SlideShare une entreprise Scribd logo
1  sur  3
Traditional Procurement Method
This is a common method that has been usually used in construction industry. Traditional
method is a procurement method that the design work will separate from construction. The
developer or client would appoint an architect to complete the design and produce
specifications of the building. The consultant team is appointed to take control of design
and cost. Upon the completion of the design, client will appoint a main contractor to carry
out the works through bidding. The contractor prepares the tender documents base on the
specifications and drawings or the bill. The lowest tenderer usually will be awarded the
contract. The contractor need to take responsibility to all the workmanship and materials
which including all works by the sub-contractors.
Based on the chart that had been shown above, the client has contractual relationship with
all parties. In this way, the client would have the closer control of the works. However, this
may bring risks in control of works of the project since the client need to deal with many
points of responsibility.
Firstly, client will appoint a consultant team which included architect, quantity surveyor and
engineers to come out with the drawings and specifications of the building. The quantity
surveyor in the consultant team will come out with the bills of quantity base on the
drawings that have been provided by the architect and engineer.
The employer appoints the contractor team to be in charge of the construction works only.
Therefore, the contractor team does not need to take responsibility for the design works.
Then, the contractor may appoint other subcontractor to undertake specialize works.
Advantages of Traditional Method
Traditional method usually come out with high quality works since the client has the closer
control to the works. For example, the consultant team must provide a design which meet
the requirements of the client. Besides, due to the advices and construction expertise that
provide by the consultant and contractor, client may compare and consider which design
and budget is more suitable for the project.
In traditional method, all tenderers produce a tender base on the same information.
Therefore, client may obtain the best or lowest price through competitive tendering.
Besides, the construction cost will be more accurate since the tender is bases on the
complete design and specifications.
If compare with other procurement method, traditional method will be easier to be
adopted. It is because this method had been commonly used for a long time, so, both
contractor and consultant team are familiar to solve or face the risks during the
procurement state of a construction progress.
Disadvantages of Traditional Method
For traditional method, client may hard to manage the project since he need to
communicate with few parties at the same time. For example, the consultant and contractor
do not have contractual relationship, hence, if they need to communicate with each other,
they must communicate with the client first, which is very inconvenience. There may be
miscommunication since the client need to communicate with so many organization too.
Traditional method requires longer period to complete the project. It is because the tender
will be provided after the design is fully completed. Furthermore, if problems occur,
consultant and contractor may shirk the responsibility to each other. The argument and
problems may need a long time to be settled.
Clear Example
The purpose of our project is to build a 20 storey condominium, assume that there is a
problem from the drawing of the design and the contractor wants to communicate and get
information from consultant team.
For traditional method, the contractor will only be appointed after the design is done,
therefore, contractor is unable to plan for the project and input his design. So, the
contractor need to communicate with the client first, then only the client will communicate
with the consultant, since, there is no contractual relationship between the consultant team
and contractor team. Besides, the changes of the design need to be approved by the client
first.
References
 C.M., Y.S., n.d. Procurement models: improving on the traditional method ... [WWW
Document]. MinterEllison. URL
http://www.minterellison.com/Pub/NL/201112_CLAa/ (accessed 12.15.11).
 @ukessays, n.d. What Is The Procurement Method Construction Essay [WWW
Document]. UKEssays. URL https://www.ukessays.com/essays/construction/what-is-
the-procurement-method-construction-essay.php (accessed 3.23.15).
 D.P., n.d. Building Procurement Methods - Construction Innovation [WWW
Document]. URL http://www.construction-
innovation.info/images/pdfs/Research_library/ResearchLibraryC/2006-034-
C/reports/Report_-_Building_Procurement_Methods.pdf (accessed 6.8).

Contenu connexe

Tendances

ECA Workshop - Brief
ECA Workshop - BriefECA Workshop - Brief
ECA Workshop - BriefKai Yun Pang
 
Standard bill of quantities
Standard bill of quantitiesStandard bill of quantities
Standard bill of quantitiesBt Lee
 
Lecture 1 introduction to construction procurement process.
Lecture 1   introduction to construction procurement process.Lecture 1   introduction to construction procurement process.
Lecture 1 introduction to construction procurement process.Aszahari Aie
 
Construction process
Construction processConstruction process
Construction processMazen Al-Qadi
 
50451783 taking-off-quantity
50451783 taking-off-quantity50451783 taking-off-quantity
50451783 taking-off-quantityhlksd
 
