MERC’s Approach Paper for solar tariff
Mohit Kathel www.indianpowerindustry.com
MPERC’s Approach Paper on Fixation of norms for determination of tariff for
procurement of power from Solar based Power Projects
MPERC has issued an approach paper to revise the norms for determination of tariff for purchase of power by
the distribution licensees from solar projects in Madhya Pradesh.
In the approach paper MPERC has considered capital cost as per the proposed norms of CERC in its Sou-Motu
petition No. 353/2013 and the norms as specified in the previous tariff order dated 01.08.2012. As per the
approach paper proposed RoE is 4% higher than previous, proposed project cost is much below than the
prevailing cost of Rs. 10 Cr. Per MW, while other norms such as Interest on Working capital, interest on dept,
depreciation are taken as it is without any variation. The proposed norms of the approach paper emphasis on
attracting developers to the market.
Terms and conditions proposed in the approach paper are:
Life of the Solar Project: 25 Years
Transmission & Wheeling charges: levied when developers is other than distribution licensee, no transmission &
wheeling charges shall be levied when buyer is distribution licensee.
Sharing of CDM benefit: “The CDM benefit should be shared on a gross basis, starting from 100% to
developers in the first year after commissioning and thereafter reducing by 10% every year till the
sharing becomes equal (50:50) between the developers and the licensees/consumers in the sixth year.
Reactive Charges: 27 Paise per unit.
Drawing of power during shutdown and other emergencies: Drawl should not exceed 10% of the capacity of
plant and will be billed as per the Temporary charges for HT industrial category defined in ARR of the
distribution company.
Shifting from one buyer to another: Developer selling to third party or having captive consumption can
terminate the existing supply agreement and can sign the new PPA with Distribution Company or utility with the
prior permission of the commission.
If the buyer desires to terminate the existing PPA signed with utility then it can only be done if the utility is
default in payment.
Existing norms and proposed norms for Solar PV projects above 2 MW, Rooftop & below 2MW and for solar
thermal is presented below:
Parameters
Project Life: Project life of all the existing and upcoming plants has been proposed as per the existing tariff order
which is 25 years.
Debt-Equity Ratio: No change has been proposed in the Debt: Equity ratio norms and is fixed as 70:30.
MERC’s Approach Paper for solar tariff
Mohit Kathel www.indianpowerindustry.com
Project Cost (Rs. Cr per MW): Due to technology advancement the project cost of solar PV projects have
reduced considerably. In the proposed norms capital cost proposed are Rs. 6.12 Cr. And Rs. 6.5 cr. against
existing 10.25 Rs. Cr and 10.5 Cr. for project above 2 MW and rooftop & below 2MW projects respectively. In
solar thermal section proposed capital cost is 12 Cr. against existing cost of 13.25 Cr.
Pre-tax return on equity: to attract new players and to enhance competition in market Pre-tax return has been
proposed on a higher side which is 20% against the existing 16% RoE.
Interest on debt: No change has been proposed in the interest rate on debt. The existing interest on debt is
12.75%.
Working capital: No change has been made in the conditions as defined in the tariff order of 01.08.2012. to
work out the working capital for solar plants three norms are being defined in the order: a) O&M expenses for
one month, b) Receivables equivalent to 2 (Two) months of energy charges for sale of electricity calculated
on the normative CUF, c) Maintenance spare @ 15% of operation and maintenance expenses.
Interest on working capital: 13.25%
Depreciation (% of project cost per annum): 7.00% (for first 10 years) and 1.333% (for 11-25 years) in case of
types of solar power plant and a salvage value (% of asset value) for solar thermal plant is 10.00%.
O&M Cost (% of project cost): 0.5% for 1st year of operation escalated at the rate of 5.72% p.a. from 2nd year
onwards plus 0.3% of depreciated assets as insurance charges.
Capacity Utilization Factor (CUF): 20% derated at the rate of 1% of CUF each year from 3rd year onwards for all
solar PV power plants and 23% derated at the rate of 0.5% of CUF each year from 3rd year onwards for solar
thermal plants.
Auxiliary Consumption: Auxiliary consumption as per proposed norms for solar PV plants shall be 0.25% and for
solar thermal it should be 6.50%.
Discounting factor specified in the Approach paper: 10.20%.
MERC Approach Paper Solar Tariff 2014.xlsx
Existing tariff order dated 01.08.2012 As Proposed Existing tariff order dated 01.08.2012 As Proposed Parameters Existing tariff order dated 01.08.2012 As Proposed
Project Life 25 Years 25 Years 25 Years 25 Years Project Life 25 Years 25 Years
Debt-Equity Ratio 70:30 70:30:00 70:30:00 70:30 Debt-Equity Ratio 70:30 70:30
Project Cost (Rs. Cr
per MW)
10.25 6.12 10.5 6.5
Project Cost (Rs. Cr
per MW)
13.25 12
Pre-tax return on equity 16% 20% 16% 20% Pre-tax return on equity 16% 20%
Interest on debt 12.75% 12.75% 12.75% 12.75% Interest on debt 12.75% 12.75%
Working capital
a) Operation & Maintenance expenses for one
month; b) Receivables equivalent to 2 (Two)
months of energy charges for sale of electricity
calculated on the normative CUF; c)
Maintenance spare @ 15% of operation and
maintenance expenses
a) Operation & Maintenance expenses for one
month; b) Receivables equivalent to
2 (Two) months of energy charges for sale of
electricity calculated on the normative CUF; c)
Maintenance spare @ 15% of operation and
maintenance expenses
a) Operation & Maintenance expenses for one
month; b) Receivables equivalent to 2 (Two)
months of energy charges for sale of electricity
calculated on the normative CUF; c)
Maintenance spare @ 15% of operation and
maintenance expenses
a) Operation & Maintenance expenses for one
month; b) Receivables equivalent to
2 (Two) months of energy charges for sale of
electricity calculated on the normative CUF; c)
Maintenance spare @ 15% of operation and
maintenance expenses
Working capital
a) Operation & Maintenance expenses for one
month; b) Receivables equivalent to 2 (Two)
months of energy charges for sale of electricity
calculated on the normative CUF; c)
Maintenance spare @ 15% of operation and
maintenance expenses
a) Operation & Maintenance expenses for one
month; b) Receivables equivalent to
2 (Two) months of energy charges for sale of
electricity calculated on the normative CUF; c)
Maintenance spare @ 15% of operation and
maintenance expenses
Interest on working
capital
13.25% 13.25% 13.25% 13.25% Interest on working capital 13.25% 0.1325
Depreciation (% of
project cost per annum)
7.00% (for first 10 years) and 1.333% (for 11-25
years)
7.00% (for first 10 years) and 1.333% (for 11-25
years)
7.00% (for first 10 years)
and 1.333% (for 11-25 years)
7.00% (for first 10 years) and 1.333% (for 11-25
years)
Salvage value (% of asset value) 10.00% 0.1
O&M Cost (% of
project cost)
0.5% for 1st year of operation escalated at the
rate of 5.72% p.a. from 2nd year onwards plus
0.3% of depreciated assets as insurance charges
0.5% for 1st year of operation escalated at the
rate of 5.72% p.a. from 2nd year onwards plus
0.3% of depreciated assets as insurance charges
0.5% for 1st year of
operation escalated at the rate of 5.72% p.a.
from 2nd year onwards plus 0.3% of depreciated
assets as insurance charges
0.5% for 1st year of operation escalated at the
rate of 5.72% p.a. from 2nd year onwards plus
0.3% of depreciated assets as insurance charges
Depreciation (% of project cost per annum)
7.00% (for first 10 years) and 1.333% (for 11-25
years)
7.00% (for first 10 years) and 1.333% (for 11-25
years)
Capacity Utilization
Factor (CUF)
20% derated at the rate of 1% of CUF each year
from 3rd year onwards.
20% derated at the rate of 1% of CUF each year
from 3rd year onwards.
20% derated at the rate of 1% of CUF each year
from 3rd year onwards.
20% derated at the rate of 1% of CUF each year
from 3rd year onwards.
O&M Cost (% of project cost)
1% for 1st year of operation
escalated at the rate of
5.72% p.a. from 2nd year onwards plus 0.3% of
depreciated assets as insurance charges
1% for 1st year of operation
escalated at the rate of 5.72% p.a. from 2nd year
onwards plus 0.3% of depreciated assets as
insurance charges
Auxiliary Consumption 0.25% 0.25% 0.25% 0.25% Capacity Utilization Factor (CUF)
23% derated at the rate of 0.5% of CUF each
year from 3rd year onwards.
23% derated at the rate of 0.5% of CUF each year
from 3rd year onwards.
Discounting factor 10.20% 10.20% 10.20% 10.20% Auxiliary Consumption 6.50% 6.50%
Discounting factor 10.20% 10.20%
Norms for Solar PV Power Plants above 2 MW Norms for Rooftop PV and small Solar Power Plants below2 MW
Parameters
Norms for working out the Tariff for Solar Thermal Power Generating Projects
Mohit Kathel 3 www.indianpowerindustry.com

