SlideShare a Scribd company logo
1 of 60
PIPE BURSTING AND PRE CHLORINATION
    COST EFFECTIVENESS ON LARGE SCALE PROJECTS
THE STATE OF WATER DISTRIBUTION SYSTEMS

                            • Encrusted
                            • Corroded
                            • Water loss up to 40%
                            • Under capacity
                            • Poor water quality




PIPE BURSTING AND PRE-CHLORINATION
BUSINESS OPPORTUNITY

• EPA estimates 750 billion dollars over
  next 20 years
• AWWA estimates 1 trillion dollars over
  next 20 years




PIPE BURSTING AND PRE-CHLORINATION
NOT ACCEPTABLE!

• The open trench method of replacement
  is becoming more costly and socially
  unacceptable.




PIPE BURSTING AND PRE-CHLORINATION
PIPE BURSTING PRESSURE PIPE

• Method was developed By British Gas and patented in 1980’s for gas distribution
  rehabilitation.
• Success led to potable water crossover.
• Pipe bursting without protection sleeve accepted along with pre-chlorination
  method in early 1990’s in the UK.
• Widely accepted in Europe with more than 60,000,000 feet installed in the past
  17 years.
• Pre-Chlorinated method of pipe bursting is accepted by AWWA in November of
  2000.


PIPE BURSTING AND PRE-CHLORINATION
PIPE BURSTING DEFINED

The breaking of an existing pipe,
expanding the broken pipe shards into the
surrounding soil while simultaneously
pulling in the “NEW” carrier line, usually
polyethylene pipe (HDPE).




PIPE BURSTING AND PRE-CHLORINATION
PIPE BURSTING
PROJECT CONSIDERATIONS
WHAT IS THE HOST MATERIAL?

• Cast Iron
• Clay tile
• Concrete
• Reinforced Concrete
• Asbestos Cement
• Non Fracturable Pipe
 –Ductile Iron – Challenging
 –Steel – Challenging
 –Use Static Machines and Slitters



PIPE BURSTING AND PRE-CHLORINATION
WHAT MATERIALS CAN BE BURST?

       Fracturable Pipes
       Cast iron, clay tile, concrete, reinforced concrete, asbestos cement,
       etc.

       Non-fracturable Pipes
       Ductile iron, steel, galvanized (require use of specialized tooling
       and static bursting machines.




PIPE BURSTING AND PRE-CHLORINATION
IPBA PROJECT CLASSIFICATION




Project classifications per IPBA (International Pipe Bursting Association) pipe bursting specification.

PIPE BURSTING AND PRE-CHLORINATION
UPSIZING: A CLOSER LOOK




Note: Illustration assumes
flow line remains the same.


PIPE BURSTING AND PRE-CHLORINATION
UPSIZING: A CLOSER LOOK




Note: Illustration assumes
flow line remains the same.


PIPE BURSTING AND PRE-CHLORINATION
UPSIZING: A CLOSER LOOK




Note: Illustration assumes
flow line remains the same.


PIPE BURSTING AND PRE-CHLORINATION
UPSIZING: A CLOSER LOOK




Note: Illustration assumes
flow line remains the same.


PIPE BURSTING AND PRE-CHLORINATION
UPSIZING – EXPANSION (WHERE IT GOES)




     Approximately 90% of compaction
     occurs upwards from the existing line.


PIPE BURSTING AND PRE-CHLORINATION
PIPE BURSTING
PRE-CHLORINATION METHOD
Pipe Bursting / Pre-chlorination Method

• A preferred method of water line rehabilitation
 –Follows path of the existing utility (reduces potential for 3rd party utility damage)
 –Easement issues and line separation limitations are reduced - the existing utility path
  is used
 –Reduce excavation costs by up to 85%
 –Able to increase the pipe diameter
 –Production: Install up to 400’ of pipe in under 2 hours
 –Pre-chlorination save cost and disruption of installing temporary services
 –FL- No permitting required for bursting: Classed as a line repair



PIPE BURSTING AND PRE-CHLORINATION
FORT PIERCE, FLORIDA




PIPE BURSTING AND PRE-CHLORINATION
Pipe Bursting with Pre-chlorination Method
using Fusible PVC




PIPE BURSTING AND PRE-CHLORINATION
PIPE BURSTING SETUP – PUSH OUT ROD




PIPE BURSTING AND PRE-CHLORINATION
PIPE BURSTING SETUP – ATTACH TOOLING & PIPE




PIPE BURSTING AND PRE-CHLORINATION
PIPE BURSTING SETUP – PULL BACK




PIPE BURSTING AND PRE-CHLORINATION
PROJECT CONSIDERATIONS – UK

• Preferred pipe material - Fusible PVC &
  HDPE.
• Upsizing used only when required
 –Bursting specifications limited to 1 upsize
   • Avoid surface heave and 3rd party utility damage
   • HDPE Pipe
     –Electro-fusion couplers for mains and service
      connections




