1. Tutor : Mohamed Rizal Mohamed Project 1 : Industrialised Building System (IBS)
LAM O WEN
GAN TECK YOU
HILMAN AQIL
JOCELYN JILL
STEVEN FERNANDO
0332615
0332294
0332341
0332751
0336748
STEEL FRAMING SYSTEM
ADVANCED
ARCHITECTURAL
CONSTRUCTION
PRODUCEDBYANAUTODESKSTUDENTVERSION
PRODUCEDBYANAUTODESKSTUDENTVERSION
PRODUCED BY AN AUTODESK STUDENT VERSION
3. I
N
T
R
O
D
U
C
T
I
O
N
I
B
S
NDUSTRIALISED
UILDING
YSTEM
Industrialisation process is an investment in equipment, facilities and technology with the objective of maximising production
output, minimising labour resource and improving quality while a building system is define as a set of interconnected element
that joint together to enable the designated performance of a building (Warswaski, 1999). The industrialised building system (IBS)
can be defined in which all building such as wall, slab, beam, column and staircase are mass produced either in factory or at site factory
under strict quality control and minimal wet site activities.
In Malaysia, Construction Industry Development Board (CIDB) formed in 1994 have been educating contractors with the concept of
IBS functioning as “assemblys of components” and implemented IBS Scoring System to measure the level of IBS usage in buildings.
CLASSIFICATIONS OF IBS
FORMWORK SYSTEM BLOCKWORK SYSTEM STEEL FRAMING SYSTEM TIMBER FRAMING SYSTEM PRE-CAST SYSTEM
Main focus on steel framing system for its
lightness and effectiveness in time. The
elements used from steel framing system
are beams, columns, trussess and portal
frames. Usually combined with pre-
cast beams, columns and floor slabs.
Due to its properties, it is used extensively
in skyscrapers.
Formwork system offer high quality
finishes, and fast construction with less
site labour and material requirement.
Used in different types of structural
construction due to it flexibility.
Usually applied in tunnel forms, tilt-
up systems, beams and columns
moulding forms, and permanent
steel formworks.
The construction method of using
conventional bricks has been developed with
the use of interlocking concrete masonry
units (CMU) and lightweight concrete
blocks. The tedious and time-consuming
traditional brick-laying tasks are greatly
simplified by the usage of these effective
alternative solutions.
This system involves prefabricated timber
truss beams and columns. It is quite popular
and widely applicable as it provides attractive
designs and high aesthetic values as chalets
for resorts,contributing very much to the
tourism industry
Precast concrete system is the group that
is most widely used in the IBS. It includes
precast concretecolumns, beams, slabs, walls,
“3-D” components such as balconies, stairs,
toilets, liftchambers, refuse chambers,
lightweight precast concrete, as well
as permanent concrete formworks
4. COMPARISON OF INDUSTRIALISED BUILDING SYSTEM AND COMMERCIAL CONSTRUCTION
Pre-engineered construction lends itself toward a simpler design,
quick and effiecient. Each component is fabricated to suit the
design, and then the steel structures are delivered to site.
Because the design creates standard sections and connections,
pre-engineered buildings are quickly erected onsite. Also,
since the framing components are pre-fabricated, foundations
are accurately determined based on weight. As a result,
pre-engineered buildings have a quicker project turnaround
and can often be delivered within two months (as compared
to six to ten months for conventional builds). Between ease of
coordination (pre-engineered construction utilizes fewer
subcontractors), speedy installation, less mess and waste,
this method lowers labour costs, and increases productivity.
Pros and Cons
Pre-engineered construction isn’t ideal for every project type.
However, if the design constraints are equitable for your
project, pre-engineered buildings offer a lower cost, less waste,
low maintenance, durability, seismic soundness (flexible frames),
and ease of expansion. Pre-engineered metal buildings are
ideal for commercial and industrial construction projects such
as gas stations, self-storage facilities, recreational facilities, and
office/shop projects.
Typically, conventional construction occurs step-by-step: excavation
and foundations are constructed before framing begins. Each
component must be completed before moving to the next step,
so scheduling is dependent upon each trade’s efficiency. Design
impacts schedule immensely, particularly if it’s a complex design
and because each component is designed from scratch, the project
duration averages about six to ten months. Conventional
construction is ideal for complex designs.