More Related Content

What's hot

Lawyer in Vietnam Oliver Massmann Solar Power Vietnam Breaking News: First Ev...
Lawyer in Vietnam Oliver Massmann Solar Power Vietnam Breaking News: First Ev...Lawyer in Vietnam Oliver Massmann Solar Power Vietnam Breaking News: First Ev...
Lawyer in Vietnam Oliver Massmann Solar Power Vietnam Breaking News: First Ev...Dr. Oliver Massmann
 
VIETNAM: DIRECT POWER PURCHASE AGREEMENTS (DPPA) AND SOLAR ROOFTOP- UPDATING ...
VIETNAM: DIRECT POWER PURCHASE AGREEMENTS (DPPA) AND SOLAR ROOFTOP- UPDATING ...VIETNAM: DIRECT POWER PURCHASE AGREEMENTS (DPPA) AND SOLAR ROOFTOP- UPDATING ...
VIETNAM: DIRECT POWER PURCHASE AGREEMENTS (DPPA) AND SOLAR ROOFTOP- UPDATING ...Dr. Oliver Massmann
 
Session 18 tender preparation & evaluation
Session 18   tender preparation & evaluationSession 18   tender preparation & evaluation
Session 18 tender preparation & evaluationChirag Jain
 
Comparison of Solar-Wind Hybrid Policies-07.02.2019
Comparison of Solar-Wind Hybrid Policies-07.02.2019Comparison of Solar-Wind Hybrid Policies-07.02.2019
Comparison of Solar-Wind Hybrid Policies-07.02.2019Gensol Engineering Limited
 
Developing Solar Projects under REC Mechanism in India
Developing Solar Projects under REC Mechanism in IndiaDeveloping Solar Projects under REC Mechanism in India
Developing Solar Projects under REC Mechanism in IndiaBhargav Parmar
 
Ceew ceew cef market handbook q1 2020-21 10 sep20
Ceew   ceew cef market handbook q1 2020-21 10 sep20Ceew   ceew cef market handbook q1 2020-21 10 sep20
Ceew ceew cef market handbook q1 2020-21 10 sep20Mayank Munjal
 
Finance and Market Presentation 02.01.2012
Finance and Market Presentation 02.01.2012Finance and Market Presentation 02.01.2012
Finance and Market Presentation 02.01.2012Ronald Moore
 
Feasibility of Solar Project with Open Access in Maharashtra
Feasibility of Solar Project with Open Access in Maharashtra Feasibility of Solar Project with Open Access in Maharashtra
Feasibility of Solar Project with Open Access in Maharashtra Gensol Engineering Limited
 
Feasibility Study of Solar Power in India
Feasibility Study of Solar Power in IndiaFeasibility Study of Solar Power in India
Feasibility Study of Solar Power in IndiaiData Insights
 
Power of sun and solar energy (india power)
Power of sun and solar energy (india power)Power of sun and solar energy (india power)
Power of sun and solar energy (india power)Mahesh Chandra Manav
 
Day2: Fuel supply issues ppt sunil wadhwa
Day2: Fuel supply issues ppt   sunil wadhwaDay2: Fuel supply issues ppt   sunil wadhwa
Day2: Fuel supply issues ppt sunil wadhwaIPPAI
 
Indian Solar Rooftop PV - A Bright Investment (21.08.18)
Indian Solar Rooftop PV - A Bright Investment (21.08.18)Indian Solar Rooftop PV - A Bright Investment (21.08.18)
Indian Solar Rooftop PV - A Bright Investment (21.08.18)Gensol Engineering Limited
 
Solar power projects under rec mechanism in india
Solar power projects under rec mechanism in indiaSolar power projects under rec mechanism in india
Solar power projects under rec mechanism in indiaBhargav Parmar
 
IREDA Scheme for Loan for grid connected Solar PV rooftop plant
IREDA Scheme for Loan for grid connected Solar PV rooftop plant IREDA Scheme for Loan for grid connected Solar PV rooftop plant
IREDA Scheme for Loan for grid connected Solar PV rooftop plant Ashish Verma
 
Incentives for Solar Developers:Generation Based Incentives
Incentives for Solar Developers:Generation Based IncentivesIncentives for Solar Developers:Generation Based Incentives
Incentives for Solar Developers:Generation Based IncentivesHIMADRI BANERJI
 