PIPE BURSTING AND PRE-CHLORINATION
Pipe Bursting




PIPE BURSTING AND PRE-CHLORINATION
Pipe Bursting with Pre-chlorination Method
using HDPE




PIPE BURSTING AND PRE-CHLORINATION
FLOW COMPARISONS: HDPE




PIPE BURSTING AND PRE-CHLORINATION
FLOW COMPARISONS: HDPE




PIPE BURSTING AND PRE-CHLORINATION
EQUIPMENT SELECTION

• Static equipment is most common for water projects
• High tonnage static pull back force
 –38 ton (2” – 6” pipe)
 –58 ton (4” – 8” pipe)
 –100 ton (4” – 16” pipe)
 –125 ton (6” – 20” pipe)
 –175 ton (6”- 24” pipe)
• No-contamination of the new Fusible PVC pipe or HDPE.



PIPE BURSTING AND PRE-CHLORINATION
WATER MAIN PROBLEMS

• Received complaints regarding potable water clarity and low pressure concerns
• Cast iron water main breaks
• New service line installations required
• Limited working space, easement issues, and heavy traffic
• Expense of open cut not a feasible option
• Congested utility infrastructure




PIPE BURSTING AND PRE-CHLORINATION
TYPICAL JOBSITE
                                     Launch,
                                     reception and
                                     service pits.




PIPE BURSTING AND PRE-CHLORINATION
NETWORK MODELING/PROJECT DESIGN

• Flow requirements: HDPE / Fusible PVC Slip-line or Burst?
• Site investigation
 –Pothole main and confirm main depth, location and material
 –Review proximity to other utilities
• Sampling Investigations
 –Downstream Series Sampling:-
   • 1 Source
   • 50 Address (>50μg/litre)
     –          (>20μg/litre more than source)
 –Pre and Post Renovation Sampling:-
   • 10 Source
   • 10 Address (>50μg/litre)
     –          (>20μg/litre more than source)



PIPE BURSTING AND PRE-CHLORINATION
CUSTOMER NOTIFICATION

• Customers are notified of mains replacement project by door hanger outlining
  the project scope
• Hanger is provided to home owner 48 hours prior to work being performed on
  their line section
• Approximately 15 to 20 homes will be off water from 8:00 am to 3:00 pm on the
  day of pipe bursting operations
• Construction crew will be moved onward the following day




PIPE BURSTING AND PRE-CHLORINATION
PRE-CHLORINATING PROCEDURES

• Liverpool Depot Coil Pre-chlorinating
  Operations
 –Chlorinated Water is filled into the HDPE
  pipe coils and left for 24 hours then flushed
  and a sample taken.




PIPE BURSTING AND PRE-CHLORINATION
FUSE ON ADAPTORS




PIPE BURSTING AND PRE-CHLORINATION
PRE-CHLORINATING PROCEDURES

 –Passed Coils are Marked-up with Gang Name, Location and Sample Reference
  Number.
 –Coils are Stored in goods-out bay prior to collection
 –Coils are Loaded on to Carousel by fork-lift truck
 –2 No. Check Sample Points
  • To check Dosage of Chloros is maintained at 25 to 30mg/l
  • To check de-chlorination of water prior to disposal




PIPE BURSTING AND PRE-CHLORINATION
PRE-CHLORINATING PROCEDURES

• Lengths of Main Above and Below Ground Pre-chlorinating Operations
 –Very similar to coil pre-chlorinating procedure
 –Source of water from on-site hydrant
 –All hoses used in operation are pre-chlorinated
 –Mobile dosage unit is used
   • Inputs the required chloros in to the main
   • De-chlorinates the water prior to discharge to sanitary sewer
 –Each length requires a 12 hour dosage period prior to laboratory sample being taken
 –Results are received next day via fax prior to being put into commission



PIPE BURSTING AND PRE-CHLORINATION
CONSTRUCTION ACTIVITY: DAY OF OPERATIONS
                                 • Excavate launch, reception
                                   and service pits.




PIPE BURSTING AND PRE-CHLORINATION
CONSTRUCTION ACTIVITY: DAY OF OPERATIONS

                                • Cut existing cast-iron main, install
                                  cap end and secure. Re-establish
                                  supply to existing main.




PIPE BURSTING AND PRE-CHLORINATION
CONSTRUCTION ACTIVITY: DAY OF OPERATIONS

                            • Position rig into launch and reception pit
                              and pay out rod. (avg. 45 minutes to
                              payout 350’ of rod)




PIPE BURSTING AND PRE-CHLORINATION
CONSTRUCTION ACTIVITY: DAY OF OPERATIONS

                                     • Guide rod enters reception pit.




PIPE BURSTING AND PRE-CHLORINATION
CONSTRUCTION ACTIVITY: DAY OF OPERATIONS


                         • Connect pulling head to fusible PVC or HDPE
                           pipe. Bursting blade and expander to pulling
                           rods.