Generally, the conventional system is comparatively cheap compared to IBS
system. In Malaysia for example, the number of projects
utilizing IBS is generally low and therefore, the market demand for
IBS manufacturers and IBS usage is low as well, thus giving rise to the high
cost. In addition, through a study, 44% strongly agreed that they preferred
conventional system than IBS because they found that conventional system is
more open and flexible. An open or flexible system would be easier to
implement since mostly timber, steel bar and nails only are required for
construction. These items does not need to be custom-fabricated and can be
fabricated on site. However, majority (89%) of respondents, especially from the
contractors, strongly disagreed that conventional method is cleaner, safer and
neater. In fact, 74% of respondents did not think that conventional systems
will decrease labor, compared with 43% in the case of IBS.
5. STEEL
FRAMING
SYSTEM
Strength and Durability :
Structural steel have dominating the weight bearing
timber . Its is lighter and stronger . A typical weight – bearing
steel fabrication is 30 % to 50 % lighter that a wooden equivalet.
So it makel steel frame construction far stronger and more
durable than the traditional wood or concreteframed alternatives.
Fire Resistance :
Structural steel frame constructions are resistant to fire , it
can reduce the fire risk to the building and retarding the
spread of a fire should one occur.
Effective Build Time :
Most steel part are prefabricated to a
specific form ordesign in the manufacturing process . These
parts can directly send to construction site . The human errors
are low because the manufacture build the steel part according
to the respective code standard and dimension.
Moisture and Weather Resistance :
Structural steel frame have great moisture resistant properties.
It component even more immune if the steel is coated with hot
zinc and powder treatments or anti paint rust .
Maintenance cost :
Steel structure is expensive to maintain due to
the action of the rust. Anti rust paint are
expensive and required to renew time to time.
Fire Resistance :
Even thought , steel is fire
resistance but it only have a very small resistance
compared to concrete . In high temperatures,
steel loses its properties. Almost from 600-700C
half of steel strength reduced.
Shape Mold :
Steel cannot be mold in any direction
because steel is only available in standard sizes and
shape , it can only be used in forms in which
sections originally exits . Not like concrete , it can
take any shape when used with suitable form work
due the meability of Newtonian fluid state from
liquid to solid.
ADVANTAGES DISADVANTAGES
6. P
R
E
C
E
D
E
N
C
E
S
T
U
D
I
E
S
a) original bracing for one of the lateral walls
using 120x0.8 Fe360 steel straps on both
side of the wall fastened at the ends with 5.5
self-drilling screws
b) lateral wall covered with LLP20/0.5
external sheeting, fastened in every trough
with 5.5 mm self-drilling screws
c) equivalent bracing, having the same
rigidity
Horizontal and vertical bracing connection
STEEL BRACING SYSTEM
BULZECS’S HOUSE
FUNCTION OF BUILDING : PRIVATE SINGLE-FAMILY HOUSE
LOCATION : TIMISOARA,ROMANIA
AREA OF HOUSE : 117.5 m
CONSTRUCTION PERIOD : 1999-2000
CONTRACTOR : LINDAB Ltd. Bucharest
IBS METHOD : STEEL FRAMING SYSTEM
IBS COMPONENTS : STEEL FRAMING,CONCRETE FLOOR SLAB
2
7. TERMOINDUSTRIAL STRUCTURE
FUNCTION OF BUILDING : SINGLE STOREY INDUSTRIAL BUILDING
LOCATION : ARAD,ROMANIA
AREA : 294 m
CONTRACTOR : LINDAB Ltd. Bucharest
IBS METHOD : STEEL FRAMING SYSTEM
2
The structure is composed by transversal frames made by built-up cold-formed
lipped channel steel. The structure has been longitudinally and transversally
braced, both in walls and roof using tension rods.
The welded connections are connections which
two components are jointed together become
a primarily structure by welds.