VIETNAM—POWER, ENERGY, AND THE AFFECT OF RECENT TRADE AGREEMENTS EU VIETNAM F...
VIETNAM—POWER, ENERGY, AND THE AFFECT OF RECENT TRADE AGREEMENTS EU VIETNAM F...VIETNAM—POWER, ENERGY, AND THE AFFECT OF RECENT TRADE AGREEMENTS EU VIETNAM F...
VIETNAM—POWER, ENERGY, AND THE AFFECT OF RECENT TRADE AGREEMENTS EU VIETNAM F...Dr. Oliver Massmann
 
Day2: Mr. Rk sinha dgh presentation ippai goa
Day2: Mr. Rk sinha dgh presentation ippai goaDay2: Mr. Rk sinha dgh presentation ippai goa
Day2: Mr. Rk sinha dgh presentation ippai goaIPPAI
 
Solar PV Financials
Solar PV FinancialsSolar PV Financials
Solar PV Financialstarunku08
 

What's hot (20)

Lawyer in Vietnam Oliver Massmann Solar Power Vietnam Breaking News: First Ev...
Lawyer in Vietnam Oliver Massmann Solar Power Vietnam Breaking News: First Ev...Lawyer in Vietnam Oliver Massmann Solar Power Vietnam Breaking News: First Ev...
Lawyer in Vietnam Oliver Massmann Solar Power Vietnam Breaking News: First Ev...
 
VIETNAM: DIRECT POWER PURCHASE AGREEMENTS (DPPA) AND SOLAR ROOFTOP- UPDATING ...
VIETNAM: DIRECT POWER PURCHASE AGREEMENTS (DPPA) AND SOLAR ROOFTOP- UPDATING ...VIETNAM: DIRECT POWER PURCHASE AGREEMENTS (DPPA) AND SOLAR ROOFTOP- UPDATING ...
VIETNAM: DIRECT POWER PURCHASE AGREEMENTS (DPPA) AND SOLAR ROOFTOP- UPDATING ...
 
Presentation by MNRE on Solar Parks
Presentation by MNRE on Solar ParksPresentation by MNRE on Solar Parks
Presentation by MNRE on Solar Parks
 
Session 18 tender preparation & evaluation
Session 18   tender preparation & evaluationSession 18   tender preparation & evaluation
Session 18 tender preparation & evaluation
 
Comparison of Solar-Wind Hybrid Policies-07.02.2019
Comparison of Solar-Wind Hybrid Policies-07.02.2019Comparison of Solar-Wind Hybrid Policies-07.02.2019
Comparison of Solar-Wind Hybrid Policies-07.02.2019
 
Developing Solar Projects under REC Mechanism in India
Developing Solar Projects under REC Mechanism in IndiaDeveloping Solar Projects under REC Mechanism in India
Developing Solar Projects under REC Mechanism in India
 
Ceew ceew cef market handbook q1 2020-21 10 sep20
Ceew   ceew cef market handbook q1 2020-21 10 sep20Ceew   ceew cef market handbook q1 2020-21 10 sep20
Ceew ceew cef market handbook q1 2020-21 10 sep20
 
Finance and Market Presentation 02.01.2012
Finance and Market Presentation 02.01.2012Finance and Market Presentation 02.01.2012
Finance and Market Presentation 02.01.2012
 
Feasibility of Solar Project with Open Access in Maharashtra
Feasibility of Solar Project with Open Access in Maharashtra Feasibility of Solar Project with Open Access in Maharashtra
Feasibility of Solar Project with Open Access in Maharashtra
 
Feasibility Study of Solar Power in India
Feasibility Study of Solar Power in IndiaFeasibility Study of Solar Power in India
Feasibility Study of Solar Power in India
 
Power of sun and solar energy (india power)
Power of sun and solar energy (india power)Power of sun and solar energy (india power)
Power of sun and solar energy (india power)
 
Day2: Fuel supply issues ppt sunil wadhwa
Day2: Fuel supply issues ppt   sunil wadhwaDay2: Fuel supply issues ppt   sunil wadhwa
Day2: Fuel supply issues ppt sunil wadhwa
 
Indian Solar Rooftop PV - A Bright Investment (21.08.18)
Indian Solar Rooftop PV - A Bright Investment (21.08.18)Indian Solar Rooftop PV - A Bright Investment (21.08.18)
Indian Solar Rooftop PV - A Bright Investment (21.08.18)
 
Solar power projects under rec mechanism in india
Solar power projects under rec mechanism in indiaSolar power projects under rec mechanism in india
Solar power projects under rec mechanism in india
 
IREDA Scheme for Loan for grid connected Solar PV rooftop plant
IREDA Scheme for Loan for grid connected Solar PV rooftop plant IREDA Scheme for Loan for grid connected Solar PV rooftop plant
IREDA Scheme for Loan for grid connected Solar PV rooftop plant
 
Incentives for Solar Developers:Generation Based Incentives
Incentives for Solar Developers:Generation Based IncentivesIncentives for Solar Developers:Generation Based Incentives
Incentives for Solar Developers:Generation Based Incentives
 
Discussion paper 16.11.2015
Discussion paper 16.11.2015Discussion paper 16.11.2015
Discussion paper 16.11.2015
 
VIETNAM—POWER, ENERGY, AND THE AFFECT OF RECENT TRADE AGREEMENTS EU VIETNAM F...
VIETNAM—POWER, ENERGY, AND THE AFFECT OF RECENT TRADE AGREEMENTS EU VIETNAM F...VIETNAM—POWER, ENERGY, AND THE AFFECT OF RECENT TRADE AGREEMENTS EU VIETNAM F...
VIETNAM—POWER, ENERGY, AND THE AFFECT OF RECENT TRADE AGREEMENTS EU VIETNAM F...
 