Professional Practice 1 Group Assignment
Professional Practice 1 Group AssignmentProfessional Practice 1 Group Assignment
Professional Practice 1 Group AssignmentHaziq1511
 
Single stage design and build method & construction project management
Single stage design and build method & construction project managementSingle stage design and build method & construction project management
Single stage design and build method & construction project managementJohn Constance
 
Estimating calculation
Estimating calculationEstimating calculation
Estimating calculationZIyeeTan
 
A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 Pang Khai Shuen
 
Strategies in building procurement (summarized)
Strategies in building procurement (summarized)Strategies in building procurement (summarized)
Strategies in building procurement (summarized)Michael Audu
 
Tender Process | A Complete Procurement Guide
Tender Process | A Complete Procurement GuideTender Process | A Complete Procurement Guide
Tender Process | A Complete Procurement GuideTender Process
 
Stakeholder’s Involvement in Construction Industry
Stakeholder’s Involvement in Construction IndustryStakeholder’s Involvement in Construction Industry
Stakeholder’s Involvement in Construction IndustryAkshika Mahanama
 
Bill of Quantities ( Door and Window )
Bill of Quantities ( Door and Window )Bill of Quantities ( Door and Window )
Bill of Quantities ( Door and Window )Lee Pei Gie
 
Assignment - Management Contracting
Assignment - Management ContractingAssignment - Management Contracting
Assignment - Management ContractingKai Yun Pang
 

Tendances (20)

ECA Workshop - Brief
ECA Workshop - BriefECA Workshop - Brief
ECA Workshop - Brief
 
Standard bill of quantities
Standard bill of quantitiesStandard bill of quantities
Standard bill of quantities
 
Lecture 1 introduction to construction procurement process.
Lecture 1   introduction to construction procurement process.Lecture 1   introduction to construction procurement process.
Lecture 1 introduction to construction procurement process.
 
Construction process
Construction processConstruction process
Construction process
 
50451783 taking-off-quantity
50451783 taking-off-quantity50451783 taking-off-quantity
50451783 taking-off-quantity
 
Professional Practice 1 Group Assignment
Professional Practice 1 Group AssignmentProfessional Practice 1 Group Assignment
Professional Practice 1 Group Assignment
 
Single stage design and build method & construction project management
Single stage design and build method & construction project managementSingle stage design and build method & construction project management
Single stage design and build method & construction project management
 
Estimating calculation
Estimating calculationEstimating calculation
Estimating calculation
 
TENDER DOCUMENT
TENDER DOCUMENTTENDER DOCUMENT
TENDER DOCUMENT
 
A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1
 
Earthwork
EarthworkEarthwork
Earthwork
 
Preliminary estimate
Preliminary estimatePreliminary estimate
Preliminary estimate
 
Strategies in building procurement (summarized)
Strategies in building procurement (summarized)Strategies in building procurement (summarized)
Strategies in building procurement (summarized)
 
Elemental Cost Analysis
Elemental Cost AnalysisElemental Cost Analysis
Elemental Cost Analysis
 
Tender Process | A Complete Procurement Guide
Tender Process | A Complete Procurement GuideTender Process | A Complete Procurement Guide
Tender Process | A Complete Procurement Guide
 
Stakeholder’s Involvement in Construction Industry
Stakeholder’s Involvement in Construction IndustryStakeholder’s Involvement in Construction Industry
Stakeholder’s Involvement in Construction Industry
 
Bills of quantities
Bills of quantitiesBills of quantities
Bills of quantities
 
Bill of Quantities ( Door and Window )
Bill of Quantities ( Door and Window )Bill of Quantities ( Door and Window )
Bill of Quantities ( Door and Window )
 
Assignment - Management Contracting
Assignment - Management ContractingAssignment - Management Contracting
Assignment - Management Contracting
 
Procurement types
Procurement typesProcurement types
Procurement types
 

En vedette

Miros Design Build Approach 3.20.02
Miros Design Build Approach 3.20.02Miros Design Build Approach 3.20.02
Miros Design Build Approach 3.20.02guest2aa104
 
Design build risks and rewards for public owner
Design build risks and rewards for public ownerDesign build risks and rewards for public owner
Design build risks and rewards for public ownerJon Straw
 
Design-Build: The Owner’s Role in Successful Outcomes
Design-Build: The Owner’s Role in Successful OutcomesDesign-Build: The Owner’s Role in Successful Outcomes
Design-Build: The Owner’s Role in Successful OutcomesMcCarthy Holdings, Inc.
 