PIPE BURSTING AND PRE-CHLORINATION
CONSTRUCTION ACTIVITY: DAY OF OPERATIONS

                            • Pull back until bursting blade arrives at
                              reception pit. (This takes an average of
                              45 – 60 minutes for 350’)




PIPE BURSTING AND PRE-CHLORINATION
CONSTRUCTION ACTIVITY: DAY OF OPERATIONS

• Undertake swabbing exercise
• Purge air out of new HDPE main through Installed ferrule at pipe end
• Connect cap-end control and pressure test pipe.
• Take bacteriological sample
• Turn water back on




PIPE BURSTING AND PRE-CHLORINATION
CONSTRUCTION ACTIVITY: DAY OF OPERATIONS

                                • Install necessary branches, valves
                                  and hydrants.




PIPE BURSTING AND PRE-CHLORINATION
CONSTRUCTION ACTIVITY: DAY OF OPERATIONS

• Pneumatic piercing tools used for
  installing new services.




PIPE BURSTING AND PRE-CHLORINATION
CONSTRUCTION ACTIVITY: DAY OF OPERATIONS

                            • Install electro-fusion saddles for service
                              connections.




PIPE BURSTING AND PRE-CHLORINATION
CONSTRUCTION ACTIVITY: DAY OF OPERATIONS

                            • Backfill excavation and permanently re-
                              instate.




PIPE BURSTING AND PRE-CHLORINATION
CONCLUSIONS

• UK has 13 major water companies serving 66 million people.
• Pre-chlorinated Pipe Bursting has nearly obsoleted open trench replacement of
  water mains in the UK
• USA has approved pre-chlorination in the majority of the US. Pipe Bursting
  water mains in the USA will continue to see solid growth, but is currently limited
  by:
 –Engineers specifying and water companies embracing HDPE for water rehab jobs
 –Lack of projects specifying the Pipe Bursting and pre-chlorinated methods




PIPE BURSTING AND PRE-CHLORINATION
CASE STUDY
BROWNSTOWN WATER IMPROVEMENT PROJECT
A joint venture of Bidigare Contractors, Inc., Northville, Michigan
and D & D Water & Sewer, Inc., Canton, Michigan.
TOWNSHIP OF BROWNSTOWN, MICHIGAN

• Ambitious water-system improvement program that includes replacing nearly
  eight miles of water mains.
• Most of it with pre-chlorinated HDPE pipe installed by pipe bursting.
• It is the first time the Township has installed pre-chlorinated pipe or used pipe
  bursting.
• Their contract calls for installation of 43,000 feet of new water mains, most of it
  8- and 12-inch pre-chlorinated HDPE pipe and installation of fire hydrants and
  gatewells.




PIPE BURSTING AND PRE-CHLORINATION
Existing water main pipes in Brownstown, Michigan.
Setting the down hole machine for the first burst.
Fusion of the new pipe to be installed.
Staging of HDPE pipe sticks for fusion.
The bursting process.
A section of new pipe shown with the tooling required to
replace the existing pipe. The tooling will be attached to
the rod string that is pushed out by the down hole unit.
Inside of a connection pit, the bursting process is shown.
Inside of another connection pit, the expander and
tooling is shown bursting through old segments of pipe.
CONCLUSION

• Township is so satisfied with how the project progressed; another 30,000 feet of
  improvements have been added that will extend completion to 2013.
THANK YOU

 FIRST NAME LAST NAME
 PRESENTER TITLE
 E: info@hammerheadmole.com
 P: 800.331.6653 | INT: +1.262.567.8833 | F: 262.567.5068
 W: www.hammerheadtrenchless.com

More Related Content

What's hot

UKWP Case study - Mauchline Final copy 23 06 15
UKWP Case study - Mauchline Final copy 23 06 15UKWP Case study - Mauchline Final copy 23 06 15
UKWP Case study - Mauchline Final copy 23 06 15
ADAM DUKE
 
J Ray Firsts
J Ray FirstsJ Ray Firsts
J Ray Firsts
MyLast1
 
06 0167 Keyhole Technology A Solid Solution For Our Road Surfaces For Trade P...
06 0167 Keyhole Technology A Solid Solution For Our Road Surfaces For Trade P...06 0167 Keyhole Technology A Solid Solution For Our Road Surfaces For Trade P...
06 0167 Keyhole Technology A Solid Solution For Our Road Surfaces For Trade P...
Gord Reynolds
 
Paper 43 - Deep Water Pipeline CT 9_2_15
Paper 43 - Deep Water Pipeline CT 9_2_15Paper 43 - Deep Water Pipeline CT 9_2_15
Paper 43 - Deep Water Pipeline CT 9_2_15
John Grover
 
Horizon 2020
Horizon 2020Horizon 2020
Horizon 2020
Pomcert
 
In-Place Pipe Support Load Testing and Hanger Surveys_Part of a Best in Class...
In-Place Pipe Support Load Testing and Hanger Surveys_Part of a Best in Class...In-Place Pipe Support Load Testing and Hanger Surveys_Part of a Best in Class...
In-Place Pipe Support Load Testing and Hanger Surveys_Part of a Best in Class...
Britt Bettell
 