Day2: Mr. Rk sinha dgh presentation ippai goa
Day2: Mr. Rk sinha dgh presentation ippai goaDay2: Mr. Rk sinha dgh presentation ippai goa
Day2: Mr. Rk sinha dgh presentation ippai goa
 
Solar PV Financials
Solar PV FinancialsSolar PV Financials
Solar PV Financials
 

Viewers also liked

12th fyp approach paper education response
12th fyp approach paper education response12th fyp approach paper education response
12th fyp approach paper education responseAnjela Taneja
 
01 conceitos, objeto, finalidade, técnicas contábeis e campo
01 conceitos, objeto, finalidade, técnicas contábeis e campo01 conceitos, objeto, finalidade, técnicas contábeis e campo
01 conceitos, objeto, finalidade, técnicas contábeis e campolucio_rick
 
Dlaczego warto być aktywnym
Dlaczego warto być aktywnymDlaczego warto być aktywnym
Dlaczego warto być aktywnymVadym Melnyk
 
How to start a startup
How to start a startupHow to start a startup
How to start a startupVadym Melnyk
 
Wykorzystanie dronów w rolnictwie
Wykorzystanie dronów w rolnictwieWykorzystanie dronów w rolnictwie
Wykorzystanie dronów w rolnictwieVadym Melnyk
 
โครงงานคอมพิวเตอร์
โครงงานคอมพิวเตอร์โครงงานคอมพิวเตอร์
โครงงานคอมพิวเตอร์Walk4Fun
 
Drony i przetwarzanie danych w chmurze Cervi Robotics
Drony i przetwarzanie danych w chmurze Cervi RoboticsDrony i przetwarzanie danych w chmurze Cervi Robotics
Drony i przetwarzanie danych w chmurze Cervi RoboticsVadym Melnyk
 
Abbott to Turnbull Ch 10
Abbott to Turnbull Ch 10Abbott to Turnbull Ch 10
Abbott to Turnbull Ch 10Sharon Bell
 
Applying read on tab 4
Applying read on tab 4Applying read on tab 4
Applying read on tab 4Mark Roberts
 
Context clues power point
Context clues power pointContext clues power point
Context clues power pointMari Gold
 
SilentVoice(サイレントボイス)とは
SilentVoice(サイレントボイス)とはSilentVoice(サイレントボイス)とは
SilentVoice(サイレントボイス)とはTomoya Onaka
 
Pengumuman seleksi casn_ggd_2016
Pengumuman seleksi casn_ggd_2016Pengumuman seleksi casn_ggd_2016
Pengumuman seleksi casn_ggd_2016Zainal Arifin
 
Dlaczego warto być aktywnym (KNNTP)
Dlaczego warto być aktywnym (KNNTP)Dlaczego warto być aktywnym (KNNTP)
Dlaczego warto być aktywnym (KNNTP)Vadym Melnyk
 
งานนำเสนอ1
งานนำเสนอ1งานนำเสนอ1
งานนำเสนอ1See Tester
 
General resource
General resourceGeneral resource
General resourceMari Gold
 
Vertical Take off and Landing drone
Vertical Take off and Landing droneVertical Take off and Landing drone
Vertical Take off and Landing droneVadym Melnyk
 
Applying read on tab 4
Applying read on tab 4Applying read on tab 4
Applying read on tab 4Mark Roberts
 

Viewers also liked (20)

12th fyp approach paper education response
12th fyp approach paper education response12th fyp approach paper education response
12th fyp approach paper education response
 
01 conceitos, objeto, finalidade, técnicas contábeis e campo
01 conceitos, objeto, finalidade, técnicas contábeis e campo01 conceitos, objeto, finalidade, técnicas contábeis e campo
01 conceitos, objeto, finalidade, técnicas contábeis e campo
 
Dlaczego warto być aktywnym
Dlaczego warto być aktywnymDlaczego warto być aktywnym
Dlaczego warto być aktywnym
 
How to start a startup
How to start a startupHow to start a startup
How to start a startup
 
Wykorzystanie dronów w rolnictwie
Wykorzystanie dronów w rolnictwieWykorzystanie dronów w rolnictwie
Wykorzystanie dronów w rolnictwie
 
Portafolio-Oct2014
Portafolio-Oct2014Portafolio-Oct2014
Portafolio-Oct2014
 
โครงงานคอมพิวเตอร์
โครงงานคอมพิวเตอร์โครงงานคอมพิวเตอร์
โครงงานคอมพิวเตอร์
 
Drony i przetwarzanie danych w chmurze Cervi Robotics
Drony i przetwarzanie danych w chmurze Cervi RoboticsDrony i przetwarzanie danych w chmurze Cervi Robotics
Drony i przetwarzanie danych w chmurze Cervi Robotics
 
Abbott to Turnbull Ch 10
Abbott to Turnbull Ch 10Abbott to Turnbull Ch 10
Abbott to Turnbull Ch 10
 
future of gmos
  future of gmos  future of gmos
future of gmos
 
Applying read on tab 4
Applying read on tab 4Applying read on tab 4
Applying read on tab 4
 
Context clues power point
Context clues power pointContext clues power point
Context clues power point
 
SilentVoice(サイレントボイス)とは
SilentVoice(サイレントボイス)とはSilentVoice(サイレントボイス)とは
SilentVoice(サイレントボイス)とは
 
Pengumuman seleksi casn_ggd_2016
Pengumuman seleksi casn_ggd_2016Pengumuman seleksi casn_ggd_2016
Pengumuman seleksi casn_ggd_2016
 
Dlaczego warto być aktywnym (KNNTP)
Dlaczego warto być aktywnym (KNNTP)Dlaczego warto być aktywnym (KNNTP)
Dlaczego warto być aktywnym (KNNTP)
 
งานนำเสนอ1
งานนำเสนอ1งานนำเสนอ1
งานนำเสนอ1
 
General resource
General resourceGeneral resource
General resource
 
Engish day
Engish dayEngish day
Engish day
 
Vertical Take off and Landing drone
Vertical Take off and Landing droneVertical Take off and Landing drone
Vertical Take off and Landing drone
 
Applying read on tab 4
Applying read on tab 4Applying read on tab 4
Applying read on tab 4
 

Similar to Merc approach paper for determination of soalr tariff 2014

Financial viability of solar power plant in Tamil Nadu
Financial viability of solar power plant in Tamil NaduFinancial viability of solar power plant in Tamil Nadu
Financial viability of solar power plant in Tamil NaduIshan Rohit
 
Session 12 project costing & economics
Session 12   project costing & economicsSession 12   project costing & economics
Session 12 project costing & economicsChirag Jain
 
LOAN SCHEME FOR FINANCING GRID CONNECTED ROOFTOP SOLAR PV POWER PROJECTS
LOAN SCHEME FOR FINANCING GRID CONNECTED ROOFTOP SOLAR PV POWER PROJECTS LOAN SCHEME FOR FINANCING GRID CONNECTED ROOFTOP SOLAR PV POWER PROJECTS
LOAN SCHEME FOR FINANCING GRID CONNECTED ROOFTOP SOLAR PV POWER PROJECTS Harish Sharma
 
Renewable Energy - Recent Initiatives
Renewable Energy - Recent InitiativesRenewable Energy - Recent Initiatives
Renewable Energy - Recent InitiativesSaurabh Mehta
 
Solar Power Development Vietnam
Solar Power Development VietnamSolar Power Development Vietnam
Solar Power Development VietnamJAIDEEP MANN
 
PNB_Roof Top Solar Power Presentation.pptx
PNB_Roof Top Solar Power Presentation.pptxPNB_Roof Top Solar Power Presentation.pptx
PNB_Roof Top Solar Power Presentation.pptxParamJothi
 
