12. Scaffolding
21/3/2023
12
• There are three basic types of scaffolds:
Supported scaffolds, which consist of one
or more platforms supported by rigid, load-
bearing members, such as poles, legs,
frames, outriggers, etc.
• Suspended scaffolds, which are one or
more platforms suspended by ropes or other
non-rigid, overhead support.
• Other scaffolds, principally man lifts,
personnel hoists, etc., which are sometimes
thought of as vehicles or machinery, but can
be regarded as another type of supported
14. Scaffolds
21/3/2023
14
Supported scaffolds consist of one or more
platforms supported by outrigger beams, brackets,
poles, legs, posts, frames, or similar rigid support.
1. Frame (or) Fabricated Scaffold
2. Mobile Scaffold
3. Ladder Jack Scaffold
4. Pump Jack Scaffold
5. Tube & Coupler Scaffold
6. Pole Scaffold
16. Mobile Scaffold
Braced to prevent collapse.
Casters and wheels locked to
prevent movement while in a
stationary position.
Platforms must not extend beyond
the base supports of the scaffold,
unless stability is ensured.
Not allowed to ride on scaffolds
unless the surface on which
scaffold is being moved is free of
pits, holes and obstructions.
21/3/2023
16
22. Aerial Lift
Ensure proper fall
protection prior to
using
Includes use of
guardrails
Never exceed load
capacity
Do not move lift truck
with workers in
basket unless
adequately designed
(upper controls –
personnel carriers) 21/3/2023
22
23. Scaffold Competent Person
21/3/2023
23
Inspect scaffolding and
components prior to
each work shift
Determine possibility of
providing fall protection
and access
Evaluate connections to
support load
Determine structural
soundness
Train erectors and
dismantlers to recognize
work hazards
26. Green Tag….
21/3/2023
26
Indicates scaffold
is complete, has
been inspected,
and is safe for
use at the time of
inspection
GREEN scaffold
tag valid for a
maximum of two
weeks
2/28/02
2/14/02
A. SULAIMAN
673-2400
K. SALEH
Khaled Saleh
673-2308
431056
K. SALEH
Khaled Saleh
673-2308
431056
K. SALEH
Khaled Saleh
673-2308
431056
K. SALEH
Khaled Saleh
673-2308
431056
3/14/02 3/28/02
A. SULAIMAN
673-2400
A. SULAIMAN
673-2400
A. SULAIMAN
673-2400
6
TANK 105
a
233100
Ahmed Sulaiman
233100
Ahmed Sulaiman
233100
Ahmed Sulaiman
2
233100
Ahmed Sulaiman
Insert fits
into holder
27. Yellow Tag….
21/3/2023
27
Indicates scaffold
has been
inspected and
may be used only
by workers
wearing a
properly anchored
personal fall
arrest system,
including a full
body harness and
lanyard
YELLOW scaffold
tag valid for two
weeks maximum
2
4/10/02
A. SULAIMAN K. SALEH
Khaled Saleh
673-2308
431056
6
TANK 105
a
233100
Ahmed Sulaiman
673-2400
Insert fits
into
holder
28. Displaying of Tag….
21/3/2023
28
RED scaffold tag (holder) to be
built into scaffold, near each point
of access, by scaffold craftsmen
Only qualified scaffold craftsmen
are allowed on a scaffold with a
RED scaffold tag
29. 21/3/2023
29
If Scaffold EQUAL TO or LESS THAN 6
meters (20 feet) high:
Scaffold Supervisor signs
GREEN or YELLOW scaffold
tag(s) and prints date when next
inspection is due
Supervisor inserts the signed
GREEN or YELLOW tag(s) into
the RED holder(s)
“Date of next inspection”
must not be more than 2
weeks ahead
30. 21/3/2023
30
If Scaffold MORE THAN 6 meters
(20 feet) tall:
Scaffold Supervisor signs tag(s)
and leaves “Date of Next
Inspection” blank
Supervisor gives the signed
GREEN or YELLOW tag(s) to a
Scaffold Inspector
• All Scaffold Inspectors and
Scaffold Supervisors MUST BE
CERTIFIED
31. 21/3/2023
31
Scaffold Inspector inspects
scaffold
As soon as possible after Scaffold
Supervisor’s inspection
Scaffold Inspector also fills in and
signs separate “Scaffold Field
Inspection Checklist”
Inspector gives this checklist to Work
Permit Issuer’s unit, who will keep it
until scaffold is taken down
If Scaffold MORE THAN 6 meters
(20 feet) tall:
32. 21/3/2023
32
If Scaffold Inspector agrees that
scaffold is safe to use, he will:
Fill in and sign GREEN or
YELLOW scaffold tag(s)
• Previously given to him by Scaffold
Supervisor
If Scaffold MORE THAN 6 meters
(20 feet) tall:
33. Scaffold Erection Requirement
21/3/2023
33
Only competent & experienced
person must be permitted to erect &
dismantle the scaffolding at site.