17. 1 2 3 4 5 6
F
G
H
I
J
7 8 9 10 11
E
D
C
B
A
1500190012003400340012003400
800041008000
1700 1700 3200 2500 3400 3400 2500 3200 3400
12500 4100 12500
29100
ScaleChecked by
Drawn by
Date
Project number
1 : 150
17/5/202010:54:34PM
STRUCTURAL PLAN
0001
ADVANCED ARCHITECTURAL CONTRUCTION
ARC 60104
Issue Date
Author
Checker
00
1 : 150
STRUCTURAL PLAN
1
18. 1 2 3 4 5 6
F
G
H
I
J
7 8 9 10 11
E
D
C
B
A
1700 1700 3200 2500 3400 5900 3200 3400
12500 4100 12500
29100
1500190012003400340012003400
800041008000
20100
MASTER
BEDROOM BEDROOM 2
BEDROOM 3
BATH 2MASTER
BATH
LIVING DINING
KITCHEN
YARD
MASTER
BEDROOMBEDROOM 2
BEDROOM 3
BATH 2 MASTER
BATH
LIVINGDINING
KITCHEN
YARD
MASTER
BEDROOM
BEDROOM 2
BEDROOM 3
BATH 2
MASTER
BATH
LIVING DINING
KITCHEN
YARD
MASTER
BEDROOM
BEDROOM 2
BEDROOM 3
BATH 2
MASTER
BATH
LIVINGDINING
KITCHEN
YARD
ScaleChecked by
Drawn by
Date
Project number
1 : 150
17/5/202010:20:16PM
GROUND FLOOR
0001
ADVANCED ARCHITECTURAL CONTRUCTION
ARC 60104
Issue Date
Author
Checker
01
1 : 150
GROUND FLOOR
1
19. 1 2 3 4 5 6
F
G
H
I
J
7 8 9 10 11
E
D
C
B
A
MASTER
BEDROOM BEDROOM 2
BEDROOM 3
BATH 2MASTER
BATH
LIVING DINING
KITCHEN
YARD
MASTER
BEDROOMBEDROOM 2
BEDROOM 3
BATH 2 MASTER
BATH
LIVINGDINING
KITCHEN
YARD
MASTER
BEDROOM
BEDROOM 2
BEDROOM 3
BATH 2
MASTER
BATH
LIVING DINING
KITCHEN
YARD
MASTER
BEDROOM
BEDROOM 2
BEDROOM 3
BATH 2
MASTER
BATH
LIVINGDINING
KITCHEN
YARD
1700 1700 3200 2500 3400 5900 3200 3400
12500 4100 12500
29100
1500190012003400340012003400
800041008000
20100
ScaleChecked by
Drawn by
Date
Project number
1 : 150
17/5/202010:20:38PM
FIRST FLOOR
0001
ADVANCED ARCHITECTURAL CONTRUCTION
ARC 60104
Issue Date
Author
Checker
02
1 : 150
FIRT FLOOR
1
20. 1 2 3 4 5 6
F
G
H
I
J
7 8 9 10 11
E
D
C
B
A
MASTER
BEDROOM BEDROOM 2
BEDROOM 3
BATH 2MASTER
BATH
LIVING DINING
KITCHEN
YARD
MASTER
BEDROOMBEDROOM 2
BEDROOM 3
BATH 2 MASTER
BATH
LIVINGDINING
KITCHEN
YARD
MASTER
BEDROOM
BEDROOM 2
BEDROOM 3
BATH 2
MASTER
BATH
LIVING DINING
KITCHEN
YARD
MASTER
BEDROOM
BEDROOM 2
BEDROOM 3
BATH 2
MASTER
BATH
LIVINGDINING
KITCHEN
YARD
1700 1700 3200 2500 3400 5900 3200 3400
12500 4100 12500
29100
1500190012003400340012003400
800041008000
20100
ScaleChecked by
Drawn by
Date
Project number
1 : 150
17/5/202010:21:07PM
SECOND FLOOR
0001
ADVANCED ARCHITECTURAL CONTRUCTION
ARC 60104
Issue Date
Author
Checker
03
1 : 150
SECOND FLOOR
1
21. 1 2 3 4 5 6
F
G
H
I
J
7 8 9 10 11
E
D
C
B
A
1700 1700 3200 2500 3400 3400 2500 3200 3400
29100
4100
340012001900150041001500190012003400
20100
ScaleChecked by
Drawn by
Date
Project number
1 : 150
17/5/202011:25:20PM
ROOF PLAN
0001
ADVANCED ARCHITECTURAL CONTRUCTION
ARC 60104
Issue Date
Author
Checker
09
1 : 150
ROOF
1
22. GROUND FLOOR
0
FIRT FLOOR
3200
1234567891011
FOUNDATION
-1010
SECOND FLOOR
6400
ROOF
9600
1700170032002500340041003400250032003400
29100
ScaleChecked by
Drawn by
Date
Project number
1 : 150
17/5/202010:21:25PM
FRONT ELEVATION
0001
ADVANCED ARCHITECTURAL CONTRUCTION
ARC 60104
Issue Date
Author
Checker
04
1 : 150
FRONT ELEVATION
1
23. GROUND FLOOR
0
FIRT FLOOR
3200
F G H I J
FOUNDATION
-1010
SECOND FLOOR
6400
ROOF
9600
EDCBA