What's hot (20)

Coning problems and remedies
Coning problems and remediesConing problems and remedies
Coning problems and remedies
 
HydroMax™ Siphonic (Syphonic) Roof Drainage
HydroMax™ Siphonic (Syphonic) Roof DrainageHydroMax™ Siphonic (Syphonic) Roof Drainage
HydroMax™ Siphonic (Syphonic) Roof Drainage
 
The High Velocity Hurricane Zone Roof Drainage Requirements
The High Velocity Hurricane Zone Roof Drainage Requirements The High Velocity Hurricane Zone Roof Drainage Requirements
The High Velocity Hurricane Zone Roof Drainage Requirements
 
Moffett Hangar One Proposed Removal Action
Moffett Hangar One Proposed Removal ActionMoffett Hangar One Proposed Removal Action
Moffett Hangar One Proposed Removal Action
 
UKWP Case study - Mauchline Final copy 23 06 15
UKWP Case study - Mauchline Final copy 23 06 15UKWP Case study - Mauchline Final copy 23 06 15
UKWP Case study - Mauchline Final copy 23 06 15
 
120625 0814 Tops
120625 0814 Tops120625 0814 Tops
120625 0814 Tops
 
Tigg Minicipal Water Treatment Systems
Tigg Minicipal Water Treatment SystemsTigg Minicipal Water Treatment Systems
Tigg Minicipal Water Treatment Systems
 
Rehabilitation insert presentation
Rehabilitation insert presentationRehabilitation insert presentation
Rehabilitation insert presentation
 
Fiberglass tank solutions rev a
Fiberglass tank solutions   rev aFiberglass tank solutions   rev a
Fiberglass tank solutions rev a
 
J Ray Firsts
J Ray FirstsJ Ray Firsts
J Ray Firsts
 
06 0167 Keyhole Technology A Solid Solution For Our Road Surfaces For Trade P...
06 0167 Keyhole Technology A Solid Solution For Our Road Surfaces For Trade P...06 0167 Keyhole Technology A Solid Solution For Our Road Surfaces For Trade P...
06 0167 Keyhole Technology A Solid Solution For Our Road Surfaces For Trade P...
 
Dariush.resume
Dariush.resumeDariush.resume
Dariush.resume
 
Pipininspect
PipininspectPipininspect
Pipininspect
 
ANSYS oil&gas seminar 2013
ANSYS oil&gas seminar 2013ANSYS oil&gas seminar 2013
ANSYS oil&gas seminar 2013
 
Paper 43 - Deep Water Pipeline CT 9_2_15
Paper 43 - Deep Water Pipeline CT 9_2_15Paper 43 - Deep Water Pipeline CT 9_2_15
Paper 43 - Deep Water Pipeline CT 9_2_15
 
Shock Control, Restraint, and Support Devices
Shock Control, Restraint, and Support Devices Shock Control, Restraint, and Support Devices
Shock Control, Restraint, and Support Devices
 
Horizon 2020
Horizon 2020Horizon 2020
Horizon 2020
 
Husam CV updated (1)
Husam CV updated (1)Husam CV updated (1)
Husam CV updated (1)
 
In-Place Pipe Support Load Testing and Hanger Surveys_Part of a Best in Class...
In-Place Pipe Support Load Testing and Hanger Surveys_Part of a Best in Class...In-Place Pipe Support Load Testing and Hanger Surveys_Part of a Best in Class...
In-Place Pipe Support Load Testing and Hanger Surveys_Part of a Best in Class...
 
Vsl pt concrete_storage_structures
Vsl pt concrete_storage_structuresVsl pt concrete_storage_structures
Vsl pt concrete_storage_structures
 

Similar to Pipe bursting and Pre-chlorination_effectiveness on large scale projects

TRIC Trenchless LA building & safety
TRIC Trenchless LA building & safetyTRIC Trenchless LA building & safety
TRIC Trenchless LA building & safety
MEL3360
 
19-07-06 Scheme Description details
19-07-06 Scheme Description details19-07-06 Scheme Description details
19-07-06 Scheme Description details
Aonghus Murray
 
Water customer presentation
Water customer presentationWater customer presentation
Water customer presentation
Suj Kang
 
BANFF Presentation_v1 1 (3)
BANFF Presentation_v1 1 (3)BANFF Presentation_v1 1 (3)
BANFF Presentation_v1 1 (3)
alois multerer
 
PLUMBING.pptrfffjedkkxfmk3eldokwndktookedfm
PLUMBING.pptrfffjedkkxfmk3eldokwndktookedfmPLUMBING.pptrfffjedkkxfmk3eldokwndktookedfm
PLUMBING.pptrfffjedkkxfmk3eldokwndktookedfm
McKevinVargas
 
Penstocks, powerhouse and tailrace
Penstocks, powerhouse and tailracePenstocks, powerhouse and tailrace
Penstocks, powerhouse and tailrace
Rakesh Sunari Magar
 