Developing Procurement Documents for Progressive Design-Build Projects
Developing Procurement Documents for Progressive Design-Build ProjectsDeveloping Procurement Documents for Progressive Design-Build Projects
Developing Procurement Documents for Progressive Design-Build ProjectsWater Design-Build Council
 
Tendering documentation
Tendering documentationTendering documentation
Tendering documentationnipuna_bopage
 

En vedette (6)

TRADITIONAL DESIGN METHOD
TRADITIONAL DESIGN METHODTRADITIONAL DESIGN METHOD
TRADITIONAL DESIGN METHOD
 
Miros Design Build Approach 3.20.02
Miros Design Build Approach 3.20.02Miros Design Build Approach 3.20.02
Miros Design Build Approach 3.20.02
 
Design build risks and rewards for public owner
Design build risks and rewards for public ownerDesign build risks and rewards for public owner
Design build risks and rewards for public owner
 
Design-Build: The Owner’s Role in Successful Outcomes
Design-Build: The Owner’s Role in Successful OutcomesDesign-Build: The Owner’s Role in Successful Outcomes
Design-Build: The Owner’s Role in Successful Outcomes
 
Developing Procurement Documents for Progressive Design-Build Projects
Developing Procurement Documents for Progressive Design-Build ProjectsDeveloping Procurement Documents for Progressive Design-Build Projects
Developing Procurement Documents for Progressive Design-Build Projects
 
Tendering documentation
Tendering documentationTendering documentation
Tendering documentation
 

Similaire à Traditional procurement method

Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1Lee Pei Gie
 
Professional practice 1 (QS)
Professional practice 1 (QS)Professional practice 1 (QS)
Professional practice 1 (QS)Hasif Alias
 
Procurement Methods and their Application.
Procurement Methods and their Application.Procurement Methods and their Application.
Procurement Methods and their Application.Lilian Nwachukwu
 
Pp1 report
Pp1 reportPp1 report
Pp1 reportahmong4
 
Professional Practice I Assignment
Professional Practice I AssignmentProfessional Practice I Assignment
Professional Practice I Assignmentashleyyeap
 
Pp1 assignment group 8
Pp1 assignment group 8Pp1 assignment group 8
Pp1 assignment group 8lohwenjun
 
Professional practice 1 (1)
Professional practice 1 (1)Professional practice 1 (1)
Professional practice 1 (1)tfkc1212
 
Professional Practice
Professional PracticeProfessional Practice
Professional Practiceseenyeeyong
 
Pp 1-report-complete
Pp 1-report-completePp 1-report-complete
Pp 1-report-completeYong Sy
 
Pp group assignment
Pp group assignmentPp group assignment
Pp group assignmentwendyteosy
 
Yam yih hwan pp1 assignment aug 14
Yam yih hwan   pp1 assignment aug 14Yam yih hwan   pp1 assignment aug 14
Yam yih hwan pp1 assignment aug 14마 이환
 
Professional Practice 1 Assignment
Professional Practice 1 AssignmentProfessional Practice 1 Assignment
Professional Practice 1 AssignmentMelvin Lim
 
Pp1 assignment
Pp1 assignmentPp1 assignment
Pp1 assignmentLwj Welson
 
Pp1 assignment
Pp1 assignmentPp1 assignment
Pp1 assignmentLwj Welson
 
Professional Practice 1 Proposal Report
Professional Practice 1 Proposal ReportProfessional Practice 1 Proposal Report
Professional Practice 1 Proposal ReportArissa Loh
 
Estimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction WorkEstimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction WorkDaniel Ross
 

Similaire à Traditional procurement method (20)

Purpose
PurposePurpose
Purpose
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1
 
Professional practice 1 (QS)
Professional practice 1 (QS)Professional practice 1 (QS)
Professional practice 1 (QS)
 
Procurement Methods and their Application.
Procurement Methods and their Application.Procurement Methods and their Application.
Procurement Methods and their Application.
 