Polices & Financial Incentives On Wind Power Development in China
Polices & Financial Incentives On Wind Power Development in ChinaPolices & Financial Incentives On Wind Power Development in China
Polices & Financial Incentives On Wind Power Development in ChinaS. W. Leung
 
Session 13 national policy & regulatory framework & available incentives
Session 13   national policy & regulatory framework & available incentivesSession 13   national policy & regulatory framework & available incentives
Session 13 national policy & regulatory framework & available incentivesChirag Jain
 
Eai presentation investment challenges in small hydro in india delhi mar 2010
Eai presentation investment challenges in small hydro in india delhi mar 2010Eai presentation investment challenges in small hydro in india delhi mar 2010
Eai presentation investment challenges in small hydro in india delhi mar 2010Renganathan M G
 
COMPETITIVE TARRIFF BIDDING
COMPETITIVE TARRIFF BIDDINGCOMPETITIVE TARRIFF BIDDING
COMPETITIVE TARRIFF BIDDINGRAVI PAL SINGH
 
Solar Panel Installation And Maintenance PowerPoint Presentation Slides
Solar Panel Installation And Maintenance PowerPoint Presentation SlidesSolar Panel Installation And Maintenance PowerPoint Presentation Slides
Solar Panel Installation And Maintenance PowerPoint Presentation SlidesSlideTeam
 

Similar to Merc approach paper for determination of soalr tariff 2014 (20)

Financial viability of solar power plant in Tamil Nadu
Financial viability of solar power plant in Tamil NaduFinancial viability of solar power plant in Tamil Nadu
Financial viability of solar power plant in Tamil Nadu
 
Session 12 project costing & economics
Session 12   project costing & economicsSession 12   project costing & economics
Session 12 project costing & economics
 
Levellised generic tariff
Levellised generic tariffLevellised generic tariff
Levellised generic tariff
 
LOAN SCHEME FOR FINANCING GRID CONNECTED ROOFTOP SOLAR PV POWER PROJECTS
LOAN SCHEME FOR FINANCING GRID CONNECTED ROOFTOP SOLAR PV POWER PROJECTS LOAN SCHEME FOR FINANCING GRID CONNECTED ROOFTOP SOLAR PV POWER PROJECTS
LOAN SCHEME FOR FINANCING GRID CONNECTED ROOFTOP SOLAR PV POWER PROJECTS
 
Renewable Energy - Recent Initiatives
Renewable Energy - Recent InitiativesRenewable Energy - Recent Initiatives
Renewable Energy - Recent Initiatives
 
Solar power plant Opportunity and Costing
Solar power plant Opportunity and CostingSolar power plant Opportunity and Costing
Solar power plant Opportunity and Costing
 
Solar Power Development Vietnam
Solar Power Development VietnamSolar Power Development Vietnam
Solar Power Development Vietnam
 
Tariff2009 14
Tariff2009 14Tariff2009 14
Tariff2009 14
 
PNB_Roof Top Solar Power Presentation.pptx
PNB_Roof Top Solar Power Presentation.pptxPNB_Roof Top Solar Power Presentation.pptx
PNB_Roof Top Solar Power Presentation.pptx
 
SunBurn Test Presentation
SunBurn Test PresentationSunBurn Test Presentation
SunBurn Test Presentation
 
Cashing on the sun
Cashing on the sunCashing on the sun
Cashing on the sun
 
Polices & Financial Incentives On Wind Power Development in China
Polices & Financial Incentives On Wind Power Development in ChinaPolices & Financial Incentives On Wind Power Development in China
Polices & Financial Incentives On Wind Power Development in China
 
Solar power - A developer prespective
Solar power - A developer prespectiveSolar power - A developer prespective
Solar power - A developer prespective
 
Session 13 national policy & regulatory framework & available incentives
Session 13   national policy & regulatory framework & available incentivesSession 13   national policy & regulatory framework & available incentives
Session 13 national policy & regulatory framework & available incentives
 
CK2017: SIDBI Initiatives on Clean Energy Adoption
CK2017: SIDBI Initiatives on Clean Energy Adoption CK2017: SIDBI Initiatives on Clean Energy Adoption
CK2017: SIDBI Initiatives on Clean Energy Adoption
 
Small Power Generation Plant
Small Power Generation PlantSmall Power Generation Plant
Small Power Generation Plant
 
Eai presentation investment challenges in small hydro in india delhi mar 2010
Eai presentation investment challenges in small hydro in india delhi mar 2010Eai presentation investment challenges in small hydro in india delhi mar 2010
Eai presentation investment challenges in small hydro in india delhi mar 2010
 
COMPETITIVE TARRIFF BIDDING
COMPETITIVE TARRIFF BIDDINGCOMPETITIVE TARRIFF BIDDING
COMPETITIVE TARRIFF BIDDING
 
Solar Panel Installation And Maintenance PowerPoint Presentation Slides
Solar Panel Installation And Maintenance PowerPoint Presentation SlidesSolar Panel Installation And Maintenance PowerPoint Presentation Slides
Solar Panel Installation And Maintenance PowerPoint Presentation Slides
 
Ltbr
LtbrLtbr
Ltbr
 

Recently uploaded

➥🔝 7737669865 🔝▻ Sambalpur Call-girls in Women Seeking Men 🔝Sambalpur🔝 Esc...
➥🔝 7737669865 🔝▻ Sambalpur Call-girls in Women Seeking Men  🔝Sambalpur🔝   Esc...➥🔝 7737669865 🔝▻ Sambalpur Call-girls in Women Seeking Men  🔝Sambalpur🔝   Esc...
➥🔝 7737669865 🔝▻ Sambalpur Call-girls in Women Seeking Men 🔝Sambalpur🔝 Esc...amitlee9823
 
➥🔝 7737669865 🔝▻ malwa Call-girls in Women Seeking Men 🔝malwa🔝 Escorts Ser...
➥🔝 7737669865 🔝▻ malwa Call-girls in Women Seeking Men  🔝malwa🔝   Escorts Ser...➥🔝 7737669865 🔝▻ malwa Call-girls in Women Seeking Men  🔝malwa🔝   Escorts Ser...
➥🔝 7737669865 🔝▻ malwa Call-girls in Women Seeking Men 🔝malwa🔝 Escorts Ser...amitlee9823
 
Call Girls Indiranagar Just Call 👗 7737669865 👗 Top Class Call Girl Service B...
Call Girls Indiranagar Just Call 👗 7737669865 👗 Top Class Call Girl Service B...Call Girls Indiranagar Just Call 👗 7737669865 👗 Top Class Call Girl Service B...
Call Girls Indiranagar Just Call 👗 7737669865 👗 Top Class Call Girl Service B...amitlee9823
 