Guardrails, mid rails & toe boards
must be placed on all open side of
platforms more than 1.2 meters
above ground (or) floor.
34. Scaffold Erection Requirement
21/3/2023
34
The top rail must be placed
approximately 1200 mm high from the
platform.
The mid rail must be placed
approximately 600 mm high from the
platform.
The toe board must be placed
approximately 300 mm from the
36. Scaffold Erection Requirement
21/3/2023
36
All scaffolds shall be provided with an access
ladder that extends to at least 1 meter above
the platform.
Platforms should be 220mm wide & 25mm
thick and it should be tightened with
scaffolding to prevent movements in high
winds.
Scaffolds should be cleaned after the
completion of work.
37. Scaffold Erection Requirement
21/3/2023
37
Should be on a firm foundation with
base plates.
Should be properly braced & tied
up.
Should have a properly tightened
platform.
Should have guardrails over 1.2
meters.
Should have adequate means of
41. Planking
21/3/2023
41
All planking or platforms shall be
overlapped (minimum 12 inches) or
secured from movement.
Scaffold planks shall extend over
their end supports not less than 6
inches nor more than 18 inches.
42. Platform Construction
21/3/2023
42
No paint on wood platforms, except
edges that may be marked for
identification.
Fully planked.
No mixed components, unless
compatible and integrity maintained.
No modification of mixed components
unless approved by competent
person.
48. PFAS
Workers must be
trained how to
properly use
PFAS.
PFAS include
anchorage, lifeline
and full body
harness with
double lanyard.
Both Active & 21/3/2023
48
49. Restrictions
Don’t overloaded.
Don’t Erect & move near power
lines .
Repair damaged components.
Restrict horizontal movement of
workers unless provided with
fall protection.
Prohibit work activities during
high winds unless authorized.
Remove whole scaffold from
service until repaired.
Note – Scaffolds must be
erected 10 feet away of the 21/3/2023
49
50. Over Head Power Lines
Proper clearance near overhead lines
Keep 10 foot minimum unless de-
energized,
Relocated, or installed protective covering
installed! 21/3/2023
50
52. Training Required
Employees must receive training from
qualified person that covers:
Nature of hazards, electrical, falls, and
falling items
Use of scaffold / handling
Maximum intended load and load
carrying capabilities of scaffold
Procedures for setup, dismantling or
moving the system
21/3/2023
52
53. Follow the manufacturer's instructions when erecting
the scaffold.
Do not work on scaffolds outside during stormy or
windy weather.
Do not climb on scaffolds that wobble or lean to one
side.
Initially inspect the scaffold prior to mounting it. Do
not use a scaffold if any pulley, block, hook or fitting
is visibly worn, cracked, rusted or otherwise
damaged.
Do not use any scaffold tagged "Out of Service".
Do not work on platforms or scaffolds unless they are
fully planked.
In General….
21/3/2023
53
54. In General….
Do not walk or work beneath a scaffold unless a wire
mesh has been installed between the top rail and the toe
board or planking.
Use your safety belts and lanyards when working on
scaffolding at a height.
Attach the lanyard to a secure member of the scaffold.
Do not climb the cross braces for access to the scaffold.
Use the ladder.
Do not jump from, to, or between scaffolding.
Do not move a mobile scaffold if anyone is on the
scaffold.
Chock the wheels of the rolling scaffold, using the wheel
blocks, and also lock the wheels by using your foot to
depress the wheel-lock, before using the scaffold.21/3/2023
54