of “uncertainty”
on any sufficiently complex project:
– Technical – uncertainty about the
functional and performance
aspects of the project's technology
that impacts the produceability of
the product or creates delays in the
schedule
– Programmatic – uncertainty about
the duration and cost of the
activities that deliver the functional
and performance elements of the
project, independent of the
technical risk
PMI College of Scheduling
“PMI” is a registered trade and service markof the Project Management Institute, Inc.
41
So much for our strategy of winning
through technical dominance
42. Wrap Up
PMI College of Scheduling
“PMI” is a registered trade and service markof the Project Management Institute, Inc.
42
A good plan, violently executed
now is better than a perfect plan
executed next week
– General George S. Patton
43. In The End Its All About The Schedule
• A slipping schedule is simply unacceptable
• “Attack” the schedule as soon as possible and
never stop attacking
• Update schedules monthly or more frequently,
look at it everyday
• Earned Value really works if – and this is a big if –
you are ruthless about following the EV process.
This can’t be said strong enough – use EV in the
way it was designed to be used.
• Keep all the data “clean” and use it to make
management decisions
PMI College of Scheduling
“PMI” is a registered trade and service markof the Project Management Institute, Inc.
43
44. Troubled Projects Always Have A
Common Set Of Attributes
Inattention to budgetary responsibilities
Work authorization not always followed
Budget and data reconciliation issues
Lack of an integrated management system
Baseline fluctuations &frequent replanning
Current period and retroactive changes
Improper use of management reserve
Earned Value techniques not reflecting actual accomplishments
Untimely and unrealistic Latest Revised Estimates (LRE)
Progress not monitored in a regular and consistent manner
Lack of vertical and horizontal traceability (critical path)
Not capturing and using cost and schedule data for corrective action
Lack of predictive variance analysis
Lack of internal surveillance and controls
Managerial actions not demonstrated using Earned Value
PMI College of Scheduling
“PMI” is a registered trade and service markof the Project Management Institute, Inc.
44
A ship on the beach is a lighthouse
to the sea – Dutch Proverb