VIP Model Call Girls Hinjewadi ( Pune ) Call ON 8005736733 Starting From 5K t...
VIP Model Call Girls Hinjewadi ( Pune ) Call ON 8005736733 Starting From 5K t...VIP Model Call Girls Hinjewadi ( Pune ) Call ON 8005736733 Starting From 5K t...
VIP Model Call Girls Hinjewadi ( Pune ) Call ON 8005736733 Starting From 5K t...SUHANI PANDEY
 
Call Girls Bannerghatta Road Just Call 👗 7737669865 👗 Top Class Call Girl Ser...
Call Girls Bannerghatta Road Just Call 👗 7737669865 👗 Top Class Call Girl Ser...Call Girls Bannerghatta Road Just Call 👗 7737669865 👗 Top Class Call Girl Ser...
Call Girls Bannerghatta Road Just Call 👗 7737669865 👗 Top Class Call Girl Ser...amitlee9823
 
Call Girls In Nandini Layout ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Nandini Layout ☎ 7737669865 🥵 Book Your One night StandCall Girls In Nandini Layout ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Nandini Layout ☎ 7737669865 🥵 Book Your One night Standamitlee9823
 
Call Girls In Doddaballapur Road ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Doddaballapur Road ☎ 7737669865 🥵 Book Your One night StandCall Girls In Doddaballapur Road ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Doddaballapur Road ☎ 7737669865 🥵 Book Your One night Standamitlee9823
 
Just Call Vip call girls kakinada Escorts ☎️9352988975 Two shot with one girl...
Just Call Vip call girls kakinada Escorts ☎️9352988975 Two shot with one girl...Just Call Vip call girls kakinada Escorts ☎️9352988975 Two shot with one girl...
Just Call Vip call girls kakinada Escorts ☎️9352988975 Two shot with one girl...gajnagarg
 
Call Girls In Hsr Layout ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Hsr Layout ☎ 7737669865 🥵 Book Your One night StandCall Girls In Hsr Layout ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Hsr Layout ☎ 7737669865 🥵 Book Your One night Standamitlee9823
 
➥🔝 7737669865 🔝▻ Ongole Call-girls in Women Seeking Men 🔝Ongole🔝 Escorts S...
➥🔝 7737669865 🔝▻ Ongole Call-girls in Women Seeking Men  🔝Ongole🔝   Escorts S...➥🔝 7737669865 🔝▻ Ongole Call-girls in Women Seeking Men  🔝Ongole🔝   Escorts S...
➥🔝 7737669865 🔝▻ Ongole Call-girls in Women Seeking Men 🔝Ongole🔝 Escorts S...amitlee9823
 
Call Girls Begur Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Begur Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Begur Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Begur Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangaloreamitlee9823
 
➥🔝 7737669865 🔝▻ mahisagar Call-girls in Women Seeking Men 🔝mahisagar🔝 Esc...
➥🔝 7737669865 🔝▻ mahisagar Call-girls in Women Seeking Men  🔝mahisagar🔝   Esc...➥🔝 7737669865 🔝▻ mahisagar Call-girls in Women Seeking Men  🔝mahisagar🔝   Esc...
➥🔝 7737669865 🔝▻ mahisagar Call-girls in Women Seeking Men 🔝mahisagar🔝 Esc...amitlee9823
 
👉 Amritsar Call Girl 👉📞 6367187148 👉📞 Just📲 Call Ruhi Call Girl Phone No Amri...
👉 Amritsar Call Girl 👉📞 6367187148 👉📞 Just📲 Call Ruhi Call Girl Phone No Amri...👉 Amritsar Call Girl 👉📞 6367187148 👉📞 Just📲 Call Ruhi Call Girl Phone No Amri...
👉 Amritsar Call Girl 👉📞 6367187148 👉📞 Just📲 Call Ruhi Call Girl Phone No Amri...karishmasinghjnh
 
Call Girls In Bellandur ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bellandur ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bellandur ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bellandur ☎ 7737669865 🥵 Book Your One night Standamitlee9823
 
DATA SUMMIT 24 Building Real-Time Pipelines With FLaNK
DATA SUMMIT 24  Building Real-Time Pipelines With FLaNKDATA SUMMIT 24  Building Real-Time Pipelines With FLaNK
DATA SUMMIT 24 Building Real-Time Pipelines With FLaNKTimothy Spann
 
Chintamani Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore ...
Chintamani Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore ...Chintamani Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore ...
Chintamani Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore ...amitlee9823
 
Junnasandra Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
Junnasandra Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...Junnasandra Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
Junnasandra Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...amitlee9823
 

Recently uploaded (20)

➥🔝 7737669865 🔝▻ Sambalpur Call-girls in Women Seeking Men 🔝Sambalpur🔝 Esc...
➥🔝 7737669865 🔝▻ Sambalpur Call-girls in Women Seeking Men  🔝Sambalpur🔝   Esc...➥🔝 7737669865 🔝▻ Sambalpur Call-girls in Women Seeking Men  🔝Sambalpur🔝   Esc...
➥🔝 7737669865 🔝▻ Sambalpur Call-girls in Women Seeking Men 🔝Sambalpur🔝 Esc...
 
➥🔝 7737669865 🔝▻ malwa Call-girls in Women Seeking Men 🔝malwa🔝 Escorts Ser...
➥🔝 7737669865 🔝▻ malwa Call-girls in Women Seeking Men  🔝malwa🔝   Escorts Ser...➥🔝 7737669865 🔝▻ malwa Call-girls in Women Seeking Men  🔝malwa🔝   Escorts Ser...
➥🔝 7737669865 🔝▻ malwa Call-girls in Women Seeking Men 🔝malwa🔝 Escorts Ser...
 
Abortion pills in Doha Qatar (+966572737505 ! Get Cytotec
Abortion pills in Doha Qatar (+966572737505 ! Get CytotecAbortion pills in Doha Qatar (+966572737505 ! Get Cytotec
Abortion pills in Doha Qatar (+966572737505 ! Get Cytotec
 
Predicting Loan Approval: A Data Science Project
Predicting Loan Approval: A Data Science ProjectPredicting Loan Approval: A Data Science Project
Predicting Loan Approval: A Data Science Project
 
(NEHA) Call Girls Katra Call Now 8617697112 Katra Escorts 24x7
(NEHA) Call Girls Katra Call Now 8617697112 Katra Escorts 24x7(NEHA) Call Girls Katra Call Now 8617697112 Katra Escorts 24x7
(NEHA) Call Girls Katra Call Now 8617697112 Katra Escorts 24x7
 
Call Girls Indiranagar Just Call 👗 7737669865 👗 Top Class Call Girl Service B...
Call Girls Indiranagar Just Call 👗 7737669865 👗 Top Class Call Girl Service B...Call Girls Indiranagar Just Call 👗 7737669865 👗 Top Class Call Girl Service B...
Call Girls Indiranagar Just Call 👗 7737669865 👗 Top Class Call Girl Service B...
 