Similar to Pipe bursting and Pre-chlorination_effectiveness on large scale projects (20)

Plumbing_services [Dr. Kamakshi Memorial Hospital].pptx
Plumbing_services [Dr. Kamakshi Memorial Hospital].pptxPlumbing_services [Dr. Kamakshi Memorial Hospital].pptx
Plumbing_services [Dr. Kamakshi Memorial Hospital].pptx
 
Blue mountains cascade dam- Horizontal direction drill
Blue mountains cascade dam- Horizontal direction drillBlue mountains cascade dam- Horizontal direction drill
Blue mountains cascade dam- Horizontal direction drill
 
TRIC Trenchless LA building & safety
TRIC Trenchless LA building & safetyTRIC Trenchless LA building & safety
TRIC Trenchless LA building & safety
 
Trenchless Technology
Trenchless TechnologyTrenchless Technology
Trenchless Technology
 
19-07-06 Scheme Description details
19-07-06 Scheme Description details19-07-06 Scheme Description details
19-07-06 Scheme Description details
 
tanajib
tanajibtanajib
tanajib
 
Barker.R.CV.
Barker.R.CV.Barker.R.CV.
Barker.R.CV.
 
Types of pipes
Types of pipesTypes of pipes
Types of pipes
 
Site Report
Site ReportSite Report
Site Report
 
Water customer presentation
Water customer presentationWater customer presentation
Water customer presentation
 
Trenchless technolgy
Trenchless technolgyTrenchless technolgy
Trenchless technolgy
 
Iimt college of polytechic, ppt
Iimt college of polytechic,   pptIimt college of polytechic,   ppt
Iimt college of polytechic, ppt
 
BANFF Presentation_v1 1 (3)
BANFF Presentation_v1 1 (3)BANFF Presentation_v1 1 (3)
BANFF Presentation_v1 1 (3)
 
Metkon Pipa Bawah Laut.pdf
Metkon Pipa Bawah Laut.pdfMetkon Pipa Bawah Laut.pdf
Metkon Pipa Bawah Laut.pdf
 
Pipe Bursting
Pipe BurstingPipe Bursting
Pipe Bursting
 
Keeping Wastewater Flowing while managing major capital works for NI Water, 9...
Keeping Wastewater Flowing while managing major capital works for NI Water, 9...Keeping Wastewater Flowing while managing major capital works for NI Water, 9...
Keeping Wastewater Flowing while managing major capital works for NI Water, 9...
 
Water transportation to drilling sites
Water transportation to drilling sitesWater transportation to drilling sites
Water transportation to drilling sites
 
PLUMBING.pptrfffjedkkxfmk3eldokwndktookedfm
PLUMBING.pptrfffjedkkxfmk3eldokwndktookedfmPLUMBING.pptrfffjedkkxfmk3eldokwndktookedfm
PLUMBING.pptrfffjedkkxfmk3eldokwndktookedfm
 
Penstocks, powerhouse and tailrace
Penstocks, powerhouse and tailracePenstocks, powerhouse and tailrace
Penstocks, powerhouse and tailrace
 
Resume 2022(1).pdf
Resume 2022(1).pdfResume 2022(1).pdf
Resume 2022(1).pdf
 

More from HammerHead Trenchless Equipment

Trenchless Installation of Drainage Culverts with Pipe Ramming Method
Trenchless Installation of Drainage Culverts with Pipe Ramming MethodTrenchless Installation of Drainage Culverts with Pipe Ramming Method
Trenchless Installation of Drainage Culverts with Pipe Ramming Method
HammerHead Trenchless Equipment
 

More from HammerHead Trenchless Equipment (14)

Pneumatic Pipe Bursting Case Studies
Pneumatic Pipe Bursting Case StudiesPneumatic Pipe Bursting Case Studies
Pneumatic Pipe Bursting Case Studies
 
Static Pipe Bursting Case Stidies
Static Pipe Bursting Case StidiesStatic Pipe Bursting Case Stidies
Static Pipe Bursting Case Stidies
 
Static Pipe Bursting Systems
Static Pipe Bursting SystemsStatic Pipe Bursting Systems
Static Pipe Bursting Systems
 
Pneumatic Pipe Bursting Systems
Pneumatic Pipe Bursting SystemsPneumatic Pipe Bursting Systems
Pneumatic Pipe Bursting Systems
 
HammerHead Mole Piercing Tools
HammerHead Mole Piercing ToolsHammerHead Mole Piercing Tools
HammerHead Mole Piercing Tools
 
The Pipe Ramming Method
The Pipe Ramming MethodThe Pipe Ramming Method
The Pipe Ramming Method
 
Trenchless Installation of Drainage Culverts with Pipe Ramming Method
Trenchless Installation of Drainage Culverts with Pipe Ramming MethodTrenchless Installation of Drainage Culverts with Pipe Ramming Method
Trenchless Installation of Drainage Culverts with Pipe Ramming Method
 