Pp1 report
Pp1 reportPp1 report
Pp1 report
 
Professional Practice I Assignment
Professional Practice I AssignmentProfessional Practice I Assignment
Professional Practice I Assignment
 
Pp1 assignment group 8
Pp1 assignment group 8Pp1 assignment group 8
Pp1 assignment group 8
 
Professional practice 1 (1)
Professional practice 1 (1)Professional practice 1 (1)
Professional practice 1 (1)
 
Professional Practice
Professional PracticeProfessional Practice
Professional Practice
 
Pp 1-report-complete
Pp 1-report-completePp 1-report-complete
Pp 1-report-complete
 
Pp group assignment
Pp group assignmentPp group assignment
Pp group assignment
 
Pp1 final
Pp1 finalPp1 final
Pp1 final
 
Yam yih hwan pp1 assignment aug 14
Yam yih hwan   pp1 assignment aug 14Yam yih hwan   pp1 assignment aug 14
Yam yih hwan pp1 assignment aug 14
 
Professional Practice 1 Assignment
Professional Practice 1 AssignmentProfessional Practice 1 Assignment
Professional Practice 1 Assignment
 
Pp report
Pp reportPp report
Pp report
 
Pp1 assignment
Pp1 assignmentPp1 assignment
Pp1 assignment
 
Pp1 assignment
Pp1 assignmentPp1 assignment
Pp1 assignment
 
Professional Practice 1 Proposal Report
Professional Practice 1 Proposal ReportProfessional Practice 1 Proposal Report
Professional Practice 1 Proposal Report
 
Estimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction WorkEstimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction Work
 
Pp1 group assignment
Pp1 group assignmentPp1 group assignment
Pp1 group assignment
 

Dernier

Presentation Activity 2. Unit 3 transv.pptx
Presentation Activity 2. Unit 3 transv.pptxPresentation Activity 2. Unit 3 transv.pptx
Presentation Activity 2. Unit 3 transv.pptxRosabel UA
 
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptxAUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptxiammrhaywood
 
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdfInclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdfTechSoup
 
Keynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designKeynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designMIPLM
 
Millenials and Fillennials (Ethical Challenge and Responses).pptx
Millenials and Fillennials (Ethical Challenge and Responses).pptxMillenials and Fillennials (Ethical Challenge and Responses).pptx
Millenials and Fillennials (Ethical Challenge and Responses).pptxJanEmmanBrigoli
 
Integumentary System SMP B. Pharm Sem I.ppt
Integumentary System SMP B. Pharm Sem I.pptIntegumentary System SMP B. Pharm Sem I.ppt
Integumentary System SMP B. Pharm Sem I.pptshraddhaparab530
 
Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4JOYLYNSAMANIEGO
 
ROLES IN A STAGE PRODUCTION in arts.pptx
ROLES IN A STAGE PRODUCTION in arts.pptxROLES IN A STAGE PRODUCTION in arts.pptx
ROLES IN A STAGE PRODUCTION in arts.pptxVanesaIglesias10
 
ICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdfICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdfVanessa Camilleri
 
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)lakshayb543
 
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17Celine George
 
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptxQ4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptxlancelewisportillo
 
Active Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdfActive Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdfPatidar M
 
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdfVirtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdfErwinPantujan2
 
Concurrency Control in Database Management system
Concurrency Control in Database Management systemConcurrency Control in Database Management system
Concurrency Control in Database Management systemChristalin Nelson
 
Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Celine George
 

Dernier (20)

Presentation Activity 2. Unit 3 transv.pptx
Presentation Activity 2. Unit 3 transv.pptxPresentation Activity 2. Unit 3 transv.pptx
Presentation Activity 2. Unit 3 transv.pptx
 
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptxAUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptx
 
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdfInclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
 
Keynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designKeynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-design
 
Paradigm shift in nursing research by RS MEHTA
Paradigm shift in nursing research by RS MEHTAParadigm shift in nursing research by RS MEHTA
Paradigm shift in nursing research by RS MEHTA
 
Millenials and Fillennials (Ethical Challenge and Responses).pptx
Millenials and Fillennials (Ethical Challenge and Responses).pptxMillenials and Fillennials (Ethical Challenge and Responses).pptx
Millenials and Fillennials (Ethical Challenge and Responses).pptx
 
Integumentary System SMP B. Pharm Sem I.ppt
Integumentary System SMP B. Pharm Sem I.pptIntegumentary System SMP B. Pharm Sem I.ppt
Integumentary System SMP B. Pharm Sem I.ppt
 
Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4
 
ROLES IN A STAGE PRODUCTION in arts.pptx
ROLES IN A STAGE PRODUCTION in arts.pptxROLES IN A STAGE PRODUCTION in arts.pptx
ROLES IN A STAGE PRODUCTION in arts.pptx
 
ICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdfICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdf
 
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
 
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
 
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptxQ4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
 
YOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptx
YOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptxYOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptx
YOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptx
 
INCLUSIVE EDUCATION PRACTICES FOR TEACHERS AND TRAINERS.pptx
INCLUSIVE EDUCATION PRACTICES FOR TEACHERS AND TRAINERS.pptxINCLUSIVE EDUCATION PRACTICES FOR TEACHERS AND TRAINERS.pptx
INCLUSIVE EDUCATION PRACTICES FOR TEACHERS AND TRAINERS.pptx
 
FINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptx
FINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptxFINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptx
FINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptx
 
Active Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdfActive Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdf
 
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdfVirtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
 
Concurrency Control in Database Management system
Concurrency Control in Database Management systemConcurrency Control in Database Management system
Concurrency Control in Database Management system
 
Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17
 

Traditional procurement method

  • 1. Traditional Procurement Method This is a common method that has been usually used in construction industry. Traditional method is a procurement method that the design work will separate from construction. The developer or client would appoint an architect to complete the design and produce specifications of the building. The consultant team is appointed to take control of design and cost. Upon the completion of the design, client will appoint a main contractor to carry out the works through bidding. The contractor prepares the tender documents base on the specifications and drawings or the bill. The lowest tenderer usually will be awarded the contract. The contractor need to take responsibility to all the workmanship and materials which including all works by the sub-contractors. Based on the chart that had been shown above, the client has contractual relationship with all parties. In this way, the client would have the closer control of the works. However, this may bring risks in control of works of the project since the client need to deal with many points of responsibility. Firstly, client will appoint a consultant team which included architect, quantity surveyor and engineers to come out with the drawings and specifications of the building. The quantity surveyor in the consultant team will come out with the bills of quantity base on the drawings that have been provided by the architect and engineer. The employer appoints the contractor team to be in charge of the construction works only. Therefore, the contractor team does not need to take responsibility for the design works. Then, the contractor may appoint other subcontractor to undertake specialize works.
  • 2. Advantages of Traditional Method Traditional method usually come out with high quality works since the client has the closer control to the works. For example, the consultant team must provide a design which meet the requirements of the client. Besides, due to the advices and construction expertise that provide by the consultant and contractor, client may compare and consider which design and budget is more suitable for the project. In traditional method, all tenderers produce a tender base on the same information. Therefore, client may obtain the best or lowest price through competitive tendering. Besides, the construction cost will be more accurate since the tender is bases on the complete design and specifications. If compare with other procurement method, traditional method will be easier to be adopted. It is because this method had been commonly used for a long time, so, both contractor and consultant team are familiar to solve or face the risks during the procurement state of a construction progress. Disadvantages of Traditional Method For traditional method, client may hard to manage the project since he need to communicate with few parties at the same time. For example, the consultant and contractor do not have contractual relationship, hence, if they need to communicate with each other, they must communicate with the client first, which is very inconvenience. There may be miscommunication since the client need to communicate with so many organization too. Traditional method requires longer period to complete the project. It is because the tender will be provided after the design is fully completed. Furthermore, if problems occur, consultant and contractor may shirk the responsibility to each other. The argument and problems may need a long time to be settled. Clear Example The purpose of our project is to build a 20 storey condominium, assume that there is a problem from the drawing of the design and the contractor wants to communicate and get information from consultant team. For traditional method, the contractor will only be appointed after the design is done, therefore, contractor is unable to plan for the project and input his design. So, the contractor need to communicate with the client first, then only the client will communicate with the consultant, since, there is no contractual relationship between the consultant team and contractor team. Besides, the changes of the design need to be approved by the client first.
  • 3. References  C.M., Y.S., n.d. Procurement models: improving on the traditional method ... [WWW Document]. MinterEllison. URL http://www.minterellison.com/Pub/NL/201112_CLAa/ (accessed 12.15.11).  @ukessays, n.d. What Is The Procurement Method Construction Essay [WWW Document]. UKEssays. URL https://www.ukessays.com/essays/construction/what-is- the-procurement-method-construction-essay.php (accessed 3.23.15).  D.P., n.d. Building Procurement Methods - Construction Innovation [WWW Document]. URL http://www.construction- innovation.info/images/pdfs/Research_library/ResearchLibraryC/2006-034- C/reports/Report_-_Building_Procurement_Methods.pdf (accessed 6.8).