VIP Model Call Girls Hinjewadi ( Pune ) Call ON 8005736733 Starting From 5K t...
VIP Model Call Girls Hinjewadi ( Pune ) Call ON 8005736733 Starting From 5K t...VIP Model Call Girls Hinjewadi ( Pune ) Call ON 8005736733 Starting From 5K t...
VIP Model Call Girls Hinjewadi ( Pune ) Call ON 8005736733 Starting From 5K t...
 
Call Girls Bannerghatta Road Just Call 👗 7737669865 👗 Top Class Call Girl Ser...
Call Girls Bannerghatta Road Just Call 👗 7737669865 👗 Top Class Call Girl Ser...Call Girls Bannerghatta Road Just Call 👗 7737669865 👗 Top Class Call Girl Ser...
Call Girls Bannerghatta Road Just Call 👗 7737669865 👗 Top Class Call Girl Ser...
 
Call Girls In Nandini Layout ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Nandini Layout ☎ 7737669865 🥵 Book Your One night StandCall Girls In Nandini Layout ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Nandini Layout ☎ 7737669865 🥵 Book Your One night Stand
 
Call Girls In Doddaballapur Road ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Doddaballapur Road ☎ 7737669865 🥵 Book Your One night StandCall Girls In Doddaballapur Road ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Doddaballapur Road ☎ 7737669865 🥵 Book Your One night Stand
 
Just Call Vip call girls kakinada Escorts ☎️9352988975 Two shot with one girl...
Just Call Vip call girls kakinada Escorts ☎️9352988975 Two shot with one girl...Just Call Vip call girls kakinada Escorts ☎️9352988975 Two shot with one girl...
Just Call Vip call girls kakinada Escorts ☎️9352988975 Two shot with one girl...
 
Call Girls In Hsr Layout ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Hsr Layout ☎ 7737669865 🥵 Book Your One night StandCall Girls In Hsr Layout ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Hsr Layout ☎ 7737669865 🥵 Book Your One night Stand
 
➥🔝 7737669865 🔝▻ Ongole Call-girls in Women Seeking Men 🔝Ongole🔝 Escorts S...
➥🔝 7737669865 🔝▻ Ongole Call-girls in Women Seeking Men  🔝Ongole🔝   Escorts S...➥🔝 7737669865 🔝▻ Ongole Call-girls in Women Seeking Men  🔝Ongole🔝   Escorts S...
➥🔝 7737669865 🔝▻ Ongole Call-girls in Women Seeking Men 🔝Ongole🔝 Escorts S...
 
Call Girls Begur Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Begur Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Begur Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Begur Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
 
➥🔝 7737669865 🔝▻ mahisagar Call-girls in Women Seeking Men 🔝mahisagar🔝 Esc...
➥🔝 7737669865 🔝▻ mahisagar Call-girls in Women Seeking Men  🔝mahisagar🔝   Esc...➥🔝 7737669865 🔝▻ mahisagar Call-girls in Women Seeking Men  🔝mahisagar🔝   Esc...
➥🔝 7737669865 🔝▻ mahisagar Call-girls in Women Seeking Men 🔝mahisagar🔝 Esc...
 
👉 Amritsar Call Girl 👉📞 6367187148 👉📞 Just📲 Call Ruhi Call Girl Phone No Amri...
👉 Amritsar Call Girl 👉📞 6367187148 👉📞 Just📲 Call Ruhi Call Girl Phone No Amri...👉 Amritsar Call Girl 👉📞 6367187148 👉📞 Just📲 Call Ruhi Call Girl Phone No Amri...
👉 Amritsar Call Girl 👉📞 6367187148 👉📞 Just📲 Call Ruhi Call Girl Phone No Amri...
 
Call Girls In Bellandur ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bellandur ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bellandur ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bellandur ☎ 7737669865 🥵 Book Your One night Stand
 
DATA SUMMIT 24 Building Real-Time Pipelines With FLaNK
DATA SUMMIT 24  Building Real-Time Pipelines With FLaNKDATA SUMMIT 24  Building Real-Time Pipelines With FLaNK
DATA SUMMIT 24 Building Real-Time Pipelines With FLaNK
 
Chintamani Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore ...
Chintamani Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore ...Chintamani Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore ...
Chintamani Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore ...
 
Junnasandra Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
Junnasandra Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...Junnasandra Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
Junnasandra Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
 