Pipe Bursting Project Considerations
Pipe Bursting Project ConsiderationsPipe Bursting Project Considerations
Pipe Bursting Project Considerations
 
HDD Assist Methods
HDD Assist MethodsHDD Assist Methods
HDD Assist Methods
 
Comparing Rehabilitation and Replacement Applications
Comparing Rehabilitation and Replacement ApplicationsComparing Rehabilitation and Replacement Applications
Comparing Rehabilitation and Replacement Applications
 
HammerHead PP Template, No Logo. 4:3
HammerHead PP Template, No Logo. 4:3HammerHead PP Template, No Logo. 4:3
HammerHead PP Template, No Logo. 4:3
 
HammerHead PP Template, 16:9
HammerHead PP Template, 16:9HammerHead PP Template, 16:9
HammerHead PP Template, 16:9
 
HammerHead PP Template, 4:3
HammerHead PP Template, 4:3HammerHead PP Template, 4:3
HammerHead PP Template, 4:3
 
HammerHead PP Template, No Logo, 16:9
HammerHead PP Template, No Logo, 16:9HammerHead PP Template, No Logo, 16:9
HammerHead PP Template, No Logo, 16:9
 

Recently uploaded

The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
heathfieldcps1
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
heathfieldcps1
 
Making and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdfMaking and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdf
Chris Hunter
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
PECB
 

Recently uploaded (20)

Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104
 
Micro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdfMicro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdf
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
 
This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.
 
Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docx
 
Making and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdfMaking and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdf
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy Consulting
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot Graph
 
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptx
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 
Role Of Transgenic Animal In Target Validation-1.pptx
Role Of Transgenic Animal In Target Validation-1.pptxRole Of Transgenic Animal In Target Validation-1.pptx
Role Of Transgenic Animal In Target Validation-1.pptx
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17
 
Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024
 

Pipe bursting and Pre-chlorination_effectiveness on large scale projects

  • 1. PIPE BURSTING AND PRE CHLORINATION COST EFFECTIVENESS ON LARGE SCALE PROJECTS
  • 2. THE STATE OF WATER DISTRIBUTION SYSTEMS • Encrusted • Corroded • Water loss up to 40% • Under capacity • Poor water quality PIPE BURSTING AND PRE-CHLORINATION
  • 3. BUSINESS OPPORTUNITY • EPA estimates 750 billion dollars over next 20 years • AWWA estimates 1 trillion dollars over next 20 years PIPE BURSTING AND PRE-CHLORINATION
  • 4. NOT ACCEPTABLE! • The open trench method of replacement is becoming more costly and socially unacceptable. PIPE BURSTING AND PRE-CHLORINATION
  • 5. PIPE BURSTING PRESSURE PIPE • Method was developed By British Gas and patented in 1980’s for gas distribution rehabilitation. • Success led to potable water crossover. • Pipe bursting without protection sleeve accepted along with pre-chlorination method in early 1990’s in the UK. • Widely accepted in Europe with more than 60,000,000 feet installed in the past 17 years. • Pre-Chlorinated method of pipe bursting is accepted by AWWA in November of 2000. PIPE BURSTING AND PRE-CHLORINATION
  • 6. PIPE BURSTING DEFINED The breaking of an existing pipe, expanding the broken pipe shards into the surrounding soil while simultaneously pulling in the “NEW” carrier line, usually polyethylene pipe (HDPE). PIPE BURSTING AND PRE-CHLORINATION
  • 8. WHAT IS THE HOST MATERIAL? • Cast Iron • Clay tile • Concrete • Reinforced Concrete • Asbestos Cement • Non Fracturable Pipe –Ductile Iron – Challenging –Steel – Challenging –Use Static Machines and Slitters PIPE BURSTING AND PRE-CHLORINATION
  • 9. WHAT MATERIALS CAN BE BURST? Fracturable Pipes Cast iron, clay tile, concrete, reinforced concrete, asbestos cement, etc. Non-fracturable Pipes Ductile iron, steel, galvanized (require use of specialized tooling and static bursting machines. PIPE BURSTING AND PRE-CHLORINATION
  • 10. IPBA PROJECT CLASSIFICATION Project classifications per IPBA (International Pipe Bursting Association) pipe bursting specification. PIPE BURSTING AND PRE-CHLORINATION
  • 11. UPSIZING: A CLOSER LOOK Note: Illustration assumes flow line remains the same. PIPE BURSTING AND PRE-CHLORINATION
  • 12. UPSIZING: A CLOSER LOOK Note: Illustration assumes flow line remains the same. PIPE BURSTING AND PRE-CHLORINATION
  • 13. UPSIZING: A CLOSER LOOK Note: Illustration assumes flow line remains the same. PIPE BURSTING AND PRE-CHLORINATION
  • 14. UPSIZING: A CLOSER LOOK Note: Illustration assumes flow line remains the same. PIPE BURSTING AND PRE-CHLORINATION
  • 15. UPSIZING – EXPANSION (WHERE IT GOES) Approximately 90% of compaction occurs upwards from the existing line. PIPE BURSTING AND PRE-CHLORINATION
  • 17. Pipe Bursting / Pre-chlorination Method • A preferred method of water line rehabilitation –Follows path of the existing utility (reduces potential for 3rd party utility damage) –Easement issues and line separation limitations are reduced - the existing utility path is used –Reduce excavation costs by up to 85% –Able to increase the pipe diameter –Production: Install up to 400’ of pipe in under 2 hours –Pre-chlorination save cost and disruption of installing temporary services –FL- No permitting required for bursting: Classed as a line repair PIPE BURSTING AND PRE-CHLORINATION
  • 18. FORT PIERCE, FLORIDA PIPE BURSTING AND PRE-CHLORINATION
  • 19. Pipe Bursting with Pre-chlorination Method using Fusible PVC PIPE BURSTING AND PRE-CHLORINATION
  • 20. PIPE BURSTING SETUP – PUSH OUT ROD PIPE BURSTING AND PRE-CHLORINATION
  • 21. PIPE BURSTING SETUP – ATTACH TOOLING & PIPE PIPE BURSTING AND PRE-CHLORINATION
  • 22. PIPE BURSTING SETUP – PULL BACK PIPE BURSTING AND PRE-CHLORINATION
  • 23. PROJECT CONSIDERATIONS – UK • Preferred pipe material - Fusible PVC & HDPE. • Upsizing used only when required –Bursting specifications limited to 1 upsize • Avoid surface heave and 3rd party utility damage • HDPE Pipe –Electro-fusion couplers for mains and service connections PIPE BURSTING AND PRE-CHLORINATION
  • 24. Pipe Bursting PIPE BURSTING AND PRE-CHLORINATION
  • 25. Pipe Bursting with Pre-chlorination Method using HDPE PIPE BURSTING AND PRE-CHLORINATION
  • 26. FLOW COMPARISONS: HDPE PIPE BURSTING AND PRE-CHLORINATION
  • 27. FLOW COMPARISONS: HDPE PIPE BURSTING AND PRE-CHLORINATION
  • 28. EQUIPMENT SELECTION • Static equipment is most common for water projects • High tonnage static pull back force –38 ton (2” – 6” pipe) –58 ton (4” – 8” pipe) –100 ton (4” – 16” pipe) –125 ton (6” – 20” pipe) –175 ton (6”- 24” pipe) • No-contamination of the new Fusible PVC pipe or HDPE. PIPE BURSTING AND PRE-CHLORINATION
  • 29. WATER MAIN PROBLEMS • Received complaints regarding potable water clarity and low pressure concerns • Cast iron water main breaks • New service line installations required • Limited working space, easement issues, and heavy traffic • Expense of open cut not a feasible option • Congested utility infrastructure PIPE BURSTING AND PRE-CHLORINATION
  • 30. TYPICAL JOBSITE Launch, reception and service pits. PIPE BURSTING AND PRE-CHLORINATION
  • 31. NETWORK MODELING/PROJECT DESIGN • Flow requirements: HDPE / Fusible PVC Slip-line or Burst? • Site investigation –Pothole main and confirm main depth, location and material –Review proximity to other utilities • Sampling Investigations –Downstream Series Sampling:- • 1 Source • 50 Address (>50μg/litre) – (>20μg/litre more than source) –Pre and Post Renovation Sampling:- • 10 Source • 10 Address (>50μg/litre) – (>20μg/litre more than source) PIPE BURSTING AND PRE-CHLORINATION