3400 1200 1900 1500 4100 1500 1900 1200 3400
20100
ScaleChecked by
Drawn by
Date
Project number
1 : 150
17/5/202010:21:50PM
RIGHT ELEVATION
0001
ADVANCED ARCHITECTURAL CONTRUCTION
ARC 60104
Issue Date
Author
Checker
07
1 : 150
RIGHT ELEVATION
1
24. GROUND FLOOR
0
FIRT FLOOR
3200
FGHIJ
FOUNDATION
-1010
SECOND FLOOR
6400
ROOF
9600
E D C B A
3400 1200 1900 1500 1500 1900 1200 34004100
20100
ScaleChecked by
Drawn by
Date
Project number
1 : 150
17/5/202010:23:29PM
LEFT ELEVATION
0001
ADVANCED ARCHITECTURAL CONTRUCTION
ARC 60104
Issue Date
Author
Checker
06
1 : 150
LEFT ELEVATION
1
25. GROUND FLOOR
0
FIRT FLOOR
3200
1 2 3 4 5 6 7 8 9 10 11
FOUNDATION
-1010
SECOND FLOOR
6400
ROOF
9600
1700 1700 3200 2500 3400 4100 3400 2500 3200 3400
29100
ScaleChecked by
Drawn by
Date
Project number
1 : 150
17/5/202010:21:38PM
BACK ELEVATION
0001
ADVANCED ARCHITECTURAL CONTRUCTION
ARC 60104
Issue Date
Author
Checker
05
1 : 150
BACK ELEVATION
1
26. GROUND FLOOR
0
FIRT FLOOR
3200
1 2 3 4 5 6 7 8 9 10 11
FOUNDATION
-1010
SECOND FLOOR
6400
ROOF
9600
1700 1700 3200 2500 3400 4100 3400 2500 3200 3400
29100
ScaleChecked by
Drawn by
Date
Project number
1 : 150
17/5/202010:22:01PM
SECTION A-A'
0001
ADVANCED ARCHITECTURAL CONTRUCTION
ARC 60104
Issue Date
Author
Checker
08
1 : 150
SECTION A-A'
1
27. COMPONENT DOOR
ISOMETRIC
PLAN
QUANTITY 24 48
SYSTEM PREFABRICATED DOORS
2100mm
760mm
2100mm
800mm
COMPONENT SLAB
ISOMETRIC
ELEVATION
SYSTEM COMPOSITE METAL DECK
2100mm
200mm140mm 60mm
381mm
COMPONENT EXTERIOR WALLS INTERIOR WALLS
ISOMETRIC
PLAN
LENGTH
SYSTEM In-situ concrete Concrete panel
287m 651m
200mm
200mm3000mm
3000mm
COMPONENT FOUNDATION COLUMN BEAM
ISOMETRIC
PLAN
QUANTITY
SYSTEM In situ concrete
80
H Column I Beam
320 528
1000mm
400mm
200mm
200mm
200mm200mm
1000mm400mm
20mm
COMPONENT ROOF TRUSSES
ISOMETRIC
ELEVATION
QUANTITY
SYSTEM PREFABRICATED STEEL FRAMING
79 88
COMPONENT WINDOW
ISOMETRIC
PLAN
QUANTITY
SYSTEM PREFABRICATED WINDOWS
72
900mm
820mm
COMPONENT
ISOMETRIC
PLAN
QUANTITY
SYSTEM PRECAST CONCRETE
4
STAIRCASE
250mm
3900mm
1800mm
135mm
28. 1754.73 m2
584.91 m2
2339.64 m2 1.00 50
Part 1 : Structural Systems
Part 2 : Wall Systems
Total Part 2
Internal wall using precast
concrete panels
External wall using concrete
with reusable system formwork
287 m 0.4
651 m 1.0
938 m
Metal columns and beams +
Precast concrete slabs
= 285 m2 x 3 storey
= 1754.73 m2
(1754.73/2339.64)
= 0.75
(0.75x1.0x50)
= 37.5
Prefab metal roof trusses
= 584.91 m2
(584.91/2339.64)
= 0.25
(287/938)
= 0.306
(0.306x0.4x20)
= 2.448
(0.694x1.0x20)
= 13.88
(651/938)
= 0.694
1 16.328
(0.25x1.0x50)
= 12.5
Vertical repetition of structure
= 100%
Repetition of floor to floor height
= 100%
Horizontal repetition of structure
= 100%
100%
100%
100%
2
2
2
20
86.328
Windows and Slabs
0% complies to MS 1064
Doors
67% complies to MS 1064
Walls
100% complies to MS 1064
Columns
100% complies to MS 1064
Beams
100% complies to MS 1064
100%
100%
100%
4
4
4
67% 2
0% 0
Part 3 : Other Simplified Construction Solutions
Total Part 3
IBS SCORE = 50(Part 1) + 16.328(Part 2) + 20(Part 3)
Total Part 1
3.
2.
1.
NO ELEMENTS
AREA (m2) or
LENGTH (m)
IBS FACTOR COVERAGE IBS SCORE
1.0
1.0