Merc approach paper for determination of soalr tariff 2014

  • 1. MERC’s Approach Paper for solar tariff Mohit Kathel www.indianpowerindustry.com MPERC’s Approach Paper on Fixation of norms for determination of tariff for procurement of power from Solar based Power Projects MPERC has issued an approach paper to revise the norms for determination of tariff for purchase of power by the distribution licensees from solar projects in Madhya Pradesh. In the approach paper MPERC has considered capital cost as per the proposed norms of CERC in its Sou-Motu petition No. 353/2013 and the norms as specified in the previous tariff order dated 01.08.2012. As per the approach paper proposed RoE is 4% higher than previous, proposed project cost is much below than the prevailing cost of Rs. 10 Cr. Per MW, while other norms such as Interest on Working capital, interest on dept, depreciation are taken as it is without any variation. The proposed norms of the approach paper emphasis on attracting developers to the market. Terms and conditions proposed in the approach paper are: Life of the Solar Project: 25 Years Transmission & Wheeling charges: levied when developers is other than distribution licensee, no transmission & wheeling charges shall be levied when buyer is distribution licensee. Sharing of CDM benefit: “The CDM benefit should be shared on a gross basis, starting from 100% to developers in the first year after commissioning and thereafter reducing by 10% every year till the sharing becomes equal (50:50) between the developers and the licensees/consumers in the sixth year. Reactive Charges: 27 Paise per unit. Drawing of power during shutdown and other emergencies: Drawl should not exceed 10% of the capacity of plant and will be billed as per the Temporary charges for HT industrial category defined in ARR of the distribution company. Shifting from one buyer to another: Developer selling to third party or having captive consumption can terminate the existing supply agreement and can sign the new PPA with Distribution Company or utility with the prior permission of the commission. If the buyer desires to terminate the existing PPA signed with utility then it can only be done if the utility is default in payment. Existing norms and proposed norms for Solar PV projects above 2 MW, Rooftop & below 2MW and for solar thermal is presented below: Parameters Project Life: Project life of all the existing and upcoming plants has been proposed as per the existing tariff order which is 25 years. Debt-Equity Ratio: No change has been proposed in the Debt: Equity ratio norms and is fixed as 70:30.
  • 2. MERC’s Approach Paper for solar tariff Mohit Kathel www.indianpowerindustry.com Project Cost (Rs. Cr per MW): Due to technology advancement the project cost of solar PV projects have reduced considerably. In the proposed norms capital cost proposed are Rs. 6.12 Cr. And Rs. 6.5 cr. against existing 10.25 Rs. Cr and 10.5 Cr. for project above 2 MW and rooftop & below 2MW projects respectively. In solar thermal section proposed capital cost is 12 Cr. against existing cost of 13.25 Cr. Pre-tax return on equity: to attract new players and to enhance competition in market Pre-tax return has been proposed on a higher side which is 20% against the existing 16% RoE. Interest on debt: No change has been proposed in the interest rate on debt. The existing interest on debt is 12.75%. Working capital: No change has been made in the conditions as defined in the tariff order of 01.08.2012. to work out the working capital for solar plants three norms are being defined in the order: a) O&M expenses for one month, b) Receivables equivalent to 2 (Two) months of energy charges for sale of electricity calculated on the normative CUF, c) Maintenance spare @ 15% of operation and maintenance expenses. Interest on working capital: 13.25% Depreciation (% of project cost per annum): 7.00% (for first 10 years) and 1.333% (for 11-25 years) in case of types of solar power plant and a salvage value (% of asset value) for solar thermal plant is 10.00%. O&M Cost (% of project cost): 0.5% for 1st year of operation escalated at the rate of 5.72% p.a. from 2nd year onwards plus 0.3% of depreciated assets as insurance charges. Capacity Utilization Factor (CUF): 20% derated at the rate of 1% of CUF each year from 3rd year onwards for all solar PV power plants and 23% derated at the rate of 0.5% of CUF each year from 3rd year onwards for solar thermal plants. Auxiliary Consumption: Auxiliary consumption as per proposed norms for solar PV plants shall be 0.25% and for solar thermal it should be 6.50%. Discounting factor specified in the Approach paper: 10.20%.
  • 3. MERC Approach Paper Solar Tariff 2014.xlsx Existing tariff order dated 01.08.2012 As Proposed Existing tariff order dated 01.08.2012 As Proposed Parameters Existing tariff order dated 01.08.2012 As Proposed Project Life 25 Years 25 Years 25 Years 25 Years Project Life 25 Years 25 Years Debt-Equity Ratio 70:30 70:30:00 70:30:00 70:30 Debt-Equity Ratio 70:30 70:30 Project Cost (Rs. Cr per MW) 10.25 6.12 10.5 6.5 Project Cost (Rs. Cr per MW) 13.25 12 Pre-tax return on equity 16% 20% 16% 20% Pre-tax return on equity 16% 20% Interest on debt 12.75% 12.75% 12.75% 12.75% Interest on debt 12.75% 12.75% Working capital a) Operation & Maintenance expenses for one month; b) Receivables equivalent to 2 (Two) months of energy charges for sale of electricity calculated on the normative CUF; c) Maintenance spare @ 15% of operation and maintenance expenses a) Operation & Maintenance expenses for one month; b) Receivables equivalent to 2 (Two) months of energy charges for sale of electricity calculated on the normative CUF; c) Maintenance spare @ 15% of operation and maintenance expenses a) Operation & Maintenance expenses for one month; b) Receivables equivalent to 2 (Two) months of energy charges for sale of electricity calculated on the normative CUF; c) Maintenance spare @ 15% of operation and maintenance expenses a) Operation & Maintenance expenses for one month; b) Receivables equivalent to 2 (Two) months of energy charges for sale of electricity calculated on the normative CUF; c) Maintenance spare @ 15% of operation and maintenance expenses Working capital a) Operation & Maintenance expenses for one month; b) Receivables equivalent to 2 (Two) months of energy charges for sale of electricity calculated on the normative CUF; c) Maintenance spare @ 15% of operation and maintenance expenses a) Operation & Maintenance expenses for one month; b) Receivables equivalent to 2 (Two) months of energy charges for sale of electricity calculated on the normative CUF; c) Maintenance spare @ 15% of operation and maintenance expenses Interest on working capital 13.25% 13.25% 13.25% 13.25% Interest on working capital 13.25% 0.1325 Depreciation (% of project cost per annum) 7.00% (for first 10 years) and 1.333% (for 11-25 years) 7.00% (for first 10 years) and 1.333% (for 11-25 years) 7.00% (for first 10 years) and 1.333% (for 11-25 years) 7.00% (for first 10 years) and 1.333% (for 11-25 years) Salvage value (% of asset value) 10.00% 0.1 O&M Cost (% of project cost) 0.5% for 1st year of operation escalated at the rate of 5.72% p.a. from 2nd year onwards plus 0.3% of depreciated assets as insurance charges 0.5% for 1st year of operation escalated at the rate of 5.72% p.a. from 2nd year onwards plus 0.3% of depreciated assets as insurance charges 0.5% for 1st year of operation escalated at the rate of 5.72% p.a. from 2nd year onwards plus 0.3% of depreciated assets as insurance charges 0.5% for 1st year of operation escalated at the rate of 5.72% p.a. from 2nd year onwards plus 0.3% of depreciated assets as insurance charges Depreciation (% of project cost per annum) 7.00% (for first 10 years) and 1.333% (for 11-25 years) 7.00% (for first 10 years) and 1.333% (for 11-25 years) Capacity Utilization Factor (CUF) 20% derated at the rate of 1% of CUF each year from 3rd year onwards. 20% derated at the rate of 1% of CUF each year from 3rd year onwards. 20% derated at the rate of 1% of CUF each year from 3rd year onwards. 20% derated at the rate of 1% of CUF each year from 3rd year onwards. O&M Cost (% of project cost) 1% for 1st year of operation escalated at the rate of 5.72% p.a. from 2nd year onwards plus 0.3% of depreciated assets as insurance charges 1% for 1st year of operation escalated at the rate of 5.72% p.a. from 2nd year onwards plus 0.3% of depreciated assets as insurance charges Auxiliary Consumption 0.25% 0.25% 0.25% 0.25% Capacity Utilization Factor (CUF) 23% derated at the rate of 0.5% of CUF each year from 3rd year onwards. 23% derated at the rate of 0.5% of CUF each year from 3rd year onwards. Discounting factor 10.20% 10.20% 10.20% 10.20% Auxiliary Consumption 6.50% 6.50% Discounting factor 10.20% 10.20% Norms for Solar PV Power Plants above 2 MW Norms for Rooftop PV and small Solar Power Plants below2 MW Parameters Norms for working out the Tariff for Solar Thermal Power Generating Projects Mohit Kathel 3 www.indianpowerindustry.com