  • 32. CUSTOMER NOTIFICATION • Customers are notified of mains replacement project by door hanger outlining the project scope • Hanger is provided to home owner 48 hours prior to work being performed on their line section • Approximately 15 to 20 homes will be off water from 8:00 am to 3:00 pm on the day of pipe bursting operations • Construction crew will be moved onward the following day PIPE BURSTING AND PRE-CHLORINATION
  • 33. PRE-CHLORINATING PROCEDURES • Liverpool Depot Coil Pre-chlorinating Operations –Chlorinated Water is filled into the HDPE pipe coils and left for 24 hours then flushed and a sample taken. PIPE BURSTING AND PRE-CHLORINATION
  • 34. FUSE ON ADAPTORS PIPE BURSTING AND PRE-CHLORINATION
  • 35. PRE-CHLORINATING PROCEDURES –Passed Coils are Marked-up with Gang Name, Location and Sample Reference Number. –Coils are Stored in goods-out bay prior to collection –Coils are Loaded on to Carousel by fork-lift truck –2 No. Check Sample Points • To check Dosage of Chloros is maintained at 25 to 30mg/l • To check de-chlorination of water prior to disposal PIPE BURSTING AND PRE-CHLORINATION
  • 36. PRE-CHLORINATING PROCEDURES • Lengths of Main Above and Below Ground Pre-chlorinating Operations –Very similar to coil pre-chlorinating procedure –Source of water from on-site hydrant –All hoses used in operation are pre-chlorinated –Mobile dosage unit is used • Inputs the required chloros in to the main • De-chlorinates the water prior to discharge to sanitary sewer –Each length requires a 12 hour dosage period prior to laboratory sample being taken –Results are received next day via fax prior to being put into commission PIPE BURSTING AND PRE-CHLORINATION
  • 37. CONSTRUCTION ACTIVITY: DAY OF OPERATIONS • Excavate launch, reception and service pits. PIPE BURSTING AND PRE-CHLORINATION
  • 38. CONSTRUCTION ACTIVITY: DAY OF OPERATIONS • Cut existing cast-iron main, install cap end and secure. Re-establish supply to existing main. PIPE BURSTING AND PRE-CHLORINATION
  • 39. CONSTRUCTION ACTIVITY: DAY OF OPERATIONS • Position rig into launch and reception pit and pay out rod. (avg. 45 minutes to payout 350’ of rod) PIPE BURSTING AND PRE-CHLORINATION
  • 40. CONSTRUCTION ACTIVITY: DAY OF OPERATIONS • Guide rod enters reception pit. PIPE BURSTING AND PRE-CHLORINATION
  • 41. CONSTRUCTION ACTIVITY: DAY OF OPERATIONS • Connect pulling head to fusible PVC or HDPE pipe. Bursting blade and expander to pulling rods. PIPE BURSTING AND PRE-CHLORINATION
  • 42. CONSTRUCTION ACTIVITY: DAY OF OPERATIONS • Pull back until bursting blade arrives at reception pit. (This takes an average of 45 – 60 minutes for 350’) PIPE BURSTING AND PRE-CHLORINATION
  • 43. CONSTRUCTION ACTIVITY: DAY OF OPERATIONS • Undertake swabbing exercise • Purge air out of new HDPE main through Installed ferrule at pipe end • Connect cap-end control and pressure test pipe. • Take bacteriological sample • Turn water back on PIPE BURSTING AND PRE-CHLORINATION
  • 44. CONSTRUCTION ACTIVITY: DAY OF OPERATIONS • Install necessary branches, valves and hydrants. PIPE BURSTING AND PRE-CHLORINATION
  • 45. CONSTRUCTION ACTIVITY: DAY OF OPERATIONS • Pneumatic piercing tools used for installing new services. PIPE BURSTING AND PRE-CHLORINATION
  • 46. CONSTRUCTION ACTIVITY: DAY OF OPERATIONS • Install electro-fusion saddles for service connections. PIPE BURSTING AND PRE-CHLORINATION
  • 47. CONSTRUCTION ACTIVITY: DAY OF OPERATIONS • Backfill excavation and permanently re- instate. PIPE BURSTING AND PRE-CHLORINATION
  • 48. CONCLUSIONS • UK has 13 major water companies serving 66 million people. • Pre-chlorinated Pipe Bursting has nearly obsoleted open trench replacement of water mains in the UK • USA has approved pre-chlorination in the majority of the US. Pipe Bursting water mains in the USA will continue to see solid growth, but is currently limited by: –Engineers specifying and water companies embracing HDPE for water rehab jobs –Lack of projects specifying the Pipe Bursting and pre-chlorinated methods PIPE BURSTING AND PRE-CHLORINATION
  • 49. CASE STUDY BROWNSTOWN WATER IMPROVEMENT PROJECT A joint venture of Bidigare Contractors, Inc., Northville, Michigan and D & D Water & Sewer, Inc., Canton, Michigan.
  • 50. TOWNSHIP OF BROWNSTOWN, MICHIGAN • Ambitious water-system improvement program that includes replacing nearly eight miles of water mains. • Most of it with pre-chlorinated HDPE pipe installed by pipe bursting. • It is the first time the Township has installed pre-chlorinated pipe or used pipe bursting. • Their contract calls for installation of 43,000 feet of new water mains, most of it 8- and 12-inch pre-chlorinated HDPE pipe and installation of fire hydrants and gatewells. PIPE BURSTING AND PRE-CHLORINATION
  • 51. Existing water main pipes in Brownstown, Michigan.
  • 52. Setting the down hole machine for the first burst.
  • 53. Fusion of the new pipe to be installed.
  • 54. Staging of HDPE pipe sticks for fusion.
  • 56. A section of new pipe shown with the tooling required to replace the existing pipe. The tooling will be attached to the rod string that is pushed out by the down hole unit.
  • 57. Inside of a connection pit, the bursting process is shown.
  • 58. Inside of another connection pit, the expander and tooling is shown bursting through old segments of pipe.
  • 59. CONCLUSION • Township is so satisfied with how the project progressed; another 30,000 feet of improvements have been added that will extend completion to 2013.
  • 60. THANK YOU FIRST NAME LAST NAME PRESENTER TITLE E: info@hammerheadmole.com P: 800.331.6653 | INT: +1.262.567.8833 | F: 262.567.5068 W: www.hammerheadtrenchless.com